ground improvement assignment

Upload: yingyiga

Post on 03-Apr-2018

222 views

Category:

Documents


1 download

TRANSCRIPT

  • 7/28/2019 Ground Improvement Assignment

    1/31

    1

    CHAPTER 1

    INTRODUCTION

    Unlike in the past when man just wanted to set up construction work on

    already well established land (naturally), nowadays land has to be improved.

    This has majorly been due to the increasing demand for construction land

    against its availability and the collapse of some landscapes due to landslides

    and the like ( A case in point is the Bukit Antagabsa incident of 1993 and the

    Bukit Segar incident of March, 2009)

    Man has devised all means to improve the properties of land and make it

    suitable for construction and habitable. Some of the properties he has tried to

    affect include but not limited to:-

    Drainage

    Permeability

    Density

    Shear force and Bearing capacity

    The objectives of ground improvement include:

    Reduce settlement of structures

    Improve shear strength and bearing capacity of the soil

    Increase factor of safety against possible slope failure of Embankments

    and dams

    Reduce shrinkage and swelling of soils

    There are very many ground improvement techniques that Man has

    devised to improve the basic soil characteristics such are; grouting, soil

    nailing, tie backs, mechanically stabilised earth walls etc.

    Under certain circumstances more than one ground improvement

    technique has to be used in order to achieve the overall objectives of

    ground improvement. A case in point is the project at Taman Bukit Segara,

  • 7/28/2019 Ground Improvement Assignment

    2/31

    2

    Cheras Kuala Lumpur in which more than one technique was used as

    discussed later in this report.

    In this report though many techniques exist it mostly tackles the soil nailing

    method of ground improvement and briefly hints on tie backs and MSE

    walls.

  • 7/28/2019 Ground Improvement Assignment

    3/31

    3

    Chapter 2

    LITERATURE REVIEW

    This report basically discusses soil nailing as a ground improvement/slope

    stabilisation technique based on a brief survey in Cheras, Kuala Lumpur,

    Malaysia.

    What is soil nailing?

    Soil nailing is a technique in which soil slopes, excavations or retaining

    walls are reinforced by the insertion of relatively slender elements - normally

    steel reinforcing bars. Wikipedia

    Soil nailing in other words is an in-situ kind of soil reinforcement technique in

    which a slender object is inserted into the soil mass in order to enhance

    stability by transferring load from active weak zones of the soil mass to

    passive strong zones.

    Soil nail walls are retaining walls which are built from the top downwards in

    cut situations where the soil has enough apparent cohesion that it can stand

    up on its own during construction. structure source

    Soil nailing traces its origin far back in 1960s when it was first used in Mexico

    and then in Europe in the 1970s. Due to the success of the projects in which

    it was used it gained popularity in many places for both Hillside development

    and in stabilising Embankments world over Malaysia inclusive.

    Soil nail walls increase the resistance to shear forces that may cause the soil

    slope to collapse. The steel bars act as the load bearing materials and as

    reinforcement structures in the slope. Predominantly, Nails are considered to

    operate in tension but there is a possibility of also working in bending/shear

    Apart from its former successes it is seen as one of the best slope stabilising

    technique because;

    It does not require much maintenance post its construction.

    http://en.wikipedia.org/wiki/Soilhttp://en.wikipedia.org/wiki/Soil
  • 7/28/2019 Ground Improvement Assignment

    4/31

    4

    It is effective in slope stabilisation

    It is also easy to construct and,

    Economical.

    It is an in-situ kind of ground improvement thus environmental friendlysince it is not a cut excavation and backfill method.

    It can be applied to sites where accessibility may be difficult i.e where

    working equipments may be difficult to move.

    It is not noisy, silent and causes no vibration of the ground making it

    suitable for urban areas.

    It is flexible and can follow difficult excavation shapes and can be

    adjusted to significant variations in soil conditions that be beencountered during construction.

    The method is well suited to projects that may be of great concern such

    as hill site developments and rehabilitation of distressed structures.

  • 7/28/2019 Ground Improvement Assignment

    5/31

    5

    Chapter 3

    METHODOLOGY

    3.1. SELECTION

    Soil nail walls are normally constructed on slopes whose soil has strong

    cohesive forces and hence can stand on their own during construction; soil

    should have a temporary sub vertical stability of about 2 metres for a period of

    not less than 2 days and the drilled hole should have a capability to stayunaltered for about 3-4 hours or more after drilling it. For this matter soil nail

    walls can not be constructed on land whose soil mostly consists of clay, loose

    sand or under water.

    Landscapes whose soils are stiff fine or cohesion soils, cemented granular

    soils, well graded granular soils with appreciable cohesion of about 5Kpa,

    most residual soils and weathered rock mass with favourable geological

    settings are suitable for soil nail wall construction; putting in mind that the

    ground profile is not under water.

    If the soils/landscape does not march the afore mentioned properties; there

    can be risks such as loosing grout as it is being inserted, collapse of drilled

    holes, poor nail to soil interface resistance due to the disturbance of the drilled

    holes and localised face stability.

    3.2 DESIGN

    There are various methods of soil nail wall designing that are used depending

    on where the construction is going to take place in respect to construction

    regulations, economic considerations and expected time of work i.e.

    temporary versus permanent. Particularly in Malaysia there is no particular

    regulation regarding the design to but the one laid down by U.S Department of

  • 7/28/2019 Ground Improvement Assignment

    6/31

    6

    Transportation, Federal Highway Administration (FHWA), 1998, is more

    recommended since it is cost efficient and practically viable.

    The codes of conduct and design manuals include:

    BS8006:1995, code of practice for strengthened/reinforced soils and other fills

    Soil nailing is discussed in section 7.5: Reinforcement of existing ground in

    BS8006:1995. There are two design procedures suggested in this manual; the

    two wedge method and log-spiral methods are recommended for analysing

    the stability of soil nailed slopes.

    HA68/94, Design methods for the reinforcement of Highway slopes by

    Reinforcement soil and soil nailing techniques

    U.S Department of Transportation, Federal Highway Administration (FHWA),

    1998, Manual for Design and Construction Monitoring Of Soil Nail Walls

    BS8081:1989 Code of Practice for Ground Anchorage

    3.3 INSTALATION

    3.3.1 Equipments:

    The following machinery needs to be in place in order to commence the soil

    nail construction:

    1. Man power: Like any other technical civil works soil nailing requires

    both skilled and unskilled labour/casual workers for the smooth runningof the project. Perhaps depending on the project it requires more

    casual workers at the site than the skilled/professionals and of course

    more professionals in the design office.

    2. Drilling Equipment: In most cases small hydraulic, track-mounted drill

    rigs are used. The rigs are mostly of the rotary/percussive type that

    uses section augers or drill rods. The advantage of these is that they

    are economical since the mobilisation costs are lowered and do not

  • 7/28/2019 Ground Improvement Assignment

    7/31

    7

    require a large space for their operation as compared to hydraulic-

    powered track mounted rigs with continuous flight augers.

    3. Grout mixing machine; it should be is recommended that a high speed

    shear colloidal mixer is used in order to attain a uniform quality grout.

    4. Gunitting /shotcreting machine with a nozzle outlet to control the

    amount of water injecting into high pressurized flow of sand and

    cement mix.

    5. Water suction pump

    6. Compressor

    Etc. as required in civil works

    3.3.2Materials

    Grout

    Hot Deep galvanised steel Rods

    Shortcrete/gunite

    PVC pipes

    Conditional spraying for the ground

    3.3.3 Procedure

    Asany other civil engineering work the first thing is to clear the land where the

    construction work is going to be done. This may involve removal of

    plantation/vegetation, flattening of some part of land either by grading or filling

    using soil of better properties, burrowing and reconditioning the wall for

    shotcrete surfacing.

    Water control measures are then put in place to avoid any alterations during

    the construction. For example in the Taman Bukit Segar hill development

    project 12metre drainage, beam drain and interceptor drain were constructed.

    PVC pipes of about 12 metres in length were inserted into the soil mass. This

    way water finds its way out of the soil mass.

    The wall is constructed from up to down i.e. the top most landscape is firstnailed and sequentially other layers follow in few steps as laid down below;

  • 7/28/2019 Ground Improvement Assignment

    8/31

    8

    The slope is drilled to about 9-12 metre depth. This is to ensure that the

    hardest part of the soil is reached since the main aim is to clamp the less

    dense soil to a denser soil so that tensile load is transferred from less stable

    active zone of the landscape is transferred to passive strong inactive zones to

    attain stability. The drilling was done numerously all over the slope at regular

    close spacing of about 0.5-2metres to ensure maximum soil-nail interaction

    within the soil mass for its reinforcement. The holes are about 75-200mm in

    diameter in order to accommodate the steel rod and a reasonable amount of

    grout. The kind of drilling used for slopes whose soil is well suited is known as

    open cast method where drilling is done without casing. This way speed is

    achieved and costs lowered.

    The drilled holes are then flushed preferably using air to remove the dust from

    the drilled holes. Rigid Hot deep galvanised steel was then put into the drilled

    holes at a slight untensioned declination of about 150. Galvanised steel was

    opted for because of its high resistive properties such as resistance to

    corrosion.

    Fig1: Drilling in progress (Source Manual for Design and construction monitoring of soil nail

    Walls, FHWA)

  • 7/28/2019 Ground Improvement Assignment

    9/31

    9

    Fig2: Nail inserted at a slight declination horizontally (Source Manual for Design and

    construction monitoring of soil nail Walls, FHWA)

    Grouting (in-situ grouting) is then done using Grout of grade 30. Grouting can

    also be done simultaneously as the galvanised steel bars are being inserted

    into the drilled holes. The grout is applied all way round the steel bar so that

    the steel rod is sandwiched between it; this reduces the risk of corrosion due

    to rusting of the steel bar.

    A bearing plate is then put at the outermost end of the steel rod in order to

    hold the nail and grout firmly onto the earth mass (wall).

    The wall is then sprayed with shotcrete and a bearing plate is put at the

    outermost end of the steel bar. The bearing plate is then fixed on the wall

    using a nut and washer.

  • 7/28/2019 Ground Improvement Assignment

    10/31

    10

    Fig3: Spraying of concrete (Source Manual for Design and construction monitoring of

    soil nail Walls, FHWA)

    Fig4 :( Source: coastal caisson.com)

    Then Nail heads are constructed over the steel rods and bearing plates. This

    is done so that the steel rods, bearing plate, nut and washer are not left

    exposed and are well attached to the wall. A simple conical/trapezoidal

    shaped structure made out of concrete can be constructed over each steel

    rod or the whole wall surface can be plastered but the former is more

    economical.

    Fig5: Nail head

  • 7/28/2019 Ground Improvement Assignment

    11/31

    11

    The above procedures are followed till the whole slope is nailed.

    3.4 QUALITY CONTROL/ASSURANCE

    It is true that not all construction works meet standards. Thus many structures

    have found their way in collapsing after a given time,t thus leading to both life

    and economic loss. Thus assurance of quality should be right from the start till

    the end of the construction and periodical surveys should be carried out in

    future though soil nailing does not require much inspection after constructionbut never know some catastrophe may occur. So to ensure quality preliminary

    and working pull outs were taken.

    Cone penetration test (CPT)

    In this test a penetrometer with a conical tip and standard geometry is pushed

    vertically into the ground at a standard rate of 20mm per second. Penetration

    at this rate is fully drained for sands with non plastic silt contents of up to 10%

    (Carraro et al.2003). This test is conducted during the site exploration to

    determine the cone resistance, qc

    Where, qc = vertical force acting on the tip of the penetrometer

    The base area of the tip

    (1000mm for the standard penetrometer with diameter of35.7mm)

    Fig6: Photographic view of nail heads

  • 7/28/2019 Ground Improvement Assignment

    12/31

    12

    The qc can then be used to conclude on the nature of soil. Of recent invention

    this test can also help in determining friction along a lateral sleeve and shear

    wave velocities, pore pressure and other quantities with the help of seismic

    shear waves.

    The test is normally used because of its simplicity, speed and probably ability

    to maintain a continuous profiling.

    Cube test ; this was do check on the quality of the grout mix used.

    Curing test/test panel; this was to test the quality of shortcrete used for

    reinforcements.

    Weight bearing capacity of the steel rods (nails) has to be determined and

    ensure that the minimum load can meet the load on the soil mass.

    Seasonal monitoring

    Apart from the monitoring by the site resident Engineer, periodical monitoring

    is done by the Local authorities such as Dewan Bandaraye Kuala Lumpur (a

    body responsible for monitoring all construction work in Kuala Lumpur) after

    every six months.

  • 7/28/2019 Ground Improvement Assignment

    13/31

    13

  • 7/28/2019 Ground Improvement Assignment

    14/31

    14

    CHAPTER 4

    ANALYSIS OF SOIL NAILING

    Soil nailing is best suited for slope stabilisation in which the soil mass can

    stand on its own.

    3.1 FAILURE MODES IN SOIL NAILING AND CORRECTION

    PROCEDURES

    Basically, for the soil nailing technique discussed in this report, where the nail

    head is attached to the ground, only one failure mode is exhibited. It is as a

    result of the sliding of the soil wedge moving down and out thus dragging the

    nails along with it. This movement results from shear stress that develops

    along the soil interface with the nails. The resistance between a nail in

    question and the soil beyond the sliding wedge can then be mobilized.

    The wedge tends to drag the nail, the stable soil mass drags it in the opposite

    direction and the nail itself pulls the wedge. If the resistance of the soil nail is

    sufficient, the wall-nail-soil system will be stable; otherwise the soil wedge will

    slide carrying along the nails with it.

    Fig 7: Failure mechanism in soil nailing

    This makes it necessary to put into consideration the wedge factor when

    designing a soil nail wall. In addition when designing a soil nail wall a slope

  • 7/28/2019 Ground Improvement Assignment

    15/31

    15

    stability mechanism with an approximately shaped slip surfaces that can

    handle the nails is used.

    Estimate design mechanisms basically rely on the assumed shape of the slip

    surface, this can be done by estimating the lateral and vertical spacings of the

    nails sh and sv respectively, and an assumed lateral earth-pressure

    distributions. This defines an influence area for each nail which may be

    multiplied by a factor of safety, FS, in order to calculate the required

    resistance from each nail, Treq

    Treq= (FS) h sv sh(i)

    Where h is the horizontal vertical stress. The minimum value of FS is 2.

    Analysis will always be backed by the type of problems and applicability of the

    said analysis method.

    There are basically two principles that can be followed when analysing the

    applicability of soil nailing that is to say, the limit equilibrium method and finite

    element method.

    Limit equilibrium Method; This is used to evaluate the overall stability of the

    soil nail wall and helps in determining the total required nail forces required to

    support the soil mass.

    Finite Element Method is normally used to predict stresses, bending moments

    and axial loads in the structural components, movement of the wall and thesettlement in the supported ground.

    3.2 Soil nailing as compared to tie backs and Mechanically Stabilised

    Earth (MSE) walls

    We should appreciate the big similarity between soil nail walls and tie backs

    as both are in-situ reinforcement methods but there also differences which

    may make one more suitable than the other under given conditions. Though

    MSE walls are slightly different they also exhibit some similarities with soil

  • 7/28/2019 Ground Improvement Assignment

    16/31

    16

    nailing as a method of ground reinforcement since they also exhibit a passive

    kind of reinforcement.

    The table (Tab 1) below as adopted from the FHWA,i998, Manual for

    construction and Design of soil nail walls. Shows the principle comparisons

    amongst soil nailing tiebacks and mechanically stabilised Earth walls.

    Soil Nail Walls Tie backs MSE Walls

    Construction

    Top-Down (Cut

    in-situ)

    Top-down(Cut in

    situ)Downup(fill up)

    Reinforcements

    are Drilled and

    grouted through

    both passive and

    active zones

    Reinforcements

    are only in active

    zones.

    Sheets for

    reinforcement are

    sandwiched

    between active

    and passive

    zones.

    Reinforcements

    are Actively

    stressed

    throughout

    excavation

    process.

    They are Actively

    stressed only at

    present

    excavation point.

    Passively

    stressed as fill

    construction

    progresses.

    Loads in

    reinforcement

    decrease from

    top to bottom.

    There is almost

    uniform load

    distribution.

    Loads in

    reinforcement

    decrease from

    bottom to top

    Wall behaviour

    Facing caries

    only load not

    supported by

    nails.

    Facing caries full

    soil dressing

    Facing caries

    only load not

    supported by

    reinforcement

    sheets.

    Load transfer

    between soil and

    Load never

    distributes to the

    Load transfer

    between soil

  • 7/28/2019 Ground Improvement Assignment

    17/31

    17

    reinforcement

    occurs along full

    length of the soil

    nail.

    active zones mass and nail

    occurs along full

    length.

    Tensile forces on

    reinforcements

    are due to gravity

    forces acting on

    the soil mass in

    active zones.

    Tensile forces in

    Anchor results

    from equilibrium

    between tensile

    forces applied to

    the anchor head

    during stressing

    and self weight of

    soil in active

    zones.

    Tensile forces on

    reinforcements

    are due to gravity

    forces in active

    zones of the soil

    Soil is partially

    confined by nails.

    Soil is confined

    by facing only.

    Soil is mostly

    confined by

    reinforcement

    depending on

    reinforcement

    used and

    spacing.

    Maximum wall

    deflection is at

    the top of the

    wall.

    Maximum wall

    deflection is mid

    way the wall

    Maximum

    deflection mostly

    at lower third

    level of the wall

    Design approach

    (internal)

    Limit equilibrium

    approach is used

    to

    Empirical Earth

    pressure

    approach is used

    to derive

    reinforcement

    stress, which is

    equated to

    reinforcement

    Empirical earth

    pressure

    distribution is

    used to calculate

    reinforcement

    stress, which is

    equated to

    reinforcement

  • 7/28/2019 Ground Improvement Assignment

    18/31

    18

    capacity to

    determine safety

    factor against

    rupture and pull

    out.

    capacity to

    determine the

    safety factor

    against

    reinforcement

    rupture and pull

    out. (but this is

    done differently

    from the one for

    tie backs)

    Reinforcement

    strength and pull

    out resistance is

    calculated once

    throughout the

    entire wallconstruction or at

    intermediate

    stages.

    Reinforcement

    strength and pull

    out resistance is

    calculated at

    each and every

    stage of

    construction

    basing on the

    anchor capacity

    required for the

    facing to

    structurally resist

    the lateral earth

    pressure.

    Reinforcement

    strength and pull

    out resistance is

    calculated at

    each and every

    stage of

    construction in

    order to resist thelocal lateral earth

    pressure in the

    tributary area of

    the

    reinforcement.

    Facing and

    facing-nail

    connection

    system are

    checked for

    possible failure

    modes such as

    flexural and shear

    using empirical

    Facings such as

    soldier piles and

    facing tieback

    system is

    checked for

    possible failure

    modes under the

    installed tie back

    pre-stress

    Facing-

    reinforcement

    system is

    checked for

    possible failure

    modes using

    empirical earth

    pressure

    distribution at the

  • 7/28/2019 Ground Improvement Assignment

    19/31

    19

    Tab 1

    Though soil nailing is one of the best technique for soil wall reinforcement bit

    may not be always applicable and therefore another technique such as tie

    backs and MSE walls may be applied as discussed below.

    Soil nailing should be given priority over tie backs where applicable because

    There is no need for high capacity structural facing since most loads

    are not transferred to the excavation facing in soil nailing.

    Soil nails have a very small diameter and therefore are less obstructed

    in heterogeneous cobbles boulders and any other hard obstacles

    unlike the soldier piles used in tie backs whose diameter is so large.

    Easier to construct and less time spent during construction of soil nails

    than tie backs because; no soldier piles required, no prestressing of

    soil nails and the construction equipments are less thus mobile and

    quite.

    The vertical components of the nail reaction at the facing are lower

    than those for tie backs and are more evenly distributed on the entire

    earth pressure

    distribution at the

    facing

    facing.

    Design approach

    (external)

    Reinforced zone

    is treated as a

    rigid body,

    evaluating

    overturning and

    bearing capacity.

    Only slope

    stability behind

    wall is typically

    evaluated, but

    bearing failure of

    the gravity wall

    must be

    evaluated under

    adverse

    foundation

    conditions

    Reinforced zone

    is treated as rigid

    body, putting;

    sliding

    overturning, and

    bearing capacity

    into

    consideration.

    Slope stability

    behind the wall is

    also evaluated

  • 7/28/2019 Ground Improvement Assignment

    20/31

    20

    excavation wall and hence no need for significant embedments in soil

    nailing as its the case with tie backs.

    There is higher system redundancy in soil nailing than in tie backs thus

    consequences of failure are less.

    For soils with low water content granular back fills that are predominantly

    frictional in nature MSE walls may be used instead of the soil nail walls since

    properties of soil in MSE walls can be pre-selected.

    The nail excavations are more suited for temporary and permanent structures

    as compared to tie backs because more movement is required for

    mobilisation of nail resistance than tie back resistance.

  • 7/28/2019 Ground Improvement Assignment

    21/31

    21

    CONCLUSION

    Applicability of any ground improvement technique will always depend on the

    number of soil factors such as its properties and the topography of the

    landscape so always feasibility of the ground improvement technique to be

    used must be evaluated. The feasible ground improvement technique taken

    should always meet the economic/financial plan.

    Though there are various methods of stabilising walls soil nailing should be

    given priority where soil conditions are favourable given its economic

    advantages and so ever.

  • 7/28/2019 Ground Improvement Assignment

    22/31

    22

    Appendix ASAFETY CONSIDERATIONS

    Before any construction work takes place an authorisation by the local bodies

    must be obtained. One of the pre requisites before authorisation is given is to

    provide a well detailed safety plan for the anticipated risks together with the

    mitigations to be undertaken.

    Soil nailing as a project is very risky since it involves working at heights, using

    electrical equipments, chemical components. So to ensure safety at the site

    guidelines should be laid out and strict regulations imposed on following them.

    The following are some of the guide lines that may be followed

    Safety Precautions While At Site in Soil Nail Wall Construction(Adapted from Safety, Health policy and Manual, Visage Contractors Sdn. Bhd.)

    1. Personal safety

    a. All workers on site are supposed to observe and abide by the rules and

    regulations as laid down and approved at the construction site

    b. One should eliminate any obvious hazardous element at the site by

    oneself or inform the concerned personnel such as site supervisor.

    c. Maximum care should be undertaken while walking or moving about

    the site in order to avoid slipping, falling or tripping.

    d. Never stand under a suspended load. One should stay alert at all

    times.

    e. Ensure that tools or other materials on scaffolds or other elevators are

    not left where they may dislodge and fall

    f. Never throw tools, materials or equipment up to down from one

    working level to another-use safe working method.

    2. Personal Protection equipment

    a. Wear face shield when engaged in grinding work.

    b. Wear gas welding gaggles when engaged in gas cutting work.

    c. Use welding shield when engaged in welding work.

    d. Use safety belts whenever working at heights greater than 3meters.

    e. Wear clear safety glasses when working at the site (not specifically for

    cutting, welding etc)

  • 7/28/2019 Ground Improvement Assignment

    23/31

    23

    f. Wear ear plugs when working in noisy environments.

    g. Always wear working garments safety boots and helmet inclusive.

    3. Excavations

    a. For excavations more than 1.5 meters deep, safety precautions should

    be taken such as slope edge, barricade, ladder etc.

    b. Excavation work should be left to competent work men but under tight

    supervision.

    c. A proper sheet pile should be constructed around inside the excavation

    pit 9incase there is sand mix with soil and water).

    d. The excavation pit should be inspected on a daily basis and hazardous

    things such as unprotected cables, leakages on gas cylinder checked

    on.

    e. In case of any changes in the support soil or surrounding surface

    condition, no one should enter and immediate action should be taken

    such as reporting the condition to safety officers or supervisors

    f. Safe ladder access should be placed into the excavation pit.

    g. Excavation should not be too close to any vehicle or scaffold erection.

    h. A proper barrier should be created around the excavation pit.

    i. Remember to always wear protective equipment such as helmet and

    suitable footwear.

    4. Carpentry

    a. Erection, dismantling of form work must be carried out under

    supervision of competent supervisor.

    b. Timber and plywood should be clamped firmly at designated platform

    c. All off-cut from timber should be kept under a rubbish pit

    d. Tidiness/housekeeping should be carried out at all times whilst on site.

    e. Hammer, measuring tape chisels and other tools should not be left at

    edges.

    f. Always remember to wear the right protective equipments such as face

    mask, helmet and safety boots while at work.

    g. Incomplete form work area must be barricade temporary for exampleusing timber or warning tape.

  • 7/28/2019 Ground Improvement Assignment

    24/31

    24

    h. Underside form work erection (slab) that is to be concreted must be

    labelled as dangerous and barricaded.

    5. Concreting /casting

    a. Before concreting commences, firm and proper working platform must

    be installed and erected by competent workmen.

    b. It should be carried out by competent work men under supervision.

    c. Always remember to wear protective equipment whilst carrying out

    concreting work.

    d. Signalman should be used during concreting using the crane.

    e. Sufficient lighting must be in place whilst concreting at night.

    f. Edge area should be barricaded immediately after concreting.

    g. Support form work should be barricaded to avoid other workers from

    entering whilst concreting is in progress.

    h. Do not exceed/overload the concrete bucket to avoid spillage.

    6. Working At heights

    a. Always use your safety belt whilst working at heights and remember to

    check your belt for any damages or defects.

    b. Use a life line when you cannot find a secure place to attach your

    safety belt/harness lanyard. Remember your safety belt/harness is only

    as strong as the point where it is attached.

    c. Excavations and trenches more than 1.5 meters (5ft) deep must have

    an access/exit ladder at travel intervals of 7.6 meters. (25ft).

    d. Do not attempt to carry tools or materials up or down ladders and

    monkey boards. Use a rope and bucket to raise or lower your tools or

    materials.

    e. The top of an erected ladder should be properly extended at least 60

    centimetres (2ft) above the landing. The ladder should be properly

    secured to the landing to prevent falling or slipping.

    f. When handrails, toe boards, safety nets, platforms or scaffolds are to

    be removed to perform work, they should be replaced as soon as the

    work is finished.

  • 7/28/2019 Ground Improvement Assignment

    25/31

    25

    g. In case of dizziness or illness the worker should immediately tell the

    supervisor and s/he should stop working at heights.

    h. Remember not to throw or toss materials or any other objects to the

    ground whilst at heights.

    7. Safety signage/signboards

    There should be signage at the site which are understood by all workers

    undertaking the project and they should not be ignored by whosoever is on

    site. Workers and community members may undertake a safety training

    program before construction commences to ensure effective communication

    at the site through use of signage and sign boards.

    The following safety and signage tools must be installed at the site before

    commencing work;

    First aid box which is fully equipped with all the necessary elements

    Fire extinguishers at different points on the site; they should be located

    in such a way that they are easily accessible,

    Keep clean sign board

    Danger openings/emergency exits

    Scaffold in progress

    Safe for use

    Alarm which is well functioning

    Call centres for easy communication

    8. Emergency Procedures

    In case of fire;

    Sound the alarm

    Extinguish

    Call the fire department or emergency service

    In case of injuries;

    First aid should be applied to the patient

    Consider visiting a clinic for minor injuries

  • 7/28/2019 Ground Improvement Assignment

    26/31

    26

    Call ambulance service in case of serious injuries

    Report injuries/discrepancies however minor/small they may seem.

    All workers are advised to offer a helping hand in case of any emergency but

    should always ensure their safety first.

    Proper communication among workers should be emphasized.

    Re-enforcement

    To ensure security at the site the following records may be taken;

    An emergence response plan should be put in place fully illustrating the

    procedures to be taken in case of any emergence.

    Records of all workers; a roll call should be taken at least twice a day

    (at arrival and departure time) for big projects.

    Checklist of all gadgets/machines/instruments: it should fully illustrate

    their working condition periodically.

    Accident report forms should be in place

    A safety program sheet

    Safety statistics

  • 7/28/2019 Ground Improvement Assignment

    27/31

    27

    Appendix B - BRIEF INFORMATION ABOUT THE SITE VISITED FOR THIS

    ASSIGNMENT

    The case study was carried out at Taman Bukit Segar hill development

    project, Cheras Kuala Lumpur, Malaysia.

    Topography: it is a highland (hill) which is over 15m high. The slope is a 90o

    slope.

    Engineering consultants: Kamal TI Sdn. Bhd.

    This project was intended to protect the residents around the area from a

    threat of a Land slide due to the slope instability. The slope had once

    collapsed leading to great economic loss and lives ceased.

    The inner layers of the Earth component of the area consist of hard rocks and

    thus a soil nail wall is applicable since the earth can stand during construction

    The high water content in the soil loosened the top layers thus leading to the

    slope instability which later resulted into its collapse in March, 2009 leaving

    many dead and others in fear. This awakened the concerned authorities and

    means to prevent further collapsing had to be devised. The photograph below

    gives a glimpse at how the hill was like before the construction of the soil nail.

    (Source: Landslides under microscope-Web blog)

  • 7/28/2019 Ground Improvement Assignment

    28/31

    28

    A slope stabilisation technique had to be set up and the drainage also had to

    be improved to make the area below the highland habitable. The engineering

    consultants deemed it necessary to set up a soil nail wall and vertical

    drainage system to cater for the stability of the wall.

    The photograph below shows how the place was like as at the time of the site

    visit.

    .

    Source: Pictures taken at Bukit Segar on 22nd October, 2009)

  • 7/28/2019 Ground Improvement Assignment

    29/31

    29

    APPENDIX C- PHOTOGRAPHY

    a-d,i- future engineers struggling their way up the soil nailed wall, f-sheet pile

    at the site,e- a clear view of the nail heads,

    a b cd

    e f g

    h ij k

    mn

    o

  • 7/28/2019 Ground Improvement Assignment

    30/31

    30

    REFERANCES

    Rodrigo Salgado, The Engineering Of Foundations, Mc-Graw Hill International

    Edition.

    Petros P. Xannthankos, Ground Anchors And Anchored Structures Wiley

    Inter-Science Publication

    Coastal Caisson Corporation,

    http://www.coastalcaisson.com/en/products/soilnailing/ (accessed on14th

    November, 2009)

    Landslides under Microscope,

    :http://landslidesgib.blogspot.com/2008_12_01_archive.html (accessed

    on1st October, 2009

    Liew Shaw Shong, Soil Nailing for slope Strengthening, retrieved from

    http://www.gnpgeo.com.my/download/publication/L_09.pdf - (on 14th october,

    2009)

    U.S Department for Transport, Federal Highway Administration, (1998),

    Manual for Design and Construction Monitoring of Soil Nail Walls, (FHWA-SA-

    96-069R) Retrieved from http://isddc.dot.gov/OLPFiles/FHWA/010571.pdf,

    accessed on 5th October, 2009

    Visage Contractors Sdn. Bhd. And JV. Suhati Sdn. Bhd., Safety, Health Policy

    and Manual, Kuala Lumpur, Malaysia, unpublished.

    Landslides under microscope, http: //landslides-

    gib.blogspot.com/2008/12/landslide-caused-by-human-activity.html Accessed

    on 14Th October, 2009

  • 7/28/2019 Ground Improvement Assignment

    31/31

    Structure Source, http://

    www.structsource.com/retainingwall/types/soilnail.htm. Retrieved on27th

    October, 2009

    Coastal caisson, http://www.coastalcaison.com/en/products/soilnailing.jpg

    (accessed on26 October, 2009)