learning pmp formulas the easy way

45
Learning PMP Formulas the Easy Way A step by step process to learn the formulas needed to pass the PMP® examination Presented by Mark Troncone, MBA, PMP®, CSM®

Upload: mark-troncone-mba-pmp-csm

Post on 05-Dec-2014

658 views

Category:

Education


5 download

DESCRIPTION

This presenttation will show anyone who is tudying for the PMP examination how to quickly learn the necessary formulas to pass the exam

TRANSCRIPT

Page 1: Learning pmp formulas the easy way

Learning PMP Formulas the Easy Way

A step by step process to learn the formulas needed to pass the PMP® examination

Presented by Mark Troncone, MBA, PMP®, CSM®

Page 2: Learning pmp formulas the easy way

About Me – Mark Troncone

PMP® Certified – Project Management Institute CRM Certified SCRUM Master® – SCRUM Alliance Certified IT Business Analyst – State of Connecticut Active career transition mentor MBA Management, BS Marketing, AS Accounting Work experience::

TransAct Technologies Starwood Hotels Affinion Group Hewitt Associates Wachovia Bank Bayer Pharmaceuticals Reader’s Digest James River Corporation

Page 3: Learning pmp formulas the easy way

Agenda

The purpose of this presentation The PMP® examination and formulas The formulas you need to know for the test The formulas explained How to learn the formulas the “easy” way Test yourself – time to prepare What to do - pre-exam Your ready!

Page 4: Learning pmp formulas the easy way

The Purpose of this Presentation

This presentation has 3 goals:

1. To explain the formulas that you will need to know for the PMP®

Examination

2. To give you an easy-to-learn method to remember these formulas

3. To ensure that you can quickly reproduce these formulas on paper before you start the PMP® exam

Page 5: Learning pmp formulas the easy way

The PMP® examination and formulas

Some things to know before the test:

Do not get intimidated by the formulas

The formulas are not hard to learn

If you follow my step by step plan it’s easy

With a little practice you should be able

to write them down in 5 minutes!

Let’s get started!!!!!!!!!!!!

Page 6: Learning pmp formulas the easy way

The Formulas You Need to Know for the Test

These are the first 5 formulas you will need to know:

Present Standard Activity PERT Communication Value Deviation Variance (3 Point Est.) Channels

FV C (R + 1)

Where:

FV = Future Value

R = Interest Rate

n = # of time periods

P - O 6

Where:

P = Pessimistic Time

O = Optimistic Time

Where:

P = Pessimistic Time

O = Optimistic Time

P + (4M) + O 6

Where:

P = Pessimistic Time

M = Most Likely Time

O = Optimistic Time

N (N – 1) 2

Where:

N = Number of People

P - O 6

2n

Page 7: Learning pmp formulas the easy way

The Formulas Explained - First 5

1. Present Value

Present value means - the value today of future cash flows

FV = Future Value

R = Interest Rate

n = Number of periods

FV (R + 1)

n

Page 8: Learning pmp formulas the easy way

The Formulas Explained - First 5

2. Activity Standard Deviation

This can be used for both Time and Cost estimates The + or – an activities/cost range

P = Most Pessimistic Time or Cost estimate for an activityO = Most Optimistic Time or Cost estimate for an activity

P - O 6

Page 9: Learning pmp formulas the easy way

The Formulas Explained - First 5

3. Activity Variance

This can be used for both Time and Cost estimates Represents variances of critical path activities

P = most Pessimistic Time or Cost estimate for an activityO = most Optimistic Time or Cost estimate for an activity

Note: Remember to Square the result which is a fancy way of multiplying the result times itself

P - O 6

2

Page 10: Learning pmp formulas the easy way

The Formulas Explained - First 5

4. Three Point Estimate (PERT)

This can be used for both Time and Cost estimates Also Known as Expected Activity Duration EAD + or – SD gives you a range for an individual activity

estimate ex) an activity can take 25 days + or – 3 days

P = Most Pessimistic Time or Cost estimate for an activityM = Most Likely Time or Cost estimate for an activityO = Most Optimistic Time or Cost estimate for an activity

P + (4M) + O 6

Page 11: Learning pmp formulas the easy way

The Formulas Explained - First 5

5. Communication Channels

This formula is used to calculate the number of communication channels required for the number of stakeholders. It will give an indication of how complex a project’s communications will be.

N = Number of Stakeholders (People)

N (N – 1) 2

Page 12: Learning pmp formulas the easy way

The Formulas You Need to Know for the Test

These are the next 4 formulas you will need to know:

4 key terms you need to know before we start:

PV = Planned Value – As of today what is the amount of work that should be completed?

EV = Earned Value – As of today what is the amount of work that is actually accomplished?

AC = Actual Cost – As of today what is the actual cost incurred for the work accomplished

BAC = Budget at Completion – How much did we budget for the total project??

Page 13: Learning pmp formulas the easy way

The Formulas You Need to Know for the Test

These are the next 4 formulas you will need to know:

CV SV CPI SPI Cost Schedule Cost Schedule

Variance Variance Performance Performance

Index Index

EV – AC

Where:

EV = Earned Value

AC = Actual Cost

EV – PV

Where:

EV = Earned Value

PV = Planned Value

EV / AC

Where:

EV = Earned Value

AC = Actual Cost

EV / PV

Where:

EV = Earned Value

PV = Planned Value

Page 14: Learning pmp formulas the easy way

The Formulas Explained - Next 4

6. CV - Cost Variance EV – AC

The difference between Earned Value and Actual Cost Negative value = Cost Overrun or over budget Positive value = on or under cost or under budget Are we under or over budget 1.0 or greater is good

EV = Earned ValueAC = Actual Costs

Page 15: Learning pmp formulas the easy way

The Formulas Explained - Next 4

7. SV - Schedule Variance EV – PV

The difference between Earned Value and Planned Value Negative value = behind schedule Positive value = on or ahead of schedule Are we ahead or behind schedule 1.0 or greater is good

EV = Earned ValuePV = Planned Value

Page 16: Learning pmp formulas the easy way

The Formulas Explained - Next 4

8. CPI - Cost Performance Index EV / AC

The ratio of Earned Value to Actual Cost Value < 1 = Cost over budget Value > 1 = Cost below budget How efficiently are we using our resources Ex) We are only getting about 89 cents out of every dollar we

put into the project – THIS IS BAD

EV = Earned ValueAC = Actual Costs

Page 17: Learning pmp formulas the easy way

The Formulas Explained - Next 4

9. SPI - Schedule Variance EV / PV

The ratio of Earned Value to Planned Value Value < 1 = behind schedule Value > 1 = on or ahead of schedule How efficiently are we using time Ex) We are only progressing at about 83 percent of the rate

planned – THIS IS BAD

EV = Earned ValuePV = Planned Value

Page 18: Learning pmp formulas the easy way

The Formulas You Need to Know for the Test

These are the next 4 formulas you will need to know:

EAC ETC TCPI VAC Estimate at Estimate to To Complete Variance

at

Completion Complete Performance Completion

Index BAC / CPI

Where:

BAC = Budget at Completion

CPI = Cost Performance Index

EAC – AC

Where:

EAC = Estimate at Completion

AC = Actual Cost

BAC - EV BAC - AC

Where:

BAC = Budget at CompletionEV = Earned ValueAC = Actual Cost

BAC - EAC

Where:

BAC = Budget at Completion

EAC = Estimate at Completion

Page 19: Learning pmp formulas the easy way

The Formulas Explained - Next 4

10. EAC - Estimate at Completion BAC / CPI The ratio of Budget at Completion to Cost Performance Index This formula is used if no variances from the BAC have occurred A forecasting formula or AC + (BAC – EV) calculates the actual to date plus remaining

budget – Ac plus the remaining work to perform As of now, how much do we expect the total project to cost

BAC = Budget at Completion

CPI = Cost Performance Index (EV / AC)

Page 20: Learning pmp formulas the easy way

The Formulas Explained - Next 4

11. ETC - Estimate to Complete EAC - AC The difference between the Estimate at Completion ratio and the

Actual Costs to date This is a forecasting formula From this point on, how much more do we expect it to cost to

finish the project cost or what will the remaining work cost

EAC = Estimate at Completion

AC = Actual Cost

Page 21: Learning pmp formulas the easy way

The Formulas Explained - Next 4

12. TCPI - To Complete BAC - EV Performance Index BAC - AC

The ratio of Budget at Completion to Earned Value divided by the ratio of Budget at Completion to Actual Cost

This formula divides the work remaining to be done by the money remaining to do it

Ex) By how much does our performance need to improve, in order come on in time and on budget

BAC = Budget at CompletionEV = Earned ValueAC = Actual Cost

Page 22: Learning pmp formulas the easy way

The Formulas Explained - Next 4

13. VAC -Variance at Completion BAC – EAC

The difference between the Budget at Completion and the Estimate at Completion ratio

This is a variance formula Ex) As of today will we be under or over budget at the end

of the project

EAC = Estimate at Completion

BAC = Budget at Completion

Page 23: Learning pmp formulas the easy way

The Formulas You Need to Know for the Test

These are final 3 formulas you will need to know:

EMV TOTAL PTA

Expected FLOAT Point of Total

Monetary Value Assumption

P x I

Where:

P = Probability

I = Impact

ES EF

LS LF

[(CP –TP) / BSR] + TC

Where:

CP = Ceiling Price

TP = Target Price

BSR = Buyers Share Ratio

TC = Target Cost

LS – ES orLF - EF

Page 24: Learning pmp formulas the easy way

The Formulas Explained - Final 3

14. EMV - Expected Monetary Value P x I

Used to determine the overall ranking of risks. A better way than evaluating just the probability or impact.

P = Probability

I = Impact

Page 25: Learning pmp formulas the easy way

The Formulas Explained - Final 3

15. Total Float = LS - ES

or LF - EF Use this formula to compute float of activities We always begin “Late” so start each formula as LS or LF Used to evaluate delay or slack on activities thus determining

resource allocation Remember activities on the “Critical Path” almost always have zero

float

LS = Late Start ES = Early Start Note: Either formula

LF = Late Finish EF = Early Finish will get the same answer

ES EF Amount of Float

LS LF

Page 26: Learning pmp formulas the easy way

The Formulas Explained - Final 3

16. PTA - Point of Total Assumption

[(CP –TP) / BSR] + TC

Only applies to Fixed Price incentive fee contracts Refers to the amount above which the seller bears all the loss

of a cost overrun Costs that go above the PTA are assumed to be due to

management

CP = Ceiling Price TP = Target Price

BSR = Buys Share Ratio TC = Target Cost

Page 27: Learning pmp formulas the easy way

How to Learn the Formulas the “Easy” Way

OK let’s put it all together….

Get a regular piece of 8” x 11” paper Draw a vertical line 2” across from the left side of the paper Draw a horizontal line 3” down from the top of the paper

Page 28: Learning pmp formulas the easy way

How to Learn the Formulas the “Easy” Way

Above the horizontal line put your first 5 formula names:

PV SD SDV PERT CC Future Standard Standard Expected Communication

Value Deviation Deviation Activity Channels Duration

Notice we start with the “present” - PV.

But these are “standard” formulas, so write SD twice and take the “V” from

the first formula PV and put it at the end of your second SD to make SDV.

Next remember to wash your hair with “PERT”

Last, you’re tired so have a “CC” on the rocks – Communication Channels

Page 29: Learning pmp formulas the easy way

How to Learn the Formulas the “Easy” Way

Next write in your first 5 formulas under them:

PV SD SDV PERT CC

FV (R + 1)

n

P - O 6

P - O 6

P - O 6

N (N – 1)2

For the first formula just know that for the Present we must know the Future divided by it’s Rate +1.

Don’t forget that the Rate + 1 result must always be taken to the n power where n = number of time periods. Ex) if the rate was 0.1 and the number of time periods were 3 years then the result would be:

(1 + 0.1) = 1.331

Notice I wrote all the SD, SDV and PERT formulas the same for now because basically they are.

3

Page 30: Learning pmp formulas the easy way

How to Learn the Formulas the “Easy” Way

Next write in your first 5 formulas under them:

PV SD SDV PERT CC

FV (R + 1)

P - O 6

P - O 6

2P + (4M) + O 6

N (N – 1) 2

For the next three formulas just know that always start out the same P – O / 6.

For SDV just square it.

For PERT remember that P-E-R-T is 4 letters, so you must have 4 pieces to the formula the P (Pessimistic) and O (Optimistic), but have to drop the M (Most Likely) x 4 in the middle.

The name “Communication Channels” has 4 “N’s” in it and is the only formula with an N in it – N standing for number of people always divided by 2.

n

Page 31: Learning pmp formulas the easy way

How to Learn the Formulas the “Easy” Way

Above the horizontal line should look like this:

FV SD SDV PERT CC

FV (R + 1)

n

P - O 6

P - O 6

2P + (4M) + O 6

N (N – 1) 2

Page 32: Learning pmp formulas the easy way

How to Learn the Formulas the “Easy” Way

Now below the horizontal line write the 4 key terms:

EV AC PV BAC

Remember: EV = Earned Value AC = Actual Cost PV = Planned Value BAC = Budget at Completion

Page 33: Learning pmp formulas the easy way

How to Learn the Formulas the “Easy” Way

Next the inside vertical line write the next 8 formulas:

CV

SV

CPI

SPI

EAC

ETC

TCPI

VAC

Notice the first 4 are COST and SCHEDULE alternating starting with “C” – COST. Do the “V” Variance before you do the “PI” Index

After you know your COST and SCHEDULES you can then “E” Estimate. Just remember “A” in EAC comes before “T” in ETC

After you Estimate you can Complete Performance. Just remember “T” comes after “E”.

After Completing Performance, how much you will be over or under budget at the end of the project. Just remember “V” comes after “T”.

Page 34: Learning pmp formulas the easy way

How to Learn the Formulas the “Easy” Way

Next to the first 4 formulas, write the following:CV = EV -

SV = EV -

CPI = EV /

SPI = EV /

EAC

ETC

TCPI

VAC

Notice the first 4 formulas all start with EV

Variances “V” are minus

Indexes “I” are divides

Page 35: Learning pmp formulas the easy way

How to Learn the Formulas the “Easy” Way

Now complete the next parts of the formulas:

CV = EV - ACSV = EV - PVCPI = EV / ACSPI = EV / PVEACETCTCPI

VAC

Notice that the Cost formulas are the same the only difference is the minus or divide signs

Notice that the Schedule formulas are the same the only difference is the minus or divide signs

For COST, “A” is closer to “C” so put in AC

For SCHEDULE, “P” is closer to “S” so put in SV

Page 36: Learning pmp formulas the easy way

How to Learn the Formulas the “Easy” Way

Now complete the next 2 formulas:

CV = EV - ACSV = EV - PVCPI = EV / ACSPI = EV / PVEAC = BAC / CPIETC = EAC - AC

TCPI

VAC

Notice that the first part of the EAC formula contains BAC – both have “AC” in it. EAC has a “C” in it – the closest formula up the chain with a “C” in it is CPI so put it in your done.

Remember to divide in this formula! It is the only one left where you have to divide.

For ETC, notice you must have completed EAC before it, which becomes the first part of this formula. The next part “AC” is contained in the first part of the formula.

Note: EAC can also be written as AC + (BAC – EV) just a little twist but contained in CPI

Page 37: Learning pmp formulas the easy way

How to Learn the Formulas the “Easy” Way

Now complete the last 2 formulas:

CV = EV - ACSV = EV - PVCPI = EV / ACSPI = EV / PVEAC = BAC / CPIETC = EAC - ACTCPI = BAC - EV

BAC - ACVAC = BAC - EAC

TCPI is the easiest formula of them all. Start off by drawing a divide line and write BAC above and below it and write 2 minus signs - you’re 50% done already! TCPI has CPI in it. Now look at the formula for CPI it contains EV/AC. Just use that to complete the formula – you’re done!

For VAC use the BAC in the previous formula. Notice VAC has “AC” in it. The closest formula up the chain that has “AC” in it is EAC. Put it in the formula – you’re done!

Notice each formula in the chain relies on a previous formula that you constructed?

Page 38: Learning pmp formulas the easy way

How to Learn the Formulas the “Easy” Way

In the middle of your page add the last 3 formulas:

EMV = P x I

FLOAT = LS - ES or LF - EF

POTA = [(CP - TP) / BSR] + TC

Note: These you will just have to know

Page 39: Learning pmp formulas the easy way

How to Learn the Formulas the “Easy” Way

EMV = P x I

FLOAT = LS - ES or LF - EF

EMV – Probability x Impact is easy to remember

ES EF FLOAT

LS LF

FLOAT – We always start late and subtract the value above it in the box. Write this box down, it may become useful if questions are asked about coming up with a critical path or forward or backwards path of an activity.

Page 40: Learning pmp formulas the easy way

How to Learn the Formulas the “Easy” Way

POTA = Point of Total Assumption

POTA = [(CP - TP) / BSR] + TC

POTA - the first half of the formula both contain “P” = PRICE. Remember you have to jump to the “C” ceiling to hit (minus) a “T” target. Never forget any buyer always gets his share so you have to divide out his “BSR” Buyers Share Ratio. But costs are always around so and you always have to add back his “TC” Target Cost

Page 41: Learning pmp formulas the easy way

How to Learn the Formulas the “Easy” Way

Those are the formulas to know for the exam

Just remember to set up the sheet the way I laid it out for you and you will do fine.

Now it’s time to test yourself – don’t get nervous, it’s easy!

Page 42: Learning pmp formulas the easy way

Test Yourself – Time to Prepare

Study the formulas until you feel confident in being able to recite them. Practice writing them down using my “T” bar on a sheet of paper. Everyday practice writing them down 5 times. If you make mistakes, understand why and correct it. Talk yourself through writing them down using my formula memory method. Do this for two weeks at different times of the day.

Page 43: Learning pmp formulas the easy way

What to do - Pre-Exam

When you feel confident with knowing the formulas:

Get an egg timer or have someone time you.

Write down the formulas as fast as you can – start off with 15 minutes maximum.

Initially, see how long it took you for this first attempt.

Use this initial time as your starting point.

Do this 5 times a day, if you make any mistakes, review the reason(s) why.

Every few days try to take off 1 to 2 minutes your time

A week before the exam you should be able to write them down in 5 minutes

Page 44: Learning pmp formulas the easy way

Your ready!

On the day of the exam you will be given 3 sheets of blank paper to use for math problems.

Before the actual exam starts on the computer you will have 15 minutes to view a computer tutorial to become familiar with the computer commands for the test.

Use part of this this time to write down the formulas on one side of a blank piece of paper

Use this paper as your guide throughout the exam for questions concerning formulas – it is perfectly OK to do this!!!!!

Remember: if you need more paper you will have to turn in used sheets – don’t worry you’ll never need more paper.

GOOD LUCK and do not worry – you will pass !!!!!!!!!!!

Page 45: Learning pmp formulas the easy way

QUESTIONS

Tell me what you think

[email protected]