kaizen case studies competition [ducab pvt. ltd ... · 1 kaizen case studies competition [ducab...
TRANSCRIPT
1
KAIZEN CASE STUDIES COMPETITION
[DUCAB Pvt. Ltd.]
[Manufacturing & Technical department]
[Reduction in Changeover Time in CCV Line ]
Team Members: Wineyya Abdullah
Shaik Iddu
Bahaa Mourad
Francis D'Silva
2
“Before” Situation Plan
Do Check
Action
A key growth strategy is to increase the annual
sales.
A key factor to achieve that goal is the ability to
increase the current capacity of MV plant.
CCV line is the bottleneck for MV plant and
constrains downstream processing.
The major non added value activity on the CCV line
is the changeover.
The changeover time must be reduced to optimize
the productivity.
By applying best practices and better utilization of
manpower and tools, we were able to improve the
overall productivity.
17-Oct-2013 World Quality Day 2013
3
“Problem” Statement Plan
Do Check
Action
In 2012, the number of major changeovers on CCV
line was 367.
This represents 44% of the total available time on
CCV line.
A 55% of reduction in changeover time would result
in 5,440Ton increase in annual productivity and
AED 27.2 million increase in added value.
Currently, the average changeover activity
required11.5 hours.
There was no standard changeover process followed
by the operators.
17-Oct-2013 World Quality Day 2013
4
“Problem” Statement
17-Oct-2013 World Quality Day 2013
Period No. of Changeover Average Changeover Time
Jan-Dec'12 367 11.5 hr
11
11.1
11.2
11.3
11.4
11.5
11.6
Average Change Over Time (2012)
Average Change Over Time PerHours
5
Root Cause Analysis
Plan
Do Check
Action
Following tools/activities were applied to identify the root cause:
• Value Stream Mapping (VSM). • Kaizen (Spiky clouds). • Videography. • In-depth analysis of changeover activity.
Root Cause:
CCV Chang- over
non ergonomic
place
End- curing Time
Work procedure
Conventional Tools
6
Improvement Plan Improved Method Previous Method
Comments Duration
External Duration Internal Improving Idea Actual
Duration
Internal Element
Description
Seq #
1.PM and 5S need
to be performed
regularly.
90
minutes
X
Increase frequency of PM for
by product separator.
180 minutes X End Curing 1
1.Reduce
unnecessary
motion.
2. remove cleaning
of flow pieces from
seq.#2 and combine
with seq.#3.
60 minutes
X
75
minutes
X
1.Locate Extruder Tools and
ethanol tank near work area.
2. Investigate a second set of
flow pieces.
90 minutes X
Disconnecting
extruders from
cross-head &
cleaning flow
pieces
2
1.Reduce wasted
2.reduce motion. 60
minutes
X
1.Design, fabricate Clamping
fixture to hold flow distributor
2.Extraction tool to remove tip
90 minutes X
Remove cross
head and clean 3
1.Replace the
conventional tools
30
minutes
X
Provide pneumatic tools to
tighten nuts.
40 minutes X
Assembling the
cross head
4
1.Can be performed
in parallel with
additional help
30 minutes
X
Perform in parallel with
seq.#3 and 4.
140 minutes X
Rewinding lead
cable and fixing
end seal
5
1.Replace the
conventional tool
140 minutes
X
Provide pneumatic tools to
tighten nuts
150 minutes X
Fixing cross head
and pre-heat 6
320
minutes
165
minutes
690
minutes
TOTAL
MINUTES:
7
After Situation Plan
Do Check
Action
Period No. of Changeover
Average Changeover
Time
May-Oct'13 130 6.2 hr
11
11.1
11.2
11.3
11.4
11.5
11.6
Average Change Over Time (2012)
Average Change OverTime Per Hours
Before Kaizen After Kaizen
8
Benefits Plan
Do Check
Action
Year 2012 Year 2013
Average Cu Tonnage in
(May-Oct'12)
890 Ton Average Cu Tonnage in
(May-Oct'13)
1079 Ton
Average changeover 11.5hrs
Average change over time
6.2hrs
Total time taken in Changeover
11.5x367 = 4221hrs
Total time taken in
Change over
6.2x367 =
2275hrs
• (4221-2275)=1945hrs Saved changeover time
• 1751km Extra produced core km in saved time
• 4656.57Tons Extra produced Cu tonnage in saved time
• AED 23.28 Million Added Value AED/annum
9
Standardization Plan
Do Check
Action
• 5S checklist.
• Documented in 5s instructions. 5S
• TPM schedule was introduced.
• Parallel to changeover.
• TPM checksheet for by- product separator area.
TPM
• Standardized Work Combination
Table.
• Visual workplace.
• Documented in Process spec.
Changeover
10
Standardization (Before Kaizen)
Hot gas in
By Products
condense
here (60c) Release Valve
opens every 10
min to clear by
product.
Cool gas out
Control valve.
Opens to
adjust flow
rate through
separator.
144c
41c
100% open
Cooling zone
chilled water coil.
11
Standardization (After Kaizen)
Hot gas in
By Products
condense
here (60c) Release Valve
opens every 10
min to clear by
product.
Cool gas out
Control valve.
Opens to
adjust flow
rate through
separator.
144c
41c
100% open 250c
60c
50% open
Cooling zone
chilled water coil.
12
Horizontal Deployment Plan
Do Check
Action
Reduction in changeover time in CCV
All Ducab Plants
- Can be implemented in similar process
(extruders).
- Improvement Plan
is being prepared
for improvement
opportunities.
- Similar Lean tools/
standardized
procedures can be
applied.
13
Single Point Lesson Plan
Do Check
Action
Pushing the control down to the
operator involvement.
14
Q&A