laporan bulan maret jufmp/jedi 2015 (monthly report march 2015) - power point
DESCRIPTION
Laporan Bulan Maret 2015 Proyek Penanganan Darurat Banjir Jakarta atau JUFMP/JEDI oleh Konsultan Supervisi Pelaksanaan JUFMP/JEDI, Construction SUpervision Consultant (CSC) for JUFMP/JEDITRANSCRIPT
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 1
Korea Engineering Consultant Corp of Korea,
in association with
PT. Puser Bumi Mekon
PT. Tetira International Consultants
PT. Duta Cipta Mandiri Engineering Consultants
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 2 Korea Engineering Consultant Corporation (KECC)
1. JUFMP/JEDI General Information 2. Consultant Services 3. Executive Summary 4. Issues 5. Ongoing Construction Packages * Package 1 * Package 2A * Package 2B * Package 3 * Package 5 6. Photo Gallery
Table of Contents
Project Information
Project Name : JUFMP/JEDI
Loan Agreement : 8121 ID
Date of Loan Sign : February 17, 2012
Effective Date : August 8, 2012
Closing Date : March 31, 2017
Loan Amount : USD 139,640,000
Executing Agency : 1. Directorate General Water Resources, MoPW 2. Directorate General Cipta Karya, MoPW 3. Provincial Government of DKI Jaya
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 3 Korea Engineering Consultant Corporation (KECC)
1. Reduce the frequency and extend of flooding in Jakarta through dredging,
and rehabilitation and construction of embankment of key waterways and
flood retention basins;
2. Establishing institutional coordination between, and strengthening their
capacity of the three responsible agencies, to improve the operations,
maintenance and management of Jakarta’s flood management system.
The project is intended to reduce the economic and social cost of flooding by
partially restoring the capacity of the city’s flood control system to its original
design level.
Project Component
1. Dredging and rehabilitation of selected floodways, canals and retention
basins: USD 176.1 million
2. Technical assistance for project management, social safeguards, and capacity
building: USD 13.4 million
Project Development Objective (PDO)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 4 Korea Engineering Consultant Corporation (KECC)
Project Organization
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 5 Korea Engineering Consultant Corporation (KECC)
Project Location
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 6 Korea Engineering Consultant Corporation (KECC)
Construction Supervision Consultant (CSC) for JUFMP/JEDI
Project Name : Construction Supervision Consultant for JUFMP{/JEDI
Source of Fund : World Bank
Addendum No.1 : 1,784,300 USD + 38,494,770,000 IDR
Contract Amount : 2,072,400 USD + 38,153,170,999 IDR
Engineer : Directorate of River and Coastal, Directorate General Water Resources, Ministry of Public Work and Housing
Contractor : Korea Engineering Consultants Corporation with PT. Puser Bumi Mekon joint venture and sub consultancy PT. Tetira International Consultant and PT. Duta Cipta Mandiri Engineering Consultant
Contract No. : 06/KTR/PPK-Ad-Satker/X/2013 September 11, 2013
Notice to Proceed : HI.0102-Ad/496 October 18, 2013
Time Period : 40.5 months Add No.1, originally 60 months
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 7 Korea Engineering Consultant Corporation (KECC)
Outline of Consultant Services
The main services of the Consultant for JUFMP/JEDI are: • Supervision of Dredging Work and Construction/Rehabilitation
of Embankment • Quality Assurances and Quality Control • Assist in Implementation of Environmental Management
(RKL/RPL) • Assist in Implementation of Resettlement Plans (RPs) • Implementation of Grievance Redress System (GRS) and
Complaint Handling • Monitoring, Reporting and Recording • Assist CPMU, CPIU and PIUs in Project Management
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 8 Korea Engineering Consultant Corporation (KECC)
Executive Summary
Figure 1. Budget Allocation for Component 1of JUFMP (in million USD)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 9 Korea Engineering Consultant Corporation (KECC)
103.5
58%
53.0
30% 22.3
12%
Total Budget 178.7
Prov Gov of DKI (37%) + IBRD (67%)
DG Water Resources (20%) + IBRD (80%)
DG Cipta Karya (20%) + IBRD (80%)
Executive Summary
Table 1. Budget Allocation for Component 1 by Packages
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 10 Korea Engineering Consultant Corporation (KECC)
Executing Agencies/ Packages Budget (Loan +
APBN/D) Loan Allocation
APBD/N
Sharing USD USD USD
1 4 = 2 + 3 2 3
DKI Jakarta 103,492,537 69,340,000 34,152,537
Package 1 36,716,418 24,600,000 12,116,418
Package 4 47,014,925 31,500,000 15,514,925
Package 7 19,761,194 13,240,000 6,521,194
DGWR 53,000,000 42,400,000 10,600,000
Package 2A 31,000,000 24,800,000 6,200,000
Package 2B 8,125,000 6,500,000 1,625,000
Package 6 13,875,000 11,100,000 2,775,000
DGCK 22,250,000 17,800,000 4,450,000
Package 3 6,717,421 5,373,937 1,343,484
Package 5 15,532,579 12,426,063 3,106,516
TOTAL 178,742,537 129,540,000 49,202,537
Executive Summary
Table 2. Budget Allocation for Component 2
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 11 Korea Engineering Consultant Corporation (KECC)
Items Total Loan IBRD
APBD/N
Sharing
Bilateral
Grant USD USD USD USD
Supervision Consultant 10,100,000 10,100,000 - -
Flood Management Information System 500,000 - - 500,000
Panel of Experts 500,000 - 500,000 -
Resetlement Cost (DKI Jaya) 2,800,000 - 2,800,000 -
Total Component 2 13,900,000 10,100,000 3,300,000 500,000
Total Project Cost (Comp 1+2) 192,642,537 139,640,000 52,502,537 500,000
Executive Summary
Table 3. Contract Amount by Packages (in million IDR)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 12 Korea Engineering Consultant Corporation (KECC)
Executing Agencies/
Packages Contract Amount Loan APBN/D Sharing
DKI Jakarta 284,180,000,000 190,400,600,000 93,779,400,000
Package 1 284,180,000,000 190,400,600,000 93,779,400,000
Package 4 - - -
Package 7 - - -
DGWR 334,965,463,260 267,972,370,608 66,993,092,652
Package 2A 260,000,000,000 208,000,000,000 52,000,000,000
Package 2B 74,965,463,260 59,972,370,608 14,993,092,652
Package 6 - - -
DGCK 208,214,431,000 166,571,544,800 41,642,886,200
Package 3 68,514,386,000 54,811,508,800 13,702,877,200
Package 5 139,700,045,000 111,760,036,000 27,940,009,000
TOTAL 827,359,894,260 624,944,515,408 202,415,378,852
Executive Summary
Figure 4. Financial Progress (in billion IDR)
-
50
100
150
200
250
300
Package 1 Package 2A Package 2B Package 3 Package 5
163.6 148.6
33.9
19.8 22.2
208.7 201.5
54.9 54.0
32.9
284.2
260.0
75.0 68.5
139.7
Disbursed Disbursement + Un-disbursement Contract Amount
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 13 Korea Engineering Consultant Corporation (KECC)
Executive Summary
Table 4. Volume of Dredge Material of On-going Packages
* Based on the latest addendum
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 14 Korea Engineering Consultant Corporation (KECC)
Package Sign Date Notice to
Proceed
Period
Volume (thousand m3)
Weight Garbage Sludge
Garbage +
Sludge
(days) (m3) (m3) (m3) (%)
Package 1 Nov 26,2013 Dec 02,2013 730 2.8 165.6 168.4 8.3
Ciliwung-Gn. Sahari 1.5 85.1 86.6 4.2
Waduk Melati 1.4 80.5 81.9 4.0
Package 2A Nov 11,2013 Nov 11,2013 730 18.8 1,007.3 1,026.1 50.4
Package 2B Nov 11,2013 Nov 11,2013 730 20.0 513.7 533.7 26.2
Package 3 Nov 15,2013 Nov 15,2013 730 0.8 48.4 49.2 2.4
Package 5 Sep 3,2014 Sep 3,2014 730 6.2 253.0 259.2 12.7
Tanjungan Drain 0.0 11.2 11.2 0.6
Lower Angke Drain 6.2 241.8 248.0 12.2
T O T A L 48.7 1,988.0 2,036.7 100.0
Executive Summary
Table 5. Progress of Dredging Works (on-going packages)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 15 Korea Engineering Consultant Corporation (KECC)
Package Trip of
Truck
Volume (thousand m3)
Garbage Sludge Garbage + Sludge
Package 1 8,072 - 149.2 149.2 88.6%
Ciliwung-Gn.Sahari 4,290 - 78.2 78.2 90.3%
Waduk Melati 3,782 - 71.0 71.0 86.7%
Package 2A 42,390 - 711.7 711.7 69.4%
Package 2B 19,377 - 334.2 334.2 62.6%
Package 3 209 - 3.6 3.6 7.3%
Package 5 - - - - -
Tanjungan Drain - - - - -
Lower Angke Drain - - - - -
T O T A L 70,048 - 1,198.7 1,198.7 58.9%
Executive Summary
Figure 5. Schedule and Progress of Construction Works (%)
0 10 20 30 40 50 60 70 80 90
Package 5
Package 3
Package 2B
Package 2A
Package 1
13.0
81.9
74.0
66.3
72.4
13.6
78.8
73.3
77.5
73.4
Progress Schedule
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 16 Korea Engineering Consultant Corporation (KECC)
Issues
1. Package 1 – Ciliwung-Gunung Sahari and Waduk Melati
a) At waduk Melati, additional work will include railing to be installed around the waduk (original contract for installing fencing was deleted during MC 0).
b) Construction of Waduk Melati pump (4 m3/s) has tight work schedule c) At Gunung Sahari drain, several several need to be completed such as
gaps between embankment edge and bridges, U-ditch along the right bank and side walk along Jl. Gunung Sahari DKI request to heighten thje side walk as it plans).
2. Package 2A – Cengkareng Floodway
a) Embankment work at both sides of the floodway between bridges at STA 2+250 – STA 2+500 has not been started yet. Contractor propose using stone masonry rather than piles for the reason of working space limitation.
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 17 Korea Engineering Consultant Corporation (KECC)
Issues
b) At STA 3+400 – STA 5+050, there are several missing portion (gaps) on the presence of road crossings and culverts.
c) Remedial works have not been started . d) Water intake at Kembangan (PAM) is not relocated yet.
3. Package 2B – Lower Sunter Floodway
a) Temporary disposal using barges is still not being used.
4. Package 3 – Cideng-Thamrin Drain
-
5. Package 4 – Sentiong Sunter, Waduk Sunter Utara, Waduk Sunter Selatan and Waduk Sunter Timur III
a) Bid opened on March 24, 2015. PT. Adhi Karya has the lowest bidding price of 296.9 billion IDR
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 18 Korea Engineering Consultant Corporation (KECC)
Issues
6. Package 5 – Lower Angke and Tanjungan Drain
a) Not sufficient storage space available for CCSPs and heavy equipment (such as crane) at Lower Angke Drain.
b) DKI proposed a detention basin between Tanjungan drain and Kamal. c) Complaint from community to widen Tanjungan drain from 10 up to
14 m.
7. Package 6 – Banjir Kanal Barat (BKB)and Upper Sunter
a) Dredge from Karet to river mouth proposed to add to Package 6. b) Bidding is delayed due to LARAP.
8. Package 7 – Grogol Seketaris, Pakin, Kali Besar, Jelakeng and Krukut
a) Bid opened March 10, 2015. PT. Waskita Karya has the lowest bidding price of 226.8 billion IDR.
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 19 Korea Engineering Consultant Corporation (KECC)
Issues
9. LARAP a) Houses and buildings along upper Sunter Floodway (Package 6) in
Kayu Putih village of Pulo Gadung sub-district have been demolished by DKI Jaya Government. PAPs of JUFMP/JEDI located on Jatinegara Kaum were not affected by the demolition.
b) Due to problem at Lower Angke Muara, Dinas Tata Air DKI modify embankment work at Kel. Kapuk Muara to stone masonry in stead of piles.
c) LARAP reports for Sentiong Sunter, Waduk Sunter Utara and Waduk Sunter Selatan were prepared and second socialization is planned.
10.Construction Supervision Consultant a) Staff of site offices have faced difficulties due to shortage of
transportation (mainly motor cycles). b) Overtime payment for enumerators and drivers not yet resolved.
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 20 Korea Engineering Consultant Corporation (KECC)
www.jufmp.com 21 Korea Engineering Consultant Corporation (KECC)
Provincial Government of DKI Jaya World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
PACKAGE 1 CILIWUNG-GUNUNG SAHARI DRAIN AND WADUK MELATI
PT. Brantas Abipraya (Persero)
Contractor:
www.jufmp.com 22 Korea Engineering Consultant Corporation (KECC)
Provincial Government of DKI Jaya World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
General Information
P I U : DPU - DKI
Contractor : PT. Brantas Abipraya
No Objection Letter : No. JUFMP 1
Letter of Acceptance : No. 14705/-7.793.2
Contract No. : 15380/-1.793.2 dated Nov 26, 2013
Contract Amount : IDR 284,180,000,000 (incl. PPN)
Signed Date : Nov 26, 2013
Notice to Proceed : 15452/-1.793.2 dated Nov 26, 2013
Completion Day : 730 Calendar days
Elapsed Days : 484 days (66.3 %)
www.jufmp.com 23 Korea Engineering Consultant Corporation (KECC)
Provincial Government of DKI Jaya World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Location and Scope of Works
ISTIQLAL MOSQUE
SHEET PILE 4,832 m
Dredging Volume: 86,557 m3
Progress : 78,185 m3 or 90.3% Embankment Repair : 4.600 m
LENGTH OF DREDGING
5,100 m
Ciliwung – Gunung Sahari Drain
www.jufmp.com 24 Korea Engineering Consultant Corporation (KECC)
Provincial Government of DKI Jaya World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Progress
I. Ciliwung-Gunung Sahari Drain 1. Dredging Work
Total volume = 86,557 m3 Progress = 78,185 m3 or 90.3% a) STA 0+500 – STA 5+100 (Upstream of Martadinata Bridge up to
Istiqlal – Pasar Baru) 2. Concrete Work
a) Total concrete = 2,033 m3 Length of concrete work 3,171 m
b) Form work type-B 450 at Ciliwung-Gunung Sahari - STA 0+625 – STA 1+037 (R) Length = 330.7 m - STA 1+050 – STA 1+120 (L) Length = 120.0 m - STA 1+731 – STA 1+997 (R+L) Length = 290.2 m - STA 2+000 – STA 1+900 (R+L) Length= 100 m
c) Reinforcement bar, deformed = 91.04 ton
www.jufmp.com 25 Korea Engineering Consultant Corporation (KECC)
Provincial Government of DKI Jaya World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Progress 3. Pilling Work
a) Furnishing of corrugated pre-stressed concrete pile (CCSP) W-450 i. CCSP W-450 L 12 m = 2,339 units ii. CCSP W-450 L 14 m = 1,573 units iii. CCSP W-450 L 17 m = 1,132 units iv. Square pile 40x40 cm= 392 units
b) Driving of CCSP W-450, total progress CCSP drived = 5,178 units i. Driving of CCSP W-450 L 12 m = 2,442 units
- STA 2+250 – STA 2+450 R = 184 units, L = 165 units - STA 2+600 – STA 2+800 R = 252 units, L = 249 units - STA 2+800 – STA 3+600 R = 780 units, L = 812 units
ii. Driving of CCSP W-450 L 14 m = 1,582 units - STA 0+550 – STA 1+300 R = 11 units, L = 143 units - STA 1+300 – STA 1+600 R = 270 units, L = 178 units - STA 1+700 – STA 2+150 R = 327 units, L = 371 units - STA 2+250 – STA 2+450 R = 144 units, L = 138 units
iii. Driving of CCSP W-450 L 17 m = 1,154 units - STA 0+550 – STA 1+300 R = 588 units, L = 566 units
www.jufmp.com 26 Korea Engineering Consultant Corporation (KECC)
Provincial Government of DKI Jaya World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Progress
4. Miscellaneous Work a) Demolishing and disposal of existing concrete, total = 12.82 m3 b) Demolishing and disposal of existing stone masonry, total = 2,488 m3
- STA 1+700 – STA 2+700 = 1,157 m3
- STA 0+500 – STA 1+650 = 1,331 m3
www.jufmp.com 27 Korea Engineering Consultant Corporation (KECC)
Provincial Government of DKI Jaya World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Location and Scope of Works
WADUK MELATI
Waduk Melati
Dredging volume : 81,878m3
Progress = 71,015 or 88.2% Embankment Repair : 4,150 m (sheet piles)
Embankment Protection =
4,150 m
Area of dredging 4.9 ha
www.jufmp.com 28 Korea Engineering Consultant Corporation (KECC)
Provincial Government of DKI Jaya World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Progress
II. Waduk Melati
1. Dredging Work Total volume = 81,878 m3 Progress = 71,015 m3 or 88.2%
- STA 0+000 – STA 0+550
2. Concrete Work a) Total concrete = 570.25 m3, length = 1,229 m b) Form work at Waduk Melati c) Reinforcement bar, deformed = 30.95 ton
3. Pilling Works a) Furnishing of corrugated pre-stressed concrete pile (CCSP) W-450
i. CCSP W-450 L 10 m = 959 units ii. CCSP W-450 L 12 m = 249 units iii. CCSP W-450 L 14 m = 0 units
www.jufmp.com 29 Korea Engineering Consultant Corporation (KECC)
Provincial Government of DKI Jaya World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Progress
3. Pilling Works
a) Furnishing of corrugated pre-stressed concrete pile (CCSP) W-450 i. CCSP W-450 L 10 m = 959 units ii. CCSP W-450 L 12 m = 249 units iii. CCSP W-450 L 14 m = 0 units
b) Driving of CCSP W-450, total = 1,208 units i. Driving CCSP W-450, L 10 m = 959 units
- STA 0+305 – 0+427 R = 608 units, L = 351 units ii. Driving CCSP W-450, L 12 m = 249 units
- STA 0+250 – 0+305 R = 3 units, L = 246 units iii. Driving CCSP W-450, L 14 m = 0 units
4. Miscellaneous Work
a) Demolishing and disposal of stone masonry, total = 1,021 m3 - STA 0+250 – STA 0+700 Right = 541 m3
- STA 0+200 – STA 0+600 Left = 480 m3
Package 1. Ciliwung-Gn Sahari Drain and Waduk Melati
Figure 1.1. Progress of Dredging and Disposal Work (thousand m3) May 2014-Mar 2015
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 30 Korea Engineering Consultant Corporation (KECC)
0.1 0.1 0.1 2.3
27.3
55.8
81.3 97.6
116.6 132.3
149.2
0
20
40
60
80
100
120
140
160
May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15
0 2
6 10
14
19 23
29
36
44
51
58
65
72
77
72
3 4 6 9
15 20
30
37
43
53
58
62 67
69 71
73
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
Package 1. Ciliwung-Gn Sahari Drain and Waduk Melati
Figure 1.2. Schedule and Progress of Construction Work (%) Dec 2013-- Mar 2015
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 31 Korea Engineering Consultant Corporation (KECC)
Schedule Progress
Package 1. Ciliwung-Gn Sahari Drain and Waduk Melati
Figure 1.3. Financial Progress (in billion IDR)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 32 Korea Engineering Consultant Corporation (KECC)
163.6
58%
45.1
16% 75.5
26%
Disbursed Undisbursed Remaining
Contract Value = 284.2
www.jufmp.com 33 Korea Engineering Consultant Corporation (KECC)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Contractor:
PACKAGE 2A CENGKARENG FLOODWAY
Adhi Karya-Hutama Karya-Jaya Konstruksi JV
Ministry of Public Works and Housing World Bank
www.jufmp.com 34 Korea Engineering Consultant Corporation (KECC)
General Information
P I U : BBWS Ciliwung-Cisadane, DGWR
Contractor : Adhi Karya-Hutama Karya-Jaya Konstruksi (JV)
No Objection Letter : No. JUFMP/107 dated Sep 7, 2013
Letter of Acceptance : No.KU.03.01/PPK SP-SNVT PJSA CC/XI/310.1 dated Nov 6, 2013
Contract No. : HK.02.03/PPK SP-SNVT PJSA CC/XI/315.4 dated Nov 11, 2013
Amendment IV : IDR 260,000,000,000 incl. 10% tax
Amendment II : IDR 234,627,368,750 incl. 10% tax
Original Contract : IDR 209,808,000,000 incl. 10% tax
Signed Date : Nov 11, 2013
Completion Day : 730 Calendar days
Elapsed Days : 505 days (69.2%)
Provincial Government of DKI Jaya World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
www.jufmp.com 35 Korea Engineering Consultant Corporation (KECC)
Location and Scope of Works Ministry of Pablic Works and Housing World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Sta 7+800
Sta 6+750
Sta 5+000
Sta 3+750
Replacement of Water Gates Sta 4+500
Sta 5+875
W : 325 ; B : 1000 L : 14 meter
KAPUK PULO BRIDGE
KEMBANGAN BRIDGE
KAPUK RAYA
DREDGING WORK
Target Length = 8,380 m
Volume=1,026,125 m3 Finished Length = 4+700 m
Volume= 711,684 m3
PILLING WORK Target Length = 5,700 m
CCSP W-325 = 5,700 units
Pile 30x30 = 1,425 units Finished Length = ……... m
CCSP W-325 = 5,703 units
Pile 30x30 = 1,203 units
PILLING WORK
Length = 4,600 m
CCSP W-325 = 110,699 units
Pile 30x30 = 390,000 units
PILLING WORK Target Length = 2,100 m CCSP W-325 = 2,100 units Pile 30x30 = 525 units
Finished Length = 1,000 m CCSP W-325 = 1,071 units Pile 30x30 = 175 units
Cengkareng Floodway
www.jufmp.com 36 Korea Engineering Consultant Corporation (KECC)
Progress Ministry of Pablic Works and Housing World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
1. General Items a) Preparation works b) Temporary access road c) Environmental test d) Environment monitoring and management e) Temporary storage area f) GPS vehicle tracking system (monitoring system) + server g) Rent of weight bridge
2. Dredging Work a) Total volume = 1,026,125 m3 Progress = 711,684 m3 (69.4%)
- STA 7+800 – STA 6+650
- STA 5+000 – STA 1+200
- STA 1+200 – STA 0+500
b) Rent of equipment for spreading on dumping area at CDF Ancol
www.jufmp.com 37 Korea Engineering Consultant Corporation (KECC)
Progress Ministry of Pablic Works and Housing World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
3. Concrete Work a) Concrete capping beam, total = 2,292.1m3
- STA 2+100 – STA 1+359 R = 260.7 m3 - STA 5+000 – STA 2+500 R = 800.5 m3 - STA 7+700 – STA 6+531 R = 352.0 m3
- STA 5+000 – STA 2+500 L = 793.1 m3 - STA 7+700 – STA 7+280 L = 85.8 m3
b) Concrete back pile 50x50x50 cm = 1,203 units = 150.30 m3
- STA 5+000 – STA 2+500 R = 601 units = 65.12 m3 - STA 5+000 – STA 2+500 L = 602 units = 68.75 m3 - STA 2+208 – STA 1+359 R = 222 units = 27.75 m3
- STA 7+700 – STA 6+531 R = 310 units = 28.75 m3
c) Concrete walling steel = 86 m3
- STA 5+000 – STA 2+500 R = 550 units = 41 m3
- STA 5+000 – STA 2+500 L = 500 units =45 m3
www.jufmp.com 38 Korea Engineering Consultant Corporation (KECC)
Progress Ministry of Pablic Works and Housing World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
4. Pilling Work a) Furnishing of CCSP, total = 8,057 units
i. CCSP W-325 A, L 12 m, total = 5,162 units ii. CCSP W-325 B, L 14 m, total = 2,567 units iii. CCSP W-325 B, L 15 m, total = 55 units iv. CCSP W-450 A, L 18 m, total = 273 units
b) Furnishing of concrete back pile 30x30, total = 2,064 units i. L 10 m, total = 1,656 units ii. L 12 m, total = 408 units
c) Driving of CCSP, total = 8,098 units - STA 5+000 – STA 2+500 at R W-325 A L 12 m, total = 1,194 units - STA 5+000 – STA 2+500 at R W-325 B L 14 m, total = 1,212 units - STA 5+000 – STA 2+500 at L W-325 A L 12 m, total = 1,632 units - STA 5+000 – STA 2+500 at L W-325 A L 12 m, total = 760 units
www.jufmp.com 39 Korea Engineering Consultant Corporation (KECC)
Progress Ministry of Pablic Works and Housing World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
c) Driving of CCSP total = 7,576 units (cont.) - STA 2+515 – STA 2+361, R W-325 B L 15 m, total= 146 units - STA 2+200 – STA 1+206, L W-325 A L 14 m, total = 603 units - STA 2+200 – STA 1+206, L W-325 A L 15 m, total = 55 units - STA 2+200 – STA 1+206, L W-450 A L 18 m, total = 300 units - STA 7+700 – STA 6+531, R W-325 A L 12 m, total = 1,114 units - STA 7+700 – STA 6+522, L W-450 A L 12 m, total = 1,082 units
d) Driving back pile 30x30 cm, total = 1,842 units
- STA 5+000 – STA 2+500 at R L 10 m = 427 units, L 12 m = 129 units - STA 5+000 – STA 2+500 at L L 10 m = 603 units - STA 7+700 – STA 6+812 at L L 10 m = 310 units - STA 7+700 – STA 6+674 at L L 10 m = 151 units - STA 2+205 – STA 1+206 at R L 10 m = 22 units, L 12 m = 192 units - STA 2+361 – STA 2+393 ar R L 12 m = 8 units
Package 2A. Cengkareng Floodway
Figure 2A.1. Progress of Dredging and Disposal Work (thousand m3) Mar 2014-- Mar 2015
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 40 Korea Engineering Consultant Corporation (KECC)
13.7 29.4
67.1 92.8
123.4 134.7
182.5 246.7
377.4 457.5
530.1 605.5
711.7
0
80
160
240
320
400
480
560
640
720
800
Package 2A. Cengkareng Floodway
Figure 2A.2. Progress of Dredging and Disposal Work (thousand m3) Dec 2014-- Mar 2015
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 41 Korea Engineering Consultant Corporation (KECC)
1 3
3
8
17 19
32
38 41
46 49
53
60 62
65 66
11
23 27
29
34 37
40
46 47
54 57
65 66 69
73
78
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
Schedule Progress
Package 2A. Cengkareng Floodway
Figure 2A.3. Financial Progress (billion IDR)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 42 Korea Engineering Consultant Corporation (KECC)
148.6
57%
52.9
20%
58.5
23%
Disbursed Undisbursed Remaining
Contract Value = 260.0
www.jufmp.com 43 Korea Engineering Consultant Corporation (KECC)
Contractor:
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
PACKAGE 2B LOWER SUNTER FLOODWAY
PT. Hutama Karya (Persero)
www.jufmp.com 44 Korea Engineering Consultant Corporation (KECC)
General Information
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
P I U : BBWS Ciliwung-Cisadane, DGWR
Contractor : PT. Hutama Karya
No Objection Letter : No. JUFMP/1
Letter of Acceptance : No.14705/-7.793.2
Contract No. : HK.02.03/PPK SP-SNVT CC/XI/315.4
Contract Amount : IDR 65,258,477,570
Amendment I No. : HK.02.03/AMD/PPK SP-SNVT/PJSA CC/II/38.5
Amendment I Amount : IDR 74,965,463,260
Signed Date : Nov 11, 2013
Notice to Proceed : Nov 11, 2013
Completion Day : 730 Calendar days
Elapsed Days : 505 days (69.2 %)
www.jufmp.com 45 Korea Engineering Consultant Corporation (KECC)
Location and Scope of Works Ministry of Pablic Works and Housing World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Concrete wall
1,000 m
Concrete Wall
400 m
Concrete Wall
400 m
Lower Sunter Floodway
www.jufmp.com 46 Korea Engineering Consultant Corporation (KECC)
Progress Ministry of Pablic Works and Housing World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
1. General Items
a) Preparation works b) Environment test c) Environmental monitoring and management 2. Dredging works
Total volume = 533,689 m3 , progress = 334,215m3 or 62.6% - STA 0+025 – STA 7+350
3.Concrete works
a) Concrete type-A (K-225), total= 1,998 m3
- STA 7+263 – STA 6+933 = 400 m3 (Jul, 2014, Kodamar) - STA 6+911 – STA 6+758 = 185 m3 (Jul, 2014, Kodamar) - STA 6+758 – STA 6+614 = 261 m3 (Aug, 2014, Kodamar) - STA 6+614 – STA 6+398 = 45 m3 (Sep, 2014, Kodamar)
www.jufmp.com 47 Korea Engineering Consultant Corporation (KECC)
Progress Ministry of Pablic Works and Housing World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
3. Concrete works
a) Concrete type-A (K-225), total= 1,998 m3 (continued)
- STA 6+407 – STA 6+442 = 58 m3 (Nov, 2014, Kodamar) - STA 7+855 – STA 7+902.82= 69 m3 (Dec 2015, Kodamar) - STA 5+775 – STA 6+357 = 63 m3 (Jan, 2015, Rumah Pompa) - STA 4+277 – STA 4+645 = 453 m3 (Feb 2015, Saingon)
- STA 5+775 – STA 6+357 = 170 m3 (Feb 2015, Rumah Pompa)
- STA 7+885 – STA 8+170 = 294 m3 (Feb 2015, Pedongkelan)
b) Formwork type A2 = 4,083 m2
c) Reinforcement bar, deformed = 87,305 kg d) Lean concrete t = 10 cm, total = 149 m3
e) Graded sand fill t = 10 cm, total = 149 m3
f) Stone masonry, total = 278 m3 - Parapet wall STA 6+300 – STA 7+241 = 35 m3 (Jan, 2015) - Parapet wall STA 6+096 – STA 5+880 =243 m3 (Feb, 2015)
www.jufmp.com 48 Korea Engineering Consultant Corporation (KECC)
Progress Ministry of Pablic Works and Housing World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
4. Pilling works
a) Furnishing of concrete pile 20x20x400 cm, total = 3,600 units = 14,400 m
b) Driving of concrete pile 20x20x400 cm, total = 2,961 units = 12,744 m - STA 6+924 – STA 7+263 Left = 668 units (Jun 2014) - STA 6+911 – STA 6+375 Left = 918 units (Aug 2014) - STA 7+885 – STA 8+170.5 Left = 410 units (Oct 2014) - STA 6+100 – STA 6+233 Left = 267 units (Nov 2014) - STA 4+277 – STA 4+644 Left = 698 units (Feb 2015)
Package 2B. Lower Sunter Floodway
Figure 2B.1. Progress of Dredging and Disposal Work (thousand m3) Mar 2014-- Mar 2015
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 49 Korea Engineering Consultant Corporation (KECC)
3.0
16.8
47.6
57.3
68.0
81.3
126.8
185.0
243.6 282.7
306.5
314.2
334.2
0
50
100
150
200
250
300
350
400
Package 2B. Lower Sunter Floodway
Figure 2B.2. Schedule and Progress of Construction Work (%) Dec 2014-- Mar 2015
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 50 Korea Engineering Consultant Corporation (KECC)
0 2
5 9
13 17
23
29
37 37
44
51
58
64
68
74
13 13 14 18
24 27
31
37
42 44
47
56 59
65 68
73
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
Schedule Progress
Package 2B. Lower Sunter Floodway
Figure 2B.3. Financial Progress (billion IDR)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 51 Korea Engineering Consultant Corporation (KECC)
33.9
45%
21.0
28% 20.0
27%
Disbursed Undisbursed Remaining
Contract Amount = 75.0
www.jufmp.com 52 Korea Engineering Consultant Corporation (KECC)
Contractor:
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
PACKAGE 2B LOWER SUNTER FLOODWAY
PT. Hutama Karya (Persero)
PACKAGE 3 CIDENG THAMRIN DRAIN
PT. Dutaraya Dinametro
Contractor:
General Information
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 53 Korea Engineering Consultant Corporation (KECC)
P I U : Directorate of Environmental Sanitation Development, Directorate General Human Settlement, Ministry of Public Work and Housing
Contractor : PT. Dutaraya Dinametro
No Objection Letter : No. JUFMP-3
Contract No. : HK.02.03/JUFMP-FSK/XI/1
Contract Amount : IDR 62,324,785,000 (Addendum 2)
IDR 48,747,011,000 (Original Contract)
Signed Date : Nov 15, 2013
Notice to Proceed : Nov 15, 2013
Completion Day : 730 Calendar days
Elapsed Days : 501 days (68.6%)
www.jufmp.com 54 Korea Engineering Consultant Corporation (KECC)
Location and Scope of Works Ministry of Pablic Works and Housing World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Reinforced Concrete Block
EXISTING
SHEETPILES
NEW SHEETPILES
SUB MACRO
DRAIN
Cideng – Thamrin Drain
www.jufmp.com 55 Korea Engineering Consultant Corporation (KECC)
Progress Ministry of Pablic Works and Housing World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
1. General Items a) Preparing works b) Environment test c) Environment monitoring and management
2. Dredging Work Total volume = 49,224 m3, progress = 3,598 m3 or 7.3% - STA CT-30 – CT-31, volume = 429 m3 - STA CT-4 – CT-7 , volume = 3,169 m3
3. Concrete Work, total = 898.8 m3 = 2,157.12 m a) Concrete Capping beam, total = 1,680 m3 = 700 m
- STA C-14 – C-18+27 = 94.17 m3 = 226 m, left and right - STA C-19 – C-25 = 122.08 m3 = 293 m, left and right - STA C-25+31 – C-26+15 = 20.00 m3 = 48 m, left and right - STA C-26+25 – C-27+25 = 22.08 m3 = 53 m, left and right - STA C-27+35 – C-32+22 = 43.33 m3 = 104 m, right - STA C-27+35 – C-32+22 = 48.33 m3 = 116 m, left
www.jufmp.com 56 Korea Engineering Consultant Corporation (KECC)
Progress Ministry of Pablic Works and Housing World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
4. Pilling Works
a) Furnishing of corrugated pre-stressed concrete pile i. Furnishing CCSP W-325 L = 14 m, total = 602 units ii. Furnishing CCSP W-350 L = 16 m, total = 1,524 units
b) Driving of CCSP W-325 L = 14 m, total = 602 units - STA C-14 – C-20, left = 301 units, right= 301 units
c) Driving of CCSP W-350 L = 16 m, total = 1,524 units - STA C-20 – C-28, left = 318 units, right = 319 units - STA C-30 – C-28, left = 136 units, right = 136 units - STA CT-1 – CT-2, left = 71 units, right = 70 units - STA CT-3 – CT-7, left = 233 units, right = 241 units
www.jufmp.com 57 Korea Engineering Consultant Corporation (KECC)
Progress Ministry of Pablic Works and Housing World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
4. Pilling Works
d) Driving of 6” Pipe 10 m under Bridges
Total target = 18,960 m = 1,896 pipes = 474 m Progress = 5,900 m = 590 pipes = 147 m - STA C-25+8 – C-25+21 Left = 50, Right = 52 pipes = 25.50 m - STA C-13+38 – C-14 Left = 16,Right = 36 pipes = 13.00 m - STA C-26+21 – C-26+26 Left = 16, Right =14 pipes = 7.50 m - STA C-27+28 – C-27+34 Left = 20, Right = 20 pipes = 10.00 m - STA C-28+10 – C-28+20 Left = 29, Right = 0 pipes = 7.25 m - STA C-30+41 – C-31+31 Left = 96, Right = 63 pipes = 39.75 m - STA C-32+28 – C-32+33 Left = 10, Right = 7 pipes = 4.25 m - STA CT-1 – CT-3 Left = 42, Right = 42 pipes = 21.00 m
Package 3. Cideng Thamrin
Figure 3.1. Schedule and Progress of Construction Work (%) Dec 2013-- Mar 2015
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 58 Korea Engineering Consultant Corporation (KECC)
5 5 3 6 10
13 16
20
25
33
41
47
62 62
71
82
0 0
5
11 15
21
26
34
41
48
63 62 64 64
72
79
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
Schedule Progress
Package 3. Cideng Thamrin Drain
Figure 3.2. Financial Progress (billion IDR)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 59 Korea Engineering Consultant Corporation (KECC)
19.8
29%
34.2
50%
14.5
21%
Disbursed Undisbursed Remaining
Contract Amount = 68.5
www.jufmp.com 60 Korea Engineering Consultant Corporation (KECC)
Ministry of Pablic Works and Housing World Bank
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
PACKAGE 5 TANJUNGAN DRAIN AND LOWER ANGKE DRAIN
PT. SAC Nusantara and PT. Penata Karya Utama (JO)
General Information
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 61 Korea Engineering Consultant Corporation (KECC)
P I U : Directorate of Environmental Sanitation Development, DGHS, MoPW
Contractor : PT. SAC Nusantara and PT. Penata Karya Keluarga Utama (JO)
No Objection Letter : -
Letter of Acceptance : No.KU.03.01/JUFMP/02/VIII/2014
Contract No. : HK.02.03/JUFMP-FSK/IX/2
Contract Amount : IDR 139,700,045,000 (incl. Tax)
Signed Date : Sep 3, 2014
Notice to Proceed : -
Completion Day : 730 Calendar days
Elapsed Days : 209 days (28.7%)
Location and Scope of Works
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 62 Korea Engineering Consultant Corporation (KECC)
LENGTH OF DREDGING
600 m SHEET PILE 1,092 m
Dredging : 11,210 m3
Embankment Repair: 1,092 m
TANJUNGAN DRAIN
Location and Scope of Works
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 63 Korea Engineering Consultant Corporation (KECC)
SHEET PILE 248 m
LENGTH OF DREDGING
4,050 m
RETAINING WALL 573 m
Dredging : 241,800 m3
Embankment Repair : 821 m
LOWER ANGKE
DRAIN
Location and Scope of Works
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 64 Korea Engineering Consultant Corporation (KECC)
I. General Items 1. Preparing works 2. Environmental test 3. Environment monitoring 4. Socialization of works at Kelurahan Pejagalan, Kecamatan
Penjaringan dan Kelurahan Kedaung Kali Angke, Kecamatan Cengkareng.
II. Tanjungan Drain
1. Pilling Works a) Furnishing of corrugate pre-stressed pile (CCSP)
i. CCSP W-500 L 16 m, total = 400 units ii. CCSP W-500 L 14 m, total = 600 units iii. Concrete square pile 0.3x0.3 m, L 10 m, total = 50 units
Location and Scope of Works
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 65 Korea Engineering Consultant Corporation (KECC)
b) Driving of CCSP W-500 L 14, total = 559 units - STA TJ.38 – STA TJ.36 at right = 98 units, at left = 91 units - STA TJ.35 – STA TJ.34 at right = 48 units, at left = 49 units - STA TJ.33 – STA TJ.32 at right = 47 units, at left = 49 units - STA TJ.30 – STA TJ.28 at right = 91 units at left = 86 units
c) Driving CCSP W-500 L 16, total = 376 units - STA TJ.36 – STA TJ.35 at right = 47 units, at left = 48 units - STA TJ.34 – STA TJ.33 at right = 47 units, at left = 48 units - STA TJ.32 – STA TJ.30 at right = 93 units, at left = 93 units
2. Concrete Works a) Concrete type A (K-225)
- Capping beam at STA Tj.37 - STA TJ.36 at left = 43.2 m3
2. Miscellaneous Work a) Rehabilitation of access bridge to Tanjungan Pump Station.
Package 3. Tanjungan Drain and Lower Angke Drain
Figure 5.1. Schedule and Progress of Construction Work (%) Oct 2014-- Mar 2015
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 66 Korea Engineering Consultant Corporation (KECC)
0.63
2.32
3.47
5.54
9.27
13.00
0.39
3.11
8.97
10.14
13.01
13.58
0
5
10
15
Oct 14 Nov 14 Dec 14 Jan 15 Feb 15 Mar 15
Schedule Progress
Package 5. Tanjungan Drain and Lower Angke Drain
Figure 5.2. Financial Progress (billion IDR)
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 67 Korea Engineering Consultant Corporation (KECC)
22.2
16%
10.7
8%
106.8
76%
Disbursed Undisbursed Remaining
Contract Value = 139.7
Photo Gallery
Package 1. Ciliwung–Gn. Sahari Drain and Waduk Melati
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 68 Korea Engineering Consultant Corporation (KECC)
Dredging under bridge using suction pump at STA 1+700
Concrete work at STA 2+700
Photo Gallery
Package 2A. Cengkareng Floodway
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 69 Korea Engineering Consultant Corporation (KECC)
STA 1+500( Trimaran): CCSP driving at the high voltage cable location (sutet).
STA 1+200( Trimaran): Temporary mud disposal for the drying
Photo Gallery
Package 2A. Cengkareng Floodway
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 70 Korea Engineering Consultant Corporation (KECC)
STA 2+400(Tol Sediyatmo): CCSP driving is doing near the tol bridge
STA 4+000 (Kp. Ambon): Concreting work for the canal steel (walling )
Photo Gallery
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 71 Korea Engineering Consultant Corporation (KECC)
Package 2B. Lower Sunter Floodway
Photo Gallery
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 72 Korea Engineering Consultant Corporation (KECC)
Package 3. Cideng – Thanrin Drain
Photo Gallery
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 73 Korea Engineering Consultant Corporation (KECC)
Package 5. Tanjungan Drain and Lower Angke Drain
Rehabilitation of acces bridge to Tanjungan Pump Station
Concrete Works at Tanjungan Drain
Photo Gallery
Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing World Bank
www.jufmp.com 74 Korea Engineering Consultant Corporation (KECC)
Package 5. Tanjungan Drain and Lower Angke Drain
Dredging work at Tanjungan drain Socialization