Kasbel Construcuction and Supply Inc. is a family
corporation, established and registered with the
Securities and Exchange Commission. Prior to this date,
the construction firm was known as Kasbel Construction
and Supply established last 2007 and was formerly
known as PER Construction (PERCON est. 1982). The
later company had been able to undertake several
projects ranging from telecommunication line designs
and installations (OSP), warehouses, residential and
commercial buildings in Luzon, Visayas, and Mindanao.
Kasbel Construction and Supply Inc. offer
personalized service, time-efficient and cost-saving
construction strategies in a safe and healthy working
environment leading towards producing high quality
outputs serving highly satisfied clients.
-
ADDRESS Main Office : Door 10 JTL Plaza Dona Vicenta Road, Bajada Davao City
Downtown Office : 26E Arellano St. Davao City
CONTACT NUMBERS
TELEFAX : 082 295-3269 CELLPHONE : 0928 524-4470 or 0939-924-0703
LEGAL ASPECTS
Name Registration : Securities and Exchange Commission Region XI, Davao City
Certificate Number: CS201430704
-
GENERAL MANAGER: EMMANUEL R. PADLAN OPERATIONS MANAGER: BEEM KASTEN PADLAN ENGINEERING DESIGN HEAD: ALEXANDER NARCISO OSP SUPERVISING ENGINEERS: VLADIMIR CASTILLO RAUL ADNADO DANNY CANONIGO FIELD ENGINEERS: JAYSON ABECIA PATRICK EDRIAN YNTIG ACE JETHRO PEREZ JOSEPH MARI ALICANDO CHERRY MALAZARTE
-
I. Engineering Works and Design Mirait Philippines Incorporated
A. Globe V-Optics Project 300kms (Fiberization of Globe Towers) Location: Mindanao Status: Ongoing
B. Big 8 Hotel Lucky 9 Inn Fiber Network Connectivity (2.5Km) Location: Tagum City Status: Completed
C. PLDT Fiber to the Home (40 Sites) Location: Tacloban, Iloilo, Cebu, Bohol, Bacolod and Palawan Status: Completed
D. PLDT Fiber To The Home Project (70 Sites)
Location: Davao City Date of Completion: August 2012
E. Globe Modernization Project Engineering Works AN Loops Design. (70 AN Sites) Location: Bukidnon, Misamis Oriental, Surigao del Norte, Surigao del Sur, Agusan del Norte and Agusan del Sur. Date of Completion: June 2012
F. Globe Nemesis Project Engineering Works from Mati San Franciso Agusan del Sur (417 kms) Date of Completion: May 2012
-
CKPT Technologies
A. Globe Nemesis Suha Project Engineering Works from Davao to Mati (300 kms) Date of Completion: April 2012
KTK Fujikura Philippines Incorporated
A. Innove Phase 3C-4 Davao Project Engineering Works and Design Date of Completion: June 2007
B. Innove Phase 3C-4 General Santos Engineering Works and Design Date of Completion: June 2007
Scope of Work: 1. Fundamental 2. Design 3. Cad Work 4. Red Line
II. Outside Plant (OSP) Mirait Philippines Incorporated
A. Globe V-Optics Project Fiber Installation (300kms) Location: Mindanao Status: Ongoing
G. Big 8 Hotel Lucky 9 Inn Fiber Network Connectivity (2.5Km) Location: Tagum City Status: Completed
B. PLDT Fiber to the Home Fiber Installation (40 Sites) Location: Tacloban, Iloilo, Cebu, Bohol, Bacolod and Palawan Date of Completion: April 2015
-
C. Globe Nemesis Project Fiber Installation (180 kms)
Location: Barobo Carmen Date of Completion: April 2014
D. Globe Nemesis Project Fiber Installation (80 kms) Location: Bukidnon, Misamis Oriental, Surigao del Norte, Surigao del Sur, Agusan del Norte and Agusan del Sur. Date of Completion: April 2014
E. Globe Nemesis Project Fiber Installation from
Barobo to San Francisco Agusan del Sur (30kms) Date of Completion: November 2012
NEPCON A. Globe BTS Fiber Protection Project
Date of Completion: December 2011 Sasa BTS Davao Air BTS Panacan 3 BTS Buhangin BTS
B. Ayala Abreeza FOC Protection Date of Completion: May 2011
ETSI Technologies, Inc. A. Globe Bacolod Project
Area: Bacolod Fiber Optic Installation
Secondary Cable Works (11 Cabinets)
KTK Fujikura Philippines Incorporated
A. PLDT OSP Rehabilitation Project
Area: Davao City Date of Completion: December 2008
B. PLDT Postpaid and DSL Installation (DP to Subscribers) Area: Davao City
-
C. Innove Phase 3C-4 Davao Project 1. Fiber Optic Cable Installation (Ring 1 and Ring 2)
Date of Completion: February 2008 2. Secondary Cable Works (16 Cabinets)
Date of Completion: April 2008
D. Innove Phase 3C - 4 Cagayan de Oro Project 1. Fiber Optic Cable Installation
Date of Completion: June 2008 2. Secondary Cable Works ( 6 Cabinets)
Status: Ongoing
E. Innove Phase 3C-4 Leyte Project 1. Secondary Cable Works (4 Cabinets)
Status: Ongoing
Scope of Works a. Right of Way Negotiation b. Installation of Underground Fiber Optic Cable c. Installation of Copper Cable d. Pole erection and anchor installation e. Installation of Pole line hardware and guying f. Messenger laying / tensioning and cable lashing g. Jointing / Splicing and closures of copper cables h. Test and commissioning
Living @ Sense Incorporated
A. Digitel Bayantel Interconnection Area: Davao City Date of Completion: August 2010
B. Globe FOC Trunkline Project Area: Tupi Koronadal
Date of Completion: March 2009