hydraulic design - scan doc.docx

Upload: cjayamangala

Post on 04-Jun-2018

237 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    1/36

    3.4.2 Hydraulic Design

    Once the peak flows were estimated, the drain conveyance capacities were determined through a

    hydraulic design. Manning's formula and continuity equation was used for various trial sections to

    obtain the optimum slope and the section of the drain. The dimensions were practically fixed to

    suit the site conditions.

    The formulas are given as follows:

    Continuity equation: Q* = A.V Where A = Cross sectional area of flow m

    Q'= Actual Discharge (cumecs) V

    = Velocity of Flow (mis)

    Manning's Equation: V

    =

    Where R = Hydraulic Mean Depth

    (m) V= Flow velocity m/s S =

    Channel slope

    Where A= Cross sectional area of flow m

    P = Wetted perimeter (m)

    Culvert channel designs were performed by selecting trial sections assuming a free board of

    0.5m and calculating the actual discharge Q' and comparing it with the peak flow Q obtained

    in the hydrologic design. For a satisfactory performance of the culvert Q' > Q i.e. the drain

    should have a capacity to carry a flow equal or more than the peak flow also the velocity of

    the flow should preferably less than 2.0 m/sec.

    3.4.3 Use of "Flow Master "and "Culvert Master" Software

    For the opening size computation "Flow Master "and "Culvert Master" software were also

    employed.

    3.4.4 Specimen calculations

    Manual calculation and software calculation for Culvrt at chainage 27+308 km are given below Culvrt at

    chainage 27+308 km was located at U/S of tributary of Maha oya.

    Existing Slope of the stream Highway crossing chainage at 27+308 km

    n

    R= A

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    2/36

    Total catchment

    Length of the longest watercourse

    Existing slope of the catchment

    Corresponding velocity of catchment

    (According to table 3.1)

    Time of concentration

    (Ponrajah's Formula)

    Return period

    Rainfall intensity

    (By Ranathunga's formula)

    = 50 Years

    I = 7895 (T+49.4) --8BB1

    = 127.54 mm/hr

    Corresponding Run off coefficient = 0.40

    (Reffering Ponrajah's table and "Applied Hydrology by Ven Te Chow")

    Q=CIA/360

    Q=8.13m3/s

    Assuming 1m water depth according to site condition,

    Using Maning's Formula Design section can be calculated.

    Full suply depth (FSD) =1 m

    Design discharge (Q) =8.13 m3/s

    Design s!ope(S) such that velocity along

    Cuvert less than 2.0m/sec =0.001

    Manning's formla corresponding to concrete (n) =0.013

    Q = 1R2/3S1/2A

    = 1A5/3

    S1/2

    \ A2/3

    n

    v> Q = 1fBWxFSDf/3S1/2

    1' (BW+2FSD)2/3n

    Solving above equation, BW,= 4.31m

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    3/36

    Taking BW = 4.5m

    Taking Free board as 0.5m, Design section = 4,5m x 1.5m

    Qmax for design section = 8.57 m3/s

    Qdesign =8.13m3/s

    Hence design section is ok for maximum discharge for 50 years return period.

    Specimen calculation for design section of culvert is same as Design section of Bridge,

    BW Calculation for 27+308 Culvert Worksheet for Rectangular Channel

    Project Description

    Project File c:\haestad\academic\fmw\ckah cor.fm2

    Worksheet 27+308

    Flow Element Rectangular Channel

    Method Manning's Formula

    Solve For Channel Depth

    input Data

    Mannings Coefficient 0.01 3

    Channel Slope 0.001 000 m/m

    Bottom Width 4.31 m

    Discharge 8.13 m /s

    Results

    Depth 1.00 m

    Flow Area 4.31 m2

    Wetted Perimeter 6.31 m

    Top Width 4.31 m

    Critical Depth 0.71 m

    Critical Slope 0.002716 m/m

    Velocity 1.89 ' m/s

    Velocity Head 0.18 m

    Specific Energy 1.18 m '*

    Froude Number 0.60 ^ "

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    4/36

    Flow is subcritical.

    4.0Drainage Opening Sizes for Culverts and Bridges and Recommended High Flood Level

    4.1 Drainage Opening Sizes for Culverts and Bridges along the Expressway

    Drainage opening sizes for culverts and bridges were decided using Rational Formula and Manning's Formula

    assuming a critical water depth required to pass a 50 years flood. The required opening sizes are given in

    Table 4.1 and the relevant hydrologic and hydraulic calculations are given in Annex (B.1) Table 4,1 -

    Recommended Drainage Opening sizes for Culverts and Bridges along the Expressway

    Culvert

    no.

    Culvert ID

    (Chainage)

    Design size Invert up

    stream (m

    MSL)

    Invert down

    stream (m

    MSL)

    Approxima

    te Length

    (m)

    Remarks

    79 25+245 10.00mx2.00m 24.00 23.97 41.3

    80 25+367 1.50mx1.50m 25.02 24.95 34.9

    81 25+565 6.25mx1.50m 25.11 25.07 35.8

    82 25+947 6.50mx1.50m 27.62 27.57 43.9

    83 26+180 2.00mx1.50m 28.10 28.05 45.2

    84 26+550 3.00mx1.50m 34.60 34.55 48.085 27+308 4.50mx1.50m 35.20 35.13 68.2

    86 27+481 1.50mx1.50m 35.00 34.95 50.0

    87 27+948 4.00mx1.50m 32.58 32.54 39.8

    88 28+400 I.75mx1.50m 33.12 33.05 60.7

    89 28+500 1.75mx1.50m 33:50 33.43 61.5

    90 28+885 2.25mx1.50m 36.50 36.44 36.9

    91 29+520 4.25mx1.50m 37.04 36.97 69.1

    92 30+036 2.50mx1.50m 38.12 38.05 41.2

    93 30+330 2.50mx1.50m 44.09 44.01 47.0,

    94 31+156 3.50mx1.50m 35.52 35.45 62.6

    95 31+240 3.50mx1.50m 35.50 35.43 68.8

    96 31+923 1.50mx1.50m 35.07 35.05 43.6

    97 32+000 3. 25m x1. 50m 34.60 34.58 36.0

    98 32+088 1.50mx1.50m 34.60 34.58 43.0

    99 32+235 1.75mx1.50m 36.02 36.00 46.4

    100 32+665 10.00mx2.00m 37.02 36.98 70.3

    101 32+985 8.50mx2.00m 36.32 36.29 42.0

    102 33+390 1.50mx1.50m 39.10 39.03 44.5

    103 33+500 1.50mx1.50m 42.58 42.51 41.3

    104 33+858 2.75mx1.50m 42.07 42.05 33.0

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    5/36

    105 33+936 6.75mx1.50m 41.13 41.11 37.1

    106 34+913 3.50mx2.50m 48.69 48.63 54.2 Dual Purpose

    107 35+358 4.25mx1.50m 36.03 35.99 46.7

    108 35+410 4.50mx1.50m35.80 35.76 45.6

    109 35+460 4.25mx1.50m 35.90 35.86 44.2

    Culvert

    no.

    Culvert ID

    (Chainage)

    Design size Invert up

    stream (m

    MSL)

    Invert down

    stream (m

    MSL)

    Approxima

    te

    Length(m)

    Remarks

    110 35+615 4.00mx1.50m 36.02 35.98 39.4

    111 35+730 4.00mx1.50m 36.50 36.45 43.2

    112 36+323 2.25mx1.50m 38.94 38.89 43.4

    113 36+385 2.25mx1.5Qm 38.14 37.97 57.5

    4 36+555 85m opening should be provided for Meerigama-Pasyala Rd and Railway Track

    114 36+608 1 .50mx1 .50m 40.36 40.25 111.0

    115 36+853 1 .50mx1 .50m 50.28 50.21 74.0

    116 37+250 2.00mx1.50m 66.69 66.64 49.5

    117 37+522 4.25mx1 .50m 58.65 58.59 57.6

    118 37+893 9.00mx1.50m 48.45 48.37 88.6

    119 38+001 9.00mx1.50m 48.45 48.39 62.7

    120 38+400 2.00mx1.50m 58.94 58.89 46.5

    121 38+676 3.25mx1.50m 59.51 59.46 57.2

    122 38+943 3.00mx1.50m 64.30 64.26 39.7

    123 39+195 3.75mx1.50m 53.46 53.39 72.4

    124 40+065 i r-2.50mx1.50m 91.38 91.31 74.3125 40+630 3.50mx1.50m 76.70 76.66 35.6

    126 40+815 3.50mx1.50m 57.98 57.92 59.2

    127 40+900 1 .75mx1 .50m 54.90 54.82 70.9

    128 41+070 2.00mx1.50m 57.75 57.71 44.8

    129 41+445 13.50mx2.00m 51.28 51.26 51.4

    130 41+565 20.00mx2.00m 48.86 48.83 68.6

    131 41+930 3.75mx1.50m 66.16. 65.91 84.5

    132 42+580 3.50mx1 .50m 103.84 103.78 54.2

    133 42+925 3.00mx1.50m 91.76 91.71 51.9

    134 43+545 9.00mx1.50m 56.52 56.47 67.8

    135 43+840 3.25mx1 .50m 53.21 53.17 48.2 '

    136 43+980 2.25mx1.50m 55.45 55.39 52.1

    137 44+120 2.75mx1.50m 56.13 56.08 53.9

    138 44+250 4.25mx1.50m 51.85 51.79 70.3

    139 44+490 1 .50mx1 .50m 54.07 54.01 55.4

    140 44+673 2.00mx1.50m 56.01 55.95 62.4

    141 45+135 2.00mx1.50m 84.01 83.95 57.2

    142 45+666 1 .50mx1 .50m 80.76 80.66 95.3

    143 46+032 1.75mx1.50m 83.95 83.86 85.9

    144 46+476 2.00mx1.50m 83.63 83.55 81.9

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    6/36

    145 46+892 1 .50mx1 .50m 67.70 67.45 82.7

    146 47+451 9.00mx1.50m 56.82 56.75 62.0

    147 47+557 7.00mx1.50m 56.61 56.55 69.7

    148 47+928 4.50mx1 .50m 66.68 66.61 57.9

    5 48+174 32.00mx4.50m 49.84 49.64 103.0

    Note: Design sizes up to Culvert No.78 has submitted to RDA in CKAH chainage from 0+000 km to 25+000 km

    4.2 Recommended High Flood Level along the Expressway

    The recommended High Flood Level for design purposes of the expressway are given below

    Table 4.2-Recommmended High Flood Levels of the Culverts across the Expressway

    Culvert ID

    (Chainage)

    Size of Proposed

    Structure

    Existing Level

    (m MSL)

    Full Suplly Depth

    (m)

    Recommended

    Flood Level (m

    MSL)

    25+245 10.00mx2.00m 24.00 1.50 25.50

    25+367 1.50mx1.50m 25.02 1.00 26.02

    25+565 6.25mx1.50m 25.11 1.00 26.11

    25+947 6.50mx1.50m 27.62 1.00 28.62

    26+180 2.00mx1.50m 28.10 1.00 29.10

    26+550 3.00mx1.50m 34.60 1.00 35.60

    27+308 4.50mx1.50m 35.20 1.00 36.20

    27+481 1.50mx1.50m 35.00 1.00 36.00

    27+948 4.00mx1.50m 32.58 1.00 33.58

    28+400 1.75mx1.50m 33.12 1.00 34.12

    28+500 1.75mx1.50m 33.50 1.00 34.5028+885 2.25mx1 .50m 36.50 1.00 37.50

    29+520 4.25mx1.50m 37.04 1.00 38.04

    30+036 2.50mx1.50m 38.12 1.00 39.12

    30+330 2.50mx1.50m 44.09 1.00 45.09

    31+156 3.50mx1.50m 35.52 1.00 36.52

    31+240 3.50mx1.50mv 35.50 1.00 36.50

    31+923 1.50mx1.50m 35.07 1.00 36.07

    32+000 3.25mx1.50m 34.60 1.00 35.60

    32+088 1.50mx1.50m 34.60 1.00 35.60

    32+235 1.75mx1.50m 36.02 1.00 37.02

    32+665 10.00mx2.00m 37.02 1.50 38.52

    32+985 8.50mx2.00m 36.32 1.50 37.82

    33+390 1.50mx1.50m 39.10 1.00 40.10

    33+500 1.50mx1.50m 42.58 1.00 43.58

    33+858 2.75mx1 .50m 42.07 1.00 43.07

    33+936 6.75mx1.50m 41.13 1.00 42.13

    34+913 3.50mx2.50m 48.69 1.00 49.69

    35+358 4.25mx1.50m 36.03 1.00 37.03

    35+410 4.50mx1.50m 35.80 1.00 36.80

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    7/36

    35+460 4.25mx1.50m 35.90 1.00 36.90

    35+615 4.00mx1.50m 36.02 1.00 37.02

    Culvert ID

    (Chainage)

    Size of Proposed

    Structure

    Existing Level

    (m MSL)

    Full Suplly

    Depth (m)

    Recommended

    Flood Level (mMSL)

    35+730 4.00mx1.50m 36.50 1.00 37.50

    36+323 2.25mx1.50m 38.94 1.00 39.94

    36+385 2.25mx1.50m 38.14 1.00 39.14

    36+555 85m opening should be provided for Meerigama-Pasyala Rd and Railway Track

    36+608 1.50mx1.50m 40.36 1.00 41.36

    36+853 1.50mx1.50m 50.28 1.00 51.28

    37+250 2.00mx1.50m 66.69 1.00 67.69

    37+522 4.25mx1.50m 58.65 1.00 59.65

    37+893 9.00mx1.50m 48.45 1.00 49.45

    38+001 9.00mx1.50m 48.45 1.00 49.45

    38+400 2.00mx1.50m 58.94 1.00 59.94

    38+676 3.25mx1.50m 59.51 1.00 60.51

    38+943 3.00mx1.50m 64.30 1.00 65.30

    39+195 3.75mx1.50m 53.46 1.00 54.46

    40+065 2.50mx1.50m 91.38 1.00 92.38

    40+630 3.50mx1.50m 76.70 1.00 77.70

    40+815 3.50mx1.50m 57.98 1.00 58.98

    40+900 1.75mx1.50m 54.90 1.00 55.90

    41+070 2.00mx1.50m 57.75 1.00 58.75

    41 +445 13.50mx2.00m 51.28 1.50 52.7841+565 20.00mx2.00m 48.86 1.50 50.36

    41+930 3.75mx1.50m "-66.16 1.00 67.16

    42+580 3.50mx1.50m * 103.84 1.00 104.84

    42+925 3.00mx1.50m 91.76 1.00 92.76

    43+545 9.00mx1.50m 56.52 1.00 57.52

    43+840 3.25mx1.50m 53.21 1.00 54.21

    43+980 2.25mx1.50m 55.45 1.00 56.45

    44+120 2.75mx1.50m 56.13 1.00 57.13

    44+250 4.25mx1.50m 51.85 1.00 52.85

    44+490 1.50mx1.50m 54.07 1.00 55.07

    44+673 2.00mx1.50m 56.01 1.00 57.01

    45+135 2.00mx1.50m 84.01 1.00 85.01

    45+666 1.50mx1.50m 80.76 1.00 81.76

    46+032 1.75mx1.50m 83.95 1.00 84.95

    46+476 2.00mx1.50m 83.63 1.00 84.63

    46+892 1.50mx1.50m 67.70 1.00 68.70

    47+451 9.00mx1.50m 56.82 1.00 57.82

    47+557 7.00mx1.50m 56.61 1.00 57.61

    47+928 4.50mx1.50m 66.68 1.00 67.68

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    8/36

    48+174 32.00mx4.50m 49.84 3.50 53.34

    4.3 Drainage Opening Sizes for Overpasses and Underpasses along the Expressway

    Drainage Opening size for overpasses and underpasses were also determined using the methods used to

    determine culvert openings. The required opening sizes are given in Table 4.3 and the relevant hydrologic and

    hydraulic calculations are given in Annex (B.2)

    Table 4.3 - Recommended Drainage Opening sizes for Overpasses and Underpasses

    Road ID Chainage Opening Size RemarksDivulapitiya-Naiwala Rd (RDA) 25+535 (LHS) 9.25mxl.50mDivulapitiya-Naiwala Rd (RDA) 25+535(RHS) l.OOmxl.SOm vMedagampitiya-Hanchapola Rd (PS) 26+394 (LHS) 2.50mxl.50mMedagampitiya-Hanchapola Rd (PS) 26+394(RHS) 4.25mxl.50m

    Banduragoda-Weyangoda Rd (PS) 27+451 (LHS) 6.00mxl.50m Should be provided to suit site conditionsBanduragoda-Weyangoda Rd (PS) 27+451 (RHS) l.SOmxl.SOm Should be provided to suit site conditionsRoad (PS) 27+980 (LHS) l.OOmxl.SOmRoad (PS) 27+980(RHS) 1.75mxl.50mBanduragoda-Weyangoda Rd (PS) 28+720 (LHS) l.OOmxl.SOm

    Banduragoda-Weyangoda Rd (PS) 28+720(RHS) l.OOmxl.SOm

    Road (PS) 29+210 (LHS) l.OOmxl.SOm

    Road (PS) 29+210(RHS) l.OOmxl.SOm

    Keppetiwalana-Baduragoda Rd (PS) 29+707 (LHS) l.OOmxl.SOmKeppetiwalana-Baduragoda Rd (PS) 29+707(RHS) l.OOmxl.SOm

    Gaspe Rd (RDA) 30+520 (LHS) l.OOmxl.SOmGaspe Rd (RDA) 30+520(RHS) 1.25mxl.50mRoad (PS) 31 +040 (LHS) l.OOmxl.SOmRoad (PS) 31+040(RHS1 l.OOmxl.SOmRoad (PS) 31 +395 (LHS) 1.25mxl.50m Should be provided to suit site conditionsRoad (PS) 31+395(RHS) 2.00mxl.50m Should be provided to suit site conditionsRoad (PS) 31+830 (LHS) 1.25mxl.50m

    Road (PS) 31+830(RHS) 1.25mxl.SOmRoad (PS) 32+839 (LHS) 6.25mxl,50m Should be provided to suit site conditionsRoad (PS) 32+839(RHS) 13.00mxl.50m Should be provided to suit site conditionsRoad (PS) 33+490 (LHS) l.OOmxl.SOm Should be provided to suit site conditionsRoad (PS) 33+490(RHS) l.SOmxl.SOm Should be provided to suit site conditionsMeerigama-Wewaldeniya Rd (PS) 37+579 (LHS) l.OOmxl.SOm Should be provided to suit site conditions

    Meerigama-Wewaldeniya Rd (PS) 37+579(RHS) l.OOmxl.SOm Should be provided to suit site conditionsMeerigama-Danovita Rd (PDA) 39+149 (LHS) l.OOmxl.SOm Should be provided to suit site conditionsMeerigama-Danovita Rd (PDA) 39+149(RHS) 1.25mxl,50m Should be provided to suit site conditionsKoshena-Soduruwatta Rd (PS) 40+510 (LHS) 2.25mxl.50mKoshena-Soduruwatta Rd (PS) 40+51 0(RHS) 1.75mxl.50m

    Diversion Rd (PS) 40+885 (LHS) l.SOmxl.SOm Should be provided to suit site conditionsDiversion Rd (PS) 40+885(RHS) 7.50mxl.50m Should be provided to suit site conditionsRoad (PS) 41 +085 (LHS) l.OOmxl.SOm

    Road (PS) 41+085(RHS) 1.75mxl.50m

    Road (RDA) 41+620 (LHS) 2.00mxl.50m Should be provided to suit site conditionsRoad (RDA) 41+620(RHS) 2.00mxl.50m Should be provided to suit site conditions

    Road (PS) 42+595 (LHS) l.OOmxl.SOm

    Road (PS) 42+595(RHS) l.OOmxl.SOm

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    9/36

    Diversion Rd (PS) 43+616 (LHS) 2.00mxl.50m Should be provided to suit site conditionsDiversion Rd (PS) 43+616(RHS) 7.00mxl.50m Should be provided to suit site conditionsRoad (PS) 44+228 (LHS) l.OOmxl.SOm Should be provided to suit site conditionsRoad (PS) 44+228(RHS) l.OOmxl.SOm Should be provided to suit site conditions

    Road ID Chainage Opening Size Remarks

    Diversion Rd (RDA) 44+444 (LHS) l.OOmxl.SOm Should be provided to suit site conditions

    Diversion Rd (RDA) 44+444(RHS) l.OOmxl.SOm Should be provided to suit site conditions

    Diversion Rd Meerigama (RDA) 45+1 54 (LHS) l.OOmxl.SOm Should be provided to suit site conditions

    Diversion Rd Meerigama (RDA) 45+1 54 (RHS) l.OOmxl.SOm Should be provided to suit site conditions

    Road (RDA) 45+464 (LHS) l.OOmxl.SOm

    Road (RDA) 45+464(RHS) l.OOmxl.SOm

    Diversion Rd (PS) 45+802 (LHS) l.OOmxl.SOm Should be provided to suit site conditions

    Diversion Rd (PS) 45+802(RHS) l.OOmxl.SOm Should be provided to suit site conditions

    Road (PS) 46+488 (LHS) 4.75mxl.50m Should be provided to suit site conditions

    Road (PS) 46+488(RHS) l.OOmxl.SOm Should be provided to suit site conditionsRoad (PS) 46+91 8 (LHS) l.OOmxl.SOm Should be provided to suit site conditions

    Road (PS) 46+91 8(RHS) l.OOmxl.SOm Should be provided to suit site conditions

    Diversion Rd (PS) 47+51 2 (LHS) l.OOmxl.SOm Should be provided to suit site conditions

    Diversion Rd (PS) 47+512(RHS) l.OOmxl.SOm Should be provided to suit site conditions

    Note : LHS and RHS are with reference to the direction of chainage increase

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    10/36

    5.0 Water Quality Monitoring Plan

    5.1 Scope of the Study

    The monitoring plan covers three phases of water quality situation in the project area. These are baseline

    (existing condition), construction phase and operational phases. The scope of this study/report is limited to

    surface water quality.

    5.2 Background

    Water pollution due to highway projects both during construction and operation are mostly a Non-Point

    Sources (NPS) Pollution issue caused by contaminated runoff. Point source pollution can also occur during the

    construction (Discharge of untreated effluent from Labor Camps, etc.) and in operation (Discharge from

    restaurants in rest areas, etc). Tackling point source pollution is relatively easy through enforcement of

    environmental protection regulations and provisions of environmenta! safeguards in the construction contracts.

    Non Point Source pollution on the other hand is difficult to address through such measures but needs

    qualitatively different approaches.

    The water quality assessments of highway projects have two basic objectives as described below.

    (a) Estimation of pollution loads or concentrations as a result of the said highway during construction and

    operation and thereby develop suitable impact mitigation measures;

    (b) Prepare an monitoring plan that will enable the authorities to determine whether the safeguards put in

    place are effective and thereby to help to meet the water quality objectives

    An important component of any water quality assessment of this nature is water quality monitoring. The

    monitoring program shall establish the baseline conditions, water quality during construction and operation.

    Water quality monitoring is an expensive exercise. Therefore one of the most important requirements of water

    quality monitoring is to determine a sampling program that would provide the required information at an

    acceptable cost. The sampling program shall cover the sampling locations, frequency (space-time framework

    of sampling plan) and water quality parameters. The choice of parameters is normally based on ambient water

    quality requirements. Cost is usually a factor that limits the type and number of parameters included in

    monitoring plans. Testing should be based on accepted standard procedures. Also

    sampling and testing should be carried out by experience technicians in accredited laboratories. This is

    important if the data are to be accepted in a court of law.

    5.3 Assessment of Project Area

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    11/36

    5.3.1 Field Assessment

    Water quality sampling plan needs identification of sampling locations. For this purpose a reconnaissance field

    visit was undertaken on 7th

    December and 14th

    December 2010 to identify the water-bodies located in the said

    stretch of the proposed expressway. This is basically a census of surface water-bodies that the proposed

    expressway cut across from Baduragoda to Abepussa Interchange. Table 5.1 provides the list of water-

    bodies (streams, canals, water pools/ponds and rivers) found in this stretch. The surface water-bodies

    identified are mainly the irrigation canals also functioning as part of the storm water drainage systems. Table

    5.1 depicts the usage of the water bodies observed during the field study [See the Notes at the bottom of

    Table 5.1]. Figure 5.1 Map shows locations and The GPS coordinates of the Location IDs defined in Table

    5.1 are provided in Table 5.2.

    Shallow wells are a common feature along the expressway trace. At several places wells were found next to

    streams/-canals with water overflowing from the mouth. These are public wells mainly used for bathing and

    washing. Wells located in home gardens are mainly for household consumption including drinking.

    Table 5.1-Surface Water-Bodies Located between Baduragoda - Ambepussa

    Location ID* Description Usage

    WQ1 Kuda Oya - major streamWashing/Bathing/ Storm water Drainage/

    (Note- Not withdrawn for water supply in

    the immediate downstream)

    WQ2 Small irrigation ditch cutting across DudlySenanayake Road Irrigation

    WQ3Small irrigation canal/ditch by the edge of the paddy filed cuttingaccress Devala Road

    Irrigation

    WQ4 Small stream which feeds a small pond used for bathing Bathing

    WQ5 Two small irrigation ditches Irrigation

    WQ6 Small irrigation canal Irrigation

    WQ7Irrigation canal with substantial flow going along the edge of the paddy

    field and parallel to the toe of the narrow lane

    Irrigation (Note: Other uses may be

    possible in the downstream)WQ8 Sizable irrigation canal flowing through paddy filed (Village

    Kebellawita)

    Irrigation (Note: Other uses may be

    possible in the downstream)WQ9 Wide irrigation canal with substantial flow Irrigation (Note: Other uses may be

    possible in the downstream)

    Location ID* Description Usage

    WQ10 Small irrigation ditch Irrigation

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    12/36

    WQ11Wide channel through paddy lands (in the vicinity of Rilagala); there

    was substantial flow

    Irrigation/ bathing/washing

    WQ12 Small irrigation stream through paddy fields Irrigation

    WQ13 Very small irrigation channel; very low flow; Latha Mawatha Irrigation

    WQ14 Large stream; substantial flow Irrigation/Bathing /Washing

    WQ15Set of small irrigation ditches

    Irrigation

    WQ16 Very small natural stream flowing through home gardens Drainage

    WQ17Sizable stream also serving as a important irrigation drainage canal;

    Stream cut across B1 7 road; there are other small irrigation ditches

    Irrigation/ Drainage/ Bathing/ Washing

    WQ18By the side of main road B17. Drainage channel; railway line is parallel

    to the road about 50 feet away

    Drainage

    WQ19 Small irrigation ditch by the side of the paddy filed fields Irrigation

    WQ20Small stream crossing the railway line and going through uncultivated

    paddy area

    Drainage

    WQ21 Two minor irrigation ditches Irrigation

    WQ22 Set of small irrigation canals crossing and going parallel to B26 road.These canals combine and convert to a sizable canal with significant

    flow

    Irrigation/ (Note: Other uses may be

    possible in the downstream)

    WQ23Two small irrigation canals flowing along the two edges of the paddy

    area; substantial flow

    Irrigation

    WQ24Two small irrigation canals flowing Tajong the two edges of the paddy

    area; ^ ,

    Irrigation

    WQ25Tank situated outside the road boundary but the spill channel of the

    tank is cut across by the proposed highway

    Bathi ng/Wash ing/I rrigation

    WQ26Wide irrigation channel going through a large paddy filed. Two other

    small irrigation ditches are flowing at the two edges of the

    paddy area

    Irrigation/ Drainage (Note: Other uses may

    be possible in the downstream)

    WQ27 Small irrigation channel flowing at the edge of the paddy land Irrigation

    WQ28 Two small irrigation ditches Irrigation

    WQ29 Very small irrigation ditch Irrigation

    WQ30 About 3 feet wide irrigation ditch running at the edge of the paddy filed

    and highland

    Irrigation/drainage

    WQ31 Small irrigation ditch Irrigation

    WQ32 Small irrigation ditch going at the edge of the paddy fields Irrigation

    WQ33Sizable irrigation canal partly lined and going through paddy lands Irrigation/washing

    Note 1: The descriptions under the "Usage" column are based on observations made during the

    reconnaissance filed visit. It is recommended that further investigations were made on ambient uses of

    major water-bodies and record the uses with more details for at least 1-2 kilometers downstream.

    Note 2: Identifications (ID) numbers of water bodies are given consecutively from the point first visited to the

    point last visited. First visited point is defined as WQ1.

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    13/36

    Note 3: Flow conditions of the streams, canals etc reflects the situation at the day of the inspection (wet

    weather with significant rainfall in the previous days).

    Note 4: Irrigation canals also acts as drainage canals in many cases

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    14/36

    Table 5.2- Water Quality Locations

    Location Longitude Latitude

    WQ1 80 12.451 7 14.669

    WQ2 80 12.246 7 14.496

    WQ3 8011.840 7 14.296WQ4 8011.674 7 14.247

    WQ5 8011.428 7 14.466

    WQ6 8011.348 7 14.720

    WQ7 8011.191 7 14.779

    WQ8 8011.094 7 14.879

    WQ9 8010.819 7 14.860

    WQ10 80 09.806 7 14.382

    WQ11 80 09.885 7 14.292

    WQ12 80 09.942 7 14.462

    WQ13 80 09.049 7 14.099

    WQ14 80 08.541 7 14.063

    WQ15 80 08.305 713.995

    WQ16 80 07.993 714.129

    WQ17 80 07.266 7 14.009

    WQ18 8007.117 7 14.007

    WQ19 80 07.224 7 14.029

    WQ20 80 06.842 7 14.590

    WQ21 80 06.569 7 14.484

    WQ22 80 05.798 7 14.294

    WQ23 8005.517 7 14.226

    WQ24 80 05.298 7 14.024

    WQ25 80 04.873 713.775

    WQ26 80 04.490 713.953

    WQ27 80 02.344 7 12.369

    WQ28 80 02.756 7 12.628

    WQ29 80 02.838 7 12.733

    WQ30 80 03.078 712.810

    WQ31 80 03.351 7 12.975

    WQ32 80.03.746 7 13.303

    WQ33 80 3.753 713.569

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    15/36

    5.3.2 Climatic Conditions

    Table 5.3 gives the average annual rainfall for calendar year at Abepussa and Henarathgoda

    (Gampaha).

    Table 5.3 - Average Annual Rainfall in Millimeters

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual

    Abepuss ' 50.4 78.1 165.8 271.6 248.2 200.2 126.3 120.7 209.7 399.8 314.5 122.4 2307.7

    Henarathgoda 63.8 79.0 141.4 241.0 382.1 231.3 138.3 145.2 250.1 346.1 298.9 159.5 2476.7

    It is assumed the rainfall quantities and pattern for Abepussa and Henarathgoda (Gampaha) gauging stationsrepresent the situation for the project area. The key observations of rainfall pattern are:

    a. January and February are the driest months and the sizable rainfall is commencing at

    end of March. March and April represent the first inter-monsoon period, b. May records significant

    rainfall and May to September is the South-West Monsoon

    period. Flooding is common in this month, c. October and November together records the heaviest

    rainfall period and these two

    months represent the second inter-monsoon period. Flooding is common in this period, d. December

    to February represent the North-East Monsoon Period.

    5.4 Ambient Water Quality Requirements

    The best yardstick for evaluating freshwater quality in this case is the ambient water quality requirements for

    satisfying various water uses. Table 5.4 reports the water quality criteria for freshwater systems for different

    categories of water uses (Central Environmental Authority, 2003). Accordingly there are seven categories of

    water uses falling into three classes as given below. Table 5.4 provides the acceptable concentration levels

    for some selected parameters for different ambient uses of water. Full details of acceptable parameter levels,

    including for heavy metals are available in the CEA publications.

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    16/36

    Categories of Water Uses

    Nature conservation

    Drinking with simple treatment

    Bathing and recreation

    Fish and aquatic life

    Drinking with conventional treatment

    Irrigation and agriculture

    Minimum quality (other uses)

    As water uses for water-bodies are identified (Table 5.1), it is possible to determine the

    important water quality parameters and minimum water quality requirements for each water-

    body using the published data. Although not required in this case other additional parameters

    can be added to evaluate the long-term impacts such as eutrophication.

    Table 5.4 - Ambient Water Quality Requirement for Water Use Categories

    Water Use

    Category

    PH Con. Turb DO COD P F SAR SO4 Cl

    High]

    1

    2 6.0 8.5 5 *6 15 0.7 1.5 250 200

    3 6.0 9.0 5 20 0.7

    4 6,0 8.5 3 15 0.4

    5 6,0 9.0 4 30 0.7 1.5 250 200

    6 6.0 8.5 700 3 0.7 6-15

    Note 1: Con-Conductivity (ds/m); Turb -Turbidity (NTU); pH, SAR -Numerical values; others -

    ppm Note 2: Requirements for nature conservation to be determined on case by case basis

    Note 3; Refer to CEA publications for concentration limits for other parameters including heavy metals

    ass

    ass I

    ass II

    ass II

    ass II

    ass II

    ass II

    ass III

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    17/36

    5.5 Sampling Plan

    5.5.1 Construction Phase

    5.5.1.1 Nature of Construction Phase

    Among the contributory factors for deterioration of water quality during road construction are:

    (a) soil loss causing high sediment loads in runoff which also cause sedimentation in streams

    and rivers, soil/sediment can also carry other pollutants to the water column; (b) biological

    pollution due to damaged drainage

    Pipes, septic tanks, uncontrolled discharge of wastewater generated in labour camps, etc;

    and (c) spills of chemicals. During construction increased turbidity, color, suspended solids

    are difficult to avoid water quality problems. Chemical pollution commonly includes petroleum

    products.

    The magnitude of impacts of these pollutants on water-bodies is dissimilar and depends on

    ambient uses. In the project area there are no ecologically sensitive water-bodies requiring

    application of conservation measures. As such in this case the water-bodies which are used

    for water supply, bathing, and recreation are the most critical in terms of water quality. The

    main water-body in this section is the Kuda Oya. Although water supply intakes are notpresent in Kuda Oya in the immediate downstrearn. from the point of intersection with the

    proposed expressway, it is possible for such intakes in this water-body considering its size.

    Most of the other water-bodies identified in Table 5.1 are irrigation/drainage canals. Thus

    water quality standards applicable to these water-bodies are significantly less.

    The other characteristic of the construction phase is that the wide spread nature of activities,

    so that water quality deterioration is reflected across the area under construction. However,

    problem could be more acute in certain areas where activities such as bridge construction are

    taking place. Similarly high biological pollution could be possible down streams of labour

    camps, if located close to waterways. [Note: Special areas such as borrow sites and mining

    sites are not included in this study].

    5.5.1.2 Special Issues (Bentonite Loss)

    Bentonite clays are heavily used in Southern Expressway Project for pile driving work. While

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    18/36

    bulk of the betonite is recovered and reused small percentage is always get to the environment

    and washed away to natural water courses during rains. Therefore the impact of bentonite on

    water quality is of special interest.

    Bentonite is basically clay consisting mostly of montmorillonite. It has large water absorbing

    capacity thus can convert to viscous liquid which is used in drilling and pilling work in

    construction engineering. Bentonite is normally refered by dominant cation such as Calcium,

    Sodium, Aluminum, or Potassium. Calcium bentonite has ion exchange characteristics. It can

    exchange its Calcium Ion to other irons. Thus theoretically a water quality change takes

    place. However, this is absolutely negligible in terms of quantities of runoff water. The other

    issue is not so much of water quality but settling of bentonite slurry in small irrigation canals,

    waterways and even on access roads. It is heavy and when mixed with water acts as a jelly.

    Thus it can settle on the drainage paths within short distance. This is unlikely to cause an

    impact unless large quantities are lost inadvertently cause drainage paths to be blocked or

    roads surfaces to become slippery when wet.

    5.5.1.3 Water Quality Parameters proposed for Monitoring

    V '

    Water-bodies listed in Table 5.1 can be divided into two broad categories based on their

    ambient uses as:

    A. Water-bodies used for bathing and recreation (water intakes were not observed in the

    immediate project area)

    B. Water-bodies serving as irrigation/drainage canals

    The water quality parameters for monitoring are determined based on pollutants that are likely

    to gain entry during construction and affecting the ambient uses. The proposed parameters

    are given in Table 5.5.

    5.5.1.4 Sampling Locations

    To an extent water-bodies in Table 5.1 divided into two environmental settings.

    (a) WQ 1- WQ 14 - somewhat hilly terrain

    (b) WQ 15 - WQ 33 - relatively flat terrain

    In similar environmental settings water quality impacts of construction are likely to be felt

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    19/36

    similarly in the downstream of the road trace. Section from WQ 15- WQ 33 (See the Map given

    in Figure 5.1) is more or less similar to the last segment of the first 25 kilometers, which was

    covered in the previous study. Also a water-body of significant importance was not found in

    this section. [Note: One irrigation tank is located at WQ 25. However, this is located upstream

    of the proposed expressway and not expected to be affected by the proposed project

    significantly].

    On the other hand WQ 1 to WQ 14 represents somewhat hilly area and not part of flood plains. It

    is assumed that water quality effects of the project are similar in this section. Therefore two

    use-wise important water-bodies are proposed in this section for monitoring. The two water-

    bodies are WQ 1 (Kuda Oya) and WQ 11 (Irrigation Canal in Rilagala Area). Monitoring at

    upstream location is also proposed for these two water-bodies. The reason for inclusion of

    upstream location in the monitoring plan is that it provides water quality data undisturbed by

    the construction activities. Thus they will be useful for assessing the construction impacts.

    [Note: Upstream water quality can be affected during flooding. This situation is not covered in

    general water quality assessment].

    Table 5.5 - Water Quality Sampling Locations for Construction Phase

    Type of Water- Water-body Sampling Locations Parametersbody ID

    A W1 300m upstream of centerline of the trace COD

    BOD

    600m downstream of centerline of theTSS

    trace Turbidity

    Color

    pH

    Colour

    Oil andA W11 200m upstream of centerline of the trace Grease

    Nitrate -N

    trace Phosphate

    5.5.1.5 Frequency of Monitoring

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    20/36

    Worst water quality situations in the water-bodies identified in Table 5.1 can occur at times

    when (a) significant runoff is generated when -the streams/canals/rivers are in low flow

    conditions during seasonal dry period or due to irrigation controls, (b) significant runoff

    generated after a long dry spell. As these conditions occur in an ad hoc manner, is not

    possible to fix an exact time for monitoring where the intention is to ascertain the worst

    water quality situation. Thus it is useful that timing of sampling to be determined by those

    responsible based on their judgment. However by considering the climatic data reported in

    Section 5.3.2 it is proposed to include minimum of five samples per year on following basis.

    (i) One sample at each sampling location in January or February immediately after a

    sizable storm event.

    (ii) One sample at each sampling location in April after a sizable storm event

    (iii) One sample at each sampling location in May

    (iv) One sample at each sampling location in August after a sizable storm event

    (v) One sample at each sampling location in October or November

    5.5.2 Operational Phase

    5.5.2.1 Nature of Operational Phase

    Operational phase water quality pollution is primarily NPS pollution. In this phase long-term

    impacts are also an important consideration as heavy metals and other chemicals including

    petroleum based products are also a concern in this phase. Nevertheless significant long-term

    effects, such as due to bio-accumulation are not expected in here. This is because substantial

    rains during May and then in October-November period has high potential for flushing out

    pollutants with less opportunity for long-term accumulation. As the water-bodies of concern are

    flowing water-bodies chances of such accumulation is reduced further.

    5.5.2.2 Water Quality Parameters proposed for Monitoring

    Detailed list of pollutants entering the runoff from roads/highways under operation are provided

    by the USEPA (1997). These mainly include: (a) particulate matter, (b) N and P from fertilizer

    and pesticides, if maintenance of turf is part of the operation, (c) verity of heavy metals from

    ware and tare of tires, combustion products, etc (d) oil and petroleum products due to spilling

    (e) pathogens from animal excreta and rest areas. It is not practical and economical for the

    water quality monitoring program to include all th,e individual pollutants. Thus the following set

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    21/36

    of waterc.

    quality parameters are proposed for water quality monitoring during operations, which can give

    the picture of general water quality status.

    Turbidity

    pH

    COD

    TSS

    Kjeldahl-N

    Phosphate-P

    Copper

    Zin

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    22/36

    5.5.2.3 Sampling Locations

    Category B water-bodies (Section 5.5.1.2) are less important during operation phase as water is

    not in direct contact with humans. Therefore only Category A water-bodies are proposed for the

    monitoring program in this phase. Water-body proposed for the sampling program during operationis WQ1. Sampling location is defined in Table 5.6 below.

    Table 5.6 -Water Quality Sampling Locations for Operational

    300m upstream of centerline of the trace

    600m downstream of centerline of the trace

    5.5.2.4 Frequency of Monitoring

    During the operational phase "first flush" in general results highest pollution concentrations in the runoff.

    First flush means rainfall caused runoff after a dry period. Such events under low flow conditions usually

    result relatively high pollution concentrations. On the other hand pollution concentration becomes less

    prominent during heavy rain period due to dilution by increased flow. Accordingly following monitoring

    schedule is proposed for operational phase, (i) One sample at each sampling location in January or

    February immediately after a sizable storm event.

    (ii) One sample at each sampling location in April after a sizable storm event (iii) One sample

    at each sampling location in August after a sizable storm event (iv) One sample at each

    sampling location in October or November

    5.6 Baseline Conditions

    Baseline water quality reflects the situation before the construction of the expressway. Baseline studyincludes two water-bodies selected for monitoring program under construction phase. The two water-bodies

    are WQ1 and WQ11 {Table 5.1). Table 5.7 provides the details of the baseline water quality plan.

    Table 5.7 - Water Quality Sampling Locations for Baseline Study

    Type of

    Water-body

    Water-body ID Sampling Locations Parameters

    A W1 600m downstream of centerline of the trace COD BOD

    Water-body

    ID

    Sampling Locations

    W1

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    23/36

    A W11 600m downstream of centerline of the trace TSS

    Turbidity

    Color

    pH

    Colour

    ,,. Oil and Grease

    Nitrate -N

    Phosphate

    ;-*. Copper

    . " Zinc

    The water quality measurements during baseline study shall reflect the same flow or hydrologic conditions

    under which the sampling was carried out during construction and operational phases. Thus sampling

    frequency (time frame) for baselines study is set as follows, (i) One sample at each sampling location in

    January or February immediately after a sizable storm event.

    (ii) One sample at each sampling location in April after a sizable storm event (iii) One sample

    at each sampling location in the month of May (iv) One sample at each sampling location in

    August after a sizable storm event (v) One sample at each sampling location in October or

    November

    One set of data is unlikely to provide us the general water quality picture for baseline conditions. For this

    purpose at least few years of data would be required. However, in reality water quality data of such length

    and coverage are often not available. It is recommended to commence the baseline water quality data

    collection as early as possible to collect a reasonably long data set to develop sufficiently accurate picture of

    water quality before the project. In absence of such possibility it is necessary to use other historical water

    quality data to generate the information required.

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    24/36

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    25/36

    6.0 Recommendations

    1. The drainage openings for small streams, Irrigation canals have been designed considering once in

    fifty year flood situation.i.e. fifty year return period. In the design future development of area which

    will increase the impervious area and the runoff volume has been considered. However with thepast experience climate changes and the percentage of land converting to developments have

    been taken in to account.

    2. Since the proposed highway trace passes through the low-lying areas and hilly areas it is

    recommended to construct the cross drainage structures to minimize the effect of backwater

    created by rising flood levels. The minimum sizes of Culverts across the proposed alignment are

    included in table 4.1. Also it should be ensured that there will not be any settlements of culverts to

    avoid adverse environmental impacts due to stagnation of water.

    3. It is observed that the present uncertainty related to climate change which links to flood damage.

    Therefore It is suggested to minimize the filling which causes adverse environment effect by

    introducing Viaduct sections wherever necessary. Also natural water paths should not be disturbed

    and should be improved.

    4. If any changes are suggested using viaduct sections in your design sofit levels of those and location

    of piers should be brought to the notice of SLLRDC for rechecking.

    5. The outlet of all the proposed culvert/bridge crossings should be dredged and connected to the

    nearby streams. The inlets of the same should be cleared about 500m upstream. These drainage

    connections should be established before filling of embankment.

    6. All drainage structures have been provided for cross drainage only. If additional structures are

    needed for irrigation purposes they should be additionally provided.

    7. It is desirable to discuss the locations of the proposed drainage crossings with Irrigation

    Department, and Department of Agrarian Development Services and farmers' organizations. If anychanges are suggested those should be brought to the notice of SILRDC for rechecking.

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    26/36

    8. The toe drains and other drainage canals in the vicinity of the road along the expressway should be

    established as proposed in the Table 4.3.

    9. Prior approval for the proposed bridges across the Kuda oya should be obtained from Department of

    Irrigation.

    10. Canal banks which already collapsed should be protected using gabions at least 200m both sides

    (U/S and D/S) of the Canals where proposed culverts are located.

    11. Canals should be dredged and kept to a desirable bed width. Necessary other maintenance should

    be carried out through the responsible institution simultaneously at least 500m both sides (U/S and

    D/S) of the Canais where proposed culverts are located.

    12. The distance proposed for downstream measurement of water quality is for the purpose of providing

    adequate mixing of pollutants with the stream flow. Also Upstream measurement is aimed at

    obtaining the undisturbed picture during measurements.

    13. The water quality monitoring plan to be implemented in three phases such as baseline (before the

    project and existing .status), construction phase and operational phase.

    14. Proper sample preservation methods are required. Therefore Sampling and testing should be carried

    out by recognized institution.

    15. Analytical methods use for water quality monitoring should be the standard methods accepted in Sri

    Lanka.

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    27/36

    Bibliography

    (i) Design of Irrigation head works for Small Catchments,2ndEdition (Revised) ,AJ.P.Ponrajah,lrrigation Department Colombo, May 1984

    (ii) Technical paper of towards more efficient hydraulic and hydrological Design of Cross drainagesstructures using new developed Intensity Duration Frequency Equations by D.G.L. RanatungaFormer Head Hydrology Division Irrigation Department.

    (iii) Applied hydrology, International Edition, 1988 by Ven Te Chow.

    (iv) Hydrological Study for Colombo-Kandy Alternate Highway Chainage from 0+000 km to25+000 km

    (v) Ambient Water Quality Guidelines, Central Environmental Authority, 2003

    (vi) Controlling Nonpoint Source Runoff Pollution from Roads, Highways and Bridges.

    Washington, D.C.: Office of Water, U.S. Environmental Protection Agency, 1995.

    (vii) Environmental Impact Assessment Report; Colombo-Kandy Alternate Highway Project;2003.

    (viii) Sources and Mitigation of Highway Runoff Pollutants; Federal Highway Administration;Washington, D.C., 1984.

    (ix) Statistical Methods for Environmental Pollution Monitoring; R.O, Gilbert; 1987.

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    28/36

    Annex (B.1): Hydrological and Hydraulic Calculation for Drainage Opening Sizes

    Culvert ID

    (Chainage)

    Total

    Catch m

    ent Area

    (ha)

    Length of

    Longest

    water

    path (m)

    Runoff

    Coeffici

    ent

    Time of

    Concent

    ration

    Tc(min)

    Rainfall

    Intensity

    (mm/hr)

    SOyr

    Discharge

    (m3/sec)

    SOyr

    slope Water

    Depth

    (m)

    Proposed Size of

    Structure

    25+245 284.37 2080 0.40 90.82 97.89 30.93 0.0006 1.50 10.00mx2.00m

    25+367 20.22 1101 0.40 55.14 127.07 2.85 0.0020 1.00 1.50mx1.50m

    25+565 90.05 1255 0.40 60.75 121.30 12.14 0.0010 1.00 6.25mx1.50m

    25+947 100.86 1348 0.40 64.14 118.08 13.23 0.0010 1.00 6.50mx1.50m

    26+180 20.08 873 0.40 46.82 136.77 3.05 0.0010 1.00 2.00mx1.50m

    26+550 25.18 738 0.40 41.90 143.30 4.01 0.0010 1.00 3.00mx1.50m

    27+308 57.39 1089 0.40 54.70 127.54 8.13 0.0010 1.00 4.50mxl50m

    27+481 8.39 449 0.40 31.37 159.78 1.49 0.0010 1.00 1.50mx1.50m

    27+948 46.67 966 0.40 50.21 132.63 6.88 0.0010 1.00 4.00mx1.50m

    28+400 ! 35.09 654 0.40 38.84 147.71 5.76 0.0010 1.00 1.75mx1.50m

    28+500 J 1.75mx1.50m

    28+885 26.36 718 0.40 41.17 144.32 4.23 0.0015 1.00 2.25mx1.50m29+520 53.06 925 0.40 48.72 134.42 7.92 0.0010 1.00 4.25mx1.50m

    30+036 26.64 780 0.40 43.43 141.20 4.18 0.0015 1.00 2.50mx1.50m

    30+330 34.72 1069 0.40 53.97 128.34 4.95 0.0015 1.00 2.50mxl50m

    31+156 -i 82.94 936 0.40 49.12 133.94 12.34 0.0010 1.00 3.50mx1.50m

    31+240 J 3.50mx1.50m

    31+923 -, 60.75 625 0.40 37.78 149.30 10.08 0.0004 1.00 1.50mxl50m

    32+000 I 3.25mx1.50m

    32+088 | 1.50mx1.50m

    32+235 J 1.75mx1.50m

    32+665 297.15 2751 0.40 115.28 84.87 28.02 0.0005 1.50 10.00mx2.00m

    32+985 223.45 2423 0.40 103.33 90.74 22.53 0.0005 1.50 8.50mx2.00m33+390 i 36.02 802 0.40 44.24 140.12 5.61 0.0015 1.00 1.50mx 1.50m

    33+500 J 1.50mx1.50m

    33+858 1 , 84.15 979 0.40 50.69 132.07 12.35 0.0005 1.00 2.75mx1.50m

    33+936 6.75mx1.50m

    34+913 14.09 435 0.40 30.86 160.69 2.52 0.0010 1.00 3.50mx2.50m

    35+358 -i 202.54 1884 0.40 83.68 102.55 23.08 0.0007 1.00 4.25mx1.50m

    35+410 4.50mx1.50m

    35+460 J 4.25mx1.50m

    35+615 ~\ 134.31 2044 0.40 89.51 98.72 14.73 0.0010 1.00 4.00mx1.50m

    35+730 J 4.00mx1.50m

    36+323 -\ 53.10 1010 0.40 51.82 130.76 7.71 0.0010 1.00 2.25mx1.50m36+385 J 2.25mx1.50m

    36+555 85m opening should be provided for Merigama-Pasyala Rd and Railway Track 85m Opening

    36+608 4.54 849 0.40 45.95 137.89 0.70 0.0010 1.00 1.50mx1.50m

    36+853 9.43 441 0.40 31.08 160.30 1.68 0.0010 1.00 1.50mx1.50m

    37+250 15.12 565 0.40 35.60 152.70 2.57 0.0010 1.00 2.00mx1.50m

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    29/36

    Culvert ID

    (Chainage)

    Total

    Catchm

    ent Area

    (ha)

    Length of

    Longest

    water

    path (m)

    Runoff

    Coeffici

    ent

    Time of

    Concentr

    ation

    Tc(min)

    Rainfall

    Intensity

    (mm/hr)

    50yr

    Discharge

    (m3/sec)

    SOyr

    slope Water

    Depth

    (m)

    Proposed Size of

    Structure

    37+522 56.11 1122 0.40 55.90 126.25 7.87 0.0010 1.00 4.25mx1 .50m

    37+893 -i 456.45 3977 0.40 159.98 68.57 34.78 0.0008 1.00 9.00mx1.50m

    38+001 J 9.00mx1.50m

    38+400 16.58 469 0.40 32.10 158.51 2.92 0.0010 1.00 2.00mx1.50m

    38+676 45.02 1662 0.40 75.59 108.42 5.42 0.0010 1.00 3.25mx1.50m

    38+943 38.00 1347 0.40 64.10 118.11 4.99 0.0010 1.00 3.00mx1.50m

    39+195 48.55 1128 0.40 56.12 126.02 6.80 0.0010 1.00 3.75mx1.50m

    40+065 24.41 802 0.40 44.24 140.12 3.80 0.0010 1.00 2.50mx1.50m

    40+630 52.94 1707 0.40 77.23 107.18 6.30 0.0010 1.00 3.50mx1.50m

    40+815 45.74 1410 0.40 66.40 116.03 5.90 0.0010 1.00 3.50mx1 .50m

    40+900 13.83 712 0.40 40.96 144.63 2.22 0.0010 1.00 1.75mx1.50m

    41+070 15.07 575 0.40 35.96 152.13 2.55 0.0010 1.00 2.00mx1.50m

    41+445 \ 1456.46 5049 0.40 199.06 58.90 95.32 0.0004 1.50 13.50mx2.00m

    41+565 20.00mx2.00m

    41+930 44.91 964 0.40 50.14 132.72 6.62 0.0010 1.00 3.75mx1.50m

    42+580 40.83 976 0.40 50.58 132.20 6.00 0.0010 1.00 3.50mx1.50m

    42+925 34.31 1064 0.40 53.79 128.54 4.90 0.0010 1.00 3.00mx1.50m

    43+545 1 193.10 1539 0.40 71.10 112.00 24.03 0.0008 1.00 9.00mx1.50m

    43+840 ^ 3.25mx1.50m

    43+980 26.35 1472 0.40 68.66 ,114.06 3.34 0.0010 1.00 2.25mx1 .50m

    44+120 31.66 1332 0.40 63.56 118.62 4.17 0.0010 1.00 2.75mx1 .50m

    44+250 57.71 1366 0.40 64.80 117.48 7.53 0.0009 1.00 4.25mx1.50m

    44+490 10.44 475 0.40 32.32 158.14 1.83 0.0010 1.00 1.50mx1.50m

    44+673 14.18 416 0.40 30.16 161.93 2.55 0.0010 1.00 2.00mx1.50m

    45+135 17.40 501 0.40 33.26 156.53 3.03 0.0010 -1.00 2.00mx1 .50m

    45+666 9.19 473 0.40 32.24 158.26 1.62 0.0010 1.00 1.50mx1.50m

    46+032 12.31 528 0.40 34.25 154.89 2.12 0.0010 1.00 1.75mx1.50m

    46+476 16.63 469 0.40 32.10 158.51 2.93 0.0010 1.00 2.00mx1.50m

    46+892 10.30 450 0.40 31.40 159.72 1.83 0.0010 1.00 1.50mx1.50m

    47+451 1 267.06 1630 0.40 74.42 109.33 32.44 0.0009 1.00 9. 00m x 1.50m

    47+557 -* 7.00mx1.50m

    47+928 62.61 1255 0.40 60.75 121.30 8.44 0.0010 1.00 4.50mx1.50m

    48+174 5057.04 13399 0.40 503.44 32.92 184.95 0.0040 3.50 32.00mx4.50m

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    30/36

    Annex (B.2): Hydrological and Hydraulic Calculation for Drainage Opening Sizes for

    Overpass and Underpass

    Culvert ID

    (Chainage)

    lotai

    Catchme

    nt Areaha

    i_engin

    of

    Longest

    water

    Runoff

    Coeffici

    ent

    i ime or

    Concentr

    ationTc min

    Kainran

    Intensity

    (mm/hr)50 r

    uiscnarg

    e

    (m3/sec)50 r

    slope

    SWater

    Depth

    (m)

    Proposed Size

    of Structure

    25+535 (LHS) 161.92 1838 0.40 82.00 103.71 18.66 0.001 1.00 9.25mxl.50m

    25+535(RHS) 2.16 202 0.40 22.36 177.47 0.43 0.001 1.00 l.OOmxl.SOm

    26+394 (LHS) 25.18 830 0.40 45.26 138.78 3.88 0.001 1.00 2.50mxl.50m

    26+394(RHS) 54.20 1063 0.40 53.75 128.58 7.74 0.001 1.00 4.25mxl.50m

    27+451 (LHS) 87.68 1215 0.40 59.29 122.75 11.96 0.001 1.00 6.00mxl.50m

    27+451 (RHS) 11.87 893 0.40 47.55 135.86 1.79 0.001 1.00 l.SOmxl.SOm

    27+980 (LHS) 5.40 347 0.40 27.65 166.61 1.00 0.001 1.00 l.OOmxl.SOm

    27+980(RHS) 15.67 821 0.40 44.93 139.21 2.42 0.001 1.00 1.75mxl.50m

    28+720 (LHS) 1m minimum openings should be provided . l.OOmxl.SOm

    28+720(RHS)l.OOmxl.SOm

    29+210 (LHS) l.OOmxl.SOm

    29+21 0(RHS) l.OOmxl.SOm

    29+707 (LHS) 0.58 94 0.40 18.43 186.59 0.12 0.001 1.00 l.OOmxl.SOm

    29+707(RHS) 5.11 515 0.40 33.77 155.67 0.88 0.001 1.00 l.OOmxl.SOm

    30+520 (LHS) 4.15 355 0.40 27.94 166.06 0.77 0.001 1.00 l.OOmxl.SOm

    30+520(RHS) 8.89 728 0.40 41.54 143.81 1.42 0.001 1.00 1.25mxl.50m

    31 +040 (LHS) 1.83 180 0.40 21.56 179.25 0.36 0.001 1.00 l.OOmxl.SOm

    31+040(RHS) 6.48 762 0.40 42.78 142.09 1.02 0.0010 1.00 l.OOmxl.SOm

    31 +395 (LHS) 9.06 539 0.40 34.65 154.23 1.55 0.001 1.00 1.25mxl.50m

    31+395(RHS) 18.83 776 0.40 43.29 141.40 2.96 0.001 1.00 2.00mxl.50m

    31+830 (LHS) 9.08 663 0.40 39.17 147.22 1.49 0.001 1.00 1.25mxl.50m

    31+830(RHS) 10.10 1712 0.40 77.41 107.04 1.20 0.001 1.00 1.25mxl.50m

    32+839 (LHS) 127.08 2627 0.40 110.76 86.99 12.28 0.001 1.00 6.25mxl.50m

    32+839(RHS) 255.40 2571 0.40 108.72 87.99 24.97 0.001 1.00 13.00mxl.50m

    33+490 (LHS) 1.93 204 0.40 22.44 177.31 0.38 0.001 1.00 l.OOmxl.SOm

    33+490(RHS) 10.63 697 0.40 40.41 145.42 1.72 0.001 1.00 l.SOmxl.SOm

    37+579 (LHS) 4.62 359 0.40 28.09 165.78 0.85 0.001 1.00 l.OOmxl.SOm

    37+579(RHS) 1.11 155 0.40 20.65 181.32 0.22 0.001 1.00 l.OOmxl.SOm

    39+1 49 (LHS) 6.89 627 0.40 37.86 149.19 1.14 0.001 1.00 l.OOmxl.SOm

    39+149(RHS) 7.99 412 0.40 30.02 162.19 1.44 0.001 1.00 1.25mxl.50m

    40+510 (LHS) 20.74 732 0.40 41.68 143.61 3.31 0.001 1.00 2.25mxl.50m

    40+51 0(RHS) 11.71 443 0.40 31.15 160,17 2.08 0.001 1.00 1.75mxl.50m

    40+885 (LHS) 9.25 425 0.40 30.49 161.34 1.66 0.001 1.00 l.SOmxl.SOm

    40+885(RHS) 119.09 1586 0.40 72.82 110.60 14.64 0.001 1.00 7.50mxl.50m

    41+085 (LHS) 0.56 95 0.40 18.46 186.50 0.12 0.001 1.00 l.OOmxl.SOm

    41+085(RHS) 14.56 778.00 0.40 43.36 141.30 2.29 0.001 1.00 1.75mx1.50m

    41+620 (LHS) 19.31 761 0.40 42.74 142.14 3.05 0.001 1.00 2.00mxl.50m

    41+620(RHS) 18.02 946 0.40 49.49 133.50 2.67 0.001 1.00 2.00mxl.50m

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    31/36

    Culvert ID

    (Chainage)lotalCatchme

    nt Area

    ha

    Length

    of

    Longest

    water

    Runoff

    Coeffici

    ent

    i ime or

    Concentr

    ation

    Tc min

    Kamtall

    Intensity(mm/hr)

    50 r

    Uischarg

    e

    (m3/sec)

    50 r

    slope

    SWaterDepth(m)

    Proposed Size

    of Structure

    42+595 (LHS) 5.59 458 0.40 31.70 159.21 0.99 0.001 1.00 l.OOmxl.SOm

    42+595(RHS) 2.37 211 0-40 22.69 176.75 0.47 0.001 1.00 l.OOmxl.SOm

    43+616 (LHS) 17.06 686 0.40 40.01 145.99 2.77 0.001 1.00 2.00mxl.50m

    43+61 6(RHS) 85.09 928 0.40 48.83 134.29 12.70 0.0009 1.00 7.00mxl.50m

    44+228 (LHS) 4.99 374 0.40 28.63 164.75 0.91 0.001 1.00 l.OOmxl.SOm

    44+228(RHS) 6.31 392 0.40 29.29 163.53 1.15 0.001 1.00 l.OOmxl.SOm

    44+444 (LHS) 4.36 457 0.40 31.66 159.27 0.77 0.001 1.00 l.OOmxl.SOm

    44+444(RHS) 1.29 171 0.40 21.23 179.99 0.26 0.001 1.00 l.OOmxl.SOm

    45+1 54 (LHS) 0.38 113 0.40 19.12 184.91 0.08 0.001 1.00 l.OOmxl.SOm

    45+154 (RHS) 6.10 1295 0.40 62.21 119.89 0.81 0.001 1.00 l.OOmxl.SOm

    45+464 (LHS) 1 m minimum openings should be provided . l.OOmxl.SOm45+464(RHS) l.OOmxl.SOm

    45+802 (LHS) l.OOmxl.SOm45+802(RHS) l.OOmxl.SOm

    46+488 (LHS) 56.71 751 0.40 42.38 142.64 8.99 0.001 1.00 4.75mxl.50m

    46+488(RHS) 2.14 370 0.40 28.49 165.02 0.39 0.001 1.00 l.OOmxl.SOm

    46+91 8 (LHS) 1.09 185 0.40 21.74 178.84 0.22 0.001 1.00 l.OOmxl.SOm

    46+91 8(RHS) 5.87 442 0.40 31.11 160.23 1.05 0.001 1.00 l.OOmxl.SOm

    47+51 2 (LHS) 5.79 380 0.40 28.85 164.34 1.06 0.001 1.00 l.OOmxl.SOm

    47+51 2(RHS) 2.71 273 0.40 24.95 171.97 0.52 0.001 1.00 l.OOmxl.SOm

    Following details are enclosed into Annex (C);

    1). Details of culverts "'

    2). Maps showing catchment areas

    3). Colombo Kandy alternate Expressway plan and longitudinal maps

    4). Longitudinal sections and Cross sections at Chainage 33+368 km, 37+8.79 km 38+001 km and

    48+174 km

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    32/36

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    33/36

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    34/36

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    35/36

  • 8/14/2019 Hydraulic Design - Scan Doc.docx

    36/36