how to safely plan and conduct riser replacement … 2013/temadag om...– simops (onboard vessel)...
TRANSCRIPT
How to safely plan and conduct riser replacement operations
November 26th, 2013
Xavier Heraudeau
2 Page 27-Nov-13
Introduction
Recovery risks management
Subsea 7 vessel capabilities
Key points to plan for recovery
Lessons learned extract
Agenda
3 Page 27-Nov-13
Introduction
• What is a riser replacement operation ?
– Reasons:
• Field life extension
• Riser life termination
• Damage to product (accidental or fatigue)
• New requirements (flow for flexibles, controls / power for umbilicals / cables)
– Configurations mostly met for replacement scopes in North Sea:
• Static risers in J-tubes
• Dynamic risers
Steep wave Lazy wave (Reversed) Pliant wave Lazy S
4 Page 27-Nov-13
Introduction
• What is a riser replacement operation ?
– Overview of recovery operations: key steps
• Topside end disconnection from floater
• Transfer of topside end from floater to vessel
• Handling of topside end through layspread
• Wave un-shaping
• Hold-down tether disconnection and counter-weight management
• Accessories removal
• Subsea connector break-off
• Subsea end storage
5 Page 27-Nov-13
Introduction
• What is a riser replacement operation ?
– Overview of installation operations key steps:
• Topside end handling onboard vessel
• Transfer of topside end to floater
• Accessories assembly
• Counter weight management
• Wave shaping
• Tethers connections
• Subsea connector installation
6 Page 27-Nov-13
Introduction
• Subsea 7 Portfolio involving flexible risers replacement only
Project Client Year Riser Type and Quantity
Skuld Marine Installation Statoil 2012 1 x 11.5" Production Riser
Marulk Subsea Installation Statoil 2011 1 x 10.5" Production Riser
Njord A Riser Replacement StatoilHydro 2010 1 x 6" Production Riser
Snorre B Riser Replacement StatoilHydro 2009-2010 2 x 5" Production Risers and 1 x 8" Production Riser
Visund Future Riser StatoilHydro 2009 3 x 6" Production Risers
Njord Gas Export Line & Riser Option Project
Norsk Hydro 2007 2 x 6" Production Risers and 1 x 10" Gas Export Riser
Veslefrikk Riser Replacements Statoil 2003 1 x 8" Water Injection Riser, 1 x 4" Mud
Visund FPU Riser Replacement Statoil 2003 4 x 6" Production Risers
Vigdis WI Riser Replacement Statoil 2002 1 x 10" Water Injection Riser
Åsgard B Riser Replacement Statoil 2002 1 x 9" Gas Injection Riser
Njord FPU Riser Replacement Norsk Hydro 2002 4 x 6" Gas Injection Risers, 1 x 6" Production Riser
7 Page 27-Nov-13
Introduction
• Subsea 7 on-going projects involving Flex decomissionning in Norway
– Statoil Subsea Lines Modification project
• Subsea 7 Portfolio involving Flex decomissioning worldwide
– Apache Van Gogh flowlines – Australia
– Apache Ningaloo Vision flowlines – Australia (on-going)
– Total Moho Bilondo riser – Congo
– Suncor Terra Nova risers – Canada
– Nexen Scott & Telford flowline – Scotland
– ...
8 Page 27-Nov-13
Introduction
Recovery risks management
Subsea 7 vessel capabilities
Key points to plan for recovery
Lessons learned extract
Agenda
9 Page 27-Nov-13
Recovery risks management
Risk Consequence Some Mitigations
Limited knowledge of annulus with only visual inspection of outer sheath
1.Pollution from annulus 2.Burst due to localised pressure
1.Annulus sampling tests 1.PPE ready on vessel 2.Annulus venting
Flexible OD variations Bend stiffener not sliding Loose accessories
Contingency procedures
Flexible bore contents Pollution onboard vessel (connection break-off)
Dedicated storage system PPE Contingency procedures Pre/de-commissioning activities tracability
10 Page 27-Nov-13
Recovery risks management
Risk Consequence Some Mitigations
BSLM release mechanism mal-functioning
Delay in operation on SIMOPS
Design that prevents locked BSLM Reversible procedures
Vessel dependance to floater equipment
Failure of winch may lead to stand-by in close proximity
Plan for back-up procedures & equipment onboard floaters
Closed I-tubes at bottom ends with potential debris
1.Dropped objects 2.Damage to product when lowering
1.Survey of I-tube 2.Design at hang-off to avoid dropped objects
11 Page 27-Nov-13
Operational risks management
Risk Consequence Some Mitigations
Extended operations in close proximity & SIMOPS in restricted weather
1.Restricted activities onboard production units 2.Increased required operational window
1.Qty of subsea operations limitation 2.Reversible procedures
Extensive marine growth
1.Extended deck operations 2.Slippery working conditions
1.Pre-survey 2.Working area designed for marine growth material 2.Cleaning tools spares
Dropped objects Damage to existing subsea infrastructures
Risk assessments Shut-down
12 Page 27-Nov-13
Introduction
Recovery risks management
Subsea 7 vessel capabilities
Key points to plan for recovery
Lessons learned extract
Agenda
13 Page 27-Nov-13
Subsea 7 vessel capabilities
• Skandi Acergy
400 Te AHC Knuckle Boom Crane
100 Te AHC Knuckle Boom Crane
FLS (125Te Flexible Lay System). + 7.2x7.2 m Moonpool
Flexible Load-out Spread
3000Te Below Deck Carousel
2 off ROV (DP work class). Deployed through moonpools
3 off 10Te deck winches
1 off 32Te Initiation winch
Principal Particulars
Length overall 157 m
Breadth 27 m
Depth to main deck 12 m
Draught 7.00 m
Deck area usable 2100 m2
Transit speed 15 kts
Maximum speed 18 kts
Accommodation 140
DP Class III
Capacities
Flexible/Umbilical installation
Riser installation
Spool/Jumper Installation
Structures/Manifold Installation
Protection structures
14 Page 27-Nov-13
Subsea 7 vessel capabilities
• Skandi 7
Principal Particulars
Length overall 120.7 m
Breadth 23 m
Depth to main deck 9 m
Draught 7 m
Deck area usable 1125 m2
Transit speed 12 kts
Maximum speed 16 kts
Accommodation 114 persons
DP Class III
Capacities
• Flexible/Umbilical installation
• Riser installation
• Spool/Jumper Installation
• Structure/Manifold Installation
• Inspection and maintenance work
• Support vessel operation
250 Te AHC Knuckle Boom Crane
VLS (260Te Vertical Lay System) + 7.2 x 7.2 m Moonpool
2 off ROV (DP work class)
15 Page 27-Nov-13
Subsea 7 vessel capabilities
• Normand Oceanic
Principal Particulars
Length overall 157 m
Breadth 27 m
Depth to main deck 12 m
Draught 7.00 m
Deck area usable 2100 m2
Transit speed 12 kts
Maximum speed 17,6 kts
Accommodation 140
DP Class III
Capacities
Flexible/Umbilical installation
Riser installation
Spool/Jumper Installation
Structures/Manifold Installation
Protection structures
400 Te AHC Knuckle Boom Crane
100 Te AHC Knuckle Boom Crane
2 off ROV (DP work class). Deployed by A-frames
4 off 12Te deck winches
16 Page 27-Nov-13
Subsea 7 vessel capabilities
• 7 Pacific
Principal Particulars
Length overall 134 m
Breadth 24 m
Depth to main deck 12 m
Draught 7.00 m
Deck area usable 978 m2
Transit speed 12,5 kts
Maximum speed 13,5 kts
Accommodation 100
DP Class II
Capacities
Flexible/Umbilical installation
Riser installation
Spool/Jumper Installation
Structures/Manifold Installation
250 Te AHC Knuckle Boom Crane
30 Te AHC Knuckle Boom Crane
2 off ROV (DP work class).
VLS (260Te Vertical Lay System). + 7.2 x 7.2 m Moonpool
17 Page 27-Nov-13
Subsea 7 vessel capabilities
• Skandi Acergy - Storage
– 24m OD / 6m high under-deck carousel
– RDS possible on deck:
• Flowlines: up to 6-slots
• Risers: up to 5 slots
18 Page 27-Nov-13
Subsea 7 vessel capabilities
• Skandi Acergy - Lifting equipment
• Present flexlay vessels, 1 slide per vessel,
19 Page 27-Nov-13
Subsea 7 vessel capabilities
• Skandi Acergy – Containment
– All below can be generic to any vessel
– IBC tanks with pumping system
– Closed volume around hang-off area
– PPE for marine growth: same as working under rain.
– PPE for pipe contents:
• Integral rubber suit for pipe contents
• Rubber gloves & boots
• Face shield + protection glasses
• Mask
• Skandi Acergy – Subsea equipment
– LARS - Safe til Hs=6m
– Up to 270kg lifting capacity
20 Page 27-Nov-13
Introduction
Recovery risks management
Subsea 7 vessel capabilities
Key points to plan for recovery
Lessons learned extract
Agenda
21 Page 27-Nov-13
Recovery operations – key points to plan for
• Platform operations
– Contingency procedures in case of difficult disconnection or equipment failure
– Function testing performed
• Vessel operations
– Thorough planning of containment operations
– Thorough planning of operations at working area while heavy cleaning
– SIMOPS (onboard vessel) due to installation of aids
– Reversible installation or recovery operations to be aimed while SIMOPS in closed proximity
– Schedule re-visited after preliminary visual survey (marine growth)
• Subsea operations
– Counter weight connection – Use of permanent clamp if possible
– ROV installation of aids on product to be limited as much as possible
– Trials to be planned for subsea installable aids
22 Page 27-Nov-13
Recovery operations – key points to plan for
• Design requirements
– All utilization of temporary installation aids to be designed in view of recovery operations
– Assessment of aids design with permanent features (anodes)
– Permanent accessories design: interfaced with Installation Contractor for aids connection and riser installability
– Riser configuration (buoyancy section mainly) to be optimised for restricting use of counter weights
– Topside BSLM selection for use at end of life
– Monitoring of annulus and pressure release systems
– Re-use of permanent equipment to be thouroughly assessed according to as-found conditions of equipment.
23 Page 27-Nov-13
Introduction
Recovery risks management
Subsea 7 vessel capabilities
Key points to plan for recovery
Lessons learned extract
Agenda
24 Page 27-Nov-13
Extract of list of Lessons extra learned on how to address safely this operation – worldwide
Lesson # Description
LL-09599 Top tension variation evaluation at vessel during pull out with flexible pipe rupture at production unit
LL-10533 Use of buoyancy module ballast cages
LL-10201 & LL-03755
Marine Growth Removal Collar for Flexible Recovery
LL-10202 Flexible Recovery - Product Packing
LL-00987 Positioning of vessel during MWA Buoy preparation and recovery works
LL-01983 Precom - management of pigs during product recovery
LL-03699 Wire Deflector for riser pull-in
LL-03781 Use of variable weight DMA
LL-03788 Positioning of RDS & reel cradles for recovery operations
LL-06647 Bend Stiffener Stopper Clamp and Tip Support
25 Page 27-Nov-13