Guidance onNew CEs
Emergency Repair ProjectsOperational Right-of-Way
Limited Federal Funds
EUM – March 2014 1
Email questions to: [email protected]
MAP-21 Congress mandated that certain
actions be categorically excluded from requirements related to EA’s and EIS’s Section 1315 (Emergency repairs) Section 1316 (Operational right-of-
way) Section 1317 (Limited Federal funds)
EUM – March 2014 2
FHWA Rulemaking
Amended 23 CFR 771.117(c) to add new CEs (c)(9) Emergency Repair Projects
(2/19/13) (c)(22) Operational Right-of-Way
(2/12/14) (c)(23) Limited Federal Funds
(2/12/14)
Rulemaking did not change procedural requirements for approval of projects Environmental requirements under
Federal and State statutes and regulations still applyo e.g. Endangered Species Act,
Public Involvement, EJ
EUM – March 2014 3
Levelof
Impacts
4EUM – March 2014
DocumentationThe new CEs are considered to meet the c-list (undocumented CE) criteria, however… FHWA required documentation to
ensure a higher level of NEPA document is not warranted No significant impacts will occur No unusual circumstances exist
An Environmental Verification Form was developed in accordance with rulemaking Only for projects that meet new CE
criteria Shows due diligence performed
EUM – March 2014 5
No Anticipated Impact
Actions related to Emergency Repairs (c)(9), Operational Right-of-Way (c)(22), and Limited Federal Funds (c)(23), are not anticipated to have impacts to: Air Quality & Noise (conduct proper
studies, as appropriate) Hazardous Materials (limited to
petroleum related underground storage tanks/releases)
Farmland Drinking Water
No documentation requiredEUM – March 2014 6
No Significant Impact
Specific environmental resource areas require documentation to illustrate allowable thresholds are not exceeded Waterway Permits
Nationwide or Regional General Permits
May include PCNs Endangered Species
No Effect or May Effect, But Not Likely to Adversely Effect
100-year Floodplain No substantial impacts
EUM – March 2014 7
No Significant Impact
Section 4(f)/6(f) No permanent incorporation of land
or conversiono No 4(f), No Use, or Exceptions
(e.g. Temporary No Use), and Maintenance or Temporary Non-Conforming Use
Cultural Resources Minimal Potential to Cause Effect or
No Historic Properties Affected
EUM – March 2014 8
EJ and PI For Operational Right-of-Way (c)(22)
and Limited Federal Funds (c)(23), the following applies Follow OES EJ Guidance
o If an EJ Analysis Report is needed or if impacts rise to disproportionate and adverse, cannot apply new CEs
PI is commensurate to project’s type and scope
9EUM – March 2014
Guidance
10
EUM – March 2014
FHWA Based on FHWA Ohio Division
correspondence of 2/18/2014, the new CE’s can be applied to projects in accordance with 23 CFR 771.117(c)
OES Guidance and Environmental Verification Form was accepted
11
EUM – March 2014
Exempt per CE PA If a project qualifies as an Exempt
Action Type under the existing CE PA, it can be processed as such with no additional documentation Complete Online CE Exempt Form Tab
12
EUM – March 2014
Exempt Exceeded When a project exceeds the limits of
an Exempt Action Type under the existing CE PA, it may meet the criteria of one of the new CE’s Environmental Verification Form
required Include documentation in Project File
Potential impacts to environmental resources will follow coordination requirements per ODOT’s typical environmental process
If thresholds exceeded altogether, a higher level of NEPA document would be required
13
EUM – March 2014
771.117(c)(9)
Emergency Repair Projects
14
EUM – March 2014
Definition Transportation facilities damaged by
an incident resulting in an emergency declared by the Governor of the State or a disaster or emergency declared by the President
Damage must be caused by a natural disaster or a catastrophic failure from an external cause
The repair occurs within existing right-of-way and in a manner that substantially conforms to pre-existing design, function, and location 1
5EUM – March 2014
Process Perform Damage Survey Assessment
The assessment will help determine if a higher level of NEPA document is warranted based on the context and intensity of impacts
Prepare Damage Survey Report (DSR)o Upload to the Project File
Upload Environmental Verification Form Document Level Tab is left blank
o Exempt Form Tab not generatedEUM – March 2014 1
6
771.117(c)(22)
Operational ROW
17
EUM – March 2014
Definition ROW disturbed for an existing
transportation facility
OR
Is maintained for a transportation purpose See guidance for specific
definitions/examples
Portions of ROW that have not been disturbed or that are not maintained for a transportation purpose do not qualify as existing operational ROW
18
EUM – March 2014
Temporary ROW Temporary easements and takings
needed for construction purposes are covered even if that work is located outside existing operational ROW
Areas acquired as temporary easements or ROW for past projects are not considered part of the existing transportation facilityo Easements end once the original
project is complete
19
EUM – March 2014
Process Upload all pertinent documentation to
the Project File Upload Environmental Verification
Form Document Level Tab is left blank
o Exempt Form Tab not generated
EUM – March 2014 20
771.117(c)(23)
Limited Federal Funds
21
EUM – March 2014
Definition A project must receive federal
transportation funds in order to qualify under this CE May include funds from a variety of
Federal sources, but only applies to FHWA actions
Projects receiving limited funds are those that: Receive less than $5,000,000
OR Have a total estimated cost of not
more than $30,000,000 and Federal funds comprise less than 15% of the total estimated project costo Includes all phases
22
EUM – March 2014
Re-Evaluation When federal funds for the project
increase beyond established thresholds
An FHWA action needed when changes occur
FHWA approvals or grants needed during construction
If federal funds are in excess of the established threshold, the project will not qualify under (c)(23)
23
EUM – March 2014
Process Upload all pertinent documentation to
the Project File Upload Environmental Verification
Form Document Level Tab is left blank
o Exempt Form Tab not generated
EUM – March 2014 24
Future Updates
25
EUM – March 2014
More to Come… Another Final Rule to follow soon…
Four new c-list CE’s Three d-list moving to c-list
Develop new CE PA
BIG changes to Online CE Feature sets illustrating changes are
in-process
26
EUM – March 2014