hydro power plants-1
TRANSCRIPT
-
8/10/2019 Hydro Power Plants-1
1/73
Hydro power plants
-
8/10/2019 Hydro Power Plants-1
2/73
Hydro power plants
Tail water
Draft tube gate
Draft tube
Turbine
Main valve
Penstock
Air inlet
Inlet gate
Surge shaft
TunnelSand trap
Trash rack
Self closing valve
-
8/10/2019 Hydro Power Plants-1
3/73
The principle the water conduits of
a traditional high head power plant
-
8/10/2019 Hydro Power Plants-1
4/73
Ulla- Frre
Original figur ved Statkraft Vestlandsverkene
-
8/10/2019 Hydro Power Plants-1
5/73
Intake gate
Intake trashrack
Headrace tunnel
Anchor block
Surge tank
Penstock inlet
Valve
Tunnel Inlettrashrack
Tunnel Inlet
Anchor block
Exp. joint
Shaddle
Power house
TailraceIV G
SC
DTR
DT end gate
Desilting basin
gate hoist
IV -inlet valveR -turbine runnerSC -spiral caseG -generator
Typical Power House with Francis Turbine
-
8/10/2019 Hydro Power Plants-1
6/73
Arrangement of a small
hydropower plant
-
8/10/2019 Hydro Power Plants-1
7/73
H = 39 mQ = 513 m3/sP = 182 MW
Drunner=7,5 m
Ligga Power Plant, Norrbotten, Sweden
-
8/10/2019 Hydro Power Plants-1
8/73
Borcha Power Plant, Turkey
H = 87,5 mP = 150 MW
Drunner=5,5 m
-
8/10/2019 Hydro Power Plants-1
9/73
Water in take
Dam
Coarse trash rack
Intake gate
Sediment settling basement
-
8/10/2019 Hydro Power Plants-1
10/73
Dams
Rockfill dams
Pilar og platedammer
Hvelvdammer
-
8/10/2019 Hydro Power Plants-1
11/73
Rock-fill dams
1. Core Moraine, crushed soft rock, concrete, asphalt
2. Filter zone Sandy gravel
3. Transition zone Fine blasted rock
4. Supporting shell Blasted rock
-
8/10/2019 Hydro Power Plants-1
12/73
Slab concrete dam
-
8/10/2019 Hydro Power Plants-1
13/73
Arc dam
-
8/10/2019 Hydro Power Plants-1
14/73
Gates in Hydro Power Plants
-
8/10/2019 Hydro Power Plants-1
15/73
Types of Gates
Radial Gates
Wheel Gates
Slide Gates
Flap Gates
Rubber Gates
-
8/10/2019 Hydro Power Plants-1
16/73
Radial Gates at lvkarleby, Sweden
-
8/10/2019 Hydro Power Plants-1
17/73
Radial Gate
The forces actingon the arc will betransferred to thebearing
-
8/10/2019 Hydro Power Plants-1
18/73
Slide Gate
Jhimruk Power Plant, Nepal
-
8/10/2019 Hydro Power Plants-1
19/73
Flap Gate
-
8/10/2019 Hydro Power Plants-1
20/73
Rubber gate
Reinforced rubberOpen position
Flow disturbance
Reinforced rubberClosed positionBracket
Air inlet
-
8/10/2019 Hydro Power Plants-1
21/73
Circular gate
ManholeHinge
Ladder
RibsPipe
End cover
Bolt
Fastening element
FrameSeal
-
8/10/2019 Hydro Power Plants-1
22/73
Circular gate
Jhimruk Power Plant, Nepal
-
8/10/2019 Hydro Power Plants-1
23/73
Trash Racks
Panauti Power Plant, Nepal
-
8/10/2019 Hydro Power Plants-1
24/73
Theun Hinboun Power PlantLaos
-
8/10/2019 Hydro Power Plants-1
25/73
GravfossPower Plant
Norway
Trash Rack size:
Width: 12 meter
Height: 13 meter
Stainless Steel
-
8/10/2019 Hydro Power Plants-1
26/73
CompRackTrash Rack delivered
by VA-Tech
-
8/10/2019 Hydro Power Plants-1
27/73
Cleaning the trash rack
-
8/10/2019 Hydro Power Plants-1
28/73
Pipes
Materials Calculation of the change of length due to the
change of the temperature
Calculation of the head loss
Calculation of maximum pressure
Static pressure
Water hammer
Calculation of the pipe thickness
Calculation of the economical correct diameter
Calculation of the forces acting on the anchors
-
8/10/2019 Hydro Power Plants-1
29/73
Materials
Steel
Polyethylene, PE
Glass-fibre reinforced UnsaturatedPolyesterplastic , GUP
Wood
Concrete
-
8/10/2019 Hydro Power Plants-1
30/73
MaterialsMaterial Max.
Diameter
Max.
Pressure
Max.
Stresses[m] [m] [MPa]
Steel, St.37 150
Steel, St.42 190
Steel, St.52 206
PE ~ 1,0 160 5
GUP 2,4Max. p = 160 m.
320Max. D: 1,4 m.
Wood ~5 80
Concrete ~5 ~ 400
St l i i t k
-
8/10/2019 Hydro Power Plants-1
31/73
Steel pipes in penstockNore Power Plant, Norway
-
8/10/2019 Hydro Power Plants-1
32/73
GUP-PipeRaubergfossen Power Plant, Norway
-
8/10/2019 Hydro Power Plants-1
33/73
Wood Pipes
Breivikbotn Power Plant, Norway vre Porsa Power Plant, Norway
-
8/10/2019 Hydro Power Plants-1
34/73
Calculation of the change of length
due to the change of the temperature
LTL Where:
L = Change of length [m]
L = Length [m]
= Coefficient of thermal expansion [m/oC m]T = Change of temperature [oC]
-
8/10/2019 Hydro Power Plants-1
35/73
Calculation of the head loss
g2c
DLfh
2
f
Where:hf = Head loss [m]
f = Friction factor [ - ]
L = Length of pipe [m]
D = Diameter of the pipe [m]
c = Water velocity [m/s]
g = Gravity [m/s2]
-
8/10/2019 Hydro Power Plants-1
36/73
-
8/10/2019 Hydro Power Plants-1
37/73
ExampleCalculation of the head loss
DcRe
Power Plant data:H = 100 m Head
Q = 10 m3/s Flow Rate
L = 1000 m Length of pipe
D = 2,0 m Diameter of the pipe
The pipe material is steel
Where:
c = 3,2 m/s Water velocity
n = 1,30810-6 m2/s Kinetic viscosity
Re = 4,9 106 Reynolds number
g2
c
D
Lfh
2
f
-
8/10/2019 Hydro Power Plants-1
38/73
0,013
Where:
Re = 4,9 106 Reynolds number
e = 0,045 mm Roughness
D = 2,0 m Diameter of the pipe
e/D = 2,25 10-5 Relative roughness
f = 0,013 Friction factor
The pipe material is steel
-
8/10/2019 Hydro Power Plants-1
39/73
ExampleCalculation of the head loss
Power Plant data:H = 100 m Head
Q = 10 m3/s Flow Rate
L = 1000 m Length of pipe
D = 2,0 m Diameter of the pipe
The pipe material is steel
Where:
f = 0,013 Friction factor
c = 3,2 m/s Water velocity
g = 9,82 m/s2 Gravity
m4,382,92
2,3
2
1000013,0
g2
c
D
Lfh
22
f
-
8/10/2019 Hydro Power Plants-1
40/73
Calculation of maximum pressure
Static head, Hgr (Gross Head)
Water hammer, hwh Deflection between pipe supports
Friction in the axial direction
Hgr
-
8/10/2019 Hydro Power Plants-1
41/73
Maximum pressure rise due to the
Water Hammer
g
cah maxwh
hwh = Pressure rise due to water hammer [mWC]
a = Speed of sound in the penstock [m/s]cmax = maximum velocity [m/s]
g = gravity [m/s2]
Jowkowsky
a
L2TIF C
E ample
-
8/10/2019 Hydro Power Plants-1
42/73
Example
Jowkowsky
m1020gcah maxwh
a = 1000 [m/s]cmax = 10 [m/s]
g = 9,81 [m/s2]
a
L2TC
-
8/10/2019 Hydro Power Plants-1
43/73
Maximum pressure rise due to the
Water Hammer
C
max
C
maxwh
Tg
L2c
T
aL2
g
cah
Where:hwh = Pressure rise due to water hammer [mWC]
a = Speed of sound in the penstock [m/s]cmax = maximum velocity [m/s]
g = gravity [m/s2]
L = Length [m]
TC = Time to close the main valve or guide vanes [s]
a
L2TIF C
-
8/10/2019 Hydro Power Plants-1
44/73
Example
m61
Tg
L2ch
C
maxwh
L = 300 [m]
TC = 10 [s]cmax = 10 [m/s]
g = 9,81 [m/s2]
-
8/10/2019 Hydro Power Plants-1
45/73
Calculation of the pipe thickness
t
Crp
tL2CpDL
sit
tsi
whgr hHgp
Where:
L = Length of the pipe [m]
Di = Inner diameter of the pipe [m]p = Pressure inside the pipe [Pa]
t = Stresses in the pipe material [Pa]
t = Thickness of the pipe [m]
Cs = Coefficient of safety [ - ]
= Density of the water [kg/m3]
Hgr = Gross Head [m]
hwh = Pressure rise due to water hammer [m]
p
t t
Based on: Material properties
Pressure from:
Water hammer
Static head
Example
-
8/10/2019 Hydro Power Plants-1
46/73
ExampleCalculation of the pipe thickness
m009,0Crp
t
tL2CpDL
t
si
tsi
MPa57,1hHgp whgr
Where:
L = 0,001 m Length of the pipeDi = 2,0 m Inner diameter of the pipe
t = 206 MPa Stresses in the pipe material
= 1000 kg/m3 Density of the water
Cs = 1,2 Coefficient of safetyHgr = 100 m Gross Head
hwh = 61 m Pressure rise due to water hammer
p
t t
Based on: Material properties
Pressure from:
Water hammer
Static head
C l l ti f th i l
-
8/10/2019 Hydro Power Plants-1
47/73
Calculation of the economical
correct diameter of the pipe
Diameter [m]
Cost[$]
0
dD
KKd
dD
dK tftot
Example
-
8/10/2019 Hydro Power Plants-1
48/73
ExampleCalculation of the economical correct diameter of the pipe
Hydraulic Losses
Where:
PLoss= Loss of power due to the head loss [W]
= Density of the water [kg/m3]
g = gravity [m/s2]
Q = Flow rate [m3/s]
hf = Head loss [m]
f = Friction factor [ - ]
L = Length of pipe [m]
r = Radius of the pipe [m]C2 = Calculation coefficient
5
2
42
2
fLossrC
rg2Q
r2LfQghQgP
Power Plant data:
H = 100 m Head
Q = 10 m3/s Flow Rate
hplant = 85 % Plant efficiency
L = 1000 m Length of pipe
Example
-
8/10/2019 Hydro Power Plants-1
49/73
ExampleCalculation of the economical correct diameter of the pipe
Cost of the Hydraulic Losses per year
Where:
Kf = Cost for the hydraulic losses []
PLoss = Loss of power due to the head loss [W]
T = Energy production time [h/year]
kWhprice= Energy price [/kWh]
r = Radius of the pipe [m]C2 = Calculation coefficient
price5
2priceLossf kWhT
r
CkWhTPK
Example
-
8/10/2019 Hydro Power Plants-1
50/73
ExampleCalculation of the economical correct diameter of the pipe
Present value of the Hydraulic Losses per year
price5
2f kWhT
r
CK
Where:
Kf = Cost for the hydraulic losses []
T = Energy production time [h/year]kWhprice= Energy price [/kWh]
r = Radius of the pipe [m]
C2 = Calculation coefficient
Present value for 20 year of operation:
n
1ii
fpvf
I1
KK
Where:
Kf pv = Present value of the hydraulic losses []
n = Lifetime, (Number of year ) [-]I = Interest rate -
Example
-
8/10/2019 Hydro Power Plants-1
51/73
ExampleCalculation of the economical correct diameter of the pipe
Cost for the Pipe Material
2
1mmm rCLrp
r2Ltr2Vm
Where:
m = Mass of the pipe [kg]
m = Density of the material [kg/m3]
V = Volume of material [m3]
r = Radius of pipe [m]
L = Length of pipe [m]
p = Pressure in the pipe [MPa]
= Maximum stress [MPa]
C1 = Calculation coefficient
Kt = Installation costs []
M = Cost for the material [
/kg]
2
1t rCMmMK
NB:
This is a simplification
because no other
component then the pipeis calculated
-
8/10/2019 Hydro Power Plants-1
52/73
ExampleCalculation of the economical correct diameter of the pipe
Installation Costs:
Pipes
Maintenance
Interests
Etc.
-
8/10/2019 Hydro Power Plants-1
53/73
ExampleCalculation of the economical correct diameter of the pipe
2
1t rCMK
Where:
Kf = Cost for the hydraulic losses []
Kt = Installation costs []
T = Energy production time [h/year]
kWhprice= Energy price [/kWh]
r = Radius of the pipe [m]
C1 = Calculation coefficient
C2 = Calculation coefficient
M = Cost for the material [/kg]
n = Lifetime, (Number of year ) [-]I = Interest rate [-]
n
1ii
price5
2
pvfI1
kWhTrC
K
0I1
kWhTC
r5rCM2
drKKd
n
1ii
price26
ft
-
8/10/2019 Hydro Power Plants-1
54/73
ExampleCalculation of the economical correct diameter of the pipe
7
n
1i
i
price2
n
1ii
price2
6
ft
I1CM
kWhTC
2
5r
0I1
kWhTC
r
5rCM2
dr
KKd
C l l ti f th f ti
-
8/10/2019 Hydro Power Plants-1
55/73
Calculation of the forces acting on
the anchors
C l l ti f th f ti
-
8/10/2019 Hydro Power Plants-1
56/73
Calculation of the forces acting on
the anchorsF5
F4F3
F1
F2
F
F1= Force due to the water pressure [N]
F2= Force due to the water pressure [N]
F3= Friction force due to the pillars upstream the anchor [N]
F4= Friction force due to the expansion joint upstream the anchor [N]
F5= Friction force due to the expansion joint downstream the anchor [N]
Calculation of the forces acting on
-
8/10/2019 Hydro Power Plants-1
57/73
Calculation of the forces acting on
the anchors
G
F
R
-
8/10/2019 Hydro Power Plants-1
58/73
Valves
-
8/10/2019 Hydro Power Plants-1
59/73
Principle drawings of valves
Open positionClosed position
Spherical valve Gate valve
Hollow-jet valve Butterfly valve
Spherical valve
-
8/10/2019 Hydro Power Plants-1
60/73
Spherical valve
B
-
8/10/2019 Hydro Power Plants-1
61/73
Bypass system
-
8/10/2019 Hydro Power Plants-1
62/73
Butterfly valve
B tt fl
-
8/10/2019 Hydro Power Plants-1
63/73
Butterfly
valve
Butterfly valve
-
8/10/2019 Hydro Power Plants-1
64/73
Butterfly valve
disk types
Hollow jet Valve
-
8/10/2019 Hydro Power Plants-1
65/73
Hollow-jet Valve
-
8/10/2019 Hydro Power Plants-1
66/73
Pelton turbines
Large heads (from
100 meter to 1800
meter)
Relatively small flowrate
Maximum of 6
nozzles
Good efficiency over
a vide range
Jostedal,Norway
-
8/10/2019 Hydro Power Plants-1
67/73
Kvrner
, y
F i t bi
-
8/10/2019 Hydro Power Plants-1
68/73
Francis turbines
Heads between 15and 700 meter
Medium Flow Rates
Good efficiencyh=0.96 for modern
machines
-
8/10/2019 Hydro Power Plants-1
69/73
SVARTISEN
-
8/10/2019 Hydro Power Plants-1
70/73
-
8/10/2019 Hydro Power Plants-1
71/73
-
8/10/2019 Hydro Power Plants-1
72/73
Kaplan turbines
Low head (from 70
meter and down to 5
meter) Large flow rates
The runner vanes can
be governed
Good efficiency over
a vide range
-
8/10/2019 Hydro Power Plants-1
73/73