l8 - project management - (part 2) (1)
TRANSCRIPT
-
7/25/2019 L8 - Project Management - (Part 2) (1)
1/31
Operations Management
(MT201)Dr. Marty Reilly
Office hours Room !11"
#ednesday 11am $ 12
Thursday 11am $ 12
-
7/25/2019 L8 - Project Management - (Part 2) (1)
2/31
TopicsPlanning & Control:
Project Management (part 2)
%ntroduction
&tages in 'ro ect Management
#or *rea do+n &tructuresProject Scheduling*
PERT & CPM
Project Crashing
-
7/25/2019 L8 - Project Management - (Part 2) (1)
3/31
,antt -hartsThe ,antt chart pro ides an o er ie+ for the 'ro ect Manager to allo+ them tomonitor pro ect progress against planned progress and so pro ides a alua/leinformation source for pro ect control.
-
7/25/2019 L8 - Project Management - (Part 2) (1)
4/31
et+or techni ues
De eloped in 1 304s-'M /y Du'ont for chemical plants (1 35)
'6RT /y *oo78 9llen : ;amilton +ith the
-
7/25/2019 L8 - Project Management - (Part 2) (1)
5/31
&i> &teps '6RT : -'M
1. Define the pro ect and prepare the +or /rea do+n structure
2. De elop relationships among the acti ities $ decide +hich acti itiesmust precede and +hich must follo+ others
?. Dra+ the net+or connecting all of the acti ities
". 9ssign time and or cost estimates to each acti ity
3. -ompute the longest time path through the net+or A this is called the
critical pathB.
-
7/25/2019 L8 - Project Management - (Part 2) (1)
6/31
1. #hen +ill the entire pro ect /e completedC
2. #hat are the critical acti ities or tas s in the pro ectC?. #hich are the noncritical acti itiesC". #hat is the pro/a/ility the pro ect +ill /e completed /y a specific
dateC3. %s the pro ect on schedule8 /ehind schedule8 or ahead of scheduleC
B. %s the money spent e ual to8 less than8 or greater than the /udgetC5. 9re there enough resources a aila/le to finish the pro ect on timeC=. %f the pro ect must /e finished in a shorter time8 +hat is the +ay to
accomplish this at least costC
!uestions '6RT : -'M can 9ns+er
-
7/25/2019 L8 - Project Management - (Part 2) (1)
7/31
9O (9cti ity on ode) 6>ample
Activity Description ImmePredece A Build internal components
B Modify roof and floor
C Construct collection stack A
D Pour concrete and install frame A, B
E Build high temperature !urner C
" Install pollution control system C
# Install air pollution device D, E
$ Inspect and test ", #
Paper Manufacturing Plant DevelopmentActivities and Predecessors
-
7/25/2019 L8 - Project Management - (Part 2) (1)
8/31
'erform a -ritical 'ath 9nalysisDetermines project duration
The critical path is the longest path through the net+or
The critical path is the shortest time in +hich thepro ect can /e completed
9ny delay in critical path acti ities delays the pro ect
-ritical path acti ities ha e no slac time
-
7/25/2019 L8 - Project Management - (Part 2) (1)
9/31
'erform a -ritical 'ath 9nalysis6>ample of a ne+ 'aper 'lant
9cti ity Description Time (+ee s)9 *uild internal components 2* Modify roof and floor ?- -onstruct collection stac 2D 'our concrete and install frame "6 *uild high$temperature /urner "
%nstall pollution control system ?, %nstall air pollution de ice 3; %nspect and test 2
Total Time (+ee s) 23
-
7/25/2019 L8 - Project Management - (Part 2) (1)
10/31
Determining the 'ro ect &chedule -ritical 'ath 9nalysis
Earliest start (ES) E earliest time at +hich an acti itcan start8 assuming all predecessors ha/een completed
Earliest finish (EF) E earliest time at +hich anacti ity can /e finished
Latest start (LS) E latest time at +hich an acti itycan start so as to not delay the completion time of theentire pro ect
Latest finish (LF) Elatest time /y +hich an acti ityhas to /e finished so as to not delay the completiontime of the entire pro ect
-
7/25/2019 L8 - Project Management - (Part 2) (1)
11/31
'erforming a -ritical 'ath 9nalysis eedto use a legend
9
9cti ity ame or &ym/ol
6arliest &tart6&
6arliest in6
Fatest &tart F& Fatest iniF
9cti ity Duration
2
-
7/25/2019 L8 - Project Management - (Part 2) (1)
12/31
or+ard 'ass
*egin at starting e ent and +or for+ardG
Earliest Start Time ule:%f an acti ity has only a single immediate predecessor8 its 6&e uals the 6 of the predecessor
%f an acti ity has multiple immediate predecessors8 its 6& is thema>imum of all the 6 alues of its predecessors
Earliest Finish Time ule:The earliest finish time (6 ) of an acti ity is the sum of itsearliest start time (6&) and its acti ity time
-
7/25/2019 L8 - Project Management - (Part 2) (1)
13/31
6& 6 et+or for 'aper 'lant
&tart
0
0
6&
0
6 E 6& H 9cti ity time
-
7/25/2019 L8 - Project Management - (Part 2) (1)
14/31
&tart0
0
0
9
2
2
6 of 9 E6& of 9 H
0
6&of 9
6& 6 et+or for 'aper 'lant
-
7/25/2019 L8 - Project Management - (Part 2) (1)
15/31
-
2
2 "
*
?
0 ?
&tart0
0
0
9
2
20
6& 6 et+or for 'aper 'lant
-
7/25/2019 L8 - Project Management - (Part 2) (1)
16/31
-
2
2 "
*
?
0 ?
&tart0
0
0
9
2
20
D
"
?E Ma> (28 ?)
6& 6 et+or for 'aper 'lant
-
7/25/2019 L8 - Project Management - (Part 2) (1)
17/31
D
"
? 5
-
2
2 "
*
?
0 ?
&tart0
0
0
9
2
20
6& 6 et+or for 'aper 'lant
-
7/25/2019 L8 - Project Management - (Part 2) (1)
18/31
6
"
?
,
3
" =
"
= 1?
5
D
"
? 5
-
2
2 "
*
?
0 ?
&tart0
0
0
9
2
20
6& 6 et+or for 'aper 'lant
-
7/25/2019 L8 - Project Management - (Part 2) (1)
19/31
Latest Finish Time ule:%f an acti ity is an immediate predecessor for ust a singleacti ity8 its F e uals the F& of the acti ity that immediatelyfollo+s it%f an acti ity is an immediate predecessor to more than one
acti ity8 its F is the minimum of all F& alues of all acti itiesthat immediately follo+ it
*ac +ard 'ass (we need this to determine slac times later)
!egin with the last e"ent and wor #ac wards
Latest Start Time ule:
The latest start time (F&) of an acti ity is the difference of its latestfinish time (F ) and its acti ity time eg8 (F& E F A 9cti ity time)
-
7/25/2019 L8 - Project Management - (Part 2) (1)
20/31
6
"
?
,
3
" =
"
= 1?
5
D
"
? 5
-
2
2 "
*
?
0 ?
&tart0
0
0
9
2
20
o
F& E F A 9cti ity time
F& F Times for 'aper 'lant
-
7/25/2019 L8 - Project Management - (Part 2) (1)
21/31
6
"
?
,
3
" =
"
= 1?
5
D
"
? 5
-
2
2 "
*
?
0 ?
&tart0
0
0
9
2
20
F E Min(F& of follo+ing acti ity)
10 1?
F& F Times for 'aper 'lant
-
7/25/2019 L8 - Project Management - (Part 2) (1)
22/31
6
"
?
,
3
" =
"
= 1?
5
10 1?
= 1?
" =
D
"
? 5
-
2
2 "
*
?
0 ?
&tart0
0
0
9
2
20
F E Min("8 10)
"2
F& F Times for 'aper 'lant
-
7/25/2019 L8 - Project Management - (Part 2) (1)
23/31
6
"
?
,
3
" =
"
= 1?
5
10 1?
= 1?
" =
D
"
? 5
-
2
2 "
*
?
0 ?
&tart0
0
0
9
2
20
"2
="
20
"1
00
F& F Times for 'aper 'lant
-
7/25/2019 L8 - Project Management - (Part 2) (1)
24/31
9fter computing the 6&8 6 8 F&8 and F times for all acti ities8
compute the slac or free time for each acti ity
&lac is the length of time an acti ity can /e delayed +ithoutdelaying the entire pro ect
&lac E F& A 6& or &lac E F A 6
-omputing &lac Time
-
7/25/2019 L8 - Project Management - (Part 2) (1)
25/31
6arliest 6arliest Fatest Fatest On
&tart inish &tart inish &lac -ritical9cti ity 6& 6 F& F F& A 6& 'ath
9 0 2 0 2 0 Ies* 0 ? 1 " 1 o- 2 " 2 " 0 IesD ? 5 " = 1 o6 " = " = 0 Ies
" 5 10 1? B o, = 1? = 1? 0 Ies; 1? 13 1? 13 0 Ies
-omputing &lac Time
Critical path is: !"C"E"#"$
-
7/25/2019 L8 - Project Management - (Part 2) (1)
26/31
6
"
?
,
3
" =
"
= 1?
5
10 1?
= 1?
" =
D
"
? 5
-
2
2 "
*
?
0 ?
&tart0
0
0
9
2
20
"2
="
20
"1
00
-ritical 'ath for 'aper 'lant
-
7/25/2019 L8 - Project Management - (Part 2) (1)
27/31
1. 6specially useful +hen scheduling and controlling large pro ects
2. &traightfor+ard concept and not mathematically comple>?. ,raphical net+or s help highlight relationships among pro ect
acti ities
". -ritical path and slac time analyses help pinpoint acti ities thatneed to /e closely +atched
3. 'ro ect documentation and graphics can point out +ho is responsi/lefor arious acti ities
B. 9pplica/le to a +ide ariety of pro ects
5.
-
7/25/2019 L8 - Project Management - (Part 2) (1)
28/31
;o+ does '6RT : -'M differC
'6RT is ery similar to -ritical 'ath Method (-'M) /ut also uses
three time estimates for each acti ity
%ptimistic Time shortest duration li ely
'ost Li el Time a erage e>pectation
Pessimistic Time the most conser ati e estimate8 ta inginto account the li elihood of set/ac s etc
2=
-
7/25/2019 L8 - Project Management - (Part 2) (1)
29/31
1. 'ro ect acti ities ha e to /e clearly defined8 independent8 and sta/lein their relationshipsG not alwa$s a realit$
2. 'recedence relationships must /e specified and net+or ed together
?. Time estimates tend to /e su/ ecti e and are su/ ect to Jfudging4 /ymanagersG were estimates su#jecti"e % too optimistic
". There is an inherent danger of too much emphasis /eing placed onthe longest8 or critical8 pathG. *near+ critical paths should also ,emonitored closel -
Fimitations Disad antages of '6RT -'M
-
7/25/2019 L8 - Project Management - (Part 2) (1)
30/31
The pro ect is /ehind scheduleThe completion time has /een mo ed for+ard
'a incur penalties if the project runs o.er late-/
%t is not uncommon to face the follo+ingsituations
&hortening the duration of the pro ect is called project crashing
Trade$Offs 9nd 'ro ect -rashing
For e0ample1 if 2e need an acti.it done 3uic er can 2eemplo e0tra staff1 or pa e0isting staff o.ertime in order toachie.e this4
d h h
-
7/25/2019 L8 - Project Management - (Part 2) (1)
31/31
The amount /y +hich an acti ity is to /e crashed is8 in fact8 permissi/le
Ta en together8 +ill the shortened acti ity durations ena/le us to finishthe pro ect /y the due dateC
Or ha e +e ust increased our spending +ithout achie ing completion/y the due dateC
eed to ensure that the total cost of crashing is as small as possi/le
actors to -onsider #hen -rashing 9 'ro ect