  • 7/25/2019 Fire Protection Commissioning Procedure

    1/39

    DOCUMENT COVER SHEET

    A 13 Aug 2009 ISSUED FOR APPROVAL B.C.PARK M.Y,JUNG H.I.LEE

    REV. DATE DESCRIPTION DGN CHK APP

    CLIENT

    PROJ. CONSULTANT

    PROJECT TITLE

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/2007)

    DESIGNED B C 13 ACONTRACTOR

    ARABIAN CONSULTING AND ENGINEERING SERVICESCO.

    GPCOEWGGENERAL PEOPLES COMMITTEE

    OF ELECTRICITY, WATER AND GAS

    GECOLGENERAL ELECTRIC

    COMPANY OF LIBYA

  • 7/25/2019 Fire Protection Commissioning Procedure

    2/39

    TABLE OF CONTENTS

    1. OBJECTIVE

    2. ACCEPTANCE CRITERIA

    3. REFERENCE

    4. PREREQUISITES

    5. PREPARATION AND NOTES

    6. TEST EQUIPMENT

    7. TEST AND COMMISSIONING PROCEDURE

    8. TEST AND COMMISSIONING SCHEDULE

    9. APPPENDIX

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    3/39

    1. OBJECTIVE

    The objective of this procedure is to provide guidelines to verify the FireFighting System being tested, and to furnish the initial start-up procedure of

    the fire fighting system except the fire alarm/ detection system.

    The equipment and control devices on the system must meet functionaldesign requirements to demonstrate reliability and continuity of process.

    The fire alarm and detection system will be tested by a separate testprocedure to be submitted later.

    2. ACCEPTANCE CRITERIA

    1. Acceptance noise level85 dB (A) in one meter distance from the source of equipment.

    2. Vibration

    Acceptable field vibration limits shall meet the vibration severity attached inappendix

    3. Bearing temperatureBearing temperature are as specified by the vendors technical manual, butNot exceed 75C.

    3. REFERENCE

    1. P & I diagram

    142007 SR00 M 1089 P& ID Fi t ti S t

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    4/39

    2. Wiring diagram

    Later Fire pump controller

    Later Fire pump diesel engine

    2. General arrangement drawing

    EE44724/01 Electric driven water fire pump

    E3955/01 Diesel driven water fire pump

    4. PREREQUISITES

    1. Raw water intake level is normal

    2. All piping, manual valves and equipment installation is completed by erectionmanual.

    3. Associated electric power is available.

    4. Associated instrument installation is completed and available to put intoservice.

    5 D l l i h l ti l diti

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    5/39

    5. PRECAUTION AND NOTES

    1. To protect personnel and the equipment:

    Barriers, danger signs, tags, area restrictions, etc. should be used bylockout & tag out procedure and permit to work system in accordancewith the commissioning plan.

    2. Stop running pump if unusual noises develop, or if monitored parametersexceed the design limits.

    3. Stop running pump if unusual noise leakage of water is occurred andcloses the relating valves.

    4. Communication is established between the test equipment and controlstation.

    5. Prior to test equipment, test area shall be cleaned.

    6. Test running time shall be as specified by the manufacture or untilequipment temperatures stabilize.

    6. AREAS TO BE PROTECTED BY FIRE PROTECTION SYSTEM

    1) Indoor hydrants

    CTG Building

    Electrical control Building

    Water Treatment Plant Building

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE:

    Fire Protection Commissioning Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    6/39

    3) Automatic CO2 System

    Gas turbine unit

    Fuel gas skid

    Corresponding Power control Center

    4) Fixed Low expansion foam system

    LFO Storage Tank

    5) Automatic water spray system

    All oil filled transformers

    Cable Cellar area in Electrical Control Building

    LFO Storage tank

    6) (Mobile and Portable fire Extinguisher)

    Class A- Office Areas

    Class B- Fuel Oil and Gas handling skid

    Class C- Control, Electrical, Switchgear and battery room

    7. TEST AND COMMISSIONING PROCEDURE

    1) General Item

    a. Prior to the commissioning test run, the system is to be checked,and then the test run of raw/ water fire fighting pump and the waterfl hi f th fi fi hti t t b t d i

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    7/39

    e. The ring main header of the fire fighting system should be flushedusing the fire water pump.

    f. Record measured values on the record sheet and / or loggingsheet while equipment is running.

    2) Specification

    a. Electric Motor driven fire water pump

    Supplier SPP Pumps Limited

    Number of pump 1 set

    Type Horizontal Thru-Stream(FM & or UL)- Axial Split Case

    Capacity 568 m/hr

    Model SPP0 TD-20E

    Motor rated 199.5 KW

    Speed 2950 rpm

    b. Electric Motor driven Jockey pump

    Supplier SPP Pumps Limited

    Number of pump 1 set

    Type Centrifugal, Horizontal

    Capacity 20m/hr

    c. Desiel engine driven fire water pump

    a) Pump

    Supplier SPP Pumps Limited

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    8/39

    b) Gear

    Type Later

    Model Later

    Ratio Later

    c) Engine

    Manufacturer Later

    Type Later

    Model Later

    Cylinder number Later

    Aspiration Later

    Governor Later

    Fuel oil pump disch. Flow Later

    Coolant flow rate Later

    Coolant oper. Pressure Later

    Lubrication type Later

    Lube oil flow Later

    Starter motor Later

    Battery capacity Later

    Low idle speed Later

    Rated speed Later

    3) Installation check

    Refer to installation checklist: attachment 1

    4) Pre- commissioning check

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    9/39

    8. TEST AND COMMISSIONING SCHEDULE

    The actual test date will be informed to GECOL engineer in advance before testbased on the attached commissioning schedule.

    9. APPENDIX

    1) P & I Diagram

    142007-SR00-M-1089 Fire protection System

    142007-SR00-M-FFS-003 Water spray system

    142007-SR00-M-FFS-005 Water cooling/ foam system

    142007-SR00-M-1059 Flow diagram fire detection system

    142007-SR00-M-1207 Fire pump house system GeneralArrangement

    2) Wiring diagram

    Later Fire pump controller

    Later Fire pump diesel engine

    3) General Arrangement drawing

    EE44724/01 El t i d i t fi

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    10/39

    ATTACHMENT 1

    INSTALLATION CHECK LIST

    MECHANICAL

    ELECTRICAL

    INSRUMENT

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    11/39

    1

    2

    : FIRE FIGHTING SYSTEM

    EQUIPMENT

    NO.

    SYSTEM

    P & I diagram.

    JOB DESCRIPTION

    Check all pipings and valves including post indicator valves,

    REMARKS

    combined foam/ water hydrant, outdoor hydrants and automatic

    water spray system have been installed as per the attached

    TITLE: INSTALLATION CHECK LIST

    deluge valves, safety valves, strainer, spray nozzles and flow

    Check the raw water fire fighting pump/engine, indoor hydrants

    meter have been installed as per the attached P& I diagram.

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

    3

    4

    DATE:

    THE ABOVE SUBJECT IN THIS SHEET HAS BEEN

    Check the diesel engine / fire pump control panel have been

    installed as per electrical drawing.

    CERTIFIED BY BELOW AUTHORITIES

    PREPARED BY:

    HDEC/ VENDOR

    have been installed as per the attached P & I diagram.

    Check all instrument ( gauge, switch, controller and transmitter)

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    12/39

    ATTACHMENT 2

    PRE- COMMISSIONING CHECK LIST

    RAW WATER FIRE FIGHTING SYSTEM

    WATER SPRAY SYSTEM

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    13/39

    1

    JOB DESCRIPTION

    EQUIPMENT : RAW WATER FIRE PUMP

    DIESEL ENGINE TEST

    1. Preparation Check

    a. Mount the engine and fasten in place.

    b. Align the engine with the pump. And disconnect the

    SYSTEM : FIRE FIGHTING SYSTEM

    d. Check to see if the fuel tank has been filled.

    e. fill engine cooling system with pro- mixture of 50% treated

    coupling/ shaft between the engine and pump.

    c. Install the fuel supply and the return lines.

    REMARKS

    TITLE: PRE- COMMISSIONING CHECK LIST

    NO.

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

    backpressure limits.

    Repair or replace if necessary.

    i. Install batteries and battery cables to the battery mainbattery contactors. Batteries should be charged 24 hrs

    j. Install the water conduits. Do not allow plumbing to cause

    any stress on the heat exchanger or aftercooler.

    k. Check for damaged or missing exhaust blankets.

    occur.

    g. Install the exhaust system. Do not allow exhaust system

    h. Install wiring between the automatic engine control and

    the engine terminal strip.

    piping to cause any stress on the engine. Do not exceed

    f. Inspect/ or install the air filter. Repair or replace the air

    filter if damanged or missing. Do not allow air filter to be

    obstructed; poor performance or engine damage may

    .

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    14/39

    ENGINE START

    a. Manual start and stop

    a) Place the selector switch in " Manual" mode

    - Observe the pilot light comes "On".- Observe the run soleniod engages, and a clicking sound is heard.

    TITLE: PRE- COMMISSIONING CHECK LIST

    SYSTEM : FIRE FIGHTING SYSTEM

    b) Lifts and holds manual crank toggle switch.

    c) Check the engine starts, and the engine speed is reached the

    the factory -set speed without the engine idling and without a

    EQUIPMENT : RAW WATER FIRE PUMP

    NO. JOB DESCRIPTION REMARKS

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commission ing Procedure

    - Engine speed:

    is functioning and the batteries are being charged. e) During the diesel engine is running. The followings should be

    checked.

    - Leaks:

    Check for leaks. Verify the coolant hose. The fuel supply and

    the return lines or any where else around the engine.

    - Oil pressure:

    Normal reading is between 55 and 88 psi ( 3.75 and 5.4 bar.) - Jacket water temperature:

    The jacket water temperature should normally remain in the

    green sector. If the pointer enters the orange sector, the engine

    is over heating and engine damage may occur.

    warm up per o .

    d) Release the manual crank toggle switch.

    -Observe the pilot light turns " Off" indicating that the alternator

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commission ing Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    15/39

    JOB DESCRIPTION REMARKS

    TITLE: PRE- COMMISSIONG CHECK LIST

    SYSTEM : FIRE FIGHTING SYSTEM

    EQUIPMENT

    NO.

    : RAW WATER FIRE PUMP

    f) After running of diesel engine observe the pilot light turns" Off" indicating that the alternator is functioning and the batteries are

    being charged .

    g) Stop the engine.

    d) Check the engine speed is reached the factory set speed.

    e) Observe the starter motor to the stop cranking has been

    actuated by electronic switch.

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commission ing Procedure

    2

    a) Start the engine by manual

    b) Check the engine speed is kept at rated speed.

    FIRE PUMP TEST

    gage.

    c. er y ng e overspee es sw c

    3) Make sure that the shaft adjusting nut is properly locked into

    c) Hold the overspeed testing switch in the "up" position until thethe engine shuts down.

    d) Check the engine shuts down immediately with overspeed

    alarm.

    e) Push the "Over speed reset" button on the control panel

    f) Restart the engine.

    1) Chek the oil level of right angle gear unit is normal in oil level

    2) Rotate the pump shaft by hand to make sure the pump is free

    and the impeller are correctly positioned.

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commission ing Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    16/39

    EQUIPMENT : DELUGE VALVE

    NO. JOB DESCRIPTION REMARKS

    TITLE: PRE- COMMISSIONING CHECK LIST

    SYSTEM : WATER SPRAY SYSTEM

    bolts, seal piping, etc.)10) On the pumps equipment with packing box, make sure the

    8) Check all anchor bolts for tightness.

    9) Check all bolting and tubing connection for tightness.

    ( driver mounting bolts, flanged coupling bolts, seal housing cover

    glands nuts are only finger tight and do not tighen packing gland

    before starting. Check the cooling water inlet and outlet lines.

    Connect the coupling /drive shaft bet, the engine and pump.

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commission ing Procedure

    2

    3

    4

    panels.

    The water spray nozzles switch are in standby.

    in the control head.

    3) The actuator or solenoid valve and the emergency release valve

    to be closed.

    4) System water pressure to be shown on pressure gage.

    5) Alarm valve is closed.

    The main gate valves, installed upstream of the automatic deluge

    valve ,are open.

    Automatic deluge valve unit condition. 1) Deluge valve is closed, full of water in pressure under the clapper.

    2) Clapper is blocked in " closed position" by the water pressure

    7) Water flow pressure switch not transmit signal to the Control

    6) Angle discharge valve for drain is closed.

    e sys em s u o wa er up o e au oma c e uge va ve c apper.

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commission ing Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    17/39

    ATTACHMENT 3

    COMMISSIONING CHECK LIST

    RAW WATER FIRE PUMP

    SYSTEM FLUSHING & SYSTEM FILL-UP WATER

    WATER SPRAY SYSTEM

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    18/39

    1

    TITLE: COMMISSIONING CHECK LIST

    JOB DESCRIPTION REMARKS

    PUMP TEST RUN

    a. Check the engine no load test has been completed.

    1) Preparation

    d. Check the following valve are closed.

    -pump discharge valve AA003 to system

    line is set in the factory.

    SYSTEM : FIRE FIGHTING SYSTEM

    EQUIPMENT : RAW WATER FIRE PUMP

    b. Check the coupling / drive shaft has been connected. c. Check the safety pressure valve located on the pump discharge

    NO.

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commission ing Procedure

    or improper operation.6) If possible, the fire pump should be left running for approximately

    30 minutes on the initial start-up. This will allow the bearing,

    packing or seals, and other parts to " Run- in" and reduce the

    possibility of trouble on the future starts.

    7) During the pump and engine test all operation data should be

    control panel momentary. -Check the direction of pump rotation, any noise and vibration.

    3) Restart the raw water fire fighting pump by manual.

    4) After the fire pump is started with the engine satisfactory, adjust

    the pump discharge pressure, if necessary. And check any

    abnormal conditions.

    - re wa er r ng ea er va ves .

    e. Open pump discharge valve AA004going to flow meter CF701

    2) Start the raw water fire pump by manual at diesel engine

    5) Check complete pump and engine for leaks, loose connection

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commission ing Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    19/39

    3

    Note: Check hydrostatic test of all fire water ring main and

    SYSTEM FLUSHING AND SYSTEM FILL-UP WATER

    4) Take the pump discharge pressure gage reading.

    5) Stop the raw water fire pump manual after reading the pump discharge flow.

    TITLE: COMMISSIONING CHECK LIST

    SYSTEM : FIRE FIGHTING SYSTEM

    NO. JOB DESCRIPTION REMARKS

    : RAW WATER FIRE PUMPEQUIPMENT

    2) Start the raw water fire pump by manual at local and

    purge the flow meter CF701.

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commission ing Procedure

    ranc es ne a een comp e e .

    - Open the valve of outdoor hydrants one by one until clean water

    comes out

    - All post indicator valves located in underground.

    - Isolating valve of indoor water hydrants.2) Execute the flushing after confirming that all water system has

    been filled up with water.

    a. Outdoor hydrants

    1) Perparation ( Check the follows valve are closed)

    a. Fill the system with raw water as follows. - inlet valve of all outdoor hydrants.

    - inlet valve of all in/ outdoor deluge valves for water spray

    - Isolating valve of all indoor water and foam/water hydrants.

    b. Check the following valves are opened.

    system.

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commission ing Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    20/39

    SYSTEM

    EQUIPMENT : DELUGE VALVE

    1

    TITLE: COMMISSIONING CHECK LIST

    : WATER SPRAY SYSTEM

    REMARKS

    1) Manual Test for Transformers

    a. Select the trasformer to be tested.

    TEST OPERATION OF DELUGE VALVE

    The actual test of deluge valve will be limited to the outdoor

    transformer except for the cable Cellar area in Electrical Control

    building and LFO Storage tank.

    NO. JOB DESCRIPTION

    b. Check the system pressure is maintained at 8.45 bar

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commission ing Procedure

    f. Close the manual valve of manual emergency station on the deluge valve.

    g. Observe the deluge valve is closed and the alarm on the fire

    alarm control panel is " OFF".

    h. Test all deluge valves for transformer as per the above test

    procedure one by one If possible

    on deluge valve to be checked.

    d. Check the following

    a) Pressure switch is closed and zone lamp of fire alarm control panel is on.

    b) Buzzer of control panel make sound.

    c) Deluge valve is opened

    d) Water discharge to transformer

    e. Check the system pressure is maintaine by the fire water

    pumps.

    c. pen e manua va ve o manua emergency s a on on

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commission ing Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    21/39

    SYSTEM

    EQUIPMENT : DELUGE VALVE

    TITLE: COMMISSIONING CHECK LIST

    : WATER SPRAY SYSTEM

    NO. JOB DESCRIPTION REMARKS

    d. Check the followings

    a) Solenoid/ actuator valve is opened.

    b) Pressure switch is closed and zone lamp of fire alarm

    control panel is on.

    d) Deluge valve is opened

    - Water discharge to transformer

    e. Reset the fire alarm on the fire alarm control panel and

    c) buzzer of control panel makes sound.

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commission ing Procedure

    2

    DATE:

    c ec e so eno ac ua or va ve s c ose an en e uge

    valve is closed.

    Test the deluge valves for all transformer as per the abovetest procedure one by one. If possible.

    THE ABOVE SUBJECT IN THIS SHEET HAS BEEN CERTIFIED

    BY BELOW AUTHOURITIES.

    PREPARED BY:

    HDEC/ VENDOR

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commission ing Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    22/39

    8. TEST AND COMMISSIONING SCHEDULE

    The actual test date will be informed to GECOL engineer in advance before testbased on the attached commissioning schedule.

    9. APPENDIX

    1) P & I Diagram

    142007-SR00-M-1089 Fire protection System

    142007-SR00-M-003 Water spray system

    142007-SR00-M-FFS-005 Water cooling/ foam system

    142007-SR00-M-1059 Flow diagram fire detection system

    142007-SR00-M-1207 Fire pump house system GeneralArrangement

    2) Wiring diagram

    Later Fire pump controller

    Later Fire pump diesel engine

    3) General Arrangement drawing

    EE44724/01 El t i d i t fi

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    23/39

  • 7/25/2019 Fire Protection Commissioning Procedure

    24/39

  • 7/25/2019 Fire Protection Commissioning Procedure

    25/39

  • 7/25/2019 Fire Protection Commissioning Procedure

    26/39

  • 7/25/2019 Fire Protection Commissioning Procedure

    27/39

  • 7/25/2019 Fire Protection Commissioning Procedure

    28/39

  • 7/25/2019 Fire Protection Commissioning Procedure

    29/39

  • 7/25/2019 Fire Protection Commissioning Procedure

    30/39

  • 7/25/2019 Fire Protection Commissioning Procedure

    31/39

  • 7/25/2019 Fire Protection Commissioning Procedure

    32/39

    Customer : Silvani Antincendi spa

  • 7/25/2019 Fire Protection Commissioning Procedure

    33/39

    Libia - HDCEProject :

    Quote Ref. : SC 080527 Date : 26 May 2008

    Via Bancora e Rimoldi, 4722070 Guanzate (CO)

    Page No : 1

    Type: Horizontal Thru-Stream (FM and/or UL) - Axial Split Case

    Pump Model:

    Pump Op. Speed: 2950 RPM, 50 Hz Electric

    SPP - TD20E

    Impeller Dia.: 314.4 mm

    Impeller No.:

    Curve No.: TD20E-C2950/2G-A1 Viscosity: 1.01

    998.2

    20 C

    WaterLiquid:

    Temperature:

    Density:

    cSt

    Item : Electric pump

    Market : FM/UL/ULC Listed Fire Pump

    Your Ref. :

    kg/m

    Rated Flow

    Rated Head

    Imp. Dia.

    Rated Power Required

    Rated NPSH Required

    568.1

    100

    314.4

    199.5

    4.7

    m/h

    m

    mm

    kW

    m

    Flow at 150%

    mHead at 150

    Power Req. at 150%NPSH Req. at 150%

    Peak Power

    852.2

    74.3

    m/h

    215.85.8

    216

    kWm

    kW

    Rated Efficiency 77.6 %

    Efficiency at 150% 79.9 %

    Approval FM

    1,0005000

    Power-kW200150

    100

    50

    Head-m

    150

    100

    50

    D6

    D1

    D1-340.0 mm, D6-240.0 mm

    NPSH

    -m 8

    6

    4

    2

    NFPA Limits:

    140% Head at shutoff 140 m

    65% Head at 150%flow

    65 m

    CommentsNPSH REQUIRED at centreline ofimpeller. Add 0.5m to LaboratoryNPSH curve for field applications

    Closed Valve Pressure 126.6 m

  • 7/25/2019 Fire Protection Commissioning Procedure

    34/39

    Customer : Silvani Antincendi spaVia Bancora e Rimoldi 47

  • 7/25/2019 Fire Protection Commissioning Procedure

    35/39

    Libia - HDCEProject :

    Quote Ref. : SC 080527 Date : 26 May 2008

    Via Bancora e Rimoldi, 4722070 Guanzate (CO)

    Page No : 2

    Type: Horizontal Thru-Stream (FM and/or UL) - Axial Split Case

    Pump Model:

    Pump Op. Speed: 2350 RPM, Diesel

    SPP - TE20D

    Impeller Dia.: 364.6 mm

    Impeller No.:

    Curve No.: TE20D-C2350 /1S-A1 Viscosity: 1.01998.2

    20 C

    WaterLiquid:

    Temperature:

    Density:cSt

    Item : Diesel pump

    Market : FM/UL/ULC Listed Fire Pump

    Your Ref. :

    kg/m

    Rated Flow

    Rated Head

    Imp. Dia.

    Rated Power Required

    Rated NPSH Required

    568.1

    100

    364.6

    204.4

    4.1

    m/h

    m

    mm

    kW

    m

    Flow at 150%

    mHead at 150

    Power Req. at 150%NPSH Req. at 150%

    Peak Power

    852.2

    83

    m/h

    2315.1

    236.3

    kWm

    kW

    Rated Efficiency 76.1 %

    Efficiency at 150% 83.4 %

    Approval FM/UL

    1,0005000

    Power-kW

    250

    200

    150

    100

    50

    Head-m

    150

    100

    50

    D3D1

    D1-378.0 mm, D3-320.0 mm

    NPSH

    -m 6

    4

    2

    NFPA Limits:

    140% Head at shutoff 140.8 m

    65% Head at 150%flow

    65.4 m

    CommentsNPSH REQUIRED at centreline ofimpeller. Add 0.5m to LaboratoryNPSH curve for field applications

    Closed Valve Pressure 120 m

    Add 2% Cooling

  • 7/25/2019 Fire Protection Commissioning Procedure

    36/39

    DIESEL ENGINE RUNNING TEST SHEET

    Unit 10 20 30

    1 Speed rpm

    2 Lube oil pressure bar

    3 Lube oil temp. C

    4 mVibration

    5 Noise dB

    6 Fuel

    tank

    level mm

    Items

    Time(Min)

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

    7 Running

    hour hr

    Rev.

    A

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)

    TITLE: Fire Protection Commissioning Procedure

  • 7/25/2019 Fire Protection Commissioning Procedure

    37/39

    PUMP RUNNING TEST RECORD

    SYSTEM EQUIPMENT NAME

    MOTOR MAKER PUMP CAPACITY (m3/hr)

    MOTOR SPEC. (V) (KW) (A) PUMP MAKERINSUL. CLASS PUMP SPEED

    MOTOR SPEED (rpm) PUMP SERIAL NO.

    MOTOR SERIAL NO.

    INSUL.. RESISTANCE AMBIENT TEMP. (C)

    Item/

    Time

    SuctPr

    (mbar)

    Dischpr

    (bar)

    rpmVolt(V)

    Amp(A)

    BEARING TEMP. WINDING TEMP VIBRATION (1/1000mm)

    1 2 3 4 R S THORIZONTAL VERTICAL AXIAL

    1 2 3 4 1 2 3 4 1 2 3 4

    DesignValue

    BeforeStart

    :

    :

    :

    :

    :

    :

    :

    NOISE (dB)

    NOISE dB

    NOISE LEVEL ACCEPTABLE CRITERIA 85 dB

    41 2

    PUMP Y

    3

    MOTOR

  • 7/25/2019 Fire Protection Commissioning Procedure

    38/39

    PUNCH LIST

    SYSTEM:SHEET: OF

    NO. DESCRIPTION RAISED BYHYUNDAI

    RESPONSIBLE

    PERSON

    COMPLETION

    DATERELEASED BY REMARKS

  • 7/25/2019 Fire Protection Commissioning Procedure

    39/39

    SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/2007)

    FIRE PROTECTION COMMISSIONING PROCEDURE

    Duration (Days)1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

    Activities

    A. INSTALLATION CHECK1) MECHANICAL

    2) ELECTRICAL/ I&C

    B. PRE-COMMISSIONG CHECK

    1) RAW WATER FIRE PUMP

    AND DIESEL ENGINE

    2) WATER SPRAY DELUGEVALVE

    C. COMMISSIONING CHECK

    1) RAW WATER FIRE PUMP

    2) SYSTEM FLUSHING &

    SYSTEM FILL-UP WATER3) ACTUAL TEST OF DELUGEVALVE OF OUTDOORTRANSFORMER