July 9, 2007TPTF Meeting
Texas Nodal Program Update
Jerry Sullivan
2Texas Nodal Program UpdateJuly 9, 2007 2
Agenda
Item Purpose Page
Program Status For Information 3
EMS CSD Status For information 4
User Interface Development Schedule for Market-facing applications
For Information and comment 5
Appendix – More details on UI Development Schedule
For information 8
3Texas Nodal Program UpdateJuly 9, 2007 3
CostScheduleScope / Quality
Legend
Summary
The program has made significant progress on reducing the backlog of NPRRs to synchronize all projects
Amber
The program is spending under budget through May’s actuals. Discussions with the ERCOT
Executive Committee outlined possible ways to ensure we are on
budget at completion.
Amber Amber
TPTF/PRS approved Baseline 1 on June 12 and Baseline 2 on June 21.
TAC recommended baseline 1&2 NPRRs on June 28. Program scope can be declared Green subject to
Board approval of NPRRs for Baseline 1 and 2.
Red
Amber
Green Estimate at Complete = <$248m
Estimate at Complete = $248 - $263m
Estimate at Complete = >$263m
Go-live = 12/1/08
Go-live = <30 days+
Go-live = >30 days+
Program is aligned with current protocols
Program is aligned to previous version of protocols
Program is not wholly aligned to protocols
EDS1 and 2 proceeding on schedule. EDS3 approach
approved by TPTF on June 11.
There are schedule risks in Baseline 1 & 2 which we are
mitigating.
Scope/Quality
Nodal
Cost
ScheduleScope/Quality
Schedule
Cost
Nodal Delivery
Nodal Delivery
4Texas Nodal Program UpdateJuly 9, 2007 4
• Provisionally Approved EMS CSD, Ver. 0.11
• Version Excluding AREVA IP Now Posted – Ver. 0.11a
• Complete Document Available To MP Employees
– No NDA Required– Contact Stacy Bridges For Immediate Access
EMS CSD Status Update
5Texas Nodal Program UpdateJuly 9, 2007 5
TPTF have made clear their want for a plan and consultation to resolve dissatisfaction over the existing user experience offered by ERCOT…
To address user experience issues ERCOT has:
Established User Experience and Visual Design Guidelines which contain the user interface (UI) Development Process and expected results in style and design approach
Provided these to the vendors as standards for UI for the applications being developed
Created a UI design schedule for each Nodal project that will be market-facing in the go-live market
6Texas Nodal Program UpdateJuly 9, 2007 6
Q3
Nodal UI Schedule Summary
Q2 Q4
June July August September October November December
2008
Outage Scheduler
Network Model Management System
Market Information System
Congestion Revenue Rights
Market Management System
Data collection & base product evaluation
With Market Participants (MPs)
Evaluation of revised UI with MPs
Created 2nd design
Define contents of landing pages
Create initial redesign
InternalValidate with MPs
Sent to ABB From ABB
Validate with MPs
Sent to ABB
Revisions from ABB
(Jan)
Validate with MPs
(Feb)
Evaluation of revised UI with MPs
Created 2nd designFrom ABB
Validate with MPs
Sent to ABB
Revisions from ABB
(Jan)
Validate with MPs
(Feb)
Created 2nd designRevised UI for PTC expected
Validate with MPs
Sent to Siemens
Revisions from
Siemens (Jan)
Validate with MPs
(Jan)
Redesign provided to Siemens (Apr 2007)
Data collection & base product evaluation
Created initial re-design
Sent to Nexant
Received from
Nexant
Initial build received from
vendor
Navigation validation assessment w/MPs
= Ongoing activity (Design, evaluation)= one-time activity (meeting/milestone)
Prototype Evaluations
MIS Validation with MPs
Assessment of CRRsystem w/MPs
Assessment of CRRprototypes w/MPs
7Texas Nodal Program UpdateJuly 9, 2007 7
Our Long Range Plan
Make User Experience an essential element of the Change Process Iterative process Evolutionary process Goal directed
Form the User Interface Design Council Market Participant focused, extension of MIS subgroup Collaborate on designs
Provide means for getting feedback Structured
System reviewsSurveys
UnstructuredHelp Desk ticket analysis “Comment Box”
July 9, 2007TPTF Meeting
Texas Nodal Program Update
UI Development Schedule – Appendix showing each project
9Texas Nodal Program UpdateJuly 9, 2007 9
MMS UI Schedule
Data collection and Base product evaluation: Jun – Jul 2007 Internal: Jun – Jul 2007 With Market Participants: Jul 2007
Initial redesign created: Jul 2007 validated with Market Participants: early Aug 2007 sent to ABB: Mid Aug 2007 from ABB: Mid Oct 2007
Evaluation of Revised UI with Market Participants: Oct – Nov 2007 Second Redesign
created: Nov 2007 validated with Market Participants: late Nov 2007 sent to ABB: early Dec 2007 Revisions from ABB: Jan 2008
Evaluation of Revised UI with Market Participants: Feb 2008
10Texas Nodal Program UpdateJuly 9, 2007 10
Outage Scheduler UI Schedule
Initial Guidance – provided tutorial for OS system prepared by ERCOT with Market Participants Forms basis for design ABB assessing changes from ABB: Mid Oct 2007
Evaluation of Revised UI with Market Participants: Oct – Nov 2007 Second Redesign
created: Nov 2007 validated with Market Participants: late Nov 2007 sent to ABB: early Dec 2007 Revisions from ABB: Jan 2008
Evaluation of Revised UI with Market Participants: Feb 2008
11Texas Nodal Program UpdateJuly 9, 2007 11
Network Model Management System UI Schedule
Initial Review of Project Tracker (NOMCR submission and tracking system
Redesign provided to Siemens: Apr 2007 Evaluation of Revised UI with Market Participants:
Prototype evaluations: Jul 2007 Revised UI for PTC expected: Sep 2007
Second Redesign Created: Oct 2007 Validated with Market Participants: late Oct 2007 Sent to Siemens: early Nov 2007 Revisions from Siemens: late Dec 2007
Evaluation of Revised UI with Market Participants: Jan 2008
12Texas Nodal Program UpdateJuly 9, 2007 12
Congestion Revenue Rights UI Schedule
Data collection and Base product evaluation: Jun – Jul 2007 Initial redesign
created: Jun 2007 sent to Nexant: Jun 2007 from Nexant: Mid Oct 2007
Evaluation of Revised UI with Market Participants Using prototypes: Aug 2007 Using CRR system: Oct 2007 (may not have all changes
implemented)
13Texas Nodal Program UpdateJuly 9, 2007 13
Market Information System UI Schedule
Collaborative effort between ERCOT, Market Participants, and vendor since mid 2006
Initial build of MIS received from vendor Jun 2007 Most links are broken – sources not in place yet
Define contents of Landing pages with Market Participants: Jul 2007
Navigation Validation assessment with Market participants: Sep 2007
MIS Validation with Market Participants: Dec 2008