Integrating information towards Digital ATM
Mini Global Demonstration
Presented By: Thien Ngo
Date: August 28, 2013
1
Demonstration Overview
Mini Global will demonstrate the applicability of the global exchange models for Flight, Aeronautical and Weather information using the FIXM, AIXM, and WXXM standards.
The demonstration intends to show how the FAA, International ANSPs and flight operators, in both the Pacific and Atlantic regions, are able to share common information to:
Improve collaborative decision making (CDM)Improve air traffic management (ATM)Promote international harmonization
2
Demonstration Objectives
• Demonstrate the exchange and applicability of global exchange models to a broader international communityo Utilize FIXM, AIXM, and WXXM standards
• Evaluate how these standards will address multiple disparate international systemso Different levels of maturityo Different levels of data model fidelity
o Recommend updates to FIXM, AIXM, and WXXM standards
• Identify and convey possible benefits that can be achieved with the global harmonization of data exchange
• Support validation of ICAO Flight and Flow-Information for a Collaborative Environment (FF-ICE)
3
Demonstration Approach
• Define/identify collaboration goals with international partners:o Collaborate to develop Use Case / Scenarios (i.e. international boundary
coordination)o Identify additional data elements in FIXM (if necessary)o Agree on integration architecture o Establish requirements for connectivity / services / data to support
demonstration o Address GUFI considerations
• Establish connectivity to Mini Global Enterprise Messaging Service• Conduct Test and Evaluate
• Perform Demonstration
4
Demonstration Partnerships
Air Navigation Service Providers• FAA• Air Services Australia• JCAB• Airways New Zealand• Fiji *• Portugal *• UK NATS *• NavCanada
ATM Industry Partners
DoD *Airline Operators
* Potential Partner
Partner decision to participate in Mini Global RMD – Sept 6, 2013Partner decision to participate in Mini Global Final Demonstration – Jan, 2014
5
High Level Mini Global Architecture
Mini Global Enterprise Message Service
(Governance, Validation, Security,
and Routing)
Mini Global Enterprise Message Service
(Governance, Validation, Security,
and Routing)
Australia Europe
Other ANSP’s, AOCs, and Partners
FAA
MGAdapter
Requires data transformation into FO format
FIXM/AIXM/WXXM messages
FTB
FAASMGAdapters
or
or
Global GUFI Service
Global GUFI Service
AAtS
or
Mini Global Enterprise Message Service
(Governance, Validation, Security,
and Routing)
Mini Global Enterprise Message Service
(Governance, Validation, Security,
and Routing)
Mini Global Enterprise Message Service(Governance, Validation, Security, and
Routing)
Mini Global Enterprise Message Service(Governance, Validation, Security, and
Routing)
Service by Harris Service by Other Service by Europe
WJHTC OVDex WJHTC OVDex
AIXM & WXXM Viewer
AIXM & WXXM Viewer
6
The Mini Global Enterprise Message Service Providers will provide the following services:
• Governance:o Policy management and enforcemento Metrics and performance
• Validation of FIXM messages• Security:
o Authorize, Authenticate• Routing:
o Support request/response, publish/subscribe message exchange patternso Content, Rules and Policy based routing
• Transformation of native data to support exchange models (MG Adapter)• Utilize standard protocols between MG Service Providers • Access to Global GUFI service
Mini Global Enterprise Messaging Service
7
FTB Architecture Phase I – FAA NAS
8
FTB Architecture Phase II– FAA NAS
9
Mini Global Benefits• Promote international harmonization
o Data exchange with other international ANSPs, AOCs, and the aviation industry
• Assess the compatibility of partner ATM systemso With respect to global exchange models (FIXM / WXXM / AIXM)o Mature the FIXM standardo Accelerates potential uses for WXXM / AIXM data exchange o Identify services / meaningful to current and future operations
• Provide the foundation for new operational capabilities / procedures utilizing international data exchange
10
Mini Global Demonstrations
• Risk Mitigation Demonstration (February 2014)o Limited number of stakeholders and limited number of capabilitieso Focus on Mini Global Enterprise Message Service Infrastructure with
multiple service providerso Demonstrate a robust and stable demo environmento Identify any associated demonstration risks to be addressed before the
final demonstrationo Continuous running service over multiple days to support stakeholder
needs• Final Demonstration (September 2014)
o Perform Mini Global demonstration with enhanced capabilities to include broader international partners
o Evaluate the effectiveness of the global exchange models in addressing the interoperability of international systems
11
Timeline Phase I (2013-2014)
TIM #3 (Engineering Checkpoint)
TIM #2 (Engineering Checkpoint)
Risk Mitigation Demo Report
Safety Assessment
Mini Global Risk Mitigation Demonstration
Mini Global Enterprise Messaging Service Infrastructure Established
Project Start
Conduct Partner Integration, Test &
Evaluation
Establish Partner
Connectivity
Initiate PartnerCollaboration
Mini Global Intl. Collaboration & Data Exchange Package
TIM #1 / Kickoff
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan 14 Feb 14 Mar 14
12
Timeline Phase II (2014-2015)
TIM #5
Apr 14 May 14 Jun 14 Jul 14 Aug 14 Sep 14 Oct 14 Nov 14 Dec 14 Jan 15 Feb 15
TIM #4(Engineering Checkpoint)
Mini Global Final Demonstration
Mini Global Demonstration
Readiness Review
Mini Global Final Demonstration Architecture & Scenarios Package
Final Demonstration Walk-Through
Conduct Partner Integration, Test &
Evaluation
Collaboration with other international
Partners
Provide feedback to the FO Program Office
Flight Object (FO)Recommendation
Report
ICAO Symposium
Mini Global Final Demonstration
Report
Mini Global Deliverables
13
Complete In Development Future
Int’l Briefing Package Mini Global RMD Demonstration Objectives
Partner Integration Report
Mini Global Architecture & Capabilities
Mini Global RMD Demonstration Requirements
Demo Plan Update (2014)
Mini Global Initial Scenarios
Integration & Test Procedures
Demonstration Report
Mini Global Demonstration Plan
Demonstration Plan Use Cases (2014)
Mini Global Use Cases Shortfalls & Benefits Safety Assessment (Final)
Safety Assessment Metrics & Methodologies
Questions
14
Contact Information
15
Thien NgoFAA NextGen Office - Mini Global Project Manager
Ian H. RossFAA NextGen Office - International Programs
13
Mini Global cloud established Sept 2013 Initiate Partner Integration Nov 2013 Risk Mitigation Demonstration Feb 2014 Final Demonstration Sept 2014
Contact Information: Thien Ngo FAA NextGen Office – Mini Global Project Manager 202-267-9447 [email protected] Ian H. Ross FAA NextGen Office – International Programs 202-267-8377 [email protected]
Partners:
Mini GlobalDemonstration
13
Mini Global major objectives include: •Demonstrate the applicability of global exchange models to a broader international community in all regions
•Evaluate how exchange models will address multiple international systems
•Recommend updates to the FIXM Standard
•Support validation of ICAO Flight and Flow - Information for a Collaboration Environment (FF-ICE)
Mini Global will demonstrate the applicability of the global exchange models for Flight, Aeronautical and Weather information using the FIXM, AIXM, and WXXM standards. With Mini Global, the aim is to increase global predictability by addressing seamless operations, integration of systems, and effective cross border operations. The demonstration intends to show how the FAA, International ANSPs and flight operators can share common information to improve collaborative decision making, improve air traffic management and promote international harmonization.
Mini Global allows partners to assess the compatibility of their ATM systems with respect to global exchange models (FIXM / WXXM / AIXM), and identify services / products meaningful to their current and future operations. Mini Global also provides the foundation for development of new operational capabilities & procedures utilizing international data exchange. The Mini Global Enterprise Messaging Service will be established in September 2013 by multiple service providers for their respective regions. Partners can integrate with the service providers in order to participate in the Mini Global demonstrations. Service Levels for participation are defined in the Mini Global Integration Checklist. Request this checklist via email to [email protected]. Partners will participate by providing information for data exchange via the Mini Global infrastructure, and: •Develop Use Case / Scenarios for Mini Global demonstrations (i.e. Border Coordination)
•Identify additional data elements (if necessary)
•Establish connectivity to the Mini Global infrastructure
•Participate in the Mini Global Risk Mitigation (Feb 2014) and/or Final Demonstration (Sept 2014)
•Provide feedback on Mini Global demonstrations (lessons learned, recommendations, etc.)