g+20 corporate house construction & project management

109
A PROJECT REPORT G+20 Corporate house Construction & Project Management Submitted by: Maitrey Patel (110320106046) Aash Shah (110320106051) Neelay Khese (110320106113) Rehan Peerzada (110320106104) Jainil Patel (110320106036) Guided By PROF. Vaishakhi R. Shah Civil Engineering Department, LJIET, Ahmedabad A Thesis Submitted to GUJARAT TECHNOLOGICAL UNIVERSITY In Partial Fulfilment of the Requirements for the Degree of BACHELOR OF ENGINEERING IN CIVIL ENGINEERING

Upload: neelay-khese

Post on 11-Jan-2017

529 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: G+20 Corporate House Construction & Project Management

A PROJECT REPORT

G+20 Corporate house Construction & Project

Management

Submitted by:

Maitrey Patel (110320106046)

Aash Shah (110320106051)

Neelay Khese (110320106113)

Rehan Peerzada (110320106104)

Jainil Patel (110320106036)

Guided By

PROF. Vaishakhi R. Shah

Civil Engineering Department,

LJIET, Ahmedabad

A Thesis Submitted to

GUJARAT TECHNOLOGICAL UNIVERSITY

In Partial Fulfilment of the Requirements for the Degree of

BACHELOR OF ENGINEERING

IN

CIVIL ENGINEERING

Page 2: G+20 Corporate House Construction & Project Management

GUJARAT TECHNOLOGICAL UNIVERSITYCERTIFICATE FOR COMPLETION OF ALL ACTIVITIES AT ONLINE PROJECT PORTAL

B.E. SEMESTER VIII, ACADEMIC YEAR 2014-2015

Date of certificate generation : 21 May 2015 (12:40)

Plagiarism Search Report

Final Project Report

Patent Drafting Exercise (PDE)

Business Model Canvas (Report)

Business Model Canvas (Image)

Submitted Four Periodic Progress Reports (PPR)

Uploaded

Uploaded

Completed

Uploaded

Uploaded

Completed

This is to certify that, Jainil Bharatbhai Patel (Enrolment

Number-110320106036) working on project entitled with

Construction And Project Management Of G+20 Corporate

House from Civil Engineering department of L. J. Institute Of

Engineering And Technology, Ahmedabad had submitted

following details at online project portal.

Name of Student :

Signature of Student :

Jainil Bharatbhai Patel

*Signature of Guide :

Name of Guide : Ms. Vaishakhi Rajeshkumar

Shah

This is a computer generated copy and does not indicate that your data has been evaluated. This is the receipt

that GTU has received a copy of the data that you have uploaded and submitted as your project work.

Disclaimer :

*Guide has to sign the certificate, Only if all above activities has been Completed / Uploaded.

Page 3: G+20 Corporate House Construction & Project Management

GUJARAT TECHNOLOGICAL UNIVERSITYCERTIFICATE FOR COMPLETION OF ALL ACTIVITIES AT ONLINE PROJECT PORTAL

B.E. SEMESTER VIII, ACADEMIC YEAR 2014-2015

Date of certificate generation : 21 May 2015 (12:45)

Plagiarism Search Report

Final Project Report

Patent Drafting Exercise (PDE)

Business Model Canvas (Report)

Business Model Canvas (Image)

Submitted Four Periodic Progress Reports (PPR)

Uploaded

Uploaded

Completed

Uploaded

Uploaded

Completed

This is to certify that, Aash Hitendra Shah (Enrolment

Number-110320106051) working on project entitled with

Construction And Project Management Of G+20 Corporate

House from Civil Engineering department of L. J. Institute Of

Engineering And Technology, Ahmedabad had submitted

following details at online project portal.

Name of Student :

Signature of Student :

Aash Hitendra Shah

*Signature of Guide :

Name of Guide : Ms. Vaishakhi Rajeshkumar

Shah

This is a computer generated copy and does not indicate that your data has been evaluated. This is the receipt

that GTU has received a copy of the data that you have uploaded and submitted as your project work.

Disclaimer :

*Guide has to sign the certificate, Only if all above activities has been Completed / Uploaded.

Page 4: G+20 Corporate House Construction & Project Management

GUJARAT TECHNOLOGICAL UNIVERSITYCERTIFICATE FOR COMPLETION OF ALL ACTIVITIES AT ONLINE PROJECT PORTAL

B.E. SEMESTER VIII, ACADEMIC YEAR 2014-2015

Date of certificate generation : 21 May 2015 (12:42)

Plagiarism Search Report

Final Project Report

Patent Drafting Exercise (PDE)

Business Model Canvas (Report)

Business Model Canvas (Image)

Submitted Four Periodic Progress Reports (PPR)

Uploaded

Uploaded

Completed

Uploaded

Uploaded

Completed

This is to certify that, Maitrey Yogeshkumar Patel (Enrolment

Number-110320106046) working on project entitled with

Construction And Project Management Of G+20 Corporate

House from Civil Engineering department of L. J. Institute Of

Engineering And Technology, Ahmedabad had submitted

following details at online project portal.

Name of Student :

Signature of Student :

Maitrey Yogeshkumar Patel

*Signature of Guide :

Name of Guide : Ms. Vaishakhi Rajeshkumar

Shah

This is a computer generated copy and does not indicate that your data has been evaluated. This is the receipt

that GTU has received a copy of the data that you have uploaded and submitted as your project work.

Disclaimer :

*Guide has to sign the certificate, Only if all above activities has been Completed / Uploaded.

Page 5: G+20 Corporate House Construction & Project Management

GUJARAT TECHNOLOGICAL UNIVERSITYCERTIFICATE FOR COMPLETION OF ALL ACTIVITIES AT ONLINE PROJECT PORTAL

B.E. SEMESTER VIII, ACADEMIC YEAR 2014-2015

Date of certificate generation : 21 May 2015 (13:07)

Plagiarism Search Report

Final Project Report

Patent Drafting Exercise (PDE)

Business Model Canvas (Report)

Business Model Canvas (Image)

Submitted Four Periodic Progress Reports (PPR)

Uploaded

Uploaded

Completed

Uploaded

Uploaded

Completed

This is to certify that, Neelay Rakesh Khese (Enrolment

Number-110320106113) working on project entitled with

Construction And Project Management Of G+20 Corporate

House from Civil Engineering department of L. J. Institute Of

Engineering And Technology, Ahmedabad had submitted

following details at online project portal.

Name of Student :

Signature of Student :

Neelay Rakesh Khese

*Signature of Guide :

Name of Guide : Ms. Vaishakhi Rajeshkumar

Shah

This is a computer generated copy and does not indicate that your data has been evaluated. This is the receipt

that GTU has received a copy of the data that you have uploaded and submitted as your project work.

Disclaimer :

*Guide has to sign the certificate, Only if all above activities has been Completed / Uploaded.

Page 6: G+20 Corporate House Construction & Project Management

GUJARAT TECHNOLOGICAL UNIVERSITYCERTIFICATE FOR COMPLETION OF ALL ACTIVITIES AT ONLINE PROJECT PORTAL

B.E. SEMESTER VIII, ACADEMIC YEAR 2014-2015

Date of certificate generation : 21 May 2015 (12:19)

Plagiarism Search Report

Final Project Report

Patent Drafting Exercise (PDE)

Business Model Canvas (Report)

Business Model Canvas (Image)

Submitted Four Periodic Progress Reports (PPR)

Uploaded

Uploaded

Completed

Uploaded

Uploaded

Completed

This is to certify that, Rehan Javed Peerzada (Enrolment

Number-110320106104) working on project entitled with

Construction And Project Management Of G+20 Corporate

House from Civil Engineering department of L. J. Institute Of

Engineering And Technology, Ahmedabad had submitted

following details at online project portal.

Name of Student :

Signature of Student :

Rehan Javed Peerzada

*Signature of Guide :

Name of Guide : Ms. Vaishakhi Rajeshkumar

Shah

This is a computer generated copy and does not indicate that your data has been evaluated. This is the receipt

that GTU has received a copy of the data that you have uploaded and submitted as your project work.

Disclaimer :

*Guide has to sign the certificate, Only if all above activities has been Completed / Uploaded.

Page 7: G+20 Corporate House Construction & Project Management

CERTIFICATE

This is to certify that project work embodied in this thesis entitled

“G+20 Corporate house Construction & Project Management” has been carried out

by Maitrey Patel (110320106046), Aash Shah (110320106051), Neelay Khese

(110320106113), Rehan Peerzada (110320106104), Jainil Patel (110320106036)

at L J Institute of Engineering & Technology Ahmedabad for partial fulfillment of

Bachelor of Engineering Degree in Civil Engineering to be awarded by Gujarat

Technological University for the term Jan-2015 to May-2015. This project work

has been carried out under my supervision and is to the satisfaction of department.

Date: 19 May, 2015

Place: Ahmedabad

Internal Guide:

Prof. Ms. Vaishakhi Shah

Civil Engineering Department,

LJIET, Ahmedabad

HOD:

Zuned Shaikh

Head of the Department,

Civil Engineering Department,

LJIET, Ahmedabad

External Sign:

Page 8: G+20 Corporate House Construction & Project Management

ACKNOWLEDGEMENT

I am very thankful to LARSEN & TOUBRO CONSTRUCTION ECC division for having given

me the opportunity to undertake my summer training at their ADANI CORPORATE HOUSE

PROJECT. I would also like to thank Debabrata Charkraborty Sir. I would like to convey thanks

to Mr. Vishal Pandya Sir, Asst. construction manager L & T construction who debriefed us about

the planning. I would like to convey my heartfelt thanks to all the staff of the project site office for

their cheerful cooperation and for all their help and guidance throughout my stay at the project

site. Lastly, I would like to thank my university LJIET for providing me such a great opportunity.

Page 9: G+20 Corporate House Construction & Project Management

www. plagiarism -detect .comDate: 21.5.2015Words: 4508Plagiarised sources: 24Plagiarised: 3%

http://www.aquariusengineers.biz/products-stationary-boom-placer.htmlplagiarised from source: 1%

the cumbersome process of laying the1.This can ensure faster pours in less manpower2.provided with a sophisticated remote control3.Hence, the movements of the boom can be controlled4.Suitable safety devices are provided to ensure accident free5.

http://profit.ndtv.com/stock/larsen-&-toubro-ltd_lt/reportsplagiarised from source: 1%

firm F L Smidth & Co in connection with the1.of cement companies that later grouped into the Associated Cement2.Together, Holck-Larsen and Toubro founded the partnership firm of L&T in3.which was converted into a limited company on February4.

http://science.howstuffworks.com/transport/engines-equipment/tower-crane.htmplagiarised from source: 1%

They're pretty hard to miss -- they often rise hundreds1.feet into the air, and can reach out just as2.The construction crew uses the tower crane to lift steel3.concrete, large tools like acetylene torches and generators4.

http://womanoperator.org/capital_building.htmplagiarised from source: 1%

They're pretty hard to miss -- they often rise hundreds1.feet into the air, and can reach out just as2.The construction crew uses the tower crane to lift steel3.concrete, large tools like acetylene torches and generators4.

http://www.china-crane.net/plagiarised from source: 1%

They're pretty hard to miss -- they often rise hundreds1.feet into the air, and can reach out just as2.The construction crew uses the tower crane to lift steel3.concrete, large tools like acetylene torches and generators4.

http://www.bsl-machinery.com/how-tower-cranes-work/plagiarised from source: 1%

They're pretty hard to miss -- they often rise hundreds1.feet into the air, and can reach out just as2.The construction crew uses the tower crane to lift steel3.concrete, large tools like acetylene torches and generators4.

http://www.stichtingnextmove.nl/big-cranes.htm

Page 10: G+20 Corporate House Construction & Project Management

plagiarised from source: >1%

They're pretty hard to miss -- they often rise hundreds1.feet into the air, and can reach out just as2.

http://www.iloveindia.com/economy-of-india/top-50-companies/larsen-and-toubro.htmlplagiarised from source: >1%

firm F L Smidth & Co in connection with the1.of cement companies that later grouped into the Associated Cement2.

http://www.slideshare.net/paliwalumed/summer-internship-report-ltplagiarised from source: >1%

Together, Holck-Larsen and Toubro founded the partnership firm of L&T in1.which was converted into a limited company on February2.

http://www.slideshare.net/AmmanAthif/tower-crane-42180127plagiarised from source: >1%

feet into the air, and can reach out just as1.concrete, large tools like acetylene torches and generators2.

http://www.deckrane.com/info/towercrn.pdfplagiarised from source: >1%

feet into the air, and can reach out just as1.concrete, large tools like acetylene torches and generators2.

http://shodhganga.inflibnet.ac.in:8080/jspui/bitstream/10603/4683/10/10_chapter 4.pdfplagiarised from source: >1%

which was converted into a limited company on February1.

http://www.slideshare.net/bhasker4u/larsenandtoubroplagiarised from source: >1%

L&T shall foster a culture of caring trust and continuous learning1.

http://www.automationengineeringinfo.com/marine/cranes/plagiarised from source: >1%

They're pretty hard to miss -- they often rise hundreds1.

http://www.slideshare.net/subhra2jyoti/organizational-structure-amp-leadership-style-in-ms-larsen-amp-toubro-mumbaiplagiarised from source: >1%

L&T shall foster a culture of caring trust and continuous learning1.

http://www.slideshare.net/victorxls/l-t-training-projectplagiarised from source: >1%

L&T shall foster a culture of caring trust and continuous learning1.

http://scholar.valpo.edu/cgi/viewcontent.cgi?article=1022&context=jvblplagiarised from source: >1%

L&T shall foster a culture of caring trust and continuous learning1.

http://civilengineer.webinfolist.com/equip/equipment-links.htmplagiarised from source: >1%

The construction crew uses the tower crane to lift steel1.

Page 11: G+20 Corporate House Construction & Project Management

http://www.machineryzone.com/used/1/cranes.htmlplagiarised from source: >1%

The construction crew uses the tower crane to lift steel1.

https://howardinturners.wordpress.com/2013/11/21/468/plagiarised from source: >1%

The construction crew uses the tower crane to lift steel1.

https://www.facebook.com/pages/All-Access-Rigging/147428015387759plagiarised from source: >1%

concrete, large tools like acetylene torches and generators1.

https://www.facebook.com/docscraneplagiarised from source: >1%

concrete, large tools like acetylene torches and generators1.

http://aquarius-engineers-pvt-ltd.b2b.sulekha.com/productsplagiarised from source: >1%

the cumbersome process of laying the1.

http://utpedia.utp.edu.my/926/plagiarised from source: >1%

feet into the air, and can reach out just as1.

Page 12: G+20 Corporate House Construction & Project Management

INDEX

1. INTRODUCTION………..............................................................................1

1.1 KEYWORD……………………………………………………………..1

1.2 WHAT IS PROJECT..............................................................................1

1.3 ABOUT THE ORGANISATION…………………………………….....6

2. LITARETURE REVIEW…………………………………………………...27

2.1 PLANNING……………………………………………………………..27

2.2 COST CONTROL……………………………………………………….27

2.3 SCHEDULE CONTROL………………………………………………..27

2.4 QUALITY CONTROL………………………………………………….28

3. METHODOLOGY………………………………………………………......29

4. STRUCTURE DESIGN……………………………………………………..30

5. CONSTRUCTION…………………………………………………………..33

5.1 SITE DETAIL…………………………………………………………...33

5.2 INOVATION IN PROJECT……………………………………………..37

5.3 EXAVATION……………………………………………………………38

5.4 FORMWORK……………………………………………………………42

5.5 RAINFORCEMENT……………………………………………………..46

Page 13: G+20 Corporate House Construction & Project Management

5.6 BAR BENDING SCHEDULING……………………………………….47

5.7 QUANTITY OF RAINFORCEMENT………………………………….49

6. PROBLEM & SOLUTION …………………………………………………52

7. MANAGEMENT………………………………………………………........54

6.1 MANAGEMENT OF EQUIPMENT……………………………………55

6.2 MANAGEMENT OF LABOUR………………………………………...60

6.3 MANAGEMENT OF MATERIAL……………………………………...61

8. CONCLUSION………………………………………………………………65

9. REFERENCE………………………………………………………………...66

APPENDIX 1- PERIODIC PROGTESS REPORT

APPENDIX 2- PATENT DRAFTING EXERCISE

APPENDIX 3- BUSINESS MODEL CANVAS

Page 14: G+20 Corporate House Construction & Project Management

CHAPTER – 1

INTRODUCTION

Page 15: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 1

Introduction

Over the years and more importantly in the recent past projects have been used as a delivery

mechanism to do business and accomplish objectives. No wonder it has become one of the fastest

growing professions in the world. Although the understanding of what constitutes a project and

what doesn’t continues to be a topic of debate. This paper attempts to provide literature search on

what is a project, its classification, characteristics, its life cycle, phases, tools etc.

1.1 Keywords: Projects, Project Management

Every one of us is a manager of projects! From a house wife to a production employee to financial

analyst, from banker to physician, from engineer to administrator, from teacher to student, we all

work on various tasks with deadlines. Regardless of our occupation, discipline, or location in an

organization, we all work on tasks that are unique and involve people who do not usually work

together. The project may have a simple objective that does not require many people or a great

deal of money, or it may be quite complex, calling for diverse skills and many resources. But the

bottom line is that every one of us manages projects!

1.2 What is a Project?

While there are several definitions of projects in the literature, one of the best has been offered by

Tuman (1983), who states:

“A project is an organization of people dedicated to a specific purpose or objective. Projects

generally involve large, expensive, unique, or high risk undertakings which have to be completed

by a certain date, for a certain amount of money, with some expected level of performance. At a

minimum, all projects need to have well defined objectives and sufficient resources to carry out

all the required tasks.”

In lines of the definition provided by Pinto & Slevin (1988), and accepted for the purpose of this

research, a project can be defined as possessing the following characteristics:

(1) A defined beginning and end (specified time to completion)

(2) A specific, preordained goal or set of goals (performance expectations)

(3) A series of complex or interrelated activities

(4) A limited budget

Diallo & Thuillier (2003) reviewed the project management literature outlined a set of evaluation

dimensions which appear regularly although not with the same occurrence:

(1) Respect to the three traditional constraints

(2) Satisfaction of the client

(3) Satisfaction of the objectives as outlined in the logical framework

Page 16: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 2

(4) Project impacts

(5) Institutional or organizational capacity built in the organization by the project

(6) Financial returns (in the case of productive projects) or the economic or social benefits (in the

case of public sector projects), and

(7) Project innovative features (outputs, management or design)

In the words of Turner (1999), “a project is an endeavour in which human, financial and material

resources are organized in a novel way to undertake a unique scope of work, of given specification,

within constraints of cost and time, so as to achieve beneficial change defined by quantitative and

qualitative objectives.”

As defined in A Guide to the Project Management Body of Knowledge (PMI, PMBOK® Guide,

2000), a project is a temporary endeavor undertaken to create a unique product or service.

Temporary means that every project has a definite beginning and a definite end. Unique means

that the product or service is different in some distinguishing way from all other projects or

services.

1. Characteristics of a Project

Typically, most projects share most if not all of the five characteristics listed below.

(1) A start and a finish (2) A time frame for completion (3) An involvement of several people on

an ad-hoc basis (4) A limited set of resources (5) A sequencing of activities and phases

2. Classification of Projects within Categories and Sub-Categories

(1) Project size

(2) Project complexity

(3) External or internal customer

(4) Degree of customer involvement in the project

(5) Levels of risk in projects

(6) Major and minor projects within a category

According to Gareis and Huemann (2000) the Project-oriented Company (POC) is an organisation

which defines “Management by Projects” as an organisational strategy, applies temporary

organisations for the performance of complex processes, manages a project portfolio of different

project types, has specific permanent organisations to provide integrative functions, applies a

“New Management Paradigm”, has an explicit project management culture, and perceives itself as

being project-oriented. Thus POCs do have specific processes, such as assignments of projects

and programmes, project management, programme management, quality management of projects

Page 17: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 3

and programmes, project portfolio co-ordination, networking between projects, personnel

management in the POC and organisational design of the POC.

3. Project Life Cycle

As maintained by PRINCE2 (2002): “A sequence of phases through which a project must pass.

There are a variety of definitions that generally reflect different industry practices… The generally

accepted sequence is: pre-feasibility validation of concepts); feasibility (detailed investigation of

viability) design; contract (procurement); implementation; commissioning; handover and

operation.

Project life cycle generally defines:

(1) The tasks to be accomplished in each phase or sub- phase

(2) The team responsible of each of the phases defined

As advocated Archibald & Voropaev (2003), there is a general agreement that the four broad,

generic project phases are (common alternative terms are shown in parentheses):

(1) Concept (initiation, identification, selection.)

(2) Definition (feasibility, development, demonstration, design prototype, quantification.)

(3) Execution (implementation, realization, production and deployment, design/construct/

commission, installation and test.)

(4) Closeout (termination, including post-completion evaluation.)

The number of phases in a project life cycle depends on a variety of factors like nature of industry,

type of output, size of project etc. Kerzner (2003) has developed a theoretical sequence of phases

that may be identified with most of the projects as is outlined below:

(1) Conceptual

(2) Planning

(3) Testing

(4) Implementation or Execution

(5) Closure

It is generally better in planning projects to analyze successive increments or distinct phases of

activity; in this way the return to each relatively small increment can be judged separately. Like

products follow a product life cycle, projects follow a project life cycle that has certain phases of

development.

Page 18: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 4

Dividing a big project in manageable chunks makes the complex task of managing projects easier,

these chunks in a sequential form can be termed as project phases which can further be divided

into sub-phases and a collection of these phases makes what is called as a project life cycle. Each

project phase is marked by completion of one or more deliverables. Although many project life

cycles have similar phase names with somewhat similar deliverables required, few are identical.

Most have four or five phases, but some have nine or more. Sub-projects within projects may also

have distinct project life cycles. Importantly, these phases are not always consecutive in nature but

are more simultaneous. Though researchers have suggested certain representative project life

cycles, for example, the waterfall model and Muench et. al’s (1994) spiral model for the software

development life-cycle, Morris’s (1994) construction project life cycle and Murphy’s (1989)

representative life cycle for a pharmaceutical project.

As per Kulkarni et al. (2004), the projects, especially the ones having a longer lifecycle, could be

categorised into many phases depending on the functions. For convenience and simplicity points

of view, the three commonly known phases is utilised, namely:

(1) Procurement phase: From inception to the financial closure and beginning of works (tendering;

dealing with governments, lenders, insurers, pressure groups, experts)

(2) Execution phase: Project execution (site installation till routine processes are reached,

significant completion)

(3) Operation and handover phase: From significant completion till the end of defect liability

period and handover

As said by Flaatten, McCubbrey, O’Riordan and Burgess (1992), ‘project execution’ (also known

as ‘project implementation’ phase) is the phase where project manager is responsible for allocating

work to the various team members, making sure that the team resources are used where most

needed, and ensuring that the workload is balanced. As intermediate deliverables are completed,

they are reviewed for verification (that they are correct and abide by project standards) and

validation (that they conform to previous work).

Wideman (1987) describes; each of these phases are unique in terms of:

(1) People allotted to them

(2) The budget available for carrying out these phases

(3) Specific time available to finish each of the phases.

8. Characteristics of a project life cycle

Risk and uncertainty is highest at the beginning stages of a project and reduces thereafter as the

project continues.

Page 19: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 5

The ability of the stakeholders to influence the final characteristics of the project’s product and the

final cost of the project is highest at the start and gets progressively lower as the project continues.

Also the cost of correcting an error increases as the project goes along.

Gantt charts

Developed by Harry Gantt in 1916, these charts give a timeline for each activity. They are used

for planning, scheduling and then recording progress against these schedules.

PERT/CPM (Critical Path Method)

Both methods show precedence relationships explicitly. Although the two methods were

developed independently during the fifties, they are surprisingly similar. Both methods, PERT and

CPM, use a graphic representation of a project that it is called "Project Network" or "CPM

diagram", and it is used to portray graphically the interrelationships of the elements of a project

and to show the order in which the activities must be performed.

Page 20: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 6

1.3 ABOUT THE ORGANIZATION: Larsen & Toubro Limited is the biggest legacy of two Danish Engineers, who built a world-class organization that is professionally managed and a leader in India's engineering and construction industry. It was the business of cement that brought the young Henning Holck-Larsen and S.K. Toubro into India. They arrived on Indian shores as representatives of the Danish engineering firm F L Smidth & Co in connection with the merger of cement companies that later grouped into the Associated Cement Companies. Together, Holck-Larsen and Toubro founded the partnership firm of L&T in 1938, which was converted into a limited company on February 7, 1946. Today, this has metamorphosed into one of India's biggest success stories. The company has grown from humble origins to a large conglomerate spanning engineering and construction. Larsen & Toubro Construction is India’s largest construction organization. Many of the country's prized landmarks - its exquisite buildings, tallest structures, largest industrial projects, longest flyover, and highest viaducts - have been built by it. Leading-edge capabilities cover every

discipline of construction: civil, mechanical, electrical and instrumentation. L&T Construction has the resources to execute projects of large magnitude and technological complexity in any part of the world. The business of L&T Construction is organized in six business sectors which will primarily be responsible for Technology Development, Business Development, International Tendering and work as Investment Centres. Head quarter in Chennai, India. In India, 7 Regional Offices and over 250 project sites. In overseas it has offices in Gulf and other overseas locations. L&T Construction’s cutting edge capabilities cover every discipline of construction – civil, mechanical, and electrical and instrumentation engineering and services extend to large industrial and infrastructure projects from concept to commissioning. L&T Construction has played a prominent role in India’s industrial and infrastructure development by executing several projects across length and breadth of the country and abroad. For ease of operations and better project management, in-depth technology and business development as well as to focus attention on domestic and international project execution, entire operation of L&T Construction is structured into four Independent Companies.

• Hydrocarbon IC

• Buildings & Factories IC

• Infrastructure IC

• Metallurgical & Material Handling IC

• Power Transmission & Distribution

• Heavy Engineering

Page 21: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 7

• Shipbuilding

• Power

• Electrical & Automation

• Machinery & Industrial Product

Page 22: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 8

BUILDING & FACTORIES: The Buildings & Factories Independent Company is equipped with the domain knowledge, requisite expertise and wide-ranging experience to undertake Engineering, Procurement and Construction (EPC) of all types of building and factory structures. • Commercial Buildings & Airports

• Residential Buildings & Factories

RESIDENTIAL BUILDINGS & FACTORIES: L&T undertakes turnkey construction of a wide range of residential buildings and factory structures. Projects are executed using the cutting edge technology, sophisticated construction equipment and project management tools for quality, safety and speed.

• Residential Building • Factories

FACTORIES: L&T offers design and turnkey construction of heavy and light factories, cement & plants including Defence Projects using the latest construction technology, with a focus on Quality, Safety and Speed. The spectrum covers: • Heavy & Light Factories (HLF) –Automobile & Ancillary Factories, Glass plants, Food processing Factories, Pharmaceutical plants, Warehouses & Logistics Parks, Workshop Complexes, Solar thin film manufacturing units, etc. • Cement & Plants (C&P) – Cement Plants, Sugar Plants, Distillery Plants, and Food Grain storage structures, Pulp & Paper Mills, Textile Mills etc. • Defence – Construction of Manufacturing Facilities and Warehouse Facilities for Defence.

Company Vision

L&T Shall be a professionally- managed Indian Multinational, committed to total Customer

satisfaction and enhancing shareholder value.

L&T-ites shall be an innovative, entrepreneurial and empowered team constantly creating value

and attending global benchmarks.

Page 23: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 9

L&T shall foster a culture of caring, trust and continuous learning while meeting expectation of

employees, stakeholders and society.

Some famous successful projects by L&T Construction:-

New gateway to Mumbai, Terminal 2

The Grand Hyatt International

Page 24: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 10

QUALITY POLICY

At L&T, Environment, Health & Safety (EHS) is given the highest priority. The EHS policy enunciated by the Corporate Management lays emphasis on Environment, Health and Safety through a structured approach and well defined practices. Systems and procedures have been established for implementing the requisites at all stages of construction and they are accredited to the International standards of ISO 9001:2008, ISO 14001:2004 and OHSAS 18001:2007.

Page 25: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 11

L&T Quality Policy:

Larsen & Toubro Limited – Buildings and factories Independent

Company (B&F IC) is committed to achieve and sustain business

excellence through value driven professional approach and total customer

satisfaction.

B&F IC shall strive to maintain leadership in its area of

business by:

Designing and building projects to specified standards within

stipulated time schedules.

Being continuous learning organization, benchmark with best

industry practices to deliver superior value to the customers.

Providing innovative and cost effective solutions in engineering

& construction with latest technology.

Effective implementation of Quality Management System as per

ISO 9001 towards total quality and continual improvement of all

processes

Developing Leaders, who set high expectations, achieve business

excellence through entrepreneurship and team work.

Ensuring greater employee morale and motivation by involving,

developing and empowering people through training and up-

gradation of their competencies.

Building long term relationships with customers and strategic

business partners based on shared objectives towards enhanced

value creation.

Quality Management System:

1. Quality Assurance

2. Quality Control

Page 26: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 12

Quality Assurance: All the activities concerned with attainment of

quality.

Contents of Quality Assurance:-

1. Site Inspections

2. Method Statements

Work Procedure

Inspection Test Plan

Checklist

Risk Assessment

3. Inspection Test Plan

4. Audits

Internal Audit

Opening Meet

NCR(Non Conformity Report)

Observation

Closing meet

External Audit

5. Trainings

Staff

Workers

6. CONQUAS( Construction Quality Assessment System)

7. Reports/MIS

Monthly Quality Report

Weekly Quality Report

8. Quality Plan

Project Quality Plan

Quality Assurance Plan

9. Inspection

For Material (Material Inspection Report)

For Work (Work Inspection Report)

Page 27: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 13

Quality Control:-

The operational Techniques and activities which together sustain the

product, service or quality to specific requirement.

1. Laboratory

Bulk Material testing as per inspection test plan

Cube compression test

Trial Mix as per data

Acceptability test

2. Batching Plant

Production of Concrete

Concrete Temperature

Slump Test

Sampling and Testing of concrete (As per IS 456)

Project Quality Plan

1. Work Methods

2. Inspection Test Plan

3. Frequency

4. Acceptance criteria.

Quality Objectives of L&T:

1. Customer Value

Product rating of structures finishes & MEP

Customer Feedback

Pre commissioning obligations

2. Process

Plan vs. Actual

Project Milestone

Financial performances

Cost prudence

Page 28: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 14

Safety records

3. Improvement

Safety performance

Cycle time

Cost of poor quality

Wastage reductions

Product quality rating

4. Leadership

Development of future leaders

5. Motivations

6. Partnerships.

Page 29: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 15

ENVIRONMENT, HEALTH & SAFETY (EHS) POLICY

Page 30: G+20 Corporate House Construction & Project Management
Page 31: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 17

VISION & MISSION

VISION L&T shall be professionally managed Indian multinational committed to total customer satisfaction and enhancing shareholder value. L&T shall be an innovative entrepreneurial and empowered team constantly creating value and attaining global benchmarks. L&T shall foster a culture of caring trust and continuous learning while meeting expectations of employees, stakeholders and society.

MISSION To achieve excellence in the field of Engineering, Procurement and Construction through world class practice and standards in quality, Safety and Project Management.

Page 32: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 18

ABOUT PROJECT

Adani Corporate House

Structural layout

Page 33: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 19

Side view

Page 34: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 20

Site Address: Adani Corporate House,

Adani Shantigram Township,

SG Highway, Ahmedabad

The corporate office forms a part of Ahmadabad’s well-known Shantigram Township spread over

600 acres, where state-of-the-art commercial complexes complement luxurious residences. The

idea was to build a tower that would be publicly recognized and distinctively read as a symbol of

the bold standards of Adani Group. The overall scheme is divided in two phases in which phase

I consists of High rise tower housing group companies and low rise structure balancing it with

amenities that cater to the staff. Subsequently, the key design has been evolved over defined axis

which orients the building to face main access road thus exploiting its frontage and giving it a

distinct identity. Meeting the client’s key requirement, the building has been planned with distinct

circulation paths and separate entrance for executives and general staff. The staff entrance and

public functions are situated at the low rise having state of the art auditorium and cafeteria above.

Grand central atrium is created at the ground level of both high and low rise volumes which

radiates transparency and openness inside the structure. The tower is designed keeping in mind

the clients desire to use maximum natural light and have large office spaces that can be grouped

easily. Small footprint on the plot has enabled large landscape spaces to be integrated with the

building enhancing the surroundings and adding a sense of openness to the overall scheme.

Page 35: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 21

Page 36: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 22

Project Brief

Client ADANI Enterprises Limited.

Architects ARCHGROUP International Architects Pvt. Ltd, Mumbai.

Structural Sterling Engineering Consultancy services Pvt. Ltd, Consultant Mumbai

MEP Consultants AECOM, UAE.

Location Shantigram, Ahmedabad.

Plot Area 11 Acres (Approx.)

Build Up Area 1.52 Million Sq ft

Project Duration 24 months

Total cost (Approx.) 210 crores

It will include a common substructure which has 3 floors as basement, 6 storey and 16 storey (with

terrace) superstructure. The maximum height of the building after completion of the project will

be 82 meters, including the helipad.

The area is divided into wings and zones according to the direction and structural designing. Wings

are named as East, West, South and North, while zoning is done as Zone I-VIII. The workforce is

of around 650 people. The site has an office, a worker colony, canteens, steel yard, formwork yard,

P&M office, and batching plant.

The execution of project is planned into 8 zones:

ZONE 1

ZONE 2 & 3

ZONE 4, 5 & 6

ZONE 7 & 8

Page 37: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 23

Page 38: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 24

Page 39: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 25

Page 40: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 26

Page 41: G+20 Corporate House Construction & Project Management

Team ID: 22722 INTRODUCTION

LJIET CIVIL 1

Page 42: G+20 Corporate House Construction & Project Management

CHAPTER – 2 LITARETURE REVIEW

Page 43: G+20 Corporate House Construction & Project Management

Team ID: 22722 Literature Review

LJIET CIVIL 27

Literature Review

2.1 Planning

Planning techniques for construction projects include a work breakdown structure; Program

Evaluation and Review Technique, or PERT, charts; and Gantt charts. A work breakdown

structure reduces complexity by breaking down the work to be done into individual tasks that are

the responsibility of a particular employee. PERT charts put the tasks into sequence to establish

what has to be completed before other tasks can start. Gantt charts are horizontal bar charts, with

each bar representing the duration of a project; these give an overview of how the project has to

proceed. Applying these techniques to construction projects allows you to reserve the required

resources and assign responsibilities to ensure the smooth functioning of project management.

2.2 Cost Control

Construction project management requires cost control. Your planning activities have helped you

identify the tasks that have to be completed and assign corresponding work. Cost control starts

with distributing the total cost to the tasks and establishing reporting procedures to track costs as

your company incurs them. You can achieve close cost control with signature rules for purchase

orders and payments. If you have to sign all purchase orders, you will know what costs the

project is generating. If your signature is required for payments, you have control over booking

costs to the project.

2.3 Schedule Control

Controlling the schedule for construction projects is critical because tasks are mutually

interdependent and delays can increase costs. Your planning has established the overall schedule

and specifies when particular tasks must be completed. A good schedule control technique is to

establish milestones that are easily observed and verified. Another technique is to use outside

events like permits to check on progress. If you have scheduled a milestone like the raising of the

building structure, you can go to the site on that day to verify whether the project team has met

the milestone. If you know that the project requires a building permit at a certain date, you can

check whether the permit has been issued.

Page 44: G+20 Corporate House Construction & Project Management

Team ID: 22722 Literature Review

LJIET CIVIL 28

2.4 Quality Control

An important function for construction projects is to control the quality of the materials and the

work because it affect the value of the structure you are building. Quality control has three parts.

You have to identify the level of quality you want, ensure that the purchase orders specify the

quality and examine the finished product to make sure you received what you ordered. When you

assign responsibility for a task in the planning stage, you also have to assign responsibility for

the quality and for the required documentation. For each item, the documentation has to include

the specified level of quality, the corresponding order and the resulting test or inspection report.

Page 45: G+20 Corporate House Construction & Project Management

CHAPTER – 3

METHODOLOGY

Page 46: G+20 Corporate House Construction & Project Management

Team ID: 22722 METHODOLOGY

LJIET CIVIL 29

Page 47: G+20 Corporate House Construction & Project Management

CHAPTER – 4 STRUCTURE DESIGN

Page 48: G+20 Corporate House Construction & Project Management

Team ID: 22722 STRUCTURE DESIGN

LJIET CIVIL 30

Page 49: G+20 Corporate House Construction & Project Management

Team ID: 22722 STRUCTURE DESIGN

LJIET CIVIL 31

Page 50: G+20 Corporate House Construction & Project Management

Team ID: 22722 STRUCTURE DESIGN

LJIET CIVIL 32

Page 51: G+20 Corporate House Construction & Project Management

CHAPTER – 5 CONSTRUCTION

Page 52: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 33

5.1 SITE DETAILS

The following components could be easily identified on the site:

Labor colony

This part of site provides shelter and various other facilities like canteen to the workers

working on the site. Approximate area 8500 sq m.

Cement batching and mixing plant

This part of the site facilitates storing of materials, testing and making of concrete on site.

Freshly prepared concrete is taken on site with the help of transit mixers having capacity

of 6 cu.m. each.

Plant type: Conveyor Type concrete batching plant

Aggregates used in making concrete:

Coarse Aggregate of 10 mm and 20 mm sizes

Sand sourced from Prantij and Mahudi (Zone II and III)

Plant Capacity: 30 cu m/hr

Strength of concrete used on site:

M-40 for RCC Structures

Page 53: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 34

M-15 for PCC

Site office

The office has following major parts: Planning Dept.

Accounts Dept.

Office of the Project Manager

Conference Room

Waiting Area Office for the Engineers

Page 54: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 35

Reinforcement yard:

This part of the site is responsible for unloading, storing and processing of steel

reinforcement used on the site. The reinforcements, being procured, confirm to the Indian

Standard 1786:2008 and are thermo- mechanically treated.

Formwork yard:

Formwork yard contains all the materials required to construct a tower, support and

barricades. It may have low duty towers, heavy duty towers, CT Props, Hydraulic jacks,

plywood, H-beams(Doka and Aluminum), Steel section.

Page 55: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 36

Page 56: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 37

5.2 INOVATION IN PROJECT:

Usage

Autoclaved Aerated Concrete (AAC) Blocks for Masonry Work.

Property Dimensions * mm

Length (L) 600

Height (H) 200

Width (D)* 75 100 125 150 200 225

Tolerance +/- 3

Application

Ideal for Masonry work for High Rise, Commercial, Institutional and Industrial Buildings.

Special Features

BRIXOLite AAC blocks are green building product manufactured using 70 % of recycled

material.

BRIXOLite is 65 % less in weight than conventional clay bricks. It saves approximately 15 %

to 20% of the steel requirement in reinforcement. Its excellent size/weight ratio allows faster

construction work.

Its uniform and bigger size of AAC blocks enable speedy construction.

High compressive strength makes BRIXOLite AAC blocks solid, therefore it is recommended

for load bearing walls, also causing minimum breakage.

Dimensional accuracy result, BRIXOLite is extremely easy to install, saves mortar and plaster

consumption.

It can be available in different sizes according to project’s requirement.

The porous structure of BRIXOLite AAC blocks provides a high acoustic insulation.

BRIXOLite AAC blocks have very low thermal conductivity and therefore a high thermal

energy efficiency is achieved. It reduce the inside temperature which results in cost savings

for heating and cooling.

One of the important property AAC blocks of extremely higher fire resistance which gives

product rating at least 4 hours and more.

Page 57: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 38

5.3 EXCAVATION AND FOOTINGS

My project at the site was in the area of excavation, reinforcement, shuttering and concreting of

foundations of various kinds, in Zone VIII.

EXCAVATION

Equipment used - Track hoe Loader, Dumper, Calibrated Auto-Level, Vertical Staff, Total

Station, Steel rods.

Process Flow -

Firstly, the grade slab level is found (50.055m)

Page 58: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 39

Auto-level is set up on the field, back sight reading is taken from a benchmark and Height

of instrument is established.

The difference between the height of the instrument and the bottom level of the footing is

found, and the relevant reading is seen on the vertical staff while excavation is being done.

After proper excavation, points for the concreting of the PCC level below the footing are

marked.

Level at Basement 3 : 50.055 (-11.50)

F1 type footing:

Total height = 350 mm + 475 mm + 725 mm + 150 mm

= 1700 mm

Bottom RL of the footing = 50.055 - 1.7

= 48.355m

Page 59: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 40

After 1 month (zone-8)

Page 60: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 41

F2 type footing:

Total height = 350 + 500 + 775 + 150 mm = 1775 mm

Bottom RL of footing = 50.055 -1.775 = 48.280m

Retaining wall:

Total height = 350 + 150 + 800 = 1300

mm

Bottom RL of footing = 50.055 -1.300 = 48.755m

Below picture shown is the key plan of the zone 1 & 8

foundation. (Level B3)

Page 61: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 42

5.4 FORMWORK

Various kinds of formworks are used at the site. One of the most important aspects is the load

carrying capacity of the tower systems and the height of the towers. Also, to support the slab and

column, formwork is used. It is of major influence to make sure that the column, slab, beam, wall

or footing stays in its place while concreting and does not run out of shape after initial setting time.

H Beam: Doka H-16, H-20, H24, Doka H-20 eco 2.45 m and Alu H-20

Plywood and H-beams are generally used to support a structural unit when concreting is to be

Page 62: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 43

done. Plywood and H-beams combined with CT Props and hydraulic jacks are used to support a

slab before and after construction.

Steel sections are used to support the plywood and to provide appropriate formwork for

construction of structural members.

A number of fundamental principles apply to all formwork.

Consideration must be given to:

Acceptable tolerances permitted;

Use of appropriate materials;

Standards of workmanship;

Construction for ease of erection and stripping.

Care and maintenance of the formwork, so that the maximum number of r

e‐uses can be achieved.

Formwork is a temporary construction; however care must be taken to prevent damage to perman

ent work. Three general principles govern formwork design and construction:

Quality accuracy of the concrete shape and the final finished surface quality.

Safetystrength of the formwork structure. Personal safety of people, both carpenters

and the public.

Economy

the structural frame is usually the most significant cost component, a dominant and critica

l factor in the time of construction.

Formwork System

Columns – L&T Column formwork

Wall – L&T Wall formwork

Floor Slabs (<4.5m height) – L&T Table formwork

Floor Slabs (>4.5m height) – L&T Heavy Duty tower formwork

Page 63: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 44

Basically in our site these are the types of the formwork are given below

1. L&T COLUMN/WALL FORMWORK SYSTEM

2. L&T TABLE FORMWORK SYSTEM

3. LOADING PLATFORM FOR TABLE FORM LIFTING

4. L&T HEAVY DUTY TOWER SYSTEM

5. L&T FLEX FORMWORK SYSTEM (FOR LOBBY SLABS& OTHER AREAS

Page 64: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 45

Scaffold Max load Per Max concentrated load

Class Platform per Bay Per Platform per Bay

(Should be over transom)

Light 225kg 100kg

Medium 450kg 150kg

Heavy 675kg 200kg

Height of Steel Aluminium

Scaffold

Up to 15m 4 3

Up to 30m 3 2

Up to 45m 2 1

Page 65: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 46

5.5 REINFORCEMENT

8 mm diameter steel reinforcement is used in making stirrups for columns. They are

also used in making bent up section like steel chairs, used for supporting two different

layers of reinforcement in a flat slab.(unit weight 0.39 kg/m)

10 mm diameter steel reinforcement is used in making stirrups for columns. They are

also used as extra bars in reinforcing flat slab.(unit weight 0.67 kg/m)

12 mm diameter steel reinforcement is used in making stirrups for some columns. They

are used in making various bent up sections like drop panel section, sections for

Page 66: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 47

retaining wall etc. (unit weight 0.89 kg/m)

16 mm diameter steel reinforcement is used in making sections for staircases. These

are also used as additional reinforcement for strengthening the column capital. These

are also used in vertical reinforcement (unit weight 1.58 kg/m)

20 mm diameter steel reinforcement is used in making sections for staircases, beams

etc. These are also used in vertical reinforcement i.e. for columns. (Unit weight 2.47

kg/m)

25 mm diameter steel reinforcement is used in making sections for staircases, beams

etc. These are also used in reinforcing columns. (Unit weight 3.85 kg/m)

32 mm diameter steel reinforcement is majorly used in reinforcing columns and

beams.(Unitweight 6.32 kg/m)

36 mm diameter steel reinforcement is majorly used in columns. (unit weight 8.00

kg/m)

Raft reinforcement consists of following things:-

Bottom X-direction all through

Bottom X – direction additional reinforcement

Bottom Y- direction all through

Bottom Y – direction additional reinforcement

Bottom X- direction all through (2nd & 3rd layer)

5.6 Bar Bending Schedule (BBS)

Most important thing in any reinforcement is the bar bending schedule of the foundation.

In bar bending schedule the vertical & horizontal reinforcement are given with the

calculations and in our case in BBS the step wise footing schedule is given like 1st step

horizontal & vertical then 2nd step likewise. It is the most important thing in any

reinforcement or concreting.

Bar bending schedule (or schedule of bars) is a list of reinforcement bars, a given RCC

work item, and is presented in a tabular form for easy visual reference. This table

Page 67: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 48

summarizes all the needed particulars of bars – diameter, shape of bending, length of each

bent and straight portions, angles of bending, total length of each bar, and number of each

type of bar. This information is a great help in preparing an estimate of quantities.

Page 68: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 49

Bar bending schedule is a list of reinforcement bars, a given work item, and is presented

in a tabular form for easy visual reference. This table summarizes the details about the bar which

consists of the following things:

Diameter

Shape of Bending

Length of each bent and straight portions

Angles of bending

Total length of each bar

Number of each type of bar

Cutting length of each bar

Weight of steel.

In general it is being used to understanding how to find out the quantities of bars in columns as

well as shear walls.

The steel yard houses the machinery to work with steel bars. These steel bars are used in the RCC

structures. The machines cut and bend the steel bars according to BBS (Bar Bending Schedule)

5.7 Quantity of reinforcement:

F1 type of footing:

Footing bottom reinforcement T16@125 c/c distance

(3700-2x75)/125 + 1 = 29 bars along L, similarly 29 bars along B => 58 nos. of bars.

Footing Top centre, Top side and Top both way

Top centre T8@250 c/c distance

(1800-2x75)/250 + 1 = 7 bars along 4 sides => 28 nos. of bars.

Top side T8@250 c/c distance

[{(3700-1800)/2}-75-2x8]/250 + 1 = 5 bars along 4 sides => 20 nos. of bars.

Top both way T8@250 c/c distance

(1800-2x75)/250 + 1 = 8 bars along B, similarly along L => 16 nos. of bars.

Page 69: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 50

Footing face bar Step-1 and Step-2 2-T10

Vertical reinforcements in column: 20-T25

Master stirrups in non-confining zone: T8@200 c/c distance - 5 nos.

Secondary stirrups in non-confining zone: T8@100 c/c distance - 20 nos.

Master stirrups in confining zone: T8@200 c/c distance - 9 nos.

Secondary stirrups in confining zone: T8@100 c/c distance - 36 nos.

Page 70: G+20 Corporate House Construction & Project Management

Team ID: 22722 CONSTRUCTION

LJIET CIVIL 51

Similarly for F2 type of footing:

Footing bottom both way: T16@125 c/c distance = 31 nos. along L and 31 nos. along B

Footing top centre step 1: T8@250 c/c distance = 6 nos. on each side => 24 nos.

Footing top side step 1: T8@250 c/c distance = 5 nos. on each side => 20 nos.

Footing top bar both way step 2: T8@250 c/c distance = 8 nos. along B and 8 nos. along L => 16

nos.

Vertical reinforcement for column: 4-T32 and 16-T25

For proper reinforcement work, first the reinforcements are marked with chalk according to c/c

distance and then tied up.

Page 71: G+20 Corporate House Construction & Project Management

CHAPTER – 6 PROBLEM & SOLUTION

Page 72: G+20 Corporate House Construction & Project Management

Team ID: 22722 PROBLEM & SOLUTION

LJIET CIVIL 52

Problems Observed

The problems we observed in our site were,

TIME DELAY:- The construction is behind schedule by 4 months. The causes of

these delays are as follow:

A) Change in design

B) Avaibility of materials

C) Weather conditions.

A. CHANGE IN DESIGN DURING ON GOING CONSTRUCTION:-

Sometimes, while the construction is ongoing. The structural designers come up with a better

design of some parts of the construction such as the quality of material, size of columns. The

change in design may also be necessary if some design was miscalculated by the structural

designer. The change in design is not an overnight modification. The change in design has to be

calculated properly and the specifications regarding the change have to be properly noted. Plus

any work which is related to the changed specification have to be planned again as well. This

change; while good and beneficial to the construction; comes at a price of time.

SOLUTIONS:

Accuracy in design detail and proper planning which includes forecasting any future

predicaments.

B. DUE TO AVAIBILITY OF MATERIALS:-

DESCRIPTION:

In our construction site certain innovative materials are used such as aerated light weight

concrete materials which is only available in surat. Avaibility of these blocks depends on

manufacturer and sometimes their avaibilities is affected due to various reasons and due to this

the construction delayed.

SOLUTION:

Now to avoid this issue proper storage on site should be protected and block should be

preordered more than the required quantity.

C. DUE TO WEATHER CONDITIONS:-

Page 73: G+20 Corporate House Construction & Project Management

Team ID: 22722 PROBLEM & SOLUTION

LJIET CIVIL 53

Weather conditions in Ahmedabad are getting unpredictable day by day such as recent heavy

hail-storm was experienced for the first time. The heat is summer is breaking all records as well.

This condition make the productivity of the workers futile which delays the construction.

SOLUTION: Now such extreme conditions are unavoidable, however management should be

prepared for such plights so that the damage and delay is minimum. These extreme conditions

should be tackled by providing proper damage control solutions.

2. FINANCES INVOLVED IN LIQUIDATED DAMAGES.

Such huge construction involves involves in getting loans from banks and various sources. But if

there is delay the construction then it directly affects the condition of loans. If there is delay in

the construction then there is the increase in the interest amount which affects the finances of the

project. And if there is major increase in interest amount then it may stop the construction also.

SOLUTION

To overcome this problem we must take care that the construction is completed in time. Else the

delay time should not be more which increases the liquidate damage.

Liquidated damages section in the contract should be revieved pre-construction, so that the

damages occurred and consequences are not drastic.

Page 74: G+20 Corporate House Construction & Project Management

CHAPTER – 7

MANAGEMENT

Page 75: G+20 Corporate House Construction & Project Management

Team ID: 22722 MANAGEMENT

LJIET CIVIL 54

Management

Good project management in construction must vigorously pursue the efficient utilization

of labour, material and equipment. Improvement of labour productivity should be a major

and continual concern of those who are responsible for cost control of constructed

facilities. Material handling, which includes procurement, inventory, shop fabrication and

field servicing, requires special attention for cost reduction. The use of new equipment and

innovative methods has made possible wholesale changes in construction technologies in

recent decades. Organizations which do not recognize the impact of various innovations

and have not adapted to changing environments have justifiably been forced out of the

mainstream of construction activities.

Observing the trends in construction technology presents a very mixed and ambiguous

picture. On the one hand, many of the techniques and materials used for construction are

essentially unchanged since the introduction of mechanization in the early part of the

twentieth century. For example, a history of the Panama Canal construction from 1904 to

1914 argues that:

The work could not have done any faster or more efficiently in our day, despite all

technological and mechanical advances in the time since, the reason being that no present

system could possibly carry the spoil away any faster or more efficiently than the system

employed. No motor trucks were used in the digging of the canal; everything ran on rails.

And because of the mud and rain, no other method would have worked half so well.

In contrast to this view of one large project, one may also point to the continual change

and improvements occurring in traditional materials and techniques. Bricklaying provides

a good example of such changes:

Bricklaying...is said not to have changed in thousands of years; perhaps in the literal

placing of brick on brick it has not. But masonry technology has changed a great deal.

Motorized wheelbarrows and mortar mixers, sophisticated scaffolding systems, and

forklift trucks now assist the bricklayer. New epoxy mortars give stronger adhesion

between bricks. Mortar additives and cold-weather protection eliminate winter shutdowns.

Add to this list of existing innovations the possibility of robotic bricklaying; automated

prototypes for masonry construction already exist. Technical change is certainly occurring

in construction, although it may occur at a slower rate than in other sectors of the economy.

Page 76: G+20 Corporate House Construction & Project Management

Team ID: 22722 MANAGEMENT

LJIET CIVIL 55

VARIOUS TYPE OF PROJECT MANAGEMENT:-

- Management of Equipment

- Management of Labour

- Management of Material

6.1 Management of Equipment:-

The selection of the appropriate type and size of construction equipment often

affects the required amount of time and effort and thus the job-site productivity of

a project. It is therefore important for site managers and construction planners to

be familiar with the characteristics of the major types of equipment most commonly

used in construction.

Type of Equipment And No. of Equipment –

1. TOWER CRANE :

Total Tower cranes used in construction: 2

Capacity at 65m Boom Length: 1.9T

Total Height of Mast: 94 m

Page 77: G+20 Corporate House Construction & Project Management

Team ID: 22722 MANAGEMENT

LJIET CIVIL 56

2. BACTHING PLANT

Total Number of Batching Plant used: 1

Model Type: CP30

Make: Sching Stetter

Capacity of Batching Plant: 30 cum/Hr

3. TRANSIT MIXER:-

Total number of transit mixer used: 2

Capacity: 6 Cum

Page 78: G+20 Corporate House Construction & Project Management

Team ID: 22722 MANAGEMENT

LJIET CIVIL 57

4. HEAVY CRAWLER CRANE:-

ONE used for Structural Steel erection.

Capacity: 250 MT

5. GANTRY CRANE:-

Total number of gantry crane used: 1

Capacity: 20 T

Page 79: G+20 Corporate House Construction & Project Management

Team ID: 22722 MANAGEMENT

LJIET CIVIL 58

6. CRAWLER CRANE:-

Total units used: 2 for Structural steel fabrication and erection.

Capacity: 80T

7. WEIGH BRIDGE:-

Total units used: 1

Capacity: 60T

Page 80: G+20 Corporate House Construction & Project Management

Team ID: 22722 MANAGEMENT

LJIET CIVIL 59

8. PICK & CARRY CRANE:-

Total units used : 1

Capacity: 15T

9. BACK HOE LOADER:-

Total units used: 2

Capacity: 0.7 Cum

6.2 Management of Labour:-

Labour Characteristics

Performance analysis is a common tool for assessing worker quality and contribution. Factors

that might be evaluated include:

Quality of Work - calibre of work produced or accomplished.

Quantity of Work - volume of acceptable work

Page 81: G+20 Corporate House Construction & Project Management

Team ID: 22722 MANAGEMENT

LJIET CIVIL 60

Job Knowledge - demonstrated knowledge of requirements, methods, techniques and

skills involved in doing the job and in applying these to increase productivity.

Related Work Knowledge - knowledge of effects of work upon other areas and

knowledge of related areas which have influence on assigned work.

Judgment - soundness of conclusions, decisions and actions.

Initiative - ability to take effective action without being told.

Resource Utilization - ability to delineate project needs and locate, plan and effectively

use all resources available.

Dependability - reliability in assuming and carrying out commitments and obligations.

Analytical Ability - effectiveness in thinking through a problem and reaching sound

conclusions.

Communicative Ability - effectiveness in using oral and written communications and

in keeping subordinates, associates, superiors and others adequately informed.

Interpersonal Skills - effectiveness in relating in an appropriate and productive manner

to others.

Ability to Work under Pressure - ability to meet tight deadlines and adapt to changes.

Security Sensitivity - ability to handle confidential information appropriately and to

exercise care in safeguarding sensitive information.

Safety Consciousness - has knowledge of good safety practices and demonstrates

awareness of own personal safety and the safety of others.

Profit and Cost Sensitivity - ability to seek out, generate and implement profit-making

ideas.

Planning Effectiveness - ability to anticipate needs, forecast conditions, set goals and

standards, plan and schedule work and measure results.

Leadership - ability to develop in others the willingness and desire to work towards

common objectives.

Delegating - effectiveness in delegating work appropriately.

Development People - ability to select, train and appraise personnel, set standards of

performance, and provide motivation to grow in their capacity. Diversity (Equal

Employment Opportunity) - ability to be sensitive to the needs of minorities, females

and other protected groups and to demonstrate affirmative action in responding to these

needs.

These different factors could each be assessed on a three point scale: (1) recognized

strength, (2) meets expectations, (3) area needing improvement. Examples of work

performance in these areas might also be provided.

Page 82: G+20 Corporate House Construction & Project Management

Team ID: 22722 MANAGEMENT

LJIET CIVIL 61

Type of Labours & Man Power Nos.

TYPE OF LABOUR NO. OF LABOUR REQUIED

CARPENTER/HELPER 300

FITTER/HELPER 250

MASON/HELPER 100

MALE COOLIE(USK) 100

WELDER/HELPER 40

RIGGER/FITTER/HELPER 70

OTHER 100

6.3 Management of Material:-

Materials management is an important element in project planning and control. Materials

represent a major expense in construction, so minimizing procurement or purchase costs

presents important opportunities for reducing costs. Poor materials management can also

result in large and avoidable costs during construction. First, if materials are purchased

early, capital may be tied up and interest charges incurred on the excess inventory of

materials. Even worse, materials may deteriorate during storage or be stolen unless special

care is taken. For example, electrical equipment often must be stored in waterproof

locations. Second, delays and extra expenses may be incurred if materials required for

particular activities are not available. Accordingly, insuring a timely flow of material is an

important concern of project managers.

Materials management is not just a concern during the monitoring stage in which

construction is taking place. Decisions about material procurement may also be required

during the initial planning and scheduling stages. For example, activities can be inserted

in the project schedule to represent purchasing of major items such as elevators for

buildings. The availability of materials may greatly influence the schedule in projects with

a fast track or very tight time schedule: sufficient time for obtaining the necessary

materials must be allowed. In some case, more expensive suppliers or shippers may be

employed to save time.

Materials management is also a problem at the organization level if central purchasing and

inventory control is used for standard items. In this case, the various projects undertaken

by the organization would present requests to the central purchasing group. In turn, this

group would maintain inventories of standard items to reduce the delay in providing

material or to obtain lower costs due to bulk purchasing. This organizational materials

Page 83: G+20 Corporate House Construction & Project Management

Team ID: 22722 MANAGEMENT

LJIET CIVIL 62

management problem is analogous to inventory control in any organization facing

continuing demand for particular items.

Materials ordering problems lend themselves particularly well to computer based systems

to insure the consistency and completeness of the purchasing process. In the manufacturing

realm, the use of automated materials requirements planning systems is common. In these

systems, the master production schedule, inventory records and product component lists

are merged to determine what items must be ordered, when they should be ordered, and

how much of each item should be ordered in each time period. The heart of these

calculations is simple arithmetic: the projected demand for each material item in each

period is subtracted from the available inventory. When the inventory becomes too low, a

new order is recommended. For items that are non-standard or not kept in inventory, the

calculation is even simpler since no inventory must be considered. With a materials

requirement system, much of the detailed record keeping is automated and project

managers are alerted to purchasing requirements.

Material Procurement and Delivery:-

The main sources of information for feedback and control of material procurement are

requisitions, bids and quotations, purchase orders and subcontracts, shipping and receiving

documents, and invoices. For projects involving the large scale use of critical resources,

the owner may initiate the procurement procedure even before the selection of a constructor

in order to avoid shortages and delays. Under ordinary circumstances, the constructor will

handle the procurement to shop for materials with the best price/performance

characteristics specified by the designer. Some overlapping and rehandling in the

procurement process is unavoidable, but it should be minimized to insure timely delivery

of the materials in good condition.

The materials for delivery to and from a construction site may be broadly classified as: (1)

bulk materials, (2) standard off-the-shelf materials, and (3) fabricated members or units.

The process of delivery, including transportation, field storage and installation will be

different for these classes of materials. The equipment needed to handle and haul these

classes of materials will also be different.

Bulk materials refer to materials in their natural or semi-processed state, such as earthwork

to be excavated, wet concrete mix, etc. which are usually encountered in large quantities

in construction. Some bulk materials such as earthwork or gravels may be measured in

bank (solid in situ) volume. Obviously, the quantities of materials for delivery may be

substantially different when expressed in different measures of volume, depending on the

characteristics of such materials.

Standard piping and valves are typical examples of standard off-the-shelf materials which

are used extensively in the chemical processing industry. Since standard off-the-shelf

materials can easily be stockpiled, the delivery process is relatively simple.

Page 84: G+20 Corporate House Construction & Project Management

Team ID: 22722 MANAGEMENT

LJIET CIVIL 63

Fabricated members such as steel beams and columns for buildings are pre-processed in a

shop to simplify the field erection procedures. Welded or bolted connections are attached

partially to the members which are cut to precise dimensions for adequate fit. Similarly,

steel tanks and pressure vessels are often partly or fully fabricated before shipping to the

field. In general, if the work can be done in the shop where working conditions can better

be controlled, it is advisable to do so, provided that the fabricated members or units can be

shipped to the construction site in a satisfactory manner at a reasonable cost.

As a further step to simplify field assembly, an entire wall panel including plumbing and

wiring or even an entire room may be prefabricated and shipped to the site. While the field

labour is greatly reduced in such cases, "materials" for delivery are in fact manufactured

products with value added by another type of labour. With modern means of transporting

construction materials and fabricated units, the percentages of costs on direct labour and

materials for a project may change if more prefabricated units are introduced in the

construction process.

In the construction industry, materials used by a specific craft are generally handled by

craftsmen, not by general labour. Thus, electricians handle electrical materials, pipefitters

handle pipe materials, etc. This multiple handling diverts scarce skilled craftsmen and

contractor supervision into activities which do not directly contribute to construction. Since

contractors are not normally in the freight business, they do not perform the tasks of freight

delivery efficiently. All these factors tend to exacerbate the problems of freight delivery

for very large projects.

7 QUANTITY OF VARIOUS MATERIAL:-

a. Ordinary Portland Cement 53 Grade

Quantity used: 30000 MT

b. Aggregates 10 mm down

Quantity used: – 44000 MT

c. Aggregates 20 mm down

Quantity Used: 52000 MT

d. Sand Medium Coarse Zone 2

Quantity used: 60000 MT

e. Admixture – 475 MT

Vardhman Make, Dosage 4.8 Kg/ Cum

f. Total Concrete Quantity to be Produced using above materials – 75000 Cum

Page 85: G+20 Corporate House Construction & Project Management

Team ID: 22722 MANAGEMENT

LJIET CIVIL 64

g. Reinforcement Steel (8 mm to 36 mm dia.) – 9100 MT

h. Structural Steel E350 Grade High Tensile – 1900 MT

i. High Tensile Strand for Post Tensioning Works – 110 MT

j. Aerated Auto Claved Light Weight Concrete Blocks – 7000 Cum

Page 86: G+20 Corporate House Construction & Project Management

CHAPTER – 9

REFERENCES

Page 87: G+20 Corporate House Construction & Project Management

Team ID: 22722 REFERENCES

LJIET CIVIL 66

1. McCullough, David, The Path Between the Seas, Simon and Schuster, 1977, pg. 531.

2. Rosefielde, Steven and Daniel Quinn Mills, "Is Construction Technologically Stagnant?", in

Lange, Julian E. and Daniel Quinn Mills, The Construction Industry, Lexington Books, 1979, pg.

83.

3. This example was adapted with permission from an unpublished paper "Managing Mega

Projects" presented by G.R. Desnoyers at the Project Management Symposium sponsored by the

Exxon Research and Engineering Company, Florham Park, NJ, November 12, 1980.

4. See R.L. Tucker, "Perfection of the Buggy Whip," The Construction Advancement Address,

ASCE, Boston, MA, Oct. 29, 1986.

5. For more detailed discussion, see D.G. Mills: "Labor Relations and Collective Bargaining"

(Chapter 4) in The Construction Industry (by J.E. Lang and D.Q. Mills), Lexington Books, D.C.

Heath and Co., Lexington, MA, 1979.

6. This example was adapted from Stukhart, G. and Bell, L.C. "Costs and Benefits of Materials

Management Systems,", ASCE Journal of Construction Engineering and Management, Vol. 113,

No. 2, June 1987, pp. 222-234.

7. The information for this example was provided by Exxon Pipeline Company, Houston, Texas,

with permission from the Alyeska Pipeline Service Co., Anchorage, Alaska.

8. This example was adapted from A.E. Kerridge, "How to Develop a Project Schedule," in A.E.

Kerridge and C. H. Vervalin (eds.), Engineering and Construction Project Management, Gulf

Publishing Company, Houston, 1986.

9. For further details on equipment characteristics, see, for example, S.W.

Nunnally, Construction Methods and Management, Second Edition, Prentice-Hall, 1986

10. See Paulson, C., "Automation and Robotics for Construction," ASCE Journal of Construction

Engineering and Management, Vol. 111, No. CO-3, 1985, pp. 190-207.

11. This example is adapted from Fred Moavenzadeh, "Construction's High-Technology

Revolution," Technology Review, October, 1985, pg. 32.

12. This and the following examples in this section have been adapted from E. Baracco-Miller

and C.T. Hendrickson, Planning for Construction, Technical Report No. R-87-162, Department

of Civil Engineering, Carnegie Mellon University, Pittsburgh, PA 1987.

Page 88: G+20 Corporate House Construction & Project Management

Team ID: 22722 REFERENCES

LJIET CIVIL 67

13. This model used the INSIGHT simulation language and was described in B.C. Paulson, W.T.

Chan, and C.C. Koo, "Construction Operations Simulation by Microcomputer," ASCE Journal of

Construction Engineering and Management, Vol. 113, No. CO-2, June 1987, pp. 302-314.

14. In the literature of queueing theory, this formula represents an M/D/1 queue, meaning that

the arrival process is Markovian or random, the service time is fixed, only one server exists, and

the system is in "steady state," implying that the service time and average arrival rate are

constant. Altering these assumptions would require changes in the waiting time formula; for

example, if service times were also random, the waiting time formula would not have the 2

shown in the denominator of Eq. (4.27). For more details on queueing systems, see Newell,

G.F. Applications of Queueing Theory, Chapman and Hall, London, 1982.

Page 89: G+20 Corporate House Construction & Project Management

APPENDIX – 1

PERIODIC PROGRESS REPORT

Page 90: G+20 Corporate House Construction & Project Management

Periodic Progess Report : First PPR

Project:

Construction And Project Management Of G+20 Corporate House

Status : Submitted  (Freeze)

What Progress you have made in the Project ?

Foundation of G+20 corporate housing.

What challenge you have faced ?

various  problems  such  as  excavation  problem,  Piling  problem,  PCC  mixture  problems,problem in design of footing.

What support you need ?

To overcome  this  problems,  proper marking  for  excavation  is  done,  proper  supervision  forexcavation of  the earth  is done with suitable equipment  for excvation. Proper PCC mixtureis made with its proper ratio. Footing was made as per the revised plan for the foundation.

Which literature you have referred ?

Refereed various tests such as Soil test, Details given by Surveyor.

Page 91: G+20 Corporate House Construction & Project Management

Periodic Progess Report : Second PPR

Project:

Construction And Project Management Of G+20 Corporate House

Status : Submitted  (Freeze)

What Progress you have made in the Project ?

Construction of Basement B­1 and B­2

What challenge you have faced ?

Problems faced such as Seepage, Land sliding.

What support you need ?

provided bituminous  sheets  for  preventing water  from entering  the  basement,  provided  theretaining support for restricting the land sliding.

Which literature you have referred ?

Design plan of basement and parking capacity.

Page 92: G+20 Corporate House Construction & Project Management

Periodic Progess Report : Third PPR

Project:

Construction And Project Management Of G+20 Corporate House

Status : Submitted  (Freeze)

What Progress you have made in the Project ?

Construction of ground floor and first floor.

What challenge you have faced ?

Problem  faced such as dry shrinkage  in concrete, permeability of concrete, Buckling,  loaddistribution problems.

What support you need ?

Proper curing of concrete, proper proportion of water cement ratio, Using of vibrator.

Which literature you have referred ?

Various  IS  codes  for  concrete  and  steel  and  designing,  using  of Mixtures  for  cement  andconcrete, proper site inspection.

Page 93: G+20 Corporate House Construction & Project Management

Periodic Progess Report : Forth PPR

Project:

Construction And Project Management Of G+20 Corporate House

Status : Submitted  (Freeze)

What Progress you have made in the Project ?

Construction management of entire project.

What challenge you have faced ?

various  problem  faced  as  Labours  problem  such  as  lack  of  labours,unskilled  labours.Equipment  problems  and  its  maintenance.  Improper  Time  management.  lack  of  rawmaterials.

What support you need ?

Supports  got  from  labour  contractor,  Quality  and  quantity  of  materials,  proper  use  ofequipment as per requirement. Quality measurements.

Which literature you have referred ?

Abstract  sheet,  Measurement  sheet,  record  book,  mustard  roll,  Updated  patterns,  CriticalPath Method (CPM), Program Evaluation and review Technique(PERT) methods.

Page 94: G+20 Corporate House Construction & Project Management

APPENDIX – 2

PATENT DRAFTING EXERCISE

Page 95: G+20 Corporate House Construction & Project Management

GIC Patent Drafting Exercise Team ID:

FORM 1

THE PATENTS ACT 1970

(39 OF 1970)

&

THE PATENTS RULES, 2003

APPLICATION FOR GRANT OF PATENT

(FOR OFFICE USE ONLY)

Application No:

Filing Date:

Amount of Fee paid:

CBR No:

GTU Innovation CouncilPatent Drafting Exercise (PDE)

22722

1. Applicant(s) :

This is just a mock Patent Drafting Exercise (PDE) for semester 8, BE students of GTU.

These documents are not to be submitted with any patent office.Note :

Page 1 of 6

Page 96: G+20 Corporate House Construction & Project Management

ID Name Nationality Address Mobile No. Email

Neelay

Rakesh Khese

Civil Engineering , L. J.

Institute Of Engineering

And Technology,

Ahmedabad , Gujarat

Technologycal University.

8460791412 nilaybond_133@

yahoo.co.in

Indian1

Maitrey

Yogeshkumar

Patel

Civil Engineering , L. J.

Institute Of Engineering

And Technology,

Ahmedabad , Gujarat

Technologycal University.

7600363968 maitreypatel007

@gmail.com

Indian2

Jainil

Bharatbhai

Patel

Civil Engineering , L. J.

Institute Of Engineering

And Technology,

Ahmedabad , Gujarat

Technologycal University.

8758283725 doodysc02@gma

il.com

Indian3

Rehan Javed

Peerzada

Civil Engineering , L. J.

Institute Of Engineering

And Technology,

Ahmedabad , Gujarat

Technologycal University.

9925586869 rehan.peerzada1

[email protected]

Indian4

Aash Hitendra

Shah

Civil Engineering , L. J.

Institute Of Engineering

And Technology,

Ahmedabad , Gujarat

Technologycal University.

7405473607 aashshah93@g

mail.com

Indian5

2. Inventor(s):

This is just a mock Patent Drafting Exercise (PDE) for semester 8, BE students of GTU.

These documents are not to be submitted with any patent office.Note :

Page 2 of 6

Page 97: G+20 Corporate House Construction & Project Management

Mobile No. Email AddressNationalityNameID

Neelay Rakesh

Khese

Civil Engineering , L. J.

Institute Of

Engineering And

Technology,

Ahmedabad , Gujarat

Technologycal

University.

8460791412 nilaybond_133

@yahoo.co.in

Indian1

Maitrey

Yogeshkumar

Patel

Civil Engineering , L. J.

Institute Of

Engineering And

Technology,

Ahmedabad , Gujarat

Technologycal

University.

7600363968 maitreypatel007

@gmail.com

Indian2

Jainil Bharatbhai

Patel

Civil Engineering , L. J.

Institute Of

Engineering And

Technology,

Ahmedabad , Gujarat

Technologycal

University.

8758283725 doodysc02@gm

ail.com

Indian3

Rehan Javed

Peerzada

Civil Engineering , L. J.

Institute Of

Engineering And

Technology,

Ahmedabad , Gujarat

Technologycal

University.

9925586869 rehan.peerzada

[email protected]

m

Indian4

Aash Hitendra

Shah

Civil Engineering , L. J.

Institute Of

Engineering And

Technology,

Ahmedabad , Gujarat

Technologycal

University.

7405473607 aashshah93@g

mail.com

Indian5

3. Title of Invention/Project:

Construction And Project Management Of G+20 Corporate House

4. Address for correspondence of applicant/authorized patent agent in india

Name:

Address:

Mobile:

Email ID:

Rehan Javed Peerzada

Civil Engineering , L. J. Institute Of Engineering And Technology, Ahmedabad , Gujarat

Technological University.

9925586869

[email protected]

This is just a mock Patent Drafting Exercise (PDE) for semester 8, BE students of GTU.

These documents are not to be submitted with any patent office.Note :

Page 3 of 6

Page 98: G+20 Corporate House Construction & Project Management

5. Priority particulars of the application(S) field in convention country

Name of the Applicant Title of the InventionFiling DateApplication No.Country

N/AN/AN/AN/AN/A

6. Particulars for filing patent co-operation treaty (pct) national phase Application

International application number International filing date as alloted by the receiving office

N/A N/A

7. Particulars for filing divisional application

Original(First) Application Number Date of filing of Original (first) application

N/A N/A

8. Particulars for filing patent of addition

Original(First) Application Number Date of filing of Original (first) application

N/A N/A

9. DECLARATIONS:

(i) Declaration by the inventor(s)

I/We, the above named inventor(s) is/are true & first inventor(s) for this invention and declare that the

applicant(s).

herein is/are my/our assignee or legal representative.

Date : 21 - May - 2015

Signature & DateName

1 Neelay Rakesh Khese

2 Maitrey Yogeshkumar

Patel

3 Jainil Bharatbhai Patel

4 Rehan Javed

Peerzada

5 Aash Hitendra Shah

(ii) Declaration by the applicant(s) in the convention country

I/We, the applicant(s) hereby declare(s) that:-

(iii) Declaration by the applicant(s)

I/We, the applicant (s) in the convention country declare that the applicant(s) herein is/are my/our

assignee or legal representative.applicant(s)

This is just a mock Patent Drafting Exercise (PDE) for semester 8, BE students of GTU.

These documents are not to be submitted with any patent office.Note :

Page 4 of 6

Page 99: G+20 Corporate House Construction & Project Management

I am/We in possession of the above mentioned invention.

The provisional/complete specification relating to the invention is filed with this aplication.

The invention as disclosed in the spcification uses the biological material from India and the necessary

permission from the competent authority shall be submitted by me/us before the grant of patent to me/us.

There is no lawful ground of objection to the grant of the patent to me/us.

I am/we are the assignee or the legal representative of true & first inventors.

The application or each of the application,particulars of each are given in the para 5 was the first applicatin in

the convention country/countries in respect of my/our invention.

The application or each of the application,particulars of each are given in the para 5 was the first applicatin in

the convention country/countries in respect of my/our invention.

I/we claim the priority from the above mentioned applications(s) filed in the convention country/countries &

state that no application for protection in respect of invention had been made in a convention country before

that date by me/us or by any person

My/Our application in india is based on international application under Patent Cooperation Treaty (PCT) as

mentioned in para 6

The application is divided out of my/our application(s) particulars of which are given in para 7 and pray that

this application may be treated as deemed to have been filed on ___________under section 16 of the Act.

The said invention is an improvement in or modification of the invention particulars of ehivh are given in para

8.

(a) Provisional specification/Complete specification

(b) Complete specification(In confirmation with the international application) / as amended before the

international Preliminary Examination Authority (IPEA),as applicable(2 copies),No.of pages.....No.of

claims.....

(c) Drawings (In confirmation with the international application)/as amended before the international

Preliminary Examination Authority(IPEA),as applicable(2 copies),No.of sheets....

(d) Priority documents

(e) Translations of priority documents/specification/international search reports

(f) Statement and undertaking on Form 3

(g) Power of Authority

(h) Declaration of inventorship on Form 5

(i) Sequence listing in electronic Form

(j) ........................................ Fees Rs.XXX in Cash /Cheque/Bank Draft bearin No.XXX Date: XXX on XXX

Bank.

10. Following are the attachments with the application:

I/We hereby declare that to the best of my /our knowledge, information and belief the fact and mtters stated

herein are correct and I/We request that a patent may be granted to me/us for the said invention.Dated this 21 day of May , 2015

This is just a mock Patent Drafting Exercise (PDE) for semester 8, BE students of GTU.

These documents are not to be submitted with any patent office.Note :

Page 5 of 6

Page 100: G+20 Corporate House Construction & Project Management

Name Signature & Date

1 Neelay Rakesh Khese

2 Maitrey Yogeshkumar

Patel

3 Jainil Bharatbhai Patel

4 Rehan Javed

Peerzada

5 Aash Hitendra Shah

This is just a mock Patent Drafting Exercise (PDE) for semester 8, BE students of GTU.

These documents are not to be submitted with any patent office.Note :

Page 6 of 6

Page 101: G+20 Corporate House Construction & Project Management

GIC Patent Drafting Exercise Team ID:

FORM 2

THE PATENTS ACT, 1970

(39 OF 1970)

&

THE PATENTS RULES, 2003

PROVISIONAL SPECIFICATION

22722

1. Title of the project/invention :

Construction And Project Management Of G+20 Corporate House

Neelay Rakesh Khese , ( Indian )

Address :Civil Engineering , L. J. Institute Of Engineering And Technology, Ahmedabad , Gujarat Technologycal

University.

Maitrey Yogeshkumar Patel , ( Indian )

Address :Civil Engineering , L. J. Institute Of Engineering And Technology, Ahmedabad , Gujarat Technologycal

University.

Jainil Bharatbhai Patel , ( Indian )

Address :Civil Engineering , L. J. Institute Of Engineering And Technology, Ahmedabad , Gujarat Technologycal

University.

Rehan Javed Peerzada , ( Indian )

Address :Civil Engineering , L. J. Institute Of Engineering And Technology, Ahmedabad , Gujarat Technologycal

University.

Aash Hitendra Shah , ( Indian )

Address :Civil Engineering , L. J. Institute Of Engineering And Technology, Ahmedabad , Gujarat Technologycal

University.

2. Applicant(s) :

3. Preamble to the description :

The following specification describes the invention.

This is just a mock Patent Drafting Exercise (PDE) for semester 8, BE students of GTU.

These documents are not to be submitted with any patent office.Note :

Page 1 of 5

Page 102: G+20 Corporate House Construction & Project Management

4. Description :

a. Field of Application / Project / Invention :

Construction Management and Development.

b. Prior Art / Background of the Invention / References :

In developing a construction plan, it is common to adopt a primary emphasis on either cost control

or on schedule control as illustrated in Fig. 9-1. Some projects are primarily divided into expense

categories with associated costs. In these cases, construction planning is cost or expense oriented .

Within the categories of expenditure, a distinction is made between costs incurred directly in the

performance of an activity and indirectly for the accomplishment of the project. For example,

borrowing expenses for project financing and overhead items are commonly treated as indirect

costs. For other projects, scheduling of work activities over time is critical and is emphasized in the

planning process. In this case, the planner insures that the proper precedence ’s among activities

are maintained and that efficient scheduling of the available resources prevails. Traditional

scheduling procedures emphasize the maintenance of task precedence ’s (resulting in critical path

scheduling procedures) or efficient use of resources over time (resulting in job shop scheduling

procedures). Finally, most complex projects require consideration of cost and scheduling over time,

so that planning, monitoring and record keeping must consider both dimensions. In these cases,

the integration of schedule and budget information is a major concern.

c. Summary of the Invention/Project :

With the competition in the construction market is fierce increasingly, profit margin of construction

enterprises is getting smaller and smaller,and cost control of construction projects become more

and more important.The control of construction project cost becomes one of the cores in project

management. Construction project management is a systematic, comprehensive, dynamic subject,

requiring construction project manager to regularize and standardize the organization, goal, quality,

safety, and cost of construction project . In this paper, in order to achieve the project cost control

effectively and create greater economic benefits,construction project management

content,measures and cost Control measures were studies.

d. Objects of the Invention/Project :

Building Construction Management Learning Outcomes :-

1. The student is prepared to assume an entry level professional constructor ’s role as a member of

a multidisciplinary team in the construction industry.

2. The student has the fundamental education that will lead to a leadership role in the construction

industry.

3. The student has developed an ethical and professional foundation to become a responsible

member of society and the construction industry.

4. The student has the fundamental skills in oral and written communication as required to

effectively communicate in the construction industry

5. The student possesses the fundamental knowledge and skills needed to manage the principal

resources of the construction industry to include human, material, equipment, and financial

resources

6. The student has a well-developed concept of mathematics and physical science

7. The student possesses an understanding of the contributions made by design professionals to

the construction processes, and can communicate and interact with design professionals within the

multidisciplinary construction team.

8. The student will understand the global nature of the construction industry.

e. Drawing(s) :

This is just a mock Patent Drafting Exercise (PDE) for semester 8, BE students of GTU.

These documents are not to be submitted with any patent office.Note :

Page 2 of 5

Page 103: G+20 Corporate House Construction & Project Management

f. Description of the Invention

Construction planning is a fundamental and challenging activity in the management and execution

of construction projects. It involves the choice of technology, the definition of work tasks, the

estimation of the required resources and durations for individual tasks, and the identification of any

interactions among the different work tasks. A good construction plan is the basis for developing

the budget and the schedule for work. Developing the construction plan is a critical task in the

management of construction, even if the plan is not written or otherwise formally recorded. In

addition to these technical aspects of construction planning, it may also be necessary to make

organizational decisions about the relationships between project participants and even which

organizations to include in a project. For example, the extent to which sub -contractors will be used

on a project is often determined during construction planning.

Most people, if you describe a train of events to them, will tell you what the result would be. They

can put those events together in their minds, and argue from them that something will come to

pass. There are few people, however, who, if you told them a result, would be able to evolve from

their own inner consciousness what the steps were which led up to that result. This power is what I

mean when I talk of reasoning backward.

Like a detective, a planner begins with a result (i.e. a facility design) and must synthesize the steps

required to yield this result. Essential aspects of construction planning include the generation of

required activities, analysis of the implications of these activities, and choice among the various

alternative means of performing activities. In contrast to a detective discovering a single train of

events, however, construction planners also face the normative problem of choosing the best

among numerous alternative plans. Moreover, a detective is faced with an observable result,

whereas a planner must imagine the final facility as described in the plans and specifications.

In developing a construction plan, it is common to adopt a primary emphasis on either cost control

or on schedule control as illustrated in Fig. 9-1. Some projects are primarily divided into expense

categories with associated costs. In these cases, construction planning is cost or expense oriented .

Within the categories of expenditure, a distinction is made between costs incurred directly in the

performance of an activity and indirectly for the accomplishment of the project. For example,

borrowing expenses for project financing and overhead items are commonly treated as indirect

costs. For other projects, scheduling of work activities over time is critical and is emphasized in the

planning process. In this case, the planner insures that the proper precedence ’s among activities

are maintained and that efficient scheduling of the available resources prevails. Traditional

scheduling procedures emphasize the maintenance of task precedence ’s (resulting in critical path

scheduling procedures) or efficient use of resources over time (resulting in job shop scheduling

procedures). Finally, most complex projects require consideration of cost and scheduling over time,

so that planning, monitoring and record keeping must consider both dimensions. In these cases,

the integration of schedule and budget information is a major concern.

g. Examples

h. Unique Features of the Project

nothing

5. Date & Signature :

Date : 21 - May - 2015

This is just a mock Patent Drafting Exercise (PDE) for semester 8, BE students of GTU.

These documents are not to be submitted with any patent office.Note :

Page 3 of 5

Page 104: G+20 Corporate House Construction & Project Management

Sign and Date

Neelay Rakesh Khese

Sign and Date

Maitrey Yogeshkumar

Patel

Sign and Date

Jainil Bharatbhai Patel

Sign and Date

Rehan Javed

Peerzada

Sign and Date

Aash Hitendra Shah

6. Abstract of the project / invention :

With the competition in the construction market is fierce increasingly, profit margin of construction

enterprises is getting smaller and smaller,and cost control of construction projects become more and more

important.The control of construction project cost becomes one of the cores in project management .

Construction project management is a systematic, comprehensive, dynamic subject, requiring construction

project manager to regularize and standardize the organization, goal, quality, safety, and cost of

construction project . In this paper, in order to achieve the project cost control effectively and create greater

economic benefits,construction project management content,measures and cost Control measures were

studies.

This is just a mock Patent Drafting Exercise (PDE) for semester 8, BE students of GTU.

These documents are not to be submitted with any patent office.Note :

Page 4 of 5

Page 105: G+20 Corporate House Construction & Project Management

Drawing Attachments :

This is just a mock Patent Drafting Exercise (PDE) for semester 8, BE students of GTU.

These documents are not to be submitted with any patent office.Note :

Page 5 of 5

Page 106: G+20 Corporate House Construction & Project Management

GIC Patent Drafting Exercise Team ID:

FORM 3

THE PATENTS ACT, 1970

(39 OF 1970)

&

THE PATENTS RULES, 2003

STATEMENT AND UNDERTAKING UNDER SECTION 8

22722

1. Declaration :Neelay Rakesh Khese , Maitrey Yogeshkumar Patel , Jainil Bharatbhai Patel , Rehan Javed Peerzada , Aash Hitendra Shah ,

I/We,

Neelay Rakesh Khese ( Indian )

Address : Civil Engineering , L. J. Institute Of Engineering And Technology,

Ahmedabad , Gujarat Technologycal University.

Maitrey Yogeshkumar Patel ( Indian )

Address : Civil Engineering , L. J. Institute Of Engineering And Technology,

Ahmedabad , Gujarat Technologycal University.

Jainil Bharatbhai Patel ( Indian )

Address : Civil Engineering , L. J. Institute Of Engineering And Technology,

Ahmedabad , Gujarat Technologycal University.

Rehan Javed Peerzada ( Indian )

Address : Civil Engineering , L. J. Institute Of Engineering And Technology,

Ahmedabad , Gujarat Technologycal University.

Aash Hitendra Shah ( Indian )

Address : Civil Engineering , L. J. Institute Of Engineering And Technology,

Ahmedabad , Gujarat Technologycal University.

2. Name, Address and Nationality of the joint Applicant :

Name of the

Country

Date of

Application

Application

Number

Status of the

Application

Date of

Publication

Date of

Grant

N/A N/A N/A N/AN/AN/A

(i) that I/We have not made any application for the same/substantially the same

invention outside India.

(ii) that the right in the application(s) has/have been assigned to,

Here by declare:

(iii) that I/We undertake that up to the date of grant of patent by the Controller , I/We

would keep him inform in writing the details regarding corresponding application(s)

for patents filed outside India within 3 months from the date of filing of such

application.

Dated this 21 day of May , 2015.

This is just a mock Patent Drafting Exercise (PDE) for semester 8, BE students of GTU.

These documents are not to be submitted with any patent office.Note :

Page 1 of 2

Page 107: G+20 Corporate House Construction & Project Management

3. Signature of Applicants :

Sign and Date

Neelay Rakesh Khese

Sign and Date

Maitrey Yogeshkumar

Patel

Sign and Date

Jainil Bharatbhai Patel

Sign and Date

Rehan Javed Peerzada

Sign and Date

Aash Hitendra Shah

To

The Controller of Patent

The Patent Office, at Mumbai.

This is just a mock Patent Drafting Exercise (PDE) for semester 8, BE students of GTU.

These documents are not to be submitted with any patent office.Note :

Page 2 of 2

Page 108: G+20 Corporate House Construction & Project Management

APPENDIX – 3

Business Model Canvas

Page 109: G+20 Corporate House Construction & Project Management