ilc conventional facilities - ilc agenda (indico) · pdf fileilc conventional facilities...

33
ILC PAC Meeting @LAL Orsay 1 International Linear Collider (ILC) Global CFS Group ILC Conventional Facilities Victor R Kuchler John Andrew Osborne Masanobu Miyahara 2015/4/13

Upload: dangkien

Post on 11-Mar-2018

216 views

Category:

Documents


3 download

TRANSCRIPT

ILC PAC Meeting @LAL Orsay 1

International Linear Collider (ILC)Global CFS Group

ILC Conventional Facilities

Victor R Kuchler

John Andrew Osborne

Masanobu Miyahara

2015/4/13

Contents

• Potential Site in Asian region

• TDR Configuration Overview

• CFS work for Change Requests

• Project Schedule - Next Steps

2015/4/13 ILC PAC Meeting @LAL Orsay 2

Asian Potential Site : KITAKAMI

LAND Features: ILC Site is located in south-west of Kitakami Highland. Land is almost covered forest, agriculture and daily farms. ILC Route is sloping terrain accessible to the underground.

Access to the Site

Tohoku

Tokyo

Kitakami

Panoramic view from the top of AWARA-Yama mountain

Landscape along the ILC Route

Climate: Annual average temperature: 10.8℃ (51.4℉)

Coldest month (Feb) : -4.8℃ (23.3℉ ) Annual precipitation : 1,338 mm Maximum amount of snow: 30 cm

2015/4/13 ILC PAC Meeting @LAL Orsay 3

Potential site conditions

- 2005First Preliminary survey<Iwate Pref.>

- 2009Second Preliminary Survey <Iwate Pref.>

- 2010Third Preliminary Survey

<Iwate Pref. & Tohoku Univ.>-2011

Ground Water Survey <Tohoku Univ.>

Geological Investigation

Sendai ●

KitakamiHighland

Pacific Ocean

- 2015Investigation Plan at the new IP area <Iwate Pref. and Tohoku Univ.>

Currently in Contract process

Potential site conditions

- 2012~13Investigation of candidate site conditions <KEK, Tohoku Univ. & Kyushu Univ.>

Topographic Map

2015/4/13 ILC PAC Meeting @LAL Orsay 4

Environmental Assessment- 2013~14

Pilot Survey (Field Survey of Raptor) <IWATE Pref.>

Bedrock Properties in Central Region

5

Potential site conditions

IP

ILC PAC Meeting @LAL Orsay2015/4/13

P-wave velocity around IP

IP

N

S

Seismic exploration result:・ Distribution of the stable Bedrock zone in whole central region.・ P-wave velocity: more than 5km/s・ The distribution of the low-velocity layer can be seen partially.

Key Plan

IP

ORIKABE Granite

3D Geographical Map

3D Bird’s-eye view from the North side

HITOKABE Granite

● OSHU

● ICHINOSEKISENMAYA Granite

ORIKABE Granite

Pacific Ocean

IWATE Pref.

MIYAGI Pref.

S

Laser rangefinder

GPS Satellite

GPS Satellite

Aerial Laser survey

※DEM: Digital Elevation Model

2015/4/13 ILC PAC Meeting @LAL Orsay 6

Potential site conditions

Design and Optimization

• Understanding of the Geology, Geography and natural environment is extremely essential requirements for civil engineering design.

• Natural Bedrock itself will be the tunnel structure in NATM tunneling.Grasp of the detailed bedrock properties is the most important item.

• 3D Design Integration with the Geology, Geography & Accelerator Lattice is needed to optimize the underground facilities layout

LatticeAccess Halls

Utility Halls

Surface

Design Integration in the Mountain site

2015/4/13 ILC PAC Meeting @LAL Orsay 7

Potential site conditions

Access Tunnel

Electric Power Infrastructure

Electric Power Demand of the ILC operation is about 1.5 % of the total Supply Capacity of Tohoku region (6 Prefectures)

The current supply reserve capacity maintains over 10%.

Electricity demand of the Tohoku districtslightly has more winter than summer.

11.6

5.2 7.1

11.8 12.0 11.1

0.0

10.0

20.0

30.0

40.0

0

5,000

10,000

15,000

20,000

SM 2011/8 WT 2012/2 SM 2012/8 WT 2013/1 SM 2013/8 WT 2014/2

Power Supply Status

Supply Capacity

Demand

Reserve Capacity

Reserve Rate

MW Reserve Rate

Data By Tohoku EPCO public document

EP Infrastructure of Tohoku District

2015/4/13 ILC PAC Meeting @LAL Orsay 8

Potential site conditions

Detector Hall

Underground Facilities

Accelerator Tunnel Length 39.7 km

Cavern Volumes 520,000 m3

Overall of the ILC Complex

TDR Configuration

CRYOMODULE KLYSTRON

2015/4/13 ILC PAC Meeting @LAL Orsay 9

Main Linac

DR

Detector Hall

RTML turn-around

Access Hall

(The background picture shows a similar site image but not the real site.)

Access Facilities Layout

AS-X Access Station on Surface

Access Tunnel

Access Road

AS-1AS-2

AS-3AS-4

AS+2 AS+3

AS+4

AS-0a AS+1

Access Road (Existing)

Mountain site Image

Access TunnelAccess Tunnel

Central Campus

Access Station

RTML

Central

Substation

Access Hall

Utility BuildingInstall HouseSubstation

Access Portal

AS-0b

Accelerator Tunnel

Wave guide system

He Compressor

Cooling Water

He Cold box2K

Access Tunnel

Substation

TDR Configuration

2015/4/13 ILC PAC Meeting @LAL Orsay 10

Main Linac Tunnel

ML Tunnel Standard Section ML Tunnel 3D-image

RF Service Tunnel Beam Tunnel

Concrete Shield-Wall

55

00

mm

Inflow Water Drainage

Lining Concrete

High Power Cables

Cooling Water

TDR Configuration

2015/4/13 ILC PAC Meeting @LAL Orsay 11

Compressor Hall

Damping RingTunnel

Cold Box HallUtility Hall

Kicker Part

1

2

Damping Ring Layout

1Damping Ring Tunnel

RF Part Tunnel

2

BDS Tunnel

6.5

4.7

Detector Hall

加速器側 サービス側

13.0

6.9

Beam LineRF Service

1 2

RF Part Tunnel

TDR Configuration

2015/4/13 ILC PAC Meeting @LAL Orsay 12

Mail Beam Dump

142m

25m

42m

142m

Main Cavern Alcoves ILD

Upper AT

Lower AT

Lower AT

Alcoves SiD

Beam tunnel

20m 20m

Utility Cavern

18m 20.5m

25m

12.5m

12.5m

142m

13

42m

25m

Section

空洞 断面寸法

Main hall H 42.0mW 25.0mL 142.0m

Alcoves H20.5mW 20.0mL 12.5m

Detector Hall

TDR Configuration

SiD

ILD

ILC PAC Meeting @LAL Orsay2015/4/13

CFS Work after TDR

Change Request proposed

1. Detector Hall with Vertical Shaft access (CR-0003)

2. Extension of the ML-tunnel length (CR-0004)

Change Request anticipated in Future

1. ML Shield-wall thickness impact

2. BDS Tunnel configuration

3. Cryogenics facilities Layout

2015/4/13 ILC PAC Meeting @LAL Orsay 14

Access TunnelW8m Grad10%

Access TunnelW11m Grad7%

AssemblyYard

DHDR

DR Yard

Access TunnelW8m Grad10%

Overview of the Change Request

AssemblyYard

DR Yard

DHDR

Vertical ShaftUtility shaft D10m

1 DH with Vertical Shaft Access ILC-CR-0003

Vertical ShaftMain shaft D18m

• Change Review Panel Members: K. Yamamoto, V. Kuchler

• Current Status: Accepted by CMB

TDR Baseline

Assembly Place: underground/DH Access way to DH underground

- only horizontal Access Tunnel (AT)- Transport. by special long trailer

New Baseline

Assembly Place: Surface building/AH Access way to DH underground

- mainly Vertical Shaft (VS)- Transport. by Gantry Crane

2015/4/13 ILC PAC Meeting @LAL Orsay 15

CFS Work After TDR

From the EDMS Meeting @KEK 2.12.2014

Assembly Hall just above the IP

Main Shaft

Utility Shaft Access Portal

Detector Hall

3D Design Integration model: Underground and Surface Facilities

ILC PAC Meeting @LAL Orsay 16

DH with Vertical Shaft Access New Baseline Layout

2015/4/13

CFS Work after TDR

TDR Baseline

144m

Utility Shaft

SiD

108m

New Baseline

ILD

ILD SiDMain Shaft MS/D18m

Access Tunnel

Detector Hall Configuration

DR

Access Tunnel

DR

2015/4/13 ILC PAC Meeting @LAL Orsay 17

CFS Work after TDR

• DH construction cost is estimated to be reduced slightly than Baseline.

ItemsBaseline New Baseline Difference

Cost ImpactA B B-A

Civil (Underground Facilities) UPDH Cavern, Access Tunnel 11,500 12,400 900 +7.8%

Architectural (Surface Buildings) EvenAssembly Hall, other buildings 1,590 1,590 0 -

Mechanical Facilities DownLCW & CHW, Air Duct, Plumbing 1,360 165 -1,195 -88%

Handling Equipment Down

Crane, Lowering & Transport, EV 3,570 2,930 -640 -17.9%

Total 18,020 17,085 -935 -5.2%

Total Cost Impact 0~-10%

Cost Impact of the Change Request

DH Construction Cost

2015/4/13 ILC PAC Meeting @LAL Orsay 18

CFS Work after TDR

Change Implementation Plan

• Change Implementation Team Members: V Kuchler (chair), K Buesser, T Markiewicz, B List, M Miyahara, and T Sanuki(Support)

• Current Status: Final draft will be discussed and reviewed at ALWC2015 meeting (Tsukuba/KEK)

Construction Schedule0 12 24 36 48 60 72 84 96 108

TotalAccess TunnelDetector Hall

Assembly HallDetector Assembly

115.934.0

54.523.0

36.0

0 12 24 36 48 60 72 84 96 108

TotalAccess Tunnel

Access ShaftDetector Hall

Assembly HallDetector Assembly

103.022.8

47.354.7

28.0

35.4

116 months

103 months

Baseline

New Baseline

2015/4/13 ILC PAC Meeting @LAL Orsay 19

CFS Work after TDR

• Total construction schedule including the installation term can be reduced for about 1 year compared with the baseline.

Gantry Crane

18m

LHC-CMS

18m

Main shaft D=18m

Center of DH

Detectors Installation

Surface

Gantry Crane

LHC-CMS/CERN

Vertical Shaft Structure

2015/4/13 ILC PAC Meeting @LAL Orsay 20

CFS Work after TDR

70

m4

2m

11

2m

Main Shaft

2 Extension of the ML Tunnel ILC-CR-0004

4907.760 4911.580 3413.787 2334.943 4795.218 4907.760 2509.7172509.717129.258129.258

4907.760 4911.580 3413.787 2334.943 4795.218 4907.760 2509.7172509.717129.258

129.25815001500

TDR Baseline

New Baseline

12,329.063 12,212.695

Additional Tunnel

13,829.063 13,712.695

Under Discussion

• Change Review Panel Members: V Kuchler (chair), N Waker,H Nakai, T Sanuki, M Miyahara

• Current Status: Under Discussion Change Implementation Team

2015/4/13 ILC PAC Meeting @LAL Orsay 21

CFS Work after TDR

Outline of the Change Request Extension of Main Linac Tunnel:• Both the Electron and Positron ML Tunnels by approximately 1.5 km. • Electron Linac Length: 12.3km →13.8 km, • Positron Linac Lebgth: 12.2 km → 13.7 km

Rational: • Adjust the total beam-line path length on the Positron side in order to fulfill the

timing constraint by the baseline method of positron production

Cost Impact of the Change Request 0004

• Current Status: Under Discussion• Further detailed discussion will be planed at ALWC2015

2015/4/13 ILC PAC Meeting @LAL Orsay 22

CFS Work after TDR

Assumption Section Cost

Change Request 0004

Section: 9m x H5.5mShield wall: 1.5m Tunnel Length: 3km

Unit cost: 1,900 kJPY/m

Total cost: 5,700 MJPY

- Beam line : Width 3.8m

- Klystron gallery: Width 3.7m

- Tunnel Inner height :5.5m

Common Dimensions

Beam LineKlystron Gallery

1 ML Shield wall thickness impact Pre-study

• Radiation shield issue will be decided by necessity of person's access• Scheme change depends on the management scenario of beam operation.

2015/4/13 ILC PAC Meeting @LAL Orsay 23

Option-1 SW2.5m

Option-3 No SW

Baseline SW3.5m

Option-2 SW1.5m

CFS Work after TDR

Summery of MLT shield wall thickness impactBaseline SW3.5m Option-1 SW2.5m Option-2 SW1.5m

Cross Section

Cross Section W11m x H5.5m

62.7 m2

W10m x H5.5m

57.2 m2

W9m x H5.5m

51.9 m2

Schedule 64.7 Month 62.1 Month 59.7 Month

Const. Cost

Total Cost 61,100 MJPY 53,500 MJPY 48,200 MJPY

Reduction Cost 0 MJPY - 7,600 MJPY - 12,900 MJPY

Comparison 100 % 88 % 79 %

11.0 10.0 9.0

100

8879

54

0 10 20 30 40 50 60 70 80 90 100

SW3.5m SW2.5m SW1.5m SW0m

SW 2.5mSW 1.5m

SW 0m

Option-1

Option-2

Option-X

Baseline SW 3.5m

2015/4/13 ILC PAC Meeting @LAL Orsay 24

CFS Work after TDR

Optional Case study X: SW1.0m, W8.5mTotal cost: 46,000 MJPY

(75%)

BaselineCL

Integrated option_1 Integrated option_2

CL CL

Shield wall width :1.5 mBDS gallery : 5.0 mService gallery : 3.0 m

Total 9.5 m

Shield wall width :1.5 mBDS gallery : 6.0 mService gallery : 3.0 m

Total 10.5 m

Revision

From the twin tunnel in TDR, reconsideration to the single tunnel BDS group is currently reviewing the equipment layout

2 BDS Tunnel Configuration Pre-study

9.5m 10.5m

2015/4/13 ILC PAC Meeting @LAL Orsay 25

CFS Work after TDR

Key Plan

BDS

3 Cryogenics Facilities Layout Pre-study

TDR BaselineAlmost all Cryogenics facilities installed in the underground(2K & 4K Cold Box, He storage tank & Buffer tank, Compressors)

New BaselineAll facilities except 2K-Cold Box installed in the surface yard(4K Cold Box, He storage tank, Compressors, Cooling tower)

Conceptual Design of Cryogenic System

Cooling

Tower2K

Cooling Water Piping

4 K Ref.

Cold Box

Helium Gas

CompressorSC

Cavities

2 K Ref.Cold Box

4K

Multi-transfer Line Helium Gas Piping

2K

Multi-transfer Line

↓TDR Scheme: in the Tunnel underground

Current Direction of Discussion

2015/4/13 ILC PAC Meeting @LAL Orsay 26

CFS Work after TDR

Current Cryogenics FlowUnderground On Surface On Surface

In Tunnel Underground

Current Cryogenics Configuration

Main Discussion Points

• No Cryogen storage underground for CFS safety reason• Shorter 2K transfer line for effective cryogen transport• Radio-activation of helium during long-term operation• Easier access for helium and liquid nitrogen supplies from companies • Noise and mechanical vibration from compressors and cooling towers• Helium inventory during long-term shutdown• High pressure gas safety code

2015/4/13 ILC PAC Meeting @LAL Orsay 27

CFS Work after TDR

From NAKAI-san’s report

Installation

Project Approval

Operation Phase

- - - 1 2 3 4 1 2 3 4 5 6 7 8 9 10 -

Underground Facilities

Surface Facilities Central Campus

ED

TD

Pre-ProjectPhase

Design Phase Construction Phase

Ground Breaking

Construction

9Y4Y

13Y

Design and Construction

Project Schedule

2015/4/13 ILC PAC Meeting @LAL Orsay 28

Focus to Design Phase

- - - 1 2 3 4

Detailed Design

TDBasic

DesignConceptual

DesignFinal

DesignED

Design PhasePre-Design Phase

ConstructionPhase

Pilot S. Environmental Impact Investigation Field Survey & Assessment Study

Pilot S.

Land acquisitionSite Survey

Basic & Detailed DesignPreliminary S.

Pilot S.Detailed Survey

Pilot S. Basic Survey

Topographical Survey

Environmental Assessment

Geological Survey

We are here

2015/4/13 ILC PAC Meeting @LAL Orsay 29

Project Schedule

ARUP Work

TOT carries out :• Data analytics to create a set of summary

outputs and visual decision aids.• Series of analytics to give a range of

Optimum Access tunnel positions onto a fixed LINAC position

From the report/John Osborne(CERN) in FCC-Week 2015

Reference: TOT on the FCC ProjectTOT Development on the ILC CFS

TOT: Tunnel Optimization Tool

User defined Input : • ILC main alignment information and

access tunnel positions in 3D space.• Sets of Requirements for Access tunnel/

portal locations to achieve

Status of Contract: CERN & KEK• On going the contract procedure

next steps

2015/4/13 ILC PAC Meeting @LAL Orsay 30

ILC & TOT

CERN & Arup will work with KEK & ILC to upgrade and adapt the Tunnel Optimisation Tool to provide the same benefits for the ILC tunnel that have been brought to the FCC feasibility study

31John Osborne (CERN-GS)

From the CERN-GS Report of FCC Week 2015 at Washington

ILC PAC Meeting @LAL Orsay

CFS Plans for work over the Upcoming 6 months

• Optimization of Horizontal Access Tunnels (CR-03 & 04)• Geological Investigation at IP area in new baseline

- with in-kind regional contribution by Tohoku Univ. and Iwate Prefecture

• CFS Workshop in July 2015 (London or CERN)- Cooperative work with CERN and ARUP for preparing for

the layout optimization software. - Global discussion of Cryogenics scheme change

Response of the Future Change Requests

• Revision of Main Linac Tunnel Configuration (ML Length and Radiation Shield-wall thickness impact )

• Revision of the BDS Tunnel configuration• Revision of the Utility Cavern with Cryogenics scheme change

Next Steps

next steps

2015/4/13 ILC PAC Meeting @LAL Orsay 32

The End

2015/4/13 ILC PAC Meeting @LAL Orsay 33