ground improvement assignment
TRANSCRIPT
-
7/28/2019 Ground Improvement Assignment
1/31
1
CHAPTER 1
INTRODUCTION
Unlike in the past when man just wanted to set up construction work on
already well established land (naturally), nowadays land has to be improved.
This has majorly been due to the increasing demand for construction land
against its availability and the collapse of some landscapes due to landslides
and the like ( A case in point is the Bukit Antagabsa incident of 1993 and the
Bukit Segar incident of March, 2009)
Man has devised all means to improve the properties of land and make it
suitable for construction and habitable. Some of the properties he has tried to
affect include but not limited to:-
Drainage
Permeability
Density
Shear force and Bearing capacity
The objectives of ground improvement include:
Reduce settlement of structures
Improve shear strength and bearing capacity of the soil
Increase factor of safety against possible slope failure of Embankments
and dams
Reduce shrinkage and swelling of soils
There are very many ground improvement techniques that Man has
devised to improve the basic soil characteristics such are; grouting, soil
nailing, tie backs, mechanically stabilised earth walls etc.
Under certain circumstances more than one ground improvement
technique has to be used in order to achieve the overall objectives of
ground improvement. A case in point is the project at Taman Bukit Segara,
-
7/28/2019 Ground Improvement Assignment
2/31
2
Cheras Kuala Lumpur in which more than one technique was used as
discussed later in this report.
In this report though many techniques exist it mostly tackles the soil nailing
method of ground improvement and briefly hints on tie backs and MSE
walls.
-
7/28/2019 Ground Improvement Assignment
3/31
3
Chapter 2
LITERATURE REVIEW
This report basically discusses soil nailing as a ground improvement/slope
stabilisation technique based on a brief survey in Cheras, Kuala Lumpur,
Malaysia.
What is soil nailing?
Soil nailing is a technique in which soil slopes, excavations or retaining
walls are reinforced by the insertion of relatively slender elements - normally
steel reinforcing bars. Wikipedia
Soil nailing in other words is an in-situ kind of soil reinforcement technique in
which a slender object is inserted into the soil mass in order to enhance
stability by transferring load from active weak zones of the soil mass to
passive strong zones.
Soil nail walls are retaining walls which are built from the top downwards in
cut situations where the soil has enough apparent cohesion that it can stand
up on its own during construction. structure source
Soil nailing traces its origin far back in 1960s when it was first used in Mexico
and then in Europe in the 1970s. Due to the success of the projects in which
it was used it gained popularity in many places for both Hillside development
and in stabilising Embankments world over Malaysia inclusive.
Soil nail walls increase the resistance to shear forces that may cause the soil
slope to collapse. The steel bars act as the load bearing materials and as
reinforcement structures in the slope. Predominantly, Nails are considered to
operate in tension but there is a possibility of also working in bending/shear
Apart from its former successes it is seen as one of the best slope stabilising
technique because;
It does not require much maintenance post its construction.
http://en.wikipedia.org/wiki/Soilhttp://en.wikipedia.org/wiki/Soil -
7/28/2019 Ground Improvement Assignment
4/31
4
It is effective in slope stabilisation
It is also easy to construct and,
Economical.
It is an in-situ kind of ground improvement thus environmental friendlysince it is not a cut excavation and backfill method.
It can be applied to sites where accessibility may be difficult i.e where
working equipments may be difficult to move.
It is not noisy, silent and causes no vibration of the ground making it
suitable for urban areas.
It is flexible and can follow difficult excavation shapes and can be
adjusted to significant variations in soil conditions that be beencountered during construction.
The method is well suited to projects that may be of great concern such
as hill site developments and rehabilitation of distressed structures.
-
7/28/2019 Ground Improvement Assignment
5/31
5
Chapter 3
METHODOLOGY
3.1. SELECTION
Soil nail walls are normally constructed on slopes whose soil has strong
cohesive forces and hence can stand on their own during construction; soil
should have a temporary sub vertical stability of about 2 metres for a period of
not less than 2 days and the drilled hole should have a capability to stayunaltered for about 3-4 hours or more after drilling it. For this matter soil nail
walls can not be constructed on land whose soil mostly consists of clay, loose
sand or under water.
Landscapes whose soils are stiff fine or cohesion soils, cemented granular
soils, well graded granular soils with appreciable cohesion of about 5Kpa,
most residual soils and weathered rock mass with favourable geological
settings are suitable for soil nail wall construction; putting in mind that the
ground profile is not under water.
If the soils/landscape does not march the afore mentioned properties; there
can be risks such as loosing grout as it is being inserted, collapse of drilled
holes, poor nail to soil interface resistance due to the disturbance of the drilled
holes and localised face stability.
3.2 DESIGN
There are various methods of soil nail wall designing that are used depending
on where the construction is going to take place in respect to construction
regulations, economic considerations and expected time of work i.e.
temporary versus permanent. Particularly in Malaysia there is no particular
regulation regarding the design to but the one laid down by U.S Department of
-
7/28/2019 Ground Improvement Assignment
6/31
6
Transportation, Federal Highway Administration (FHWA), 1998, is more
recommended since it is cost efficient and practically viable.
The codes of conduct and design manuals include:
BS8006:1995, code of practice for strengthened/reinforced soils and other fills
Soil nailing is discussed in section 7.5: Reinforcement of existing ground in
BS8006:1995. There are two design procedures suggested in this manual; the
two wedge method and log-spiral methods are recommended for analysing
the stability of soil nailed slopes.
HA68/94, Design methods for the reinforcement of Highway slopes by
Reinforcement soil and soil nailing techniques
U.S Department of Transportation, Federal Highway Administration (FHWA),
1998, Manual for Design and Construction Monitoring Of Soil Nail Walls
BS8081:1989 Code of Practice for Ground Anchorage
3.3 INSTALATION
3.3.1 Equipments:
The following machinery needs to be in place in order to commence the soil
nail construction:
1. Man power: Like any other technical civil works soil nailing requires
both skilled and unskilled labour/casual workers for the smooth runningof the project. Perhaps depending on the project it requires more
casual workers at the site than the skilled/professionals and of course
more professionals in the design office.
2. Drilling Equipment: In most cases small hydraulic, track-mounted drill
rigs are used. The rigs are mostly of the rotary/percussive type that
uses section augers or drill rods. The advantage of these is that they
are economical since the mobilisation costs are lowered and do not
-
7/28/2019 Ground Improvement Assignment
7/31
7
require a large space for their operation as compared to hydraulic-
powered track mounted rigs with continuous flight augers.
3. Grout mixing machine; it should be is recommended that a high speed
shear colloidal mixer is used in order to attain a uniform quality grout.
4. Gunitting /shotcreting machine with a nozzle outlet to control the
amount of water injecting into high pressurized flow of sand and
cement mix.
5. Water suction pump
6. Compressor
Etc. as required in civil works
3.3.2Materials
Grout
Hot Deep galvanised steel Rods
Shortcrete/gunite
PVC pipes
Conditional spraying for the ground
3.3.3 Procedure
Asany other civil engineering work the first thing is to clear the land where the
construction work is going to be done. This may involve removal of
plantation/vegetation, flattening of some part of land either by grading or filling
using soil of better properties, burrowing and reconditioning the wall for
shotcrete surfacing.
Water control measures are then put in place to avoid any alterations during
the construction. For example in the Taman Bukit Segar hill development
project 12metre drainage, beam drain and interceptor drain were constructed.
PVC pipes of about 12 metres in length were inserted into the soil mass. This
way water finds its way out of the soil mass.
The wall is constructed from up to down i.e. the top most landscape is firstnailed and sequentially other layers follow in few steps as laid down below;
-
7/28/2019 Ground Improvement Assignment
8/31
8
The slope is drilled to about 9-12 metre depth. This is to ensure that the
hardest part of the soil is reached since the main aim is to clamp the less
dense soil to a denser soil so that tensile load is transferred from less stable
active zone of the landscape is transferred to passive strong inactive zones to
attain stability. The drilling was done numerously all over the slope at regular
close spacing of about 0.5-2metres to ensure maximum soil-nail interaction
within the soil mass for its reinforcement. The holes are about 75-200mm in
diameter in order to accommodate the steel rod and a reasonable amount of
grout. The kind of drilling used for slopes whose soil is well suited is known as
open cast method where drilling is done without casing. This way speed is
achieved and costs lowered.
The drilled holes are then flushed preferably using air to remove the dust from
the drilled holes. Rigid Hot deep galvanised steel was then put into the drilled
holes at a slight untensioned declination of about 150. Galvanised steel was
opted for because of its high resistive properties such as resistance to
corrosion.
Fig1: Drilling in progress (Source Manual for Design and construction monitoring of soil nail
Walls, FHWA)
-
7/28/2019 Ground Improvement Assignment
9/31
9
Fig2: Nail inserted at a slight declination horizontally (Source Manual for Design and
construction monitoring of soil nail Walls, FHWA)
Grouting (in-situ grouting) is then done using Grout of grade 30. Grouting can
also be done simultaneously as the galvanised steel bars are being inserted
into the drilled holes. The grout is applied all way round the steel bar so that
the steel rod is sandwiched between it; this reduces the risk of corrosion due
to rusting of the steel bar.
A bearing plate is then put at the outermost end of the steel rod in order to
hold the nail and grout firmly onto the earth mass (wall).
The wall is then sprayed with shotcrete and a bearing plate is put at the
outermost end of the steel bar. The bearing plate is then fixed on the wall
using a nut and washer.
-
7/28/2019 Ground Improvement Assignment
10/31
10
Fig3: Spraying of concrete (Source Manual for Design and construction monitoring of
soil nail Walls, FHWA)
Fig4 :( Source: coastal caisson.com)
Then Nail heads are constructed over the steel rods and bearing plates. This
is done so that the steel rods, bearing plate, nut and washer are not left
exposed and are well attached to the wall. A simple conical/trapezoidal
shaped structure made out of concrete can be constructed over each steel
rod or the whole wall surface can be plastered but the former is more
economical.
Fig5: Nail head
-
7/28/2019 Ground Improvement Assignment
11/31
11
The above procedures are followed till the whole slope is nailed.
3.4 QUALITY CONTROL/ASSURANCE
It is true that not all construction works meet standards. Thus many structures
have found their way in collapsing after a given time,t thus leading to both life
and economic loss. Thus assurance of quality should be right from the start till
the end of the construction and periodical surveys should be carried out in
future though soil nailing does not require much inspection after constructionbut never know some catastrophe may occur. So to ensure quality preliminary
and working pull outs were taken.
Cone penetration test (CPT)
In this test a penetrometer with a conical tip and standard geometry is pushed
vertically into the ground at a standard rate of 20mm per second. Penetration
at this rate is fully drained for sands with non plastic silt contents of up to 10%
(Carraro et al.2003). This test is conducted during the site exploration to
determine the cone resistance, qc
Where, qc = vertical force acting on the tip of the penetrometer
The base area of the tip
(1000mm for the standard penetrometer with diameter of35.7mm)
Fig6: Photographic view of nail heads
-
7/28/2019 Ground Improvement Assignment
12/31
12
The qc can then be used to conclude on the nature of soil. Of recent invention
this test can also help in determining friction along a lateral sleeve and shear
wave velocities, pore pressure and other quantities with the help of seismic
shear waves.
The test is normally used because of its simplicity, speed and probably ability
to maintain a continuous profiling.
Cube test ; this was do check on the quality of the grout mix used.
Curing test/test panel; this was to test the quality of shortcrete used for
reinforcements.
Weight bearing capacity of the steel rods (nails) has to be determined and
ensure that the minimum load can meet the load on the soil mass.
Seasonal monitoring
Apart from the monitoring by the site resident Engineer, periodical monitoring
is done by the Local authorities such as Dewan Bandaraye Kuala Lumpur (a
body responsible for monitoring all construction work in Kuala Lumpur) after
every six months.
-
7/28/2019 Ground Improvement Assignment
13/31
13
-
7/28/2019 Ground Improvement Assignment
14/31
14
CHAPTER 4
ANALYSIS OF SOIL NAILING
Soil nailing is best suited for slope stabilisation in which the soil mass can
stand on its own.
3.1 FAILURE MODES IN SOIL NAILING AND CORRECTION
PROCEDURES
Basically, for the soil nailing technique discussed in this report, where the nail
head is attached to the ground, only one failure mode is exhibited. It is as a
result of the sliding of the soil wedge moving down and out thus dragging the
nails along with it. This movement results from shear stress that develops
along the soil interface with the nails. The resistance between a nail in
question and the soil beyond the sliding wedge can then be mobilized.
The wedge tends to drag the nail, the stable soil mass drags it in the opposite
direction and the nail itself pulls the wedge. If the resistance of the soil nail is
sufficient, the wall-nail-soil system will be stable; otherwise the soil wedge will
slide carrying along the nails with it.
Fig 7: Failure mechanism in soil nailing
This makes it necessary to put into consideration the wedge factor when
designing a soil nail wall. In addition when designing a soil nail wall a slope
-
7/28/2019 Ground Improvement Assignment
15/31
15
stability mechanism with an approximately shaped slip surfaces that can
handle the nails is used.
Estimate design mechanisms basically rely on the assumed shape of the slip
surface, this can be done by estimating the lateral and vertical spacings of the
nails sh and sv respectively, and an assumed lateral earth-pressure
distributions. This defines an influence area for each nail which may be
multiplied by a factor of safety, FS, in order to calculate the required
resistance from each nail, Treq
Treq= (FS) h sv sh(i)
Where h is the horizontal vertical stress. The minimum value of FS is 2.
Analysis will always be backed by the type of problems and applicability of the
said analysis method.
There are basically two principles that can be followed when analysing the
applicability of soil nailing that is to say, the limit equilibrium method and finite
element method.
Limit equilibrium Method; This is used to evaluate the overall stability of the
soil nail wall and helps in determining the total required nail forces required to
support the soil mass.
Finite Element Method is normally used to predict stresses, bending moments
and axial loads in the structural components, movement of the wall and thesettlement in the supported ground.
3.2 Soil nailing as compared to tie backs and Mechanically Stabilised
Earth (MSE) walls
We should appreciate the big similarity between soil nail walls and tie backs
as both are in-situ reinforcement methods but there also differences which
may make one more suitable than the other under given conditions. Though
MSE walls are slightly different they also exhibit some similarities with soil
-
7/28/2019 Ground Improvement Assignment
16/31
16
nailing as a method of ground reinforcement since they also exhibit a passive
kind of reinforcement.
The table (Tab 1) below as adopted from the FHWA,i998, Manual for
construction and Design of soil nail walls. Shows the principle comparisons
amongst soil nailing tiebacks and mechanically stabilised Earth walls.
Soil Nail Walls Tie backs MSE Walls
Construction
Top-Down (Cut
in-situ)
Top-down(Cut in
situ)Downup(fill up)
Reinforcements
are Drilled and
grouted through
both passive and
active zones
Reinforcements
are only in active
zones.
Sheets for
reinforcement are
sandwiched
between active
and passive
zones.
Reinforcements
are Actively
stressed
throughout
excavation
process.
They are Actively
stressed only at
present
excavation point.
Passively
stressed as fill
construction
progresses.
Loads in
reinforcement
decrease from
top to bottom.
There is almost
uniform load
distribution.
Loads in
reinforcement
decrease from
bottom to top
Wall behaviour
Facing caries
only load not
supported by
nails.
Facing caries full
soil dressing
Facing caries
only load not
supported by
reinforcement
sheets.
Load transfer
between soil and
Load never
distributes to the
Load transfer
between soil
-
7/28/2019 Ground Improvement Assignment
17/31
17
reinforcement
occurs along full
length of the soil
nail.
active zones mass and nail
occurs along full
length.
Tensile forces on
reinforcements
are due to gravity
forces acting on
the soil mass in
active zones.
Tensile forces in
Anchor results
from equilibrium
between tensile
forces applied to
the anchor head
during stressing
and self weight of
soil in active
zones.
Tensile forces on
reinforcements
are due to gravity
forces in active
zones of the soil
Soil is partially
confined by nails.
Soil is confined
by facing only.
Soil is mostly
confined by
reinforcement
depending on
reinforcement
used and
spacing.
Maximum wall
deflection is at
the top of the
wall.
Maximum wall
deflection is mid
way the wall
Maximum
deflection mostly
at lower third
level of the wall
Design approach
(internal)
Limit equilibrium
approach is used
to
Empirical Earth
pressure
approach is used
to derive
reinforcement
stress, which is
equated to
reinforcement
Empirical earth
pressure
distribution is
used to calculate
reinforcement
stress, which is
equated to
reinforcement
-
7/28/2019 Ground Improvement Assignment
18/31
18
capacity to
determine safety
factor against
rupture and pull
out.
capacity to
determine the
safety factor
against
reinforcement
rupture and pull
out. (but this is
done differently
from the one for
tie backs)
Reinforcement
strength and pull
out resistance is
calculated once
throughout the
entire wallconstruction or at
intermediate
stages.
Reinforcement
strength and pull
out resistance is
calculated at
each and every
stage of
construction
basing on the
anchor capacity
required for the
facing to
structurally resist
the lateral earth
pressure.
Reinforcement
strength and pull
out resistance is
calculated at
each and every
stage of
construction in
order to resist thelocal lateral earth
pressure in the
tributary area of
the
reinforcement.
Facing and
facing-nail
connection
system are
checked for
possible failure
modes such as
flexural and shear
using empirical
Facings such as
soldier piles and
facing tieback
system is
checked for
possible failure
modes under the
installed tie back
pre-stress
Facing-
reinforcement
system is
checked for
possible failure
modes using
empirical earth
pressure
distribution at the
-
7/28/2019 Ground Improvement Assignment
19/31
19
Tab 1
Though soil nailing is one of the best technique for soil wall reinforcement bit
may not be always applicable and therefore another technique such as tie
backs and MSE walls may be applied as discussed below.
Soil nailing should be given priority over tie backs where applicable because
There is no need for high capacity structural facing since most loads
are not transferred to the excavation facing in soil nailing.
Soil nails have a very small diameter and therefore are less obstructed
in heterogeneous cobbles boulders and any other hard obstacles
unlike the soldier piles used in tie backs whose diameter is so large.
Easier to construct and less time spent during construction of soil nails
than tie backs because; no soldier piles required, no prestressing of
soil nails and the construction equipments are less thus mobile and
quite.
The vertical components of the nail reaction at the facing are lower
than those for tie backs and are more evenly distributed on the entire
earth pressure
distribution at the
facing
facing.
Design approach
(external)
Reinforced zone
is treated as a
rigid body,
evaluating
overturning and
bearing capacity.
Only slope
stability behind
wall is typically
evaluated, but
bearing failure of
the gravity wall
must be
evaluated under
adverse
foundation
conditions
Reinforced zone
is treated as rigid
body, putting;
sliding
overturning, and
bearing capacity
into
consideration.
Slope stability
behind the wall is
also evaluated
-
7/28/2019 Ground Improvement Assignment
20/31
20
excavation wall and hence no need for significant embedments in soil
nailing as its the case with tie backs.
There is higher system redundancy in soil nailing than in tie backs thus
consequences of failure are less.
For soils with low water content granular back fills that are predominantly
frictional in nature MSE walls may be used instead of the soil nail walls since
properties of soil in MSE walls can be pre-selected.
The nail excavations are more suited for temporary and permanent structures
as compared to tie backs because more movement is required for
mobilisation of nail resistance than tie back resistance.
-
7/28/2019 Ground Improvement Assignment
21/31
21
CONCLUSION
Applicability of any ground improvement technique will always depend on the
number of soil factors such as its properties and the topography of the
landscape so always feasibility of the ground improvement technique to be
used must be evaluated. The feasible ground improvement technique taken
should always meet the economic/financial plan.
Though there are various methods of stabilising walls soil nailing should be
given priority where soil conditions are favourable given its economic
advantages and so ever.
-
7/28/2019 Ground Improvement Assignment
22/31
22
Appendix ASAFETY CONSIDERATIONS
Before any construction work takes place an authorisation by the local bodies
must be obtained. One of the pre requisites before authorisation is given is to
provide a well detailed safety plan for the anticipated risks together with the
mitigations to be undertaken.
Soil nailing as a project is very risky since it involves working at heights, using
electrical equipments, chemical components. So to ensure safety at the site
guidelines should be laid out and strict regulations imposed on following them.
The following are some of the guide lines that may be followed
Safety Precautions While At Site in Soil Nail Wall Construction(Adapted from Safety, Health policy and Manual, Visage Contractors Sdn. Bhd.)
1. Personal safety
a. All workers on site are supposed to observe and abide by the rules and
regulations as laid down and approved at the construction site
b. One should eliminate any obvious hazardous element at the site by
oneself or inform the concerned personnel such as site supervisor.
c. Maximum care should be undertaken while walking or moving about
the site in order to avoid slipping, falling or tripping.
d. Never stand under a suspended load. One should stay alert at all
times.
e. Ensure that tools or other materials on scaffolds or other elevators are
not left where they may dislodge and fall
f. Never throw tools, materials or equipment up to down from one
working level to another-use safe working method.
2. Personal Protection equipment
a. Wear face shield when engaged in grinding work.
b. Wear gas welding gaggles when engaged in gas cutting work.
c. Use welding shield when engaged in welding work.
d. Use safety belts whenever working at heights greater than 3meters.
e. Wear clear safety glasses when working at the site (not specifically for
cutting, welding etc)
-
7/28/2019 Ground Improvement Assignment
23/31
23
f. Wear ear plugs when working in noisy environments.
g. Always wear working garments safety boots and helmet inclusive.
3. Excavations
a. For excavations more than 1.5 meters deep, safety precautions should
be taken such as slope edge, barricade, ladder etc.
b. Excavation work should be left to competent work men but under tight
supervision.
c. A proper sheet pile should be constructed around inside the excavation
pit 9incase there is sand mix with soil and water).
d. The excavation pit should be inspected on a daily basis and hazardous
things such as unprotected cables, leakages on gas cylinder checked
on.
e. In case of any changes in the support soil or surrounding surface
condition, no one should enter and immediate action should be taken
such as reporting the condition to safety officers or supervisors
f. Safe ladder access should be placed into the excavation pit.
g. Excavation should not be too close to any vehicle or scaffold erection.
h. A proper barrier should be created around the excavation pit.
i. Remember to always wear protective equipment such as helmet and
suitable footwear.
4. Carpentry
a. Erection, dismantling of form work must be carried out under
supervision of competent supervisor.
b. Timber and plywood should be clamped firmly at designated platform
c. All off-cut from timber should be kept under a rubbish pit
d. Tidiness/housekeeping should be carried out at all times whilst on site.
e. Hammer, measuring tape chisels and other tools should not be left at
edges.
f. Always remember to wear the right protective equipments such as face
mask, helmet and safety boots while at work.
g. Incomplete form work area must be barricade temporary for exampleusing timber or warning tape.
-
7/28/2019 Ground Improvement Assignment
24/31
24
h. Underside form work erection (slab) that is to be concreted must be
labelled as dangerous and barricaded.
5. Concreting /casting
a. Before concreting commences, firm and proper working platform must
be installed and erected by competent workmen.
b. It should be carried out by competent work men under supervision.
c. Always remember to wear protective equipment whilst carrying out
concreting work.
d. Signalman should be used during concreting using the crane.
e. Sufficient lighting must be in place whilst concreting at night.
f. Edge area should be barricaded immediately after concreting.
g. Support form work should be barricaded to avoid other workers from
entering whilst concreting is in progress.
h. Do not exceed/overload the concrete bucket to avoid spillage.
6. Working At heights
a. Always use your safety belt whilst working at heights and remember to
check your belt for any damages or defects.
b. Use a life line when you cannot find a secure place to attach your
safety belt/harness lanyard. Remember your safety belt/harness is only
as strong as the point where it is attached.
c. Excavations and trenches more than 1.5 meters (5ft) deep must have
an access/exit ladder at travel intervals of 7.6 meters. (25ft).
d. Do not attempt to carry tools or materials up or down ladders and
monkey boards. Use a rope and bucket to raise or lower your tools or
materials.
e. The top of an erected ladder should be properly extended at least 60
centimetres (2ft) above the landing. The ladder should be properly
secured to the landing to prevent falling or slipping.
f. When handrails, toe boards, safety nets, platforms or scaffolds are to
be removed to perform work, they should be replaced as soon as the
work is finished.
-
7/28/2019 Ground Improvement Assignment
25/31
25
g. In case of dizziness or illness the worker should immediately tell the
supervisor and s/he should stop working at heights.
h. Remember not to throw or toss materials or any other objects to the
ground whilst at heights.
7. Safety signage/signboards
There should be signage at the site which are understood by all workers
undertaking the project and they should not be ignored by whosoever is on
site. Workers and community members may undertake a safety training
program before construction commences to ensure effective communication
at the site through use of signage and sign boards.
The following safety and signage tools must be installed at the site before
commencing work;
First aid box which is fully equipped with all the necessary elements
Fire extinguishers at different points on the site; they should be located
in such a way that they are easily accessible,
Keep clean sign board
Danger openings/emergency exits
Scaffold in progress
Safe for use
Alarm which is well functioning
Call centres for easy communication
8. Emergency Procedures
In case of fire;
Sound the alarm
Extinguish
Call the fire department or emergency service
In case of injuries;
First aid should be applied to the patient
Consider visiting a clinic for minor injuries
-
7/28/2019 Ground Improvement Assignment
26/31
26
Call ambulance service in case of serious injuries
Report injuries/discrepancies however minor/small they may seem.
All workers are advised to offer a helping hand in case of any emergency but
should always ensure their safety first.
Proper communication among workers should be emphasized.
Re-enforcement
To ensure security at the site the following records may be taken;
An emergence response plan should be put in place fully illustrating the
procedures to be taken in case of any emergence.
Records of all workers; a roll call should be taken at least twice a day
(at arrival and departure time) for big projects.
Checklist of all gadgets/machines/instruments: it should fully illustrate
their working condition periodically.
Accident report forms should be in place
A safety program sheet
Safety statistics
-
7/28/2019 Ground Improvement Assignment
27/31
27
Appendix B - BRIEF INFORMATION ABOUT THE SITE VISITED FOR THIS
ASSIGNMENT
The case study was carried out at Taman Bukit Segar hill development
project, Cheras Kuala Lumpur, Malaysia.
Topography: it is a highland (hill) which is over 15m high. The slope is a 90o
slope.
Engineering consultants: Kamal TI Sdn. Bhd.
This project was intended to protect the residents around the area from a
threat of a Land slide due to the slope instability. The slope had once
collapsed leading to great economic loss and lives ceased.
The inner layers of the Earth component of the area consist of hard rocks and
thus a soil nail wall is applicable since the earth can stand during construction
The high water content in the soil loosened the top layers thus leading to the
slope instability which later resulted into its collapse in March, 2009 leaving
many dead and others in fear. This awakened the concerned authorities and
means to prevent further collapsing had to be devised. The photograph below
gives a glimpse at how the hill was like before the construction of the soil nail.
(Source: Landslides under microscope-Web blog)
-
7/28/2019 Ground Improvement Assignment
28/31
28
A slope stabilisation technique had to be set up and the drainage also had to
be improved to make the area below the highland habitable. The engineering
consultants deemed it necessary to set up a soil nail wall and vertical
drainage system to cater for the stability of the wall.
The photograph below shows how the place was like as at the time of the site
visit.
.
Source: Pictures taken at Bukit Segar on 22nd October, 2009)
-
7/28/2019 Ground Improvement Assignment
29/31
29
APPENDIX C- PHOTOGRAPHY
a-d,i- future engineers struggling their way up the soil nailed wall, f-sheet pile
at the site,e- a clear view of the nail heads,
a b cd
e f g
h ij k
mn
o
-
7/28/2019 Ground Improvement Assignment
30/31
30
REFERANCES
Rodrigo Salgado, The Engineering Of Foundations, Mc-Graw Hill International
Edition.
Petros P. Xannthankos, Ground Anchors And Anchored Structures Wiley
Inter-Science Publication
Coastal Caisson Corporation,
http://www.coastalcaisson.com/en/products/soilnailing/ (accessed on14th
November, 2009)
Landslides under Microscope,
:http://landslidesgib.blogspot.com/2008_12_01_archive.html (accessed
on1st October, 2009
Liew Shaw Shong, Soil Nailing for slope Strengthening, retrieved from
http://www.gnpgeo.com.my/download/publication/L_09.pdf - (on 14th october,
2009)
U.S Department for Transport, Federal Highway Administration, (1998),
Manual for Design and Construction Monitoring of Soil Nail Walls, (FHWA-SA-
96-069R) Retrieved from http://isddc.dot.gov/OLPFiles/FHWA/010571.pdf,
accessed on 5th October, 2009
Visage Contractors Sdn. Bhd. And JV. Suhati Sdn. Bhd., Safety, Health Policy
and Manual, Kuala Lumpur, Malaysia, unpublished.
Landslides under microscope, http: //landslides-
gib.blogspot.com/2008/12/landslide-caused-by-human-activity.html Accessed
on 14Th October, 2009
-
7/28/2019 Ground Improvement Assignment
31/31
Structure Source, http://
www.structsource.com/retainingwall/types/soilnail.htm. Retrieved on27th
October, 2009
Coastal caisson, http://www.coastalcaison.com/en/products/soilnailing.jpg
(accessed on26 October, 2009)