ih35e spring 2012 - txdot - dallas construction projects | keep it

2
PROJECT TRACKER INTERSTATE 35E TEXAS DEPARTMENT OF TRANSPORTATION Providing safe, effective, and efficient movement of people and goods INTERSTATE 35E • PROJECT TRACKER Spring • 2012 DALLAS DISTRICT Proposed I-35E looking north, south of Round Grove Road. OVERVIEW Interstate 35E (I-35E) serves the rapidly growing areas of southern and central Denton County, as well as the major Dallas suburbs immediately north of I-635. This corridor functions as a major artery for hundreds of thousands of commuters, as well as a primary link to major universities in the city of Denton, including the fourth-largest university in the state, the University of North Texas (UNT). In addition, I-35E functions as an important truck corridor and accommodates more than 12,000 trucks daily, according to 2008 state vehicle counts. The interstate also handles almost 200,000 total vehicles daily near I-635, and 128,000 vehicles a day across Lewisville Lake. Because of the challenges of crossing the Lewisville Lake and the lack of I-35E frontage roads across the lake, viable north- south commuting alternatives to I-35E do not exist. This condition makes it imperative to provide motorists reliable alternatives with a combination of continuous frontage roads and managed lanes in the I-35E corridor. The proposed $4.8 billion project would rebuild the entire 28-mile corridor and provide managed lanes that feature dynamic pricing to keep traffic moving at 50 mph. Approximately $1.1 billion in funding has been identified for this project, with most coming from SH 121 regional toll revenue funds dedicated to Denton County. PROJECT HISTORY/TIMELINE * I-35E constructed: 1950s and 1960s * Major Investment Study for future expansion: Began 1998 * Environmental Assessment process: 2003-2012 (complete) * Express Lane Demonstration Program Approval by Federal Highway Administration: Sept. 30, 2009 * Finding of No Significant Impact by FHWA: Jan. 28, 2011 (middle section); Dec. 28, 2011 (south); Jan. 31, 2012 (north) ENVIRONMENTAL REVIEW STATUS * Environmental Assessment public meetings: 2008 * FHWA schematic approval for all three sections: Oct. 28, 2009 * All public hearings complete * North section: Finding of No Significant Impact (FONSI) from FHWA received Jan. 31, 2012; FONSI received for all sections. PROJECT PROGRESS * Nine teams responded to TxDOT’s request for qualifications that were due March 23. Five design-build teams and four concession teams submitted qualification statements. * The Senate Bill (SB) 1420 Committee determined at its March 26 meeting that Phase 1A of the project should be delivered as a design-build project with public financing and utlizing the Regional Transportation Council managed lane policy. * To maintain flexibility in the future, no determination has been made on the type of financing or delivery method for construction of the remaining project, known as Phase 1B. * An aesthetics master plan has been developed with the help of local stakeholders. * Legislative authority granted for public-private partnership during 2011 session. Authority has been granted through August 2015. EARLY PROJECTS: * Began right of way (ROW) acquisition, middle section: 2011 * Funding committed by the Texas Transportation Commission to complete FM 407 intersection: Late 2010. * Construction of pedestrian bridge at the University of North Texas to access new football stadium. Goal for opening is 2012 football season. PROJECT FACTS LENGTH * North section (US 380 to FM 2181): 10.5 miles * Middle section (FM 2181 to Pres. George Bush TP): 12.1 miles * South section (Pres. George Bush TP to I-635): 5.5 miles COST * Design and construction (2010 estimate): $3.4 billion (ultimate) * Right of way (2010 estimate): $1.4 billion (ultimate) CONSTRUCTION DATES * Anticipated start date: 2013 (Phase 1A) NEXT STEPS * Proposal process began with a request for information (RFI). Responses were submitted July 20, 2011. * ROW acquisition begins soon in north and south sections. * Request for qualifications shortlist expected in April 2012. * A draft request for proposals (RFP) could be issued in May 2012 and a final RFP issued in July 2012. A contract could be awarded by the end of 2012. * Construction schedule expedited, potential start date after procurement process: 2013

Upload: others

Post on 12-Sep-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: IH35E Spring 2012 - TxDOT - Dallas Construction Projects | Keep It

PROJECT TRACKERINTERSTATE 35E

TEXAS DEPARTMENT OF TRANSPORTATION Providing safe, effective, and efficient movement of people and goods

INTERSTATE 35E • PROJECT TRACKER Spring • 2012

DALLAS DISTRICT

Proposed I-35E looking north, south of Round Grove Road.

OVERVIEWInterstate 35E (I-35E) serves the rapidly growing areas of southern and central Denton County, as well as the major Dallas suburbs immediately north of I-635. This corridor functions as a major artery for hundreds of thousands of commuters, as well as a primary link to major universities in the city of Denton, including the fourth-largest university in the state, the University of North Texas (UNT). In addition, I-35E functions as an important truck corridor and accommodates more than 12,000 trucks daily, according to 2008 state vehicle counts. The interstate also handles almost 200,000 total vehicles daily near I-635, and 128,000 vehicles a day across Lewisville Lake. Because of the challenges of crossing the Lewisville Lake and the lack of I-35E frontage roads across the lake, viable north-south commuting alternatives to I-35E do not exist. This condition makes it imperative to provide motorists reliable alternatives with a combination of continuous frontage roads and managed lanes in the I-35E corridor. The proposed $4.8 billion project would rebuild the entire 28-mile corridor and provide managed lanes that feature dynamic pricing to keep traffi c moving at 50 mph. Approximately $1.1 billion in funding has been identifi ed for this project, with most coming from SH 121 regional toll revenue funds dedicated to Denton County.

PROJECT HISTORY/TIMELINE* I-35E constructed: 1950s and 1960s * Major Investment Study for future expansion: Began 1998* Environmental Assessment process: 2003-2012 (complete) * Express Lane Demonstration Program Approval by Federal Highway Administration: Sept. 30, 2009* Finding of No Signifi cant Impact by FHWA: Jan. 28, 2011 (middle section); Dec. 28, 2011 (south); Jan. 31, 2012 (north)

ENVIRONMENTAL REVIEW STATUS* Environmental Assessment public meetings: 2008* FHWA schematic approval for all three sections: Oct. 28, 2009* All public hearings complete * North section: Finding of No Signifi cant Impact (FONSI) from FHWA received Jan. 31, 2012; FONSI received for all sections.

PROJECT PROGRESS* Nine teams responded to TxDOT’s request for qualifi cations that were due March 23. Five design-build teams and four concession teams submitted qualifi cation statements. * The Senate Bill (SB) 1420 Committee determined at its March 26 meeting that Phase 1A of the project should be delivered as a design-build project with public fi nancing and utlizing the Regional Transportation Council managed lane policy. * To maintain fl exibility in the future, no determination has been made on the type of fi nancing or delivery method for construction of the remaining project, known as Phase 1B. * An aesthetics master plan has been developed with the help of local stakeholders. * Legislative authority granted for public-private partnership during 2011 session. Authority has been granted through August 2015.

EARLY PROJECTS:

* Began right of way (ROW) acquisition, middle section: 2011* Funding committed by the Texas Transportation Commission to complete FM 407 intersection: Late 2010.* Construction of pedestrian bridge at the University of North Texas to access new football stadium. Goal for opening is 2012 football season.

PROJECT FACTS

LENGTH

* North section (US 380 to FM 2181): 10.5 miles* Middle section (FM 2181 to Pres. George Bush TP): 12.1 miles* South section (Pres. George Bush TP to I-635): 5.5 miles

COST

* Design and construction (2010 estimate): $3.4 billion (ultimate)* Right of way (2010 estimate): $1.4 billion (ultimate)

CONSTRUCTION DATES

* Anticipated start date: 2013 (Phase 1A)

NEXT STEPS* Proposal process began with a request for information (RFI). Responses were submitted July 20, 2011.* ROW acquisition begins soon in north and south sections.* Request for qualifi cations shortlist expected in April 2012.* A draft request for proposals (RFP) could be issued in May 2012 and a fi nal RFP issued in July 2012. A contract could be awarded by the end of 2012.* Construction schedule expedited, potential start date after procurement process: 2013

Page 2: IH35E Spring 2012 - TxDOT - Dallas Construction Projects | Keep It

DALLAS DISTRICT

INTERSTATE 35E CONTACTS

INTERSTATE 35E • PROJECT TRACKER

INTERSTATE 35E • PROJECT TRACKER Spring • 2012

INTERSTATE 35E CONTACTS

INTERSTATE 35E • PROJECT TRACKER Spring • 2012

NO

TE: H

ighl

ight

ed a

reas

are

not

to sc

ale.

DENTON

Grapevine Lake

Ray RobertsLake

121

121

288

288

455

428

428

428

428

423

423

455

455

156

407

380380

35W

35

35

380

377

377

377

377

LewisvilleLake

26

26

77

Sanger

PilotPoint

Aubrey

Krugerville

Lincoln Park

Prosper

Frisco

Coppell

Grapevine

Carrollton

Farmers Branch

OakPoint

Hackberry

The Colony

Hebron

Addison

Lewisville

Copper Canyon

Hickory Creek

Shady Shores

Argyle

FlowerMound

2499

11711171

1830

3163

2164 2153

1385

1385

407

2931

114

TrophyClub

114

635

Westlake

Southlake 97

DFWInt’l. Airport

N

5 miles

CO

LLIN

CO

.

DEN

TON

CO

.

TARRANT CO.

DENTON CO.DALLAS CO.

DENTON CO.

35E

Corinth

77

35E

77

35ERo

adw

ay a

nd L

imits

Exist

ing

front

age

road

lane

s (E

ach

dir.

)

Exist

ing

HOV

lane

s (E

ach

dir.

)

Exist

ing

mai

nla

nes

(Eac

h d

ir.)

2 - 3

2

2 - 3

*3

2 - 3

*3

0 0 1

*Disc

ontin

uous

. **

Loop

288

to F

M 2

181.

***

Inte

rim c

onfig

urat

ion

relie

s prim

arily

on

use

of e

xistin

g pa

vem

ent f

or e

xpan

sion.

Fin

al c

onfig

urat

ion

invo

lves

reco

nstru

ctio

n of

rem

aind

er o

f the

cor

ridor

. Tx

DO

T gr

aphi

c

Nort

h:

F

M 2

181

to U

.S. 3

80

Mid

dle

: P

resid

ent G

eorg

e Bu

sh T

urnp

ike

to F

M 2

181

South

:

I-6

35 to

Pre

siden

t Geo

rge

Bush

Tur

npik

e

Inte

rim**

* fro

ntag

ero

ad la

nes

(Eac

h d

ir., 2

017)

Inte

rim**

* ge

nera

lpu

rpos

e la

nes

(Eac

h d

ir., 2

017)

Inte

rim**

* re

vers

ible

m

anag

edla

nes

(201

7)

32

- 3

42

- 3

42

- 3

2**

2 2

Prop

osed

fro

ntag

ero

ad la

nes

(Eac

h d

ir., 2

030)

Prop

osed

ge

nera

lpu

rpos

e la

nes

(Eac

h d

ir., 2

030)

Prop

osed

m

anag

edla

nes

(Eac

h d

ir., 2

030)

32

- 3

42

- 3

42

- 3

1 - 2

2 2

John Hudspeth, P.E.Project ManagerTexas Dept. of TransportationP.O. Box 133067Dallas, TX 75313214-320-6171

Project website: www.keepitmovingdallas.com“IH 35E” link

Texas Department of TransportationP.O. Box 133067Dallas, TX 75313214-320-6100