kagra roadmap and progress evaluation assessment s.miyoki m.ando 2012/7/30

26
KAGRA Roadmap KAGRA Roadmap and and Progress Evaluation Progress Evaluation Assessment Assessment S.Miyoki S.Miyoki M.Ando M.Ando 2012/7/30 2012/7/30

Upload: alisa

Post on 21-Mar-2016

58 views

Category:

Documents


0 download

DESCRIPTION

KAGRA Roadmap and Progress Evaluation Assessment S.Miyoki  M.Ando 2012/7/30. Outline. Introduction Updated KAGRA Roadmap KAGRA Progress Chart (KPC) as milestones according to bottom up plans KAGRA Progress Chart Evaluation Summary. Update Roadmap - Ando’s Ext.Rev Presentation-. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

KAGRA RoadmapKAGRA Roadmapand and

Progress Evaluation Progress Evaluation AssessmentAssessmentS.Miyoki S.Miyoki M.AndoM.Ando

2012/7/302012/7/30

Page 2: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

Outline

• Introduction• Updated KAGRA Roadmap• KAGRA Progress Chart (KPC) as

milestones according to bottom up plans

• KAGRA Progress Chart Evaluation

• Summary

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

Page 3: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

Update Roadmap- Ando’s Ext.Rev Presentation-

We Updated the KAGRA Roadmap. • Mainly because of delay in the excavation

schedule. • It is regarded as a good chance to refine the

schedule. • Recent some budget status might require minor

changes.Roadmap special working group was held

chaired by M.Ando • We made iteration between the project constraints

and the bottom-up plans submitted from subgroups.

• Open discussions in the collaboration were done -> Finally, this recommendation was approved by EO.

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

Page 4: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

KAGRA Roadmap (ic1)

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

2013 2014 2015 2016 2017 2018Tunnel Excavation(14/3)

FPMI (15/12)

Vacuum(15/3)

DRMI (16/9)

Type-A Cryo(16/9)

RSE(17/8)

Cryo-RSE(18/3)

TuningAndObservation

Sapphire Test mass preparation(16/3)

b-KAGRA

i-KAGRA• Training for km-scale IFO.

• Sorting out the problems involved in KAGRA

• Short observation will be done

• Introduce Full Type-A SAS, Cryogenic and RSE Technique.

• Realize the targeted sensitivity and observation.

12

12

12

12

12

12

ic1 phase

Page 5: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

Tunnel Excavation and FAL Construction

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

Tunnel Excavation Power line, water line, air

humidity conditioner, network installation

Clean room construction

North Direction

Mozumi Tunnel

GW Atotsu Tunnel

From 12/5

From 12/6

till 14/3

GW Office(2012/08)

30 degY arm

X arm

Page 6: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

KAGRA Roadmap (ic2)

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

2013 2014 2015 2016 2017 2018Tunnel Excavation(2014/3)

FPMI (2015/12)

Vacuum(2015/3)

DRMI (2016/9)

Type-A Cryo(2016/9)

RSE(2017/8)

Cryo-RSE(2018/3)

TuningAndObservation

Sapphire Test mass preparation(16/3)

b-KAGRA

i-KAGRA

12

12

12

12

12

12

ic2 phase

Page 7: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

Vacuum and Laser Stuff Installation 1

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

• Both Arm and IY*, EY* installation

• Laser, MC*, IFI, IMM installation

No ConnectionParallel task

Type-C

Type-AType-B

Mozumi Tunnel

GW Atotsu Tunnel

EYC,EYV, EYT

EXC,EXV, EXT

IXC,IXV, IXT

IYC,IYV

MCE

EYA

IYA

IXA

VIS Types

MCFIFI, IMM

Laser EXA

GW Office

Page 8: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

Vacuum and Laser Stuff Installation 2

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

Mozumi Tunnel

GW Atotsu Tunnel

MCE

MCF

PRM MR2

MR3IFI, IMM

Type-C

Type-AType-B

VIS Types

EYC,EYV, EYT

EXC,EXV, EXT

IXC,IXV, IXT

IYC,IYV

EYA

IYA

IXA EXA

• Center part construction without SR* and OMC, OFI

• Type-A SAS test at Y End at room tmp

• Cryogenic test at X End

Laser

GW Office

Page 9: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

KAGRA Roadmap (ic3)

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

2013 2014 2015 2016 2017 2018Tunnel Excavation(14/3)

FPMI (15/12)

Vacuum(15/3)

DRMI (16/9)

Type-A Cryo(16/9)

RSE(17/8)

Cryo-RSE(18/3)

TuningAndObservation

Sapphire Test mass preparation(16/3)

b-KAGRA

i-KAGRA

12

12

12

12

12

12

ic3 phase

Page 10: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

iKAGRA CommissioningMozumi Tunnel

GW Atotsu Tunnel

MCE

MCF

PRM MR2

MR3

Type-C

Type-AType-B

VIS Types

EYC,EYV, EYT

EXC,EXV, EXT

IXC,IXV, IXT

IYC,IYV

EYA

IYA

IXA EXA

IFI, IMM• Low Laser Power (15W ?)

• FPMI operation using Silica Mirrors in IXA, IYA, EYA, EXA.

• Short Commissioning ~ 1 month(15/12)

Laser

GW Office

Page 11: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

KAGRA Roadmap (bc1)

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

2013 2014 2015 2016 2017 2018Tunnel

Excavation

FPMI (15/12)

Vacuum(15/3)

DRMI (16/9)

Type-A Cryo(16/9)

RSE(17/8) Cryo-

RSE(18/3)

TuningAnd

Observation

Sapphire Test mass preparation(16/3)

b-KAGRA

i-KAGRA

12

12

12

12

12

12

bc1 phase

Page 12: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

bKAGRA Commissioning 1

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

Mozumi Tunnel

GW Atotsu Tunnel

MCE

MCF

PRM MR2

MR3

Type-C

Type-AType-B

VIS Types

EYC,EYV, EYT

EXC,EXV, EXT

IXC,IXV, IXT

IYC,IYV

EYA

IYA

IXA EXA

IFI, IMM

• SR*, OMC, OFI are prepared.• VIS upgrade to Type-B for

core optics• DRMI Operation using Silica

Mirrors• Full test of VIS Type-A +

Cryo-Mirror

SRM

SR3

OFIOMC

SR2

Laser

GW Office

Page 13: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

KAGRA Roadmap (bc2)

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

2013 2014 2015 2016 2017 2018Tunnel

Excavation

FPMI (15/12)

Vacuum(15/3)

DRMI (16/9)

Type-A Cryo(16/9)

RSE(17/8) Cryo-

RSE(18/3)

TuningAnd

Observation

Sapphire Test mass preparation(16/3)

b-KAGRA

i-KAGRA

12

12

12

12

12

12

bc2 phase

Page 14: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

bKAGRA Commissioning 2

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

Mozumi Tunnel

GW Atotsu Tunnel

MCE

MCF

PRM MR2

MR3

Type-C

Type-AType-B

VIS Types

EYC,EYV, EYT

EXC,EXV, EXT

IXC,IXV, IXT

IYC,IYV

EYA

IYA

IXA EXA

IFI, IMM

• Sapphire mirrors suspended Type-A.

• RSE Operation (Sapphire mirrors at room temp.)

SRM

SR3

OFIOMC

SR2

Laser

GW Office

Page 15: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

KAGRA Roadmap (bc3,4)

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

2013 2014 2015 2016 2017 2018Tunnel

Excavation

FPMI (15/12)

Vacuum(15/3)

DRMI (16/9)

Type-A Cryo(16/9)

RSE(17/8) Cryo-

RSE(18/3)

TuningAnd

Observation

Sapphire Test mass preparation(16/3)

b-KAGRA

i-KAGRA

12

12

12

12

12

12

bc3,4 phase

Page 16: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

bKAGRA Commissioning 3

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

Mozumi Tunnel

GW Atotsu Tunnel

MCE

MCF

PRM MR2

MR3

Type-C

Type-AType-B

VIS Types

EYC,EYV, EYT

EXC,EXV, EXT

IXC,IXV, IXT

IYC,IYV

EYA

IYA

IXA EXA

IFI, IMM

• RSE Operation (at Cryo Temp.)

• IFO Tuning • Observation

SRM

SR3

OFIOMC

SR2

Laser

GW Office

Page 17: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

In the Last PAB Report … ‘We believe the project needs a more systematic

technique for monitoring of status and plans, in effect, some version of a performance measurement system. … We recommend that some form of baseline planning and performance assessment be added to the project.’-> A :Progress Evaluation System Introduction

‘A key element in this performance measurement system will be establishing an integrated schedule, built up from the individual subsystem schedules.’

-> A: Construct Master schedule and make detail schedule from each subgroup Bottom-up Plans.

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

Page 18: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

Bottom-up Plan and Progress Evaluation System

Schedule management system for quantitative evaluation of project progress was introduced.

Progress evaluation is done by a ‘Milestone scheme’. • Set ~10 milestones for each subsystem, picked up

from a detailed schedule of each subsystem. • Status for the milestones will be checked in regular

“Chief” meetings.• Required progress evaluation accuracy is ~20%

resolution. • The status will be open for all the collaborators. • For this purposes, a software and network system :

MS Project and Web server were prepared.

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

Page 19: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

KAGRA Progress Chat (KPC)based on bottom-up Plan

• KAGRA bottom up schedules of all subgroups are collected in one MS Project file.

• The mile stones and some important construction items , their anteroposterior relation and period are listed with respect to each subgroup.

• Time schedule consistency and anteroposterior relations between subgroups items are also specified.

KAGRA External Review 2012/4/17~20 in ICRR, Kashiwa

Page 20: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

All KAGRA Progress Chart (KPC)

KAGRA External Review 2012/4/17~20 in ICRR, Kashiwa

Subgroups Schedule for each milestones

Page 21: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

Important Items and Anteroposterior relations in

Subgroups

KAGRA External Review 2012/4/17~20 in ICRR, Kashiwa

VAC milestones and some importantItems and schedule.

Detailed Progress schedule and Milestones

Page 22: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

Anteroposterior relations bw Sub-Gs

KAGRA External Review 2012/4/17~20 in ICRR, Kashiwa

VIS milestones and schedules

CRY milestones and schedules

Page 23: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

KPC progress sign for each item

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

• Black lines in the bar shows progress rate.

Page 24: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

Progress Evaluation and Action• Each subgroup chief is requested to check

the progress with this schedule for each item by himself in every chief meetings (every tweek weeks).

• If the chief encounters some problems that result in the delay of schedule, he is encouraged to consult with SEO.

• SEO should find any signs that show progress delay as soon as possible, and try to find reasons and problems with chiefs, and to show solutions. At the same time SEO should report to EO about KPC.

KAGRA External Review 2012/4/17~20 in ICRR, Kashiwa

Page 25: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

Where we can find the KPC ?

KAGRA External Review 2012/4/17~20 in ICRR, Kashiwa

• Schedule can be found in the “Chief meeting report page (pass required)” and the “Subgroup blog page (free access)” (in Japanese).

Progress schedule link

http://gwclio.icrr.u-tokyo.ac.jp/lcgtsubgroup/http://gwclio.icrr.u-tokyo.ac.jp/lcgtchief/

Page 26: KAGRA Roadmap and  Progress Evaluation Assessment S.Miyoki   M.Ando 2012/7/30

Summary• KAGRA Roadmap was refined and some

minor re-refines might be expected because of budget status in the future.

• As detailed roadmap progress, KPC (KAGRA Progress Chart) was prepared by gathering milestone items (bottom-up plans) of subgroups.

• Chiefs are requested to update their progress status in KPC, while SEO members should check them, follow and report any troubles and delays for them to EO.

F2F Meeting 2012/7/30~1 in ICRR, Kashiwa