Rehoming Process Overview

by

Jamal Arshad (LCC)July 11th, 2008

Page 2: Jamal Rehoming Process Overview 071108

Rehoming Scenarios

• Rehoming to a different parent MSC• Rehoming to a different parent MGW• Rehoming to a different parent BSC

Page 3: Jamal Rehoming Process Overview 071108

Rehoming Scenarios

• BSC Rehoming – Parent MSC changes

MSC(1) MSC(2)

BSC(1)

BTS(2)BTS(1) BTS(3) BTS(4) BTS(5) BTS(6) BTS(7)

Page 4: Jamal Rehoming Process Overview 071108

Rehoming Scenarios

• BSC Rehoming – Parent MSC changes

MSC(1) MSC(2)

BSC(1)

BTS(2)BTS(1) BTS(3) BTS(4) BTS(5) BTS(6) BTS(7)

Page 5: Jamal Rehoming Process Overview 071108

Rehoming Scenarios

• BSC Rehoming – Parent MGW changes

MGW(1) MGW(2)

BSC(1)

BTS(2)BTS(1) BTS(3) BTS(4) BTS(5) BTS(6) BTS(7)

MSS(1)

Page 6: Jamal Rehoming Process Overview 071108

Rehoming Scenarios

• BSC Rehoming – Parent MGW changes

MGW(1) MGW(2)

BSC(1)

BTS(2)BTS(1) BTS(3) BTS(4) BTS(5) BTS(6) BTS(7)

MSS(1)

Page 7: Jamal Rehoming Process Overview 071108

Rehoming Scenario

• Site Rehoming – Parent BSC changes

MSC(1)

BSC(2)

BTS(2)BTS(1) BTS(3) BTS(4) BTS(5) BTS(6) BTS(7)

BSC(1)

BTS(3) BTS(4) BTS(5)

Page 8: Jamal Rehoming Process Overview 071108

Rehoming Scenario

• Site Rehoming – Parent BSC changes

MSC(1)

BSC(2)

BTS(2)BTS(1) BTS(3) BTS(4) BTS(5) BTS(6) BTS(7)

BSC(1)

BTS(3) BTS(4) BTS(5)

Page 9: Jamal Rehoming Process Overview 071108

Why spend on Rehoming?

• Switch capacity• BSC capacity• Upgraded technology• Border optimization• Performance degradation

Page 10: Jamal Rehoming Process Overview 071108

Switch Capacity Overloaded•BSC rehomed from MSS42\\MGW04 to MSS54\\MGW06

•Avoid chocking in switch

•A requirement from NSS

Page 11: Jamal Rehoming Process Overview 071108

BSC Capacity Overloaded• 49 sites rehomed from IAB003_BSC1 and

IAB003_BSC3 to IAB004_BSC2 (S12)

BSC3i-600•600TRXs

•4500Erlangs

•124E1s upgradable to 252

BSC3i-2000•2000TRXs

•12000Erlangs

•378E1s

Page 12: Jamal Rehoming Process Overview 071108

Upgraded Technology•Shorter setup time

•Shorter routing path

•Speech perception

•Pool structure possible

Page 13: Jamal Rehoming Process Overview 071108

Upgraded Technology

Page 14: Jamal Rehoming Process Overview 071108

Border Optimization

•BSC CP Load

•MSC CP Load

•Extra Location Updates

•Inter BSC HO delay

•KPIs’ degradation

•Bad design

Page 15: Jamal Rehoming Process Overview 071108

Border Optimization

Page 16: Jamal Rehoming Process Overview 071108

Border Optimization

Page 17: Jamal Rehoming Process Overview 071108

Performance Degradation•Mismatch of BSC and MSC definitions•Sudden degradation of statistics

Page 18: Jamal Rehoming Process Overview 071108

Performance Monitoring

• Drive Testing• Statistical monitoring

Page 19: Jamal Rehoming Process Overview 071108

Drive Tester’s Check List• Inter BSC HO (both directions on all borders) • Inter MSC HO (both directions on all borders)• Intra cell HO (900 to 1800 and 1800 to 900) • Call drops• Call setup time• Inter cell HO • Location updates (both directions on all borders) • Speech codecs (AMR, Non AMR)• GPRS/EDGE• Calls from HOME PLMN to other PLMNs and vice versa• Emergency calls – Route verification• Subscriber distribution in VLRs (if pool activated)

Page 20: Jamal Rehoming Process Overview 071108

Statistical Performance Monitoring

• Routine checks of all KPIs

Page 21: Jamal Rehoming Process Overview 071108

Phase 5 Plan•IPW104_BSC2 •IJL005_BSC3 •IPW023_BSC2 •IPW104_BSC1 •LGT100_BSC2 •IPW023_BSC1 •IAB004_BSC2 •IAB004_BSC1, IAB003_BSC3, IIB103_BSC2 •IAB003_BSC1 •IPW751_BSC3 (28/38) •IIB213_BSC1•IRP310_BSC2 •IRP606_BSC1 •IPW751_BSC2