final year project ppt - the future of pavement design
DESCRIPTION
Investigation into the use of the mechanistic empirical pavement design methodology for the design of a roadway pavement in Vergenoegen.TRANSCRIPT
UNIVERSITY OF GUYANAFaculty of Technology
Department of Civil Engineering
NAME: RIAZ ZALILREG.NO: 10/0933/0102
INTERNAL SUPERVISOR: DR. CHARLES GARRETT
TITLE
Pilot Study into the Use of Mechanistic-Empirical Design Technology for the Design of a Roadway Pavement in Vergenoegen
PRESENTATION OUTLINE Introduction Background Problem Statement Objectives Scope of project Methodology Pavement Design Approach Pavement Response Modeling Pavement Alternatives AASHTO 1993 Design AASHTO 2002 Evaluation Economic Evaluation Pavement Type Selection Pavement Structure Conclusion Recommendations
INTRODUCTION
Purpose of Access Road:1. Facilitate the movement of farmers to and from
the backlands2. Access route to arable farm lands for cultivation 3. Low volume roadwayGeometric Configuration:Length = 3 miles ( km)Width = 22 ft ( m)
BACKGROUND
The Access Road in VergenoegenLook at this road…I ain’t going deh!
BACKGROUNDLocation (6052’24.9’’N and 58021’51.30’’W)
Main Road
Access Road
Access Road
BACKGROUND
Condition (Wet Seasons)
BACKGROUND
Condition (Dry Seasons)
PROBLEM STATEMENT
The statement of problem is to design a new pavement structure for the access road in Vergenoegen that could fulfill all the traffic and environmental conditions while at the same time being an economically viable structure.
OBJECTIVES Quantify and characterize the loadings of the various
vehicles that uses the current facility Investigate and evaluate the potential of suitable pavement
alternatives for a cost effective alternative to accommodate the present and future traffic loads on the road
Evaluate the potential advantages and disadvantages of pavement alternatives
Carry out life cycle cost analysis on the various pavement alternatives to determine the most promising alternative
Design proposal of a suitable access road based on the most promising pavement alternative
LIMITATIONS
Selection is limited to the most feasible alternatives considered
Use of the AASHTO 1993 & AASHTO 2002 Guides for the Design of Pavement structures
Pavement distress is based on cracking and rutting predictions as computed from the pavement responses using the WinJULEA software
METHODOLOGY
1 Inputs
Materials
Traffic loadings
Environmental data
2 Design Alternati
ves
Layer thickness
design
3 Evaluati
on
Technical
Economical
4 Pavemen
t selection
Most feasible
alternative
5 Design Proposal
Site specific
conditions
PAVEMENT DESIGN APPROACHAASHTO 1993 Guide for the Design of Pavement Structures
AASHTO 2002 Guide for the Mechanistic-Empirical Design of Pavement Structures
PAVEMENT RESPONSE MODELING
PAVEMENT ALTERNATIVES
Alternative 1 Flexible PavementAlternative 2 Semi Rigid PavementAlternative 3 Cement Treated Pavement
AASHTO 1993 DESIGN
Design Traffic (Overall 18kips ESALs)
Graph Showing the Cumulative 18kips ESALs Over the 20 year Design Life
0 5 10 15 200
20000
40000
60000
80000
100000
120000
140000
160000
Cumulative 18kips ESAL
Time(years)
18kips ESAL
136, 584
AASHTO 1993 DESIGN
Design Traffic for 20 YearsW18 = DDxDLxW18
DD = 50% (0.5) DL = 100% (1)W18 = 136,584.6342 [18kips ESALs]
Therefore,W18 = 0.5 x 1 x 136, 584.6342 18kips ESALsW18 = 68, 293 [18kips ESAL]
AASHTO 1993 Design
Pavement Material PropertiesMaterial Function CBR (%) Modulus (psi) Structural Layer
Coefficient (Correlated from AASHTO 93 )
Hot Mix Asphalt Surface Course 400,000 @ 68F 0.43
Crusher Run Base Course 60 0.12
Cement Stabilized Material
Base Course 830,000 @ 7days 0.22
White Sand Subbase Course 6 0.06
In-Situ Soil Subgrade 2 3000
OTHER FACTORS
Design ParametersReliability, R = 75%Standard Deviation, So = 0.45Initial Serviceability, pi = 4.5Terminal Serviceability, pt = 2
DESIGN NOMOGRAPH
Required Structural Number
Design Chart for Flexible Pavements used for Estimating the Structural Number Required
LAYER THICKNESS COMPUTATION
Alternative 1 (Flexible Pavement)
Initial Structural Number 2.3
Layer Thickness Determination
Layer 1 Thickness, D1 (inch) 2
Layer 2 Thickness, D2 (inch) 6
Layer 3 Thickness, D3 (inch) 12
Final Structural Number 2.3
Asphalt Concrete
Crusher Run
Ordinary White Sand
2in
6in
12in
LAYER THICKNESS COMPUTATION
Alternative 2 (Semi Rigid Pavement)
Initial Structural Number 2.3
Layer Thickness Determination
Layer 1 Thickness, D1 (inch) 2
Layer 2 Thickness, D2 (inch) 4
Layer 3 Thickness, D3 (inch) 12
Final Structural Number 2.5
Asphalt ConcreteCement Treated
Base
Ordinary White Sand
2in
4in
12in
LAYER THICKNESS COMPUTATION
Alternative 3 (Cement Treated Pavement)
Initial Structural Number 2.3
Layer Thickness Determination
Layer 1 Thickness, D1 (inch) 1
Layer 2 Thickness, D2 (inch) 7
Layer 3 Thickness, D3 (inch) 13
Final Structural Number 2.3
Chip SealCement Treated
Base
Ordinary White Sand
1in
7in
13in
AASHTO 2002 EVALUATIONMaterial Function Resilient Modulus
(psi)Poisson’s Ratio
Hot Mix Asphalt Surface Course 400,000 0.25
Crusher Run Base Course 25,715 0.15
Cement Stabilized Material
Base Course 830,000 0.35
White Sand Subbase Course 8,182 0.3
In-Situ Soil Subgrade 3000 0.2
Note:All pavement layers were assumed to be fully bonded together at the
interfaces.
EVALUATION CRITERIATraffic Loadings
9000 lbs9,000 lbs18,000 lbs
Tire Radius = 6inches
Tire Pressure = 75psi
Fully Bonded Conditions
FLEXIBLE PAVEMENT
Bottom Up Cracking (HMA)
0 5 10 15 200
1
2
3
4
5
6
7
8
9
Bottom Up Cracking Prediction vs Time
Time (years)
% of lane area cracked
Chart Showing the % of Lane Area Cracked Over the Design Life for the Flexible Pavement as a Result of Bottom Up Cracking
FLEXIBLE PAVEMENT
Top Down (Longitudinal) Cracking (HMA)
0 5 10 15 200
1000
2000
3000
4000
5000
6000
7000
8000
Longitudional Cracking Prediction vs Time
Time (Years)
Feet/mile
Chart Showing the Length of Longitudinal Cracking of the Flexible Pavement Over the Design Life as a Result of Top Down Cracking
FLEXIBLE PAVEMENT
Rutting (Entire Pavement)
0 5 10 15 200.2
0.25
0.3
0.35
0.4
0.45
0.5
0.55
0.6
Rutting vs Time
Time(years)
Rutting (in)
Chart Indicating Total Rutting of the Flexible Pavement Over the Design Life
SEMI RIGID PAVEMENT
Bottom Up Cracking (HMA)
0 5 10 15 200
0.00005
0.0001
0.00015
0.0002
0.00025
Bottom Up Cracking vs Time
Time (years)
% of lane cracked
Chart Indicating Predicated % of Lane Area Cracked for the HMA Layer of the Semi Rigid Pavement Over the Design Life as a Result of Bottom Up
Cracking
SEMI RIGID PAVEMENT
Top Down (Longitudinal) Cracking (HMA)
0 5 10 15 200
0.005
0.01
0.015
0.02
0.025
0.03
0.035
0.04
Longitudinal Cracking Vs Time
Time (Years)
Feet/mile
Chart Indicating Predicted Longitudinal Cracking of the HMA Layer for the Semi Rigid Pavement over the Design Life as a Result of Top Down
Cracking
SEMI RIGID PAVEMENT
Rutting (HMA)
0 5 10 15 20
-0.005
2.60208521396521E-18
0.005
0.01
0.015
0.02
Rutting Vs Time
Time (years)
Rutting (in)
Chart Indicating Total Rutting in HMA Layer of the Semi Rigid Pavement Over the Design Life
SEMI RIGID PAVEMENT
Flexural Cracking (CTB)
0 5 10 15 200
200
400
600
800
1000
1200
Fatigue Cracking vs Time
Time(Years)
feet/500ft
Chart Indicating Length of Cracking at the Bottom of the Cement Treated Layer for the Semi Rigid Pavement Over the Design Life as a
Result of Fatigue Cracking
CEMENT TREATED PAVEMENT
Flexural Cracking (CTB)
0 5 10 15 20250
300
350
400
450
500
Fatigue Cracking vs Time
Time(years)
feet/500ft
Chart Indicating Length of cracks at the Bottom of the Cement Treated Layer for the Cement Treated Pavement over the Design Life as a Result
of Fatigue Cracking
ECONOMIC EVALUATIONPavement Alternatives Construction Cost/100m (G$)
Flexible Pavement 4, 601, 600
Semi Rigid Pavement 3, 153, 600
Cement Treated Pavement
1, 661, 400
Cost of Construction for Pavement Alternatives
PAVEMENT TYPE SELECTIONEvaluation
CriteriaConstruction
CostEase of
MaintenanceLife Cycle
CostFailure
potentialLoad
DistributionMoisture
SensitivityTotal
Weight 25 5 30 10 20 10 100Flexible Pavement
10 2 16 2 8 4 42
Semi Rigid Pavement
16 3 20 4 12 5 60
CTB Pavement
22 3.5 28 5 15 8 81.5
Decision Matrix for the Selection of the Most Suitable Pavement Alternative
PAVEMENT STRUCTURE
ROADWAY DESIGN
Subgrade
Shoulder
Chip Seal (1in) Cement
Treated Layer (7in)
White Sand (13in)
CONCLUSION
The pavement alternatives evaluated ranged from flexible, semi rigid to cement treated pavements
Utilization of the AASHTO 2002 Guide for the Design & Evaluation of Pavement Structures
The most viable pavement alternative is the cement treated pavement since it is the most cost effective pavement structure while optimizing the level of service to the road users
RECOMMENDATIONS
Calibration of the empirical models to local conditions to relate predicted distress to actual distress occurrence
The use of the axle load spectra concept instead of the 18kips ESAL concept
Modeling of the environmental conditions on the performance of the pavement structures (temperature & moisture)
Modeling of other distress modes such as reflective cracking
THE ENDTHANK YOU FOR LISTENING!
ANY QUESTIONS?