hillhead extension options
TRANSCRIPT
-
8/12/2019 Hillhead Extension Options
1/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
Alterations
And
extensions
Options
Study
-
8/12/2019 Hillhead Extension Options
2/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
Contents
1.0 Introduction
2.0 Options Location Plan
3.0 Options Description
4.0 Proposed Layouts
5.0 Cost Report
-
8/12/2019 Hillhead Extension Options
3/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
In addition, the demand for dining space
requires that the school Gym is unavailable
for PE activity for long periods of the day,with many classes having to be escorted to
a remote playing field within Kelvingrove
Park. Therefore, the potential for additionalspace for indoor or outdoor physical activity
is explored within this report.
The report utilises record informationavailable to PM&D at the time of writing,including PDF copies of the original
Architects drawings. It is noted that some
minor discrepancies exist between theseand the completed school.
A visual inspection only of the Engineeringinstallations was conducted. Further
analysis and consideration of the completed,
Structural and M&E Designs will be requiredbefore any of the proposed options are
investigated further. Particular emphasis is
placed on the Fire Engineering solutionserving the original design, which permits
single means of escape from a number of
points on the upper floor. Increasedoccupancy capacity may exceed the Fire
Engineered design. Furthermore, unknownStatutory Design and Planning constraints
may have influenced the height and form of
the original school designs.For this reason, PM&D recommend that the
original building designers are fullyconsulted during the next stage.
1.0 Introduction
Due to increasing demand on pupil places atHillhead Primary School, Education Services
have requested DRS PM&D identify
potential options and associated costs toaccommodate additional teaching spaces
within the constraints of the schools existing
infrastructure provision and confined site
boundaries.
The Primary School is originally designed for
a capacity of 632 pupils, but the current role
is 652, requiring that the two GP rooms arefully utilised as Class Bases at present. The
Head Teacher has advised that the role
projection for year 2017/18 is 714, which willresult in an overall shortfall of three teaching
spaces.
Existing toilet provision is at a minimumacceptable level to satisfy Building
Standards and would remain so if theprojected Primary School role of 714 was to
extend into the Existing Nursery. However,
should the Nursery remain within the schoolcampus, the toilet provision will need to
increase.
An immediate and potentially short term
solution to the increasing capacity isrequired prior to the beginning of term in
August 2014. This is the subject of Option 1.
-
8/12/2019 Hillhead Extension Options
4/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
2.0 Options Location Plan
and 10
-
8/12/2019 Hillhead Extension Options
5/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
3.1 Option 1A
Formation of Class Base and ICT
Breakout Space within existing
Library (required August 2014)
Form free standing teaching wall as dividingscreen between rooms (with cable drops),
but conditioned as a single space.
The Head Teacher has reported that the
room overheats due to a predominance of
Reglit glass.Review of air con installation is required in
view of apparent inadequacy of existinginstallation.
Include full height vertical louvre blinds
throughout to mitigate comfort issues.Further review required with original
Designers to offer comment and propose
resolution.
Review of fire engineering strategy is
required due to the increased design loadingcapacity.
PM&D to obtain Fire Engineers report for
analysis.
Note, room has limited outlook due to
predominance of Reglit glass. Should thisoption be a permanent solution, PM&D
recommend the incorporation of additional
windows, requiring Planning Consent.
OPTION 1B
Retain Library as oversized Class
Base
Retain room as a single space / oversized
classroom, with alterations / upgrades as
necessary to M&E installation.
-
8/12/2019 Hillhead Extension Options
6/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
3.2 Option 2
Formation of Dance Studio w ithin
Undercroft Car Park
Note, headroom restrictions (2600 to u/s
beams + 900mm beam depth [excludes new
sprung hardwood floor make up].Two means of escape to be provided from
basement.
Access, including DDA, to be provided fromexisting adjacent functions, such as
changing facilities.
Existing access available via lift, externalstair from ground floor roof terrace and car
park entrance.
Note, the potential exists to form a newenclosure to the existing adjacent external
stair to provide direct covered access
between the Dance Studio and changingrooms.
Adequacy of existing changing provision tobe reviewed.
New windows to external wall, formed within
existing louver vent openings.Mechanical extract from car park may be
required due to reduced cross ventilation.
Resultant net reduction of 8no car spaceswithin car park.
-
8/12/2019 Hillhead Extension Options
7/22Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
3.3 Option 3
Formation o f single Class Base / GP
room enclosure over Social Space.
Partial infill of void permits borrowed light
through to ground floor and maintains
double height spatial quality at the mainentrance.
Clear storey glazing to corridor walls for
borrowed light into classroom.Glazing to back wall for borrowed light.
Connection to vent stacks at high level to be
explored.Assumes new structure can span across
void between existing steel.
Allow for two means of escape due todirection of travel via voids.
Option 3A
Form new partial floor infill only, with halfheight partitions as open plan ICT breakoutspace.
OPTION 3B
Ground floor Social space
Proposal to create ICT study booths alongcorridor sides with informal debate seating
within main body of floor.Include allowance for sliding folding screen
to entrance side (optional).
Option may require formation of additional
table and chair storage to facilitate further
flexible use of the space.
-
8/12/2019 Hillhead Extension Options
8/22Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
3.4 Option 4
New Gym Hall, and GP rooms
The Option is subject to the successful
purchase of the adjacent domestic property.
Existing adjacent dwelling and associated
structures to be removed.
New building formed to accommodate Gym,
Drama and GP space.Circular plan form proposed, clad inmatching facing brick, to compliment the
existing Architectural response and avoid
the impression of narrow alleyways betweenbuildings.
Direct access to Gym and GP room is via
the existing bridge link and in close proximityto changing rooms within the Community
Block.
Direct access to the Drama space isprovided via a new bridge link, which also
offers a second means of escape from the
Gym.The need to tie in floor levels will result in a
deep underbuilding, which may be
considered for use as additional parking,storage and sheltered external play space.
The option will be subject to Planningconsiderations, daylighting issues and the
proximity to the neighbouring churchbuilding.
Further consideration is required with regardto the adequacy of the existing changing
facilities.
Option 4A
Form outdoor Multi Use Games Area withassociated fence enclosure in lieu of Gym
building.
-
8/12/2019 Hillhead Extension Options
9/22Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
3.5 Option 5
Al terations to Ex isting Nursery to
Accommodate 3 Primary Classrooms
Existing partition layout, generally, to be
retained, providing 2no Classrooms at 75m2
and 1no at 66m2.Small toilet within one of the existing
classrooms to be removed.
Reconfigure access to existing unisex toiletand convert to girls only. Sanitary ware to be
replaced with adult sized units.
Form small store off toilet access corridor.Form dedicated Boys Toilet within former HT
room.
-
8/12/2019 Hillhead Extension Options
10/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
3.6 Option 6
Extended External Hard Play Surface
Area of soft landscaping to the southern endof the site to be replaced with concrete
paving to match existing.
Perimeter edge to be formed as tiered steps,following the existing contours, to create a
small outdoor performance venue.
-
8/12/2019 Hillhead Extension Options
11/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
3.7 Option 7
Formation of 2 st orey Classroom and
Breakout extension.
East flank Classroom block extended
southwards by a single classroom on bothfloors, with small Breakout space on Ground
floor and Unisex Accessible Toilet at First
Floor.Extension to be clad in facing brick to match,
creating a stop end to the existing
Architectural form.
Reconfiguration of final escape door andexternal steps required.
Note, accurate location of the site boundaryadjacent to the proposed extension
is subject to further research. Access and
footpath width may require widening.
Include contingency sum for retentionstructure at river bank to widen footpath.
External views from existing Nursery Staff
Base is compromised.
External play area reduced.
Option to be considered only if Option 5,
expansion in to Nursery, is not feasible orclassroom numbers are not adequate.
-
8/12/2019 Hillhead Extension Options
12/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
3.8 Option 8
Formation of single classroom
extension at first floor.
Extend the southern classroom block
Westwards, at first floor only, to provide 1no
additional classroom.Proposal permits access around perimeter
of building and avoids reduction of outdoor
play area.The already stretched fire Engineering
solution for the building will require a second
means of escape is provided from the farend of the first floor corridor. This is
achieved via an external bridge spanning on
to the western landscaped embankment,with a platform which connects to the
existing access steps from Kelvin Way.
The proposal is subject to further analysis of
available headroom at ground leveland adequacy of toilet provision at First
Floor.
-
8/12/2019 Hillhead Extension Options
13/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
3.9 Option 9
Formation of External toilet block
within entrance recess.
Small external toilet enclosure formed within
entrance recess to be held clear of existing
glazed entrance screen to avoidcompromising existing smoke extract/vent
arrangement.
Enclosure to be naturally ventilated and clad
in appropriate materials to compliment the
existing entrance design.
-
8/12/2019 Hillhead Extension Options
14/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
3.10 Option 10
Formation of First Floor pavilion
Extension over Existing Nursery
Accommodation
3no. class bases with wide breakout corridor
to be formed over roof of existing Nurserywing.
Plan arrangement and overall feasibility of
proposal is subject to further analysis of theability of the existing structure to carry the
additional load.
2no. glazed link corridors required to providetwo means of escape from new
accommodation, subject to analysis of
existing fire strategy.Include for escape bridge at first floor level
to span across playground to western
boundary landscaped embankment.
-
8/12/2019 Hillhead Extension Options
15/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
4.0 Proposed Layouts
Options Location Plan
and 10
-
8/12/2019 Hillhead Extension Options
16/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
4.1 Community Block
First Floor Plan as Proposed
-
8/12/2019 Hillhead Extension Options
17/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
4.2 Community Block
Lower Ground Floor Plan as Proposed
-
8/12/2019 Hillhead Extension Options
18/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
4.3Classroom Block
Ground Floor Plan as Proposed
-
8/12/2019 Hillhead Extension Options
19/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
4.4 Classroom Block
First Floor Plan as Proposed
Option 3 and 3A
-
8/12/2019 Hillhead Extension Options
20/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
4.5 Classroom Block
Ground Floor Plan
Proposed Alterations to Nursery
-
8/12/2019 Hillhead Extension Options
21/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
4.6 Classroom Block
First Floor Plan
Proposed Extension over Nursery
-
8/12/2019 Hillhead Extension Options
22/22
Hillhead Pre 12 School Campus Alterations and Extensions 5thFebruary 2014 DRS Project Management and Design
4.7 Option 4
Proposed Gym, Drama and GP room
Extension
Option 4A
Outdoor Multi Use Games Area in
lieu of Gym building