November 22, 2016 Ray Ritcey, Chair Halifax Water Halifax, Nova Scotia The regular meeting of the Halifax Water Board will be held on Thursday, November 24, 2016 at 8:30 a.m. in the Boardroom at 450 Cowie Hill Road, Halifax.
AGENDA
In Camera Reports
1C Approval of Minutes of the Special In-Camera Meeting held on Thursday, October 27, 2016
2C Business Arising from the Minutes of September 29, 2016 and October 27, 2016 a)
3C Legal Matter (Verbal – 10 minutes)
4C Governance Matter (Verbal – 10 minutes) Regular Reports
1. a) Ratification of In-Camera Motions b) Approval of the Order of Business and Approval of Additions and Deletions (5 minutes)
2. Approval of Minutes of Special Meeting held on Thursday, October 27, 2016
3. Business Arising from the Minutes of September 29, 2016 and October 27, 2016 a)
4. Operating Results for the Seven Months Ended October 31, 2016 (5 minutes)
5. Capital Projects: (None)
6. Lead Service Line Replacement Program – Application to the NSUARB (20 minutes) Information Reports
1-I Operations and Financial Monthly Update 2-I Capital Budget Approvals to Date 3-I Bank Balance 4-I Wastewater Systems – Odour Management 5-I Halifax Regional Water Commission Employees’ Pension Plan – 3rd Quarter, 2016 – Financial Report
Original Signed By:
James G. Spurr Secretary
HALIFAX REGIONAL WATER COMMISSION October 27, 2016
1
HALIFAX REGIONAL WATER COMMISSION MINUTES
October 27, 2016
PRESENT: Commissioner Ray Ritcey, Chair Commissioner Russell Walker, Vice Chair Commissioner Jacques Dube Commissioner David Hendsbee Commissioner Don Mason Commissioner Darlene Fenton Commissioner Barry Dalrymple REGRETS: Commissioner Mike Savage STAFF: Carl Yates, General Manager, HRWC Cathie O’Toole, Director, Corporate Services , HRWC James Spurr, Legal Counsel, HRWC Kenda MacKenzie, Director, Regulatory Services, HRWC (In
Part) Lorna Skinner, Administrative Assistant, HRWC
HALIFAX REGIONAL WATER COMMISSION October 27, 2016
2
TABLE OF CONTENTS CALL TO ORDER ........................................................................................................................ 3 1. APPROVAL OF MINUTES - SEPTEMBER 29, 2016 ....................................................... 3 2. BUSINESS ARISING FROM MINUTES ........................................................................... 3 a) Business Plan for Lead Service Line Replacement ................................................ 3 b) AMI Project Update - Verbal ....................................................................................... 3 3 STORMWATER RATE APPLICATION ............................................................................ 3 4. OPERATING RESULTS FOR SIX MONTHS ENDED SEPTEMBER 30, 2016 ............... 4 5. DATE OF NEXT MEETING ............................................................................................... 4
HALIFAX REGIONAL WATER COMMISSION October 27, 2016
3
CALL TO ORDER The Chair called the regular meeting to order at 9:00 a.m. in the Board Room of the HRWC, 450 Cowie Hill Road. The Board moved In Camera at 9:00 and the regular meeting reconvened at 9:02 a.m.
1. APPROVAL OF MINUTES – September 29, 2016
MOVED BY Commissioner Walker, seconded by Commissioner Mason that the Halifax Regional Water Commission Board approve the minutes of September 29, 2016. MOTION PUT AND PASSED. 2. BUSINESS ARISING FROM MINUTES a) Business Plan for Lead Service Line Replacement
A report dated October 18, 2016, was submitted. Carl Yates informed the Board that the tabled report and overview of this issue was also presented to and approved by the Environment, Health & Safety Committee. Mr. Yates stated that the Lead Service Line replacement program reflects the National Drinking Water Advisory Council recommendations to the US Environmental Protection Agency. The goal is to remove all lead service lines (both public and private) over a 30-year period. Mr. Yates added that communication to the rate payers will be key over the life of this project. MOVED BY Commissioner Mason, seconded by Commissioner Fenton that the Halifax Regional Water Commission Board approve the proposed business plan for a revised Lead Service Line replacement program, consistent with the recommendations of the National Drinking Water Advisory Council to the USEPA. MOTION PUT AND PASSED. b) AMI Project Update (Verbal) Cathie O’Toole informed the Board that the NSUARB issued the Order for approval of this project on October 26, 2016. 3. STORMWATER RATE APPLICATION At this time Kenda MacKenzie joined the meeting. A report dated October 20, 2016, was submitted. Cathie O’Toole gave a presentation on the Stormwater Rate Application that will be
HALIFAX REGIONAL WATER COMMISSION October 27, 2016
4
submitted to the NSUARB on October 31, 2016, to adjust Stormwater rates to reflect the approved Cost of Service Manual. This presentation included the history of the delivery of Stormwater service, the proposed rates for both residential and non-residential customers, the key changes reflected in the Application and the revenue requirements. Commissioner Dalrymple suggested that full page advertisements placed in local community newspapers summarizing the history of Stormwater service would be very beneficial. The Board agreed. Ms. O’Toole added that the same day the Application will be filed, several educational tools will be launched on the Halifax Water website: an educational Stormwater video, six info-graphics, and a customer web application that will allow customers to view their property and determine if they are within the Stormwater service boundary. MOVED BY Commissioner Fenton, seconded by Commissioner Mason that the Halifax Regional Water Commission Board approve the submission to the Nova Scotia Utility & Review Board to adjust Stormwater rates to reflect the approved Cost of Service Manual. MOTION PUT AND PASSED. At this time, Kenda MacKenzie exited the meeting. 4. OPERATING RESULTS FOR THE SIX MONTHS ENDED SEPTEMBER 30, 2016 A report dated October 20, 2016, was submitted. Cathie O’Toole gave a brief overview of the operating results. 5. DATE OF NEXT MEETING The next meeting is scheduled for November 24, 2016. The meeting was adjourned at 10:29 a.m. Original Signed By: Original Signed By: James G. Spurr Commissioner Ray Ritcey Secretary Chair The following Information Items were submitted: 1-I 2015/16 Annual Report 2-I 2015/16 Corporate Balanced Scorecard - Results 3-I Water Supply Update
ITEM # 4 HRWC Board
November 24, 2016
Page 1 of 7
TO: Ray Ritcey, Chair and Members of the Halifax Regional Water Commission Board
SUBMITTED BY: Original Signed By:
Cathie O’Toole, MBA, CPA, CGA, Director, Corporate Services APPROVED: Original Signed By:
Carl Yates, M.A.Sc., P.Eng., General Manager DATE: November 16, 2016 SUBJECT: Operating Results for the Seven Months Ended October 31, 2016
INFORMATION REPORT
ORIGIN Financial Statements BACKGROUND The Board is required to review periodic financial information throughout the year. DISCUSSION Attached are the operating results for the first seven (7) months of the 2016/17 fiscal year, period ending October 31, 2016. The statements reflect direct operating costs by department and allocations among water, wastewater and stormwater for common costs shared across all the services provided by Halifax Regional Water Commission (HRWC). HRWC is a fully regulated government business enterprise, falling under the jurisdiction of the Nova Scotia Utility and Review Board (NSUARB). The NSUARB requires that HRWC file Financial Statements and rate applications with the Board based on the NSUARB Handbook for Accounting and Reporting for Water Utilities. The Accounting Standards Board (AcSB) requires rate regulated entities to conform to International Financial Reporting Standards (IFRS). The Commission has converted the SAP financial records to IFRS for the purposes of the annual audit and consolidation of the financial statements with those of Halifax Regional Municipality (HRM). The budget for the 2016/17 fiscal year was prepared using the NSUARB format and financial results will continue to be provided in NSUARB format.
ITEM # 4 HRWC Board
November 24, 2016
Page 2 of 7
Summary information is provided for the Balance Sheet on Page 1 and the Income Statement on Page 2. A detailed presentation of the Balance Sheet and Income Statement is provided on Pages 3 and 4. Pages 5 through 8 provide Income Statements by Service and for Regulated and Un-Regulated Services. Pages 9 and 10 provide the Balance Sheet and Income Statement in IFRS format. Consolidated Income Statement - Page 2 Consolidated operating revenue of $82.2 million is $4.0 million greater than revenue reported for the same year-to-date period last year. Consolidated operating expenses of $52.5 million are $1.9 million lower than the same period last year.
The Net Profit for the year is $11.3 million, an improvement of $4.9 million from the same time in the prior year. The budget for the year, approved at the January 28, 2016 Board meeting, was for a profit of $154 thousand. Results for the year to date have been reviewed in conjunction with plans for the remainder of the year. An update to the Forecast reflects the change from the budget to a profit of $4.2 million, a total change of $4.0 million. The Net Surplus to date is a result of both high Operating Revenue and low Operating Expenses relative to the Budget. Revenue is expected to follow the normal seasonal pattern and fall in line with the Budget and Forecast. It is anticipated that Operating Expenses will increase during the fiscal year as planned initiatives are completed and the impact of fall and winter seasons are realized. Balance Sheet - Page 3 The cash balance of $58.4 million is up $18.6 million from the prior year. In response to the high cash balance, the amount of new debt to be issued in November was reduced from the budgeted amount of $31.9 million to $7.1 million. The cash balance and capital expenditures will be monitored to determine if the additional cash is required from the Municipal Finance Corporation’s Spring debenture. The Customers & Contractual Accounts Receivable balance of $15.9 million has increased $3.7 million from the same time last year. The Customers and Contractual – Unbilled Services figure
Actual YTD Actual YTD2016/17 2015/16
'000 '000 $ Change % Change
Operating Revenue $82,193 $78,234 $3,959 5.1%Operating Expenses $52,469 $54,379 ($1,910) -3.5%Operating Profit (Loss) $29,724 $23,855 $5,868 24.6%
Non Operating Revenue $1,878 $1,822 $56 3.1%Non Operating Expenditure $20,308 $19,240 $1,068 5.6%Net Surplus (Deficit) $11,294 $6,437 $4,857 75.5%
Summarized Consolidated Operating Results
ITEM # 4 HRWC Board
November 24, 2016
Page 3 of 7
represents the estimated revenue that has been earned but not yet billed to customers due to the monthly or quarterly billing cycle. The Unbilled Services amount is down $0.2 million to $17.4 million. The amounts receivable from HRM of $3.9 million are down $0.4 million from the prior year. The liquidity on the balance sheet (ratio of current assets divided by current liabilities) is 2.09, up from the ratio of 1.54 at the same time last year. Plant in Service assets net of Accumulated Depreciation is $1.0 billion and is $48.6 million higher than at this time last year. Capital Assets Under Construction is down $20.6 million to $41.5 million. In the prior year, Assets Under Construction included significant balances for the Lakeside Diversion and Kearney Lake Road projects. The following table highlights the major projects currently underway:
Figures used in the various tables throughout the report may contain differences due to Excel rounding.
Trade liabilities of $11.2 million have decreased $1.0 million when compared to the prior year. Liabilities to HRM of $5.8 million are on par with the prior year. The amount owing to HRM includes the accrual for the annual dividend ($2.7 million accrued towards the $4.6 million annual payment), the accrued balance of the valve box and manhole adjustment work ($2.6 million), the Stormwater Right of Way customer billings ($0.3 million), plus other miscellaneous operating and capital accruals. Unearned Revenue is down $2.6 million. The current portion of Long Term Debt balance of $23.2 million is up $0.8 million from the prior year. Long Term Debt is up $10.4 million from last year, which is net of repayments of $17.9 million. The debt service ratio is currently 21.4%, a slight increase from 21.2% last year. This is well below the maximum 35% ratio allowed under the blanket guarantee agreement with HRM.
The cumulative Operating Surplus of $7.8 million at the beginning of the fiscal year has grown to $19.1 million with the year-to-date profit of $11.3 million.
Cumulative'000
MacDonald Bridge Transmission Main $6,138Aerotech Wastewater Treatment Facility $2,857Geizer 158 Reservoir Rehabilitation $2,813All other projects $29,722Total $41,531
Capital Assets Under Construction
2016/17 2015/16'000 '000
Water $59,424 $53,568Wastewater $134,466 $132,569Stormwater $11,056 $8,442Combined $204,947 $194,578
Long Term Debt by ServiceYTD Debt Servicing Cost Ratio
2016/17 2015/16Water 19.1% 18.9%Wastewater 24.7% 24.0%Stormwater 11.3% 14.9%Combined 21.4% 21.2%
Debt Servicing Ratio by Service
ITEM # 4 HRWC Board
November 24, 2016
Page 4 of 7
Income Statement – All Services - Page 4 The following table compares the results with a seven month pro-rated forecast for the year. The forecast to the end of the year, can be seen on page 2 of the attachment to this report and shows a projected surplus of $4.2 million dollars.
Customer Rates The following table summarizes the most significant customer rates.
Operating Revenue Operating Revenue is $3.0 million ahead of the pro-rated forecast for the year. This reflects the seasonal pattern of consumption that is typically higher for the summer months. Metered Sales revenue is up $2.4 million (9.5%) for Water Service and $1.7 million (4.2%) for Wastewater Service. Metered Sales consist of base and volumetric charges. Base charges are on par with budget expectations. Volumetric revenue budgets for 2016/17 were based on a 3% decrease in metered consumption. Year-to-date billed water consumption is down only 1.3% compared to the prior year. On a 12 month rolling basis, billed consumption is down 1.4%. The full extent to which the dry summer weather has influenced consumption is not yet reflected in the results to date due to the 13 week billing cycle for residential customers. As most of the
Seven MonthActual YTD Forecast
2016/17 2016/17'000 '000 $ Variance % Variance
Operating Revenue $82,193 $79,274 $2,919 3.7%Operating Expenses $52,469 $57,539 ($5,070) -8.8%Operating Profit (Loss) $29,724 $21,735 $7,989 36.8%
Non Operating Revenue $1,878 $1,933 ($56) -2.9%Non Operating Expenditure $20,308 $21,219 ($911) -4.3%Net Surplus (Deficit) $11,294 $2,450 $8,844 361.1%
Summarized Consolidated Operating Results
Effective EffectiveApril 1/16 May 1/15 $ Change % Change
Volumetric Charges (per m3)Water 0.976 0.845 0.131 15.5%Wastewater 1.753 1.638 0.115 7.0%Combined 2.729 2.483 0.246 9.9%
Base Charges (per year)Water No Change 0.0%Wastewater Varies 1.1%-7.7%Stormwater - Residential 33.39 33.39 No Change 0.0%Stormwater- HRM ROW - 41.00 Eliminated -100.0%
Summary of Rate Changes
Varies by meter sizeVaries by meter size
ITEM # 4 HRWC Board
November 24, 2016
Page 5 of 7
increase in revenue is attributable to higher rates and seasonality, the financial benefit realized to date from consumption is approximately $0.4 million. Wastewater Metered Sales also consists of a volumetric discharge component and a base charge component. For most customers, the discharge component is based on the metered water consumption, and the volumes and revenue reflect the decline in water consumption. The billed discharge volume to date has declined 2.4%, and on a rolling 12 month basis, the billed discharge volume has declined by the same 2.4%. The wastewater revenue budget for 2016/17 was also based on an assumed 3% decrease in discharge volume based on metered consumption. The dry summer conditions also led to low water levels and the imposition of water restrictions from September 19 to October 24 for Dartmouth and surrounding areas serviced by Lake Major. System input from the Lake Major facility declined by approximately 2.5 million litres (7.2%) per day for seven weeks (compared to the same time last year). At this volume, the potential impact of the restrictions would be to reduce revenue by approximately $241 thousand. This would be mitigated by bulk water sales re-directed to the West and Central regions, unmetered customers on flat rate bills, and normal water loss within the distribution system. Stormwater Site Generated revenue is on par with budget and the prior year. Other Services and Fees are currently ahead of budget and the prior year, with notable increases in Private Fire Protection and Septage Tipping fees. Operating Expenses Operating Expenses of $52.5 million are $1.9 million below the prior year and $5.1 million below the pro-rated forecast for the year. All expense categories are below budget and forecast. Increases over prior year expenditures are seen in Engineering and Information Services, Small Systems, Scada Control & Pumping, and Depreciation. Administration and Pension shows the most significant decline. The following table summarizes Operating Expenses by their nature and indicates that the reduced expenditures relative to budget are being realized across all expense categories.
Seven MonthActual YTD Forecast
2016/17 2016/17'000 '000 $ Variance % Variance
Salaries & Benefits $22,261 $23,284 ($1,023) -4.4%Contract Services $6,743 $7,424 ($681) -9.2%Materials & Supplies $5,424 $6,809 ($1,386) -20.3%Power $3,346 $4,127 ($781) -18.9%Chemicals $2,487 $2,959 ($472) -16.0%Other Expenses $1,250 $1,312 ($63) -4.8%Depreciation $10,959 $11,622 ($663) -5.7%Total Operating Expenses $52,469 $57,539 ($5,070) -8.8%
Summary of Operating Expenses by Nature
ITEM # 4 HRWC Board
November 24, 2016
Page 6 of 7
Financial Revenue Investment income is below budget and the prior year. The decline in investment income has been somewhat offset by an increase in miscellaneous revenue, which includes various un-regulated activities such as tower leases, energy generation and rental properties. Financial Expenses Long Term Debt costs are on par with budget and up slightly from the prior year due to higher levels of debt. The forecast for Long Term Debt costs will be updated in future projections based on the results from the Fall 2016 Debenture. The Fall Debenture was priced on Oct. 25, 2016 and resulted in an all-in rate of 2.44% for HRWC to borrow $7,052,667 over a 10 year term, with a 20 year amortization schedule. The following table shows operating results for each service.
Water Operations - Page 5 Water Operations show a profit of $4.2 million, compared to a profit of $1.6 million for the previous year at this time. Metered Sales revenue is up $2.4 million (9.5%). Operating Expenses have decreased by $1.0 million (4.6%) which is primarily attributable to savings in Administration and Pension. Wastewater Operations - Page 6 Wastewater Operations show a profit of $5.2 million, up from a profit of $3.4 million in the prior year. Wastewater revenue has increased $1.9 million from the prior year, with Metered Sales and Septage Tipping Fees accounting for the increase. Operating expenses have decreased by $0.7 million from the previous year. Higher costs in some categories have been offset by savings in others. Stormwater Operations - Page 7 Stormwater Operations show a profit of $1.9 million, an improvement over the profit of $1.4 million for the same period last year. Stormwater Revenue and Expenses are similar to the prior year figures.
2016/17 2015/16'000 '000
Water $4,231 $1,652Wastewater $5,208 $3,372Stormwater $1,855 $1,414Net Surplus (Deficit) $11,294 $6,437
Year to Date Operating Results by Service
ITEM # 4 HRWC Board
November 24, 2016
Page 7 of 7
Regulated and Unregulated Operations - Page 8 Activities regulated by the NSUARB show a profit of $10.5 million, ahead of the $5.9 million profit for the same period last year. Unregulated activities show a profit of $0.8 million, an increase from the profit of $0.5 million for the prior year. Notable increases in Unregulated Revenue are seen in Septage Tipping Fees and Energy Projects. Unregulated Expenses are higher than the prior year, particularly in the contracted Wastewater Treatment facilities.
Results under International Financial Reporting Standards - Pages 9 & 10 As noted previously, the AcSB requires HRWC, as a rate regulated utility, to report financial results using International Financial Reporting Standards (IFRS). On the IFRS Balance Sheet, Accumulated Depreciation is higher producing a lower value for assets, Contributed Capital is treated as a long term liability and amortized rather than being treated as a contribution to equity, and the Operating Surplus is much higher due to changes in the Income Statement. On the IFRS Income Statement, Operating Revenue is the same. Depreciation Expense is higher as contributed assets are depreciated and some assets are depreciated more quickly. Financial Revenue is higher as the amortization of contributed capital is treated as revenue. The most significant change is Financial Expenses are lower as there is no expense for the Long Term Debt Principal appropriation – a difference of $12.4 million to date and $22.7 million for the full year. The IFRS Net Profit for the year is $22.6 million. ATTACHMENT Unaudited Operating Results for the seven (7) months ended October 31, 2016
2016/17 2015/16'000 '000
Regulated Activities $10,535 $5,943Unregulated Activities $759 $494Net Surplus (Deficit) $11,294 $6,437
Results by Activity
Report prepared by: Original Signed By:
Warren Brake, Manager, Accounting, B.Comm, CPA, CGA
ITEM # 4HRWC BOARD
November 24, 2016Page 1 of 10
HALIFAX WATERUNAUDITED BALANCE SHEET - CONSOLIDATED
AS OF OCTOBER 31, 2016
2016 2015'000 '000
ASSETS
Cash $58,363 $39,788 Amounts Receivable $37,263 $34,239 Materials & Supplies $1,613 $1,554 Prepaid Expenses $273 $224
$97,512 $75,805
Regulatory Asset $3,468 $3,676 Plant in Service $1,044,404 $995,558 Assets Under Construction $41,531 $62,092
$1,089,403 $1,061,326
Unamortized Debt Discount & Issue Expense $1,057 $1,007
$1,187,973 $1,138,137
LIABILITIES & CAPITAL
Trade Payables & Accrued Liabilities $19,506 $20,397 Deposits & Unearned Revenue $3,900 $6,450 Current Portion of LT Debt $23,195 $22,374
$46,601 $49,221
Pension & Accrued Retirement Benefits $60,206 $70,832 RDC & Special Purpose Reserves $11,078 $13,716 Long Term Debt $204,947 $194,578
Total Liabilities $322,831 $328,347
Capital Surplus, Committed Reserves, & Accumulated OCI $846,028 $800,417 Operating Surplus $7,819 $2,936 Excess (Deficiency) of Revenue over Expenditure - Consolidated $11,294 $6,437
Total Capital & Surplus $865,141 $809,790
$1,187,973 $1,138,137
G:\Finance\general\Fin Acct\Excel\FinStmts\Month\2016‐17\7_FS OCT 16
ITEM # 4HRWC BOARD
November 24, 2016Page 2 of 10
HALIFAX WATER
APRIL 1/16 - OCTOBER 31/16 (7 MONTHS)58.33%
ACTUAL ACTUAL APR 1/16 APR 1/16(CURRENT MONTH) (YEAR TO DATE) MAR 31/17 MAR 31/17
THIS YEAR LAST YEAR THIS YEAR LAST YEAR BUDGET* FORECAST % of'000 '000 DESCRIPTION '000 '000 '000 '000 FORECAST
$11,292 $11,521 OPERATING REVENUE $82,193 $78,234 $135,675 $135,898 60.48%
$6,944 $7,942 OPERATING EXPENSES $52,469 $54,379 $102,426 $98,638 53.19%
$4,348 $3,579 OPERATING PROFIT $29,724 $23,855 $33,250 $37,260 79.77%
FINANCIAL REVENUE$75 $74 INVESTMENT INCOME $434 $480 $810 $810 53.59%
$167 $167 PNS FUNDING HHSP DEBT $1,167 $1,167 $2,000 $2,000 58.33%$61 $25 MISCELLANEOUS $277 $175 $504 $504 54.91%
$302 $265 $1,878 $1,822 $3,314 $3,314 56.65%
FINANCIAL EXPENSES$709 $713 LONG TERM DEBT INTEREST $5,046 $5,101 $8,872 $8,872 56.88%
$1,800 $1,647 LONG TERM DEBT PRINCIPAL $12,426 $11,392 $22,652 $22,652 54.86%$16 $15 AMORTIZATION DEBT DISCOUNT $115 $103 $199 $199 57.84%
$382 $377 DIVIDEND/GRANT IN LIEU OF TAXES $2,692 $2,642 $4,663 $4,578 58.79%$4 $1 MISCELLANEOUS $28 $2 $24 $74 38.30%
$2,910 $2,752 $20,308 $19,240 $36,410 $36,375 55.83%
NET PROFIT (LOSS) BEFORE $1,740 $1,092 OTHER COMPREHENSIVE INCOME $11,294 $6,437 $154 $4,199 268.95%
$0 $0 OTHER COMPREHENSIVE INCOME $0 $0 $0 $0
NET PROFIT (LOSS) AVAILABLE FOR$1,740 $1,092 CAPITAL EXPENDITURES $11,294 $6,437 $154 $4,199 268.95%
UNAUDITED INCOME STATEMENT - CONSOLIDATED
G:\Finance\general\Fin Acct\Excel\FinStmts\Month\2016‐17\7_FS OCT 16
ITEM # 4HRWC BOARD
November 24, 2016Page 3 of 10
HALIFAX WATERUNAUDITED BALANCE SHEET
AS OF OCTOBER 31, 2016
2016 2015'000 '000
ASSETS
Cash $58,363 $39,788
Amounts ReceivableCustomers & Contractual $15,879 $12,205 Customers & Contractual - Unbilled Services $17,457 $17,702 Halifax Regional Municipality $3,927 $4,332
Materials & Supplies $1,613 $1,554 Prepaid Expenses $273 $224
$97,512 $75,805
Regulatory Asset $3,468 $3,676 Plant in Service - Water $584,609 $567,439 Plant in Service - Wastewater $695,811 $643,325 Plant in Service - Stormwater $131,419 $118,065
Less: Accumulated Depreciation - Water ($167,223) ($156,826) Accumulated Depreciation - Wastewater ($174,098) ($152,593) Accumulated Depreciation - Stormwater ($26,114) ($23,852)
$1,047,873 $999,234 Assets Under Construction $41,531 $62,092
$1,089,403 $1,061,326
Unamortized Debt Discount & Issue Expense $1,057 $1,007
$1,187,973 $1,138,137
LIABILITIES & CAPITAL
Trade $11,162 $12,201 Interest on Long Term Debt $2,591 $2,448 Halifax Regional Municipality $5,754 $5,748
Contractor & Customer Deposits $189 $186 Unearned Revenue $3,711 $6,263
Current Portion of LT Debt $23,195 $22,374 $46,601 $49,221
Accrued Post-Retirement Benefits $466 $458 Accrued Pre-Retirement Benefit $3,675 $3,568 Deferred Pension Liability $56,065 $66,805
Special Purpose Reserves not allocated to projects $1,822 $5,477 Regional Development Charge $9,255 $8,239
Long Term Debt-Water $59,424 $53,568 Long Term Debt-Wastewater $134,466 $132,569 Long Term Debt-Stormwater $11,056 $8,442
Total Liabilities $322,831 $328,347
Capital Surplus $875,194 $828,417 Committed Reserves $2,391 $13,946 Accumulated Other Comprehensive Income ($43,936) ($54,325)Operating Surplus used to Fund Capital $12,380 $12,380 Operating Surplus $7,819 $2,936 Excess (Deficiency) of Revenue over Expenditure - Consolidated $11,294 $6,437
Total Capital & Surplus $865,141 $809,790
$1,187,973 $1,138,137
G:\Finance\general\Fin Acct\Excel\FinStmts\Month\2016‐17\7_FS OCT 16
ITEM # 4HRWC BOARD
November 24, 2016Page 4 of 10
APR 1/16 APR 1/16MAR 31/17 MAR 31/17
THIS YEAR LAST YEAR THIS YEAR LAST YEAR BUDGET* FORECAST % of % of'000 '000 DESCRIPTION '000 '000 '000 '000 BUDGET* FORECAST
REVENUE$3,851 $3,822 METERED SALES - WATER $28,156 $25,715 $46,475 $46,475 60.58% 60.58%$5,619 $5,867 METERED SALES - WASTEWATER $41,364 $39,693 $68,052 $68,052 60.78% 60.78%
$572 $557 STORMWATER SITE GENERATED SERVICE $3,923 $3,923 $6,708 $6,708 58.48% 58.48%$590 $669 FIRE PROTECTION $4,127 $4,685 $7,074 $7,074 58.33% 58.33%$323 $323 STORMWATER RIGHT OF WAY SERVICE $2,264 $2,264 $3,881 $3,881 58.33% 58.33%$258 $222 OTHER SERVICES AND FEES $1,821 $1,450 $2,586 $2,809 70.43% 64.85%
$45 $33 CUSTOMER LATE PAY./COLLECTION FEES $296 $306 $530 $530 55.95% 55.95%$34 $27 MISCELLANEOUS $241 $198 $369 $369 65.45% 65.45%
$11,292 $11,521 $82,193 $78,234 $135,675 $135,898 60.58% 60.48% EXPENSES
$552 $551 WATER SUPPLY & TREATMENT $3,993 $4,191 $7,983 $7,983 50.02% 50.02%$578 $633 TRANSMISSION & DISTRIBUTION $4,734 $4,736 $8,710 $8,657 54.35% 54.69%$734 $728 WASTEWATER COLLECTION $4,932 $5,352 $9,446 $9,334 52.22% 52.84%
$1,236 $1,683 WASTEWATER TREATMENT PLANTS $9,719 $9,884 $19,425 $18,189 50.03% 53.43%$271 $400 STORMWATER COLLECTION $2,191 $2,317 $4,761 $4,803 46.03% 45.63%$264 $278 SMALL SYSTEMS AND OTHER SERVICES $1,693 $1,570 $3,132 $2,968 54.06% 57.04%$160 $143 SCADA, CONTROL & PUMPING $1,168 $943 $2,089 $2,088 55.93% 55.96%$563 $488 ENGINEERING & INFORMATION SERVICES $4,217 $3,669 $8,067 $7,978 52.27% 52.86%$142 $208 ENVIRONMENTAL SERVICES $1,218 $1,310 $2,605 $2,605 46.77% 46.75%$341 $316 CUSTOMER SERVICE $2,460 $2,541 $4,419 $4,413 55.67% 55.73%$592 $1,000 ADMINISTRATION & PENSION $5,184 $7,191 $10,631 $9,696 48.77% 53.47%
$1,513 $1,513 DEPRECIATION $10,959 $10,675 $21,159 $19,923 51.79% 55.00%$6,944 $7,942 $52,469 $54,379 $102,426 $98,638 51.23% 53.19%
$4,348 $3,579 OPERATING PROFIT $29,724 $23,855 $33,250 $37,260 89.40% 79.77%
FINANCIAL REVENUE$75 $74 INVESTMENT INCOME $434 $480 $810 $810 53.59% 53.59%
$167 $167 PNS FUNDING HHSP DEBT $1,167 $1,167 $2,000 $2,000 58.33% 58.33%$61 $25 MISCELLANEOUS $277 $175 $504 $504 54.91% 54.91%
$302 $265 $1,878 $1,822 $3,314 $3,314 56.65% 56.65%
FINANCIAL EXPENSES$709 $713 LONG TERM DEBT INTEREST $5,046 $5,101 $8,872 $8,872 56.88% 56.88%
$1,800 $1,647 LONG TERM DEBT PRINCIPAL $12,426 $11,392 $22,652 $22,652 54.86% 54.86%$16 $15 AMORTIZATION DEBT DISCOUNT $115 $103 $199 $199 57.84% 57.84%
$382 $377 DIVIDEND/GRANT IN LIEU OF TAXES $2,692 $2,642 $4,663 $4,578 57.73% 58.79%$4 $1 MISCELLANEOUS $28 $2 $24 $74 119.28% 38.30%
$2,910 $2,752 $20,308 $19,240 $36,410 $36,375 55.78% 55.83%
NET PROFIT (LOSS) BEFORE $1,740 $1,092 OTHER COMPREHENSIVE INCOME $11,294 $6,437 $154 $4,199 7325.00% 268.95%
$0 $0 OTHER COMPREHENSIVE INCOME $0 $0 $0 $0
NET PROFIT (LOSS) AVAILABLE FOR$1,740 $1,092 CAPITAL EXPENDITURES $11,294 $6,437 $154 $4,199 7325.00% 268.95%
(CURRENT MONTH) (YEAR TO DATE)
HALIFAX WATERUNAUDITED INCOME STATEMENT - ALL SERVICES
APRIL 1/16 - OCTOBER 31/16 (7 MONTHS)58.33%
ACTUAL ACTUAL
G:\Finance\general\Fin Acct\Excel\FinStmts\Month\2016‐17\7_FS OCT 16
ITEM # 4HRWC BOARD
November 24, 2016Page 5 of 10
APR 1/16 APR 1/16MAR 31/17 MAR 31/17
THIS YEAR LAST YEAR THIS YEAR LAST YEAR BUDGET* FORECAST % of'000 '000 DESCRIPTION '000 '000 '000 '000 FORECAST
REVENUE$3,851 $3,822 METERED SALES $28,156 $25,715 $46,475 $46,475 60.58%
$590 $669 FIRE PROTECTION $4,127 $4,685 $7,074 $7,074 58.33%$73 $61 PRIVATE FIRE PROTECTION SERVICES $481 $386 $840 $840 57.29%$35 $33 BULK WATER STATIONS $254 $205 $326 $326 77.79%$23 $14 CUSTOMER LATE PAY./COLLECTION FEES $156 $111 $203 $203 76.68%$14 $11 MISCELLANEOUS $99 $75 $142 $142 69.18%
$4,586 $4,610 $33,272 $31,177 $55,061 $55,061 60.43% EXPENSES
$552 $551 WATER SUPPLY & TREATMENT $3,993 $4,191 $7,983 $7,983 50.02%$578 $633 TRANSMISSION & DISTRIBUTION $4,734 $4,736 $8,710 $8,657 54.69%$86 $81 SMALL SYSTEMS (inc. Contract Systems) $603 $599 $883 $883 68.35%$58 $59 SCADA, CONTROL & PUMPING $428 $379 $846 $846 50.65%
$227 $224 ENGINEERING & INFORMATION SERVICES $2,048 $1,836 $3,848 $3,848 53.21%$17 $37 ENVIRONMENTAL SERVICES $248 $281 $515 $515 48.09%
$174 $161 CUSTOMER SERVICE $1,253 $1,295 $2,251 $2,249 55.74%$304 $510 ADMINISTRATION & PENSION $2,647 $3,662 $5,416 $4,940 53.58%$614 $622 DEPRECIATION $4,441 $4,401 $8,563 $8,131 54.61%
$2,610 $2,878 $20,395 $21,381 $39,015 $38,051 53.60%
$1,976 $1,731 OPERATING PROFIT $12,877 $9,796 $16,047 $17,010 75.70%
FINANCIAL REVENUE$34 $37 INVESTMENT INCOME $196 $241 $365 $365 53.71%$34 $19 MISCELLANEOUS $212 $145 $432 $432 49.12%$68 $56 $408 $387 $796 $796 51.22%
FINANCIAL EXPENSES$201 $203 LONG TERM DEBT INTEREST $1,425 $1,459 $2,486 $2,486 57.33%$706 $633 LONG TERM DEBT PRINCIPAL $4,874 $4,379 $8,576 $8,576 56.83%
$7 $7 AMORTIZATION DEBT DISCOUNT $55 $50 $100 $100 54.89%$382 $377 DIVIDEND/GRANT IN LIEU OF TAXES $2,692 $2,642 $4,663 $4,578 58.79%
$0 $1 MISCELLANEOUS $9 $2 $24 $24 35.99%$1,297 $1,221 $9,054 $8,531 $15,848 $15,764 57.43%
NET PROFIT (LOSS) AVAILABLE FOR$747 $566 CAPITAL EXPENDITURES $4,231 $1,652 $995 $2,042 207.19%
ACTUAL(CURRENT MONTH)
UNAUDITED INCOME STATEMENT - WATER OPERATIONSHALIFAX WATER
APRIL 1/16 - OCTOBER 31/16 (7 MONTHS)58.33%
ACTUAL(YEAR TO DATE)
G:\Finance\general\Fin Acct\Excel\FinStmts\Month\2016‐17\7_FS OCT 16
ITEM # 4HRWC BOARD
November 24, 2016Page 6 of 10
ACTUAL ACTUAL APR 1/16 APR 1/16(CURRENT MONTH) (YEAR TO DATE) MAR 31/17 MAR 31/17
THIS YEAR LAST YEAR THIS YEAR LAST YEAR BUDGET* FORECAST % of'000 '000 DESCRIPTION '000 '000 '000 '000 FORECAST
REVENUE$5,619 $5,867 METERED SALES $41,364 $39,693 $68,052 $68,052 60.78%
$0 $10 WASTEWATER OVERSTRENGTH AGREEMENTS $23 $81 $0 $23 100.00%$25 $30 LEACHATE $184 $151 $389 $389 47.34%$7 $4 CONTRACT REVENUE $43 $56 $86 $86 49.78%
$17 $17 DEWATERING FACILITY/SLUDGE LAGOON $122 $107 $210 $210 58.33%$0 $0 AIRLINE EFFLUENT $54 $32 $86 $86 63.33%
$101 $67 SEPTAGE TIPPING FEES $660 $432 $650 $850 77.70%$19 $15 CUSTOMER LATE PAY./COLLECTION FEES $112 $155 $257 $257 43.53%$11 $10 MISCELLANEOUS $84 $74 $133 $133 63.55%
$5,799 $6,020 $42,647 $40,782 $69,862 $70,084 60.85% EXPENSES
$734 $728 WASTEWATER COLLECTION $4,932 $5,352 $9,446 $9,334 52.84%$1,236 $1,683 WASTEWATER TREATMENT PLANTS $9,719 $9,884 $19,425 $18,189 53.43%
$86 $82 SMALL SYSTEMS $670 $558 $1,251 $1,248 53.69%$57 $84 DEWATERING FACILITY/ SLUDGE MGM'T $210 $227 $556 $396 53.13%$13 $5 BIOSOLIDS TREATMENT $51 $55 $101 $101 50.81%$22 $26 LEACHATE CONTRACT $158 $131 $341 $341 46.41%$98 $81 SCADA, CONTROL & PUMPING $716 $545 $1,215 $1,215 58.98%
$251 $227 ENGINEERING & INFORMATION SERVICES $1,867 $1,576 $3,629 $3,552 52.56%$75 $100 ENVIRONMENTAL SERVICES $606 $627 $1,254 $1,225 49.47%
$144 $133 CUSTOMER SERVICE $1,038 $1,072 $1,864 $1,862 55.73%$247 $422 ADMINISTRATION & PENSION $2,182 $3,036 $4,485 $4,091 53.34%$850 $853 DEPRECIATION $6,174 $6,008 $11,982 $11,157 55.33%
$3,813 $4,425 $28,324 $29,071 $55,549 $52,710 53.73%
$1,986 $1,595 OPERATING PROFIT $14,323 $11,711 $14,312 $17,374 82.44%
FINANCIAL REVENUE$34 $37 INVESTMENT INCOME $196 $239 $365 $365 53.71%
$167 $167 PNS FUNDING HHSP DEBT $1,167 $1,167 $2,000 $2,000 58.33%$27 $5 MISCELLANEOUS $65 $30 $72 $72 89.48%
$227 $209 $1,427 $1,435 $2,437 $2,437 58.57%
FINANCIAL EXPENSES$458 $464 LONG TERM DEBT INTEREST $3,276 $3,321 $5,817 $5,817 56.32%
$1,042 $926 LONG TERM DEBT PRINCIPAL $7,192 $6,404 $12,978 $12,978 55.42%$8 $7 AMORTIZATION DEBT DISCOUNT $55 $49 $89 $89 62.11%$4 $0 MISCELLANEOUS $20 $0 $0 $50 39.39%
$1,512 $1,397 $10,543 $9,774 $18,884 $18,934 55.68%
NET PROFIT (LOSS) AVAILABLE FOR$701 $407 CAPITAL EXPENDITURES $5,208 $3,372 ($2,135 ) $877 593.89%
UNAUDITED INCOME STATEMENT - WASTEWATER OPERATIONSHALIFAX WATER
APRIL 1/16 - OCTOBER 31/16 (7 MONTHS)58.33%
G:\Finance\general\Fin Acct\Excel\FinStmts\Month\2016‐17\7_FS OCT 16
ITEM # 4HRWC BOARD
November 24, 2016Page 7 of 10
ACTUAL ACTUAL APR 1/16 APR 1/16(CURRENT MONTH) (YEAR TO DATE) MAR 31/17 MAR 31/17
THIS YEAR LAST YEAR THIS YEAR LAST YEAR BUDGET* FORECAST % of'000 '000 DESCRIPTION '000 '000 '000 '000 FORECAST
REVENUE$572 $557 STORMWATER SITE GENERATED SERVICE $3,923 $3,923 $6,708 $6,708 58.48%$323 $323 STORMWATER RIGHT OF WAY SERVICE $2,264 $2,264 $3,881 $3,881 58.33%
$3 $4 CUSTOMER LATE PAY./COLLECTION FEES $29 $40 $70 $70 41.34%$9 $7 MISCELLANEOUS $58 $49 $93 $93 62.44%
$908 $891 $6,274 $6,275 $10,753 $10,753 58.35% EXPENSES
$271 $400 STORMWATER COLLECTION $2,191 $2,317 $4,761 $4,803 45.63%$3 $3 SCADA, CONTROL & PUMPING $24 $18 $28 $28 85.38%
$85 $37 ENGINEERING & INFORMATION SERVICES $303 $256 $590 $578 52.39%$50 $70 ENVIRONMENTAL SERVICES $364 $402 $835 $865 42.10%$23 $22 CUSTOMER SERVICE $169 $174 $303 $303 55.73%$40 $69 ADMINISTRATION & PENSION $355 $494 $729 $665 53.34%$49 $38 DEPRECIATION $344 $266 $614 $635 54.27%
$522 $639 $3,750 $3,927 $7,862 $7,876 47.61%
$386 $253 OPERATING PROFIT $2,524 $2,348 $2,891 $2,877 87.73%
FINANCIAL REVENUE$8 $0 INVESTMENT INCOME $43 $0 $81 $81 52.55%$0 $0 MISCELLANEOUS $0 $0 $0 $0 0.00%$8 $0 $43 $0 $81 $81 52.55%
FINANCIAL EXPENSES$49 $45 LONG TERM DEBT INTEREST $345 $321 $569 $569 60.59%$52 $88 LONG TERM DEBT PRINCIPAL $361 $609 $1,098 $1,098 32.89%
$1 $1 AMORTIZATION DEBT DISCOUNT $5 $4 $11 $11 49.77%$102 $134 $711 $934 $1,678 $1,678 42.39%
NET PROFIT (LOSS) AVAILABLE FOR$291 $119 CAPITAL EXPENDITURES $1,855 $1,414 $1,294 $1,280 144.91%
HALIFAX WATERUNAUDITED INCOME STATEMENT - STORMWATER OPERATIONS
APRIL 1/16 - OCTOBER 31/16 (7 MONTHS)58.33%
G:\Finance\general\Fin Acct\Excel\FinStmts\Month\2016‐17\7_FS OCT 16
ITEM # 4HRWC BOARD
November 24, 2016Page 8 of 10
ACTUAL APR 1/16 APR 1/16(YEAR TO DATE) MAR 31/17 MAR 31/17 % of
DESCRIPTION THIS YEAR LAST YEAR BUDGET* FORECAST FORECAST
REGULATED ACTIVITIES
REVENUE METERED SALES $73,443 $69,331 $121,235 $121,235 60.58% FIRE PROTECTION $4,127 $4,685 $7,074 $7,074 58.33% PRIVATE FIRE PROTECTION $481 $386 $840 $840 57.29% STORMWATER SERVICE $2,264 $2,264 $3,881 $3,881 58.33% OTHER OPERATING REVENUE $792 $778 $1,203 $1,225 64.66%
$81,108 $77,444 $134,234 $134,256 60.41% EXPENSES WATER SUPPLY & TREATMENT $3,993 $4,191 $7,983 $7,983 50.02% TRANSMISSION & DISTRIBUTION $4,734 $4,736 $8,710 $8,657 54.69% WASTEWATER & STORMWATER COLLECTION $7,110 $7,668 $14,207 $14,137 50.29% WASTEWATER TREATMENT PLANTS $9,719 $9,884 $19,425 $18,189 53.43% SMALL SYSTEMS $1,265 $1,154 $2,116 $2,112 59.88% SCADA, CONTROL & PUMPING $1,168 $943 $2,089 $2,088 55.96% ENGINEERING & INFORMATION SERVICES $4,217 $3,669 $8,067 $7,978 52.86% ENVIRONMENTAL SERVICES $1,218 $1,310 $2,605 $2,605 46.75% CUSTOMER SERVICE $2,439 $2,521 $4,384 $4,378 55.71% ADMINISTRATION & PENSION $5,171 $7,180 $10,610 $9,676 53.45% DEPRECIATION $10,955 $10,672 $21,159 $19,923 54.99%
$51,990 $53,927 $101,354 $97,726 53.20%
FINANCIAL REVENUE INVESTMENT INCOME $434 $480 $810 $810 53.59% MISCELLANEOUS $1,263 $1,185 $2,125 $2,125 59.44%
$1,697 $1,665 $2,935 $2,935 57.83% FINANCIAL EXPENSES LONG TERM DEBT INTEREST $5,046 $5,101 $8,872 $8,872 56.88% LONG TERM DEBT PRINCIPAL $12,426 $11,392 $22,652 $22,652 54.86% AMORTIZATION DEBT DISCOUNT $115 $103 $199 $199 57.84% DIVIDEND/GRANT IN LIEU OF TAXES $2,692 $2,642 $4,663 $4,578 58.79% MISCELLANEOUS $0 $0 $0 $0 0.00%
$20,280 $19,238 $36,386 $36,302 55.86% NET PROFIT (LOSS) AVAILABLE FOR CAPITAL EXPENDITURES $10,535 $5,943 ($571 ) $3,163 333.04%
UNREGULATED ACTIVITIES
REVENUE SEPTAGE TIPPING FEES $660 $432 $650 $850 77.70% LEACHATE $184 $151 $389 $389 47.34% CONTRACT REVENUE $43 $56 $86 $86 49.78% DEWATERING $122 $107 $210 $210 58.33% AIRLINE EFFLUENT $54 $32 $86 $86 63.33% ENERGY PROJECTS $97 $15 $184 $184 53.00% MISCELLANEOUS $22 $12 $22 $22 99.75%
$1,183 $806 $1,625 $1,825 64.80% EXPENSES WATER SUPPLY & TREATMENT $9 $3 $18 $18 46.82% WASTEWATER TREATMENT $434 $413 $998 $837 51.78% MISCELLANEOUS $27 $0 $37 $37 72.50% SPONSORSHIPS & DONATIONS $33 $32 $56 $56 59.68% DEPRECIATION $3 $3 $0 $0 0.00%
$505 $452 $1,109 $948 53.31% FINANCIAL REVENUE MISCELLANEOUS $110 $141 $232 $232 47.25%
$110 $141 $232 $232 47.25% FINANCIAL EXPENSES MISCELLANEOUS $28 $2 $24 $74 38.30%
$28 $2 $24 $74 38.30% NET PROFIT (LOSS) AVAILABLE FOR CAPITAL EXPENDITURES $759 $494 $726 $1,036 73.26%
NET PROFIT (LOSS) AVAILABLE FOR TOTAL CAPITAL EXPENDITURES (REG & UNREG) $11,294 $6,437 $154 $4,199 268.95%
HALIFAX WATERUNAUDITED INCOME STATEMENT - REGULATED AND UNREGULATED OPERATIONS
APRIL 1/16 - OCTOBER 31/16 (7 MONTHS)58.33%
G:\Finance\general\Fin Acct\Excel\FinStmts\Month\2016‐17\7_FS OCT 16
ITEM # 4HRWC BOARD
November 24, 2016Page 9 of 10
HALIFAX WATERUNAUDITED BALANCE SHEET - IFRS FORMAT
AS OF OCTOBER 31, 2016
2016 2015'000 '000
ASSETS
Cash $58,363 $39,788
Amounts ReceivableCustomers & Contractual $15,879 $12,205 Customers & Contractual - Unbilled Services $17,457 $17,702 Halifax Regional Municipality $3,927 $4,332
Materials & Supplies $1,613 $1,554
Prepaid Expenses $273 $224 $97,512 $75,805
Regulatory Asset $3,468 $3,676 Plant in Service - Water $584,609 $567,439 Plant in Service - Wastewater $695,811 $643,325 Plant in Service - Stormwater $131,419 $118,065
Less: Accumulated Depreciation - Water ($172,919) ($161,431) Accumulated Depreciation - Wastewater ($180,826) ($158,239) Accumulated Depreciation - Stormwater ($26,114) ($23,852)
$1,035,449 $988,984 Assets Under Construction $41,531 $62,092
$1,076,980 $1,051,076
Unamortized Debt Discount & Issue Expense $1,057 $1,007
$1,175,549 $1,127,887
LIABILITIES
Trade $11,162 $12,201 Interest on Long Term Debt $2,591 $2,448 Halifax Regional Municipality $5,754 $5,748
Contractor & Customer Deposits $189 $186 Unearned Revenue $3,711 $6,263
Current Portion of Deferred Contributed Capital $12,526 $12,526 Current Portion of LT Debt $23,195 $22,374
$59,127 $61,747
Accrued Post-Retirement Benefits $466 $458 Accrued Pre-Retirement Benefit $3,675 $3,568 Deferred Pension Liability $56,065 $66,805
Deferred Contributed Capital $704,952 $694,193
Long Term Debt-Water $59,424 $53,568 Long Term Debt-Wastewater $134,466 $132,569 Long Term Debt-Stormwater $11,056 $8,442
Total Liabilities $1,029,232 $1,021,349
EQUITYAccumulated Other Comprehensive Income ($43,936) ($54,325)Accumulated Surplus $167,607 $144,299 Excess (Deficiency) of Revenue over Expenditure $22,646 $16,564
Total Equity $146,317 $106,538
$1,175,549 $1,127,887
G:\Finance\general\Fin Acct\Excel\FinStmts\Month\2016‐17\7_FS OCT 16
ITEM # 4HRWC BOARD
November 24, 2016Page 10 of 10
APR 1/16 APR 1/16MAR 31/17 MAR 31/17
THIS YEAR LAST YEAR THIS YEAR LAST YEAR BUDGET* FORECAST % of % of'000 '000 DESCRIPTION '000 '000 '000 '000 BUDGET* FORECAST
REVENUE$3,851 $3,822 METERED SALES - WATER $28,156 $25,715 $46,475 $46,475 60.58% 60.58%$5,619 $5,867 METERED SALES - WASTEWATER $41,364 $39,693 $68,052 $68,052 60.78% 60.78%
$572 $557 STORMWATER SITE GENERATED SERVICE $3,923 $3,923 $6,708 $6,708 58.48% 58.48%$590 $669 FIRE PROTECTION $4,127 $4,685 $7,074 $7,074 58.33% 58.33%$323 $323 STORMWATER RIGHT OF WAY SERVICE $2,264 $2,264 $3,881 $3,881 58.33% 58.33%$258 $222 OTHER SERVICES AND FEES $1,821 $1,450 $2,586 $2,809 70.43% 64.85%
$45 $33 CUSTOMER LATE PAY./COLLECTION FEES $296 $306 $530 $530 55.95% 55.95%$34 $27 MISCELLANEOUS $241 $198 $369 $369 65.45% 65.45%
$11,292 $11,521 $82,193 $78,234 $135,675 $135,898 60.58% 60.48% EXPENSES
$552 $551 WATER SUPPLY & TREATMENT $3,993 $4,191 $7,983 $7,983 50.02% 50.02%$578 $633 TRANSMISSION & DISTRIBUTION $4,734 $4,736 $8,710 $8,657 54.35% 54.69%$734 $728 WASTEWATER COLLECTION $4,932 $5,352 $9,446 $9,334 52.22% 52.84%
$1,236 $1,683 WASTEWATER TREATMENT PLANTS $9,719 $9,884 $19,425 $18,189 50.03% 53.43%$271 $400 STORMWATER COLLECTION $2,191 $2,317 $4,761 $4,803 46.03% 45.63%$264 $278 SMALL SYSTEMS AND OTHER SERVICES $1,693 $1,570 $3,132 $2,968 54.06% 57.04%$160 $143 SCADA, CONTROL & PUMPING $1,168 $943 $2,089 $2,088 55.93% 55.96%$563 $488 ENGINEERING & INFORMATION SERVICES $4,217 $3,669 $8,067 $7,978 52.27% 52.86%$142 $208 ENVIRONMENTAL SERVICES $1,218 $1,310 $2,605 $2,605 46.77% 46.75%$341 $316 CUSTOMER SERVICE $2,460 $2,541 $4,419 $4,413 55.67% 55.73%$592 $1,000 ADMINISTRATION & PENSION $5,184 $7,191 $10,631 $9,696 48.77% 53.47%
$2,736 $2,720 DEPRECIATION $19,394 $19,124 $21,159 $21,157 91.66% 91.67%$8,167 $9,149 $60,904 $62,828 $102,426 $99,871 59.46% 60.98%
$3,125 $2,372 OPERATING PROFIT $21,288 $15,407 $33,250 $36,027 64.03% 59.09%
FINANCIAL REVENUE$75 $74 INVESTMENT INCOME $434 $480 $810 $810 53.59% 53.59%
$167 $167 PNS FUNDING HHSP DEBT $1,167 $1,167 $2,000 $2,000 58.33% 58.33%$1,093 $1,051 MISCELLANEOUS $7,638 $7,359 $504 $504 1514.77% 1514.77%$1,335 $1,291 $9,239 $9,005 $3,314 $3,314 278.77% 278.77%
FINANCIAL EXPENSES$709 $713 LONG TERM DEBT INTEREST $5,046 $5,101 $8,872 $8,872 56.88% 56.88%
$16 $15 AMORTIZATION DEBT DISCOUNT $115 $103 $199 $199 57.84% 57.84%$382 $377 DIVIDEND/GRANT IN LIEU OF TAXES $2,692 $2,642 $4,663 $4,578 57.73% 58.79%
$4 $1 MISCELLANEOUS $28 $2 $24 $74 119.28% 38.30%$1,110 $1,105 $7,881 $7,848 $13,758 $13,724 57.29% 57.43%
NET PROFIT (LOSS) BEFORE $3,350 $2,558 OTHER COMPREHENSIVE INCOME $22,646 $16,564 $22,806 $25,617 99.30% 88.40%
$0 $0 OTHER COMPREHENSIVE INCOME $0 $0 $0 $0 0.00% 0.00%
NET PROFIT (LOSS) AVAILABLE FOR$3,350 $2,558 CAPITAL EXPENDITURES $22,646 $16,564 $22,806 $25,617 99.30% 88.40%
(CURRENT MONTH) (YEAR TO DATE)
HALIFAX WATERUNAUDITED INCOME STATEMENT - IFRS FORMAT - ALL SERVICES
APRIL 1/16 - OCTOBER 31/16 (7 MONTHS)58.33%
ACTUAL ACTUAL
G:\Finance\general\Fin Acct\Excel\FinStmts\Month\2016‐17\7_FS OCT 16
ITEM #6 HRWC Board
November 24, 2016
TO: Ray Ritcey, Chair and Members of the Halifax Regional Water
Commission Board SUBMITTED BY: Original Signed By: Reid Campbell, M.Eng., P.Eng., Director, Water Services APPROVED: Original Signed By: Carl Yates M.A.Sc., P.Eng., General Manager DATE: November 18, 2016 SUBJECT: Lead Service Line Replacement Program – Application to the
NSUARB ORIGIN Lead Service Line Replacement Program Business Plan, approved by the Halifax Water Board at the October 27, 2016 meeting. RECOMMENDATION It is recommended that the Halifax Water Board approve an application to the Nova Scotia Utility and Review Board, to amend the Halifax Water Rules and Regulations, to enable Halifax Water to financially contribute to the replacement of Lead Service Lines (LSL’s) on private property in the following two circumstances:
1. Where Halifax Water, due to an unplanned or emergency circumstance disturbs or replaces a LSL, the LSL will be replaced in its entirety at Halifax Water’s expense.
2. In any other circumstance where a LSL is replacement is planned, including both customer initiated and Halifax Water initiated, Halifax Water will contribute 25% of the cost of the replacement of the LSL on private property up to a maximum contribution of $2,500.
Page 1 of 5
ITEM #6 HRWC Board
November 24, 2016
BACKGROUND Halifax Water does not currently have the authority to spend rate base funds on private property. Accordingly, any time Halifax Water has replaced a LSL, the customer has been responsible for replacing the LSL on their property. Halifax Water estimates that no more than 10% of Halifax Water customers have chosen to replace their LSL when Halifax Water initiates replacement of the public portion. As a consequence, staff estimate that there are approximately 10,000 private LSL’s remaining despite the fact that all but 2,500 public LSL’s have been replaced. Research conducted through our NSERC Industrial Chair by Dalhousie University has established that, at best, there is no benefit to replacing only a portion of the LSL and in many cases, a partial replacement will result in increased lead levels within the customer’s premise. This research has been confirmed by numerous researchers. A white paper released by the USEPA in October, 2016, proposes that new regulations permit only complete LSL replacement. With the knowledge that partial LSL replacement increases lead levels and that only 10% of customers replace the private portion of their LSL, in 2012, Halifax Water stopped doing partial replacements. The consequence of this is that to replace our remaining 2500 LSL’s we are dependent on convincing the customer to replace their LSL. This has two further consequences. Halifax Water can no longer do larger scale LSL replacement programs as part of Halifax street and sidewalk renewal programs which are the most cost effective way to replace public LSL’s. As well, Halifax Water has been deferring renewal of water mains on streets with LSL’s which is a sub-optimal asset renewal decision which will, with time, create a backlog of overdue water main renewal projects. DISCUSSION The two circumstances, cited in the recommendation have different motivating factors and will be discussed individually as follows. Unplanned or Emergency LSL Replacement
In a small number of cases each year, Halifax Water is required to replace a LSL on short notice. These include:
• Detecting a leaking public LSL.
• Repairing a water main break where a LSL is connected to the repaired section.
• Having to renew Halifax Water infrastructure where a LSL is connected or in the vicinity.
• Inadvertently disturbing a LSL (physical disturbance of an LSL can have the same effects as a partial replacement).
Page 2 of 5
ITEM #6 HRWC Board
November 24, 2016
In these circumstances, the outcome for the customer will be, in a majority of cases, an increase in lead levels experienced inside the home. Because Halifax Water activity has resulted in damaging of the customer’s private property, resulting in increased exposure to lead, the appropriate response is for Halifax Water to immediately address the situation by replacing the customer’s LSL to the water meter. Planned LSL Renewals Halifax Water’s business plan for LSL replacement, consistent with the National (US) Drinking Water Advisory Council (NDWAC) recommendations, is based on replacing all LSL’s in the Halifax Water system by 2050. In order to do this, Halifax Water will have to communicate frequently with customers to ensure that they take steps to replace the private portion of the LSL. The NDWAC recommendations also make clear that LSL replacement is a shared responsibility between the utility and the customer. In Halifax Water’s experience, there are numerous barriers to customer’s replacing their LSL’s. These include:
• Not believing themselves to be at risk;
• Not seeing it as a worthwhile investment in their property;
• Lack of understanding of how to have the work done;
• Lack of time to prepare to have the work done;
• Cost Halifax Water’s business plan includes steps to work with customers to address all of these barriers. These steps include planned discussions with Halifax municipal staff as to whether financing LSL replacement on the tax bill is an option and with senior levels of government to explore whether existing funding programs could be directed to LSL replacement. Notwithstanding these steps, staff believe that the cost barrier will remain a significant one with the average cost of LSL replacement being approximately $5,000. Further, as the program progresses, lacking a financial assistance program, the first few years of LSL replacement will be limited to customers with the financial means and motivation to do the LSL replacement unassisted. With time, the group of remaining LSL customers, yet to be addressed, will be weighted to those who are financially disadvantaged. There is a direct benefit to Halifax Water in providing a financial incentive to customer to replace their LSL. Currently, having made the decision to cease partial LSL replacements, Halifax Water is unable to conduct full street or neighbourhood replacement programs in conjunction with Halifax street and sidewalk projects. This is the most efficient means of replacing LSL’s compared to “one-of” replacements and the ability to share in street restoration costs. With a financial incentive as part of the
Page 3 of 5
ITEM #6 HRWC Board
November 24, 2016
approach to address customer barriers to replacement, there is a much greater probability of being able to assemble full street projects. Further, as indicated above, Halifax Water is currently making sub-optimal water main renewal choices by avoiding streets with LSL’s. Staff is therefore recommending that a financial incentive of 25% of the replacement cost be provided for planned LSL renewal’s up to a maximum contribution of $2,500. The cap of $2,500 is proposed on the bases that a maximum project cost of $10,000 captures the full cost range in the vast majority of cases. Private renewal projects in excess of $10,000 would typically involve high end private property improvements. The basis for the 25% contribution limit recognizes that this is still primarily a private property responsibility and aligns with Halifax Water intentions in having the customer opt to proceed. The 25% contribution is also consistent with the planned transmission main upgrade on Quinpool Road in Halifax. The NSUARB has recently approved the Quinpool Road Transmission Main Structural Lining project scheduled for construction in 2017. This project will require that approximately 12 LSL’s be replaced and Halifax Water has proposed that replacement of the private portion of the LSL be included in the project. As the project is 75% funded by senior levels of government, Halifax Water is, in this case, responsible for 25% of the cost of the private LSL renewal. Bill 62, introduced in the fall session of the Nova Scotia Legislature received Royal Assent on November 10. This Bill amends the Municipal Government Act and the Halifax Charter to permit municipalities to finance water supply infrastructure on private property. This Bill, intended to enable municipalities to assist homeowners with private property water supply issues experienced in this summer’s drought, is sufficiently broad to facilitate private LSL replacement. Even with the financial incentive, the decision to replace the private LSL will remain a voluntary choice by the customer. Regardless of incentives, there will remain a small portion of customers who are unwilling or unable to replace their LSL. A variety of business processes will need to be developed to define how Halifax Water staff and contractors interact with the customer on private property including a legal release that the customer will be required to execute in advance. Development of these processes will be a priority in the coming months, ahead of the 2017 construction season. BUDGET IMPLICATIONS Much work needs to be completed to determine how many private LSL’s are remaining in the system but the current estimate is 10,000. The average cost to replace a private LSL is approximately $5,000 with an average proposed utility contribution of $1,250. Based on this, in 2016 dollars, the cost of this program is $12.5 million over 30 years.
Page 4 of 5
ITEM #6 HRWC Board
November 24, 2016
In order to replace all public LSL’s by 2050, Halifax Water will need to ramp up from its current replacement rate of 25 to 100 per year. This will require an increase in program funding for service replacement from current levels to approximately $1 million per year. In the initial years of the program the focus will be on public LSL replacements and associated private LSL replacements. Costs for the program will be accommodated within annual capital budgets. ALTERNATIVES None recommended. ATTACHMENT
Report Prepared by: Original Signed By: Reid Campbell, M.Eng., P.Eng., Director, Water Services 902-490-4877
Financial Reviewed by: Original Signed By:
Cathie O’Toole, MBA, CPA, CGA, Director, Corporate Services 902-490-3685
Page 5 of 5
ITEM# 1-I Page 1 of 16 HRWC Board November 24, 2016
TO: Ray Ritcey, Chair and Members of the Halifax Regional Water Commission
Board SUBMITTED BY: Original Signed By:
Cathie O’Toole, MBA, CPA, CGA, Director, Corporate Services Original Signed By: Reid Campbell, P.Eng., Director, Water Services Original Signed By: Susheel Arora, M.A.Sc., P.Eng., Director, Wastewater & Stormwater Services
Original Signed By: Kenda MacKenzie, P.Eng., Director, Regulatory Services APPROVED: Original Signed By:
Carl D. Yates, M.A.Sc., P.Eng., General Manager SUBJECT: Financial and Operations Information Report
INFORMATION REPORT ORIGIN: Regular update. This report provides a high level overview of financial and operational performance for the utility. Financial results are presented first, followed by indicators and statistics for water and wastewater.
ITEM# 1-I Page 2 of 16
HRWC Board November 24, 2016
FINANCIAL
ITEM# 1-I Page 3 of 16
HRWC Board November 24, 2016
Regional Water Main Break/Leak Data
Water Accountability
Year
Total Breaks/Leaks
Current 12 Month Rolling Total (up to August 31/16)
Losses per Service Connection/Day
(International Water Association Standard) 2015/16 226
215
2014/15 210 Period Ending September 30, 2016
2013/14 213 Real Losses: 249 litres
CBS Target: 180
2012/13 262 2011/12 205
Total 1116
Yr. Avg. 217.6
Average Daily Water Production
ITEM# 1-I Page 4 of 16
HRWC Board November 24, 2016
ObjectiveTotal Sites
% of Sites Achieving Target
All Sites: 90th
Percentile < 15 µg/L
CBSC Awarded
Points
Disinfection 65 97% --- 17Total Trihalomethanes 24 100% --- 20Haloacetic Acids 21 95% --- 16Particle Removal 5 100% --- 20Corrosion Control* 69 --- 6.1 20TOTAL 93
Score: 93/100
Water Quality Master Plan Objectives
2016-2017 Q2
ITEM# 1-I Page 5 of 16
HRWC Board November 24, 2016
In this report each facility is assessed using monthly or quarterly averages, depending on the averaging period specified in its Approval to Operate.
CBOD5
(mg/L)
TSS (mg/L)
NSE Limit
Avg.NSE Limit
Avg.NSE Limit
Avg.NSE Limit
Avg.NSE Limit
Avg.NSE Limit
Avg.NSE Limit
Avg.NSE Limit
Avg.
Halifax 50 32 40 12 5000 1176 6-9 6.9 Continued
Dartmouth 50 37 40 16 5000 855 6-9 6.9 Continued
Herring Cove 50 23 40 15 5000 87 6-9 7.0 Continued
Eastern Passage 50 8 40 9 5000 61 6-9 7.1 Continued
Mill Cove 25 10 25 10 200 491 6.5-9 6.6 Continued
Springfield 20 3 20 4 200 10 6-9 6.8 0.02 1.03 Continued
Belmont 25 13 25 21 200 1842 6-9 6.8 0.02 0.10 Continued
Frame 20 9 20 12 200 69 6-9 6.5 0.02 0.00 Continued
Middle Musq. 20 5 20 11 200 21 6-9 7.4 Continued
Uplands 20 8 20 5 200 23 6-9 7.1 Continued
Aerotech 5 5 5 5 200 11 6-9 7.35.7 W 1.2 S
0.2 0.5 0.3 Continued
North Preston 10 5 10 3 200 10 6-9 7.0 3 0.2 1.5 0.8 Continued
Lockview 20 6 20 7 200 21 6.5-9 6.9 8.0 S 2.4 1.2 S 0.7 Continued
Steeves (Wellington) 20 5 20 1 200 10 6.5-9 7.4 14.4 S 0.1 1.0 S 0.1 Continued
BLT 15 7 20 12 200 10 6-9 7.35 W 3 S
2.23 W 1 S
2.1 0.02 0.12 5 6.6 Continued
Avg. of all Facilities
NOTES & ACRONYMS:CBOD5 - Carbonaceous 5-Day Biochemical Oxygen Demand NSE Compliant
TSS - Total Suspended Solids NSE Non-CompliantTRC - Total Residual ChlorineW / S - Winter / Summer compliance limitsNSE requires monthly averages be less than the NSE Compliance Limit for each parameter (Dartmouth, Eastern Passage, Halifax, Herring Cove, Mill Cove)NSE requires quarterly averages be less than the NSE Compliance Limit for each parameter (Aerotech, Lockview, Mid. Musq., Belmont, Frame, BLT, Uplands, North Preston, Steeves, Springfield)Continued - All parameters remain essentially unchanged since the last reportImproved - One or more parameter(s) became compliant since the last reportDeclined - One or more parameters(s) became non-compliant since the last report
12
LEGEND
6.60.30.81.07.0313
-
10
No t acute ly le tha l
Trend Toxicity
Dissolved Oxygen (mg/L)
-
-
-
-
- -
-
-
-
-
-
- - -
Wastewater Treatment Facility Compliance Summary
Rolling Averages - August, September and October 2016
-
-
-
-
- - -
- -
E. coli (counts/ 100mL)
pHAmmonia
(mg/L)Phosphorous
(mg/L)TRC
(mg/L)
-No t acute ly
le tha l
Lethal
Lethal
-
-
No t acute ly le tha l
Lethal
No t acute ly le tha l
-
- -
- -
-
-
-
-
-
-
Wastewater Treatment
Facility
-
-
- -
-
- - -
-
No t acute ly le tha l
- - -
-
ITEM# 1-I Page 6 of 16
HRWC Board November 24, 2016
NOTES & ACRONYMS: CSO - Combined Sewer Overflow SSO - Sanitary Sewer Overflow
Rainfall data is from Halifax Water’s rain gauge at the Halifax WWTF.
There were two overflows on days when there was no recorded rainfall, as follows:
1. July 13: The CSO at the Wallace St CSO was due to planned maintenance required to clear blockages caused by debris.
2. July 20: The CSO at the Wallace St CSO was due to blockages caused by debris.
ITEM# 1-I Page 7 of 16
HRWC Board November 24, 2016
NOTES & ACRONYMS: CSO - Combined Sewer Overflow SSO - Sanitary Sewer Overflow
Rainfall data is from Halifax Water’s rain gauge at the Halifax WWTF.
There were two overflows on days when there was no recorded rainfall, as follows:
1. August 20: The SSO at the Fish Hatchery Park PS was due to a mechanical failure at the station.
2. August 23: The CSO at the Wallace St CSO was due to a planned maintenance required to clear blockages caused by debris.
ITEM# 1-I Page 8 of 16
HRWC Board November 24, 2016
NOTES & ACRONYMS: CSO - Combined Sewer Overflow SSO - Sanitary Sewer Overflow
Rainfall data is from Halifax Water’s rain gauge at the Halifax WWTF.
There were no overflows on any days when there was no recorded rainfall.
ITEM# 1-I Page 9 of 16
HRWC Board November 24, 2016
Lower numbers represent better performance
ITEM# 1-I Page 10 of 16
HRWC Board November 24, 2016
Lower numbers represent better performance. TSS and cBOD Q3 averages were borderline with the NSE Approval limit, but considered to be within compliance.
Lower numbers represent better performance
ITEM# 1-I Page 11 of 16
HRWC Board November 24, 2016
Lower numbers represent better performance
Lower numbers represent better performance
ITEM# 1-I Page 12 of 16
HRWC Board November 24, 2016
Lower numbers represent better performance
Lower numbers represent better performance
ITEM# 1-I Page 13 of 16
HRWC Board November 24, 2016
Lower numbers represent better performance
Lower numbers represent better performance
ITEM# 1-I Page 14 of 16
HRWC Board November 24, 2016
Lower numbers represent better performance
Lower numbers represent better performance
ITEM# 1-I Page 15 of 16
HRWC Board November 24, 2016
Lower numbers represent better performance
Lower numbers represent better performance
ITEM# 1-I Page 16 of 16
HRWC Board November 24, 2016
Lower numbers represent better performance
Lower numbers represent better performance
ITEM 2-IHRWC Board
November 24, 2016
20-Apr-16
25-Apr-16
WATER
Approved Budget $16,453,000 97% WASTEWATER
Approvals to date $15,947,600 Approved Budget $35,838,000 88% Total Budget: $66,777,000.00
Approvals to date $31,424,200 Total To Date: $60,052,800.00
STORMWATER
Approved Budget $3,951,000 90% CORPORATE PROJECTS
Approvals to date $3,563,000 Approved Budget $10,535,000 77% Total % to date 90%
Approvals to date $9,118,000
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
$0
$2,000,000
$4,000,000
$6,000,000
$8,000,000
$10,000,000
$12,000,000
$14,000,000
$16,000,000
$18,000,000
$20,000,000
Water Budget
97%
$0
$500,000
$1,000,000
$1,500,000
$2,000,000
$2,500,000
$3,000,000
$3,500,000
$4,000,000Stormwater Budget
91%
$0
$2,000,000
$4,000,000
$6,000,000
$8,000,000
$10,000,000
$12,000,000
Corporate Projects
90%
$0
$5,000,000
$10,000,000
$15,000,000
$20,000,000
$25,000,000
$30,000,000
$35,000,000
$40,000,000
Wastewater Budget
88%
ITEM 2-I
HRWC Board
November 24, 2016
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
2016/17 Capital Budget
28-Jan-16 24-Mar-16 Advanced Funding Integrated Projects
East
Murray Hill Drive W/M Renewal $455,000 $455,000 Dexter $377,077 $479,730
Farquharson Street Water Main Renewal $500,000 $500,000 Dexter $387,693 $458,858
Brompton Road $215,000 $215,000 Dexter $166,299 $190,582
Everette Street Water Main Renewal $410,000 $410,000 Dexter $251,384 $328,500
24-Mar-16 West
Scarlet Rd $335,000 $335,000 Dexter
Foxglove Lane $150,000 $150,000 Dexter
Parmbelle Lane $250,000 $250,000 Dexter
George Dauphinee Drive $620,000 $620,000 Deferred to 2017
Layton Road $325,000 $325,000 Deferred to 2017
Inverness Avenue $260,000 $260,000 Dexter $169,621 $223,214
24-Mar-16 Central
Tillock Drive $380,000 $380,000 Sackville Trenching $256,059 $351,245
Tillock Court $100,000 $100,000
Included in Tillock
Drive Tender
Total Integrated Project $4,000,000 $4,000,000
5-Mar-15 13-Apr-15
Macdonald Bridge Transmission Main Replacement project $7,700,000:
funding in the amount of $354,000 is available from underspending on
the Kearney Lake Road Water Transmission Main Phase 2: funding
in the amount of $3,750,000 is available from the 2015/16
Capital Budget under "Macdonald Bridge Transmission Main Replacement"
and funding in the amount of $3,295,000 will be included in the 2016/17
Capital Budget $7,700,000 $3,295,000 CBCL
28-Jan-16 13-Apr-16 Valve Renewals $125,000 $125,000
28-Jan-16 13-Apr-16 Hydrant Renewals $75,000 $75,000
WATER
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
TOTAL CAPITAL BUDGET FOR WATER $16,453,000
Date of Approval
$563,792 $631,009
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
WATER
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
TOTAL CAPITAL BUDGET FOR WATER $16,453,000
Date of Approval
28-Jan-16 13-Apr-16 Service Line Renewals $190,000 $190,000
28-Jan-16 13-Apr-16 Large Tapping Machine c/w electric operator and 4" to 12" cutters $34,000 $34,000
28-Jan-16 13-Apr-16 Small Hydro Vac for valve box maintenance $25,000 $25,000
28-Jan-16 13-Apr-16 Plastic Shell Cutters for Tapping Machine $12,000 $12,000
28-Jan-16 13-Apr-16 Portable valve Exerciser $10,000 $10,000
28-Jan-16 13-Apr-16 Confined Space Entry System for Bennery Lake Water Supply Plant $14,000 $14,000
28-Jan-16 19-Feb-16 Geizer 158 Reservoir Rehabilitation $2,170,000 $2,170,000 MacDonald Appl. $1,711,189 $1,971,005
$5,950,000
Accumulative Total - January, 2016 $9,950,000
23-Feb-16 JD Kline Replace Power Pole at Low Lift Station $40,000 $40,000
23-Feb-16 Bedford Connector Transmission Main Phase 3 - Design $90,000 $90,000
23-Feb-16 Lyle Street Control Chamber Access Improvement $30,000 $30,000
23-Feb-16
Topsail Control Chamber - Confined Space Energy Retrofit - funding
available from underspending in 2015/16 CB under "Geizer 158 Retrofit
Chamber Retrofit which did not proceed last year $43,000 $0
23-Feb-16 Confined Space Entry Retrofit - Bridgeview PRV Chamber $79,000 $79,000
23-Feb-16 Robie 2 Chamber Upgrades $160,000 $160,000
23-Feb-16 Automated Flushing Program $20,000 $20,000
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
WATER
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
TOTAL CAPITAL BUDGET FOR WATER $16,453,000
Date of Approval
24-Feb-16 Relocated CT Calculation Equipment Lucasville Meter Chamber $31,000 $31,000
23-Feb-16
Critical Valves Bedford Hwy - funding in the amount of $57,000 is available
from underspending in SAP #3-1921 2015/16 Capital Budget $57,000 $0
25-Feb-16 6-Apr-16 Lake Major Water Supply Plant - New Diesel Generator $1,900,000 $1,900,000
Accumulative Total - February, 2016 $2,350,000
8-Mar-16 Bennery Lake WSP Surge Protection $17,000 $17,000
8-Mar-16 Lake Major WSP Purchase Fluorescence Meter $90,000 $90,000
8-Mar-16 Lake Major WSP - Replace Contactors in the MCC $34,000 $34,000
8-Mar-16 Lake Major WSP - Integrate Chlorine Alarms $50,000 $50,000
8-Mar-16 Lake Major WSP Chemical Feed Pump Replacements $85,000 $85,000
8-Mar-16 JD Kline WSP New Laptop system to Backwash Filters $12,000 $12,000
8-Mar-16 JD Kline WSP - Ampgard III to Vacuum Contactor Conversion Program $40,000 $40,000
8-Mar-16 Purchase Inline Zeta Potential Meters for Water Plants $100,000 $100,000
8-Mar-16 Purchase Particle Counters for Water Plants $235,000 $235,000
30-Mar-16 Lake Major WSP - Dewatering Equipment $100,000 $100,000
30-Mar-16
Cliff Street Watermain Replacement was not originally budgeted for in
2016/17. Funding in the amount of $60K is available from underspending in
the "First Street Watermain Renewal Project" (SAP3-2028) $60,000 $0
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
WATER
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
TOTAL CAPITAL BUDGET FOR WATER $16,453,000
Date of Approval
30-Mar-16
Lake Major WSP - Dedicated Service Water Pumping Station
Design Phase $60,000 $60,000
30-Mar-16 Bennery Lake WSP - Power Monitoring $20,000 $20,000
30-Mar-16 Lake Major WSP - Replace Fluoride System $10,000 $10,000
30-Mar-16
J.D. Kline Replace Turbidimeters and ph. Meters
project was not identified for 2016/17. Funding in the amount of $11K is
available from underspending in the 2015/16 JD Kline Chemical Feed Pump
Replacement Program $11,000 $0
30-Mar-16 2015/16 CB Governor's Brook Transmission Main Oversizing $197,000 $0
30-Mar-16 Lakeside Timberlea CCC 2015/16 $2,000 $0
31-Mar-16 22-Apr-16 JD Kline WSP - Replacement of the Lime Feed and Delivery System $300,000 $300,000
Accumulative Total - March, 2016 $1,153,000
15-Apr-16 4-May-16 Bennery Lake WSP Plate Settlers $440,000 $440,000
Accumulative Total - April , 2016 $440,000
25-May-16 Rechlorination Station Upgrades $26,000 $26,000
25-May-16 Versa Valve Removal Project $20,000 $20,000
25-May-16 Temporary Water Line - Pipe Materials Purchase East Region $18,000 $18,000
25-May-16 Water Distribution Pressure Monitoring Equipment $10,000 $10,000
25-May-16 Belmont PRV Valve Replacement $10,000 $10,000
25-May-16 Chlorine Analyzer Replacement Program $23,000 $23,000
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
WATER
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
TOTAL CAPITAL BUDGET FOR WATER $16,453,000
Date of Approval
25-May-16 Zinck PRV Meter Replacement $8,000 $8,000
25-May-16 Bedford Reservoir Inflow Meter Replacement $8,000 $8,000
Accumulative Total - May , 2016 $123,000
24-Jun-16
Gander Avenue Water Main Renewal Integrated Project
This project was not budgeted for in 2016/17: Funding in the amount of
$140,000 from underspending in the Farquaharson Street WM Project, and
$100,000 is available from underspending in the Everette Street and
Brompton Avenue Water Main Renewal IP $240,000 $0 Dexter Construction $230,480 $240,000
27-Jun-16
Courtney Road Meter Chamber Abandonment project was not budgeted for in
the 2016/17 CB. Funding in the amount of $17,000 is available from the
2015/16 CB - Renfrew abandonment project which has been deferred to
another budget year $17,000 $0
29-Jun-16 Lake Major Water Supply Plant - Isolating the Treatment Trains $68,000 $68,000
30-Jun-16 7-Jul-16
Geizer 158 Reservoir Rehabilitation - Floor Replacement project was not
budgeted for in 2016/17
Funding in the amount of $2.75 Million is available from underspending
on the Macdonald Bridge Transmission main project which will be re-
budgeted for in 2017/18 $2,750,000 $0
Accumulative Total - June , 2016 $68,000
5-Jul-16 JD Kline WSP Industrial Water Pumps Upgrade $160,000 $160,000
13-Jul-16 JD Kline - Pump Station MCC Ventilation $72,000 $72,000
22-Jul-16 JD Kline WSP Geosmin Taxonomy Study $165,000 $165,000
29-Jul-16 Water Treatment Facility Security Upgrades $50,000 $50,000
29-Jul-16Horne's Road Bridge Watermain Replacement Project was not budgeted for
in 2016/17: Funding in the amount of $90,000 is available from
underspending on the Tillock Drive WM Renewal Project (SAP $3-2307) $90,000 $0
Accumulative Total - July , 2016 $447,000
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
WATER
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
TOTAL CAPITAL BUDGET FOR WATER $16,453,000
Date of Approval
22-Aug-16
Bennery Lake Water Supply Plant - Low Lift VFD Pump Replacement
Program $110,000 $110,000
23-Aug-16 Water Sampling Station Relocation Program $29,000 $29,000
31-Aug-16
CSE Retrofits - Central Region project was not included in the 2016/17 CB:
Funding in the amount of $100K is available from underspending in the (SAP
#3-2307) Tillock Court Water Main Project $100,000 $0
31-Aug-16
Hare Lane WM Emergency Renewal Project was not budgeted for in
2016/17: Funding in the amount of $25K is available from underspending in
the Murray Hill WM Renewal Project $25,000 $0
Accumulative Total - August, 2016 $139,000
06-Sep-16 Water transmission Main Condition Assessment Program $75,000 $75,000
06-Sep-16 Water Structures Condition Assessment Program $150,000 $150,000
15-Sep-16
JD Kline WS Plant Building Roof Renewal project was not identified in
2016/17: Funding in the amount of $155K is available from the 2015/16 CB
under: Wastewater - JD Kline Entrance Road Project which will be deferred
to 2017/18 $145,000 $0
23-Sep-16 Lake Major HVAC Study $100,000 $100,000
23-Sep-16 JD Kline WSP Raw Water Pump Upgrade Study $230,000 $230,000
23-Sep-16
JD Kline WSP Uninterruptible Power Supply System Replacement project in
the amount of $30,000 was not budgeted for in 2016/17
Funding in the amount of $30,000 is available from underspending in SAP #3-
1420 (2010/11 CB) (JD Kline Replace Raw Water Pump) which is under
budget $30,000 $0
23-Sep-16 Peninsula Low North Transmission Main Rehabilitation Design $40,000 $40,000
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
WATER
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
TOTAL CAPITAL BUDGET FOR WATER $16,453,000
Date of Approval
29-Sep-16 31-Oct-16
Quinpool Road/Peninsula Transmission Main Rehabilitation was not
budgeted for in 2016/17
funding from CWWF provides 75% cost sharing, with HW providing 25%
of eligible costs, and 100% of ineligible costs. This will equate to $469,500
from CWWF and $206,500 from HW
Funding in the amount of $206,500 is available from underspending in the
"Water - Critical Valves project which is not proceeding this year $676,000 $676,000
Accumulative Total - September, 2016 $1,271,000
11-Oct-16
Lake Major WSP Fire Alarm System Upgrades project was not
budgeted for in 2016/17: Funding in the amount of $30K is available from
underspending in the Lake Major WSP Replace Lime Feed & Delivery$30,000 $0
12-Oct-16
Bedford West CCC (Wastewater) Various Phases 2016/17
$6,600 from the $14,000 in Item 3.045 Bedford West CCC and $11,200 from
the $66,000 in Item 2.074 Bedford West CCC $6,600 $6,600
Accumulative Total - October, 2016 $6,600
9-Nov-16
JD Kline Water Supply Plant - Man Down System was not budgeted for in
2016/17 Funding in the amount of $10,000 is available from underspending
in the 2016/17 CB under "JD Kline Electric Motor Power Efficiency
Upgrades Projects (SAP #3-1521)$10,000 $0
Accumulative Total - November, 2016 $0
Total To Date $15,947,600
ITEM 2-I
HRWC Board
November 24, 2016
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
28-Jan-16 24-Mar-16
2016/17 Capital Budget Advanced Funding Integrated
Projects
East
Murray Hill Drive W/M Renewal $38,000 $38,000 Dexter Construction $6,166 $27,810
Farquharson Street Water Main Renewal $109,000 $109,000 Dexter Construction $56,966 $78,215
Brompton Road $278,000 $278,000 Dexter Construction $141,471 $199,881
Everette Street Water Main Renewal $97,000 $97,000 Dexter Construction $52,608 $69,524
Alfred Street $199,000 $199,000 Dexter Construction $55,663 $148,477
Beckfoot Drive $9,000 $9,000 to be undertaken by HW Ops
Strath Lane $226,000 $226,000 Dexter Construction $86,977.00 $147,739.00
Westwood Drive $121,000 $121,000 Dexter Construction $5,769.00 $8,690.00
28-Jan-16 24-Mar-16 West Dexter Construction $20,112.00 $56,488.00
Scarlet Rd $206,000 $206,000
Foxglove Lane $13,000 $13,000
Parmbelle Lane $79,000 $79,000
George Dauphinee Drive $54,000 $54,000 deferred to 2017
Layton Road $13,000 $13,000 work not required
Inverness Avenue $22,000 $22,000 work not required
28-Jan-16 24-Mar-16 Central
Tillock Drive $13,000 $13,000 to be undertaken by HW Ops
Tillock Court $9,000 $9,000 to be undertaken by HW Ops
Doyle Street $19,000 $19,000
McQuarrie Bridge (Fall River) $150,000 $150,000 work not required
Lydgate Drive $9,000 $9,000 to be undertaken by HW Ops
Total Integrated Projects $1,664,000
WASTEWATER
TOTAL CAPITAL BUDGET FOR WASTEWATER $35,838,000
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
Date of Approval
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
WASTEWATER
TOTAL CAPITAL BUDGET FOR WASTEWATER $35,838,000
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
Date of Approval
28-Jan-16 13-Apr-16 Manhole Renewals $32,000 $32,000
28-Jan-16 13-Apr-16 Lateral Replacements $2,190,000 $2,190,000
28-Jan-16 13-Apr-16 SIR Program Flow Meters and Related Equipment $40,000 $40,000
26-Nov-16 12-Jan-16 Corporate Flow Monitoring Program (2015/16, 2016/17) $660,000 $660,000
28-Jan-16 13-Apr-16 Miscellaneous Equipment Replacement $70,000 $70,000
28-Jan-16 10-Mar-16
Wastewater System - Trenchless Rehabilitation Program:
Funding in the amount of $300,000 from underspending in the
2015/16 Sewer Lining Program: and $1,500,000 is available
from the 2016/17 Capital Budget $1,800,000 $1,500,000 Insituform Tec Limited $805,192 $1,472,779
29-Jan-16
Leiblin Pumping Station Elimination Preliminary
Design Halifax $75,000 $75,000 HW staff
$4,567,000
Accumulative Total - January, 2016 $6,231,000
03-Feb-16
The $42,500 in regulated activity funding is available from two
sources. $20,000 is available from underspending on the Mill
Cove CHP Fatal Flaw/Due Diligence Analysis, and the
Preliminary Design and Cost Analysis , with the remaining
$22,500 available from projected under spending within the
2015/16 Wastewater – Energy – Energy Management Capital
Program. The $42,500 in unregulated activity funding is
available from within the 2016/17 Unregulated Capital Budget -
Mill Cove Biogas CHP. $85,000 $0
19-Feb-16Bisset Pumping Station Forcemain Replacement
project from 2015/16 Capital Budget $240,000 $0
25-Feb-16 8-Apr-16 Balsam Road Pumping Station (PS) Elimination $770,000 $770,000 Dexter Construction
25-Feb-16 5-Apr-16 Northwest Arm Sewer Rehabilitation - Detailed Design $300,000 $300,000 Robinson Consultants $588,150 $585,900
25-Feb-16 6-Apr-16 Waterfront Drive Wastewater System Replacement $500,000 $500,000
Project deferred pending
outcome of other capital work
Accumulative Total - February 2016 $1,570,000
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
WASTEWATER
TOTAL CAPITAL BUDGET FOR WASTEWATER $35,838,000
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
Date of Approval
09-Mar-16
Wastewater Pump Station Upgrade Program - East Region
2015/16 Capital Budget $110,000 $0
10-Mar-16
HRM Land Transfer - Subdivision Costs
Project was not included in the 2016/17 Budget. Funding in the
amount of $75,000 is available from underspending in the
Lakeside Pumping Station Diversion Project in the 2015/16 CB $75,000 $0
29-Mar-16
Halifax WWTF - Various Upgrades: $76,000:
Funding available from underspending in 2012/13 CB in the
following projects:
Dartmouth WWTF HHSP Upgrades $5,000
Herring Cove WWTF HHSP Upgrades 13/14 CB $41,000
Halifax WWTF HHSP Upgrades 13/14 CB $14,000
Lakeside PS Diversion to HFX Sewershed: $16,000 $76,000 $0
29-Mar-16
WW Pump Station Upgrade Program
Central Region (2015/16 CB) $70,000 $0
31-Mar-16 26-May-16
Bedford PS Rehabilitation (at Mill Cove WWTF) funding in the
amount of $2.85M is available from the 2016/17 CB
The remainder of funds in the amount of $400K is available from
underspending in the 2015/16 Lakeside Pumping Station
Diversion Project which came in under budget $3,250,000 $2,850,000 Filtrum Inc. $1,495,600
31-Mar-16 14-Apr-16
2015/16 Wastewater Pumping Station Upgrade Program -
West Region $420,000 $0
Accumulative Total - March 2016 $2,850,000
04-Apr-16
North Park Upgrade Integrated Project - Additional scope
funding in the amount of $55K is available from under spending
in the 2015/16 CB under Lahey Road Integrated Project $55,000 $0
04-Apr-16 2015/16 Wet Weather Management Program $125,000 $0
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
WASTEWATER
TOTAL CAPITAL BUDGET FOR WASTEWATER $35,838,000
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
Date of Approval
15-Apr-16
HWWTF Halifax Wastewater Treatment Facility
Ventilation Air Heat Recovery Project
This project was originally scheduled for 2017/18. Due to the
successful results from Herring Cove WWTF Vent Air Heat
Recovery project, it was decided to use the funds allocated
from 2015/16 CB under "WW HCWWTF - Heat Recovery
Phase 2 - Effluent Heat Recovery $250,000 $0
28-Apr-16 22-Aug-16
Aerotech WWTF Expansion and Upgrade Project -
Construction / Design $22,755,000 $13,960,000
Accumulative Total - April 2016 $13,960,000
3-May-16 Eastern Passage WWTF Secondary Clarifier Launder Covers $49,000 $49,000
03-May-16
Mill Cove WWTF - Various Capital Projects:
Compressor Replacement: $20,000
Entrance Gate Replacement: $20,000
Wet Scrubber Media Replacement: $20,000
Digester Roof Coating: $135,000 $195,000 $195,000
04-May-16 Roach's Pond Pumping Station - Trash Rack $75,000 $75,000
24-May-16 EPWWTF Process Water Filter Upgrades $26,000 $26,000
24-May-16 EPWWTF Automation of RAS Gates $97,000 $97,000
24-May-16
EPWWTF - Fall Protection Grates - Sludge Tank and Inlet
Chamber $6,000 $6,000
25-May-16 DWWTF - Influent Duty Pump Installation $160,000 $160,000
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
WASTEWATER
TOTAL CAPITAL BUDGET FOR WASTEWATER $35,838,000
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
Date of Approval
31-May-16
Mill Cove TF - Clarified Access - Project not budgeted for in
2016/17: Funding in the amount of $55K is available under
2016/17 "Emergency Wastewater Treatment Facility Equipment
replacement $200,000 $55,000
Accumulative Total - May 2016 $663,000
29-Jun-16 Pumping Station Standard $135,000 $135,000
29-Jun-16 Autoport Pleasant Street PS Replacement $200,000 $200,000
29-Jun-16
Additional Funding - Bedford CCC for Temporary
Pumping Station#1 and Phase 5-4: Funding in the amount of
$12,000 is available from underspending in the 2016/17 CB
under: Leiblin PS Elimination Project that came in under budget$12,000 $0
Accumulative Total - June, 2016 $335,000
05-Jul-16
NS Power Meter Relocations
Funding is available from the 2015/16 CB from underspending in
the Energy Management Retrofit Project $22,750 $0
05-Jul-16
Beechville Lakeside Timberlea WW Treatment Facility
Clarifier Access funding in the amount of $16K is available from
2016/17 CB - Emergency WW Treatment Facility Equipment
Replacements) $200,000 $16,000
06-Jul-16 HWWTF Installation of TSS Analyzer $82,000 $82,000
05-Jul-16 6-Sep-16 Eastern Passage Pumping Station - Efficiency/Pump Control $650,000 $650,000
19-Jul-16
Smallwood Avenue WW IP (2016) project was not
budgeted for in 2016/17: Funding in the amount of 72,000 is
available from the Waterfront Drive WW System Replacement
project which will not be proceeding at this time $72,000 $0 Dexter Construction $57,043 $46,929
25-Jul-16
Centrifuge Dewater Equipment - Mill Cove WWTF project was
not budgeted for in 2016/17: Funding in the amount of $167,000
is available from the Dartmouth Wastewater Treatment Facility -
Fine Screen Upgrade project which will not be proceeding this
year $1,000,000 $167,000
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
WASTEWATER
TOTAL CAPITAL BUDGET FOR WASTEWATER $35,838,000
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
Date of Approval
27-Jul-16
Springfield Lake WWTF - UV Installation was not budgeted for
in 2016/17. Funding in the amount of $245K is available from
the 2015/16 CB under "Frame Subdivision Wastewater
Collection System Replacement and Wastewater Treatment
Facility Upgrade which is under budget $245,000 $0
27-Jul-16
5000 lb. Forklift Acquisition Mill Cove Project was not budgeted
for in 2016/17: Funding in the amount of $25,000 is available
from the Corporate Projects - Fleet Upgrade Program
Wastewater $25,000 $0
22-Jul-16
Bedford Hwy SW System Emergency Repair was not budgeted
for in the 2016/17 CB: Funding in the amount of $75K is
available from underspending in the 2015/16 CB under the
Lakeview Ave Twin Culvert Replacement Project which came in
under budget $75,000 $0
29-Jul-16
Hines Road Sewer Odour Issue: Funding in the amount of $25K
is available under 2016/17 CB and the reminder of $35,000 is
available from underspending in the Shore Drive Forcemain
Replacement & Twinning project: $60,000 $25,000
29-Jul-16 Wastewater Treatment facility security upgrades $200,000 $200,000
29-Jul-16
Hornes Road Bridge Wastewater Main Replacement project was
not budgeted for in 2016/17: Funding in the amount of $90K is
available from the Waterfront Drive WW System Replacement
project which will not proceed at this time $90,000 $0
Accumulative Total - July, 2016 $1,140,000
11-Aug-16
Inglis Street Sewer - Hydraulic Analysis - Funding in the amount
of $33,000 is available from the 2015/16 CB and there is $250K
in the 2016/17 CB in which we are only
using $19K at this time $250,000 $19,000
12-Aug-16 Emergency Pumping Station Pump Replacements $270,000 $250,000
12-Aug-16 Wastewater Pumping Station Upgrade Program - West Region $225,000 $210,000
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
WASTEWATER
TOTAL CAPITAL BUDGET FOR WASTEWATER $35,838,000
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
Date of Approval
12-Aug-16 Wastewater Pumping Station Upgrade Program - East Region $200,000 $200,000
12-Aug-16 Wastewater Pumping Station Upgrade Program - Central Region $65,000 $65,000
23-Aug-16 BLT WWTF Lighting Upgrade $35,000 $25,000
31-Aug-16 EPWWTF - Storage Shed $41,000 $41,000
31-Aug-16 HWWTF Pump Replacement Sludge Mixing Systems $140,000 $82,000
31-Aug-16
Hammonds Plains Road SW IP (2016) was not budgeted for in
the 2016/17 CB. Funding is available from underspending in the
following three approved projects:
Herring Cove Road Culvert: $85,000
Drainage Remediation Program: $25,000
and Sackville Cross Road Stormwater system: $85,000
$195,000 $0
31-Aug-16
Mill Cove Biogas CHP - Detailed design and Cost Analysis
Funding in the amount of $16K is available from underspending
in the HWWTF OCS VDF Project (SAP 6-1028) which came in
under budget $16,000 $0
Accumulative Total - August, 2016 $892,000
06-Sep-16 19-Sep-16 BFP - Front End Loader Replacement $253,000 $253,000
06-Sep-16 Wastewater Forcemains Condition Assessment $75,000 $75,000
06-Sep-16 East and Central Wastewater Infrastructure Plan $225,000 $125,000
08-Sep-16
HWWTF - Emergency Raw Water Pump VFD Replacement:
Funding in the amount of $125K is available from the 2016/17
CB Under "WWTF - Emergency Equipment Replacement $200,000 $125,000
12-Sep-16 5-Oct-16 Mill Cove WW Treatment Facility UV Upgrade $2,080,000 $2,080,000
12-Sep-16 WWTF Plant Optimization Program $175,000 $175,000
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
WASTEWATER
TOTAL CAPITAL BUDGET FOR WASTEWATER $35,838,000
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
Date of Approval
29-Sep-16 27-Oct-16
Northwest Arm Rehabilitation - Detailed Design
The project is funded from the CWWF, the total cost to HW is
estimated to be $187,500 (25% of eligible costs) (25% of
$550,000) plus 100% ineligible costs (100% of $50,000) $300,000 $300,000
Accumulative Total - September, 2016 $3,133,000
11-Oct-16 RWWP Projects MCs, MC3, WW Storage Project $245,000 $245,000
12-Oct-16
Bedford West CCC (Wastewater) Various Phases 2016/17
$6,600 from the $14,000 in Item 3.045 Bedford West CCC and
$11,200 from the $66,000 in Item 2.074 Bedford West CCC $11,200 $11,200
18-Oct-16
Mill Cove Secondary Flow Instrumentation Replacement Project
was not budgeted for in 2016/17. Funding in the amount of $45K
is available from underspending in the DWWTF Fine Screen
Upgrade project which came in under budget $45,000 $45,000
24-Oct-16
Harbour Solutions WWTF Fine Screen Upgrades projects
(Various location):
Dartmouth WWTF: $109,000
Halifax WWTF Screen Upgrade: $75,000
Herring Cove WWTF - Screen Upgrade: $65,000
Funding in the amount of $249,000 is available from
underspending in the Dartmouth WWTF Fine Screen Upgrade
Project $1,000,000 $249,000
Accumulative Total - October 2016 $550,200
09-Nov-16 2016/17 Wet Weather Management Program $100,000 $100,000
Accumulative Total - November 2016 $100,000
Total To Date: $31,424,200
ITEM 2-I
HRWC Board
November 24, 2016
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
2016/17 Stormwater
Advanced Funding Integrated Projects
East
28-Jan-16 24-Mar-16 Murray Hill Drive W/M Renewal $28,000 $28,000 Dexter Construction $17,520 $21,292
Farquharson Street Water Main Renewal $19,000 $19,000 Dexter Construction $14,391 $13,036
Brompton Road $151,000 $151,000 Dexter Construction $35,835 $108,631
Everette Street Water Main Renewal $28,000 $28,000 Dexter Construction $5,319 $21,075
Alfred Street $11,000 $11,000
work to be undertaken
by HW Ops
Beckfoot Drive $9,000 $9,000 work not required
Strath Lane $122,000 $122,000
28-Jan-16 24-Mar-16 West
George Dauphinee Drive $34,000 $34,000 deferred to 2017
28-Jan-16 24-Mar-16 Central
Tillock Court $19,000 $19,000
work to be undertaken
by HW Ops
Doyle Street $75,000 $75,000 deferred to 2017
Baker Drive $52,000 $52,000 work not required
Second Avenue $70,000 $70,000
work to be undertaken
by HW Ops
Total Integrated Projects $618,000 $618,000
28-Jan-16 13-Apr-16 Manhole Renewals $29,000 $29,000
28-Jan-16 13-Apr-16 Catchbasin Renewals $29,000 $29,000
28-Jan-16 13-Apr-16 Lateral Replacements $87,000 $87,000
$145,000
Accumulative Total January, 2016 $763,000
STORMWATER
TOTAL CAPITAL BUDGET FOR STORMWATER $3,951,000
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
Date of Approval
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
STORMWATER
TOTAL CAPITAL BUDGET FOR STORMWATER $3,951,000
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
Date of Approval
23-Feb-16 Wilson Drive & Highway 2 - Culvert Replacement $223,000 $223,000 Harbour Constru. $109,270 $167,400
25-Feb-16 6-Apr-16 Sackville Cross Road Stormwater System Renewal $1,090,000 $1,090,000 Dexter Construction $659,680.71 $970,902.66
25-Feb-16 6-Apr-16 Bedford Highway at Shaunslieve Drive Culvert Upgrade $407,000 $247,000 Brycon Construction $152,128 $336,141
25-Feb-16 21-Mar-16
Sullivan's Pond Storm Sewer System Replacement - Design
Funding in the amount of $100,000 is available from 2015/16 CB
under "Stormwater Pipes - Sullivan's Pond Storm Sewer
Replacement - Phase 1 and $300,000 is available from the 2016/17
CB Under "Stormwater Pipes Sullivan's Pond Storm Sewer
Replacement Phase 1. The total approved to date is $950,000 $400,000 $300,000 CBCL
Accumulative Total February, 2016 $1,860,000
7-Apr-16 25-Apr-16 2016/17 Driveway Culvert Program $450,000 $450,000
Accumulative Total April, 2016 $450,000
30-May-16
Yankeetown Road (near Civic 258) Culvert Replacement was not
budgeted for in 2016/17: Funding in the amount of $200,000 is
available from underspending in the 2015/16 CB under Cow Bay
Road Deep Storm Sewer project which came in under budget $200,000 $0 Harbour Construction
Accumulative Total for May, 2016 $0
6-Jun-16 Bank of Montreal Stormwater Lateral - 5151 George Street $90,000 $90,000
Accumulative Total for June, 2016 $90,000
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
STORMWATER
TOTAL CAPITAL BUDGET FOR STORMWATER $3,951,000
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
Date of Approval
22-Jul-16
Bedford Hwy SW System Emergency Repair was not budgeted for in
the 2016/17 CB: Funding in the amount of $75K is available from
underspending in the 2015/16 CB under the Lakeview Ave Twin
Culvert Replacement Project which came in under budget $75,000 $0
22-Jul-16 Clement Street Berm - SW Control System $264,000 $264,000
29-Jul-16 Inverness Avenue Culvert Replacement Project $136,000 $136,000 Harbour Construction $83,496.24 $146,000.00
Accumulative Total for July, 2016 $400,000
23-Sep-16
Sycamore Lane Storm Sewer Replacement project was not budgeted
for in 2016/17 CB: Funding in the amount of $150,000 is available
from underspending in the Sackville Cross Road Stormwater System
Renewal project which came in under budget $150,000 $0
Accumulative Total for September 2016 $0
10-Nov-16
Ellenvale Run Retain Wall System project was not identified in the
2016/17 CB. Funding in the amount of $125,000 is available from
underspending in the Sackville Cross Road Stormwater System
Renewal Project which came in under budget $125,000 $0
Accumulative Total for November 2016 $0
Total to Date $3,563,000
ITEM 2-I
HRWC Board
November 24, 2016
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
30-Jul-15 15-Oct-15
Computerized Management Maintenance System Phase 2
(Project was approved in October 15, 2015 by NSUARB) $1,500,000 $1,500,000
28-Jan-16 13-Apr-16 Desktop Computer Replacement Program $180,000 $180,000
28-Jan-16 13-Apr-16 Network Infrastructure Upgrades $200,000 $200,000
28-Jan-16 13-Apr-16 Survey Equipment - GPS Total Station $30,000 $30,000
28-Jan-16 13-Apr-16 Document Management Program $200,000 $200,000
28-Jan-16 13-Apr-16 SharePoint $200,00 $200,000
AMI/AMR Meter System Upgrades $3,300,000 $3,300,000
28-Jan-16 13-Apr-16 Fleet Upgrade Program Water $505,000 $505,000
28-Jan-16 13-Apr-16 Fleet Upgrade Program Wastewater $920,000 $920,000
28-Jan-16 13-Apr-16 Fleet Upgrade Program Stormwater $230,000 $230,000
Accumulative Total January, 2016 $7,265,000
28-Apr-16 12-Aug-16 GIS Hardware/Software Program 2015/16 $400,000 $0
31-May-16 CRM Interfaces $200,000 $200,000
Accumulative Total May, 2016 $200,000
CORPORATE PROJECTS
TOTAL CAPITAL BUDGET FOR CORPORATE PROJECTS $10,535,000
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
Date of Approval
ITEM 2-I
HRWC Board
November 24, 2016
HRWC
BOARD GM NSUARB Description
Approved
Amount
Net Additions
to Budget
Consultant/
Contractor
Construction
Tender
Price
Construction
Budget
Estimate
CORPORATE PROJECTS
TOTAL CAPITAL BUDGET FOR CORPORATE PROJECTS $10,535,000
CAPITAL BUDGET APPROVALS TO DATE - 2016/17
Date of Approval
15-Jun-16 Customer Service Portal $220,000 $220,000
Accumulative Total June, 2016 $220,000
5-Jul-16
SCADA Control System Enhancements 2016/17 (cost are split 50/50 for
W/WW $200,000 $200,000
29-Jul-16 450 Cowie Hill Road External Lighting Project $25,000 $23,000
Accumulative Total July, 2016 $223,000
6-Sep-16 Asset Management Program Development $100,000 $100,000
6-Sep-16 Assess Asset Management Software - Part 2 $50,000 $50,000
23-Sep-16
Furniture & Building Improvements - Billing Services Project was not
budgeted for in the 2016/17 Capital Budget
Funding in the amount of $60,000 is available from underspending in the
2016/17 CB Under "Corporate Projects - IT Disaster Recovery Site"
which will not be proceeding this year $60,000 $60,000
Accumulative Total September, 2016 $210,000
21-Nov-16 GIS Data Program $1,000,000 $1,000,000
Accumulative Total November, 2016 $1,000,000
Total to date $9,118,000
Item 3-I17-Nov-16
FINANCIAL REPORT
Consolidated balance of the four operating accountsmaintained by the Commission as of: 17-Nov-i 6 $64,266,396
Rate of interest on the above balance - $64,266,395.86Investment Rate of Return 0.074%
ITEM # 4-I
HRWC Board November 24, 2016
Page 1 of 7
TO: Ray Ritcey, Chair and Members of the Halifax Regional Water
Commission Board SUBMITTED BY: Original Signed By:
Susheel Arora, M.A.Sc., P.Eng., Director, Wastewater & Stormwater Services
APPROVED: Original Signed By:
Carl Yates, M.A.Sc., P.Eng., General Manager DATE: November 14, 2016 SUBJECT: Wastewater Systems – Odour Management
INFORMATION REPORT
ORIGIN Operations staff in response to customer complaints and concerns experienced during summer, 2016 BACKGROUND Halifax Water owns and operates 15 Wastewater Treatment Facilities (WWTFs) and 172 Sewage Pump Stations (SPSs). These facilities range from very small packaged plants to large facilities with complex infrastructure. Similarly, there are small pump stations to very large pump stations. Most of these facilities, except for the small plants, are equipped with odour control systems that vary in design depending on the employed sewage treatment processes. The large pump stations are also equipped with carbon scrubbers. The Halifax Harbour Solutions facilities and Eastern Passage WWTF (EPWWTF) were designed with one of the most stringent odour control limits in the world; thus are equipped with industry leading equipment to address the stringent specifications. The scrubber system at the EPWWTF was designed and constructed to a performance specification of 6 parts per billion Hydrogen Sulphide (H2S) as measured at the stack exhaust in any five minute rolling average. The Harbour Solutions WWTFs were designed and constructed to performance standard of 4 parts per billion Total Reduced Sulphur (TRS) as measured at points of stack discharge over any 5 minute rolling
ITEM # 4-I HRWC Board
November 24, 2016
Page 2 of 7
average. To meet these stringent requirements multistage scrubber systems are used for air treatment in these facilities. Below is a summary of air scrubber treatment processes at the Harbour Solutions facilities. These facilities have three stage odour scrubbing equipment; an acid wash, base wash, and carbon system, as follows:
Chemical oxidation of organics by chlorine through the addition of sodium hypochlorite;
pH adjustment is performed by addition of caustic to improve oxidation in the second stage;
Residual organic scavenging is performed by a granular activated carbon (GAC) filter in the final stage.
Some of the other facilities have varying degree of odour control equipment but all of these have a final stage of carbon scrubbers. The following summarizes the treatment processes within the EPWWTF:
A front end bio-trickling filter consisting of porous media provides biological treatment of the building air;
A second stage biofilter consisting of gravel aggregate media provides secondary biological treatment;
Residual organic scavenging is performed by granular activated carbon (GAC) filter in the final stage.
Prior to treatment at any of Halifax Water WWTFs, sewage is conveyed though an extensive collection network. During collection, sewage often has to travel several kilometers before it reaches the WWTF which takes several hours. This travel time depletes the dissolved oxygen level creating septic conditions. The septic conditions promote H2S generation that can get released along the way. H2S provides for offensive odours when released to the atmosphere from the collections system or wastewater facility. Over the past summer there have been several complaints from several areas, more notably near the Eastern Passage, Dartmouth, and Mill Cove WWTFs. The other areas of concern have been in the collection system such as Hines Road in Dartmouth and Inglis Street in Halifax. The Hines Road sewer system is part of the Bissett Lake pump station sewershed; this area has reported odour problems for several years and efforts have been ongoing to mitigate the odours. It is noteworthy that all sewer systems that are subjected to high residence time of sewage have some level of odour.
ITEM # 4-I HRWC Board
November 24, 2016
Page 3 of 7
DISCUSSION Weather Impacts Before discussing the specific details of the various areas of concern, it is important to understand the impacts of weather phenomenon on odour potential in a community. The summer of 2016 was the driest and warmest experienced in HRM for decades. These warm and dry conditions contribute to septic conditions in sewer systems and plant processes in two ways. The warm sanitary sewer promotes increased biological growth rates that consume available oxygen leading to septic conditions that produce odorous sulfur compounds. Secondly, the low flow associated with dry conditions increases the hydraulic residence time (HRT) in the system which provides more time for the microbes to exert demand on dissolved oxygen. In tandem, these effects lead to dramatic increases in dissolved oxygen demand which leads to septic conditions. In addition to elevated sewer temperatures and increased HRT’s, low overnight temperatures associated with the intense high pressure system stationed off our region in September combined with calm winds to produce atmospheric inversions. The cooler nights were a mixed blessing, slightly reducing sewer temperatures but at the same time causing atmospheric inversions that hold air handling exhausts near the plant and at ground level. Despite extra efforts and due diligence, it is challenging to design and implement odour control systems for extreme events such as the weather pattern during the summer of 2016. Most sewer systems experience odour issues during extended droughts and the Halifax area is no exception. Notwithstanding these challenges, operations and engineering staff continue to address the identified point sources of odour as noted in the sections below.
Dartmouth Waste Water Treatment Facility (DWWTF) During the summer of 2016, staff received odour complaints from residents nearby the DWWTF. In response to these complaints, staff undertook multiple troubleshooting investigations and implemented many process changes. Below is a summary of efforts made to minimize odours at the facility:
In an effort to increase odour reducing chemicals in the wet scrubber system, staff installed a new chemical dosing pump on October 17, 2016. The new pump has a higher capacity and led to higher chlorine residuals in the recirculation fluid to mitigate odours;
Staff has also initiated a project to modify the fluid handling process for the side stream coming off the dewatering process which has high liquid phase sulfur concentrations. The changes will reduce the amount of hydrogen sulfide that is
ITEM # 4-I HRWC Board
November 24, 2016
Page 4 of 7
added to the building air and the scrubber system. This is scheduled to be complete by the end of November;
In addition to the unfavorable weather conditions, a diversion of sewer wastes from local haulers increased the septic loading to the Dartmouth WWTF from the middle of September to the middle of October. This timeframe coincided with the night time atmospheric inversions which compounded the issue. The septage volumes were reduced into this system in mid October;
A recent upgrade to the ducting system was performed to permit bypassing of the carbon scrubber system to facilitate maintenance. It was discovered that the isolation damper was not sealing as per the design; this was allowing untreated process air to bypass the wet scrubber system and be directly discharged. The bypass ducting isolation damper was sealed up around October 15, 2016 and this had a direct improvement on air quality;
It was also noticed on several occasions that the odour readings at the plant were below the specified limits of 25 ppb, however, the odour was generated from the contributory sewers; the manholes near the plant were treated with carbon inserts;
The sewage collection system was flushed on some streets in late August with jet trucks in the vicinity of locations that had potential for odour generation.
With the optimization efforts as described above, staff do not anticipate reoccurrence of the odour issues in the future. Staff will review Standard Operating Procedures and make the required modifications to ensure that the systems are performing at optimum levels before the onset of warmer temperatures.
Mill Cove Waste Water Treatment Facility (MCWWTF) The area around this treatment facility has seen tremendous growth in terms of condominiums and increased recreation at Dewolfe Park. During the summer months, offensive odours were mainly reported from residents living in the condominium buildings. The MCWWTF has 5 carbon scrubbers in various areas of the plant. There were several steps taken to mitigate the odours:
Introduction of Bioxide at Fish Hatchery WWPS located at the mouth of the Sackville River;
Carbon inserts were installed in the manholes at the intersection of Convoy Run and Waterfront Drive;
Increased monitoring at the fence line and in the adjacent neighborhood;
Increased sludge hauling frequency by additional 5 loads per week;
Covering the sludge trailer, and installed a scrubber on the trailer in July;
ITEM # 4-I HRWC Board
November 24, 2016
Page 5 of 7
Changed carbon in 4 carbon scrubbers: the headworks carbon scrubber media is scheduled for replacement in the Spring of 2017;
Sewer system flushing with jet trucks was conducted in the area;
Diversion of sewage waste from haulers dumping into a station at Memory Lane in Sackville to Aerotech WWTF beginning September 28, 2016.
Eastern Passage Waste Water Treatment Facility (EPWWTF) Staff received odour complaints from residents near the EPWWTF during the summer of 2016. Immediately staff investigated and undertook numerous actions to mitigate the issue. However, extenuating circumstances of ongoing warranty repairs to the EPWWTF compounded the challenges. The bio filter was not functioning as intended and the design build contractor performed the necessary repairs. In addition, at this particular location, odours also stem from the collection system and have been addressed through a formal study, as referenced further in this report. At the EPWWTF the following actions have been taken:
Staff are working with EPWWTF design-builder to have all warranty work completed in a timely manner;
Staff initiative a program of additional odour monitoring around the facility and neighbourhood;
Staff used chemical addition (bioxide) in the sludge holding tanks;
Modifications have been made to the ducting to improve ventilation near the distribution chamber of the headworks where the sewage enters the plant;
Passive carbon scrubbers have been installed on the sludge holding tank vents;
Ongoing optimization of odour control system operation.
Bissett Road Sewage Collection System A section of the Hines Road sewer was designed as a pressure sewer to eliminate the requirement of a pump station at the EPWWTF. The Bissett Road sewer system terminates at the Hines Road pressure sewer near CFB Shearwater. For an overview of the Bissett Lake sewershed, please see Figure 1, Bissett Road PS Sewer Collection System. As sewer travels in a gravity section it pulls air downstream due to friction between the liquid/air interface. When the gravity system transitions to a pressure system, the airspace is confined and positive pressure is generated. This positive pressure results in the release of air through any opening in the conveyance system. Due to the long hydraulic retention time of the Bissett Lake sewer system, septic conditions can persist in the warmer months. In recent years this has led to odour complaints from residents and trail users in this area.
ITEM # 4-I HRWC Board
November 24, 2016
Page 6 of 7
In response to those odour complaints, Halifax Water staff have taken considerable actions to reduce the odours:
Multiple manholes were sealed and granular activated carbon added to manholes to reduce the amount of odour causing sulphur compounds released;
Bioxide dosing was increased;
In locations where operations staff confirmed unpleasant odours, environmentally safe masking agents were installed to reduce odours;
Vivian Road is a small local sewer that connects to the lower reaches of Bissett Lake sewershed near Hines Road. The positive air pressure at this location caused migration of sewer gas into the local sewer. The Vivian Lane sewer system generated a number of odour complaints in 2015. In response Halifax Water installed a check valve device to isolate the head space of each sewer and eliminate sewer gas migration;
There are a number of air release valves (ARV) on the Bissett Road pump station forcemain. The function of an ARV is to release airspace in the forcemain to prevent air lock in the system. This airspace can release unpleasant odours when conveyed sewer is septic. Operations staff have added GAC to ARVs, manholes, and vent pipes to reduce the quantity of odourous sulphur compounds that is released. In addition to GAC treatment, operations staff have also changed the pump station logic to reduce pump cycling. This decreases the frequency at which the forcemain airspace is released.
Inglis Street Sewage Collection System This system exhibits similar characteristics as the Bissett Road system. For an overview of the Inglis Street sewer system, please see Figure 2, Inglis Street Sewer Collection System. The odour complaints from this area began soon after the commissioning of the Harbour Solutions infrastructure. Similar measures as described above for the Bissett Road collection system have been deployed in this sewershed with some success as complaints have dropped off significantly. The recent extended dry weather event brought some complaints but have dissipated with the recent rain activity.
Odour Control Investigation In recognition of increased odours over the summer of 2016, Halifax Water retained the services of CH2M Hill to provide expert opinion on the two areas of the collection system referenced above. This engagement has led to a draft report that outlines a phased approach to addressing odours in the lower reaches of the Bissett gravity main and the Inglis Street sewer system. The draft report is currently under review by Halifax Water staff with final delivery expected December 2016. The draft report has outlined a phased approach for each of the sewer systems. Phase I for each system is optimized delivery of
ITEM # 4-I HRWC Board
November 24, 2016
Page 7 of 7
nitrate salt (trade name Bioxide). This chemical addition is an inherently safe chemical to dose. When added to sewer systems, it reduces the sulphide generation potential of the sewer and associated odours. Pending the recommendations of the final report, Halifax Water intends to install optimized dosing systems for each respective sewer prior to the warm summer conditions of 2017. A number of options are being evaluated for phase II of the program. The options include the addition of granular activated carbon, biofilter, and wet scrubber systems for the Bissett gravity main. Options for the Inglis Street sewer include addition of a biofilter or connection of the sewer air space to the Pier A pumping station via an air jumper. Air from the sewer system would then be treated by the existing Pier A scrubber system. The options evaluation will determine if sufficient capacity exists in the existing scrubber to handle the extra load. The final report will provide concrete recommendations that will be implemented by 2018. If land acquisition is required, the estimated completion dates will be subject to this added process. FINANCIAL IMPLICATIONS: Funds have been allocated in the Capital Budgets of 2017-18 and 2018-19 for implementation of solutions for the Bissett Road and Inglis Street sewersheds. Funds have also been included in the operating budgets for future years for several operational activities such as enhanced monitoring, replacement of carbon scrubber media, and increase in Bioxide dosing at several locations. ATTACHMENTS 1. Map - Bissett Road PS Sewer Collection System 2. Map - Inglis Street Sewer Collection System
Report Prepared by: Original Signed By:
Susheel Arora, Director, Wastewater & Stormwater Services 902-490-6254
1:42,000
FMFM
FM
FM
GP
GPGP
GP
GPGP
FMFM
õ
C
%2
%2%2
%2
BISSETT RD
CALDWELL RD
MAIN ST
DYKE RD
HINES RD
MAIN RDASTRAL DR
COLE HARBOUR RD
COW
BAY R
D
ROSS RD
FOREST HILLS PKY
LAWRENCETOWN RD
MOUNT EDWARD RD
COLBY DR
SPRING AVE
RITCEY CRES
DOROTHEA DRJOHN STEWART DR
REGAL RDLUCIEN DR
RAPTOR WAY
COLE DR
ARKLOW DR
DELTA DR
ATHOLEA DR
GREEN BAY DR
NOVA TERRSWANTON DR
BROOM RD
POPLAR DR
AUBURN DR
CRANBERRY CRES
ELLENVALE AVE
BOUNDARY RD
FADER ST
PARKW
AY DR
SCHOONER DR
SPENCE DR
BRADORIAN DR
SMITH AVE
LAWLOR CRES
FLANDRUM HILL RD
HOWARD AVE
KELTIC DR
LUNDY DR
COLE
RIDGE
CRT
PORTLAND ST
BLAKE AVESPRUCE DR
ELLEN DR
ANDERSON ST
OLD BIRCH RD
WILDWOOD BLVD
PAXT
ON D
R
BAYSWATER RD
BELMONT A
VE
FIRE HALL RD
BROOKVIEW DR
BISSE
TT LA
KE RD
PLAZA DR
LAURA DR
MUIN DR
KILGAR RD
ERIN DR
COW BAY RD
Bissett Lake PS
¹
Figure 1: Bissett Rd PS Sewer Collection System
Vivian Lane connector
Bioxide dosing location.
Drawn by: SDDate: November 16, 2016
Legend
C Treatment Facility
õ Wastewater Pumping Station
%2 Air release valvesBissett Lake PS SewershedArea does not contribute to Bissett Lake PSPressure SewerBissett Lake PS Forcemains
GP
#
FM
#
Trail system
Bissett Lake PS Sewershed Information:Sewer travel distance: 14 kmSewershed area: 735 HA# of services: 3,845
Bissett Lake PS Sewershed
Figure 2: Inglis St Sewer Collection System
Legend
C Treatment Facility
õ Combined Pumping StationAST SewershedArea does not contribute to ASTAST Gravity SewerAST PS Forcemain
FM
õ
õ
C
CHALIFAX WWTF
Pier A PS & CSO
Atlantic School of Theology PS
OXFORD ST
SOUTH ST
PURCELLS COVE RD
ALMON ST
QUINPOOL RD
INGLIS ST
NORTH ST
KEMPT RDGOTTINGEN ST
JUBILEE RD
HERR
ING
COVE
RD
CONNOLLY ST
TOWER RD
MAIN AVE
JOSE
PH H
OWE D
R
BRUNSWICK ST
BEECH ST
HOLLIS ST
AGRICOLA ST
CROWN DR
CHEBUCTO RD
ISLEVILLE ST
MARGINAL RD
QUEEN ST
BARRINGTON ST
DUBLIN ST
COBURG RD
NOVALEA DR
HENRY ST
BAYERS RD
WINDSOR ST
CORK ST
SUMMIT ST
ALEX ST
COWIE HILL RD
SACKVILLE ST
MAYNARD ST
YOUNG ST
DINGLE RD
SOUTH PARK ST
DUFFUS ST
BROOK ST
RUFUS AVE
VERNON ST
LEEDS ST EDWARD ST
PROVO WALLIS ST
CHARLES ST
LONDON ST
ROMA
NS AV
E
SCHOOL AVE
ALLAN ST
RUSSELL ST
HIGH ST
OAKLAND RD
MICMAC ST
BEAUFORT AVE
BAYN
E ST
MELROSE AVE
TA17 RD
MILSOM ST
SHORE RDPRESTON ST
WALNUT ST
PIERS AVE
PARK
HILL R
D
QUINN ST
LOWER WATER ST
UNION ST
SPRINGVALE AVE
OSBORNE S
T
NORWOOD ST
AFRICVILLE RD
FRANCKLYN ST
CUNARD ST
LYLE S
T
TA13 RD
CIRCLE DR
JOYCE AVE
BILBY ST
MUMFORD RD
MORRIS ST
POPLAR ST
DOWNS AVE
STAIRS ST
MCLEAN ST
WALTER HAVILL DR
MASSACHUSETTS AVE
COLLEGE ST
ALDERNEY DR
DUKE ST
KAYE ST
BELL RD
ARGYLE ST
TITUS ST
FLINN ST
LARCH ST
FIRST ST
COOK AVE
AHERN AVE
PHILIP ST
ROBIE STBR
IDGE
VIEW
DR
KING ST
PERC
Y ST
EDGEWOOD AVE
SUMMER ST
VICTORIA RDMELWOOD AVE
TAMARACK DR
FLEMING DR
CASTINE WAY
INVERNESS A
VE
OLD SAMBRO RD
EDGEHILL RD
EVANS AVE
DUNDAS ST
WELLINGTON ST
GEORGE DAUPHINEE AVE
LAYTON RD
SPRY AVE
MELVILLE AVE
FULLER TERR
BROMLEY RD
HIGHLAND AVE
THIRD ST
TA16 RD
GARDEN ST
CHISHOLM AVE
RUTHERFORD ST
DESM
OND
AVE
ARMAMENT RD
RESERVE RD
CRES
TVIEW
DR
SEBASTIAN ST
YOUNG AVE
HOOD S
T
PRYOR ST
BELMONT RD
YUKON ST
FRASER ST
WALTON DR
MAY ST
ARMSHORE DR
BINNEY ST
HEINISH AVE FALKLAND ST
FIELDING AVE
FINCH LANE
MELTON AVE
ARTZ ST
PACIFIC ST
Point Pleasant Park
Northwest Arm
AST Sewershed Information:Sewer travel distance: ~ 8kmSewershed area: 2 HA# of services: 2,633
Bioxide dosing locationat the AST PS.
1:30,000¹
Drawn by: SDDate: November 16, 2016
#
FM
#
AST PS Sewershed
ITEM # 5-I
HRWC Board
November 24, 2016
Page 1 of 2
TO: Ray Ritcey, Chair and Members of the Halifax Regional Water
Commission Board SUBMITTED BY: Original Signed By:
Cathie O’Toole, MBA, CPA, CGA, Director, Corporate Services
APPROVED: Original Signed By: Carl Yates, M.A.Sc., P.Eng., General Manager
DATE: November 16, 2016
SUBJECT: Halifax Regional Water Commission Employees’ Pension Plan
3rd Quarter, 2016 – Financial Report
INFORMATION REPORT
ORIGIN Corporate Services staff
BACKGROUND As an initiative for 2016, the Halifax Regional Water Commission Employees’ Pension Plan (hereinafter called the “Plan”) administration has prepared a budget, and are proposing to report on a quarterly basis, the unaudited financial results of the Plan to the Board. Budgets have not been prepared in the past, nor has there been reporting of this nature regarding the Plan’s financial results, other than the Board approval of the annual, audited financial statements. The initial budget and financial report for the 2nd quarter of 2016 were presented to the Board, September 29, 2016 (Item #8-I).
DISCUSSION The attached Statement of changes in net assets available for benefits outlines the annual budget for the Plan and the financial performance of the Plan to the end of the 3rd quarter (January 1 to September 30, 2016). Favourable or unfavourable variances reported compare actual results to prorated budget amounts (75% = 9 months/ 12 months), which
ITEM # 5-I HRWC Board
November 24, 2016
Page 2 of 2
serves as a benchmark for the nine (9) month period in 2016. Results for 2015 and 2014 are shown for comparative purposes; however, Plan changes became effective January 1, 2016 affecting contributions. As shown on the Statement of changes in net assets available for benefits attached, net assets available for benefits has increased by $4.0 million over the nine (9) month period ending September 30, 2016. The budget for 2016 forecasted a decrease in net assets available of $0.5 million. Results for the period compared to the benchmark show a favourable variance in the amount of $4.3 million. Revenue for the period totaled $3.7 million, which compared to the benchmark, results in a favourable variance of $4.9 million. Revenue is most affected by the performance of the HRM Master Trust, and change tends to be more volatile compared to contributions and expenses of the Plan. The large variance is attributed directly to the increase in the fair value of the investment assets, which rebounded after a dismal 1st quarter. Gains in the fair value for the period amounted to $2.0 million, which consisted of $3.7 million in the 3rd quarter, compared to $1.6 million and ($3.2) million in the 2nd and 1st quarters respectively. Investment income for the period is performing above expectations, surpassing the benchmark by $0.2 million or 14%. Contributions are tracking as expected compared to budget, showing only a minimal variance compared to prorated budget amounts. Expenses of $3.8 million for the period are higher than the benchmark of $3.2 million, resulting in an unfavourable variance of $0.6 million or 18%. One of the main contributors to the unfavourable variance was death benefits paid in the 3rd quarter totaling $0.5 million which were not previously budgeted. The other contributor was termination benefits totaling $0.6 million, which are tracking $0.2 million or 54% higher than the benchmark. This is due to the retirement of several long serving members during the period. The higher costs associated with death and termination benefits are offset somewhat by favourable variances for benefit payments and actuarial/consulting fees. Expenditures in these areas however are expected to increase throughout the remainder of the year as more members retire, additional costs associated with work on required changes in the Plan text are incurred, and accrued expenditures are reimbursed by the trustee. ATTACHMENT Statement of changes in net assets available for benefits, for the nine (9) month period ended September 30, 2016.
Report Prepared by: Original Signed By Warren Brake on behalf of:
Allan Campbell, B.Comm, CPA, CMA Manager, Finance 902-490-4288
Item 5-IAttachment
HRWC BoardNovember 24, 2019Halifax Regional Water Commission Employees' Pension Plan
Statement of changes in net assets available for benefitsFor the nine (9) month period ended September 30, 2016Benchmark 75%
Prorated
Budget Actual ActualBudget Actual 75% $ % 2015 2014
Revenue1
Net investment income:
Total investment income $2,056,000 $1,758,309 1,542,000 216,309 14% $2,350,179 $2,297,149
Investment manager fees ($151,000) ($103,787) (113,250) 9,463 -8% ($188,555) ($175,227)
Increase (decrease) in the fair value of investment assets ($3,550,000) $2,053,093 (2,662,500) 4,715,593 -177% $7,313,583 $5,156,004
($1,645,000) $3,707,614 (1,233,750) 4,941,364 -401% $9,475,207 $7,277,926
Contributions2
Participants:
Current service (inc AVC's) $2,420,000 $1,812,641 1,815,000 (2,359) 0% $2,655,143 $2,768,168
Reciprocal transfers $0 $0 0 0 n/a $598,383 $0
Sponsors:
Current service (inc LTD) $2,207,000 $1,654,378 1,655,250 (872) 0% $2,741,953 $2,885,772
Unfunded liability $825,000 $618,750 618,750 0 0% $2,952,200 $2,952,200
$5,452,000 $4,085,768 4,089,000 (3,232) 0% $8,947,679 $8,606,140
Expenses3
Benefit payments:
Benefit payments $3,524,000 $2,626,919 2,643,000 16,081 1% $3,246,032 $3,020,172
Termination payments $550,000 $635,607 412,500 (223,107) -54% $1,021,997 $475,930
Death benefit payments $0 $509,236 0 (509,236) n/a $0 $9,188
Administrative:
Actuarial & consulting fees $170,000 $32,195 127,500 95,305 75% $134,296 $148,865
Audit & accounting fees $9,000 $0 6,750 6,750 100% $660 $8,584
Bank custodian fees $23,000 $13,244 17,250 4,006 23% $21,567 $21,423
Insurance $8,000 $0 6,000 6,000 100% $7,950 $7,950
Miscellaneous $13,000 $11,569 9,750 (1,819) -19% $11,641 $10,050
Professional fees $20,000 $10,027 15,000 4,973 33% $18,313 $13,542
Registration fees $2,000 $0 1,500 1,500 100% $2,074 $2,040
Training (Trustees/ Administration/ Pension Committee) $8,000 $0 6,000 6,000 100% $0 $0
$4,327,000 $3,838,797 3,245,250 (593,547) -18% $4,464,530 $3,717,744
Increase (decrease) in net assets available for benefits ($520,000) $3,954,585 (390,000) 4,344,585 -1114% $13,958,356 $12,166,322
Net assets available for benefits, beginning of period $100,434,444 $100,434,444 $86,476,088 $74,309,766
Increase (decrease) in net assets available for benefits ($520,000) $3,954,585 $13,958,356 $12,166,322
Net assets available for benefits, end of period $99,914,444 $104,389,029 $100,434,444 $86,476,088
Note:
1
2
3 Budgeted amounts for benefit payments are derived by using the actual amounts paid to pensioners for the seven (7) months of the year, then adding an estimated amount for the remainder of the year based on actual benefit payments paid July 1, 2016. All other expenses are based on best estimates.
For the purposes of this statement, expenses are reported on a cash basis.
2016
Variance F(U)
Budgeted amounts for revenue are derived by annualizing the amounts reported on the unitization reports for the five (5) month period ended May 31, 2016.
Budgeted amounts for contributions are derived by using the actual amounts remitted for the five (5) month period ended May 31, 2016, then adding forecasted amounts for the remainder of the year, as reported in the annual contribution planner filed with the trustee.
Actual contributions for the period have been adjusted to reflect contribution rate changes made in May, 2016, retroactive to January 1, 2016. Current contribution rates are 10.65% and 9.85% respectively for employees and the employer, which were reduced from 12.95% previously for each. This retroactivity also applied to the special payments made by the employer related to the unfunded liability, resulting in a reduction to $0.8 million per annum from $2,8 million.
G:\Finance\general\Fin Acct\Excel\Pension\PPFS 2016\Budget and Quarterly Statements\PP Budget & Qrtly FS 2016 _ FINAL v.3