hiradmat : report from wg2 wanf dismantling december 10, 2009s. evrard 1 wanf cleaning t1 removal...
DESCRIPTION
T1 removal December 10, 2009S. Evrard 3 MCA + 6 TAX blocks Procedure prepared by EN/HE Forklift shielding study in progress Forklift preparation in Weeks 2 Work foreseen in week 3 (11 15 January)TRANSCRIPT
HiRadMat : report from WG2 – WANF dismantling
December 10, 2009S. Evrard
1
• WANF cleaning• T1 removal• Access and Ventilation hardware• Integration : naming convention• Short Term Planning : co-activities in January 2010• Long Term Planning
Agenda
WANF cleaning
December 10, 2009S. Evrard
2
• Technical specification worked out with RP : WANF cleaning• PE launched (S. Sonnerat, purchase officer)• 4 companies enquired (all contacted):
– Cerap (F, Mr X. Labat)– Salvarem (F, Mr B. Agret)– Techman (F, Mr O. Rotelle)– Technubel (B, Mr K. Lenie)
• Deadline offers return: Tues. 15.12• Work foreseen in week 4 (18 22 January)
T1 removal
December 10, 2009S. Evrard
3
• MCA + 6 TAX blocks• Procedure prepared by EN/HE• Forklift shielding study in progress• Forklift preparation in Weeks 2 • Work foreseen in week 3 (11 15
January)
ACCESS
December 10, 2009S. Evrard
4
Ventilation door
December 10, 2009S. Evrard
5
Co-activities in January 2010
December 10, 2009
6
EN-HE
EN-HE
EN-CVContractor
EN-HE
GS-ASE, IT
-CS
EN-HE: T1 : MCA + Tax blocksEN-HE: furet removalEN-HE: Electrical cabinet refurbish.