july 7, 2008 tptf texas nodal market implementation: - market readiness metrics update jerry...
DESCRIPTION
3 3 Texas Nodal Program UpdateJuly 7, 2008 Status Update All status levels for overall readiness remain the sameTRANSCRIPT
July 7, 2008TPTF
Texas Nodal Market Implementation:- Market Readiness Metrics Update
Jerry Sullivan
2Texas Nodal Program UpdateJuly 7, 2008 2
Agenda: Market Readiness Metrics Update
• Status Update– ERCOT Staff Readiness– Market Participants
• Cycle 4 Survey Update• Metric Update
– EDS
• Appendix (see separate file)
• Metrics Review (see separate file)
3Texas Nodal Program UpdateJuly 7, 2008 3
Status Update
All status levels for overall readiness remain the same
4Texas Nodal Program UpdateJuly 7, 2008 4
ERCOT Readiness
• Engagement (green)• new survey results came out at the end of
June - ERCOT remains fully engaged
• Training (amber)• training efforts are on-going
• Process (amber)• one department in System Operations is
behind performance levels
• Staffing (amber)• ERCOT is currently ~95% staffed
(98% required for green status)• recruitment is on-going
• Testing (green)• no recent developments
ERCOT Staff Readiness status is AMBER
15 July 2008 ERCOT Public
5Texas Nodal Program UpdateJuly 7, 2008 5
Market Participant Readiness
Market Participant Readiness status is AMBER
• Engagement (amber)• limited survey response from QSEs and LSEs
drives amber status
• Connectivity (green)• several new entrants to the market have been
successfully tested
• Registration and Qualification (amber)• MP10 (resource mapping) has, again,
improved steadily since the last meeting• MP11 (RARF data) – only 5 RARFs have not
been received (RARFs representing more than 99.5% of MWs have been submitted)
• Telemetry (green)• no change
• Training (amber)• limited survey response from QSEs drives
amber status
• Trials Participation (green)• improvement in MP15 (EDS 3 trials
participation)
15 July 2008 ERCOT Public
6Texas Nodal Program UpdateJuly 7, 2008 6
Cycle 4 Survey Update
• There were varying degrees of response to the Cycle 4 Survey
– QSEs with Resources and TDSPs had 100% response to the Cycle 4 Survey– 87% of QSEs have responded to the survey (up from 72%)
– 81% of LSEs have responded to the survey (up from 67%)
• This limited response is driving several metrics to red– QSEs without Resources are red for MP1, MP12, and MP13– LSEs are red for MP19
• ERCOT Account Managers will continue their outreach efforts to MPs who were non-responsive to the Cycle 4 Survey or who reported negative answers
• The survey will remain open through August 15th
• Updates to the Cycle 4 Survey can be submitted using the excel form found on the metrics website (same process as previous surveys)
Cycle 4 Survey Data was reported on the scorecards on June 12th
7Texas Nodal Program UpdateJuly 7, 2008 7
Metric Updates
• Metrics will be updated on a weekly basis
• Changes will appear on the scorecard on Wednesday afternoon
• You will be notified Tuesday or Wednesday morning if you will be going red
• Contact us if you notice any inconsistencies
• Survey data will now be stockpiled and updated on a weekly basis
• There will not be a “Wall of Shame” in the Board presentation next week
8Texas Nodal Program UpdateJuly 7, 2008 8
Status Update: EDS
• EDS 1 (green) no changes
• EDS 2 (red) state estimator convergence values were consistently higher last week EMO12 (Network Operations Model and SE Performance) is now amber
approximately 71 unobservable buses (less than 2%)
• EDS 3 (amber) Maintained amber status CRR5 (Trial Operation of Annual CRR Auction during Trials) expected to go amber 7/11
• EDS 4 (red) waiting on EMS 5 delivery to proceed with EMO3 (Verify Outage Evaluation System Functionality) site fail-over test scheduled for 7/8
EDS status remains unchanged since the last meeting
9Texas Nodal Program UpdateJuly 7, 2008 9
Questions ?