fotovoltaic project romania 2.7 mw (brasov)
DESCRIPTION
solar project in Romaniaphase ready to build with connection contractTRANSCRIPT
George CiubotaruGeorge Ciubotaru
BalsBals 11
PV PV Project Project
PresentationPresentation
Paul Voicu
Phone: +40744355200
George Ciubotaru
Phone: +40726359574
Key investment highlights• Bals 1 project is part of solar PV Portfolio of projects located in Oltenia area, in Olt & Dolj counties:
• Among the best areas in terms of radiation in Romania
• The area is still not crowded and suitable for solar PV developments (the first projects to obtain the
connection permit in the corresponding substations);
• In an area not influenced by wind parks, with a good stability of the grid.
Portfolio AreaPortfolio Area
• The project is developed through the SPV Green
Solar Power;
• The location is represented by one land plot with
an area of 15 Ha;
• The estimated installed capacity is 8 MWp;
Project location
• Average GHR radiation in site is of 1443 KWh/m²;
• The access to the site is assured by a European
road (E574/DN65) and a exploitation road (2,4 KM
from asphalt to the entry in the site);
• The ownership of the land is the direct property
of the SPV.
Site photos
Project Plot of land – Flat area
Bals Substation 300 m from site
Exploitation Road – in site access
Status of the project
• The solution study for grid connection has
been approved and the grid connection
permit (ATR) has been issued at the End of
February 2012;
• The project has obtained all the necessary
Location/SPV
Bobicesti
Status
Installed Capacity (MW) 8.0
Prefeasibility Study
Land rights
Certificate of urbanism
Environmental Approval • The project has obtained all the necessary
permits and approvals;
• Distance to substation of only 800 m;
• Grid connection cost (according to the ATR
is of 240 thou euro VAT excluded).
Removal of land from agricultural use (ANIF, OSPA, OCPI)
Other permits (Compet, Public Health, General Staff, CFR, ISU)
Location Permit
Solution Study For Grid Connection
Grid Connection Permit (ATR)
Building Permit
Transmission line – easement rights and building permit
Technical Details
Location/SPV
Bobicesti
Installed Capacity (MW) 8.0
Land Size (Ha) 15
Distance to Substation (Km) 0.8
Global Horizontal Radiation 1400-1480
6
Estimated Net Production (kWp/KWh/year) 1250-1270
Mounting System fixed tilt
Transmission Line UGL
Substation 20 kV
The Developer
• Over 36 Mil Euro turnover and over 350 employees at the end of 2011
• As secondary fields of activity the company operates in:
• Industry (Chemical and petrochemical, Metal processing , Industrial appliances, Food processing,
Transportation and others)
• Real Estate (Industrial and Residential)
• Entered the renewable energy market in 2010 with the intention of capitalizing on the electrical works
and project management expertize
Turnover evolution (MIL. EURO)
The company holds the following certificates:
• Certificate for electrical works issued by National Authority for the
Energy Regulation (ANRE);
• Certificate of registered supplier for TRANSELECTRICA, ELECTRICA and
E-ON Moldova;
• Authorization for land improvement projects (civil works and
installation and commissioning works) issued by the Agriculture, Woods
and Rural Development Ministry
•is one of the most important producers of LV and MV equipment as well as and integrated solutions. The
company is structured in several business units: Low Voltage, Medium Voltage, Power Distribution
Equipment, Turnkey Projects, Steel parts, Maintenance
Project structure
Project Companies
INVESTOR 2New investor at fully
permitted stage
INVESTOR 1Developers
Project Companies
INVESTOR 2New investor at fully
permitted stage
INVESTOR 1Developers
Project Companies
Bank loan/ supplier credit
Project Companies
Bank loan/ supplier credit
• The deal structure can be flexible as the projects can be acquired individually or as a pipeline
depending on the investors
Romanian Power Market Summary
• Romania is a fast-growing early stage Renewable energy market within the European Union, with a
solid legal framework in place.
• At the end of August 2012 there were over 521 MW of solar PV projects with grid connection
contracts and 1,032 MW with ATR (grid connection permit)
• A new incentive scheme was approved in July 2010 (Law 139/2010, revising the Law 220/2008), and
has been reinforced through the Government Emergency Ordinance (GEO) number 88/ October 12,
2011 on the E-RES support mechanism.
• According to this Law, Romania has set overall renewable energy targets for final consumption of• According to this Law, Romania has set overall renewable energy targets for final consumption of
electricity (including hydropower) as follows: 33% in 2010, 35% in 2015, and 38% in 2020.
• Also, in July 2012, Law 123/2012 has been issued and published in the Official Gazette. The law
establishes, among others, energy market liberalization.
• PV power generators are remunerated in 2 ways:
• Sale of the electricity generated;
• Sale of Green Certificates attributed.
• Regarding electricity, generators from renewable sources have priority access to the transport and
distribution grids, and are able to sell electricity generated in the Wholesale market at the market
price, or alternatively, at a regulated price set yearly by the regulator.
• The Green Certificate system has improved significantly with the last change in law: Solar PV power
plants receive 6 Green Certificates (GC) per MWh generated, until reaching 15 years from the start of
operations;
• The price of Green Certificates is capped and floored each year until 2025 at 55 €/GC and 27€/GC at the
beginning of the year, based on the exchange rate of December previous year. Cap and floor values are
adjusted yearly with inflation (EU27) and floor value for the period starting with 2026 cannot be lower
than the 2025 value;
Romanian Power Market Summary
Green Certificates Scheme
Regulator
Power Suppliers
Transelectrica
Trading Platform
Bilateral
Centralized Market
Quota obligationProvisions of GCs
Eligible RES
producers
Penalty for quota
unfulfillment
Green Certificates Scheme
National
Environment Fund
Romanian Power Market Summary
• Quotas for the post-2020 period will be defined later by the Government, but will be no lower
• Electricity distributors have to redeem Green Certificates at the end of each year, as a percentage
of their energy sales. The quotas have been increased compared to the previous version of the law
in order to further encourage the quota fulfillment;
than the 2020 quota;
• Penalty for electricity suppliers that are unable to fulfill the mandatory quotas is set at EUR 110;
• Currently there is a significant undersupply of GCs needed to achieve the renewable share in
generation mix;
• Secondary legislation elaborated by ANRE (The National Regulatory Authority) was approved in
early November 2011;
• Thus for the first time Romania has an attractive and applicable supporting mechanism for
renewables.