gba 573 - it project management final project - establishment of a project management management...
TRANSCRIPT
GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Management Office
10 July, 2003
Page 2GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Introduction 2
Project Plan and Schedule 6
Return on Investment 14
Risk Management and Communication Plan 19
Table of Contents
x
.Page 3
GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Introduction
Page 4GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Project Overview
Introduction
Company background ABC Corp is a software and system development company that conducts multiple IT related projects on an ongoing basis.
Recent research has shown that a best practice is to establish an office to lead and manage IT projects.
PMO background and Justification It was determined that a Project Management Office (PMO) would improve ABC’s ability to appropriately and effectively manage and staff IT projects and reduce costs.
Over the last five years projects have experienced trouble either in the form of: Scope creep, resource shortages, increase in costs and delays in project completion, and project failures. Overall ABC incurs an average cost of $348,000 annually.
High Level PMO Responsibilities Consistent project management methodology
A standardized project management tools.
Instituting a project governance process
Project oversight of IT projects company-wide.
Page 5GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Project Overview
Introduction
Project Team Project Manger
Project Team Member 1 – Direct support to Project Manager and workshops
Project Team Member 2 – Development of materials and deliverables
Project Team Member 3 – Administrative support
Executive Review Member – Member from Executive Management to conduct ongoing (weekly status) reviews.
Management – Final PMO Action Plan Review and Signoff.
Page 6GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Current PMO Research
Introduction
Current Research for PMO Project offices will be established in more than 60 percent of IS organizations by 2003 and will often plan and control
project resources beyond IS (0.7 probability).
IT projects undertaken using a proven project management methodology carry less risk and have a greater chance of success than unstructured projects.
A consistently used methodology improves productivity by at least 30 percent (0.8 probability)”.
An organization (of any size) needs a project management methodology when it desires consistent, predictable results and a process that is open to improvement. In the absence of a stable process for IT project delivery, there is no possibility that project management will be consistently improved, because improvements are random and non-repeatable.
Source: Gartner
x
.Page 7
GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Project Plan and Schedule
Page 8GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Project Objectives
Project Plan and Schedule
The Project Team and Management have identified the following objectives for the PMO and future company projects: Objective #1: Enhance ABC abilities to and capabilities in managing IT projects and services in order to ensure
project success (resources, time, cost).
Objective #2: Increase the business value derived from IT projects and services through utilizing project synergies and resources.
Objective #3: Provide a standard methodology and approach to implementing, managing and executing projects.
Objective #4: Establish a collaborative project management environment.
Objective #5: Ability to effectively manage ABC’s IT projects portfolio.
Page 9GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Project Plan and Schedule
The Project Team will be staffed with the following positions: Project Manger
Project Team Member 1 – Direct support to Project Manager and workshops
Project Team Member 2 – Development of materials and deliverables
Project Team Member 3 – Administrative support
Executive Review Member – Member from Executive Management to conduct ongoing (weekly status) reviews.
Management – Final PMO Action Plan Review and Signoff.
Staffing
Page 10GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Project Schedule
Project Plan and Schedule
Project Schedule The project will be split into two overall phases:
Phase I. will be the establishment of the PMO foundation
Phase II. will be the actual implementation of the PMO.
Project Timeframes are as follows: Phase I. – Two Months
Phase II. – Four Years
The two phases will be treated, overall, as two separate projects. This report represents those components of Phase I.
The PMO Project Team will develop the following through consensus building workshops: PMO mission, vision, goals and objectives
PMO initiatives and objectives
PMO roles and responsibilities.
PMO Organizational Structure and Functions
PMO Framework and Processes
PMO Action Plan
Define short term strategies and quick wins to optimize project management capabilities given existing resource limitations
Page 11GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Project Workshops
Project Plan and Schedule
Workshop 1 - Review Background Information During the first workshop, workshop participants will review background information and relevant trends, methodologies and practices.
Workshop 2 – Assess Current Environment Ensure that internal and external factors are considered
Current resources (e.g., staff skills, funding, project tools), organizational readiness (e.g., culture, organizational support), governance, and project management maturity.
Identify strengths and weaknesses relative to project management, as well as perceived opportunities and threats in the establishment of a PMO (SWOT Analysis).
Workshop 3 – Vision and Mission Statements, Goals and Objectives Based on input solicited from the interviews, research, trends and best practices
Develop draft Vision and Mission Statements along with associated Goals and Objectives.
Page 12GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Project Workshops
Project Plan and Schedule
Workshop 4 – Organizational and Staffing Structure Development of proposed organizational structure for the PMO
Develop recommendations for staffing roles and responsibilities and organization structure
Workshop 5 – Identify PMO Framework and Processes Review best practice PMO framework material and implied PMO processes
Review project lifecycles and processes
Focus on consensus-based adoption of project management lifecycle
Page 13GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Project Plan and Schedule
ID Task Name Duration Start
1 Phase I 48 days Mon 8/4/03
2 Project Initiation 2 days Mon 8/4/03
3 Project Planning Rev iew Meeting 1 day Mon 8/4/03
4 Project Kickof f Meeting 1 day Tue 8/5/03
5 Conduct Preliminary Research 7 day s Mon 8/4/03
6 Workshop I - Review Background Information 4 days Wed 8/13/03
7 Dev elop Workshop Materials 3 day s Wed 8/13/03
8 Conduct Workshop 1 day Mon 8/18/03
9 Document Workshop Results 1 day Mon 8/18/03
10 Workshop II - Assess Current Environment 4 days Tue 8/19/03
11 Dev elop Workshop Materials 3 day s Tue 8/19/03
12 Conduct Workshop 1 day Fri 8/22/03
13 Document Workshop Results 1 day Fri 8/22/03
14 Workshop III - Vision, Mission, Goals and Objectives 4 days Mon 8/25/03
15 Dev elop Workshop Materials 3 day s Mon 8/25/03
16 Conduct Workshop 1 day Thu 8/28/03
17 Document Workshop Results 1 day Thu 8/28/03
18 Workshop IV - Organizaton and Staffing Structure 6 days Fri 8/29/03
19 Dev elop Workshop Materials 4 day s Fri 8/29/03
20 Conduct Workshop 2 day s Thu 9/4/03
21 Document Workshop Results 1 day Fri 9/5/03
22 Workshop V - Identify PMO Framework and Processes 7 days Mon 9/8/03
23 Dev elop Workshop Materials 5 day s Mon 9/8/03
24 Conduct Workshop 2 day s Mon 9/15/03
25 Document Workshop Results 1 day Tue 9/16/03
26 Dev elop Draf t PMO Action Plan 10 day s Wed 9/17/03
27 Rev iew PMO Action Plan with Management 3 day s Wed 10/1/03
28 Finalize PMO Action Plan 2 day s Mon 10/6/03
29 Conduct Project Closeout Meeting 1 day Wed 10/8/03
7/27 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 10/5 10/12July 2003 August 2003 September 2003 October 2003
Project Schedule - Phase I.
Page 14GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Project Deliverables
Project Plan and Schedule
Project deliverables include the following: Develop of workshop materials
Conducting workshops
Documentation and dissemination of workshop results
PMO Action Plan Document high-level action items necessary to establish the PMO and implement its initiatives.
PMO Requirements (resources, timelines, functions, organization, responsibilities, etc.)
Implementation Strategies
Implementation Schedule
x
.Page 15
GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Return on Investment
Page 16GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Expected BenefitsReturn on Investment
The primary benefit to establishing the PMO is the improved control and management of projects including the reduction of: Delayed projects
Scope creep
Resource increase
Cost overruns
Project failure
Average total annual loss due to the above factors: Delayed Projects $55,000
Scope Creep $64,000
Resource Increase $26,000
Cost Overruns $78,000
Project Failures $125,000
Totals $348,000
Page 17GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Expected CostsReturn on Investment
Phase I CostsCosts associated with Phase I of the project are displayed in the table below:
Steps Associated Deliverables HoursResource
Cost*
Project Planning and KickoffMeeting
MS PowerPoint Presentation MS Project Schedule MS Word Project Status Reports
25 $2,500
Task 2. Conduct PreliminaryResearch
Research documents as required Documentation Checklist
30 $3,000
Task 3. Conduct PMOWorkshops
Findings Review Constraints and Opportunities PMO Mission and Vision, Goals
and Objectives PMO Organizational and Staffing
Structure Best Practice PMO Review
and Organizational WorkflowRequirements
116 $11,600
Task 4. Develop PMORequirements and Action Plan
Action Plan Management Presentation
48 $4,800
Total 219 $21,900
Page 18GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Expected Costs
Return on Investment
Phase II Costs
Cost associated with Phase II are displayed in the table below:
Steps Associated Deliverables Hours ResourceCost*
Implementation of PMO PhaseI Results
350 $35,000
Methodology Development 80 $8,000
Project Manager Training On-time costsAnnual Costs
NA $10,000$8,000
Re-organization tasks andbusiness processreorganization
125 $12,500
Ongoing Department SupportBudget
Annual Costs NA $125,000
Contingency of 10% $15,550
Total NA $214,050
Page 19GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Break Even AnalysisReturn on Investment
Total first year costs are $235,950, this represents a return on investment in 8.6 months after implementation.
x
.Page 20
GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Risk Management and Communication Plan
Page 21GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Risk Management and Communication Plan
Risk Management will be assessed on an ongoing basis throughout the project from the project planning phase through project closeout.
Project risk will be divided into the following areas and assessed: Strategic Risk – Alignment with overall business strategy, objectives being met, and management commitment
Financial Risk – Staying within project budget, cost and benefits being realized, payback period defined and on target.
Project Management Risk – Ongoing team experience and balance, on schedule, milestones being met, scope changes, and issues.
Change Management and Operational Risk – Ongoing acceptance of deliverables, stakeholder acceptance, impact of project failure and are staff issues being addressed.
Risk Management
Page 22GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Office10 July, 2003r
Risk Management and Communication Plan
Communication Plan will address the following: Organizational Structure
Organizational Chart
Contact Information
Roles and Responsibilities
Regularly Scheduled Meetings Meetings
Description
Participants
Frequency
Project Documentation Project Documents
Responsibility
Frequency
Distribution Group
Escalation Procedures
Communication Plan
GBA 573 - IT Project ManagementFinal Project - Establishment of a Project Management Management Office
10 July, 2003