Integrated Cost & Schedule Risk Analysis Dynamic Integrated Cost Estimator (DICE) Model This document contains Booz Allen Hamilton proprietary and confidential information and is intended solely for the use and information of the client to whom it is addressed. This data shall not be released to other contractors without written consent from Booz Allen Hamilton. Adelaide, Australia 28 June, 2011 Booz Allen Proprietary/Not for Distribution

Upload: researcheryourgov

Post on 23-Oct-2014

94 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Graham Gilmer & Eric Druker - Presentation

Integrated Cost & Schedule Risk Analysis Dynamic Integrated Cost Estimator (DICE) Model

This document contains Booz Allen Hamilton proprietary and confidential information and is intended solely for the use and information of the client to

whom it is addressed. This data shall not be released to other contractors without written consent from Booz Allen Hamilton.

Adelaide, Australia28 June, 2011

Booz Allen Proprietary/Not for Distribution

Page 2: Graham Gilmer & Eric Druker - Presentation

2

Outline

Introduction

RealTime Analytics™

Overview of Joint Confidence Level Analysis

NASA’s Joint Confidence Level Policy

Dynamic Integrated Cost Estimator (DICE) JCL Analysis Tool

Page 3: Graham Gilmer & Eric Druker - Presentation

3

Attempt at Humor

Page 4: Graham Gilmer & Eric Druker - Presentation

4

Whether assessing/analyzing NASA, DoD or Intelligence Community owned projects, the story is the same each time: Programs are increasingly experiencing growth above and beyond their initial cost and schedule estimates

This is not just a cosmetic problem: Cost and schedule growth delays capabilities and constraints the budgets of other programs causing a waterfall of instability

Studies have examined the reasons behind this growth reaching similar conclusions

1. Early program optimism leading to optimistic estimates

2. Insufficient cost and schedule reserves available to cover risk

3. Weak independent validation of cost and schedule

Recognizing this, many guides, including the GAO’s Cost Estimating Handbook, have included Risk Analysis as a required step in best practice cost estimating processes

Introduction

Page 5: Graham Gilmer & Eric Druker - Presentation

5

RealTime Analytics™

One of the challenges in performing cost and schedule analysis is the time required to run simulations

– Risk analysis, required for all cost estimates by 2009 Weapons System Acquisition Reform Act of 2009 and GAO, requires the use of simulations

– Run-times of minutes or hours prohibit most risk analyses models from being decision making tools as they can not be re-run during meetings

RealTime Analytics™ (RTA) is a collection of technologies, tools and methodologies allowing complex analytics to be performed far faster than using currently available methods

This presentation will focus on the Dynamic Integrated Cost Estimator (DICE) and the methodologies it addresses:

– Joint Confidence Level Analysis (Integrated Cost & Schedule Risk Analysis)

RTA tools allow simulations to run up to 99.99% faster than comparable industry tools

Simulations formerly taking minutes or hours to run now finish in under 1 second

– Allows decision makers to run an unlimited number of excursion scenarios without ever leaving the meeting room

Page 6: Graham Gilmer & Eric Druker - Presentation

6

Decision makers are starting to recognize that there is rarely a relation between cost risk analysis results and the program’s schedule

– This can lead to risk adjusted cost estimates that, if come to pass, will almost always imply associated schedule growth

From the other side, traditional schedule risk analysis typically leads to risk adjusted schedules that, if come to pass, will result in cost growth

Even when both of these analyses are performed on a program, they are typically done by disjoint groups under different sets of assumptions

Joint Cost & Schedule Risk Analysis is an attempt to integrate cost and schedule risk analysis in a way that produces meaningful, compatible results

This presentation will cover:

– NASA’s JCL Policy

– How JCLs are performed

Introduction to Joint Confidence Level Analysis

Page 7: Graham Gilmer & Eric Druker - Presentation

7

Historically, cost and schedule risk analyses are developed separately and their results are not compatible

– This can lead to risk adjusted cost estimates that, if come to pass, will almost always imply associated schedule growth and vice versa

– Joint Confidence Level Analysis combines cost and schedule risk analysis into a single, coherent output

Joint Confidence Level (JCL) analysis1 results in a bivariate distribution of final projected cost and schedule pairs

– Joint Confidence Levels represent the probability of finishing at or under both cost and schedule

JCL Analysis allows a program to:

– Defend budgetary and scheduling decisions

– Prioritize risks and other threats based on their overall impact to the program and not simply their anticipated local impact

– Develop more precise risk mitigation plans

What is Joint Confidence Level Analysis?

1Also known as Integrated Cost & Schedule Risk Analysis or Joint Cost & Schedule Risk Analysis

Cost

Pro

bab

ility

70% Joint Confidence Level Curve

Sch

edu

le

Page 8: Graham Gilmer & Eric Druker - Presentation

8

What is Joint Confidence Level Analysis?

The primary output from JCL analysis is the JCL scatter-plot

– Each point on the scatter plot represents 1 iteration of a Monte Carlo simulation performed on the JCL model

JCL scatter-plot provides:

– Joint Confidence Levels (e.g. For NASA Budgeting)

– Relationship between cost and schedule (e.g. $ cost growth/days schedule growth)

9/23/10

4/11/11

10/28/11

5/15/12

12/1/12

6/19/13

1/5/14

7/24/14

$603 $803 $1,003 $1,203

Laun

ch D

ate

Total Cost ($M)

Joint Confidence LevelFinal Results

Knee in the Curve Values50% 70%

Cost $787.7M $831.5MFOC 10/8/12 1/29/13

JCL DistrubutionProject Baseline = 61%70% JCL50% JCL

Page 9: Graham Gilmer & Eric Druker - Presentation

9

JCL Analysis: NASA Policy & Air Force Research

JCL Analysis becoming more common in industry

– In use by oil industry for years

– Already a requirement for NASA projects per NPD 1000.5

– Air Force completing research on JCL Analysis1

Several methods available for integrating cost & schedule; preferred method depends on program phase and available data

Parametric approaches:

– Typically used phase A and before or by oversight groups

– Divided into multiple regression and multivariate regression approaches

Build-up approaches:

– Typically used following phase B by PMOs

– Cost risk analysis and schedule risk analysis performed separately

– Quality checks performed to make sure analyses are compatible

1Joint Cost Schedule Model (JCSM): Recent AFCAA Efforts to Assess Integrated Cost and Schedule Analysis. Hogan, Greg (et al). SCEA 2011

Page 10: Graham Gilmer & Eric Druker - Presentation

10

JCL Analysis: Overview of Methods

1Joint Cost Schedule Model (JCSM): Recent AFCAA Efforts to Assess Integrated Cost and Schedule Analysis. Hogan, Greg (et al). SCEA 2011

Cost Risk Analysis:

•Inputs-Based Simulation•Outputs-Based Simulation•Scenario Based•Parametric Analysis

Schedule Risk Analysis:

•Parametric Analysis•Schedule-Based Simulation

Monte Carlo

Simulation

9/23/10

4/11/11

10/28/11

5/15/12

12/1/12

6/19/13

1/5/14

7/24/14

$603 $803 $1,003 $1,203

Laun

ch D

ate

Total Cost ($M)

Joint Confidence LevelFinal Results

Knee in the Curve Values50% 70%

Cost $787.7M $831.5MFOC 10/8/12 1/29/13

JCL DistrubutionProject Baseline = 61%70% JCL50% JCL

Joint Risk Analysis:

•Cost Loaded Schedule-Based Simulation (NASA Policy)•Multivariate Regression

9/23/10

4/11/11

10/28/11

5/15/12

12/1/12

6/19/13

1/5/14

7/24/14

$603 $803 $1,003 $1,203

Laun

ch D

ate

Total Cost ($M)

Joint Confidence LevelFinal Results

Knee in the Curve Values50% 70%

Cost $787.7M $831.5MFOC 10/8/12 1/29/13

JCL DistrubutionProject Baseline = 61%70% JCL50% JCL

Joint Risk Analysis methods estimate cost and schedule simultaneously; JCL scatter plot produced directly from analysis

When Joint Risk Analysis methods are not used, cost and schedule risk analyses must be combined using a Monte Carlo simulation

When risk analyses are combined, care must be taken to ensure results are compatible

Page 11: Graham Gilmer & Eric Druker - Presentation

11

JCL analysis can be performed using existing resources; likely risk management, cost estimating, and scheduling personnel

The artifacts needed to perform a JCL analysis are:

– A program schedule (IMS or analysis schedule) with uncertainty bounds on task durations

– A quantified risk register (probabilities, cost and schedule impacts) where each risk is mapped to a task in the IMS

– A cost estimate with uncertainty bounds that maps to the schedule

Creation of these artifacts requires communication between program’s cost estimating, scheduling and risk management staff

Joint Confidence Level Analysis Process at NASA

Integrated Risk Assessment

Program Risk

Register

Integrated Master

Schedule

Cost Estimate

Page 12: Graham Gilmer & Eric Druker - Presentation

12

Joint Confidence Level Analysis has gained significant momentum recently

– NASA is leading the way in the development of this methodology

– NASA Policy Directive 1000.5 mandates that programs will be baselined at the “70 percent confidence level” using a “joint cost and schedule probability distribution”2

– NPD 1000.5 also stipulates that projects are funded at no less than 50% of the JCL or as approved by the decision authority, maintaining JCLs through the program lifecycle

– The goal is to provide stronger assurance that NASA can meet cost and schedule targets3

– A recent GAO report cites NASA’s JCL policy as an effort “to provide transparency on the effects of funding changes on the probability of meeting cost and schedule commitments” 4

– NASA Cost Analysis Division (CAD) has developed a handbook to provide more information and guidance on this topic

– Programs conducting JCL Analysis include James Webb Space Telescope and SOFIA

While the methodology has made substantial strides, the cost and schedule communities must overcome political and technical obstacles before full adoption

NASA Joint Confidence Level Analysis Policy

2 – NPD 1000.5 - http://www.hq.nasa.gov/office/codeq/doctree/10005.htm - January 15, 20093 – JCL Status Report - http://www.nasa.gov/pdf/421542main_JCL%20Status%20Report-2010%20Feb.pdf – February 20104 – GAO Report – “NASA – Assessments of Selected Large-Scale Projects” - http://www.gao.gov/new.items/d11239sp.pdf - March 2011

Page 13: Graham Gilmer & Eric Druker - Presentation

13

NASA JCL Model Prototype: DICE

In Fall 2010, NASA CAD commissioned the development of a JCL model prototype

The intention of this effort was to explore the value of producing a standard toolset for NASA programs conducting JCL analysis

Booz Allen created the Dynamic Integrated Cost Estimator (DICE) with a focus on streamlining the JCL process and decreasing simulation runtimes

Other key features of the DICE prototype development included:

– Rapid schedule import from MS Project

– Cost-Loading

– Discrete Risk Analysis

– JCL Scatter Plots and Iso-Curves

– Benchmarking effort with other JCL tools

It is important to note that there are many tools that projects can use to develop JCLs, but DICE is optimized for this analysis

Page 14: Graham Gilmer & Eric Druker - Presentation

14

DICE facilitates Joint Confidence Level Analysis

DICE is an Adobe Flex-based tool for cutting-edge cost and schedule risk analysis

– Includes modeling capability for producing build-up Joint Confidence Levels (JCLs)

– Achieves industry-leading runtimes using Booz Allen’s RealTime Analytics

Page 15: Graham Gilmer & Eric Druker - Presentation

15

DICE – Benchmarking against Primavera Risk Analysis

Runtimes (3200-line schedule) S-Curves (at 0.4 correlation)

Correlation Key Points

– Identical input parameters to ensure consistency in benchmarking

– Importing risks from 3rd party template

– Outputs <1% variation from Primavera

Task Run Time DICE Primavera Opening Tool 0:02 0:05 Import Schedule 0:03 2:05:27 Load Risk File 0:03 0:01 Initialize Correlation 0:02 0:05 Run Simulation 0:09 2:27 Export Data 0:08 0:00

Schedule Cost

Total Project Cost

Project End Date

Project End Date

Page 16: Graham Gilmer & Eric Druker - Presentation

16

DICE Demo

Page 17: Graham Gilmer & Eric Druker - Presentation

17

Conclusion

Booz Allen’s recent innovations in simulation technology enable analysts to support decision making in near real-time

– Decision makers can see the impact of changes to their program, real-time, without ever leaving the meeting room

– There is no longer a limit on the number of excursions that can be run on an analysis

New Joint Confidence Level methods changes the way programs look at cost and schedule risk

– Analyses are no longer performed and viewed separately, but rather are integrated and optimized using a standard tool

– Decision makers have more insight into their program than ever before

– Opening of communication lines between cost, schedule and risk management staff results in better program management

Page 18: Graham Gilmer & Eric Druker - Presentation

18

Points of Contact

Booz | Allen | Hamilton

Colin SmithAssociate

Booz Allen Hamilton Inc.Suite 2100

230 Peachtree Street NWAtlanta, GA 30303

Tel (404) [email protected]

Booz | Allen | Hamilton

Booz | Allen | Hamilton

Brandon HerzogConsultant

Booz Allen Hamilton Inc.1530 Wilson Blvd., 10th Floor

Arlington, VA 22209Tel (703) 526-6040

[email protected]

Graham GilmerAssociate

Booz Allen Hamilton Inc.1530 Wilson Blvd., 10th Floor

Arlington, VA 22209Tel (703) 526-2413

[email protected]

Booz | Allen | Hamilton

Eric DrukerAssociate

Booz Allen Hamilton Inc.St. Louis, MO

Tel (314) [email protected]

Page 19: Graham Gilmer & Eric Druker - Presentation

19

DICE Functionality – Gantt Chart and Cost/Schedule Uncertainty

Organizes project tasks, costs, constraints, schedule interrelationships, and adds uncertainty to individual cost and schedule items

Page 20: Graham Gilmer & Eric Druker - Presentation

20

DICE Functionality – Cost-Loading

DICE can load schedules with time-dependent and time-independent costs, generating standard outputs such as JCL scatter plots and iso-curves

Page 21: Graham Gilmer & Eric Druker - Presentation

21

DICE Functionality – Fiscal Year Segmenting

DICE accounts for costs (and uncertainty) by fiscal year – aids budget planning

Page 22: Graham Gilmer & Eric Druker - Presentation

22

DICE Functionality – Run-time Features

DICE incorporates blanket correlation across the model, or specifies individual correlation between schedule tasks, time-independent costs, or risks

The model is optimized for Joint Confidence Level Analysis

– Greatly increases understanding of how schedule growth impacts cost

– Contains robust schedule logic functionality and discrete risk integration

DICE includes RealTime Analytics to enable industry-leading simulation runtimes

– Reduces the time required to evaluate decisions and provides decision makers with on-the-spot analysis

– Booz Allen’s RTA allows for quick initial runtimes and near-immediate re-runs

Interactive features provide intuitive user experience and rapid evaluation of alternatives

– Enables comparison of multiple different scenarios or confidence levels of the same project

– Builds off of existing tools (like MS Project, Excel) for seamless data integration, cost visualization, and navigation of risk analysis

Page 23: Graham Gilmer & Eric Druker - Presentation

23

RealTime Analytics: Excel Tool

Page 24: Graham Gilmer & Eric Druker - Presentation

24

RealTime Analytics Excel Tool™Introduction

RealTime Analytics™ Excel Tool

– Excel add-in enabling fast running of simulations

– Similar in capabilities to Crystal Ball and @Risk

Benefits:

– Runtime savings of >99% vs. COTS tools

– Analysis can be run without ever leaving the meeting room

– Decreased simulation runtimes allows running of unlimited number of excursion scenarios

– Not a numerical approximation approach such as Method of Moments, it simply runs simulations faster than existing tools

Uses:

– Cost estimating/risk analysis/risk management

– Insurance pricing/actuarial models

– Portfolio optimization/trade-off analysis

– Cash flow/profit analysis

Page 25: Graham Gilmer & Eric Druker - Presentation

25

RealTime Analytics Excel Tool:Benchmarking vs. Crystal Ball & @Risk

Comparison of Simulation Results

File Size265 MB

15 MB

Simulations include mix of triangular, normal, beta, lognormal and uniform distributions with same parameters in each model

444 correlated distributions with 9,620 forecasted values

Baseline scenario is the time to “prime” the models; includes adding in correlation

Each additional scenario is time to re-run model when a single distribution parameter is changed

Crystal Ball RTA

Simulation Run Times

Assumptions

0%10%20%30%40%50%60%70%80%90%

100%

$25,000 $35,000 $45,000 $55,000 $65,000 $75,000

Cum

ulati

ve P

roba

bilit

y

Cost

Results

CB RTA '@ Risk

<1 Second

4 Min

12 Min

12 Min

10 Min

6 Hrs 10 Min

7 Hrs 48 Min

13 Hrs 48 Min

Each "Excursion Scenario"

Baseline Scenario

Crystal Ball (Normal Mode) Crystal Ball (Extreme Mode) @Risk Real Time Analytics

~ ~

~