hiradmat : report from wg2 – wanf dismantling
DESCRIPTION
HiRadMat : report from WG2 – WANF dismantling . Agenda. WANF cleaning T1 removal Access and Ventilation hardware Integration : naming convention Short Term Planning : co-activities in January 2010 Long Term Planning . WANF cleaning . - PowerPoint PPT PresentationTRANSCRIPT
HiRadMat : report from WG2 – WANF dismantling
December 10, 2009S. Evrard
1
• WANF cleaning• T1 removal• Access and Ventilation hardware• Integration : naming convention• Short Term Planning : co-activities in January 2010• Long Term Planning
Agenda
WANF cleaning
December 10, 2009S. Evrard
2
• Technical specification worked out with RP : WANF cleaning• PE launched (S. Sonnerat, purchase officer)• 4 companies enquired (all contacted):
– Cerap (F, Mr X. Labat)– Salvarem (F, Mr B. Agret)– Techman (F, Mr O. Rotelle)– Technubel (B, Mr K. Lenie)
• Deadline offers return: Tues. 15.12• Work foreseen in week 4 (18 22 January)
T1 removal
December 10, 2009S. Evrard
3
• MCA + 6 TAX blocks• Procedure prepared by EN/HE• Forklift shielding study in progress• Forklift preparation in Weeks 2 • Work foreseen in week 3 (11 15
January)
ACCESS
December 10, 2009S. Evrard
4
Integration issues
December 10, 2009S. Evrard
5
• Kick-off meeting done• Naming convention
Co-activities in January 2010
December 10, 2009
6
EN-HE
EN-HE
EN-CVContractor
EN-HE
GS-ASE, IT
-CS
EN-HE: T1 : MCA + Tax blocksEN-HE: furet removalEN-HE: Electrical cabinet refurbish.