Large-scale marine energy projects in Natura 2000 sitesLegal aspectsOosterschelde & Pentland Firth case study

Sander van HeesPhD researcher

Page 2: Large scale marine energy projects in Natura2000 - legal aspects

Case studies

Pentland Firth (UK) – MeyGen (first phase)

6 turbines (6 MW)

Oosterschelde (NL) – Tocardo

5 turbines (1.2 MW)

Page 3: Large scale marine energy projects in Natura2000 - legal aspects

Designated Natura 2000 sites

Pentland Firth (UK) Oosterschelde (NL)

Page 4: Large scale marine energy projects in Natura2000 - legal aspects

Potential impacts on protected nature

Pentland Firth (UK) Oosterschelde (NL)

Birds (eg ‘Red-throated diver’)- Displacement and a loss of foraging habitat- Bird-turbine collisions

Marine mammals (seals and cetaceans**) and fish (eg Atlantic salmon) - Mammal-turbine collisions- Barrier effects

Overall: a lack of knowledge

Habitats- Increased erosion of sand banks

Marine mammals (seals and cetaceans**) and fish (eg Sea lamprey) - Mammal-turbine collisions- Barrier effects

Birds (eg Sandwich Tern)- Less visibility because of turbulence

Overall: a lack of knowledge

Page 5: Large scale marine energy projects in Natura2000 - legal aspects

Decision making process for protected habitats

1. Is there a probability, or a risk, that the project will have a significant effect on the site?

Page 6: Large scale marine energy projects in Natura2000 - legal aspects

Decision making process for protected habitats

1. Is there a probability, or a risk, that the project will have a significant effect on the site?

Competent authority may grant authorisation of the project

NO

2. Appropriate assessment

YES - Can it be excluded on the basis of objective information, that the plan or project will have a significant effect on the site concerned?

- Is the project likely to undermine the conservation objectives of the site?

Page 7: Large scale marine energy projects in Natura2000 - legal aspects

Decision making process for protected habitats

1. Is there a probability, or a risk, that the project will have a significant effect on the site?

3. Does reasonable scientific doubt remain as to the absence of lasting adverse effects

on the integrity of the site?

Competent authority may grant authorisation of the project

NO

2. Appropriate assessment

YES

* Mitigation *

- Are the protected habitats and species stable or increasing and are the specific structure and functions which are necessary for its long-term maintenance exist and are likely to continue to exist for the foreseeable future?

- No exclusion of all possible risks

- Are possible mitigation measures available?

- Does step 3 offer flexibility to competent authorities?

Page 8: Large scale marine energy projects in Natura2000 - legal aspects

Decision making process for protected habitats

1. Is there a probability, or a risk, that the project will have a significant effect on the site?

3. Does reasonable scientific doubt remain as to the absence of lasting adverse effects

on the integrity of the site?

4. Competent authority must refuse authorisation of the project

Competent authority may grant authorisation of the project

YES NO

2. Appropriate assessment

YES

* Mitigation *

Page 9: Large scale marine energy projects in Natura2000 - legal aspects

Decision making process for protected habitats

1. Is there a probability, or a risk, that the project will have a significant effect on the site?

3. Does reasonable scientific doubt remain as to the absence of lasting adverse effects

on the integrity of the site?

4. Competent authority must refuse authorisation of the project

Competent authority may grant authorisation of the project

Unless:1. No alternative solutions2. ‘Imperative reasons of overriding public interest’3. Compensation4. Inform the European Commission

YES NO

2. Appropriate assessment

YES

* Mitigation *

Page 10: Large scale marine energy projects in Natura2000 - legal aspects
Page 11: Large scale marine energy projects in Natura2000 - legal aspects

Decision making process for protected species

Is one of the prohibitions breached?

• Prohibition of deliberate disturbance, capture or killing.• Prohibition of deterioration or destruction of breeding sites or

resting places.

Competent authority may grant authorisation of the project

Exception, for non-bird species (eg porpoises):

- No satisfactory alternative- Populations maintain at favourable conservation status- imperative reason of overriding public interest

Yes

NO

Exception, for bird species:

- No satisfactory alternative- Listed reasons: it is in the interest of public

health and safety; for the protection of flora and fauna, etc…….

Page 12: Large scale marine energy projects in Natura2000 - legal aspects

Sander van HeesPhD researcher

Utrecht Centre for Water, Oceans and Sustainability Law

[email protected]