l8 - project management - (part 2) (1)

Upload: paco-porras

Post on 25-Feb-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    1/31

    Operations Management

    (MT201)Dr. Marty Reilly

    [email protected]

    Office hours Room !11"

    #ednesday 11am $ 12

    Thursday 11am $ 12

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    2/31

    TopicsPlanning & Control:

    Project Management (part 2)

    %ntroduction

    &tages in 'ro ect Management

    #or *rea do+n &tructuresProject Scheduling*

    PERT & CPM

    Project Crashing

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    3/31

    ,antt -hartsThe ,antt chart pro ides an o er ie+ for the 'ro ect Manager to allo+ them tomonitor pro ect progress against planned progress and so pro ides a alua/leinformation source for pro ect control.

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    4/31

    et+or techni ues

    De eloped in 1 304s-'M /y Du'ont for chemical plants (1 35)

    '6RT /y *oo78 9llen : ;amilton +ith the

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    5/31

    &i> &teps '6RT : -'M

    1. Define the pro ect and prepare the +or /rea do+n structure

    2. De elop relationships among the acti ities $ decide +hich acti itiesmust precede and +hich must follo+ others

    ?. Dra+ the net+or connecting all of the acti ities

    ". 9ssign time and or cost estimates to each acti ity

    3. -ompute the longest time path through the net+or A this is called the

    critical pathB.

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    6/31

    1. #hen +ill the entire pro ect /e completedC

    2. #hat are the critical acti ities or tas s in the pro ectC?. #hich are the noncritical acti itiesC". #hat is the pro/a/ility the pro ect +ill /e completed /y a specific

    dateC3. %s the pro ect on schedule8 /ehind schedule8 or ahead of scheduleC

    B. %s the money spent e ual to8 less than8 or greater than the /udgetC5. 9re there enough resources a aila/le to finish the pro ect on timeC=. %f the pro ect must /e finished in a shorter time8 +hat is the +ay to

    accomplish this at least costC

    !uestions '6RT : -'M can 9ns+er

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    7/31

    9O (9cti ity on ode) 6>ample

    Activity Description ImmePredece A Build internal components

    B Modify roof and floor

    C Construct collection stack A

    D Pour concrete and install frame A, B

    E Build high temperature !urner C

    " Install pollution control system C

    # Install air pollution device D, E

    $ Inspect and test ", #

    Paper Manufacturing Plant DevelopmentActivities and Predecessors

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    8/31

    'erform a -ritical 'ath 9nalysisDetermines project duration

    The critical path is the longest path through the net+or

    The critical path is the shortest time in +hich thepro ect can /e completed

    9ny delay in critical path acti ities delays the pro ect

    -ritical path acti ities ha e no slac time

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    9/31

    'erform a -ritical 'ath 9nalysis6>ample of a ne+ 'aper 'lant

    9cti ity Description Time (+ee s)9 *uild internal components 2* Modify roof and floor ?- -onstruct collection stac 2D 'our concrete and install frame "6 *uild high$temperature /urner "

    %nstall pollution control system ?, %nstall air pollution de ice 3; %nspect and test 2

    Total Time (+ee s) 23

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    10/31

    Determining the 'ro ect &chedule -ritical 'ath 9nalysis

    Earliest start (ES) E earliest time at +hich an acti itcan start8 assuming all predecessors ha/een completed

    Earliest finish (EF) E earliest time at +hich anacti ity can /e finished

    Latest start (LS) E latest time at +hich an acti itycan start so as to not delay the completion time of theentire pro ect

    Latest finish (LF) Elatest time /y +hich an acti ityhas to /e finished so as to not delay the completiontime of the entire pro ect

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    11/31

    'erforming a -ritical 'ath 9nalysis eedto use a legend

    9

    9cti ity ame or &ym/ol

    6arliest &tart6&

    6arliest in6

    Fatest &tart F& Fatest iniF

    9cti ity Duration

    2

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    12/31

    or+ard 'ass

    *egin at starting e ent and +or for+ardG

    Earliest Start Time ule:%f an acti ity has only a single immediate predecessor8 its 6&e uals the 6 of the predecessor

    %f an acti ity has multiple immediate predecessors8 its 6& is thema>imum of all the 6 alues of its predecessors

    Earliest Finish Time ule:The earliest finish time (6 ) of an acti ity is the sum of itsearliest start time (6&) and its acti ity time

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    13/31

    6& 6 et+or for 'aper 'lant

    &tart

    0

    0

    6&

    0

    6 E 6& H 9cti ity time

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    14/31

    &tart0

    0

    0

    9

    2

    2

    6 of 9 E6& of 9 H

    0

    6&of 9

    6& 6 et+or for 'aper 'lant

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    15/31

    -

    2

    2 "

    *

    ?

    0 ?

    &tart0

    0

    0

    9

    2

    20

    6& 6 et+or for 'aper 'lant

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    16/31

    -

    2

    2 "

    *

    ?

    0 ?

    &tart0

    0

    0

    9

    2

    20

    D

    "

    ?E Ma> (28 ?)

    6& 6 et+or for 'aper 'lant

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    17/31

    D

    "

    ? 5

    -

    2

    2 "

    *

    ?

    0 ?

    &tart0

    0

    0

    9

    2

    20

    6& 6 et+or for 'aper 'lant

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    18/31

    6

    "

    ?

    ,

    3

    " =

    "

    = 1?

    5

    D

    "

    ? 5

    -

    2

    2 "

    *

    ?

    0 ?

    &tart0

    0

    0

    9

    2

    20

    6& 6 et+or for 'aper 'lant

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    19/31

    Latest Finish Time ule:%f an acti ity is an immediate predecessor for ust a singleacti ity8 its F e uals the F& of the acti ity that immediatelyfollo+s it%f an acti ity is an immediate predecessor to more than one

    acti ity8 its F is the minimum of all F& alues of all acti itiesthat immediately follo+ it

    *ac +ard 'ass (we need this to determine slac times later)

    !egin with the last e"ent and wor #ac wards

    Latest Start Time ule:

    The latest start time (F&) of an acti ity is the difference of its latestfinish time (F ) and its acti ity time eg8 (F& E F A 9cti ity time)

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    20/31

    6

    "

    ?

    ,

    3

    " =

    "

    = 1?

    5

    D

    "

    ? 5

    -

    2

    2 "

    *

    ?

    0 ?

    &tart0

    0

    0

    9

    2

    20

    o

    F& E F A 9cti ity time

    F& F Times for 'aper 'lant

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    21/31

    6

    "

    ?

    ,

    3

    " =

    "

    = 1?

    5

    D

    "

    ? 5

    -

    2

    2 "

    *

    ?

    0 ?

    &tart0

    0

    0

    9

    2

    20

    F E Min(F& of follo+ing acti ity)

    10 1?

    F& F Times for 'aper 'lant

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    22/31

    6

    "

    ?

    ,

    3

    " =

    "

    = 1?

    5

    10 1?

    = 1?

    " =

    D

    "

    ? 5

    -

    2

    2 "

    *

    ?

    0 ?

    &tart0

    0

    0

    9

    2

    20

    F E Min("8 10)

    "2

    F& F Times for 'aper 'lant

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    23/31

    6

    "

    ?

    ,

    3

    " =

    "

    = 1?

    5

    10 1?

    = 1?

    " =

    D

    "

    ? 5

    -

    2

    2 "

    *

    ?

    0 ?

    &tart0

    0

    0

    9

    2

    20

    "2

    ="

    20

    "1

    00

    F& F Times for 'aper 'lant

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    24/31

    9fter computing the 6&8 6 8 F&8 and F times for all acti ities8

    compute the slac or free time for each acti ity

    &lac is the length of time an acti ity can /e delayed +ithoutdelaying the entire pro ect

    &lac E F& A 6& or &lac E F A 6

    -omputing &lac Time

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    25/31

    6arliest 6arliest Fatest Fatest On

    &tart inish &tart inish &lac -ritical9cti ity 6& 6 F& F F& A 6& 'ath

    9 0 2 0 2 0 Ies* 0 ? 1 " 1 o- 2 " 2 " 0 IesD ? 5 " = 1 o6 " = " = 0 Ies

    " 5 10 1? B o, = 1? = 1? 0 Ies; 1? 13 1? 13 0 Ies

    -omputing &lac Time

    Critical path is: !"C"E"#"$

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    26/31

    6

    "

    ?

    ,

    3

    " =

    "

    = 1?

    5

    10 1?

    = 1?

    " =

    D

    "

    ? 5

    -

    2

    2 "

    *

    ?

    0 ?

    &tart0

    0

    0

    9

    2

    20

    "2

    ="

    20

    "1

    00

    -ritical 'ath for 'aper 'lant

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    27/31

    1. 6specially useful +hen scheduling and controlling large pro ects

    2. &traightfor+ard concept and not mathematically comple>?. ,raphical net+or s help highlight relationships among pro ect

    acti ities

    ". -ritical path and slac time analyses help pinpoint acti ities thatneed to /e closely +atched

    3. 'ro ect documentation and graphics can point out +ho is responsi/lefor arious acti ities

    B. 9pplica/le to a +ide ariety of pro ects

    5.

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    28/31

    ;o+ does '6RT : -'M differC

    '6RT is ery similar to -ritical 'ath Method (-'M) /ut also uses

    three time estimates for each acti ity

    %ptimistic Time shortest duration li ely

    'ost Li el Time a erage e>pectation

    Pessimistic Time the most conser ati e estimate8 ta inginto account the li elihood of set/ac s etc

    2=

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    29/31

    1. 'ro ect acti ities ha e to /e clearly defined8 independent8 and sta/lein their relationshipsG not alwa$s a realit$

    2. 'recedence relationships must /e specified and net+or ed together

    ?. Time estimates tend to /e su/ ecti e and are su/ ect to Jfudging4 /ymanagersG were estimates su#jecti"e % too optimistic

    ". There is an inherent danger of too much emphasis /eing placed onthe longest8 or critical8 pathG. *near+ critical paths should also ,emonitored closel -

    Fimitations Disad antages of '6RT -'M

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    30/31

    The pro ect is /ehind scheduleThe completion time has /een mo ed for+ard

    'a incur penalties if the project runs o.er late-/

    %t is not uncommon to face the follo+ingsituations

    &hortening the duration of the pro ect is called project crashing

    Trade$Offs 9nd 'ro ect -rashing

    For e0ample1 if 2e need an acti.it done 3uic er can 2eemplo e0tra staff1 or pa e0isting staff o.ertime in order toachie.e this4

    d h h

  • 7/25/2019 L8 - Project Management - (Part 2) (1)

    31/31

    The amount /y +hich an acti ity is to /e crashed is8 in fact8 permissi/le

    Ta en together8 +ill the shortened acti ity durations ena/le us to finishthe pro ect /y the due dateC

    Or ha e +e ust increased our spending +ithout achie ing completion/y the due dateC

    eed to ensure that the total cost of crashing is as small as possi/le

    actors to -onsider #hen -rashing 9 'ro ect