Page 1: July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan

July 9, 2007TPTF Meeting

Texas Nodal Program Update

Jerry Sullivan

Page 2: July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan

2Texas Nodal Program UpdateJuly 9, 2007 2

Agenda

Item Purpose Page

Program Status For Information 3

EMS CSD Status For information 4

User Interface Development Schedule for Market-facing applications

For Information and comment 5

Appendix – More details on UI Development Schedule

For information 8

Page 3: July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan

3Texas Nodal Program UpdateJuly 9, 2007 3

CostScheduleScope / Quality

Legend

Summary

The program has made significant progress on reducing the backlog of NPRRs to synchronize all projects

Amber

The program is spending under budget through May’s actuals. Discussions with the ERCOT

Executive Committee outlined possible ways to ensure we are on

budget at completion.

Amber Amber

TPTF/PRS approved Baseline 1 on June 12 and Baseline 2 on June 21.

TAC recommended baseline 1&2 NPRRs on June 28. Program scope can be declared Green subject to

Board approval of NPRRs for Baseline 1 and 2.

Red

Amber

Green Estimate at Complete = <$248m

Estimate at Complete = $248 - $263m

Estimate at Complete = >$263m

Go-live = 12/1/08

Go-live = <30 days+

Go-live = >30 days+

Program is aligned with current protocols

Program is aligned to previous version of protocols

Program is not wholly aligned to protocols

EDS1 and 2 proceeding on schedule. EDS3 approach

approved by TPTF on June 11.

There are schedule risks in Baseline 1 & 2 which we are

mitigating.

Scope/Quality

Nodal

Cost

ScheduleScope/Quality

Schedule

Cost

Nodal Delivery

Nodal Delivery

Page 4: July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan

4Texas Nodal Program UpdateJuly 9, 2007 4

• Provisionally Approved EMS CSD, Ver. 0.11

• Version Excluding AREVA IP Now Posted – Ver. 0.11a

• Complete Document Available To MP Employees

– No NDA Required– Contact Stacy Bridges For Immediate Access

[email protected]

EMS CSD Status Update

Page 5: July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan

5Texas Nodal Program UpdateJuly 9, 2007 5

TPTF have made clear their want for a plan and consultation to resolve dissatisfaction over the existing user experience offered by ERCOT…

To address user experience issues ERCOT has:

Established User Experience and Visual Design Guidelines which contain the user interface (UI) Development Process and expected results in style and design approach

Provided these to the vendors as standards for UI for the applications being developed

Created a UI design schedule for each Nodal project that will be market-facing in the go-live market

Page 6: July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan

6Texas Nodal Program UpdateJuly 9, 2007 6

Q3

Nodal UI Schedule Summary

Q2 Q4

June July August September October November December

2008

Outage Scheduler

Network Model Management System

Market Information System

Congestion Revenue Rights

Market Management System

Data collection & base product evaluation

With Market Participants (MPs)

Evaluation of revised UI with MPs

Created 2nd design

Define contents of landing pages

Create initial redesign

InternalValidate with MPs

Sent to ABB From ABB

Validate with MPs

Sent to ABB

Revisions from ABB

(Jan)

Validate with MPs

(Feb)

Evaluation of revised UI with MPs

Created 2nd designFrom ABB

Validate with MPs

Sent to ABB

Revisions from ABB

(Jan)

Validate with MPs

(Feb)

Created 2nd designRevised UI for PTC expected

Validate with MPs

Sent to Siemens

Revisions from

Siemens (Jan)

Validate with MPs

(Jan)

Redesign provided to Siemens (Apr 2007)

Data collection & base product evaluation

Created initial re-design

Sent to Nexant

Received from

Nexant

Initial build received from

vendor

Navigation validation assessment w/MPs

= Ongoing activity (Design, evaluation)= one-time activity (meeting/milestone)

Prototype Evaluations

MIS Validation with MPs

Assessment of CRRsystem w/MPs

Assessment of CRRprototypes w/MPs

Page 7: July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan

7Texas Nodal Program UpdateJuly 9, 2007 7

Our Long Range Plan

Make User Experience an essential element of the Change Process Iterative process Evolutionary process Goal directed

Form the User Interface Design Council Market Participant focused, extension of MIS subgroup Collaborate on designs

Provide means for getting feedback Structured

System reviewsSurveys

UnstructuredHelp Desk ticket analysis “Comment Box”

Page 8: July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan

July 9, 2007TPTF Meeting

Texas Nodal Program Update

UI Development Schedule – Appendix showing each project

Page 9: July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan

9Texas Nodal Program UpdateJuly 9, 2007 9

MMS UI Schedule

Data collection and Base product evaluation: Jun – Jul 2007 Internal: Jun – Jul 2007 With Market Participants: Jul 2007

Initial redesign created: Jul 2007 validated with Market Participants: early Aug 2007 sent to ABB: Mid Aug 2007 from ABB: Mid Oct 2007

Evaluation of Revised UI with Market Participants: Oct – Nov 2007 Second Redesign

created: Nov 2007 validated with Market Participants: late Nov 2007 sent to ABB: early Dec 2007 Revisions from ABB: Jan 2008

Evaluation of Revised UI with Market Participants: Feb 2008

Page 10: July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan

10Texas Nodal Program UpdateJuly 9, 2007 10

Outage Scheduler UI Schedule

Initial Guidance – provided tutorial for OS system prepared by ERCOT with Market Participants Forms basis for design ABB assessing changes from ABB: Mid Oct 2007

Evaluation of Revised UI with Market Participants: Oct – Nov 2007 Second Redesign

created: Nov 2007 validated with Market Participants: late Nov 2007 sent to ABB: early Dec 2007 Revisions from ABB: Jan 2008

Evaluation of Revised UI with Market Participants: Feb 2008

Page 11: July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan

11Texas Nodal Program UpdateJuly 9, 2007 11

Network Model Management System UI Schedule

Initial Review of Project Tracker (NOMCR submission and tracking system

Redesign provided to Siemens: Apr 2007 Evaluation of Revised UI with Market Participants:

Prototype evaluations: Jul 2007 Revised UI for PTC expected: Sep 2007

Second Redesign Created: Oct 2007 Validated with Market Participants: late Oct 2007 Sent to Siemens: early Nov 2007 Revisions from Siemens: late Dec 2007

Evaluation of Revised UI with Market Participants: Jan 2008

Page 12: July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan

12Texas Nodal Program UpdateJuly 9, 2007 12

Congestion Revenue Rights UI Schedule

Data collection and Base product evaluation: Jun – Jul 2007 Initial redesign

created: Jun 2007 sent to Nexant: Jun 2007 from Nexant: Mid Oct 2007

Evaluation of Revised UI with Market Participants Using prototypes: Aug 2007 Using CRR system: Oct 2007 (may not have all changes

implemented)

Page 13: July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan

13Texas Nodal Program UpdateJuly 9, 2007 13

Market Information System UI Schedule

Collaborative effort between ERCOT, Market Participants, and vendor since mid 2006

Initial build of MIS received from vendor Jun 2007 Most links are broken – sources not in place yet

Define contents of Landing pages with Market Participants: Jul 2007

Navigation Validation assessment with Market participants: Sep 2007

MIS Validation with Market Participants: Dec 2008