harlan wyton heating review proposal r1

Upload: mirali74

Post on 03-Jun-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Harlan Wyton Heating Review Proposal R1

    1/7

    Harlan Labs, Wyton Heating Review Proposal

    1

    Harlan Labs, Wyton

    Heating Review Proposal

    NAME: Mir Ali

    Date: 06/08/2012

    Project No. 12138

    Rev R1

  • 8/12/2019 Harlan Wyton Heating Review Proposal R1

    2/7

    Harlan Labs, Wyton Heating Review Proposal

    2

    Contents

    1 Harlan Labs Heating Review............................................................................................................... 3

    Executive Summary ............................................................................................................................... 3

    Background ............................................................................................................................................... 3

    1.1

    Project Development ................................................................................................................. 3

    a. Energy Efficient AHUs for buildings: ...................................................................................... 4

    b. Replacing existing Burners with new energy efficient Burners: ........... ........... ........ 4

    c) DX Cooling Units ................................................................................................................................. 5

    d) Sustainability Project: ............................................................................................................... 5

    PC Sums ...................................................................................................................................................... 5

    1.2 Programme .................................................................................................................................... 6

  • 8/12/2019 Harlan Wyton Heating Review Proposal R1

    3/7

    Harlan Labs, Wyton Heating Review Proposal

    3

    1 Harlan Labs Heating Review

    Executive Summary:

    Heating for the various buildings at Harlan Labs, Wyton is provided by a number of gas fired burners

    located in the AHU providing tempered air to the buildings. A site wide energy audit was carried out

    recently, found that the site does not currently meet the Government and Industry stipulated Guidelines

    in some areas.

    The Wyton site does not have any form of cooling which would be needed to meet maximum

    temperature requirements. Based on the site visit, operational problems with the heating only AHUs

    were identified primarily due to the age of the plant.

    These AHUs / burnerswere installed in the 1980s and are well past the CIBSE recommended design life

    expectancy of 15 years. Due to their present age, the frequencies of maintenance and operational

    failures have increased many folds.

    Background:

    Based on the Home Office (HO) Code of Practice for the housing and care of animals in designated

    breeding and supplying establishments, and HO Animals (scientific procedures) Act 1986 Pg 31 requires

    some form of cooling to be provided in order to attain temperatures between 15-24 Deg C for beaglesto deal with extremes of temperature.

    Due consideration should be made to comply with European regulations when Directive 2010/63/EU will

    take full effect from 1 January 2013, these regulations prescribe the temperature, relative humidity,

    space ventilation, lighting, and noise levels within these spaces, which require a provisional 1520 ACPH.

    Stocking densities should be taken into account when selecting air change rates.

    1.1 Project Development

    Based on the discussions we had with Harlan team, who have instructed us to look at the existing AHUs

    and burners in order to meet regulatory compliance and also to optimise energy consumption at site

    through Low energy design.

  • 8/12/2019 Harlan Wyton Heating Review Proposal R1

    4/7

    Harlan Labs, Wyton Heating Review Proposal

    4

    The following projects aim to address some maintenance issues at site and also look at reducing energy

    consumption at site.

    a.

    Energy Efficient AHUs for the buildings

    b.

    Replacing Burners with new energy efficient Burners

    c.

    Standalone DX systems for the buildings to achieve compliance

    d.

    Sustainable solutions

    a.

    Energy Efficient AHUs for buildings:

    The AHUs serving thebrood and stock housing and the Whelping Puppies buildings are more than 30

    years old and have exceeded their economic lifespan, also these AHUs are not capable of providing 15-

    20 AHCP as mandated by the European directive which comes into effect in January 2013.

    We would recommend that these be replaced with Low Energy AHUs capable of providing the air

    change rate as mandated under the European directive, while incorporating system redundancy to allow

    the AHUs to function during downtime.

    Deliverables:

    HVAC System Schematics & layout plans

    Cooling Plant design & options

    System Electrical requirements

    Initial Scheme design

    Capital Plan

    Proposal & Business Case

    b. Replacing existing Burners with new energy efficient Burners:

    The burners serving barriers were installed in the 1980s and are well past the CIBSE recommended

    design life expectancy of 15 years.

    Due to their present age, the frequencies of maintenance and operational failures have increased many

    folds. It is also worth noting that these burners have an efficiency of 60-70%, we would recommend that

    these be replaced with energy efficient burners which have an efficiency in excess of 90%, the burners

    selected should be fully modulating, have weather compensation and incorporate an intelligent boiler

    controller for energy optimised operation, it should be interfaced with the BMS as part of the proposed

    works to assist in setting up energy optimisation schedules. This would result in lower energy

    consumption and would reflect in lower energy consumption at site.

  • 8/12/2019 Harlan Wyton Heating Review Proposal R1

    5/7

    Harlan Labs, Wyton Heating Review Proposal

    5

    c) DX Cooling Units

    DX cooling units present a less expensive alternative to incorporate cooling at site in order to achieve

    regulatory compliance. However, it should be noted that the electrical supplies at site are stretched

    thereby requiring exploring alternatives including reinforcing the electrical supply to site.

    There exists an alternative approach to this problem which has been included as a sustainability project.

    d)Sustainability Project:

    As the site is considering installing cooling to comply with home office regulation along with the fact

    that the heaters are in excess of 30 years old and in need replacement, it is therefore recommended

    that a gas based heat pump solution providing heating and cooling be explored thereby providing both

    heating and cooling at site.

    It is worth noting that the electrical infrastructure at site is stretched, any additional cooling demands

    for compliance would require additional electrical reinforcements at site. This solution does not require

    expensive electrical infrastructure upgrades.

    An option to consider would be a Gas based heat pump providing heating and cooling to the buildings.

    There exists an opportunity for the site to be totally carbon neutral and also work towards improving

    local community relations. While this option is by far more expensive than others investigated, we

    believe this would help the site reduce the negative press / publicity it has attracted over sometime

    while helping to reduce energy consumption and result in becoming a carbon neutral site. We shall also

    review government and other funding sources for the scheme to evaluate payback periods.

    We shall also explore an opportunity to seek services of an Energy Supply Company (ESCO), who would

    set up the proposed plant and infrastructure while seeking long term energy contracts from the site.

    PC Sums

    In order to provide some idea of future costs to deliver the project to construction we would

    like to provide the following PC sums. We would expect the actual costs to be under these

    amounts.

    Costs to carry out a heating review, action plan as stated above: 41,600.00 with proposals

    mentioned developed to 25% accuracy. This excludes 3,250 for producing Schematic

    drawings per Building.

  • 8/12/2019 Harlan Wyton Heating Review Proposal R1

    6/7

    Harlan Labs, Wyton Heating Review Proposal

    6

    Scope of Deliverables:

    To carry out a survey of boiler systems and proposed deliverables

    Wyton Heating Review Scope of deliverables

    Action Who When Completed

    Detailed survey of AHU and burner system

    (Per Building) including current air flow

    validation, efficiency checks, pressurerequirements etc

    EECO2 ASAP

    Produce schematics of each Building EECO2

    Assessment of current and future loads (if

    fabric improvements adopted)(per Bldg)

    EECO2

    Review AHU compliance with Home Office

    and proposed EU Regulations (Per Bldg)

    EECO2

    Proposals for new energy efficient burners EECO2

    Review of Electrical Infrastructure /

    Electrical Survey to support proposed

    works

    EECO2

    Review Sustainability system for costbenefit analysis (Site Wide) EECO2

    Engage with Energy Partners / Client EECO2/CFM In above

    Scope, programme, costs & benefits to

    Harlan Labs.

    EECO2/CFM In above

    Way Forward:

    Issue Order to EECO2 /CFM

    Site Project Leader Appointment and key project contacts

    EECO2 / CFM to organise and monitor progress

    EECO2 will develop Projects as identified above

    1.2

    Programme

    It would take approximately 4-6 weeks from order to carry out all the survey and deliver a detailed

    report for rolling out the energy reduction programme.

  • 8/12/2019 Harlan Wyton Heating Review Proposal R1

    7/7

    Harlan Labs, Wyton Heating Review Proposal

    7