final report-group 1

312
PCB 4033 FIELD DEVELOPMENT PLAN GULFAKS FIELD, NORTH SEA Prepared By: GROUP 1 Ngo Nguyet Tran ID: 15769 Negar Hadian Nasr ID: 17029 Shodiq Khoirur Rofieq ID: 17019 Emadeldin Ali Mahmoud Khairy Ali ID: 14695 Aidil Yunus Bin Ismail ID: 16760 Final Report submitted to the Universiti Teknologi PETRONAS in partial fulfillment of the requirement for the Bachelor of Engineering (Hons) Petroleum Engineering MAY 2015

Upload: emad-eldin-khairy

Post on 10-Dec-2015

240 views

Category:

Documents


10 download

DESCRIPTION

Group project on economical optimization of an oil and gas field

TRANSCRIPT

Page 1: Final Report-Group 1

PCB 4033 FIELD DEVELOPMENT PLAN

GULFAKS FIELD, NORTH SEA

Prepared By: GROUP 1

Ngo Nguyet Tran ID: 15769

Negar Hadian Nasr ID: 17029

Shodiq Khoirur Rofieq ID: 17019

Emadeldin Ali Mahmoud Khairy Ali ID: 14695

Aidil Yunus Bin Ismail ID: 16760

Final Report submitted to the

Universiti Teknologi PETRONAS

in partial fulfillment of the requirement for the

Bachelor of Engineering (Hons)

Petroleum Engineering

MAY 2015

Universiti Teknologi PETRONAS

Bandar Seri Iskandar

32610 Tronoh

Perak Darul Ridzuan

Page 2: Final Report-Group 1

CERTIFICATION OF APPROVAL

GULFAKS FIELD DEVELOPMENT PROJECT REPORT

Prepared by GROUP 1

Ngo Nguyet Tran ID: 15769

Negar Hadian Nasr ID: 17029

Shodiq Khoirur Rofieq ID: 17019

Emadeldin Ali Mahmoud Khairy Ali ID: 14695

Aidil Yunus Bin Ismail ID: 16760

Final Report submitted to the

Universiti Teknologi PETRONAS

in partial fulfillment of the requirement for the

Bachelor of Engineering (Hons)

Petroleum Engineering

Approved by,

------------------------------------------------ -----------------------------------------

(MR. BERIHUN MAMO NEGASH) (DR. SYAHRIR RIDHA)

FDP II SUPERVISOR 1 FDP II SUPERVISOR 2

UNIVERSITI TEKNOLOGI PETRONAS

ii

Page 3: Final Report-Group 1

MAY 2015

CERTIFICATION OF ORIGINALITY

This is to certify that we are responsible for the work submitted in this project, that the

original work is our own except as specified in the references and acknowledgements, and

that the original work contained herein have not been undertaken or done by unspecified

sources or persons.

Ngo Nguyet Tran Negar Hadian Nasr

Shodiq Khoirur Rofieq Emadeldin Ali Mahmoud Khairy Ali

Aidil Yunus Bin Ismail

iii

Page 4: Final Report-Group 1

ACKNOWLEDGEMENT

Firstly, we would like to express our sincere gratitude to all parties who has

contributed along the process of our Final Development Plan (FDP). We also

want to take this opportunity to thank to Geoscience and Petroleum

Engineering Department for giving us opportunity to experience and

complete this project as our learning process and get more information and

knowledge about FDP.

Our sincere thanks also go to thank Universiti Teknologi PETRONAS (UTP) for giving

students an opportunity to expose ourselves in the real working project. Apart from that, it is

important to us to handle the project by ourselves which definitely encourage student to be

more independent in the future.

We would like to extend our sincerest appreciation to Mr. Berihun Mamo

Negash and Dr.Syahrir Ridha for their constant support and help, on hand

working skills and exposure to oil and gas industry throughout our project despite their

hectic schedule. We are greatful to them for sharing their technical

knowledge which has indeed helped us to complete our FDP successfully.

Heartfelt thanks to the FDP coordinator, Ms Asyraf Md Akhir, for her

dedication in arranging the briefings and seminars to enlighten us about

this project. Apart from that, we feel very much obliged for herefforts in

finding appropriate supervisors to guide us throughout this project.

Last but not least, we would also like to thank all our fellow colleagues, friends and

family for their direct/indirect support and assistance throughout the project.

FDP provides us with a good opportunity to recap and apply what we have

learnt throughout the Final Year of Petroleum Engineering Program. It

Page 5: Final Report-Group 1

provides us with a solid platform to overcome any obstacle in our future

technical endeavors.

Table of Contents

CERTIFICATION OF APPROVAL..........................................................................................................ii

CERTIFICATION OF ORIGINALITY....................................................................................................iii

ACKNOWLEDGEMENT.........................................................................................................................iv

CHAPTER 1 INTRODUCTION................................................................................................................1

1.1 Project Background..........................................................................................................................1

1.2 Problem Statement............................................................................................................................2

1.3 Objectives.........................................................................................................................................4

1.4 Scope of Study..................................................................................................................................4

CHAPTER 2 GEOLOGY AND GEOPHYSICS.......................................................................................6

2.1 Dimensional (2D) Cross Imaging.....................................................................................................6

2.2 Regional Setting...............................................................................................................................8

2.3 Hydrocarbon Petroleum System.......................................................................................................9

2.3.2 Reservoir Rock........................................................................................................................10

2.4 Depositional Environment and Facie Analysis..............................................................................12

2.4.1 Cretaceous...............................................................................................................................13

2.4.2 Tarbert.....................................................................................................................................13

2.4.3 Ness.........................................................................................................................................13

2.4.4 Etive.........................................................................................................................................14

2.5 Summary of Depositional Environment.........................................................................................14

CHAPTER 3 RESERVOIR ENGINEERING..........................................................................................15

3.1 Introduction....................................................................................................................................15

3.1.1 Objective..................................................................................................................................15

3.1.2 Data Given For Reservoir Study.............................................................................................16

3.2 Fluid Data Analysis........................................................................................................................16

3.2.1 Reservoir Pressure and Fluid Contact.....................................................................................16

3.2.2 Reservoir Fluid Studies...........................................................................................................19

3.2.3 Special Core Analysis (SCAL)................................................................................................25

Page 6: Final Report-Group 1

3.2.4 Reserves Estimation................................................................................................................30

3.3 History matching............................................................................................................................33

3.3.1 Overview.................................................................................................................................33

3.3.2 History Matching Results from the study................................................................................35

3.4 Production Forecast & Optimization..............................................................................................44

3.4.1 Base case analysis....................................................................................................................44

3.4.2 Secondary recovery.................................................................................................................48

3.4.3 Water injection........................................................................................................................48

3.4.4 Water injection timing sensitivity analysis..............................................................................53

3.5 Enhanced Oil Recovery (EOR) Plan..............................................................................................55

3.5.1 Reservoir Properties of Gullfaks Field....................................................................................55

3.5.2 EOR Screening Criteria...........................................................................................................55

3.5.3 EOR Plan.................................................................................................................................57

3.6 Reservoir Management...................................................................................................................60

3.6.1 Reservoir Management............................................................................................................61

3.6.2 Reservoir Surveillance.............................................................................................................61

CHAPTER 4 DRILLING ENGINEERING.............................................................................................64

4.1 Introduction....................................................................................................................................64

4.1.1 Problem Statement...................................................................................................................64

4.1.2 Objective..................................................................................................................................65

4.2 Drilling Rig Selection.....................................................................................................................65

4.3 Rig Location...................................................................................................................................66

4.4 Well Trajectories............................................................................................................................67

4.5 Casing Design.................................................................................................................................69

4.6 Bit Selection...................................................................................................................................73

4.6.1 Size of Bit................................................................................................................................73

4.6.2 Type of Bit...............................................................................................................................73

4.6.3 Factors affecting Bit selection.................................................................................................74

4.7 Drilling Fluid System.....................................................................................................................77

4.8 Casing Cementation........................................................................................................................79

4.9 Potential Drilling Hazard................................................................................................................82

4.10 Well Control.................................................................................................................................84

4.10.1 Kick.......................................................................................................................................84

Page 7: Final Report-Group 1

4.10.2 Kick identification.................................................................................................................85

4.11 Time and Cost Estimation............................................................................................................87

4.12 Drilling Optimization...................................................................................................................88

4.13 New Drilling Technology Consideration.....................................................................................89

4.13.1 New Drilling technologies.....................................................................................................89

4.13.2 Jet drilling..............................................................................................................................89

4.13.3 Utilization of laser technology in drilling..............................................................................92

4.13.4 Utilization of Electrical Plasma for Hard Rock Drilling.......................................................95

CHAPTER 5 PRODUCTION TECHNOLOGY......................................................................................99

5.1 Introduction....................................................................................................................................99

5.1.1 Overview.................................................................................................................................99

5.1.2 Objectives................................................................................................................................99

5.2 Completion String Design and Philosophy..................................................................................100

5.2.1 Completion Design................................................................................................................100

5.2.2 String completion..................................................................................................................101

5.2.3 Type of completion................................................................................................................102

5.2.4 Design Philosophy.................................................................................................................103

5.3 Wellhead and Christmas Tree Design..........................................................................................104

5.3.1 Wellhead................................................................................................................................105

5.3.2 Christmas Tree.......................................................................................................................106

5.4 Material Selection.........................................................................................................................109

5.5 Perforation Techniques.................................................................................................................111

5.5.1 Shaped Charged Characteristic and Performance.................................................................111

5.5.2 Spacing..................................................................................................................................113

5.5.3 Gun size.................................................................................................................................115

5.5.4 Conveyance Methods............................................................................................................115

5.5.5 Perforation Design.................................................................................................................117

5.6 Well Completion Plan..................................................................................................................118

5.6.1 Summary................................................................................................................................118

5.6.2 Well Completion Matrix........................................................................................................118

5.6.3 Proposed Completion Schematic...........................................................................................119

5.6.4 Completion String Design and Accessories..........................................................................122

5.7 Inflow/Outflow Performance Prediction......................................................................................124

Page 8: Final Report-Group 1

5.7.1 Nodal Analysis......................................................................................................................124

5.7.2 Base Case Model...................................................................................................................125

5.7.3 Water Cut Limits...................................................................................................................128

5.7.4 Tubing Selection....................................................................................................................129

5.7.5 GOR Sensitivity.....................................................................................................................132

5.8 Artificial Lift Selection.................................................................................................................133

5.8.1 Selection Criteria...................................................................................................................133

5.8.2 Gas Lift Design......................................................................................................................135

5.9 Sand Control.................................................................................................................................139

5.9.1 Sand Failure Prediction.........................................................................................................139

5.9.2 Problems Caused by Sand Flow............................................................................................140

5.9.3 Sand Control Consideration and Design...............................................................................141

5.10 Potential Production Problems...................................................................................................147

5.10.1 Formation Damage..............................................................................................................147

5.10.2 Well Stimulation..................................................................................................................150

5.10.3 Flow Assurance Issues.........................................................................................................151

5.10.4 Other Production Problems.................................................................................................160

CHAPTER 6 FACILITIES ENGINEERING.........................................................................................161

6.1 Introduction..................................................................................................................................161

6.1.1 Overview...............................................................................................................................161

6.1.2 Problem Statement and Objectives........................................................................................161

6.2 Design Basis and Philosophy.......................................................................................................162

6.2.1 Design Basis..........................................................................................................................163

6.2.2 Reservoir Data.......................................................................................................................164

6.2.3 Rig selection..........................................................................................................................165

6.2.4 Platform selection..................................................................................................................166

6.3 Development Scenario..................................................................................................................169

6.3.1 Option A – 3 Steel jacket wellhead Platform + Pipeline.......................................................170

6.3.2 Option B – 2 Subsea development platforms + 1Steel jacket wellhead platform + Pipeline171

6.3.3 Option C –1 Subsea development platform + 2 Steel jacket wellhead platforms + Pipeline172

6.3.4 Option D – 3 Steel jacket wellhead Platform + FPSO..........................................................174

6.4 Engineering Design and Planning Considerations.......................................................................176

6.4.1 Platform Design.....................................................................................................................176

Page 9: Final Report-Group 1

6.4.2 Gas Compression Requirements............................................................................................176

6.4.3 Water Injection Requirement.................................................................................................176

6.4.4 Telemetry System..................................................................................................................177

6.4.5 Corrosion Control - Production Facilities.............................................................................177

6.5 Platform Utilities and Service Facilities.......................................................................................178

6.5.1 Topside Structure...................................................................................................................178

6.5.2 Substructure...........................................................................................................................180

6.5.3 Wellhead module...................................................................................................................180

6.5.4 Separation..............................................................................................................................181

6.5.5 Metering.................................................................................................................................183

6.5.6 Well Control Panel................................................................................................................183

6.5.7 Flare system...........................................................................................................................184

6.6 Production Support Facilities.......................................................................................................185

6.6.1 Water injection......................................................................................................................185

6.6.2 Sea water Lifting and Filtering..............................................................................................185

6.6.3 Deoxygenation and Pumping.................................................................................................185

6.6.4 Gas compression facilities.....................................................................................................186

6.7 Gullfaks Pipeline System..............................................................................................................187

6.7.1 Pipeline sizing........................................................................................................................187

6.7.2 Pipeline Classification...........................................................................................................190

6.7.3 Pipeline modeling..................................................................................................................191

6.8 Operation and Maintenance Philosophy.......................................................................................192

6.8.1 Operation...............................................................................................................................192

6.8.2 Maintenance...........................................................................................................................193

6.9 Project Schedule...........................................................................................................................195

6.10 Abandonment..............................................................................................................................196

CHAPTER 7 ECONOMIC ENGINEERING.........................................................................................198

CHAPTER 8 HEALTH, SAFETY AND ENVIRONMENT.................................................................199

REFERENCES.......................................................................................................................................200

APPENDICES........................................................................................................................................202

Production Technology Appendices...................................................................................................202

Page 10: Final Report-Group 1
Page 11: Final Report-Group 1

List of Figures

Figure 1: Location of Gullfaks field in the North Sea................................................................................1Figure 2: Surface map of Base Cretaceous.................................................................................................6Figure 3: Cross section of producing exploration wells in Gulfaks Field..................................................7Figure 4: North South Cross section...........................................................................................................7Figure 5: East West Cross section..............................................................................................................8Figure 6: Regional view of Gulfaks...........................................................................................................9Figure 7: Depositional Environment and Lithology in Gullfaks..............................................................14Figure 8: Pressure Distribution for Well A10......................................................................................17Figure 9: Pressure Distribution for Well B9........................................................................................17Figure 10: Pressure Distribution for both wells..................................................................................18Figure 11: PVTi Software work Flowchart..........................................................................................20Figure 12: Constant Composition Expansion Diagram......................................................................22Figure 13: Differential Liberation Diagram........................................................................................22Figure 14: Oil-Water Relative Permeability Curves................................................................................26Figure 15: Gas-Oil Relative Permeability Curves....................................................................................26Figure 16: Water-Oil Capillary Pressure..................................................................................................27Figure 17: STOIIP and GIIP Calculation Concept...................................................................................29Figure 18: A10 Production Rate...............................................................................................................33Figure 19: A10 Bottom hole Pressure (base case)....................................................................................34Figure 20: A10 surrounding.....................................................................................................................35Figure 21: Cross Sectional View Of Reservoir........................................................................................36Figure 22: A10 Bottom Hole Pressure (case 1)........................................................................................36Figure 23: Gas Production Rate case 1.....................................................................................................37Figure 24: Match Attempt 1.....................................................................................................................38Figure 25: Match Attempt 2.....................................................................................................................39Figure 26: Match Attempt 3.....................................................................................................................40Figure 27: Water Production Rate............................................................................................................41Figure 28: Cumulative oil production for all the wells............................................................................42Figure 29: Cumulative oil production for all the wells except (C2, C3 and C4)......................................43Figure 30: Field oil production cumulative for all the 10 cases...............................................................44Figure 31: Oil production cumulative for all the 10 cases.......................................................................44Figure 32: Base case vs all the wells producing.......................................................................................45Figure 33: Natural depletion vs 5 injectors..............................................................................................47Figure 34: Natural depletion vs 3 injectors..............................................................................................47Figure 35: Natural depletion vs 4 injectors..............................................................................................48Figure 36: Natural depletion vs 2 injectors..........................................................................................48Figure 37: Natural depletion vs 1 injector................................................................................................49Figure 38: Comparison between different cases for water injection........................................................49Figure 39: Comparison between injector cases oil production.................................................................50Figure 40: Sensitivity analysis on water injection timing........................................................................51Figure 41: Natural depletion vs Optimum No. of injectors optimum injection timing case....................52

Page 12: Final Report-Group 1

Figure 42: Nitrogen Injection Process for Recovery Improvement.........................................................55Figure 43: Carbon Dioxide Reinjection Process for Recovery Improvement*........................................56Figure 44: Types of Rig............................................................................................................................63Figure 45: Location of Rig.......................................................................................................................65Figure 46: Optimum places for the two platforms used for drilling of all the wells Yellow triangle for injection wells platform and red triangle for producer wells platform.....................................................66Figure 47: Well targets coordinates and wellheads coordinates...............................................................66Figure 48 Equivalent Mudweight vs Depth..............................................................................................68Figure 49: Insert Bit..................................................................................................................................71Figure 50: Milled Tooth Bit......................................................................................................................72Figure 51: PDC bit....................................................................................................................................72Figure 52: Drilling fluid circulation system.............................................................................................75Figure 53: Wellbore Profile.....................................................................................................................79Figure 54: Depth progress vs time for drilling plan of sample well A20.................................................85Figure 55 Jet drill tool..............................................................................................................................89Figure 56: Test well layout.......................................................................................................................89Figure 57: Rock failure due to spalling....................................................................................................91Figure 58 Conditions under which laser removes rock with or without significant melting...................92Figure 59 Plasma drilling system.............................................................................................................94Figure 60: Production Tubing String......................................................................................................100Figure 61: Wellhead and Christmas tree................................................................................................103Figure 62: Corrosion Resistant Alloy Selection Process*......................................................................108Figure 63: Shaped Charged Components...............................................................................................109Figure 64: The importance of using a conical liner in a shaped.............................................................110Figure 65: Picture demonstrates the angle of the cone and the liner material determines the penetration depth and the perforation's diameter.......................................................................................................111Figure 66: Perforation Charge Arrangement..........................................................................................112Figure 67: Results of underbalanced, balanced and overbalanced perforations.....................................114Figure 68: Single String Oil Producer Tubing........................................................................................118Figure 69: Single String Water Injector Tubing.....................................................................................119Figure 70: Base Case IPR for Gullfaks Field.........................................................................................124Figure 71: Base Case Nodal Analysis....................................................................................................125Figure 72: Sensitivity analysis on tubing size for reservoir pressure 2516psia......................................128Figure 73: Oil rate at different water cut without Gas Lifted.................................................................135Figure 74: Oil rate at different water cut with Gas Lifted......................................................................135Figure 75: Oil production influenced by various gas lift injection rate..................................................136Figure 76: Potential Sand Production...................................................................................................138Figure 77: Various types of mechanical sand control method...............................................................140Figure 78: Typical sand analysis distribution.........................................................................................142Figure 79: Typical relationships between mud type, cost & risk of formation damage.........................146Figure 80: Damage area during Perforation...........................................................................................147Figure 81: Possible well design for CO2 injection (from Cooper, 2009)...............................................150Figure 82: Production forecast profile for Gullfaks Field......................................................................161Figure 83: Types of offshore drilling rigs..............................................................................................163

Page 13: Final Report-Group 1

Figure 84: Type of Oil Platform.............................................................................................................165Figure 85: Example of Steel Jacket platform.........................................................................................166Figure 86: Option A................................................................................................................................168Figure 87: Option B................................................................................................................................170Figure 88: Option C................................................................................................................................171Figure 89: Option D................................................................................................................................173Figure 90: Typical elevation view of an offshore platform....................................................................176Figure 91: Schematic of an offshore platform, illustrating the concept of modularization....................177Figure 92: Equipment arrangement plan of a typical offshore platform illustrating..............................177Figure 93: Process Flow Diagram.........................................................................................................178Figure 94: Horizontal Separator.............................................................................................................180Figure 95: Well Abandonment for Open Hole Completion*.................................................................195Figure 96: General Well Abandonment for Cased Hole........................................................................195

Page 14: Final Report-Group 1

List of Tables

Table 1: Fluid Contacts Table...............................................................................................................18Table 2: The Experiment and PVT Parameters..................................................................................20Table 3: Compositional Analysis...........................................................................................................23Table 4: Facies classification of Core Sample..........................................................................................28Table 5: STOIIP Calculation....................................................................................................................30Table 6: GIIP Calculation.........................................................................................................................30Table 7: 10 cases with their following producing wells...........................................................................43Table 8: Water injection for different cases.............................................................................................46Table 9: Ranking the injector cases..........................................................................................................50Table 10: Parameters of the Gullfaks field...............................................................................................53Table 11: Summary of screening criteria for EOR Methods....................................................................54Table 12: Reservoir Surveillance and Its Purposes [9].............................................................................60Table 13: Rig Selection............................................................................................................................64Table 14: Types of Margin.......................................................................................................................68Table 15: Casing setting depth and Mud Program...................................................................................70Table 16: Bit Selection and Bit size.........................................................................................................74Table 17: Mud Program............................................................................................................................76Table 18: Classification of Well Cement.................................................................................................77Table 19: Cement Program.......................................................................................................................78Table 20: Summary Cement calculation..................................................................................................78Table 21: Drilling Schedule......................................................................................................................85Table 22: Comparison between different borehole completion approaches............................................98Table 23: Comparison of single and dual strings completion..................................................................99Table 24: Basic Types of Xmas Tree.....................................................................................................104Table 25: Xmas Configuration...............................................................................................................105Table 26: Summary of Dry Tree vs Wet Tree*......................................................................................105Table 27: Benefits vs Challenges of Dry Tree & Wet Tree*.................................................................106Table 28: Summary of the perforation system selected.........................................................................115Table 29: Well Completion Option for Gullfaks field...........................................................................116Table 30: Well Completion Matrix for Gullfaks Field...........................................................................116Table 31: Base Case Calculated data from Prosper................................................................................125Table 32: Effect of water cut on various reservoir pressures.................................................................126Table 33: Different tubing sizes with different reservoir pressure.........................................................129Table 34: GOR values with different reservoir pressure........................................................................130Table 35: Artificial lift methods and its features....................................................................................132Table 36: Comparison on production before and after installing Gas Lift.............................................134Table 37: Screen gauge used with various types of gravel size.............................................................143Table 38: Available Stimulation Techniques.........................................................................................148Table 39: General Material Specification and Characteristic.................................................................151Table 40: General Monitoring Methods for Corrosion..........................................................................152Table 41: Comparison of two common mitigation strategies for wax deposition..................................158

Page 15: Final Report-Group 1

Table 42: Reservoir and Fluid Properties of Gullfaks Field...................................................................162Table 43: Option A.................................................................................................................................168Table 44: Option B.................................................................................................................................169Table 45: Option C.................................................................................................................................171Table 46: Option D.................................................................................................................................172Table 47: Proposed Project Schedule.....................................................................................................193

Page 16: Final Report-Group 1

CHAPTER 1 INTRODUCTION

1.1 Project Background

Gullfaks is an oil and gas field in the Norwegian sector of the North Sea operated by Statoil. It was discovered in 1978, in block 34/10, at a water depth of 130-230 meters. The initial recoverable reserve is 2.1 billion barrels (330×106 m3), and the remaining recoverable reserve in 2004 is 234 million barrels (37.2×106 m3). This oil field reached peak production in 2001 at 180,000 barrels per day (29,000 m3/d). It has satellite fields Gullfaks South, Rimfaks, Skinfaks and Gullveig.

It was formed during Upper Jurassic to Lower Cretaceous with westerly structural dip gradually decreasing towards the east. The major north to south striking faults with easterly dipping fault planes divided the field into several rotated blocks. Central and eastern parts have been eroded by the early Cretaceous transgression. The field is related to block 34/10 which is approximately 175 km northwest of Bergen and covers an area of 55 km² and occupies the eastern half of the 10-25 km wide Gullfaks fault block (Fossen and Hesthammer, 2000). The Schlumberger geological modelling software product Petrel uses the Gullfaks field as the sample data set for its introductory course.

The project consists of three production platforms Gullfaks A (1986), Gullfaks B (1988), and Gullfaks C (1989). Gullfaks C sits 217 metres (712 ft) below the waterline. The height of the total structure measured from the sea floor is 380 metres (1,250 ft), making it taller than the Eiffel Tower. Gullfaks C produces 250,000 barrels per day (40,000 m3/d) of oil. The Tordis field, which is located 11 km south east of Gullfaks C, has a subsea separation manifold installed in 2007 which is tied-back to the existing Gullfaks infrastructure.

Figure 1: Location of Gullfaks field in the North Sea

1

Page 17: Final Report-Group 1

Between November 2009 and May 2010 a well being drilled from Gullfaks C experienced

multiple well control incidents which were investigated by the Norwegian Petroleum Safety

Authority and summarized in a report released on 19 November 2010. The report stated that

only chance prevented the final and most serious incident on 19 May 2010 from becoming a

full-scale disaster.

Conditions have now changed from alluvial to the basin conditions which can be steady (e.g. a

lake) or can be dominated by waves and tidal motion in an oceanographic setting. In any case

the sediments can be redistributed and reworked by basinal processes such as coastal current

drift, long shore drift, storms, waves and tidal currents. The balance between the alluvial input

and the basin conditions determines the shape of the coastline and controls the delta evolution.

As the delta builds out in geological timescales is related to the sediment input and the

accommodation space, the stages are described relative to the amount of sediment increase or

decrease and the amount of sea level rise or fall.

Basically in this project the Gullfaks field is subdivided into 4 major stratigraphic units, which

are the Cretaceous, Tarbert, Ness and Etive formations. This petroleum system is a sequence

of sandstones, siltstones, shales and coals with maximum thickness of 300-400 m. The

Broom and Oseberg formations may represent early lateral infill of the basin whereas the

remaining formations comprise a major regressive (Ness and Etive formations) to transgressive

(Tarbert and Ness formations) clastic wedge (Helland-Hansen et al, 1992).

1.2 Problem Statement

As mentioned earlier Gulfaks field project has developed in three main stages or production

platforms: Gulfaks A, where is built in 1986, then followed by Gulfaks B, where is built in

1988 and finally Gulfaks C, where is built in 1989. The field was discovered and then starts the

production at 1978 and 1986, respectively.

Volumetric estimation is required at all stages of the field life cycle. In many instances,

a first estimate of how big an accumulation could be requested. At the very first stage or if the

2

Page 18: Final Report-Group 1

data available is very sparse, a quick look estimation can be made using field-wide averages.

These approaches of estimation are applied here by using the Material Balance Techniques.

The field development project (FDP) report should cover all aspects of field

development which are as following:

Phase I: Geology & Geophysics and Petrophysics

Phase II: Reservoir Engineering

Phase III: Drilling Engineering, Production Technology and Facilities Engineering

Phase IV: Project Economics

Phase V: Sustainable Development and Health, Safety, & Environment

As of now, we are doing the Geology & Geophysics and Petrophysics part which is the

Phase I of the field development project.

Dataset for Gullfaks field are given which includes:

Well log data

Well deviation survey

Surface contour map

Well marker depth

Core data

PVT fluid data

MDT data

Well test data

Seismic data were not provided as part of the data acquisition. This will be one the cause of

uncertainties especially in geology development phase as seismic control is important in

interpreting important structural features.

3

Page 19: Final Report-Group 1

1.3 Objectives

The objectives of the Gullfaks Field Design Project are to think deeply on how to develop and

improve the field performance. Through understanding the geological characteristic and

reservoir characteristic, the complexity distribution of oil and gas in the reservoir can be

overcame. Optimization the field performance, applying economics and environmental

elements are considered in the project. The objectives in formulating the best, possible FDP

will include the following:

a) Maximizing economic return

b) Maximizing recoverable hydrocarbons

c) Maximizing hydrocarbon production

d) Compliance with health, safety and environment requirements

e) Providing recommendations in reducing risks and uncertainties

f) Providing sustainable development options

The ultimate goal to come up with in this project is to maximize the return to operator within

the stipulated schedule. This goal must be achieved within technically and economically

viable development plan. The processes and development stages mentioned must be fulfill

with very focusing on the goal and follow the step of the development.

1.4 Scope of Study

The general scope of works for the Gullfaks FDP is:

1. To develop the 3D static model of Gullfaks Field using:

PETREL software

Manual method

2. Perform volumetric calculation for Gulfaks oil field:

STOIIP and GIIP, reserve estimation (proven, probable & possible)

4

Page 20: Final Report-Group 1

Parameters: Gross rock volume, Net to Gross, porosity, Swc, oil and gas formation

volume factors, and fluid contacts.

3. To determine the Gross Rock Volume, Net to Gross (NTG), porosity and

saturation distribution profile, types of fluids and their contacts, Stock Tank Oil

Initially in Place (STOIIP) and Gas Initially in Place (GIIP).

4. To develop the 3D static model of Gullfaks Field using PETREL software.

5. To prepare a dynamic model from the 3D static model and perform

simulation to achieve the highest recovery factor (RF) and economic return of the

field.

6. To prepare well completion and production facilities design and propose a drilling

program.

7. To propose the most feasible and economical facilities in all the stages of

development.

8. To perform economic evaluation and sensitivity analysis for all development stages

and options.

9. To ensure the FDP is in compliance with national regulation and HSE

requirements.

5

Page 21: Final Report-Group 1

CHAPTER 2 GEOLOGY AND GEOPHYSICS

2.1 Dimensional (2D) Cross Imaging

Surface map are maps given with contour lines drawn on it to indicate the depth of a particular area. Contour lines connect all the points on a plane that has equivalent depth. There are foursurfaces in Gulfaks field given in this project called, Base Cretaceous, Top Tarbert, Top Ness and Top Etive. Figure 2 shows one of the surface maps with contour lines that is being provided for this project:

Figure 2: Surface map of Base Cretaceous

6

Page 22: Final Report-Group 1

Here, the 2D cross section shows the intersection of most producing exploration wells in

Gulfaks field. Based on this cross section, it can be seen that there is a fault represent by the

arrow and also anticline which generally referred to hydrocarbon reservoir trap.

Figure 4: North South Cross section

7

Figure 3: Cross section of producing exploration wells in Gulfaks Field.

Page 23: Final Report-Group 1

Figure 5: East West Cross section

2.2 Regional Setting

Gullfaks field is located in the Norwegian sector of the northern North Sea along the western

flank of the Viking Graben. Gullfaks represents the shallowest structural element of the

Tampen spur. The field is related to block 34/10 which is approximately 175 km northwest of

Bergen and covers an area of 55 km2 and occupies the eastern half of the 10-25 km wide

Gullfaks fault block (Fossen and Hesthammer, 2000).

8

Page 24: Final Report-Group 1

Figure 6: Regional view of Gulfaks

2.3 Hydrocarbon Petroleum System

Understanding petroleum system in Gullfaks field is imperative to determine how the

hydrocarbon is produced and migrated into the reservoir trap. For this section, petroleum

system description is based on literature review as seismic data are not given in this project.

2.3.1 Source Rock

9

Page 25: Final Report-Group 1

The two main source rocks in this field are the oil-prone Draupne formation and gas-prone

Heather formation.

2.3.1.1 Draupne FormationThe Draupne formation is the main shale rock that forms the hydrocarbon source in this field.

Its physical characteristics include brownish black, medium to dark olive grey, non-

calcareous mudstones, which are locally silty and micaeous (Kubala et al, 2003). The

thickness of this formation is typically 50 – 250m, but may exceed 1200 m in localized area.

Immature organic materials in Draupne formation consist mostly of Type II kerogen

(William and Douglas, 1980) and are considered as highly prospective oil generating source

rock (Goff, 1983).

2.3.1.2 Heather FormationHeather formation is made up of dark grey silty mudstones with intermittent thin carbonate

layers. Thickness of this formation ranges up to 1000 m (Kubala et al, 2003) and it is typically

gas prone but studies by Gormly et al (1994). Total Organic Carbon (TOC) values are typically

between 2-2.5 % (Goff, 1983). The coal layers within the Ness formation of the Middle

Jurassic Brent Group are also categorized as main source rocks for gas generation in this

formation (Chung et al, 1995).

2.3.2 Reservoir Rock

2.3.2.1 Triassic and Lower Jurassic

The Triassic reservoir can usually be seen in tilted fault blocks with the variety properties of

Jurassic Cretaceous erosion and onlap. In North specifically at northern area will have most of

Triassic reservoir except of Snorre field. Snorre field have the accumulation of overlapping of

Lower and Middle Jurassic reservoir (Goldsmith et al, 2003). The reservoir units are

sandstones of early and middle Jurassic age, around 2000m subsea and measure several

hundred meters thick. Reservoir quality is generally very high, with permeability ranging from

few tens of mD to several Darcys depending on layer and location.

The properties of main reservoir intervals have thick fluvial channel and sheet flood deposits.

The characteristics of these reservoirs imitate deposition in terrestrial and semi-arid conditions

10

Page 26: Final Report-Group 1

although the younger Statfjord formation has marginal marine influence increment. Reservoir

quality is both a function of the initial depositional facies with the more distal, matured and

cleaner sands having higher initial and ultimate porosities (Goldsmith et al, 2003). The

Statfjord formation is the most important hydrocarbon bearing reservoir in the category.

2.3.2.2 Middle Jurassic

Most of the Middle Jurassic reservoirs in the northern North Sea are arkoses and subarkoses

with quartz, clay minerals and feldspars constituting about 95% of the total mineralogy

(Humso et al, 2002). These sandstones are both quartz and calcite cemented at depths

exceeding 2500 m (Walderhaug and BjØrkum, 1992). The reservoirs form a thick clastic

wedge comprising laterally extensive interconnected fluvial, deltaic and coastal depositional

systems with porosities and permeabilities ranging from 20-30% and 50-500 mD respectively

at shallow depths (Giles et al, 1992).

In the northern North Sea, the Middle Jurassic reservoirs are represented by the Brent Group,

which comprises the Tarbert (youngest), Ness, Etive, Rannoch and Broom formations (Vollset

and Dore, 1984). The basal Brent is typically upper shoreface sandstones whiles the upper part

of the group is represented by transgressive sandstones (Gautier, 2005).

2.3.2.3 Upper Jurassic

Up to 100m of Upper Jurassic shales (Heather Formation) are locally preserved in the

hanging walls to the main faults in the Gullfkas Field, particularly in the western part.

2.3.3 Traps and Seals

There are present of traps and seals in the North Sea especially at Gulfaks field itself. That’s

where many accumulated places have stored the hydrocarbon. This trapping are likely happen

because of tectonic movement of the formation plate and hence fault is formed which have

sealed by fine grains (Gautier, 2005). As example, Viking graben have hydrocarbon trapped in

11

Page 27: Final Report-Group 1

lateral trapping and sealed. The reservoir rocks are juxtaposed by non-reservoir rocks at faults

contacts (Gautier, 2005).

2.4 Depositional Environment and Facie Analysis

The location where particular sediments are deposited is known as depositional environment.

The depositional environment is essential to understand various physical, chemical and

biological processes associated with the deposition of particular type of sediments and

also their lithification through cementing and compaction.

The Gullfaks field occupies the eastern half of a major, 10-25 km-wide, north-northeast-

trending fault and is bounded by faults with kilometer-scale offsets. The sand reservoir

formation of the Gullfaks Field forms a subordinate, but extremely heterogeneous, reservoir in

the Gullfaks field.

The reservoir is divided into three main units, but only the upper unit contains

significant producible hydrocarbons. This reservoir was deposited in a tide-dominated deltaic

setting and it is characterized by a significant proportion of heterolithic facies (mm/cm-

scale sand-shale laminations). The individual sand laminae within reservoir heterolithic

facies are fine- to medium-grained with a porosity range of 25-40 % and a horizontal

permeability range of 10-2000 mD. However, total effective permeability within this

unit is strongly influenced by the sand-shale ratios of the heterolithic facies and by the

lateral extent of individual day laminae.

It is known that Middle Jurassic deposits of the reservoirs in Gullfaks field are shown

by the deltaic sediments with deposition strongly affected by regressive/transgressive

cycles and happened during the late phase of post-rift subsidence following the Late

Permian/Early Triassic rifting (Ryseth, 2000). The thickness of this formation is from ongoing

faulting due to tectonic movement of the plate and thermally driven subsidence.

The most of oil in the Gullfaks field is found by the Brent group formation. The Brent group

consists of four main stratigraphic formations there are Cretaceous, Etive, Ness and Tarbert.

The depositional environment of each stratigraphic formation is different so it is caused

12

Page 28: Final Report-Group 1

to difference in reservoir characteristic. For overall, the Brent group formation consists of

sandstone, shale and siltstone and depositional environment is a delta system and has a very

good reservoir. The oil recovery factor in this formation is 60 % (Statoil Hydro, 2007).

2.4.1 Cretaceous

Newest pattern of plate rifting and erosion of uplifted fault parts in the late Jurassic and early

Cretaceous was followed by a major rise in sea level across the Gullfaks formation. This result

in Cretaceous sediments deposited in uncertainty on late Jurassic sediment of the North Sea

and later called as Base Cretaceous Unconformity (BCU).

In North Sea, specifically at northern part the Lower Cretaceous deposits comprise shallow

marine mudstone, calcareous shale and mixed ratio of sand. In Late Cretaceous, the sea level

maintained to be at peak and the clastic sedimentation is decreased where this then dominated

by planktonic carbonate algae. However, in area of Viking graben, the carbonates are not pure

and have been replaced by marls. The Upper Cretaceous contain mudstones and minor

imbedded of limestone of the Shetland Group (Surlyk et al, 2003).

2.4.2 Tarbert

Tarbert formation is located at the upper of Brent group and it is the youngest

formation. The thickness of this formation is around 75 to 105 m and the range of

permeability is 300 to 10000 md. Sediment structures and typical features in this formation

comprises of medium fine grained cross stratified sandstone, coarcenning upwards sequences

in lower part containing shale and coal beds and bioturbated. The depositional environment

this part is progradational sequence in an overall retreating/transgressive part of the

delta. Furthermore, reservoir characteristic of this formation is very good reservoir

quality, very good lateral continuity and poor sand strength (Tollefsen et al., 1992). The total

oil reserve and oil recovery factor in Tarbert is 135 MSm^3.

13

Page 29: Final Report-Group 1

2.4.3 Ness

Ness formation is located at the upper of Brent group same as Tarbert formation. The thickness

of this formation is around 85 to 115 m and the range of permeability is 200 to 6000

md. Sediment structures and typical features in this formation consists of sandstone

units comprise minor mouth bars, thin sand bodies and bioturbated. The depositional

environment this part is delta top and fluvial marginal marine. Moreover, reservoir

characteristic of this formation is very poor reservoir quality, poor continuity of sand

and moderated poor sand strength (Tollefsen et al., 1992). It is a heterogeneous formation with

a lot of fault present and it is leading to complex communication pattern internally and with

other formation, so it makes a poor reservoir quality. The total oil reserve and oil recovery

factor in Ness is 46 MSm^3.

2.4.4 EtiveEtive is located at the lower of Brent group. The thickness of Etive formation is around 15

to 40 m and the range of permeability is 2000 to 7000 md. Sediment structures and

typical features in this formation consist of medium coarse grained massive cross- stratified

sandstones. The depositional environment this part is foreshore and beach. In additional,

reservoir characteristic of this formation is very good reservoir quality, very good lateral

continuity and poor sand strength (Tollefsen et al., 1992).

2.5 Summary of Depositional Environment

Depositional environment of Gullfaks field can be summarized as shown subsequently

14

Page 30: Final Report-Group 1

CHAPTER 3 RESERVOIR ENGINEERING

3.1 Introduction

The purpose of Reservoir engineering is to make a comprehensive study of the recovery

mechanism of the reservoir and its production forecast. Reservoir engineering phase includes

the analysis of PVT data, separator test, well test results and others. Moreover, the history

matching of reservoir properties associated with the given build-up and drawdown test of well

A10 was performed. The data histories including bottom hole pressure, gas rate, water rate and

oil rate were recorded for A10 well for duration of 16 days, from 1-July-2013 until 16-July-

2013.

This chapter will also discuss the recovery mechanism of the reservoir and reservoir

management system. The number of wells and well placement location could be

determined from the analysis of the available data.

3.1.1 Objective

The main objectives of Reservoir engineering part is the investigation and analysis of the

following items to:

Analyze reservoir data and properties based on PVT and well test data.

To history match bottom hole pressure, gas rate, water rate and oil rate of well A10

from observed data and Petrel model.

Estimate cumulative production based on drive mechanisms used.

Forecast production profile.

Propose a development plan for the reservoir based on the number of wells, type of

completion and well placement.

Suggest a reservoir management plan for enhancing the recovery and optimize

reservoir performance.

15

Page 31: Final Report-Group 1

3.1.2 Data Given For Reservoir Study

Well RFT and Historical Production Report – Singlerate

Well RFT and Historical Production Report – Multirate

3.2 Fluid Data Analysis

3.2.1 Reservoir Pressure and Fluid Contact

In this study, Reservoir Data start with recognizing the contacts within the wells. This sets of

data called water-oil contact (WOC) and gas-oil contact (GOC) is essential for reservoir

management and reservoir optimization plan in future. GOC is defined as the transitional

contact which separates the gas phase and oil phase in the particular reservoir and thus forming

a zone containing mixtures of gas and oil. Since the gas is lighter in term of density as

compared to oil, this give a result where the gas to be accumulated above the contact while the

oil is located below the contact. In the other hand, WOC is defined as the contact that separate

between oil and water in a reservoir. Water phase is found below the contact as it is denser than

the water phase.

Well A10 and Well B9 are the wildcat wells in the Gulfaks reservoir and these wells were

drilled in order to test the potential of hydrocarbon in the reservoir. From the graphs below, the

GOC and WOC is determined from the sudden change of the characteristic of the pressure

gradient.

Specifically in the project, the fluid contacts are only determined through the Formation-tester

pressure surveys due to the limitation of the availability data. Since the MDT Formation

Pressure Data Report for Well A10 and Well B9 are given, GOC and WOC for this reservoir

will be identified by plotting the data. In general, pressure gradient of gas is likely around

0.10psi/ft, oil is from 0.25 to 0.35psi/ft whereas for water is from 0.40 to 0.55psi/ft.

16

Page 32: Final Report-Group 1

Figure 8: Pressure Distribution for Well A10

Figure 9: Pressure Distribution for Well B9

17

Page 33: Final Report-Group 1

Figure 10: Pressure Distribution for both wells

Data from both wells were combined into one plot (above) to identify the major fluid gradients.

It can be seen that there are 2 shifts in the pressure gradient, hence 3 straight lines. 3 lines of

best fit were plotted and their formulas were found. Obtaining of the contacts would require

solving the simultaneous equations. The two plots above show the plots of data from each well

separately. Consequently, the lines of best fit differ when data from each well is considered

alone. The results are shown below:

Table 1: Fluid Contacts Table

RESULTSGOC WOC

TVD (m) P (bar) TVD (m) P (bar)Well A10 Only 1701.370 167.927Well B9 Only 1891.000 178.706Both Wells 1700.670 167.925 1891.810 178.773AVERAGE 1701.020 167.926 1891.405 178.740

18

Page 34: Final Report-Group 1

3.2.2 Reservoir Fluid Studies

PVT analysis of reservoir fluid samples provides an important input for reservoir numerical

modeling. A set of Gulfaks field oil and gas separator samples were collected. The fluid

properties need to be known over a wide range of temperatures and pressures.

However, we are also unable to measure directly all the things we need to know about the

hydrocarbons. Hence, the fluid is modelled mathematically by matching equations of state

(EOS) to the fluid properties obtained from lab experiments and field measurements. The

matched equation of state can then be used to generate the fluid’s PVT data at various ranges

of pressure and temperature and this data can then be used as input for computational

simulation of fluid flow in the reservoir.

During the part of building the base fluid model, Equation of State should

be chosen. Experimental analysis gives the most accurate result in predicting the

characteristic of the fluid, but the major setback is this method requires a long time to conduct

the experiment and sample should be required from the reservoir. The condition of the sample

also will affect the accuracy of the experiments. The second method which is using the

Equation of State is more towards analytical method which saves time and does not require

sample of the reservoir fluid to conduct the experiments. The accuracy of this analytical

method depends greatly on the Equation of State used. Equation of State is merely an

equation relating pressure, temperature, volume and composition. Equation of State provides

reliable volumetric data over the used equation.

In PVT analysis, there are various experiments could be conducted to get the PVT parameter.

Using PVTi, we could also simulate these experiments to produce the same PVT analysis. The

experiments and PVT parameters and PVTi Sofware Workflow Chart are illustrated in the

table and figure below.

19

Page 35: Final Report-Group 1

Table 2: The Experiment and PVT Parameters

Bubble Point Test Constant Composition

Expansion Test (CCE)

Differential Liberation

Test

(DLL)

Saturation Pressure

Liquid density

Relative Volume Liquid Viscosity

Vapor Viscosity

Gas Oil Ratio

Gas Formation Volume

Factor.

20

Input the composition of Hydrocarbon into the pvti software and build the base fluid model.

Input the expremintal given data.

Apply different equation of state (EOS) which give best matching with given expremintal data.

Perform regression upon the fluid model.

Select the fluid model with least errors between the observed and calculated data.

Tabulate the results of other PVT parameter which not given.

Page 36: Final Report-Group 1

Figure 11: PVTi Software work Flowchart

The available data from the fluid study report (DST#1) contains details of three experiments; a

Constant Composition Expansion (CCE) experiment, a Differential Liberation (DL)

experiment and a Bubble Point experiment. Used for all three experiments is a PVT cell, which

is a vessel whose internal volume is known under a wide range of temperatures and pressures,

and can be maintained in a constant (adjustable) temperature environment. The cell is

equipped with a high-pressure window through which you can see (and measure) any liquids

present. Pressure and volume changes are effected by introducing or withdrawing mercury

under pressure directly at the base of the cell, or above a floating piston that forms the “roof”

of the cell. Ports exists for the charging and withdrawal of fluids during the experiments.

Initially the cell is charged with a mixture that we believe represents the reservoir composition.

The cell is then left to attain equilibrium at the desired temperature and pressure, some cells

having the ability to agitate the contents to help achieve this more rapidly.

21

Page 37: Final Report-Group 1

3.2.2.1 Constant Composition Expansion (CCE) experiment

Starting at a pressure above reservoir pressure, the cell pressure is gradually reduced, and the

expanding volume measured. While the mixture remains above the dew point, the Z-factors

can be calculated directly, as the number of moles in the cell will be known from the charging

measurements. Several pressure traverses will be made in order to define the dew point as

accurately as possible. As the pressure is reduced below the dew point, the condensed liquid

volume is measured and reported as a function of the cell volume at the dew point. This

measurement is all that can be obtained from the experiment once the dew point is crossed, as

the number of moles in the liquid, and its composition are unknown. However, it is an

important set of experimental data for fluid modelling. The ultimate result obtained from this

experiment is the oil’s bubble point pressure, which is at 2516.7 psia.

Figure 12: Constant Composition Expansion Diagram

3.2.2.2 Differential Liberation (DL) experiment

The Differential Liberation experiment is usually only performed on nonvolatile oils. Most

crude oils analysed by this experiment generally report the so-called black oil properties of

gasoil ratio, Rs, oil formation volume factor, Bo and gas formation volume factor Bg which is

22

Page 38: Final Report-Group 1

sufficient for inclusion in most simulators with black oil PVT treatments, such as ECLIPSE

100. Black oil properties of crudes (and volatile fluids using an extended black oil treatment,

including a vaporising oil term Rv, the condensate-gas ratio) can be generated from a

compositional description via an Equation of State and the simulation of suitable experiments.

Figure 13: Differential Liberation Diagram

The data obtained from this experiment include:

Oil Formation volume factor: 1.1 bbl/stb

Solution Gas Oil Ratio: 1.1342 scf/stb

Oil Density : 45.11 lb/ft3

3.2.2.3 Compositional Analysis

Detail hydrocarbon compositions from C1 to C7+ were obtained. The compositions of

separator oil, separator gas and calculated wellstream are tabulated as follows.

Table 3: Compositional Analysis

Component

Mole%, Yi MW yi*MW Tcri, R yi*Tcri, R

Pcri, psia

yi*Pcri, psia

23

Page 39: Final Report-Group 1

CO2 1.49 0.0149 44.0100 0.656 547.91 8.164 1071 15.958N2 0.27 0.0027 28.0100 0.076 227.49 0.614 493.1 1.331C1 60.66 0.6066 16.0430 9.732 343.33 208.264 666.4 404.238C2 15.32 0.1532 30.0700 4.607 549.92 84.248 706.5 108.236C3 10.14 0.1014 44.0970 4.471 666.06 67.538 616 62.462IC4 1.88 0.0188 58.1230 1.093 734.46 13.808 527.9 9.925NC4 4.82 0.0482 58.1230 2.802 765.62 36.903 550.6 26.539IC5 1.43 0.0143 72.1500 1.032 829.1 11.856 490.4 7.013NC5 1.30 0.0130 72.1500 0.938 845.8 10.995 488.6 6.352C6 2.59 0.0259 86.1770 2.232 1113.6 28.842 436.9 11.316C7+ 0.09 0.0009 218.0000 0.196 1350 1.215 255 0.230SUM 100 1 27.83 472.45 653.6

3.2.2.4 PVT Result (Summary)

The following is the summary of the results obtained from the PVT analysis:

Reported Reservoir Conditions

Reservoir Pressure: 2516 psia

Reservoir Temperature: 220 °F

Constant Composition Expansion

Bubble-point Pressure: 2516.7 psia

Differential Liberation Test

Oil Formation Volume Factor: 1.1 bbl/STB

Solution Gas-Oil Ratio: 1.1342 Mscf/STB

Oil Density: 45.11 lb/ft3

24

Page 40: Final Report-Group 1

Reservoir Fluid Viscosity

Oil Viscosity: 1.33 cp

25

Page 41: Final Report-Group 1

3.2.3 Special Core Analysis (SCAL)

In the Special Core Analysis (SCAL) report, there are a total of three (3) core samples from a

single well in Gulfaks field which were taken at depth intervals of 1794-1796m, 1824-1827m

and 1903-1905m respectively. The reservoir condition is reported at reservoir pressure of 2516

psia and reservoir temperature of 220 deg F. Moreover, no Routine Core Analysis (RCAL)

report available for this project. Core samples which were used for lab measurements to obtain

different rock properties (relative permeability, capillary pressure) are discussed in the

following sections.

3.2.3.1 Capillary pressure and J-function

The capillary pressures data obtained from SCAL analysis studies is plotted into Capillary

Pressure curve and were used to derive J-function to develop initial water saturation

distribution in the reservoir according to the sand facies. Capillary pressure is the difference in

pressure across the interface between two immiscible fluids, it’s a function a saturation and

saturation history (drainage or imbibition) for a given reservoir rock and fluids at a constant

temperature. The role of capillary pressure curves in the initial oil distribution lies in estimation

of the saturation of fluids in transition zones. Depending on the facies type, the pore size

distribution is different, which implies a difference of residual water saturation and residual gas

saturation. A poor reservoir rock will demonstrate higher connate water saturation and longer

transition zone as compared to a good reservoir rock.

From the graph below, the capillary pressure curve from the three (3) samples can actually be

grouped according to the sand quality. It is illustrated that sample 1-2001 has the highest

quality of rock type among others. Each sand facies will be assigned with its own capillary

pressure to further include the heterogeneity of the reservoir.

26

Page 42: Final Report-Group 1

Table 4: Facies classification of Core Sample

Core sample Permeability (mD) Porosity Facies classes

1-2001 385 0.28 Good sand

1-3001 58 0.175 Shaly sand

1-4003 212 0.22 Fair sand

J-function is used to transform the capillary pressure curve to a universal curve before

classifying according to the sand facies. The capillary pressures were used to derive J-function

to develop initial water saturation distribution in the reservoir. Rock samples with different

pore-size distribution, permeability, and porosity will yield different capillary pressure curves.

Poor reservoir rock will show higher connate water saturation and higher transition zone due to

smaller capillary tube.

Table 5: Laboratory-reservoir fluid properties for capillary conversion

27

Page 43: Final Report-Group 1

These pressures however, must first be converted from laboratory measurement to reservoir

condition before they are utilized. Hence, we will use the formula as follows.

Equation used to convert to reservoir fluid system:

(Pc)res=(σcosθ)res

(σcosθ )lab

(Pc)lab

Capillary pressure for different reservoir system can be express as follow:

28

Where:

θres /θlab : Reservoir/lab contact angle σres /σlab : Reservoir/lab interfacial tension

Where:

Pcoil-water : Capillary pressure for oil-water system Pcgas-water : Capillary pressure for gas-water system

Page 44: Final Report-Group 1

The capillary pressures calculated previously will then be converted to dimensionless function

of water saturation for rock type classification using the J-function method.

Usually a constant of 0.26145 is multiplied with the J-function values for field data units

conversion. The water saturation is usually normalized to eliminate the different critical end

points saturations. To normalize the water saturation, we will use the formula:

Where:

Sw : Water saturation corresponding to the capillary pressure value

Swi : Initial water saturation of core sample

J-function values versus normalized water saturation were plotted to classify the capillary

curve according to sand facies. The average J-function curve is then de-normalized to obtain

the gas-oil/water-oil capillary pressure curve according to the rock classifications. Capillary

pressure curve will describe the saturation profile in the dynamic modeling.

29

Where:

Pc (Sw) : Capillary pressure at different wetting saturation σ cos θ : Interfacial tension and cosine θ of oil/gas-water k : Rock permeability (Darcy) Ø : Rock porosity (fraction)

Page 45: Final Report-Group 1

Figure 15: Capillary pressure curve classification based on J-function vs. Sw

From the plot above, the capillary pressure curves from the three (3) samples can actually be

grouped according to the sand quality. Each average curve will then be de-normalized by

selecting the nearest matched curve and de-normalization will be based on the values of the

core sample selected. In this project, based on the facies modeling of the reservoir, 3 average

curve selected as good sand, fair sand and shale sand. Each sand facies will be assigned with

its own capillary pressure to further include the heterogeneity of the reservoir.

30

Good sand Shale sand Fair sand

Page 46: Final Report-Group 1

3.2.3.2 Relative Permeability

Relative Permeability for each core sample of Gullfaks field are generated and displayed in the

consequent figures. There are two relative permeability curve generated for each facies namely

gas oil relative permeability curve and water relative permeability curve.

The nonwetting phase relative permeability curve shows that the nonwetting phase begins to

flow at the relatively low saturation of the nonwetting phase. The saturation of the oil at this

point is called critical oil saturation Soc.

The wetting phase relative permeability curve shows that the wetting phase will cease to flow

at a relatively large saturation. This is because the wetting phase preferentially occupies the

smaller pore spaces, where capillary forces are the greatest. The saturation of the water at this

point is referred to as the irreducible water saturation Swir or connate-water saturation Swi—

both terms are used interchangeably.

31

Figure 16: Oil-Water Relative Permeability Curves

Page 47: Final Report-Group 1

.

3.2.4 Reserves EstimationThe estimation of the HCIIP is based on the availability of any pressure and production data.

Volumetric calculation is basically one of the common practices by all the geologists and

geophysicists in industry to evaluate the economic value of that certain particular field

development. As the time goes by, some of the information of the reservoir will de dynamic as

a function of time, therefore this volumetric calculation must be viewed as the present

estimation as it is expected to change throughout the reservoir life. HCIIP can be separated into

oil and gas phases.

Stock Tank Oil Initially In Place (STOIIP)

Gas Initially In Place (GIIP)

32

Figure 17: Gas-Oil Relative Permeability Curves

Page 48: Final Report-Group 1

HCIIP is a function of the Gross Rock Volume (GRV) multiplied by the Net to Gross (NTG),

Porosity and oil or gas saturation. All these fractions are used to discount any volume of the

GRV that does not add to the hydrocarbon volume. Furthermore, HCIIP is not the volume of

hydrocarbons in the reservoir, but at stock tank (at the surface) conditions. Hence the name

STOIIP: Stock Tank Oil Initially In Place when talking about oil. For gas the name is just

GIIP.

To calculate stock tank conditions the temperature, composition and pressure of the fluids in

the reservoir is used to calculate a Formation Volume Factor. This factor is used to express the

expansion of the gas when brought to surface. For oil, it is used to express the volume decrease

due to gas escaping from the fluid when the pressure drops. In addition to that, HCIIP is not the

volume that is eventually produced as no reservoir can be produced to the last drop of oil and

gas. The recovery factor is a last factor that can be used to estimate the recoverable volume of

Hydrocarbons but is very much dependent on the development method for the field.

Figure 18: STOIIP and GIIP Calculation Concept

33

Page 49: Final Report-Group 1

𝐻𝐶𝐼𝐼𝑃 = 𝐺𝑅𝑉 ×𝑁/𝐺× Ø × 𝑆h𝑐 × 1/𝐹𝑉𝐹For oil volumetric calculation:

𝑆𝑇𝑂𝐼𝐼𝑃 = 𝐺𝑅𝑉 ×𝑁/𝐺× Ø × (1 - 𝑆𝑤) × 1/𝐵𝑜For gas volumetric calculation:

𝐺𝐼𝐼𝑃 = 𝐺𝑅𝑉 ×𝑁/𝐺× Ø × (1 - 𝑆𝑤) × 1/𝐵𝑔

3.2.4.1Stock Tank Oil Initialy in Place (STOIIP)

Table 6: STOIIP Calculation

STOIIP CALCULATION

GRV(m^2)*10^6 Net to gross porosity 1-Sw Bo STOIIP (m^3)*10^6BC-TT TT-TN TN-TE

1266.239581 0.0820.3360.421

sum in m^

0.255 0.734 1.1 17.66742646917.4225358 0.255 0.734 1.1 52.4508145869.2069361 0.255 0.734 1.1 62.26569418

3 unit 132.3839351

3.2.4.2Gas Initialy in Place (GIIP)

Table 7: GIIP Calculation

GIIP CALCULATION

GRV(m^2)*10^6 Net to gross porosity 1-Sw Bg GIIP (m^3)*10^6BC-TT TT-TN TN-TE

18.59410431 0.0820.3360.421

sum in m^

0.255 0.734 0.005696 50.1020360414.28571429 0.255 0.734 0.005696 157.727528113.60544218 0.255 0.734 0.005696 188.2179403

3 unit 396.0475044

34

Page 50: Final Report-Group 1

From calculation above, we conclude that Stock Tank Oil Initially In Place (STOIIP) to be

132.3839351 (m^3)*10^6 and Gas Initially In Place (GIIP) at 396.0475044 (m^3)*10^6.

3.2.5Well test analysisWell testing is a very effective way to test the properties of the drilled well and some of the reservoir average properties. The basic idea of well testing is to always monitor and record the change in reservoir pressure with the change in flow rate. Then plotting the relationship between them on a Cartesian, semi-log or log-log scale and from these plots, some of the reservoir properties can be determined such as:

Formation permeability

Reservoir‟s boundary conditions

Average reservoir pressure

Skin effects

In this project the Drill Stem Test DST for well A10 is analyzed mainly to determine the average reservoir permeability which can assist in the history matching as well as in determining the drainage radius for each well for better well placement Well A10 is an exploration well. For simplicity single rate test was used. There was two test one drawdown test the other is build up test.

Pansys software was used in analyzing the well test data. And the following findings were made.

The test overview was as following

Figure 19 well test over view

35

Page 51: Final Report-Group 1

A pressure draw down test at a constant rate of 4715 bbl/day, for 73 hours, followed by a

shutin build up test to complete 190 hours.

3.2.5.1 Drawdown down test analysis

It was analyzed on a semi log plot and the results are in the following figure.

Figure 20 semi-log plot of the drawdown test

The test shows straight line trend of MTR early and then boundary effect takes over. And

shows k=28.6 md , And radius of investigation of 764 ft.

By matching it’s log-log plot to boundary condition type curve on pansys. The following was

optained.

36

Page 52: Final Report-Group 1

Figure 21 Boundary type curve matching

The match showed that there is a nearby single fault of L=67.5 ft. and this fault is the reason

why MTR region is so small.

3.2.5.2 Buildup test analysisFrom log-log plot the MTR region was identified by the flat deferential pressure trend.

Figure 22 log-log plot of pressure and differential pressure for buildup

And the MTR region could be identified by the dashed lines. Then by using this region from

the semi log plot, K and radius of investigation could be calculated.

37

Page 53: Final Report-Group 1

Figure 23 Semi-log plot of build-up test

K was found to be 191 md and radius of investigation was found to be 2619 ft.

And the type curve plot confirms the presence of a single fault as shown in the figure below.

Figure 24 boundary type curve plot for build-up.

And the fault is of l=90ft.

It is to be noted that, Build up test results are more reliable than draw down tests. As flow rate

is easily maintained at zero rather than fluctuating around 4715bbl/day drawdown. Also, it

lasted for longer time and has shown flat differential pressure which is a sign of MTR.

38

Page 54: Final Report-Group 1

Thus it can be assumed that, average permeability around well A10 is 191 md and that radius

of investigation of the test reached 2619 ft.

3.3 History matching

3.3.1 Overview

In general, the reservoir simulation process can be divided into three main phases:

I. Input data gathering

II. History matching

III. Performance prediction

The first step in a simulation study is the collection and analysis of data. Data must be acquired

and evaluated with a focus on its quality and the identification of relevant drive mechanisms

that should be included in the model. Input data normally contains of general data, grid data,

rock and fluid data, production/injection data and well data.

The next phase of the reservoir simulation study is the history matching phase. The goal of

history matching is to prepare a flow model that can contribute to reservoir management

decision making. History matching is an iterative process that makes it possible to integrate

reservoir geoscience and engineering data. Starting with an initial reservoir description, the

model is used to match and predict reservoir performance by adjusting the reservoir parameters

of a model until the simulated performance matches the observed or historical behavior.

The history matching procedure consists of the following sequential steps:

39

Page 55: Final Report-Group 1

1. Pressure matching

2. Saturation matching

3. Productivity matching

The pressure is usually the first dynamic variable to be matched during the history matching

process. A comparison of estimated reservoir pressures obtained from well tests of a single

well on successive days shows that errors in reported historical pressures can be up to 10

percent of pressure drawdown. While production rates are usually from monthly production

records. The modeler specifies one rate or well pressure, and then verifies that the rate is

entered properly by comparing observed cumulative production with model cumulative

production. After the rate of one phase is specified, the rates of all other phases must be

matched by model performance.

The fundamental concept in history matching is the hierarchy of uncertainty, where relative

permeability data are typically placed at the top of the hierarchy of uncertainty because they

are modified more often than other data. Initial fluid volumes may be modified by changing a

variety of input parameters, including relative permeability endpoints and fluid contacts.

Typically, observed and calculated parameters are compared by making plots of pressure

versus time, cumulative production (or injection) versus time, production (or injection) rates

versus time, and GOR, WOR, or water cut versus time. However, there are limitations on

history matching process including unreliable or limited field data, interpretation errors, and

numerical effects.

Once a match of historical data is available, the next step involves predicting the future

performance of a reservoir when the modeler switches from rate control during the history

match to pressure control during the prediction stage of a study. This prediction could be for

existing operating conditions or for some alternate development plan, such as infill drilling or

waterflooding after primary production, and so forth. The main objective is to determine the

optimum operating condition in order to maximize the economic recovery of hydrocarbons

from the reservoir.

40

Page 56: Final Report-Group 1

3.3.2 History Matching Results from the study

The only available field data for history matching comes from Well A10’s multi-rate well test,

which is run on constant liquid rate. Hence, the only logical way to history match is to run the

well A10 in the petrel model on constant rate and try to match the observed data, which

consists of the bottom hole pressure profile as well as the water and gas production curves. A

history strategy was set up accordingly in order to produce the required schedule section for

our field’s data set to run with Eclipse simulators. As shown in the figure below, the history

strategy was created from observed data and hence it overlaps/follows the observed data points

exactly.

Figure 25: A10 Production Rate

41

Page 57: Final Report-Group 1

Matching A10 bottom-hole pressure

As expected, the base case BHP (shown as red curve HM0 in graph below) does not match the

observed data. This means that certain properties of the model (rock and fluid properties) need

to be changed in order to bring the BHP curve down. Although our group did not do a

comprehensive sensitivity analysis of all possible parameters that can be changed, we did a

quick sensitivity study and found conclusively that absolute rock permeability was the most

sensitive parameter. Hence we should not need to change it much in order to get a good match.

Also, it is quite evident that the reservoir must have a higher permeability than the real

reservoir and that is why it can produce at the same rate with higher BHP pressures. Hence our

group tried changing the permeability of the cells surrounding the well in the I, J and K

direction to find the best combination that can match our observed data.

Figure 26: A10 Bottom hole Pressure (base case)

42

Page 58: Final Report-Group 1

Figure 27: A10 surrounding

Our group has decided to not multiply the permeability array of the whole reservoir because we

feel that it does not make sense to change the properties of cells that do not contribute to well

A10’s production. Furthermore, those properties have been derived from accurate well log and

core data, and we strongly feel that it should not be changed unless we have better quality data

with better certainty. Hence, to solve this, we created a geometrical property with radius of

600m around the well A10 (shown in figure on the right) and used it to apply a filter when

modifying the reservoir properties. In this way, only the properties of the cells within a 600m

radius of the well gets changed. 600m radius was chosen as an appropriate radius after we did

some investigation into the maximum possible drainage area of the well when critical

properties such as permeability are lowered. Part of this investigation included taking cross

sectional views of the reservoir and seeing how far away from the well the production is taking

place (as shown in figure below).

43

Page 59: Final Report-Group 1

Figure 28: Cross Sectional View Of Reservoir

After much investigation and trying out numerous combinations of altered permeabilities, our

group found out that the best match we can get is when we multiply permeability in I direction

by 0.7 and permeability in J direction by 0.9. The resulting match is shown in the figure below.

We call this case 1.

Figure 29: A10 Bottom Hole Pressure (case 1)

44

Page 60: Final Report-Group 1

Matching A10 gas production rate

Figure 30: Gas Production Rate case 1

As can be seen in the figure above, the gas production rate of case 1 is so high that the

observed data look like they are zero when the two data are compared. Hence, our team set out

to change several things in order to try to lower gas production and to get a match:

1. Raising the gas cap

Our group thought that maybe gas coning was happening and that enormous amounts of

gas were being produced from the gas cap. In order to test this theory, we raised the gas-oil

contact so that it was way above the topmost grid-block. In other words, there no longer a

gas cap. However, as the figure below shows, this only reduced gas production slightly,

which shows that production from the gas cap was not significant at all. This meant that it

was either we have a wrong fluid model (with too high Rs) or that the pressure drop was

causing gas to evolve out of the oil too quickly in the oil zone and that it is getting

produced in favour of the oil.

45

Page 61: Final Report-Group 1

Figure 31: Match Attempt 1

2. Stopping movement of free gas

In order to test our theory and stop the preferable production of free gas, we tried changing

the relative permeability curve of the gas in order to restrict the movement of the free gas

phase. However, even after lowering the gas relative permeability curve by half, there was

only a slight drop in gas production (shown by brown curve in figure below). So we tried

setting the relative permeability curves to zero instead. The drop in gas production was also

not enough (shown as red curve in figure below).

46

Page 62: Final Report-Group 1

Figure 32: Match Attempt 2

3. Changing the fluid model

Finally, to check if it was our fluid model that was wrong, we used pre-sets to build a “dead

oil” fluid model, which is known to have a low solution gas ratio. However, the figure

below shows that even though the gas production from the “dead oil” case was

significantly lower than that of case 1, we can clearly see that it was still too high compared

to the observed data, which still looks “squashed” down to zero when compare to the two

simulated gas production. In conclusion, our group believes that something must be wrong

with the observed data and not our model. Therefore we cannot and should not match our

data to the observed gas production rate.

47

Page 63: Final Report-Group 1

Figure 33: Match Attempt 3

Matching A10 water production rate:

Matching this rate curve was not a problem because there was no aquifer below the oil zone in

the region where well A10 was producing. Hence, as can be seen by the graph below, the

water production for the case 1 showed zero production just like the observed data.

48

Page 64: Final Report-Group 1

Figure 34: Water Production Rate

Case 1 was deemed the best matched case and was used as the model going forward into the

production prediction and optimization stage.

49

Page 65: Final Report-Group 1

3.4 Production Forecast & Optimization

In order to identify the best possible strategy to develop and produce the field, sensitivity

analysis was done. The simulation model was run with different configurations in steps in

order to quantify the development uncertainties and depletion strategies. Due to the time

constraints and the inability to identify the dominant drive mechanism of the field, the

sensitivity analysis was done in a way that would give the best possible results. They are

discussed in the following sections.

3.4.1 Base case analysis

For the base case, first, all the existing 12 wells (using the existing

completions – perforation Intervals) were run as producer individually with

natural depletion drive via fluid expansion for 10 years and they ranked

based on their individual performance and their ranking is used as a guide

for the next step. Based on the production of each well, the wells with the

lowest production rate removed from the combination and next case will

run without those wells. The process is continued till the last well and the

total cumulative production is compared among the cases to identify which

combination of wells is the best. The results are summarized below:

50

Figure 35: Cumulative oil production for all the wells

Page 66: Final Report-Group 1

Based on the figure shown, the production of following wells (C2, C3 and

C4) is very low. It’s because these wells are located below oil water

contact. Even though the best location for perforation was chosen for all of

them still they result in having early water breakthrough.

51

Figure 36: Cumulative oil production for all the wells except (C2, C3 and C4)

Page 67: Final Report-Group 1

As it’s clear from this figure, well B9 has the highest production rate

followed by A20, A10, A19, A16, A15 and C5. There are 10 different cases

run in order to find the optimum number of producing wells.

Based on the results taken from these graphs, the case number 7 with 7

wells B9, A20, A10, A19, A16, A15 and C5 has the highest cumulative oil

production. This case will be selected as the optimum case with the best

52

CASE 1 2 3 4 5 6 7 8 9 10NO OF WELLS 1 2 3 4 5 6 7 8 9 11

B9 B9 B9 B9 B9 B9 B9 B9 B9 B9A20 A20 A20 A20 A20 A20 A20 A20 A20

A10 A10 A10 A10 A10 A10 A10 A10A19 A19 A19 A19 A19 A19 A19

A16 A16 A16 A16 A16 A16A15 A15 A15 A15 A15

C5 C5 C5 C5B8 B8 B8

C6 C3C2C4C6

TOTAL OIL PRODUCTION (sm3) 715700 1221900 1647100 1973000 2301400 2501500 2670800 2761800 2755300 2523000

-1 1 3 5 7 9 1170000

570000

1070000

1570000

2070000

2570000

CUMULATIVE OIL PRODUCTION CASES

No. of producers

CU

MU

LA

TIV

E O

IL P

RO

DU

CT

ION

(sm

3)

Figure 37: Field oil production cumulative for all the 10 casesFigure 38: Oil production cumulative for all the 10 cases

Page 68: Final Report-Group 1

producing wells. It is called our base case and the following tests will be

done on this case.

Figure below show comparison between the base case with the case with

all the 12 wells open for production:

53

Figure 39: Base case vs all the wells producing

Page 69: Final Report-Group 1

3.4.2 Secondary recovery

To improve the oil recovery for this field, secondary drive mechanisms such

as water flooding is suitable as the reservoir is supported by an aquifer

from the bottom therefore individual water flood cases are analyzed which

each will be explained in the following sections. However for this section,

the injection wells are selected from the existing wells not by adding a new

well. Selection of injectors was done based on the location of each wells

which are supported by aquifer.

3.4.3 Water injection

To improve the oil recovery of the Gullfaks field, water injection scheme is proposed. The

injection wells used are the existing proposed wells given in FDP data pack (C4, C6, B8, C3

and C2). The injection wells are controlled by the bottom hole pressure of the wells which is

set to 400 bar in the PETREL 2013 simulator. A base case with water injections was created.

There are as well 5 different cases define for water injection process.th first case is 1 injector

with 7 producing wells (base case). The second, third, fourth and fifth are 2, 3 4 and

5 injectors.

54

CASES 1 2 3 4 5NO OF INJECTORS 5 4 3 2 1

C4 C4 C4 C4 C4C6 C6 C6 C6B8 B8 B8C3 C3C2

Table 9: Water injection for different cases

Page 70: Final Report-Group 1

The best base case with natural depletion is compared with the base case with 1,2,3,4 and 5

water injectors. The results are as follows:

55

Figure 40: Natural depletion vs 5 injectorsFigure 41: Natural depletion vs 3 injectors

Figure 42: Natural depletion vs 4 injectors

Page 71: Final Report-Group 1

Figure 43: Natural depletion vs 2 injectors

From the results simulated, it can be seen that production with water injection strategy is better

than the one with natural depletion strategy. Hence it is determined that the field will be

produced with water injection strategy rather than just natural depletion alone. For the water

injector base case, the combination of 7 production wells with water injection will be used.

Based on this figure the 4 injectors, case no 2 (C4, C6, B8 and C3) give

higher oil production result compare to the rest. However based on the

optimum case curve the 3 injector and 4 injectors doesn’t have much

difference so 3 injector will be selected as the best case for water injection.

56

CASES 1 2 3 4 5NO OF INJECTORS 5 4 3 2 1

C4 C4 C4 C4 C4C6 C6 C6 C6B8 B8 B8C3 C3C2

TOTAL OIL PRODUCTION (sm3) 5283700 5434000 5329300 4718700 3536800

Figure 44: Natural depletion vs 1 injector

Figure 45: Comparison between different cases for water injection

Table 10: Ranking the injector cases

Page 72: Final Report-Group 1

The

next step is to do sensitivity analysis on the water injector combination with 7 producer wells.

3.4.4Water injection timing sensitivity analysis

After choosing the optimum number of injection wells, Sensitivity analysis was made to find

the optimum timing for water injection.

The timing for water injection is very important in reservoir production as injecting water into

the reservoir at different time will lead to different production profile.

The sensitivity analysis was made on 5 different cases (Injection after 2 years, 4 years, 6years

and 8years) and compared to the optimum injection case with injection right from start.

57

1 2 3 4 53536800

4036800

4536800

5036800

5536800

INJECTOR CASES

No. of injectors

TO

TA

L O

IL P

RO

DU

CT

ION

(sm

3)

Figure 46: Comparison between injector cases oil production

Page 73: Final Report-Group 1

Figure 47: Sensitivity analysis on water injection timing

The results showed that the field’s production is at its optimum when the

water injection started since the beginning of the production. This also

indicates that the reservoir’s aquifer has little effect on the production and

water injection is needed in order to fully maximize the field’s hydrocarbon

recovery.

Figure 48: Natural depletion vs Optimum No. of injectors optimum injection timing case.

58

Page 74: Final Report-Group 1

3.5 Enhanced Oil Recovery (EOR) Plan

3.5.1 Reservoir Properties of Gullfaks Field

The reservoir and fluid properties of the Gullfaks field are summarized in following table.

Table 11: Parameters of the Gullfaks field

Reservoir Property Value Oil Gravity , API 64.2 Reservoir Temperature 220 F Original Reservoir pressure 2516 psia Oil Viscosity ,cp 1.337cp Porosity 0.27 Horizontal permeability 270md Reservoir Depth , ft >5000Residual Oil Saturation 77.4

3.5.2 EOR Screening Criteria

Screening criteria have been widely used to identify EOR applicability in a particular field

before any detailed evaluation is started. EOR screening represents a key step to reducing the

number of options for further detailed evaluations. Table Summary of screening criteria for

EOR Methods shows the summary of screening criteria which is based on a combination of the

reservoir and oil characteristics of successful projects plus the optimum conditions needed for

good oil displacement by the different fluids. The suggested criteria in following table are

informative and intended to show approximate ranges of good projects but they may be

misleading

59

Page 75: Final Report-Group 1

Table 12: Summary of screening criteria for EOR Methods

60

Page 76: Final Report-Group 1

3.5.3 EOR Plan

Screening processes were carried out to identify potential EOR processes for Gullfaks

reservoirs. Based on swelling test provided, it indicates that Immiscible Gas Flooding and CO2

gas Injection which are suitable and meet the criteria in order to be implemented at Gullfaks

field.

3.5.3.1 Immiscible Gas Flooding

In this method, nitrogen is injected to the reservoir to maintain the pressure and to produce

better sweep efficiency. This is achieved by creating miscibility or partial miscibility which

reduces the viscosity of oil and cause oil swelling, which resulting in increasing in the recovery

factor.

Figure 49: Nitrogen Injection Process for Recovery Improvement

61

Page 77: Final Report-Group 1

3.5.3.2 CO2 Gas Injection

The main objective of carbon dioxide injection gas is to swell the oil, lower its viscosity

which result in lowering the interfacial tension between the oil and rock, thus improving the

microscopic sweep efficiency. CO2 flooding can obtain high oil recovery from light oil and

especially in water flooded reservoir in some cases. Miscible CO2 injection can extract the light

to intermediate components of the oil, and develop miscibility to displace the crude oil from

the reservoir. The Figure below illustrates the carbon dioxide injection process.

Figure 50: Carbon Dioxide Reinjection Process for Recovery Improvement*

*Retrieved from http://energy.gov/fe/science-innovation/oil-gas-research/enhanced-oil-recovery

CO2 volumes injected during a process are typically at least 25% PV. A volume of relatively

pure CO2 is injected to mobilize and displace residual oil. Through multiple contacts between

the CO2 and oil phases, intermediate and higher molecular weight hydrocarbons are extracted

62

Page 78: Final Report-Group 1

into the CO2-rich phase. Under proper conditions, this CO2-rich phase will reach a

composition that is miscible with the original reservoir oil. From that point, miscible or near-

miscible conditions exist at the displacing front interface. Under ideal conditions, this

miscibility condition will be reached very quickly in the reservoir and the distance required to

establish multiple-contact miscibility initially is negligible compared with the distance between

the wells. Gas injection often comes with early breakthrough and viscous finger issue due

to its low viscosity.

For future EOR considerations, the main factors that should be considered are the current oil in

place, residual oil Saturation (Sor), and the economical, geo-political and management policy.

Further testing should be done to estimate the current oil in place or residual oil in place and

evaluate how much oil would the EOR recover. Current oil price would also play a role in

deciding whether the EOR plans would be feasible at the time of evaluation. Government

incentives such as tax and royalty would also be a deciding factor.

63

Page 79: Final Report-Group 1

3.6 Reservoir Management

Reservoir engineering phase deals with the human, technological and financial aspects of the

field, while trying to minimize the expenses and investment done to the development of the

field and also maximizing the recovery factor of the hydrocarbons in the reservoir [8].

It is envisaged the optimum development plan for Gullfaks field is by 7 production wells (B9,

A20, A10, A19, A16, A15 and C5). Oil produced will be on 1st January 2013 for

production life of 10 years. The reservoirs will be depleted naturally supported by a water

injection strategy. To improve the oil recovery of the Gullfaks field, water injection scheme is

proposed. Consequently, there are three additional injection wells, which are C4, C6, and B8. It

is realized that the field’s production is at its optimum when the water injection started since

the beginning of the production. This also indicates that the reservoir’s aquifer has little effect

on the production and water injection is needed in order to fully maximize the field’s

hydrocarbon recovery. Thus, Water injection at Gullfaks will commence at the first year of

production. Target production has to be monitored closely. Full field review should be done

and any plans for infill drilling can be considered later on. Future plans for the field might be

revised when more information regarding the field is obtained.

The reservoir management plan of Gullfaks field consists of the reservoir goal, operational

strategies to reach the objectives, and reservoir surveillance plan to identify performance issues

and to enhance the operations of the reservoir. To be able to manage reservoirs properly and to

optimize recovery, it is important that proper reservoir management and monitoring is carried

out, particularly during the early dynamic phase of production.

64

Page 80: Final Report-Group 1

3.6.1 Reservoir Management

The goals of reservoir management are:

To maximize oil recovery by optimizing reservoir performance throughout reservoir

lifetime.

To run the well test on new and existing wells for data acquisition on reservoir

properties and characteristics.

To implement secondary recovery for pressure maintenance by injecting water and

maintaining reservoir pressure above bubble point.

To practice reservoir simulation in order to provide enhancement of reservoir models

for reliable predictions.

To monitor reservoir daily, monthly and annual production for reservoir performance

and maintaining operation strategies.

To implement tertiary recovery in order to improve sweep efficiency of trapped

residual oil.

To install surface facilities than can fulfill the requirement for reservoir management

and development.

3.6.2 Reservoir Surveillance

In operating and monitoring reservoir performance, several surveillance methods need to be

used in order to minimize the uncertainties in reservoir characteristics. With the lack of data

acquired on new drilled wells in early field development, this surveillance done on reservoir

can give better quality on data and reservoir information further to comprehend about the

architecture of the reservoir [12]. Suggested surveillance is done on the operations stated in table

below.

65

Page 81: Final Report-Group 1

Table 13: Reservoir Surveillance and Its Purposes [9].

Parameters Purposes

Bottom hole pressure measurementsTo monitor reservoir pressure; maintaining pressure above bubble point with the respective drawdown pressure.

Pressure transient studiesFlowing Build Up (FBU) and drawdown test can be carried out in order to determine reservoir properties such as permeability, oil rate, productivity index and skin for new drilled and existing wells. To investigate the effect of early and late time region such wellbore storage, skin, faults and reservoir boundary.

Production loggingProvide data on water and oil saturation and fluid contacts.

Flow rate measurements.Monitoring oil production and water injection rate Record and limiting water production after 50% of water cut

Sand Production MonitoringMonitoring sand production through production test choke inspection and fluid samples by recording amount of sand produced.

Every effort will be made to ensure Gullfaks field reservoirs will be managed prudently and in

accordance to Norway government guidelines. Reservoir management for Gullfaks field can be

divided into two phases, which are initial production and routine production phases. In every

phase, appropriate data acquisition is planned to achieve specific objectives in order to

optimize the field development planning as well as to effectively monitor reservoir

performance to maximize recovery.

Periodical surveillance is essential to obtain optimal reservoir management. Bottomhole

pressure measurements and monthly well tests are especially important to determination of the

reservoir parameters and aquifer strength. The aquifer strength could be confirmed only after

66

Page 82: Final Report-Group 1

several years of production. Revisions to the STOIIP and GIIP should be done after drilling the

development wells in the drilling campaign.

Initial flowing and build-up (FBU) will also be carried out at the first opportunity available.

From initial FBU, the initial reservoir pressure, the permeability, the skin factors, the reservoir

boundary and other useful reservoir parameters would be obtained. The initial FBU data will

be analyzed to ensure the reservoir characteristics are considered in revising the reservoir

management and production allocation.

Routine production rate test will be performed once a month to determine its oil, gas, and water

rates. The measurement of surface condition such as wellhead pressure (THP), choke size and

casing head pressure and the API gravity of the produced liquid hydrocarbon will also be

recorded during the monthly production test.

Static bottom hole pressure (BHP) surveys will be performed annually. This would be useful,

as it would permit material balance study. Key wells will need to be identified so as the six

month BHP surveys are done on these wells. While the remaining active wells will be the

rotational wells and BHP surveys will be done on annually basis. The BHP survey data would

be used to continually monitor the reservoir pressure and areal pressure distribution,

particularly in the late field life.

The production test rate and BHP survey must comply with the procedures approved by

Norway government. The results of the reservoir simulation models will be used as a guide for

the reservoir surveillance engineers to determine the optimal production strategy. Sensitivity

analyses of different depletion plans have been carried out to increase the recovery factor such

as number of wells, types of wells, water injection.

Due to unconsolidated nature of the reservoir rocks, sand production will be monitored from

the monthly test choke inspection and fluid samples by recording amount of sand produced.

Close monitoring, especially on water breakthrough, would provide indication of any

problematic wells or reservoirs for early diagnosis. Early corrective measures could be

undertaken to prevent well/reservoir problems and prevent excessive water production in early

field life.

67

Page 83: Final Report-Group 1

CHAPTER 4 DRILLING ENGINEERING

4.1 Introduction

Drilling operations have a substantial importance in the Field Development Plan as it

represents a large portion of the total project’s costs. This phase of FDP describes the stages

that should be done in order to design development plan using the information that are

achieved from geosciences and reservoir engineers. The Gullfaks field is located in the

Tampen area, a part of the Viking Graben in the North Sea. Due to the large

area of the field, which is 50 km2, Gullfaks was developed with three

platforms, Gullfaks A, B and C. Geologically, Gullfaks was described as the

most complex field that had been developed so far on the Norwegian

Continental Shelf (NCS) when it was put on production.

The development plan of Gullfaks Field is to drill 7 production wells (B9,

A20, A10, A19, A16, A15 and C5), with 3 injection wells (C4, C6, and B8).

The proposal of the development should contain the objectives of the well

and the location of the target with the geological cross section. All

activities involve in the drilling phase are to be conducted according

to the standard guidelines provided by PETRONAS HSE. On the other hand,

the drilling program should comprise of these important elements such as

drilling rig to be used for the well, proposed location for the drilling rig, hole

sizes and depths together with the casing sizes and depths. Other aspects

like drilling fluid specification, well, control equipment and bits and

hydraulics program are also included.

4.1.1 Problem Statement

There are several steps that should be done during drilling operations that

include: selection of platform and suitable offshore rig, well

trajectories, casing design, bit selection, drilling fluid system, casing

cementation and drilling hazards. Also the overall cost estimate for the

68

Page 84: Final Report-Group 1

drilling operation should be calculated. Finally, drilling optimization and

new drilling technology should be investigated. For this part of the Field

Development Plan, first suitable platform and offshore rig should be

selected based on some criteria. Casing plan should be done to make the

drilling operations cost-efficient and safe.

4.1.2 Objective

The main objectives of drilling operations in the Field Development Plan of Gullfaks field are

as follows:

Propose an appropriate platform and offshore rig applicable in our field.

Design well trajectories, casing design, selection of bits, drilling fluid system, casing

cementation and also drilling hazards.

Estimate overall time and cost of the drilling operations.

4.2 Drilling Rig Selection

Drilling technology is continually expanding, and some rigs combine elements from different

models to attain particular capabilities. Generally the main types of offshore oil rig include the

following:

Tender-Assisted-Drilling (TAD).

Jack-up Rig.

Semi-submersible.

Drillship.

69

Page 85: Final Report-Group 1

Figure 51: Types of Rig

Rigs classification is based on the of location, whether offshore or onshore and the rig’s

capacity as in the effective drilling depth that can be attained. Offshore rigs perform the

same function as the land drilling rig. The difference between these two is that land rig has

complexity in terms of mobility while the offshore rig is in the aspect of the design.

There are two main types of offshore drilling rigs, which are floating type and bottom-

supported unit. Floating unit type would include the semi-submersible (bottle-type, column

stabilized), barge rig and drill ship. Meanwhile, bottom-supported unit comprised of posted

barges, bottle-type submersibles, arctic submersibles), jackups and platforms. In shallow water

or swamps, a barge which is a shallow-draft, flat-bottomed vessel water or swamps is used. In

general, table below shows the most common used offshore oil rigs.

Table 14: Rig Selection

Drilling Rig Type Water depth (ft) Average Daily Rate (USD)

Jack-up Rig 200-500 $60,000-100,000

Semi-submersible Rig 1499-4000 $298,000-432,000

Drillship 4000-5000 $243,000-524,000

Sources: Rig zone website, Riglogix http://www.rigzone.com/search.asp?q=jack+up+rig

The sea depth for Guillfaks is around 130-230m (427-755ft). Initially, Jack-up rig and semi-

submersible rig are preferable due to variation of water depth.. Since proposed location have

water depth ranging from 130-150m (400-500ft) therefore Jack up rig is choosed.

4.3 Rig Location

One of the most important parts in the well trajectory planning is the rig

location. To propose the best location of the rig, many factors should be

taken into consideration such as the total length of the measured depths

70

Page 86: Final Report-Group 1

(MD) from the rig to the targets (wells) and the drilling trajectory process

(type of trajectory, build up rate and drop down rate). These factors affect

economically on the drilling cost and process. The less drilled measured

depths, the less the drilling cost. For these reasons the proposed rig

location has been decided to be at 3 different point.

451000 452000 453000 454000 455000 456000 457000 458000 4590006778000

6779000

6780000

6781000

6782000

6783000

6784000

6785000

6786000

6787000

6788000

c platform

b platform

a platform

c6

c4

b8

a15

c5

b9

a10

a16

a19

a20

Drilling Rig Locationa20

a19

a16

a10

b9

c5

a15

b8

c4

c6

a platform

b platform

c platform

y (m)

x (m

)

Figure 52: Location of Rig

4.4 Well Trajectories

In this project, PETREL software will be used to help in designing the wells. Completion and

reservoir drainage considerations are key factors in well path design. All producer wells and

injector wells will be drilled from two platforms (one for the seven producer wells and another

for the three injector wells) to keep the wells from only two platforms wells will need to be

deviated to reach the target zones.

71

Page 87: Final Report-Group 1

The original plan was, calculating the optimum place for injector and producer drilling rig

using average X and y coordinates of the targets of the wells producer and injector wells

respectively. To keep minimum distance drilled possible for all the wells.

Figure 53: Optimum places for the two platforms used for drilling of all the wells Yellow triangle for injection wells platform and red triangle for producer wells platform

The reason for choice of the deviated wells from common platforms (one for drilling and one

for production), is due to saving cost of production and injection facilities being installed each

in a single place. Also, the installation of production or injection facilities on a single platform

without the other will allow for more space to be used on the platforms. As well, to facilitate

transportation of the produced oil from the single production platform as compared to several

producing platforms.

72

Page 88: Final Report-Group 1

producer wells x y x ya20 456397.9 6782861a19 456416.7 6782831a16 456510.4 6784012a10 456979.1 6782712b9 456727.7 6785559c5 453503.7 6783002a15 456645.1 6781580

injector wells x y x yb8 457746.9 6787093c4 454640.2 6786211c6 451503.8 6781788

Well head coordinatesTarget coordinates

456168.64 6783222.6

454630.32 6785030.5

Target coordinates Well head coordinates

Figure 54: Well targets coordinates and wellheads coordinates

However, this was changed since we have found data in literature suggesting that in Gulfaks field. There is three platforms. Namely A,B and C.

So the well trajectories followed the following patterns.

Drilling rig coordinatesWell target X y x ya20 456397.92 6782861.07

456589.8255 6782799.335

a19 456416.68 6782831.44a16 456510.4055 6784012.02a10 456979.0637 6782712.412a15 456645.0581 6781579.733 b9 456727.6572 6785559.446

457237.2964 6786326.03b8 457746.9356 6787092.614 c5 453503.7221 6783001.797

453215.9155 6783666.89c4 454640.1872 6786210.631c6 451503.8373 6781788.243

Table: Well targets vs optimum drilling location

73

Page 89: Final Report-Group 1

451000 452000 453000 454000 455000 456000 457000 458000 4590006778000

6779000

6780000

6781000

6782000

6783000

6784000

6785000

6786000

6787000

6788000

c platform

b platform

a platform

c6

c4

b8

a15

c5

b9

a10

a16

a19

a20

Drilling Rig Location

y (m)

x (m

)

Figure 55 Drilling rigs location

4.5 Casing Design

The casing design have many details that must be taken into consideration such as determination of

casing setting depth, size, grade and weight of the casing for each interval. The casing shoe setting

depth is usually a function of the drilled formations. Pore pressure and fracture pressure gradient can

affect directly to the casing setting depth. The casing size is determined depending on the well depth. In

deep wells, the drilling process needs to start drill with large hole size and many casings to cover the

hole length, but it starts with smaller hole size and less number of casings in shallow wells. The casing

weight and grade are selected based on the load conditions (burst, collapse and tensile) for the well. In

general, the main functions of casing are:

• To isolate unstable formations.

• To protect weak formations from the high mudweights that effect on zone fracture.

• To isolate zones with abnormal high pore pressure.

• To seal off lost circulation zones.

74

Page 90: Final Report-Group 1

• To allow selective access for production from or into the reservoir.

• To provide structural support for the wellhead and BOPs.

All the casing configuration is designed based on pressure containment, cost effectiveness and

completion requirements. The design is based on SPE casing design criteria and it must conform to

PETRONAS Procedures for Drilling Operation (PDO), PETRONAS Technical Standards (PTS), PCSB

Drilling Manual and Well Design Manual (WDM).

Table 15: Types of Margin

Margin name Types of Margin Function

Safety Margin 1.05 Trip Margin Allow for reduction in effective mud weight caused by upward pipe movement during tripping operations (swab pressure)

5% is taken from EMW

Safety Margin 0.95 Kick Margin Prevent fracture of formation by kick pressure and surge pressure.

5% is added to EMW

75

Page 91: Final Report-Group 1

Figure 56 Equivalent Mudweight vs Depth

The figure above shows the pore pressure and fracture pressure profile with proposed casing

seat, while the table explain the margin. To have a better casing design plan, safety margin is

used to keep the mudweight in the safe window. Therefore well can be drilled without

damaging the formation and engineers still have control over the well. According to School of

Petroleum Engineering, UNSW (PTRL5022) safety margin taken at 0.5ppg for trip margin and

also kick margin. In this project trip margin and kick margin is proposed 5% from the

Equivalent Mud Weight. Casing is design based on the operating window (between Trip

margin and kick margin) accordingly except at the depth grater than 1800m, it is because the

mud should not excees 15ppg. The mud density of 15 ppg was the heaviest weight that could

be reasonably held in suspension with the given mixing system, 4000 HHP was the estimated

effective horsepower of all the cementing pumps avaiable, 7000 psi was the highest pressure

76

Page 92: Final Report-Group 1

utilizing a 20% safety factor for burst on the existing tubulars. Therefor, to minimize the

problems regarding transporting the mud through the pipe, Equivalent Mud Weight is set at

14.4ppg (depth below 1800m). The following casing intervals are used in the Gullfaks Field:

A. Conductor Casing 30" (100m)

The purpose of running conductor casing is to prevent shallow unconsolidated

formations from washing out or craving-in, which may be caused by circulation of

mud. All conductors for the development wells will be 30" and the hole size is 36".

This conductor is driven into 100 m below the seabed.

B. Surface Casing 20" (100-490m)

Surface casing is the second casing string that will be run in borehole after conductor

casing. The main purpose of running this casing string is to seal off fresh water zones and

to provide structural support to wellhead and BOP equipment. The open hole that has been

drilled for this casing is 26". To determine the formation fracture pressure, leak-off test will

be performed after drilling out surface casing shoe.

C. Intermediate Casing 13 3/8" (490-1600m)

After running this casing in the hole, the next hole size will depend on the weight per foot

of this casing. Lithology and hole problems including weak zones, lost circulation zones,

reactive shale, represent the first factor to be considered before setting the depth of the

Intermediate casing, then mud weight requirement for the next hole section should be

prepared.

D. Production Casing 9 5/8" (1600-2300m)

The setting depth of Production Casing or Liner is generally based on the reservoir

77

Page 93: Final Report-Group 1

testing and production requirements. The 12 1/4" open hole has been drilled before

running 9 5/8" production casing. In addition to that, the distance from the reservoir to

the casing shoe depth depends on the depth of the lowest perforation, Completion design

requirements and amount of anticipated perforation debris and sand fill.

Table 16: Casing setting depth and Mud Program

Hole size Casing size Casing setting depth (m)

Casing setting depth (ft)

Mudweight used (ppg)

36” 30” 100 328 6-6.3

26” 20” 490 1608 8-8.3

17 ½” 13 3/8” 1600 5248 10-11

12 1/4” 9 5/8” 2300 7546 14.1-14.4

4.6 Bit Selection

Bit selection design should be conducted after completing casing and drilling fluid design.

4.6.1 Size of Bit

The selection of the bit sizes that will be used to drill a well depends on the well design which

includes the sizes of the holes and casing characteristics (sizes and weights). The casing size

and weight force the bit designers to choose the suitable bit size in order to drill the next hole.

78

Page 94: Final Report-Group 1

4.6.2 Type of Bit

Basically, there are three types of drilling bit; Drag Bits, Roller Cone Bits and Diamond Bits.

Drag Bits: are the first bits used in rotary drilling, but they are no longer in common use.

Roller Cone Bits: Roller cone bits (or rock bits) are still the most common type of bit used

worldwide. The cutting action is provided by cones which have either steel teeth or

tungsten carbide inserts. There are two type of this bit; milled tooth bits and tungsten

carbide insert bits, figures 6 and 7. The first one is used to drill soft to medium formations

while the second one is used to drill medium to hard formations.

Diamond Bits: this type of bit is used to drill hard formations. There are three main types

of this bit; Natural Diamond Bits, polycrystalline diamond compact (PDC) bits, and

Thermally Stable Polycrystalline (TSP) diamond bits. This kind of bits is used to drill hard

and very hard formations. Figure 8 shows a (PDC) bit.

Figure 57: Insert Bit

Figure 58: Milled Tooth Bit

79

Page 95: Final Report-Group 1

Figure 59: PDC bit

4.6.3 Factors affecting Bit selection

There are two main factors that play a big role on the bit selection. These factors are;

Formation characteristics.

The type of the selected bit depends on the formation hardness characteristics. For

example, long tooth soft bits are used to drill soft formations in shallow depths and

short tooth ones to drill hard formations. Drillibility usually decreases with depth due to

increasing in the rock hardness and overburden. Other factors such as the mud flow

properties and low hydraulic power also make drilling harder at deeper depths.

Generally, milled tooth bits are used for soft to medium formations, insert bits are used

for medium to hard formations while Diamond bits are used for hard and very hard

formations.

Bits are classified according to the International Association of Drilling Contractors

(IADC) code. This code is defined by three numbers and one character. The sequence

of numeric characters defines the “Series, Type and Features” of the bit. The additional

character defines additional design features. The (IADC) bit comparison table is used to

select the best bit for a particular application.

Economic considerations.

The most important factor in bit selection is the drilling cost ($/ft) and the bit cost.

80

Page 96: Final Report-Group 1

This cost can be minimized by selecting the best bit that gives less drilling cost. There

are other factors that effect on the rate of penetration (ROP) and the drilling cost such

as weight on bit (WOB), rotary speed and hydraulics. However, the choice of the bit

type can have a bigger impact on drilling costs than the operating parameters.

For all drilling operating, bit selection should be based on a cost per foot of hole drilled.

This provides a bit comparison based on an optimum relationship between penetration

rate, bit footage, rig cost, trip time, and bit cost. Generally, the equation below is used

throughout the industry to calculate the cost per foot of hole for each bit run.

C=B+R (T+t )

F

Where;

C = drilling cost ($/ft).

B = bit cost ($).

R = rig operating cost ($/hr).

T = drilling time (hr).

t = round trip time (hr).

F = hole drilled by bit (ft).

In this FDP, The proposed bits to use for Gullfaks field are Mill Tooth Bits (for soft to medium

formations) and Tungsten Carbide Insert Bits (for harder formations). And the bit sizes have

been selected according to suitable bit clearance. For example, the table below shows the

selected bits. For the lithology hardness, we assumed that the formation hardness is increasing

with the depth due to the beds’ compaction.

Table 17: Bit Selection and Bit size

HoleSize(in)

Casing size (in) Type of lithology*

Formation hardness

Selected bit size (inch)

Bittype

36 30 Almost soft to medium

Driven N/A

81

Page 97: Final Report-Group 1

26 20Mainly claystone. Almost soft

to medium 26MilledTooth

17 1/2 13 3/8Mainly claystone poorly

consolidated with siltstone and sand.

Soft to medium 17 1/2

MilledTooth with high

IADC code

At deeper depth 17 ½

13 3/8Claystone/mudstone, Medium

17 1/2tungsten carbide

insert bits

12 1/4 9 5/8Mudstone, siltstone,

sandstone.Medium to

hard 9 5/8tungsten carbide

insert bits

4.7 Drilling Fluid System

Drilling fluid system is critical factor for the drilling process and can effect directly on the

drilling pereformance and drilling cost. The primary objectives of the drilling mud are to

remove the drilled cuttings from the borehole whilst drilling and to prevent fluids from flowing

from the formations that have been drilled into the borehole, additional functions of drilling

mud are to maintain wellbore stability, cool and lubricate the bit. Morever, drillinge fluid

enables bit to enhance drilling activity by providing sufficient hydraulic horsepower.

82

Page 98: Final Report-Group 1

Figure 60: Drilling fluid circulation system

In order to achieve drilling mud functions, the optimum density of mud for each hole

section must be estimated based on pressure profile. Mud density must be above the pore

pressure to prevent influx, and less than fracture pressure to prevent formation fracturing and

fluid losses.

There are two most common types of drilling fluid that are always used; water based mud and

oil based mud. Water based muds (WBM) are those drilling fluid in which the continuous

phase of the system is water (salt water or fresh water) and oil based muds (OBM) are those in

which the continuouse phase is oil. There are other types of drilling fluids, i.e. pure gas or gas

liquid mixture (foam). In recent years, the oil based mud has been replaced by synthetic fluids.

WBM has been proposed as a drilling mud for the wells of Gullfaks Field as long as seawater

can be access easily and disposal of them are not hazardous for the environment. According to

the formation types and lithology profile, there are many shale formation sections. These shale

sections may lead to shale reactions if WBM is used. The reactive shale must be treated by

using WBM combines (KCl) with partially–Hydrolyzed polyacrylamide- KCl-PHPA mud.

PHPA helps stabilize shale by coating it with a protictive layer of polymer. It helps to prevent

clay, shale formation from swelling and reducing the possibility of stuck pipe during drilling

operation.

Other additives also can be used to reduce shale reactions such as deflocculant, to avoid

flocculation on the mud system, and Loss Circulation Material (LCM), to minimize the

fliud losses and plug the big porous and permeable holes in the formation. There is

possiblity to add Glycol to reduce torque, increase drilling rate and minimize

environmental impact of drilling operation. In term of additive, weighting and viscous agent

should be used for adequate well cleaning and stability. Chosen additive must be eco-friendly

like using Hematite (Fe2O3) instead of Barite (BaSO4) as weighting material, because its

disposal can settle on seabed.

83

Page 99: Final Report-Group 1

The table below shows proposed drilling fluid types and weight at the shoe for each section,

(according to PCSB Well Design), based on the obtained results from the Casing Seat

software.

Table 18: Mud Program

Hole size (in)

Casing size (in)

Mud type Mud @ shoe (ppg)

26 20 Saline WBM 8.3

17 ½ 13 3/8 KCL/PHPA 11.1

12 1/4 9 5/8 KCL/PHPA 14.4

4.8 Casing Cementation

There are many reasons for using cement in oil well operations. The most important functions

of a cement sheath between the casing and borehole are to prevent any movement of fluids

between the permeable zones, to provide support of the wellbore and to prevent any collapse

of the formation inside the reservoir while drilling. It is also gives support to the casing string

being put in place while providing protection against corrosion from the reservoir fluids.

Table 19: Classification of Well Cement

The American Petroleum Institute (API) classifies well cement into nine classes. They ranged

from class A to class H. The selected type of cement is heavily depend on the conditions of the

84

Page 100: Final Report-Group 1

well being drilled and the formation temperture at the specific target depth. The API class G

cement is proposed to use in Gullfaks field for wells cementing operations. This type of cement

is selected becaues it is compatible with most additives, reasonable depth and can be used over

a wide range of temperature and pressure. Also, it is considered the most common type of

cement that is being used in most areas.

Table 20: Cement Program

Depth (ft)

Interval

Hole Size (inch

)

Casing Size (inch)

Cement Type

Casing Area (ft)Volume

(ft)Volume (bbls)

Volume excess 15%

0-328.1 328.1 36 30 GConductor

  0 0 0  

0-1607.6 1607.1 26 20 GSurface 1.916

71.505

52419.556

0 430.9094 495.5458

0-5248 524817 1/2 13 3/8 G

Intermediate 0.8844

0.6947

3645.9310 649.3199 746.7178

0-7546 754612 1/4 9 5/8 G

Production 0.3988

0.3132

2363.6212 420.9477 484.0898

TOTAL VOLUME 1501.17691726.353

4

Table 21: Summary Cement calculation

Depth (ft) Casing Volume (bbls)water (40%) cement (60%) cement (gal)

cement (sacks)

0-328.1 Conductor   0 0 0 0

0-1607.6 Surface 495.545755 198.218302 297.327453 12487.75303 537.0033507

0-5248 Intermediate 746.7178319 298.687133 448.0306991 18817.28936 809.1886041

0-7546 Production 484.0898172 193.635927 290.4538903 12199.06339 524.5890036

Total Volume 1726.353404 690.541362 1035.812042 43504.10578 1870.780958

85

Page 101: Final Report-Group 1

From the above table , the total amount of cement being used 7610 sacks with 2809 bbl of total mixwater required.

Wellbore Profile

86

100m

490m 537 sacks

1600m810 sacks

Conductor casing 30”36” hole

Surface casing 20”26” hole

Conductor 13 3/8”17 1/2” hole

Page 102: Final Report-Group 1

Figure 61: Wellbore Profile

4.9 Potential Drilling Hazard

There are numerous drilling problems that may occur while drilling even if precautions are considered properly not only to facilities and operation it also brings safety issues to the workers. The most common occurred problems are:

1. Shallow Gas

As mentioned in given data for Gullfaks, potential shallow gas can be confidently interpreted

by using seismic surveys. The only mitigation would be is either drill any pilot hole prior to

opening up and continue with drilling operations or drill with slightly heavier mud that

previously used.

2. Unconsolidated Problems

Stuck pipes could happen when drilling into unconsolidated formation since bond between

particles are weak. Particles in the formations will separate and fall down hole. If there

are a lot of unconsolidated particles in the annulus, the drilling string can possibly be packed

off and stuck.

There are some observable indications of stuck pipe due to unconsolidated formations. One

way is to continue observing the shale shakers if there are unusually high contents of gravel or

sand with increasing mudweight, rheology of the mud and high sand contents in the drilling

mud. Other warning signs include abnormally increasing pump pressure or drilling torque

with losses recorded in the drilling fluid levels in the mud tanks. First mitigation plan is to

87

2300m524 sacks

Conductor 9 5/8”12 1/4” hole

Page 103: Final Report-Group 1

circulate at low pressures. Preventive measures would be to use high viscosity mud to aid in

hole cleaning and the drilling mud to be kept constantly at its specification. The ROP should be

controlled at the depths with known lithology of unconsolidated formation.

3. Shale Instability

This hazard could happen when water in the mud is absorbed by shale formations causing

swelling effect on formations. When there is high amounts of water, shale will not be able to

hold their particles together and finally falls apart into the well. This can lead to borehole

collapse and can cause stuck pipes to occur. The mitigation is to maintain a level of clay

inhibitor in the mud during drilling as well as monitoring the shale shakers for unusual

amount of clay.

4. Hole Deviation

Another drilling problem that is a hazard for the drilling operations of Gullfaks field is the

Hole deviation. This issue describes the unplanned departure of the drill bit from a preselected

borehole path. Deviation of the bit from its original and desired trajectory leads to serious

problems such as higher drilling costs. Several following factors may be responsible for this

occurrence:

Heterogeneous nature of formation and dip angle.

Drill string characteristics, specifically the BHA makeup.

Stabilizers (location, number).

Applied weight on bit (WOB).

Hole-inclination angle from vertical.

5. Lost Circulation

Lost circulation occurs when a fractured or the reservoir has high unconsolidated formation

sections, it can also happen if too high mud weight is used and the formation fracture

gradient is exceeded. The complete prevention of lost circulation is impossible. However,

limiting circulation loss is feasible by applying some specific precautions. These precautions

88

Page 104: Final Report-Group 1

include: Maintaining proper mud weight, Minimizing annular-friction pressure losses during

drilling and avoiding restrictions in the annular space.

6. Borehole Instability

Another common type of drilling hazards that may occurs also for the Gullfaks Field is called

Borehole instability. This type of hazard is the undesirable condition of an open hole interval

that does not maintain its gauge size and shape and/or its structural integrity. The causes for

borehole instability include:

Mechanical failure caused by in-situ stresses.

Erosion caused by fluid circulation.

Chemical caused by interaction of borehole fluid with the formation.

Total prevention of borehole instability is not possible because returning the physical and

chemical in-situ conditions of the rock to its original structure is impossible. Though, there are

some mitigation plans that are applicable in order to prevent this occurrence. These plans

include:

Proper mud-weight selection and maintenance

Proper hole-trajectory selection

Use of borehole fluid compatible with the formation being drilled

4.10 Well ControlWell control equipment and training procedures are very important in the drilling phase

through this project. During drilling operations many problems that may occur such as casing

collapse, casing burst, an influx of the formation fluids into the borehole (kick), blow out,

leaking tube, gas filled casing. The kick occurs when the borehole pressure, due to the column

of drilling fluid, has less pressure than the pressure of formation fluids. To prevent the kick, the

borehole pressure should be higher than the formation pressure at all times during drilling. A

kick must be identified earlier before it can reach the surface in order to prevent blowout.

89

Page 105: Final Report-Group 1

Blowouts occur when an uncontrolled kick in the wellbore reaches the surface. It will cause a

lot of problems and it will complicate well control operations, loss of human life, loss of rig

and equipment, loss of reservoir fluids, damage to the environment and huge cost of bringing

the well under control again.

4.10.1 Kick

A kick is a well control problem in which the pressure found within the drilled rock is higher

than the mud hydrostatic pressure acting on the borehole or rock face. When this occurs, the

greater formation pressure has a tendency to force formation fluids into the wellbore. This

forced fluid flow is called a kick. If the flow is successfully controlled, the kick is considered

to have been killed. An uncontrolled kick that increases in severity may result in what is known

as a “blowout.”

The main causes of kick are failing to fill the hole properly when tripping, swabbing in a kick

while tripping out, insufficient mud weight, abnormal formation pressure, loss of circulation,

shallow gas sands and excessive drilling rate in gas bearing sands.

4.10.2 Kick identification

If a kick occurs, and is not detected, a blowout may develop. The drilling crew must therefore

be alert and know the warning signs that indicate that an influx has occurred at the bottom of

the borehole.

There are Primary Indicators and Secondary Indicators that are potential to become a kick. The

Primary Indicators are flow rate increase, pit volume increase, flowing well with pumps shut

off and improper hole fill up during trips. Secondary Indicators are; drilling break, gas cut mud

and changes in pump pressure.

If a kick has been detected in the bottom hole and all the Primary Control precautions are lost,

the kick will reach onto the surface. In this case, Secondary Control precautions should be done

in order to control the uncontrolled fluid flow. The main precautions should be considered are

as follows:

90

Page 106: Final Report-Group 1

i. Precautions Whilst Drilling:

Raise kelly above the rotary table until a tool joint appears.

Stop the mud pumps.

Close the annular preventer.

Read shut in drill pipe pressure, annulus pressure and pit gain.

ii. Precautions During Tripping:

Set the top tool joint on slips.

Install a safety valve on top of the string (the valve must be open).

Close the safety valve and the annular preventer.

Make up the Kelly.

Open the safety valve.

Read the shut in pressures and the pit gain.

After these precautions are done, the killing mud should be prepared and pump it into the well

in order to kill the well and control it again.

91

Page 107: Final Report-Group 1

4.11 Time Estimation

Seabed 0 0 0Drill 36" hole until 100m 100 1 1Set 30" conductor casing 100 1 2Cement 30" conductor casing 100 1 3Waiting for cement to hardened 100 1 4Drill 26" open hole until 490m 490 2 6Set 20" surface casing 490 2 8Cement 20" surface casing 490 1 9Waiting for cement to hardened 490 1 10

Drill 17 1/2"open hole until 1500m 1600 3 13

Set 13 3/8" intermediate casing 1600 3 16Cement 13 3/8" intermediate casing 1600 1 17Waiting for cement to hardened 1600 1 18Drill 12 1/4" open hole until 1750m 2300 2 20Set 9 5/8" Production casing 2300 3 23Cement 9 5/8" production casing 2300 1 24Waiting for cement to hardened 2300 1 25

Cumulative Duration (Days)

Well Activity Depth,m Duration (Days)

A20

Table 22: Drilling Schedule

92

Page 108: Final Report-Group 1

Figure 62: Depth progress vs time for drilling plan of sample well A20

4.12 Drilling Optimization

Drilling optimizations proposed for this reservoir:

Rotary Steerable System (RSS)

For the deviated drilling section, the Rotary Steerable System is preferable compared to

conventional mud motors. The RSS improves the removal of the drill cuttings from the

wellbore and also eliminating the time for wellbore cleanout. A smoother well trajectory will

induce less drag on the drill string as well as the torque required from the surface.

Multilateral Completion

In this study multilateral completion designs were considered as this development only

involves a total of 10 development wells. Application of multilateral wells may be able to

reduce the number of wellhead and size of topside facilities under some options.

Pile Driven Conductor

93

Page 109: Final Report-Group 1

In order to minimize the installation time, drive pipe conductors will be used. The conductor

threads will be rugged and easy to handle. The threads will also be able to stand high torque.

This would allow for deep stabbing and quick connection makeup. The body will be flushed

internally and externally from any restriction to avoid excess drag. Hydraulic hammer will be

used for piling the conductors. The hammer used should have a good power control and can

records the blows and force required for driving conductors. As there will be many conductors

to be piled, the hammer should have no loss of performance after prolonged operation.

Mono-bore Completion

In comparison to slim well, monobore completion will only use single tubular from the

wellhead until the production zone. This method will significantly reduce the drilling time, rig

time and total drilling cost. Due to considerable high risk formation in Galfaks, further study

may be made to investigate feasible applicable of monobore completion in this development.

Cement Assessment Tool (CAT)

The combination of cement and Swell Technology provides a long term isolation for the micro

annulus. The Cement Assurance Tool (CAT) is to be deployed together with the primary

cementing job at the casing pipe. The benefit of the CAT is that it can effectively seal irregular

borehole geometry with complement to all cement slurry design. For highly deviated and

horizontal wells, they often have greater exposure to the reservoir than vertical well, thus

achieving zonal isolation is critical. An incomplete cement sheath surrounding the cement

might occur if casing centralization is less than optimum, drilling cutting removal not

complete, pockets of viscous mud remaining in well.

94

Page 110: Final Report-Group 1

4.13 New Drilling Technology Consideration

4.13.1New Drilling technologies

Drilling is the only way to get the hydrocarbon out of rocks; therefore, it plays a major role in

exploration and development of oil and gas fields. New drilling technologies should be

discovered and developed so that it reduces the costs and time of drilling and increases the

drilling efficiency. Worldwide, the research groups have been dealing with several innovative

drilling technologies. Their common aim is to significantly decrease the overall price of the

drilling process, particularly to keep the high constant speed, energy efficiency and shorter

drilling time. There are above twenty innovative non-contact technologies at different maturity

such as: laser, water jet, plasma torch, ultrasonic, microwave, and several others. However few

of them reached Proof-of-the-Concept in laboratory and are currently developed in outside

testing sites.

4.13.2 Jet drilling

According to (Jack, et al. 2008) High-pressure rotary jet drilling holds the promise of increased

rate of penetration with reduced weight-on-bit, torque and vibration levels. A high-pressure

rotary jet drill, pressure intensifier and gas separator have been developed to allow jet drilling

using conventional surface pumping equipment and coiled tubing. High-pressure reaction

turbine jet rotors have been developed for drilling holes ranging from 1-1/8” to 3-5/8”. Jet

drilling tests have shown that 70 MPa (10,000 psi) jets can effectively drill most conventional

oil and gas producing formations. Conventional pumps, swivels and tubing operate at up to 28

MPa (4000 psi). A 2.5:1 pressure intensifier was developed to allow jetting at the pressure

required for effective drilling. The intensifier can operate on two-phase flow using a downhole

gas separator. In two-phase operation the separated gas is used to power the intensifier and the

high-pressure water is provided to the jetting nozzles. The gas exhaust from the intensifier is

ported to the drilling head to extend the range of the jets. Tests have demonstrated that the jet

drilling BHA is capable of cement milling but rates of penetration are lower than a motor and

mill and the pumping pressures required are higher. The tools could find applications in

situations where a motor cannot be used. For example the tools could power a small diameter

95

Page 111: Final Report-Group 1

lance jet drill through an ultra-short radius curve for lateral drilling. Well service applications

include removal of hard scale without risk of damage to damage to downhole equipment.

Jet drilling is limited by the threshold pressure required to erode rock and by submerged fluid

jet dissipation. The jet pressure delivered to the rock surface determines the ability of the jet to

cut the rock. The jet power then determines the rate of drilling. The pressure that can be

delivered to a jetting tool through coiled tubing (CT) is limited by fatigue limits of the coil and

the pressure capabilities of available pumps. Approaches to jet drilling at the pressure available

through coil include abrasives, and alternate fluids such as supercritical carbon dioxide or acid.

The consumables associated with these approaches add significant cost and complexity to the

operation. Another approach is to boost the pressure of the jets with a downhole intensifier. A

downhole intensifier has been developed for jet-assisted drilling of 7-7/8” to 8-3/4” holes. The

unit was designed to work with a conventional rotary drill string and to run on drilling mud.

The intensifier area ratio was 14:1 - delivering 84 lpm at 200 MPa from mud supplied at 1260

lpm and 23 MPa. This system provided increased rate of penetration but required higher mud

pressure and the economic benefit was marginal.

A coiled tubing downhole intensifier has been developed to boost fluid pressure by 2:1 to

enable mineral scale milling with standard coil and pumps. A rotary gas separator removes the

nitrogen from the jetting fluid to allow jetting with a straight fluid jet. Dual passage rotary

jetting tools port the nitrogen around the jets to enhance jet range. Jet drilling of oil and gas

producing formations requires a jet pressure of at least 70 MPa. A larger version of this tool

with a higher intensification ratio for rock drilling has been made available as well.

96

Page 112: Final Report-Group 1

Figure 63 Jet drill tool

Figure 64: Test well layout

4.13.3 Utilization of laser technology in drilling

One of these technologies is utilization of lasers. Based on (Bazargan, Et al. 2013), LASER is

the acronym for Light Amplification by Stimulated Emission of Radiation. It is generated by a

device which converts energy to electromagnetic beams or photons. These photons are

97

Page 113: Final Report-Group 1

produced due to the returning of excited atoms to their lower energy state which releases a

photon. This light radiation is then focused to form intense high powered beams which can

fragment, melt or vaporize a rock.

According to (Sinha. P, 2006) Mechanism of rock destruction is due to ‘Specific Energy’ that

is defined as the energy required to move a unit volume of rock for a given laser system. It has

been found that usually specific energy is lowest for shale followed by sandstone and

limestone. This is an important factor as 70% of formation encountered while drilling consists

of shale. Limestone has a high threshold energy compared to sandstone and shale.

4.13.3.1 Rock spallation

The laser radiations incident on the rocks are reflected, scattered or absorbed. Reflected and

scattered beam are the losses while it is the absorbed beam that is responsible for rock heating

and destruction. Again, the absorbed energy is utilized for fusion (melting), vaporization or

spallation of the rock. It has been found that rock spallation is the most efficient and hence, the

desirable mode for rock destruction.

During spallation, the rock absorbs heat resulting in development of cracks within the rock.

The rock weakens and breaks away. Spallation requires lesser specific energy and rock

removal is easier. For spallation, specific energy is found to be inversely related to specific

power. Rate of penetration is related to specific power and specific energy by following

ROP = SP / SE

Here, the basic difference between SP and SE simply lies in the fact that SP is the power

delivered to the laser system while SE is the amount of energy consumed for spallation of a

given formation. Thus to improve rate of penetration, high specific power and low specific

energy should be used. Laser spallation mechanism satisfies the above criterion and hence is

preferable over conventional methods. Spallation is usually attributed to the thermal stresses

induced in the rock upon lasing. The imperfections or flaws existing in rocks are aggravated

upon application of heat via lasing. The rock fails along these flaw lines and finally spalls as in

the following figure.

98

Page 114: Final Report-Group 1

Figure 65: Rock failure due to spalling

Sometimes, in case of thermally conductive rocks, lasing can lead to dehydration of the water

of crystallization associated with minerals present within the rock formation exposed to lasing.

These evaporated vapors expand within the rock volume inducing stresses leading to

mechanical failure and hence promotes spallation. Conditions need to be identified under

which the laser energy will break and remove rock without significant melting as explained by

this figure.

Figure 66 Conditions under which laser removes rock with or without significant melting

99

Page 115: Final Report-Group 1

The zone on the left is spallation zone occurring at lower average power. Melting zone is on

the right. Specific energy for spallation is lowest just before melting. At low laser powers,

considerable energy is consumed by thermal expansion, fracture formation and mineral

decomposition leaving little energy left for destruction of rock material. Hence, as power

increases, rock removal gets more effective. Once melting starts, secondary effects begin to

consume additional energy and SE values increase. Therefore, it is desired for the laser to work

within the spallation zone and as close to the transition zone. Black body radiation and plasma

screening effects can affect the magnitude of specific energy while drilling. When rock

temperature becomes high upon lasing, it turns into an intense source of radiation (black-body).

Result, a substantial amount of incident energy is emitted back. Else, ionized gas (plasma) can

form over the surface exposed to laser. This plasma layer formed just above the lased rock

surface reduces the transfer of energy to rocks.

4.13.3.2 Laser based drilling system design

A laser drilling system would require transferring light energy from a laser system placed on

the surface, down a borehole by a fiber optic bundle, to a series of lenses that would direct the

laser light to the rock face. Large hole can be created by overlapped lasing and creating small

holes adjacent to each other. The exact method for getting the laser energy to the bottom of the

hole is the subject of future paper; hence some type of delivery system has to be designed. One

of the basic decisions in designing a laser based drilling system is over the choice of the laser

system. Drilling rate may no longer depend on parameters like weight-on-bit, mud flow rate,

rotary speed, bit design, bore size. Laser parameters like laser type, wavelength, mode of

operation (CW or RP), power density, beam profile can be considered to develop the most

efficient laser drilling system. Near-infrared radiation can be preferred over visible radiation as

availability of high power lasers is in the infrared.

100

Page 116: Final Report-Group 1

4.13.4 Utilization of Electrical Plasma for Hard Rock Drilling

Based on (Kogis, et al. 2015) The electrical plasma-based tool changes completely from its

inception the paradigm of the drilling as well as casing milling. The most important advance in

comparison to conventional plasma torch technology is that the electrical arc with temperatures

of tens of thousands of degrees Kelvin heats directly the surface, especially the radiation

component, with minimalized heating of intermediate gas (the intermediate gas flow in

conventional plasma torches reduces the efficiency of heat transfer into the rock). Moreover,

the arc creates area-wide, relatively homogeneous heat flow from spiral arc on the whole

surface for high-intensity disintegration process. Compared to conventional plasma torch

technology, electrical plasma-based technology allows the use of electrohydraulic

phenomenon, generating shock waves for the destruction and transport of disintegrated

material. System also allows obtaining electrical and/or optical characteristics of the arc in the

interaction with the rock to derive indirect sensory information (e.g. online spectroscopy for

logging while drilling.). The technology has been tested on various rock types including

sandstone, limestone, halite, granite and quartzite. Currently, the demonstration prototype is

being tested for drilling of testing borehole in the quarry.

Figure 67 Plasma drilling system

Theory

101

Page 117: Final Report-Group 1

The electrical arc with temperatures up to ten thousand of degrees Kelvin heats directly the

surface of the disintegrated material, especially the radiation component, with minimalized

heating of intermediate gas (the intermediate gas flow in conventional plasma-torches reduces

the efficiency of heat transfer into the material).

The heat flow is area-wide, relatively homogeneous by applying long arc on the whole surface

for high-intensity disintegration process.

Rotating spiral arc, in addition to the thermal influence, has “built-in” centrifugal pump

function for disintegrated material removal.

Compared to conventional plasma torch technology, direct electric arc plasma technology

allows the use of electrohydraulic phenomenon, generating shockwaves and pressure waves. It

utilizes generated mechanical power for the destruction and transport of disintegrated material

out of the BHA area.

The pressure waves are generated using high intensity short current pulses. These pulses are

accumulated with a time transformation of charging/discharging from 4 to 7 orders of

magnitude, thus allowing an increase in instantaneous pulse disintegration effect with power

pulses in scale of MW.

The technology is a radical abandonment of the rotary drilling technologies with connected

tubes transferring the torque. Thermal rock-disintegration is a non-contact process, without

vibrations and weight on bit. When drilling using electrical plasma, thermal characteristics

(boiling point, melting point, thermal conductivity) of the rock are determinants for ROP, not

mechanical properties as by mechanical drilling. Based on this feature, drilling in hard rocks

reaches similar parameters as drilling in sedimentary rocks and brings significant benefits in

ROP. The following modes of disintegration are possible distinguishing by plasma

temperature:

● Spallation

● Melting

● Evaporation

102

Page 118: Final Report-Group 1

Current drilling technologies either do not, or only to a restricted extent allow performing Real

Time Data Acquisition (RTDA) using spectroscopy. The reason for this comes from the

incompatibility of spectroscopic devices with drilling mechanisms, which means spectroscopy

cannot be carried out unless the drilling string is pulled out of the well for purpose of drill

bit/tool replacement or delivery of a particular rock sample for analysis. Since the continual

information of the rock composition is crucial for the whole drilling process efficiency, a

market demand has emerged and persists for such system. An example of a long-established

approach in exploration is the method of coring, which however, is considerably more

expensive and the degree of automation is small. The technology uses thermal plasma for rock

destruction. For the purpose of the real-time rock analysis and active feedback, the same

plasma source could be employed to provide material excitation to the spectroscopic signal.

The melted and evaporated rock elements are highly excited and produce radiation of relatively

high intensity. This radiation is characteristic and typical for every chemical element present in

a particular drilled substance. Detection of emitted optical signal is guided by optical fibers to

pre-processing by standard analogue spectroscopic module and finally processed on the surface

by spectroscope and sophisticated recognition by adaptive algorithms.

In this way, constant drilling together with rock analysis could be simultaneously achieved,

unlike the traditional drilling systems, which require additional devices sensitive to vibration or

transporting of rock samples to the surface.

103

Page 119: Final Report-Group 1

CHAPTER 5 PRODUCTION TECHNOLOGY

5.1 Introduction

5.1.1 Overview

Production Technology is a part in production field of the petroleum industry that deals with

optimizing the production of oil, gas from the reservoir, with the least cost using technology,

which in this case is, the design on the well completion system. Completion design is a mix of

physics, chemistry, mathematics, engineering, geology, hydraulics, material science and

practical hands-on well site experience.

Designing the completion system will need all of this information:

• Design Philosophy

• Well Completion Plan

• Wellhead and Christmas Tree Design

• Inflow/Outflow Performance Predictions

• Artificial Lift Selection

In the consequent sections, a detailed study of production technology in Gullfaks field from the

wellbore to the surface aspects was executed. It is delivered by using WellFlo, Weatherford

company software, to perform Nodal Analysis of each well. Initially, oil and gas production

flows naturally from the reservoir. To assist the production, water injection scheme and gas lift

systems were introduced. Besides, various production problems and their corresponding

remedies are also discussed, along with the design recommendations for different

production/well completion components.

5.1.2 Objectives

The objectives of the production technology design are to:

Analyze the production performance and well deliverability under different factors.

Design a safe and effective well completion for producers and water injectors.

Identify potential production problems and propose solutions.

104

Page 120: Final Report-Group 1

Allow future intervention for any production enhancement activities.

5.2 Completion String Design and Philosophy

Design philosophy is the study of assumptions, foundations, and implications of designing the

completion system. Proper completion design is crucial in maximizing recovery and it is so

important to effectively drain out the reservoir fluids to surface, provide subsurface and surface

flow control and safety.

5.2.1 Completion Design

Generally, there are three approaches for completion of reservoir zone, which are open hole

completion, screen or pre-slotted liner completion, and cemented & perforated casing/ liner

completions. Each approach has its applications, advantages and disadvantages, which have

been presented in following table.

Table 23: Comparison between different borehole completion approaches

Type of Completion

Open Hole Completion Screen or Pre-slotted Liner Completion

Cemented & Perforated casing/ liner

Design

Applications Consolidated formations

Low cost / multi well developments

Deep wells,

Inclined/high angles of borehole

Reservoir rock consists of relatively large and homogenous

Wide range of applications

105

Page 121: Final Report-Group 1

consolidated with depletion drive

Naturally fractured reservoirs

Some horizontal and multi-lateral wells

sand grains Dependent upon the

screen or slot sizes and the sand particle sizes

Advantages

Less rig time. Eliminate cementing

and perforating cost. Higher production

with less damage.

Low cost technique Prevent any produced

sand Prevent major

borehole collapse Facilitate the passage

of logging tools

Have proper isolation on any hydrocarbon above the targeted sand.

Selective production can be done with SSD.

Disadvantages

Not recommended for wells where distinctive variations in layeral permeability.

Lack of zonal control for production and injection.

Inability for zonal control and may only effectively control sand

Loss in productivity due to slots may quickly become plugged and impede flow

More rig time to cement and perforate target sand.

Small tubular required for perforation.

Coiled-tubing might be required for perforation.

5.2.2 String completion

There are 2 types of production tubing string; single and dual completion string. Single

completion string is a completion string that is only consists on tubing. This is usually used for

one zone completion, or maybe comingled production. As for dual completion string, there are

2 tubing installed inside the bottom hole, giving the option, for example, to produce from 2

different zone, without let them comingle.

Table 24: Comparison of single and dual strings completion

Completion Type Benefits

Dual Strings Completion

Used in applications in which it is desirable to produce two zones simultaneously while keeping them isolated from each other.

Two strings of tubing are run from the surface to the dual packer. One string terminates at the dual packer, and the other string of

tubing extends from the dual packer to the lower single-string packer.

Single String Completion Corresponds to a single zone of fluids from a single wellbore.

106

Page 122: Final Report-Group 1

Encloses the tubulars, packers, and other tools which enable the flow path for crude oil and natural gases.

Figure 68: Production Tubing String

5.2.3 Type of completion

There are three types of completion accordingly:

i- Sequential Completions

The simplest form of completion string which is consists of 1 tubing string (single

string) with 1 zone of production.

ii- Commingle Completions Two or more zones are produced at the same time, in the same tubing.

Usually being done for zones which produce the same type of oil/gas, or when

producing gas and oil, but separated on the surface, by separator.

However, this type of completion will make the job much more difficult, and more

costly.

107

Page 123: Final Report-Group 1

iii- Selective zone Completions Permits selective production, injection, testing, stimulation, and isolation of various

zones.

Selectivity after completion is accomplished by opening and closing sliding sleeves

between the packers.

5.2.4 Design Philosophy

According to the optimum reservoir simulation outcomes, a total of 7 development wells are

proposed for Gullfaks excluding 3 old producers that have been converted to injectors. The

permeability of reservoir is assumed to be homogenous throughout the production interval.

Since there is only one production interval and the lack of zonal control for production or

injection is also minimized, the single string is suggested. Furthermore, the thickness of pay

zone is adequately high to produce by using vertical well. As presented in Drilling Engineering

Section, due to overpressure and high porosity, high permeability reservoir sands of Gullfaks

field, the formation is weak which will possibly cause sand issues during the production. Sand

grain migrates from the reservoir rock and follows the produced water and oil upstream

causing the production equipment impairment, hence, monitoring in production rates to avoid

damage on the equipment.

Based on several factors and the data discussed, the vertical well completion designed for all 7

single string oil producers is proposed. The production strategy is to produce the oil through

cased hole completion. A sand control screen liner is also installed to prevent the possible sand

problem, which is going to elaborate in detailed subsequently.

108

Page 124: Final Report-Group 1

5.3 Wellhead and Christmas Tree Design

The primary purpose of wellheads is to provide the suspension point and pressure seals for the

casing strings that run from the bottom of the hole sections to the surface pressure control

equipment. Wellheads also provide the structural and pressure-containing interface for drilling

and production equipment. They are rated for working pressures of 2000 psi to 15,000 psi (or

greater). They must be selected to meet the pressure, temperature, corrosion, and production

compatibility requirements of the well.

While Christmas tree is the cross-over between the wellhead casing and the flowline to the

production process. It is defined as all the equipment from and including the wellhead

connection through to and including the downstream flange of the choke. A Christmas tree

controls the wellhead pressure and the flow of hydrocarbon fluids and enables the well to be

shut off in an emergency. It also provides access into the well for wirelining, coiled tubing and

logging operations. The tree must be designed to withstand all pressure levels such as gas

lifting, gas injection, and the pressures arising due to a fracture or kill operation.

The design of wellhead and Xmas tree for Gullfaks field complies with the standard

specification of API 6A Latest Edition. “API Spec 6A is an International Standard that

specifies requirements and gives recommendations for the performance, dimensional and

functional interchangeability, design, materials, testing, inspection, welding, marking,

handling, storing, shipment, purchasing, repair and remanufacture of wellhead and Christmas

tree equipment for use in the petroleum and natural gas industries.”

The figure below shows one example of wellhead and Xmas tree.

109

Page 125: Final Report-Group 1

Figure 69: Wellhead and Christmas tree

5.3.1 Wellhead

Surface wellhead is installed after casing string is run for specific sections. Inside the wellhead

are casing hangers that suspend the casing and provide annulus seal. Wellhead comprises upper

and lower part. Upper wellhead will be installed and suspends the smaller casing string after

the previous casing string. Main functions of wellhead are:

Suspends casing and tubing string.

Provide support for the Blow Out Preventer (BOP) and Christmas Tree.

Sealing off the various annulus pressure and isolation between casings at the surface

when many casing strings are used.

Provides pressure monitoring and pumping access to annuli between the different

casing/tubing strings.

110

Page 126: Final Report-Group 1

5.3.2 Christmas Tree

The basic types of Christmas tree available are:

Table 25: Basic Types of Xmas Tree

Type of Christmas tree Design

1. Single Composite Tree

Used on low pressure (up to 3,000 psi) oil wells, this type of tree is in common use worldwide. The number of joints and potential leakage points make it unsuitable for high pressure, and for use on gas wells. Composite dual trees are also available but are not in common use.

2. Single Solid Block Tree

For higher pressure applications, the valve seats and components are installed in a one piece solid block body. Trees of this type are available up to 10,000 psi, or higher if required.

3. Dual Solid Block Tree

For dual tubing strings, the solid block tree is the most widely used configuration. The valves controlling flow from the deeper zone, the long string, are the lower valves on the tree. While there are some exceptions to this convention, unless the tree is clearly marked it can be assumed that the valve positions reflect the subsurface connections.

111

Page 127: Final Report-Group 1

The design for the Christmas tree of Gullfaks field is listed as below

Table 26: Xmas Configuration

Components Configuration

Active wing valve Hydraulically operated

Lower master valve Local and remote operated

Upper master valve Hydraulically operated

Kill wing valve Local and remote operated

Swab valve Local and remote operated

Additionally, there are two categories of Christmas tree which are dry tree and wet tree. For

dry tree production, the wells are essentially extended to a surface platform where personnel

have ready access to the production tree for operations, maintenance and inspections. While in

wet tree production, the production tree is located on the sea floor, thousands of feet under

water. The following tables present the summary on various features and benefits vs challenges

of Dry Tree & Wet Tree accordingly, in order to be selected in Gullfaks development well.

Table 27: Summary of Dry Tree vs Wet Tree*

112

Page 128: Final Report-Group 1

Table 28: Benefits vs Challenges of Dry Tree & Wet Tree*

Benefits Challenges

Dry Tree

Tree and well control at surface in close proximity of people

Drilling conducted from the facility – reduced CAPEX

Direct vertical access to wells for future intervention activities

Minimal offshore construction

Enable future drilling and expansion

Safety concern due to well access at surface

Large vessel payloads due to the need for supporting risers

Require high cost vessels such as Spar, TLP due to design sensitivity to vessel motions

Complex riser design issues

Limited by existing riser tensioner capacity

Riser interface with vessel require speciality joints, e.g. keel joint, tapered stress joint

Heavy lift requirement for riser installation

Wet Tree

Tree and well access at the seabed isolated from people

Full range of hull types can be used

Low cost hull forms are feasible

Simplified riser/vessel interfaces

Drilling and workover will need a separate MODU or require hull with drilling/workover capability increasing the overall CAPEX

Potentially large vessel payloads due to risers

Flow assurance may be a challenge due to potentially long tie-in

High spec pipe-lay vessels required to install risers and flowlines

*retrieved from SPE presentation

113

Page 129: Final Report-Group 1

5.4 Material Selection

Conductor, surface and intermediate casing are used for structural integrity, which

typically requires significantly larger diameters and heavier weights than tubing. Moreover,

casing is not expected to come into contact with the produced fluids. Thus, approximately

entire casing and liners are commonly made from carbon steel, while there is a small

section of casing that is exposed to reservoir fluids and should generally be made of the

same material as that selected for the tubing. This section is referred to as ‘exposed

casing’ or ‘exposed lining’ and is cemented in place for well bore integrity in some well

designs and also perforated and used for production in others. Therefore, material

selection for casing and tubing is essential for Gullfaks development plan estimated 10 years of

production.

Classifying materials which can be safely deployed is the main focus of the material selection

process. Selection will be determined by parameters associated with the production and

shut in environments, for instance, temperature (e.g., bottom hole and shut in), pH,

chloride concentration, and H2S partial pressure. Particularly, cost considerations, lead

time, quality assurance, and schedule are also influenced factors into the material selection

process.

Reservoir fluids flowing through the production tubing are often corrosive, making necessary

the use of corrosion resistant alloys (CRA) offshore. CRAs contain various quantities of Ni,

Mo, Cr, Cu, and other elements for corrosion resistance, making them significantly more

expensive than carbon steel (CS). Commonly, CRAs can be categorized into four groups in

increasing order of corrosion resistance and cost: Martensitic stainless steel (MSS),

duplex and super duplex stainless steels (DSS and SDSS), super austenitic stainless

steels, and high Nickel Alloys. With the exception of the API 5CT L80 13Cr steel, all

other CRA casing and tubing alloys are proprietary.  As can been seen from Corrosion

Resistant Alloy Selection Process, the appropriate material is chosen based the on presence

of elemental sulfur and a combination of H2S partial pressure, chloride concentration and

temperature.

114

Page 130: Final Report-Group 1

Referred to DST report, no CO2 and H2S were detected from the Gullfaks field. From PVT

data, there is low content of CO2 and no any H2S presence in the production fluid. Corrosion

Resistant Alloy Selection Process shows that required material for Gullfaks is Martensitic

Stainless Steel. The other completion accessories are suggested to use the same material as

production tubing to avoid galvanic corrosion due to dissimilar metals.

Figure 70: Corrosion Resistant Alloy Selection Process*

*Retrieved from http://www.gateinc.com/gatekeeper/gat2004-gkp-2014-08

115

Page 131: Final Report-Group 1

5.5 Perforation Techniques

In cased hole completions (the majority of wells), once the completion string is in place, the

final stage is to provide the communication path between the well-bore and all desired zones.

These activities are known as perforation, which use explosive charges to produce holes

through the wall of the casing, the cement sheath and penetrate into the formation, thereby

allowing oil or gas to flow to the surface as well as evaluating and optimizing production

rate/injectivity from each zone.

Perforating is accomplished by using a perforating gun - loaded with shaped charges - that is

lowered into the well and detonated in the wellbore.

5.5.1 Shaped Charged Characteristic and Performance

The basic shaped charge consists of a conical liner, a primer explosive charge, the main

explosive charge, and charge case or container, which is illustrated in the following figure.

Figure 71: Shaped Charged Components

The main explosive charge is extremely powerful in energy releasing specific energy per unit

weight of explosive. Detonation of the main charge is complete after only 100 -300 micro

seconds. This fast reaction time is of importance in that it concentrates the detonation energy of

116

Page 132: Final Report-Group 1

the exploding charge to very limited target area. The impact pressure caused by the jet is

approximately 10 to 15 million psi. This pressure overcomes the casing and formation strength

and forces material radially away from the jet axis. In addition, a conical liner concentrates the

explosive force so that it provides maximum penetration of the target over a limited area.

Depends on the shape of conical liner that gives different effects into the formation (See Figure

below):

(a) A flat ended charge spreads the force of the explosion over a wide area of the target with

very limited penetration.

(b) A conical shaped charge concentrates the force of the explosion and provides greater

penetration.

(c) If the conical cavity is lined with a metallic liner, the penetration is greatly increased by a

lined conical cavity.

Figure 72: The importance of using a conical liner in a shaped

Furthermore, charge container can be either a metal or a disintegrateable case e.g. ceramic. The

force of the explosion on a specified target area is directly assisted by a metal case. The angle

of the cone and the liner material determines the penetration depth and the perforation's

diameter (for a given charge weight). A copper liner gives a wide diameter hole (< 1.0 in.) as

117

Page 133: Final Report-Group 1

used for sand control or popped hydraulic fractured completions, while a deep penetrating

charge (~ 0.5 in. diameter) uses a sintered metal liner. The display below is an example.

Figure 73: Picture demonstrates the angle of the cone and the liner material determines the

penetration depth and the perforation's diameter

5.5.2 Spacing

Spacing in perforation system is the distance between the perforations, and is affected by

perforation density and phasing. Spacing of each charge should be sufficient in order to avoid

the mutual overlapping of the elastoplastic stress areas in the vicinity of perforations during oil

and gas production and prevent the sloughing and failure of single perforation from leading to

a chain reaction, thus avoiding the sloughing and sand production of the whole perforating

section. In addition, when having larger perforation spacing, it will cause smaller mutual

118

Page 134: Final Report-Group 1

interference between perforations, thus, result in lower perforation density. Furthermore, sand

migration and production may be generated because the flow rate of single perforation for low

perforation density is high. Shot density that indicate by shot per foot (spf) and phasing also

affect stability of perforation tunnel.

Figure 74: Perforation Charge Arrangement

119

Page 135: Final Report-Group 1

5.5.3 Gun size

The gun size to be used for the perforating activity must have the size that is almost near the

casing size and with a minimum gun clearance of ½ inch. For instance, to perform the

perforation in 7-inch casing, the 5-inch casing gun will be used for the execution. Moreover,

the size of the perforating gun will dictate the maximum explosive load which can be

accommodated in the charges.

5.5.4 Conveyance Methods

In general, there are two types of conveyance method, which are tubing conveyed perforation

(TCP) and wireline conveyed perforation. However, TCP is much more favorable than the

wireline, because TCP has its advantages as following:

The ability to use large charges at high shot densities; creating perforations with a long

length and with diameter entrance holes (negative skin) completions.

The perforating operation can be completed in one run even for long intervals. Intervals

in excess of 1,000 m have been shot in one run.

The well is not perforated until after it has been completed and it is safe to allow well

fluids to enter the wellbore.

Perforating can be done either in underbalance, balance/slightly overbalance, and extremely

overbalance.

i. Underbalanced Perforating

High flow capacity formations where perforation may be a choke on flow.

Natural completions in thinner zones with high reservoir pressures

Where later operations will be underbalanced

Competent sandstones (some exceptions; cavities for instance)

Where the best possible test is needed

ii. Balanced / Slightly Overbalanced Perforating

120

Page 136: Final Report-Group 1

Only when the wellbore fluid is non-damaging and low particulate.

When fracturing – note that high overbalance may make breakdown more

difficult.

When perforation tunnels can collapse at the slightest underbalance

iii. Extreme Overbalanced Perforating (EOP)

EOP is a process that breaks down perforation by high pressures generated by

high gas pressures or gas generating charges.

Where perforation breakdown is very difficult or expensive (pumping

equipment).

Where permeability is low (<1 md) and typical perforation with underbalance is

not effective.

Where permeability is high (k >100 md) and no fracturing planned, but damage

bypass is needed.

Figure 75: Results of underbalanced, balanced and overbalanced perforations

121

Page 137: Final Report-Group 1

5.5.5 Perforation Design

After considering different perforation parameters, the consequent table summarizes suggested

perforation designs for Gullfaks field planning. It is benefit in achieving successful perforation

performance, providing ideal communication path between the well-bore and all desired zones

and obtaining the optimum production rate from each zone.

Table 29: Summary of the perforation system selected

Parameters Selection Justification

Perforation Density (spf)

12 Low flow rate of single perforation, low fluid velocity, low sand

Phase 30 Provide more efficient flow characteristics

Charge Type Big Hole Provide mechanical stability, big hole that make the gravel packing process become efficient, and because of the sand formation that easily can cause the tunnel to become smaller.

Penetration Depth <10ft

Perforation Diameter

8-10 times size of the

particle

Best effectiveness

Conveyance Method

Tubing Conveyed Perforating

(TCP)

Since it will be going to be overbalance perforation, this is suitable for overbalance perforation; that withstand high pressure.

122

Page 138: Final Report-Group 1

5.6 Well Completion Plan

5.6.1 Summary

To achieve successful well completion for Gullfaks field, the following option has been given:

Table 30: Well Completion Option for Gullfaks field

Completion Parameters Options Tubing size Range from 2-3/8” to 5-1/2” Type of completion Single String Tubing material Carbon steel, Low Alloy Steel or

Corrosion Resistance Alloy (CRA) Completion Cased holePerforation Tubing Conveyed Perforating Artificial Lift Gas Lift Sand Control Gravel Pack

5.6.2 Well Completion Matrix

A total of ten wells are proposed for Gullfaks which consists of seven oil producers and three

water injectors. Sand control method selection will be mentioned in Sand Control Section of this

report. The conceptual well completion matrix is summarized in table below based on the

location of the well.

Table 31: Well Completion Matrix for Gullfaks Field

Well Name Type Description Remarks

A10 SS Cased hole, TCP Perforation

Gravel Pack

Oil Producer Well

A15 SS Cased hole, TCP Perforation

Gravel Pack

Oil Producer Well

A16 SS Cased hole,TCP Perforation

Gravel Pack

Oil Producer Well

A19 SS Cased hole, TCP Perforation

Gravel Pack

Oil Producer Well

123

Page 139: Final Report-Group 1

A20 SS Cased hole,TCP Perforation

Gravel Pack

Oil Producer Well

B9 SS Cased hole, TCP Perforation

Gravel Pack

Oil Producer Well

C5 SS Cased hole,TCP Perforation

Gravel Pack

Oil Producer Well

B8 SS TCP Perforation, Inject water into

acquifer

Water Injector Well

C4 SS TCP Perforation, Inject water into

acquifer

Water Injector Well

C6 SS TCP Perforation, Inject water into

acquifer

Water Injector Well

5.6.3 Proposed Completion Schematic

Well schematic is a tool string design with configuration of completion components and

tubing. The selection of components is varying with the tubing size which is essential to take

into account to make sure that the selective components will provide the continuous flow path

with minimum flow restriction that happen due to components’ groove profile.

The design the basic tool string is assumed that all wells having the same conditions. The

following proposed schematics diagram consists of single string oil producer and single string

water injector. The selection components must be based on tubing size.

124

Page 140: Final Report-Group 1

: WEIGHT: : 310 PPF: : 133 PPF: : 68 PPF: : 43.5/47 PPF: 130 m :: XXX m-AMSL : -

: XXX m

Flow Coupling

TR-SCSSSV

Flow Coupling

GL Mandrel

GL Mandrel

GL Mandrel(GLV Dummy)

Sliding Sleeve(Closed)

13-3/8" shoe Casing setting depth

Sliding Sleeve (Closed)9-5/8"sump packer

8.313" Bore XN Nipple

POP AssemblyEnd of Tubing

9-5/8"sump packer

Proposed by Ngo Nguyet Tran -Group 1

TD at XXX m-MDDF

9-5/8" shoe

RESERVOIR (Oil Producer)

Sand Interval: XXX - XXX m-MDDF

Perforation Method: TCP

Gravel Packed

(Depth TBC) Liner

(Depth TBC)

(GLV Orifice)

(GLV Unloading)

(self-equalizing type)

TBC

IN INEQUIPMENT

MIN ID MAX OD

Note: All depths are in meter from Sea BedDEPTH LONG STRING

m-MDDF (OIL PRODUCER)

DRILL FLOOR TO THF

WATER DEPTH LINERMAXIMUM DEVIATION 55-60 deg PRO. CASING 9-5/8" 2300m-MDDFPBTD ? m-MDDF INT. CASING 13-3/8" 1600 m-MDDF

TBC

WELL NAME: XXX Oil Producer

LOCATION / SLOT: GULLFAKS Block 34/10

PROPOSE COMPLETION SCHEMATIC

DATE OF COMPLETION SIZE DEPTHRIG CONDUCTOR 30" 100 m-MDDFTD XXX m-MDDF SUR. CASING 20" 490m-MDDF

DRILL FLOOR HEIGHT TUBING TBC

Figure 76: Single String Oil Producer Tubing

125

Page 141: Final Report-Group 1

: WEIGHT: : 310 PPF: : 133 PPF: : 68 PPF: : 43.5/47 PPF: 130 m :: XXX m-AMSL : -

: XXX m

Flow CouplingTR-SCSSSVFlow Coupling

13-3/8" Casing setting depth

9-5/8" Hydraulic Packer

8.313" Bore XN Nipple

POP AssemblyEnd of Tubing

9-5/8" shoe

WELL NAME: XXX Injector

LOCATION / SLOT: GULLFAKS Block 34/10

PROPOSE COMPLETION SCHEMATIC

DATE OF COMPLETION SIZE DEPTHRIG CONDUCTOR 30" 100 m-MDDFTD XXX m-MDDF SUR. CASING 20" 490m-MDDFPBTD ? m-MDDF INT. CASING 13-3/8" 1600 m-MDDF

WATER DEPTH LINERMAXIMUM DEVIATION 55-60 deg PRO. CASING 9-5/8" 2300m-MDDF

DRILL FLOOR HEIGHT TUBING TBC -

Note: All depths are in meter from Sea BedDEPTH LONG STRING

DRILL FLOOR TO THF

m-MDDF (OIL PRODUCER)

MAX OD

IN INEQUIPMENT

MIN ID

TBC

(self-equalizing type)

13-3/8" Hydraulic Packer

(Depth TBC) Liner

WATER ZONE

Interval: XXX - XXX m-MDDF

Perforation Method: TCP

TD at XXX m-MDDF

Proposed by Ngo Nguyet Tran -Group 1

Figure 77: Single String Water Injector Tubing

126

Page 142: Final Report-Group 1

5.6.4 Completion String Design and Accessories

The production strategy is to produce the oil from single zone through open hole completion

with packer isolating the casing and tubing in order the fluid to flow only through the tubings.

Following are the design for the downhole completion:

i. Single tubing string of 3-1/2” ID is proposed at this moment. It may be changed upon

the Nodal Analysis to meet the required targets.

ii. For well control, tubing retrievable SCSSV is proposed for completion. Retrievable

vales are preferred as it is easier to maintain and to be replaced when broken, while O-

rings of the valves may be permanently damaged during production/well intervention

campaign.

iii. Flow coupling, X-Nipple and XN-Nipple will be installed as per standard practice for

oil producer. Nipple is to ease the future well intervention campaign. In addition, No-go

nipple (XN Nipple) is to avoid any wireline tools from dropping off the string. Flow

coupling is to protect from internal and external erosion caused by high velocity &

turbulence flow.

iv. Three Gas lift mandrels (GLM) with dummy valves will be installed to enable future

installation of gas lift valves.

v. Gravel pack is installed in order to prevent or control the sand production.

vi. For safe measures and double barrier precaution, single hydraulic retrievable packer

will be used for single string oil producers. The hydraulic packer will act to prevent

communication between the different sands. Hydraulic packer is recommended for

deviated or horizontal well because no tubing movement is required to set the packer,

thus this is important during well completion. Communication is only allowed by

opening the sliding slide doors.

vii. As for the water injectors, a higher grade of hydraulic packer or permanent packer is

required for internal isolation in order to overcome any temperature and pressure

change should the cold injected water and hot oil produced will influence the downhole

thermodynamic and pressure systems.

viii. In the future, gas conning is highly expected to breakthrough in the horizontal section

due to the thick gross volume of gas cap (150m) above the producing oil zone. Future

127

Page 143: Final Report-Group 1

zone change activities are expected, so that gas conning problem can be control.

Because of that, XD-SDD (wireline control SSD) cannot be used due to high

inclination angle (>80 degree) of horizontal section. Hence, hydraulic surface control

SSD is suggested to achieve an effective reservoir management campaign and to ease

the future well intervention activities.

ix. It is necessary to periodically monitor reservoir pressures in order to determine if all the

reservoir units in Gullfaks are behaving as one pressure system or not. The installation

of Permanent Downhole Gauge (PDGs) as an improved well monitoring system in

selected wells will provide the pressure data when required. Re-evaluation of reserves

status, reservoir drive mechanisms and development strategies depend heavily on

correct knowledge of reservoir pressures.

128

Page 144: Final Report-Group 1

5.7 Inflow/Outflow Performance Prediction

5.7.1 Nodal Analysis

Using the data from the Reservoir part of well test, the completion can be designed using the

concept of finding the optimum tubing size for the completion and allows to determined flow

potential or deliverability of the wells by finding the common value of the production rate for

inflow and outflow (IPR and OPR) as well as bottomhole pressure (BHP). Furthermore, based

on the Production Technology notes (2010), it is stated that, an estimation of the expected

production rates at various times in the field's life is the proper way to design the tubing string.

This is because by gaining the information on these volumes, required size of the production

can easily be estimated.

Hence, NODAL Analysis approach will be used as it is an analytical tool that used to enhance

well production by optimizing well completion design. This approach views the total

producing system as a group of components which includes all the components upstream and

downstream such as separator, surface choke, well bore pressure and reservoir pressure. By

doing this, completion design to suit reservoir deliverability and any restriction that may exist

in the system can be identified thus improving production efficiency. An improper design of

any one component, or a mismatch of components, adversely affects the performance of the

entire system.

Additionally, node can be select anywhere in the production system as it can be as reservoir,

wellhead or at the wellbore. Then, all the components upstream of the node comprise the

inflow section, while the outflow section consists all of the components downstream of the

node. A relationship between flow rate and pressure drop must be available for each

component in the system for the analysis to be made. Nodal analysis is performed on the

principle of pressure continuity, where there is only one unique pressure value at given node

regardless of whether the pressure is evaluated from the performance of upstream or

downstream equipment.

129

Page 145: Final Report-Group 1

The performance curve (pressure-rate relation) of upstream equipment is called inflow

performance curve and the performance curve of downstream equipment is called outflow

performance curve. The intersection of the two performance curves defines the operating point,

which is operating flowrate and pressure, at the specified node.

5.7.2 Base Case Model

The models for well development were generated using PROSPER, a production simulation

software from Petroleum Experts, based on available data from exploration and appraisal wells

of Gullfaks field. Well A20 is used for the analysis with some assumptions are made to

represent the whole reservoir, for instance, permeability and water depth were taken as average

value; reservoir properties (oil gravity, GOR, gas gravity, etc..) were made with well test and

associated with Petrel value; tubing ID is 4.052”; cased hole completion; and so on …

The data will be coming from the test point data of the well test report. The main flow data

consist of the following:

Reservoir pressure

Well test production data

Wellhead pressure

Reservoir layer pressure for the interested zone

Bottomhole temperature

Mid perforation depth

Effective permeability (assume Darcy skin equal to zero)

5.7.2.1 Inflow Performance Relationship (IPR)

Vogel model is used in the construction of Inflow Performance Relationship Curve shown the

figure below. Calculated productivity index (PI) based on data given is 3.36 stb/day/psi

generates an absolute open flow (AOF) of 4834.7 stb/day for matching with the development

plans (See Figure Base Case IPR for Gullfaks Field. The Glaso correlation is used for the gas

solution, bubble point pressure and formation volume factor, while Beggs et al has been chosen

130

Page 146: Final Report-Group 1

to represent the vertical flow correlation for Gullfaks field. All the correlation mentioned above

yield a high accuracy during the matching process compared to the other correlations.

Figure 78: Base Case IPR for Gullfaks Field

5.7.2.2 Operating Point

Operating point is the point where the IPR curve intersects with Vertical Lift Performance

(VLP) at specific pressure and flow rate at a given condition. The operating point of the

Gullfaks well was constructed using Prosper as well. The simulation result is show bellowed.

The natural flow for the base case model can be predicted from the intersection between the

inflow performance curve and outflow performance curve shown in the following Table.

Table 32: Base Case Calculated data from Prosper

Productivity Index, STB/day/psi 3.36

131

Page 147: Final Report-Group 1

Absolute Open Flow, STB/day 3384

Operating pressure, psia 1570

Producing capacity, STB/day 1910

Figure 79: Base Case Nodal Analysis

132

Page 148: Final Report-Group 1

5.7.3 Water Cut Limits

As seen from the values of the table, the greatest oil production rate will be at its initial state

whereby reservoir pressure is 2516 psia with 30% of water cut. As the reservoir pressure

depletes, it is shown that the oil production decreases. Similarly, increasing percentage of

water cut for the same reservoir pressure will still decreases the oil production rate. Increasing

fw will increase total liquid density, GLR decreases because gas comes from the oil phase.

Thus, hydrostatic component increase causes BHP increases with water cut, ultimately shifted

the intersection point to the left.

With a water injection scheme in place, it is expected to face even more severe water

production from Gullfaks. One way of dealing with such a problem is to plug-off “watered-

out” perforations. The advantages will be prevent, reduce or isolate water production, hence no

need to dispose water, which results in cost-saving and increases flowing pressure, allowing

higher flow rates at upper zones. Stability of zones also increases. However, there are

disadvantages such as if cement plug is set it could damage the formation, reducing

permeability and increase the skin effects, and thus, reduces production. Solutions that are

injected in plugging operation can reduce hydrocarbon flow out of producing formation.

Plugging off operation is costly and time consuming.

Table 33: Effect of water cut on various reservoir pressures

Oil Production Rate (STB/d)

Reservoir Pressure

(psia)

2516 2400 2300

Wat

er C

ut

(%)

30 1910 1700 1520

40 1825 1605 1430

50 1712 1485 1310

60 1553 1345 1150

133

Page 149: Final Report-Group 1

5.7.4 Tubing Selection

Tubing is one of the important component parts in the production system of a flowing well and

is the main channel for oil and gas field development. It is a tube used in a wellbore through

which production fluids are produced (travel). So, the size of the tubing should be selected,

carefully and according to the condition of the well. This is to ensure that the energy

consumption for lifting and the longest flowing time from the wellbore to the surface can be

utilized rationally and efficiently. Since size will affect much on the production, proper tubing

size must be used because going undersize and oversize can lead to different cons. If it is

undersize, the flow velocity will be excessive, thus, the increase of friction between the

flowing fluid and the wall of the tubing and result in the tubing will limit the production rate.

Contrarily, oversized tubing may lead to an excessive liquid phase loss due to slippage effect

or an excessive downhole liquid loading during lifting. In order to tackle this matter, sensitivity

analysis of tubing size should be carried out using the nodal analysis method.

The intersections of the TPR curves and the IPR curve are just the production points under the

various tubing sizes. In general, increasing the tubing size will increase the production rate of a

flowing well, as shown in Figure below for reservoir pressure of 2516 psia. However, when the

tubing size exceeds the critical size, the increase in tubing size may lead to a decrease in

production rate.

134

Page 150: Final Report-Group 1

Figure 80: Sensitivity analysis on tubing size for reservoir pressure 2516psia

It can be observed from table below, the optimum tubing size is 5.5” OD with 4.767” ID. As

discussed earlier, if the tubing size exceeds this critical size, the increase in tubing size may

lead to a decrease in production rate. This is because it increases friction & consequently

pressure drop decreases up to a certain point. Therefore in this completion tubing with 5.5”OD

can be chosen.

There are two main factors in choosing the most optimum production tubing size. Firstly, the

tubing size that is selected must have a lower pressure drop due to friction and turbulence. So

since larger tubing size will yield lower frictional flow, it will cause lower pressure drop, and

thus, maintain an optimized oil production rate. Second factor will be the water cut. The aim is

to get high oil rate. This means we should increase of tubing size. However, by this, we need

135

Page 151: Final Report-Group 1

more energy to lift up the oil, so need high water cut (so that energy needed is less). But this

water cut can't be too high to avoid excessive water production.

Table 34: Different tubing sizes with different reservoir pressure

Oil Production Rate (STB/d)

Reservoir Pressure

(psia)

2516 2400 2300

Tu

bin

g ID

(in

ches

)

2.992 1495 1260 1125

3.548 1575 1525 1370

3.954 1880 1675 1490

4.052 1910 1680 1505

4.767 2125 1870 1700

136

Page 152: Final Report-Group 1

5.7.5 GOR Sensitivity

As shown in below table for 2 phase (liquid + gas), GOR has more effect than any other

variables GLR increase, liquid holdup decreases hence there will be decrease in hydrostatic

component. However, total rate is increasing, and friction loss component depends on rate

squared. One of the best methods is using gas lift to increase GLR but up to certain point only.

The table also shows that beyond GOR of 6000 scf/stb the production rate will decrease.

Table 35: GOR values with different reservoir pressure.

Oil Production Rate (STB/d)

Reservoir Pressure

(psia)

2516 2400 2300

GO

R (

SC

F/S

TB

)

1000 1910 1700 1520

2000 2175 1950 1770

3000 2300 2075 1890

4000 2355 2130 1950

5000 2370 2150 1965

6000 2360 2140 1960

137

Page 153: Final Report-Group 1

5.8 Artificial Lift Selection

5.8.1 Selection Criteria

Artificial lift is defined as any method used to raise oil to the surface through a well after

reservoir pressure has declined to the point at which the well no longer produces by means of

natural energy. Artificial lift is essential in wells when there is inadequate pressure in the

reservoir to lift the produced fluids to the surface, but often used in naturally flowing wells

(which do not technically need it) to increase the flow rate above what would flow naturally.

The produced fluid can be oil, water or a mix of oil and water, typically mixed with some

amount of gas.

The most common of artificial lift are: rod pumps, electrical submersible pumps, hydraulic

pumps, progressive cavity pumps, gas lift. Selection of most economic that yields optimum

production is very crucial to the success of production development phase. All five artificial lift

are compared according to different well condition show in tabulated form below.

There are several artificial lift methods available, but due to certain constraining factor, only

gas lift and Electric Submersible Pump (ESP) is been considered to be install in this well. Main

consideration is offshore located well and it is currently producing solution gas together with

the oil production. These automatically rule out rod pump and hydraulic pump.

Gas lift valve can be used to a useful life of 10-20 years compared to the ESP which can last

for only 3-6 years before they are required to be changed and maintained. Nevertheless, ESP

may be the best artificial lift method in the world at current stage where almost 70% of the

world oil productions are from the utilization of ESP. However the productions are most often

for high production well ranging from 1000-64000 stb/day. Since for Gullfaks wells, we are

producing at the rate approximately 2000-3000 stb/day per one well, it would not be

economical for ESP utilization in the field since there is higher capital and maintenance cost

involved, where having gas lift on site would be sufficient to produce.

138

Page 154: Final Report-Group 1

Table 36: Artificial lift methods and its features

Well

Condition

Rod Pump PCP Gas Lift ESP Hydraulic

Pump

Design

Operating

Depth

Fair Fair Good Fair Very good

Operating

Volume

To 6,000

BFPD

To 4,500 BFPD

To 30,000 BFPD

To 40,000 BFPD

To 15,000 BFPD

Temperature To 550 F To 235 F N/A To 400 F To 550 F

Service Workover or

Pulling Rig

Workover or

Pulling Rig

Wireline or

Workover

Rig

Workover or

Pulling Rig

Hydraulic or

Wireline

Scale Fair Fair Fair Poor Fair

Sand Fair Good Very good Fair Poor

High GOR Poor Fair Very good Good Fair

Deviation Poor Fair Very good Good Very good

Paraffin Poor Good Poor Good Poor

Corrosion Good Fair Fair Fair Poor

139

Page 155: Final Report-Group 1

5.8.2 Gas Lift Design

5.8.2.1 Design Basis

Using the gas lift method, gas injected reduces the density of the produced fluid assisting the

fluid flow from the reservoir through the tubing to the wellhead. The gas is injected through

gas lift valves, which are run in side pocket mandrels together with the tubing string, and is

designed so that only one valve is open passing gas at one time. The purpose of injecting gas

into the tubing is to decrease the density of the flowing gas liquid mixture and therefore

decreasing the required flowing bottomhole pressure.

There are two types of gas lift. One of it is continuous flow gas lift. The main feature in the

continuous flow gas lift is merely to lighten the gradient in the liquid column so that the

reservoir pressure available will be adequate to cause flow to occur or to increase.

Alternatively, the other type of the gas lift maybe used when reservoir will not produce in a

continuous manner. This method is called intermittent gas lift because a column of liquid is

allowed to accumulate in the bottom of the well and then a large volume of gas is quickly

injected below this column to lift it to the surface. This cycle is repeated at an experimentally

determined optimum combination of fill-up time, the liquid column lifting time and volume of

gas injected. As a reservoir depleted, it may become necessary to consider gas lift as primary

artificial lift to maintain economic oil recovery.

The main concerned in gas lift design is the specification, facing and pressure setting of the

unloading and operating valves in order to initiate and maintain oil production with economic

gas injection rate. After design installation, a primary concern in the daily operation of gas lift

is the cost of the gas compression facilities. This can be uneconomic if the excessive gas

volumes are circulated due to shallow injection depth or if excessive volumes are circulated

with diminishing returns. The first of these is due to faulty design. The latter is due to improper

operation of even a correctly designed system.

Gullfaks field development is in appraisal phase so most of the variables are not available even

in the Gullfaks previous well test data. As it is stated in the given proposal that Gullfaks well

will start using gas lift after 4 years of production then the production string must prepare for

gas lift operation by including the Gas Lift Mandrel (dummy) in tubing string design. For

140

Page 156: Final Report-Group 1

Gullfaks gas lifting system, side pocket mandrels with dummy valves will be installed initially

in the production string. When gas lift is required, the dummy valves can be replaced with gas

lift valves using wireline. The aquifer support is estimated to be weak and gas lift will be

required after 4 years of production in the case of high water production.

5.8.2.2 Production Analysis by using Gas Lift Method

The design developed by Prosper software consists of three Valves, where the operating valve

is located at the lowest desired position accordingly:

Valve 1 (24/64th inch) located at 1136.79m MD

Valve 2 (32/64th inch) located at 1572.51m MD

Valve 3 (operating valve – 34/64th inch) located at 1699.07m MD

Under natural flow depletion without any support from artificial lift, at 30% water cut, oil

production rate is about 1910 STB/D while gas production rate is 1.91MMscf/d. By installing

continuous flow gas lift with the proposed design above, Prosper simulator demonstrates that

oil production rate can be increased to approximately 2117 STB/D by injecting 1.5 MMscf/D

gas into wellbore (as shown in below table). Additionally, this amount of gas is taken from

available produced gas to inject back into the well as cost saving. Therefore, Gas Lift is

proven to be the best method to be installed as artificial lift in Gullfaks field.

Table 37: Comparison on production before and after installing Gas Lift

WC Oil (stb/d) Water (stb/d) Gas (MMscf/d)  30 1910.64 818.845 1.91 No Gas Lifted

30 2117.32 907.421 2.331.5 MMscf/d of

Gas Lift Injected

141

Page 157: Final Report-Group 1

A clear comparison on benefit of Gas Lift on Oil rate under various water cut conditions (30-

80%) is illustrated in following graphs.

Figure 81: Oil rate at different water cut without Gas Lifted

Figure 82: Oil rate at different water cut with Gas Lifted

142

Page 158: Final Report-Group 1

Furthermore, as illustrated in following graph, the higher amount of gas is injected, the higher

oil production rate obtained. However, the increment is up to an optimum point, whereby if the

injection rate is beyond this limit, it will have reverted effect, the production rate will be

decreased. In this case, maximum gas lift injection rate is 7.5 MMSCF/D to produce

approximately 2250 STB/D.

Figure 83: Oil production influenced by various gas lift injection rate

143

Page 159: Final Report-Group 1

5.9 Sand Control

5.9.1 Sand Failure Prediction

Sand formation is a natural activities or properties in a formation that cause the unconsolidated

sand from the formation to enter the wellbore, and sometimes, being produced together with

the oil; sand production. The key factor in sand production is the formation failure which is

governed by in-situ stresses in addition to the mechanical properties of the rock. Stresses

around wellbore / perforations are more concentrated and weak rocks (unconfined compressive

strength less than 1000 psi) are prone to deformation under these conditions. In addition,

drilling and perforating contribute to damage in the near wellbore region of the formation. The

fluid production and the associated drag force applied on the weakened formation induce

erosion at sandface and sand grains are transported up the wellbore.

The two key processes in the physics of sand production are:

i. Stresses acting on the rock surrounding the wellbore must exceed the strength of the

rock so that it fails.

ii. Transport (fluid flow) is required to move sand from the failed zone into the production

system.

Rock will not fail due to fluid flow alone. Rock only fails as a result of stresses acting in the

near wellbore area. These stresses are caused by the pressure difference between the formation

and the wellbore (that is, drawdown and/or depletion), fluid frictional forces and the tectonic

forces acting through the formation (weight of overburden, and horizontal stresses). When the

magnitude of the combined forces exceeds the strength of the formation, the rock will fail, and

sand may be produced. In the failed zone a highly plastic state must prevail for the drag forces

introduced from fluid flow to move sand from the formation into the well. The implication is

that there will be a critical flow rate or drawdown pressure below which sand will not be

produced. If this rate is below a desired production rate, some form of sand control is

necessary to maintain well integrity.

144

Page 160: Final Report-Group 1

The following depiction is an example of potential sand production occurrence where the failed

zone around a perforation tunnel and providing the source of sand production is highlighted in

red. The radius of the failure zone can be several times the radius of the opening depending on

the rock strength, stress and flow conditions.

Figure 84: Potential Sand Production

5.9.2 Problems Caused by Sand Flow

Sand production causes severe issues and several integrity challenges. In high rate gas wells,

especially in a subsea completion environment, sand production leads to serious and dangerous

erosion because of the velocity of the sand grains striking the tubulars and/or surface facilities.

Sand production in water injectors is also an issue especially where cross-flow can occur.

Cross flow generally occurs from low permeability to high permeability layers in water

injection wells after shut-in. However, since low permeability sands typically will have higher

rock strength, they may not produce sand. Sand is also restricted from flowing out of the

perforation cavities due to sand bridging. This bridging will tend to break down dependent on

a large number of variables, including; perforation geometry, sand size, well angle, wettability

factors, capillary forces, differential pressure and flow rate. Among these factors, wettability,

145

Page 161: Final Report-Group 1

capillary forces, and in situ stresses tend to prevent movement of particles and enhance sand

bridging.

On the other hands, in low PI wells, some companies advocate deliberately inducing sand

production to stabilise the formation. This removes near wellbore formation damage which

can result in a significant increase in PI. Recent experience in the North Sea on one platform

showed that sand production increased PI by up to 120% in some wells and by 40% on

average. However, this process demands a rigorous approach to sand surveillance monitoring

and well monitoring, surface handling and disposal of sand and represents a high risk strategy.

5.9.3 Sand Control Consideration and Design

5.9.3.1 Sand Management

Sand management requires an understanding of the mechanisms that cause sanding and the

development of a field-validated methodology to predict the critical conditions for sand

production. Nowadays, sand management solutions call for an integrated, multi-disciplinary

approach that draws on the skills of geologists, petrophysicists, reservoir and production

engineers. It involves the integration of laboratory core tests, well log and field test analyses,

sanding records, water and hydrocarbon production analyses, the use of predictive modelling,

well performance modelling and, perhaps most importantly, sound engineering judgement.

Quantifying sand transport and erosion risk is primary information for well management

optimisation against sand production. If the sanding evaluation indicates a high risk of sand

production, then solids transport models are used to assess whether it will it be lifted to surface

or settle over perforation. If it settles over the perforation, downhole sand control will usually

be required. If it is lifted to surface, the tubing and surface facilities erosion rates can also be

modelled to assess tolerable flow rates.

The combination of sand failure and transport/erosion models are vital to the decision whether

sand exclusion (downhole) sand control or sand production can be effectively managed by

more passive means, such as: oriented perforation; selective/deferred perforation and

selective/deferred shut off; and well management/operational procedures (e.g. bean up rates). If

146

Page 162: Final Report-Group 1

these passive measures cannot guarantee well integrity or productivity, then sand exclusion

downhole will be required. The decision on the optimum form of sand control involves

analysis of many technical and economic factors.

5.9.3.2 Sand Control Design

Sand control can be done either passive or active. But majority will apply passive sand control,

which involves accepting sand production, choke management, selective perforation, oriented

perforation and well preconditioning. However, passive sand control may arise other issues as

it may reduce the well productivity, cost to maintain surface and downhole equipment is high

due to erosion and passive approach may lead to loss of the well. Other optimal selections for

completing sand-prone reservoir actively, is by physically restrain sand movement or known

also as sand exclusion.

a) Sand Control Method

Figure below shows various types of mechanical sand control that can be used.

Figure 85: Various types of mechanical sand control method

147

Page 163: Final Report-Group 1

Consideration:

Reduction of Drag Forces-Flow rate per unit area, if applicable, should be given first

consideration. Increase flow area if possible. Good well completion practices are

paramount.

Gravel Packing-This offers the only practical sand control for long zones. Gravel

packing may also be most practical for short zones-but remedial work, multiple

completions, small hole diameters, and abnonnal pressures increase difficulty and cost.

Open hole gravel pack should always be used on single completions where water or gas

shut-off or other change of completion interval is not anticipated.

Inside casing, gravel pack restricts productivity-but productivity may be maximized by

a sufficient number of large clean perforations and effective placement of the gravel.

Resin Consolidation-This is used in short zones where, for one reason or another, a

gravel pack cannot be used. Some of the applications are: small pipe diameter, top zone

of a dual completion, offshore or isolated location where tubing hoist is not available

and abnormal formation pressures make through tubing work advisable.

Resin Sand Pack-This has most of the same problems and advantages of the inside

casing gravel pack.

b) Gullfaks sand control recommendation

As discussed earlier, due to overpressure and high porosity, high permeability reservoir sands

of Gullfaks field, the formation is weak which will feasibly cause sand issues during the

production. Thus, here is some suggestion to monitor the sand production problems as briefly

listed below:

Acoustic sand detectors should be installed on all production wells corresponding to

topside on all pipelines. The sand detectors were designed to report estimated amounts

of produced sand.

Completed using gravel pack.

148

Page 164: Final Report-Group 1

c) Design Procedure

As for the gravel size, some method should be used in order to get the get the information to be

used for gravel pack selection. The best method is to use the laser particle size analysis (LPSA)

and particle size distribution (PSD). This is because; the LSA can evaluate, calculate the media

size diameter and grain size distribution. The, using the PSD using the LPSA result proper

gravel and screen size can be determined. Tips from Saucier said, optimum gravel sand size is

obtained when the median size of the gravel sand is no more than six times larger than the

median size of the formation sand.

The chart below shows a typical sand analysis distribution. Ten percentile sand size is defined

as the point on the distribution scale where 10 % by weight of the sand is of larger size and

90% of smaller size.

Figure 86: Typical sand analysis distribution

149

Page 165: Final Report-Group 1

A uniformity coefficient, can be calculated as Cu = D 40D 90

, where D40 is the 40 percentile size

and D90 is the 90 percentile size (D90):

- Cu< 3 well sorted, highly uniform sand

- 3< Cu< 5 uniform sand

- 5 < Cu< 10 moderate/poorly sorted sand

- Cu > 10 poorly sorted non- sorted sand

According to Tiffin criteria, the sorting coefficient is taken into account where Cs= D10D 95

- Cs< 10 (well sorted) Cs>10 (Not well Sorted)

Percentage fines content is defined as ‘fines’ that can pass through 44 microns gravel particles

pore size.

Cs< 10 => standalone screens

Cu< 3 and fines < 2% => wire-wrapped screens

3 < Cu< 5 and 2% < fines < 5% => mesh screens

Cs>10 or Cu> 5 or fines > 5% -gravel pack, can utilize slotted liner

As for the screen, the size of the screen to be chosen need to be smaller than the smallest grain

size in the formation. This is to ensure that no or less sand particle can be prevented from

entering the wellbore. Proper selection can be done based on the following table

Table 38: Screen gauge used with various types of gravel size

Gravel size

(US Mesh)

Gravel size

(in.)

Screen Opening

(in.) (micron)Screen Gauge

40/60 0.0165-0.0098 0.008 ~200 8

30/50 0.0230-0.0120 0.010 ~250 10

150

Page 166: Final Report-Group 1

20/40 0.0330-0.0165 0.012 ~300 12

16/30 0.0470-0.0230 0.016 ~400 16

12/20 0.0660-0.0330 0.020 ~500 20

8/12 0.0940-0.0470 0.028 ~700 28

151

Page 167: Final Report-Group 1

5.10 Potential Production Problems

In this section, the potential production problems occurrence during the operation, such as

formation damage, skin, flow assurance issues, are going to be explained while the

recommended monitoring or mitigation strategies are also proposed accordingly.

5.10.1 Formation Damage

Formation damage is defined as “A reduction in the natural capability of a reservoir to produce

its fluids, such as a decrease in porosity or permeability or both”. It usually occurs near the

wellbore (within a feet of wellbore), however damage sometimes can penetrate deeper into the

formation depending on formation properties and damage mechanism. This reduction in

permeability can be due to a multitude of causes, but in all cases it will reduce the natural

productivity due to the imposition of the extra pressure drop as the fluid flows to the wellbore.

Formation damage can occur throughout the life of the well from the moment that the drill bit

penetrates the formation. All well activities need to be evaluated for their potential for causing

formation damage, including: Drilling, Cementing, Perforating, Production, Injection. The

following sections will discuss about the various sources of formation damage as well as the

techniques by which formation damage can be stopped.

5.10.1.1 Drilling Operations

When over balance drilling (Wellbore Pressure > Formation Pressure) is conducted, pressure

balance required between the drilling fluid and the reservoir pressure to keep the well under

control will results in these mud particulates being forced into the formation. A filter cake will

be formed on the surface of the wellbore and some particles will also invade into the formation.

These solids will not easily flow back into the wellbore when the pressure gradient has been

reversed. Thus, formation damage has been created.

152

Page 168: Final Report-Group 1

The solid particles in the drilling mud have a size which is good enough to form filter cake on

the borehole wall. The permeability of this filter cake and the formation influences the rate at

which the mud filtrate invades the formation. From figure below, it shows the typical

relationship between drilling fluid type, cost and the risk of formation damage. It is realized

that using oil based mud (OBM) helps in reducing the risk of damage but costly. Thus, it is

suggested to design an appropriate mixing mud for the drilling operation.

Figure 87: Typical relationships between mud type, cost & risk of formation damage

5.10.1.2 Cementing

The success of casing or liner cementation in turn means the removal of mud cake. This

removal of the mud cake triggers the fluid loss i.e. filtrate from the cement slurry. This cement

slurry filtrate is highly reactive to any kind of formation clays due to its highly alkaline nature.

It also has a high concentration of calcium cations which can lead to precipitation of calcium

carbonate, calcium hydroxide (Lime) or calcium silicate. Also, cement slurries have a very

high natural fluid loss unless controlled by suitable additives. Another form of formation

damage is when natural fractures are present in the formation making the fluid loss control

additive ineffective. Moreover, some reservoir formation is naturally fractured, thus, the

cement slurry flows through these fractures may cause some blockages within it.

153

Page 169: Final Report-Group 1

Proper fluid loss control is necessary since excessive dehydration of the slurry will lead to

failure of the cement job, use of fluid loss control additives may help overcome this problem.

The depth of cement fluid loss is less since the filtrate volume is limited and hence can be

bypassed by the perforations. To avoid natural fractures being clogged, changing the

completion design to open hole is the simplest way. But this causes hindrance to integrity of

the hole and in extreme cases it may collapse.

5.10.1.3 Perforation

Perforation operations cause pulverization and compaction of the rock around the perforation,

which can reduce the permeability of the rock surrounding the perforation. As shown in the

figure, the damage region around the perforation is about ¼ to ½ inches in thickness with

permeability of the zone being 7% to 20% of the undamaged permeability. This deleterious

effect can be minimized by perforating with sufficient underbalance pressure, or sometimes

with extreme overbalance.

The “cleaning up” process is often attributed to the progressive removal of perforating debris

(charge debris, rockfragments and the low permeability crushed zone); all of which reduce the

well inflow. This removal increases the transmissibility between the well and the formation.

Figure 88: Damage area during Perforation

154

Page 170: Final Report-Group 1

5.10.1.4 Production

Typical production formation damage phenomena that lead to such reduction in well

productivity are; fines movement, use of incompatible workover fluids, inorganic and organic

scale formation and bacteria.

5.10.2 Well Stimulation

The earlier discussion was focused on the various types of formation damages which are

expected to take place during different processes throughout the life of the well. Consequently,

various well stimulation techniques have listed down in subsequent table, which help to

overcome formation damage.

155

Page 171: Final Report-Group 1

Table 39: Available Stimulation Techniques

Despite its benefits, in contrary, well stimulation can also causing formation damage unless

proper thought is given to fluid selection:

Reaction products generated by the reaction between the injected acid and the

formation rock may precipitate, causing a reduced permeability (formation damage).

The acid may weaken the rock, by attacking the intergrain cement so that (normally

temporary) sand production is observed when the well is returned to production.

The above deconsolidation process may generate “fines” which can migrate and block

pore throats.

Acid can be incompatible with crude oil leading to formation of a solid “sludge” which

can block pores or a viscous acid / oil emulsion formation.

156

Page 172: Final Report-Group 1

A further form of acid/crude oil incompatibility is the formation of a highly viscous

water/oil emulsion.

5.10.3 Flow Assurance Issues

5.10.3.1 Corrosion

Corrosion problem is one of the nightmares in oil and gas industry (Nalli, 2010). Based on

PVT report given, the Gullfaks field has 0.91% mole percent of CO2 in its wellstream and CO2

content is 0.08-1.49% in the production. Carbon dioxide has been determined as one of the

main corroding agent in the oil and gas industries. This is due to the fact that CO2 will dissolve

in water and form acid, which in turn reduce the pH value of the flowing fluid and create a

corrosive environment in the pipelines.

Corrosion monitoring is a very important step because we will know the corrosion condition in

the pipeline from time to time and take any precaution and maintenance steps if necessary.

Recent technology enables the pipelines to be monitored using intelligent pigging operations

like magnetic flux or ultrasonic pigs. These pigs will inspect the internal condition of the pipe

such as the wall thickness and corrosion condition besides carrying out the normal pipe

cleaning operation. Since prevention is always better than cure, regular pipeline shutdown and

turnaround operations shall be carried out to check the condition of pipelines and also

equipment like separators, drums and heaters. If the condition is below the safety level, the

equipment or pipelines must be either repaired or replaced to prevent any accident form

occurring.

Several common materials for pipeline manufacturing and their characteristics will be listed in

the table below. However, it should be noted that this list only serves as a general guidance

because there are still many other factors that we need to consider before making the selection

of material. They include detailed study of the flow regimes and patterns, flowing environment

such as pressure and temperature, corrosion mechanism involved and also the duration or

lifespan expected for the particular pipeline.

157

Page 173: Final Report-Group 1

Figure 89: Possible well design for CO2 injection (from Cooper, 2009).

Table 40: General Material Specification and Characteristic

No.

General Material Specification

Application Use in Hydrocarbon Industry

End Use in Hydrocarbon Industry

Oil and Gas Application

1 C- Mang-Silicon Steels (Carbon Steels)

General purpose, medium corrosion, medium temperature up to 200°C. Also low temperature up to -45°C.

Pressure vessels, Heat exchangers, Tanks, Spheres and Piping

Bulk fluids, crude pipelines, flow lines. Water and steam injection lines. Production and test separators, KO drums,

158

Page 174: Final Report-Group 1

storage tanks.

2 C- Chrome-Moly Steels (Low and Medium Alloy Steels)

Medium corrosive and high temperature up to 600°C media application. An economic compromise between CS/SS.

Furnace tubing, Heat exchangers, Re boilers, Pressure vessels, High temperature piping.

Well head items, chokes, manifolds and well components with sour and high temperature application.

3 Straight Chromium Steels (Chromium >12% and <18%)

Highly corrosive and very high temperature medium up to above 800°C application.

Furnace/ Heater tubing, High temperature vessels, Columns, High temperature heat exchangers

Christmas trees, well heads, downhole rods, valves and casing pipes.

4 Chromium- Nickel Steels (Stainless Steels: Chromium> 18% and Nickel >8%)

Highly corrosive, high temperature medium up to 800°C and strong oxidizing medium.

Pressure vessels, Columns, Heat exchangers, Alloy claddings, Piping & Cryogenic applications

Valve trims, instruments and internals of separators and tanks, low chloride levels.

5 Nickel Steels (2.5%/ 3.5%/ 9% Nickel)

Mildly corrosive and very low temperature media up to -100°C.

Cryogenic storage vessels, Heat exchangers, and piping especially for LNG applications.

Rarely used in oil and gas sectors except for LNG storage tanks, piping and pumps.

6 Duplex Stainless Steels (22% Chromium: Duplex; 25% Chromium: Super Duplex)

Saline and highly chloride concentrated media and moderate temperatures up to 60°C.

Pressure vessels, Exchangers, Piping with saline and chloride environments.

Piping, vessel and tank internals where very high level of chloride is present.

7 Nickel- Chrome (Inconels: Nickel-Chromium-Iron)

High corrosive, high temperature, high chloride and high sour media.

Piping, Tubing, Instruments normally for high temperature and high sour environments.

Well head and flow lines, manifolds with high sour and temperature applications.

159

Page 175: Final Report-Group 1

8 Nickel- Iron (Incoloys: Nickel-Iron-Chromium)

High corrosive, high temperature, high chloride, high sour environment

Piping, Tubing, Instruments normally for high temperature and high sour applications.

Well head and flow lines, manifolds with high sour and temperature applications.

The following table shows general monitoring methods for corrosion.

Table 41: General Monitoring Methods for Corrosion

Method Measures Comments

Coupons Average corrosion rate by weight loss. Pitting rate by pit depth measurement.

Must be positioned where corrosion is occurring.

Spools Pattern of attack. Pitting rate by pit depth measurement. May be able to weigh.

Very useful in surface systems. Not as easy to remove as a coupon.

Linear Polarization

Instantaneous general corrosion rate. Requires conductive fluid (water). May have problems in sour systems.

Potentiodynamic Polarization

Estimate pitting and general corrosion rates.

Used primarily for corrosion inhibitor evaluation.

Electrical Resistance

Change in electrical resistance of corroding element. Gives general corrosion rate.

Not normally used in sour systems due to conductivity of iron sulfide.

Galvanic Probe Current generated by bimetallic couple.

Primarily used for O2 detection.

Hydrogen Probe Hydrogen generated by corrosion of probe. Rate of pressure increase is proportional to corrosion rate.

For sour systems. Must be temperature compensated.

Hydrogen Patch Probe

Hydrogen generated by corrosion of pipe wall. Gives hydrogen permeation rate.

Used only in sour systems.

Dissolved Gas Analysis

O2, H2S, CO2 Presence of H2S in sweet system indicates sulfate reducing bacteria.

160

Page 176: Final Report-Group 1

Corrosion Product Analysis

Indicates which dissolved gas is responsible for corrosion.

FeS will oxidize to iron oxide on exposure to air.

Dissolved Iron Amount of iron dissolved by corrosion.

Not quantitative in sour or oxygenated systems. Must subtract any “natural” iron.

Inhibitor Concentration

Concentration of inhibitor present in fluid.

Helpful to determine inhibitor distribution in system.

Bacteria Counts Number of bacteria present. Related to corrosion rate.

Mechanical Calipers

Internal corrosion in tubing or casing. Pitting or general.

Scale or corrosion product may mask pits.

Electromagnetic Induction

Measures wall thickness and ID of casing.

Does not detect small holes or isolated pitting.

Ultrasonic Scanning

Measures ID in tubing and casing. Some tools also measure wall thickness.

Response is attenuated by scale buildup.

Magnetic-Flux-Leakage Pigs

Detects both internal and external attack in pipelines. General or pitting corrosion.

System must be built to accept tool. Reserved for large systems due to cost.

Ultrasonic Pigs Measures both ID and OD of pipelines.

Line must be filled with liquid.

Wire-line Pipeline Inspection

Tools

Measures both ID and OD of pipelines.

Maximum inspection length is a little over a mile.

Ultrasonic Inspection

Thickness of metal. Presence of pits or cracks.

Very localized measurement.

Radiography General or pitting corrosion. Particularly useful in locating pitting corrosion in piping and wellheads.

Visual Inspection

Pattern and severity of attack. Extremely reliable but often inconvenient.

161

Page 177: Final Report-Group 1

5.10.3.2 Emulsion

An emulsion is a dispersion (droplets) of one liquid (dispersed phase) in another immiscible

liquid (continuous liquid). Crude oil is usually produced along with water, generally

commingled production with water causes emulsion formation. Crude oil emulsions form when

oil and water (brine) come into contact with each other, when there is sufficient mixing, and

when an emulsifying agent or emulsifier is present. Emulsions can be difficult to treat and may

cause several operational problems in wet-crude handling facilities and gas/oil separating

plants. The presence of emulsion will lead to a number of problems including:

Create high-pressure drops in flow lines

Lead to an increase in demulsifier use

Sometimes cause trips or upsets in wet-crude handling facilities

Results in corrosion and catalyst poisoning in downstream processing facilities.

However, it is believed that any serious emulsion problem is not anticipated from new wells in

the early stage of the production period. To reduce the emulsion tendency of the Gullfaks

crude, it is suggested to inject demulsifiers, which are chemical compounds that widely used to

destabilize, and assist in coalescence of crude-oil emulsions.

5.10.3.3 Asphaltenes

Asphaltenes is known as amorphous, bituminous, solid material which precipitates from some

crude. It is made up of a complex mixture of asphaltenes, resins and maltenes which were

originally present in the crude oil under the original reservoir conditions as a metastable

colloidal dispersion. The precipitation process is triggered by pressure reductions – asphaltenes

precipitation is often first observed near the bubble point such that the change in crude oil

composition due to the removal of some of the lower molecular weight species from the crude

oil destabilizes the colloidal dispersion that maintained the asphaltenic material in suspension.

The effect of composition and pressure on asphaltene precipitation is generally believed to be

162

Page 178: Final Report-Group 1

stronger than the effect of temperature. Particularly, when CO2 injected into the oil reservoir it

will contribute to the asphaltene precipitation by composition change. However, there is no data

as to how much asphaltene by weight presence in the crude oil.

5.10.3.4 Hydrates

Hydrate is a snow like substance formed by the combination of free water, gas that might occur in

production lines and chemical lines where has relatively high pressure and ambient temperatures

well above the normal freezing point of water at elevated pressure. In Gullfaks field, the gas

production is high, there may probably create hydrates plug. Hence, hydrate prevention and

control are important for flow assurance of Gullfaks field development. It can be achieved by

proper insulation or injecting methanol at the wellhead as well as carrying out sequential

pressure build-up/pressure depletion of the area.

5.10.3.5 Wax/Paraffin Deposition

In many production systems wax would tend to deposit on the pipe wall during production.

Wax is made up of long-chain (>18), normal or branched with some cyclic and aromatic

hydrocarbon with the composition CnH2n+2 (Freund et. al., 1982). The wax deposition depends

on the fluid composition and temperature. Production cases where low fluid temperatures

occurs in the pipeline, where wax both deposits at the wall and precipitates as particles

suspended in the oil. Both diameter reduction due to the wax layer at the wall and the effect of

suspended wax particles on oil viscosity may significantly increase pipeline pressure drop and

thereby reduce the production capacity of a pipeline. Precipitated wax may cause fluid turning

non-Newtonian with an increase in viscosity.

When further cooled enough and at “right conditions” the precipitated wax could form a gel.

This temperature is called the Pour Point. The solid wax is dissolved in the crude oil at

reservoir temperatures and forms a crystalline precipitate when the flowing fluid temperature

reduces below wax appearance temperature (WAT) or when flowing fluid temperature greater

than wall temperature (Toil > Twall); in other words, Twall < TM < WAT. The temperature

difference between the reservoir temperature and WAT ranges from only a few degrees

163

Page 179: Final Report-Group 1

centigrade to many tens of degrees. Wax precipitation is highly dependent on the temperature.

However, pressure changes only have a minor effect on the value of the wax appearance

temperature.

The wax deposition can lead to various severe matters, such as increasing the fluid viscosity,

higher pressure loss and pump pressure, restriction of flow within tubing, pipelines and process

equipment, affecting the accuracy of monitoring equipment, failure to restart in the case of

severely plugged pipelines and difficult separation process as the wax crystals provide

emulsion stabilization.

From DST and PVT data of Gullfaks field, there is no indication of wax content. But after a

period of time, have been observations of pressure build-up in pipelines due to wax precipitation.

Because the oil produced from Gullfaks field is waxy, and wax can precipitate at low temperatures.

Therefore measurement shall be taken to avoid wax accumulation. Consequently, if there is

wax presence in future, the wax mitigation strategies will be as follows:

Prevention:

Insulation

Active Heating DEH

Hot Oil Circulation

Chemicals

Diluents

Remediation

Pigging

Coiled Tubing

Chemicals

Sacrificial Spools

Self-Insulation

Shear Stripping

Soak and Cough

Chilling Systems (Cold Flow Slurry) Prevention

164

Page 180: Final Report-Group 1

Insulation

Active Heating DEH

Hot Oil Circulation

Chemicals

Diluents

Remediation

Pigging

Coiled Tubing

Chemicals

Sacrificial Spools

Self-Insulation

Shear Stripping

Soak and Cough

Chilling Systems (Cold Flow Slurry)

The below table exhibits advantages and disadvantages of two common mitigation strategies

for wax deposition issues:

Wax Table 42: Comparison of two common mitigation strategies for wax deposition

Mitigation Strategies

Insulation Heating

Applications Use of flowline/riser insulation to ensure arrival above WAT

Types of insulation External coatings Pipe-in-pipe Buried pipelines

Heat desired portion of systems Localised heating Heating medium

circulation Internal hot oil fluid

circulation Type of heating:

Active (direct) heating

165

Page 181: Final Report-Group 1

Indirect heating

Advantages

Common practice No operating expenses

No risk of gel formation Active system

Disadvantages

Initial CAPEX cost Potentially difficult to

provide sufficient insulation:– WATs from 65°C – 75°C– long tiebacks– cold environment

CAPEX increases to allow for infrastructure to be included

Circulation temperature must be sufficient to ensure arrival temperature

5.10.4 Other Production Problems

Some of other potential issues that can be encountered in the wells and the common techniques

to encounter them can be referred at the Production Appendices.

166

Page 182: Final Report-Group 1

CHAPTER 6 FACILITIES ENGINEERING

6.1 Introduction

6.1.1 Overview

The functions of offshore production facilities are very much the same as those described for

land operations. An offshore production platform is rather like a gathering station;

hydrocarbons have to be collected, processed and evacuated for further treatment or storage.

However, the design and layout of the offshore facilities are very different from those on land

for the following reasons: (1) A platform has to be installed above sea level before drilling and

process facilities can be placed offshore. (2) There are no utilities offshore, so all light, water,

power and living quarters, etc. also have to be installed to support operations. (3) Weight and

space restrictions make platform-based storage tanks non-viable, so alternative storage

methods have to be employed.

This section will describe the facilities required to accommodate the production of fluids from

the Gullfaks field. It also involves the design of other production support system, incorporating

operation and maintenance philosophy. In general, facilities engineering covers all aspects of

equipment and system design right from the well head to its final delivery point. This

development considers safety issues, cost effectiveness and economical values. The design

philosophy of the development is based on 7 well producers and 3 injection wells.

6.1.2 Problem Statement and Objectives

Design selection for the Development, Engineering Design Consideration, and Surface

Operation Facilities and Platform Utilities suitable for the Gullfaks field with economic

and environmental considerations.

Implementation of Operation and Maintenances (O&M) philosophy of the facilities and

its abandonment options.

167

Page 183: Final Report-Group 1

6.2 Design Basis and Philosophy

In order to build the best platform design, the following factors are considered:

Offshore environment: Structure will be located in exposed and hostile environment.

Thus, reliable source of information on local winds, wave and current stability plus

with stability of the structure play an important role in determines safety measure of the

platform. Apart from that, facilities design should minimize environmental impact and

damages to the environment.

Economic Justification: Besides aiming for a high hydrocarbon recovery, platform

design should consider economic side of it. The equipment’s capacity and sizing should

not be over-designed, but maintained to an optimum performance according to the field

capacity. Miscalculation in designing will cause an unnecessary money outflow and

increase in overall cost.

Processes: The design of filters, vessels, separator, and pump must be specifically abide

the type of fluids produced and properties of the fluid. The produced fluid must

undergo primary separation and necessary treatment before evacuated to the onshore

facilities. The factors affecting behavior of the fluid flow, temperature and pressure of

the fluid and material of the pipe that can withstand it need to be considered.

Design Flexibility: Future consideration must be taken into account during current

design to reduce cost for renovation. Additional slots must be allocated for potential

development based on production forecast that has been done.

Safety Measures: Safety has always been the top priority in oil and gas industry in

general and specifically in highly-risk working environment of plants and platforms.

The need for a safe working condition and measures are a lot far exceeding the need of

hydrocarbon production as the impacts caused by failures in safety aspects are

catastrophic. The safety measure are HSE plan, safety personnel, safety equipment,

backup facilities, emergency procedures, multiple stage failure containment and

emergency shutdown system. These are all been looked into prior to installation to

safeguard the nature of operation and most importantly the personnel on board.

Geological Consideration: Sea floor topography and formation profile will influence

the platform design. Gullfaks, North Sea Field is located in shallow marine water, so it

is highly possible for the platform to be fixed rig.

168

Page 184: Final Report-Group 1

6.2.1 Design Basis

Several design factors are looked into consideration for several reasons which are safety issue,

to ensure the platform built will be reliable and economically viable and facilities design that

will be able to withstand the volume of oil produced for certain period of time. The

geographical data of Gullfaks Field:

Location : 175 km from Mongstad Oil Terminal (Bergen, Norway)

Water Depth : 130-230 meters

Number of wells: 7 production wells and 3 injection wells.

The production forecast profile for Gullfaks Field is as below:

Figure 90: Production forecast profile for Gullfaks Field

169

Page 185: Final Report-Group 1

6.2.2 Reservoir Data

Referring to Table below, Gullfaks fluid is a non-problematic in nature. The fluid can be

classified as black oil. Flow assurance is a key part in assessing the technical viability of this

project. Specific issues addressed are fluid flow (line pressure drop and flow patterns), wax

mitigation and corrosion control.

Two design philosophies are strongly adopted for the Gullfaks field. They are:

1. Selecting the optimum Facilities, through cost optimization

2. Following safety guidelines at all times

Table 43: Reservoir and Fluid Properties of Gullfaks Field.

Oil Gravity (˚API) 64.2

Viscosity (cp) 1.33

Highest Composition C1+ with 36.47 mole %

Oil Saturation (% PV) 77.4

Formation Type Consolidated Sandstone

Temperature (˚F) 220

Depth (ft) >5000

Several other factors also have to be considered while designing the facilities system. They

include the following:

1. The offshore location of the Gullfaks field

2. The required production facility services with regards to the field's oil recovery

mechanism

3. Processing facilities required for fluid handling

4. Properties and Phase behaviour of the produced fluid

5. The man power required to operate the facilities.

170

Page 186: Final Report-Group 1

6.2.3 Rig selection

The type of rig which will be selected depends upon a number of parameters, in particular:

cost and availability

water depth of location (offshore)

mobility/transportability (onshore)

depth of target zone and expected formation pressures

prevailing weather/metocean conditions in the area of operation

experience of the drilling crew (in particular the safety record)

Figure 91: Types of offshore drilling rigs

Considering the water depth of Gullfaks reservoir and the sea conditions, we have chosen Jack-

up rig as mentioned in the drilling section of this report. Jack-up rigs are either towed to the

drilling location (or alongside a jacket) or are equipped with a propulsion system. The three or

four legs of the rig are lowered onto the seabed. After some penetration the rig will lift itself to

a determined operating height above the sea level. If soft sediment is suspected at seabed, large

mud mats will be placed on the seabed to allow a better distribution of weight. All drilling and

supporting equipment are integrated into the overall structure. Jack-up rigs are operational in

water depths up to about 900ft and as shallow as 15ft. Globally, they are the most common rig

type, used for a wide range of environments and all types of wells.

171

Page 187: Final Report-Group 1

6.2.4 Platform selection

The water level in Gullfaks field is approximately 130-230 meters only which is considering as

shallow marine water. Therefore, the platform is chosen based on platform effectiveness, cost

and suitability to the production and facilities required. This criteria provided is to ensure the

smoothness of the production as well as occupying facilities that are needed to be installed on

it. Some aspects that are taken into account after predicting production forecast on production,

the fluid properties and flow rates and economical factor of the development plan.

Selection of the type of platform depends on several factors:

1) The depth of water

2) Sea conditions and environment

3) Production life of the wells

4) Cost of the platform system

5) The distance from the shore

A platform is a large mechanical structure which facilitates the activities related to drilling and

production of hydrocarbons. Offshore platforms can be split broadly into two categories: fixed

and floating. Fixed platforms are generally classified by their mechanical construction. There

are four main types:

Steel Jacket Platforms

Gravity-Based Platforms

Tension Leg Platforms (TLPs)

Minimum facility systems.

Floating platforms can also be categorised into three main types:

semi-submersible vessels

ship-shaped monohull vessels (such as floating production, storage and offloading

(FPSO))

SPAR platforms.

172

Page 188: Final Report-Group 1

Therefore a fixed platform would be most suitable and economical. But detailed study is

carried out to be certain. Fixed platforms are built on concrete or steel legs which are anchored

onto the seabed to support the deck consisting of drilling rigs, production facilities and

accommodation deck for crews.

Figure 92: Type of Oil Platform

Based on the water depth and sea conditions, the feasible alternatives for our Gullfaks field

production platforms seems to be either steel jacket platforms or gravity-based platforms.

1. Steel piled jackets are the most common type of platform and are employed in a wide

range of sea conditions, from the comparative calm of the South China Sea to the

hostile Northern North Sea. Steel jackets are used in water depths of up to 150m and

may support production facilities a further 50m above mean sea level (MSL). In

deepwater, all the process and support facilities are normally supported on a single

jacket, but in shallow seas it may be cheaper and safer to support drilling, production

and accommodation modules on different jackets. In some areas, single well jackets are

common, connected by subsea pipelines to a central processing platform. Steel jackets

are constructed from welded steel pipe. The jacket is fabricated onshore and then

173

Page 189: Final Report-Group 1

floated out horizontally on a barge and set upright on location. Once in position a jacket

is pinned to the seafloor with steel piles. Prefabricated units or modules containing

processing equipment, drilling and other equipment are installed by lift barges on to the

top of the jacket, and the whole assembly is connected and tested by commissioning

teams. Steel jackets can weigh 20,000 tons or more and support a similar weight of

equipment. The figure below shows an example of a steel jacket.

Figure 93: Example of Steel Jacket platform

2. Concrete or steel gravity-based structures can be deployed in similar water depths to

steel jacket platforms. Gravity-based platforms rely on weight to secure them to the

seabed, which eliminates the need for piling in hard seabeds. Concrete gravity based

structures (which are by far the most common) are built with huge ballast tanks

surrounding hollow concrete legs. They can be floated into position without a barge and

are sunk once on site by flooding the ballast tanks. For example, the Mobil Hibernia

Platform (offshore Canada) weighs around 450,000 tons and is designed and

constructed to resist iceberg impact! The legs of the platform can be used as settling

tanks or temporary storage facilities for crude oil where oil is exported via tankers, or to

allow production to continue in the event of a pipeline shutdown. The Brent D platform

in the North Sea weighs more than 200,000 tons and can store over a million barrels of

oil.

174

Page 190: Final Report-Group 1

6.3 Development Scenario

Due to Gullfaks B being located between Gullfaks A and C, the produced fluid can be

evacuated to Gullfaks B because of distance and pipeline cost considerations. The distance

from Gullfaks A and C are 4km and 3km respectively and a 12 inch diameter pipe can be used.

That gives an opportunity to host tie-in system expenditure to be reduced, since there is no use

long length pipeline to tie-in to the fluid gathering target at Gullfaks B.

In total, four (4) scenarios were considered for the facility design development for Gulfaks

Field. The scenarios are shown as follow:

Option A – 3 Steel jacket wellhead Platform + Pipeline

Option B – 2 Subsea development platforms + 1Steel jacket wellhead platform +

Pipeline

Option C –1 Subsea development platform + 2 Steel jacket wellhead platforms +

Pipeline

Option D – 3 Steel jacket wellhead Platform + FPSO

175

Page 191: Final Report-Group 1

6.3.1 Option A – 3 Steel jacket wellhead Platform + Pipeline

Drilling by Jack up rig

Triple 4 legged steel jacket platform: Minimum facility topsides with NO normal visits;

basic utilities including control, power, corrosion inhibition, oil processing, water

injection, gas compression and storage.

Pipeline from GF-B to terminal onshore – 175 km. Processed crude export via pipeline

to terminal.

Table 44: Option A

Cost Estimates (USD million)

Topside + Substructure (3 Platforms) 165

Pipelines 250

Development Wells 110

Total CAPEX 525

Figure 94: Option A

176

12 in. pipe

20 in. pipe

3 KM

4 KM

175 KM

GF-C

GF-B

GF-A

GULLFAKS FIELD

MONGSTAD OIL TERMINAL (BERGEN)

Page 192: Final Report-Group 1

6.3.2 Option B – 2 Subsea development platforms + 1Steel jacket wellhead platform +

Pipeline

Drilling by Jack up rig

One 4-legged steel jacket platform: Minimum facility topsides with NO normal visits;

basic utilities including control, power, corrosion inhibition, oil processing, water

injection, gas compression and storage.

Subsea platforms for GF-A and GF-C

Pipeline from GF-B to terminal onshore – 175 km

Cost Estimates (USD million)

Topside + Substructure (1 Platforms) 55

Pipelines 250

Development Wells 110

Subsea development 180

Total CAPEX 595

Table 45: Option B

177

Page 193: Final Report-Group 1

Figure 95: Option B

6.3.3 Option C –1 Subsea development platform + 2 Steel jacket wellhead platforms +

Pipeline

Drilling by Jack up rig

Two 4-legged steel jacket platform: Minimum facility topsides with NO normal visits;

basic utilities including control, power, corrosion inhibition, oil processing, water

injection, gas compression and storage.

Subsea platforms for GF-A

Pipeline from GF-B to terminal onshore – 175 km

Cost Estimates (USD million)

178

12 in. pipe20 in. pipe

3 KM

4 KM

175 KM

GF-C

GF-B

GF-A

GULLFAKS FIELD

MONGSTAD OIL TERMINAL (BERGEN)

Page 194: Final Report-Group 1

Topside + Substructure (2 Platform) 110

Pipelines 250

Development Wells 110

Subsea development 90

Total CAPEX 560

Table 46: Option C

Figure 96: Option C

179

12 in. pipe20 in. pipe

3 KM

4 KM

175 KM

GF-C

GF-B

GF-A

GULLFAKS FIELD

MONGSTAD OIL TERMINAL (BERGEN)

Page 195: Final Report-Group 1

6.3.4 Option D – 3 Steel jacket wellhead Platform + FPSO

Drilling by Jack up rig

Triple 4 legged steel jacket platform: Minimum facility topsides with NO normal visits;

basic utilities including control, power, corrosion inhibition, oil processing, water

injection, gas compression and storage.

FPSO is used to transport oil to tanker or oil terminal.

Cost Estimates (USD million)

Topside + Substructure (3 Platforms) 165

FPSO 210

Development Wells 110

Total CAPEX 485

Table 47: Option D

180

Page 196: Final Report-Group 1

Figure 97: Option D

Hence, based on CAPEX considerations alone, Option D is chosen due to it having the lowest costs.

181

12 in. pipe

20 in. pipe

3 KM

4 KM

175 KM

GF-C

GF-B

GF-A

GULLFAKS FIELD

MONGSTAD OIL TERMINAL (BERGEN)

Page 197: Final Report-Group 1

6.4 Engineering Design and Planning Considerations

The facilities planning for Gullfaks field involved the following considerations:

6.4.1 Platform Design

A Gullfaks platform has integrated a production and utility facility which is typical of offshore

platform configurations. Platform construction is of a modular design which allows all

facilities such as production equipment, piping, cabling and instrumentation to be installed at

an onshore fabrication yard. Considerable cost savings are realized by this approach relative to

offshore installations of these facilities. Gullfaks platform facility was based on a standardized

two-module type design.

6.4.2 Gas Compression Requirements

Three-dimensional reservoir studies indicated that gas injection will be required in the Gullfaks

reservoir for pressure maintenance. The maximum gas production in Gullfaks Field is 27.3

MMscf/d and Central Processing Platform gas compression is 50 MMscf/d. While Gullfaks

maximum gas production is 5.8 MMscf/d which gas compression module in Gullfaks Complex

is sufficient handle and not required to upgrade. The maximum gas injection for gas lift is

3.402 MMscf/d.

6.4.3 Water Injection Requirement

Water injection facilities are planned as the reservoirs were interpreted insufficient aquifer

strength. There’s no water production rate in first year of production in Gullfaks and three

dimensional reservoir studies indicated the water injection starts on the first year. Gullfaks

required 40 Mstb/d. and capacity in Gullfaks field is 120 Mstb/d. There’s insufficient data on

to evaluate water production in Gullfaks Field. Hence, future water injection requirement will

be further evaluated as additional reservoir performance data becomes available.

182

Page 198: Final Report-Group 1

6.4.4 Telemetry System

Gullfaks satellite platform is designed for unmanned operation. A microprocessor based

telemetry system operated via a radio link was installed for remote operation of Gullfaks Field.

The following aspects of the Gullfaks operation are remotely handled on Gullfaks Central

Processing Platform:

Individual well testing

Monitoring of well status and production measurements

Monitoring and control of critical equipment

Initiation of a process and emergency shutdown

6.4.5 Corrosion Control - Production Facilities

One of the most significant engineering considerations in the planning of the facilities was the

control of corrosion caused by the high CO2 content of the wellstream. The Gullfaks well

stream contains small amount of carbon dioxide. However, this CO2 content in the well-stream

also requires proper material selection and corrosion protection measures in the facilities

design. Carbon steel has been specified for well tubulars, flowlines and separator vessels for

the Gullfaks process facilities. For the wellheads, it was considered advisable to have stainless

steel lower master valve and alloy steel valve trims for the remainder. Corrosion inhibitor is

injected into the flowlines and the crude oil production pipelines. Corrosion monitoring points

were installed to enable a close scrutiny of susceptible areas in the system.

183

Page 199: Final Report-Group 1

6.5 Platform Utilities and Service Facilities

6.5.1 Topside Structure

The topside design mainly depends on the space, facilities required and weight. The platform

will vary in complexity according to the number of wells and type of processing facilities

required. Gullfaks topside structure will be an integrated deck comprises mainly:

Production deck - used to place the well head

Helideck – it welded to the side of the platform for helicopter landing.

Mezzanine deck- it is functioning as to accommodate crane.

Living quarters – Capacity for offshore operation is between 80-120 men.

Figure 98: Typical elevation view of an offshore platform

184

Page 200: Final Report-Group 1

Figure 99: Schematic of an offshore platform, illustrating the concept of modularization

Figure 100: Equipment arrangement plan of a typical offshore platform illustrating

185

Page 201: Final Report-Group 1

6.5.2 Substructure

Gullfaks jacket shall be a four pile of steel-insert structure and comply with the standard design

regulation. The structure is only few meters in height and it allows some gap between the

seawater level and weather deck. The substructure shall be designed to withstand loading of the

top structure modules, storms and can withstand minor incident such as minor ship crash. The

jacket shall also accommodate the risers for production communication from seabed to

platform, caisson and boat loading with consideration of the sea level depth.

Process Flow

Figure 101: Process Flow Diagram

6.5.3 Wellhead module

Manifold systems

Manifold should have configuration options that include production, injection, and test

manifolds. It as well should have multiple tie-in and header configurations to facilitate

construction of the production system. There are different type of manifolds systems:

1. Production Manifold

186

Page 202: Final Report-Group 1

Production manifolds is used to lower the pressure from the wellhead. It consists of a set of

high pressure valves and at least two chokes. These chokes can be fixed or adjustable or a

mix of both. The redundancy is needed so that if one choke has to be taken out of service,

the flow can be directed through another one. By lowering pressure the retrieved gases can

be flared off on site.

2. Injection Manifold

An injection manifold is a structure containing a network of valves and pipework designed

to direct injection fluids to one or more wells.  The injection manifolds can be configured

to handle a variety of fluids, typically water or gas, and can be designed to facilitate any

field’s enhanced recovery strategy. The water injection manifold is for feeding injection

water to water injection wells along with metering system while lift gas manifold for

feeding lift gas to well along with injection gas regulation/control and measurement

system.

3. Test Manifold and Test Separator

A plat is receiving a multi phased flow from many wells via manifold. Flow from one well

only may be taken to the test separator. Vessel is used to separate and meter a small amount

of oil and gas. There are several types of test separators can be used which are two-phase

or three-phase or spherical, vertical or horizontal. Different meters will be equipped for test

separators to determine the rates of oil, gas and water. This is important to diagnose well

problems, to evaluate the production performance of individual well and can manage the

reserves properly. Test separators also known as well testers or a well checkers.

6.5.4 Separation

More often, the well produces a combination of gas, oil and water, with various contaminants

that must be separated and processed. The production separators come in many forms and

designs. In gravity separation, the well flow is fed into a horizontal vessel. The retention period

is typically five minutes, allowing gas to bubble out, water to settle at the bottom and oil to be

taken out in the middle. The pressure is often reduced in several stages (high pressure

187

Page 203: Final Report-Group 1

separator, low pressure separator, etc.) to allow controlled separation of volatile components. A

sudden pressure reduction might allow flash vaporization leading to instability and safety

hazards.

The separator that will be used for Gullfaks Field is horizontal separators since they are

normally more efficient at handling large volumes of gas than vertical separators. This is

because the interface area is larger in a horizontal separator than a vertical separator, it is easier

for the gas bubbles, which come out of solution as the liquid approaches equilibrium, to reach

the vapor space.

Advantages of horizontal separator:

Horizontal separators smaller and less expensive than vertical for given gas capacity

Liquid droplets easier to separate out of gas continuous phase

Gas bubbles easier to come out of the liquid phase to reach vapour space because interface

area larger

Greater liquid capacity because well suited for liquid-liquid separation

Figure 102: Horizontal Separator

188

Page 204: Final Report-Group 1

6.5.5 Metering

Metering stations allow operators to monitor and manage the natural gas and oil exported from

the production installation. These employ specialized meters to measure the natural gas or oil

as it flows through the pipeline, without impeding its movement. This metered volume

represents a transfer of ownership from a producer to a customer (or another division within

the company), and is called custody transfer metering. It forms the basis for invoicing the sold

product and also for production taxes and revenue sharing between partners. Accuracy

requirements are often set by governmental authorities. Typically, a metering installation

consists of a number of meter runs so that one meter will not have to handle the full capacity

range, and associated prover loops so that the meter accuracy can be tested and calibrated at

regular intervals.

6.5.5.1 Crude Oil Metering

At turbine meter station, the flow rate of the crude oil will be metered and regulated by the

surge level control valve located in the crude oil pump discharge header. There will be turbine

meters, piped in in parallel with one meter sparing the other at the meter station. Oil flow

readout will be by a net oil computer.

6.5.5.2 Gas Metering

Gas flowing from the Test Separator and Production Separators will being metered by using

orifice meters. The differentials will be transmitted to a central control panel whose

instruments will provide both instantaneous and totalized flow rates.

6.5.6 Well Control Panel

Pneumatic control panels are designed to monitor crucial wellhead safety parameters. They

provide sequential start up and safe shutdown of production wells.

Surface Facility Protection: A safety analysis or hazardous operability (HAZOP)

analysis of surface facilities including rotary and process equipments is carried out. All

possible hazards, interrelation between various parameters are identified and listed. The

189

Page 205: Final Report-Group 1

functional chart thus evolved is the SAFE (Safety Analysis and Function Evaluation)

chart. The SAFE chart forms the basis for design of panel in surface safety protection.

Fire and gas leakage protection system: Any gas leakage is automatically detected

and appropriate shutdown action initiated to prevent formation of combustible mixture.

All sources of ignition are also shutdown. Any eruption of fire is detected and

appropriate shutdown and suppression action initiated

Well control & Protection: A major function of the wellhead shutdown panel is to

control the well through the surface and sub-surface safety valves. The interrelations

between various valves are well defined and their sequential operation established.

Remote monitoring and control of essential process variables including well testing will

be through the operation station.

6.5.7 Flare system

When raw natural gas are produced in the facilities that are lacking gas transportation

infrastructure, the gas will be transported to flare system to be flared as a waste or unusable

gas. The other consideration to flare the gas is the construction of gas pipelines and utilization

of other gas transportation means is not economically feasible. A gas seal is installed in the

flare stack to prevent the air to flow back into a flare stack due to wind or thermal contraction

of stack gases and create an explosion potential. A liquid seal that is located downstream of the

3-Phase Separator is used to stop flame propagation in the unlikely event of flashback. It is also

used to remove liquid droplets from the gas and also prevent gas from travel to upstream.

Liquid seal contain a predetermined level of water in the base of the drum.

190

Page 206: Final Report-Group 1

6.6 Production Support Facilities

6.6.1Water injection

Water Injection will be used as secondary recovery methods for pressure maintenance. It is

relatively low cost and efficient means of improving oil production from a depleting field.

Treated water is injected under pressure into flanks of the oil bearing strata through propose

drilled wells. Water displaces any remaining particles of oil and reduces free space, thus

increase reservoir pressure. To prevent damage to the Reservoir the quality of water injected is

strictly complied with. Also, the health of the pipelines carrying the injection water to the wells

and well platforms is taken care of by dozing chemicals to prevent corrosion. The Major

components of Water Injection systems are; sea water lift pumps, coarse filters, fine filters,

deoxygenation towers, booster pumps, main injection pumps and chemical dosing pumps.

While chemical dozing system is included flocculent, scale inhibitor, corrosion inhibitor,

chlorination, bactericide and oxygen scavenger.

6.6.2 Sea water Lifting and Filtering

Water from sea is Lifted with seawater lift pumps and fed to Coarse Filters and fine filters

for filtering. Coarse filters filter the particle to 20 microns. Fine filters filter the particle to 2

microns. Poly electrolyte and coagulants are added in sea water lift pump discharge to promote

coagulation of suspended particles.

6.6.3 Deoxygenation and Pumping

The filtered water flows to Deoxygenating towers for removal of oxygen. Deoxygenation

prevents formation of aerobic bacterial colonies (sulphur reducing bacteria) in the Water

Injection flow lines. Vacuum pumps and Oxygen scavenger chemical dozed facilitates oxygen

removal in the towers. Booster Pumps take suction from De‐oxygenation Towers and feed

Main Injection Pumps. Scale inhibitors, Bactericide and corrosion inhibitor chemicals are

dozed in the discharge of booster pumps.

191

Page 207: Final Report-Group 1

6.6.4 Gas compression facilities

Gas compression facilities are required to provide gas injection for reservoir pressure

maintenance, gas re-injection to dispose of produced gas and gas lift to enhance vertical lift

performance in production wells. The following equipment use for gas compression:

gas compressor complete with driver package

gas scrubber

gas coolers

glycol dehydration system

pipings, control and instrumentation systems

192

Page 208: Final Report-Group 1

6.7 Gullfaks Pipeline System

6.7.1 Pipeline sizing

Pipeline sizing play an important role in transporting hydrocarbon from one platform to the

other platform. This is to make sure that the pipeline is capable of transporting fluid at the

required amount and to maintain the fluid velocity in order to avoid solid particle from

depositing at the lower part of the pipeline. The purpose of doing pipeline sizing is to ensure

that the pipeline can accommodate the require capacity within the available pressure

constraints. Pipeline sizing depends on available pressure drop, flowing velocities and the flow

rate of the liquid. The line needs to be large enough in order to accommodate sufficient

pressure to move the fluid in the pipeline. Assuming that available pressure drop can be altered

by changing the outlet pressure which is separator, the pipeline sizing can be selected based on

the fluid velocity and flow rate. There is a limit to the fluid velocity, in order to prevent

pipeline erosion.

It is possible that liquid droplets in the flow stream will impact on the wall of the pipe causing

erosion of the products of corrosion. This is called erosion/corrosion. Erosion of the pipe wall

itself could occur if solid particles, particularly sand, are entrained in the flow stream.

Steps in selecting the pipeline Sizing and wall thickness:

Determine the max and min velocity allowable for specific fluid types

Find pressure drop of the system

Determine the I.D of pipe relative to the velocity

Determine pressure drop in the pipeline

Find the wall thickness based on the standard

Choose the appropriate pipeline size from the standard

Fluid velocity in oil field unit:

V=0.012Q

D2

193

Page 209: Final Report-Group 1

Gas velocity in oil field unit:

V=60QgTZ

D2 p

The minimum fluid velocity in multiphase systems must be relatively high to keep the liquid

moving and prevent or minimize slugging. The maximum recommended velocity for gas line is

60 ft/sec to inhibit noise and 50 ft/sec for CO2 corrosion inhibition and maximum

recommended velocity for liquid line is 15 ft/sec. In addition, to re-confirm the earlier

calculation, pipeline sizing also can be decided from

d=[(11.9+ ZTR16.7 P )QL /1000 V ]

1 /2

d = pipe ID, in

Z= compressibility factor, dimensionless

R = gas/liquid ratio, ft3/bbl

P = Pressure, psia

T = gas/liquid flowing temperature, OR

V = maximum allowable velocity, ft/sec

QL= Liquid-flow rate, bbl/d

Standard nominal pipe sizes range from 4-inch (100 mm) up to 80-inch (2000 mm) in

diameter. In petroleum industry, 60-inch is the largest diameter installed to date. Most line-

pipes used on offshore facilities are metallic. Non-metallic pipes are also being used today. A

metallic line-pipe is usually manufactured using one of these techniques:

Seamless Method

Electric Welding (ERW)

Submerged Arc Welding (SAW)

There are two types of Submerged Arc Welding (SAW) pipe. They are Longitudinal

Submerged Arc Welding and Spiral Submerged Arc Welding.

194

Page 210: Final Report-Group 1

Pressure Drop Calculation

The rate of flow of mixture is W (lb/hr) = 3180 QgS+ 14.6 Ql(S.G.)R= 106x Qg/Ql

ρm=12409× (S .G ) × P+2.7 × R× S × P

198.7× P+R ×T × Z (lb/ft3)

ΔP drop= 6.9x10-8 xLxW2/(ρm x d5)

Where

d = pipe ID, inZ= compressibility factor, dimensionlessR = gas/liquid ratio, ft3/bblP = Pressure, psiaT = gas/liquid flowing temperature, ORQL= Liquid-flow rate, bbl/dQg = gas flow rate, MMscfd

S = specific gravity of gas at standard conditions (air =1)

(S.G.) = specific gravity of liquid relative to water

Based on data from Well A20 obtained from Nodal Analysis, and reservoir properties, pressure

drop calculation is as following:

Data:

Maximum Pipeline length: 7000ft

Liquid flowrate = 4000 bbl/d

Gas flowrate = 1.9 mmscf/d

(S.G.)= 0.724

S=0.8515

Z=0.774

Temperature =80F

Inlet pressure =900psia

195

Page 211: Final Report-Group 1

Results:

W=47426.363 lb/fr

R = 475 ft3/bbl

ρm = 24 lb/ft3

ΔP drop= 45266.36/d5

Line ID (inch) Pressure drop (psia)

2 1414.6

4 44

6 5.8

So, minimum pipeline ID 6 inches is recommended for transporting 2 phase liquid and gas.

6.7.2 Pipeline Classification

The onshore and/or offshore pipelines have several types:

Gathering pipeline

These lines are used to transport oil from field pressure and storage to large tank where it is

accumulated for pumping into the long distance called trunk line. Gathering pipelines typically

consist of lines ranging from 4″-8″ inside diameter.

Trunk pipeline

From large central storage, oil is moved through large diameter, long distance pipeline called

trunk line to refineries. Pump are required at the beginning of the trunk line and pumping

stations must also be spaced along the pipeline to maintain pipeline pressure at the level

required to overcome friction, change in the elevation and other losses.

Transmission or transportation pipeline

Mainly long pipes with large diameters, moving products (oil, gas, refined products) between

cities, countries and even continents. These transportation networks include several compressor

196

Page 212: Final Report-Group 1

stations in gas lines or pump stations for crude and multi-products pipelines. The large

diameter may range from 24 to 60 inches

Distribution pipeline

Composed of several interconnected pipelines with small diameters, used to take the products

to the final consumer. Feeder lines to distribute gas to homes and businesses downstream.

Pipelines at terminals for distributing products to tanks and storage facilities are included in

this group.

6.7.3 Pipeline modeling

Models the entire pipeline system to account for pressure, temperature and flow at major

checkpoints. Based on this model the management system can perform:

Pressure balancing to make certain that pressure set points are correct to meet demand

forecasts and avoid potential overload conditions.

Production allocation, which ensures that producers are able to deliver their contractual

volumes into the network.

Leak detection, which compares actual measured data against dynamic data predicted

by the model. A discrepancy indicates a leak (or a failing measurement). Simple liquid

systems only calculate basic mass balance (in-out), while an advanced modeling system

can give more precise data on size and position of the leak within a certain response

time.

Pig or scraper tracking is used to track the position of the pig within the pipeline, both

from pig detection instruments and the pressure drop caused by the pig in the pipeline.

In case of liquid pipelines transporting batches of different products, a batch transfer

system is needed. Based on information on when each product is injected into the

pipeline, and gravity measurement at the receiving end, it is possible to sequentially

transfer different products, such as gasoline and diesel in the same pipeline. Depending

on product characteristics, there will be an interface section between the two products

that widens as the product moves along the line. This “off spec” product must be

197

Page 213: Final Report-Group 1

discarded at the receiving end to avoid product degradation. It is often disposed by

mixing with larger volumes of low grade fuel products. This system is often used with

countrywide refined product distribution to terminals.

6.8 Operation and Maintenance Philosophy

6.8.1 Operation

Gulfaks field will be operated in accordance with relevant operators’ procedures guidelines,

Norwegian Petroleum Directorate (NPD), NORSOK STANDARD, Petroleum Safety Authority

and other applicable statutory requirements. The maintenance philosophy is required to ensure

that the operational integrity in every Gullfaks platform facilities is capable of safety

performing the tasks.

Health, Safety and Environment (HSE) involves health and safety of personnel, preservation of

the environment and company’s reputation, safeguards of structure and facilities production of

hydrocarbon. Preventive Maintenance includes inspection, servicing and adjustment with the

objective of preventing breakdown of equipment. This is appropriate for highly critical

equipment where the cost of failure is high, or where failure implies a significant negative

impact on safety or the environment Breakdown Maintenance is suitable for equipment whose

failure does not threaten production, safety or the environment and where the cost of

preventing failure would be greater than the consequence of failure.

Condition Monitoring is to monitor performance of the equipment on a continuous basis, then

abnormal behavior can be identified, and preventive maintenance can be performed when

required. This obviously takes the equipment out of service, and may be costly. Non

Destructive Testing (NDT) Inspection is to detect flaws or imperfection during manufacture or

those that develop during service. Where internal flaws are suspected, use is made of ultrasonic

testing. It is conceived for the following activities:

Routine inspection and maintenance.

Operational tasks such as replenishing chemicals for wax and corrosion inhibition

injection as well as launching the pig to Gullfaks in the pipeline.

198

Page 214: Final Report-Group 1

Housekeeping, consisting of cleaning of sump, solar panels, battery and instrument

checks.

Pipeline Operation Philosophy

The primary process intent is to transport the crude within the pipe line handling capacity of

Gullfaks and its associated network platforms.

Process Control

To achieve the process intent the following shall be monitored and controlled:

Export pressure, temperature and flow rates.

Flow rate fluctuations.

Operations modes: normal/transient-pigging/startup/shut down and blow down.

Moisture/dew point level finally GOR (monitor only).

Pigging

Pipe line requires regular cleaning by pig which removes settled sand, stagnant water collected

at low points (corrosion prevention) ,wax deposit etc. The pig may be in the form of a sphere to

displace fluids or cylinder with brushes to scrape the inside surface of the line. Intelligence

pigs can be used to inspect the pipe line condition and record the results

6.8.2 Maintenance

The aim of maintenance in this case is to protect the technical integrity of the facilities and

pipelines throughout their life cycle, resulting in high availability of equipment and system.

This is in agreement with the design intent to achieve production objectives at optimum costs

without jeopardizing safety, environment, production plans and legal obligations. The

inspection and maintenance philosophy encompasses the following:

i. The designs shall adopt (fit purpose) concept where possible using minimal operator

intervention, reliable components with the highest availability and reliable records.

199

Page 215: Final Report-Group 1

ii. Choice of equipment and systems will be based on proven technology and system with

regional spares and technical support.

iii. Utilization of advanced control system with self-diagnostic and predictive maintenance

capability.

iv. Standardization between systems skids and platform.

v. Maintenance Reference Plan (MRP) delineates the lifetime key maintenance activities

to ensure preservation of the facilities technical integrity throughout its lifetime.

vi. Equipment selection and maintenance based on proven technology that satisfies

specific operating condition, specification and maintainability for the lowest life cycle

costs. Consideration to use new technology will be based on significant advantages

offered over current ones.

vii. Maximising predictive maintenance by monitoring key safety and production

equipment and these parameters shall be extended onshore for shore-based specialists’

surveillance.

viii. Corrective maintenance by using complete serviced units shall be made to reduce

equipment downtime and offshore work when changing out faulty units. Bypass

facility, standby or backup of key critical facilities shall be provided where appropriate

to allow for delayed shore-based maintenance or specialists support.

200

Page 216: Final Report-Group 1

6.9 Project Schedule

Gullfaks’ proposed project schedule is illustrated in table below. Project delay and cost

overruns are most likely to occur during the fabrication period. Great effort will be put in this

stage to ensure expected output could be delivered on time without the expenses of the quality

and extra cost.

Table 48: Proposed Project Schedule

ActivitiesDuration

(Months)

FDP Approval for Gullfaks and Conceptual Integrated

Development 2

Bid Award Cycle - Conceptual Design 1.5

Conceptual Engineering 4

Bid Award Cycle - FEED 1.5

FEED 4

Bid Award Cycle - EPCC 1.5

Detailed Design 4

Procurement 6

Fabrication 8

Lay Pipeline 1.5

Install Jacket and Topside 2

Hook-Up and Comissioning 1

201

Page 217: Final Report-Group 1

6.10 Abandonment

Decommissioning of Gullfaks platform will take place when it is no longer economical to

continue production. During abandonment, all platforms shall be fully removed according to

specification and International Maritime guideline for offshore development structures. Below

are the general abandonment plan is as follows:

Platform should be initially design such that can be removed readily for future

abandonment.

The well shall be cemented and plugged above at least 100 ft from current depleted

zones and killed.

The jacket piles shall be cut below mudline.

All pipeline to and from platform must be pigged, capped and abandoned in-place.

A total of 30-35 days is expected for complete decommissioning of the whole jacket

structure.

Planning for decommissioning is an integral part of the overall management process and

should be considered at the beginning of the development during design. Parts of the facilities

are treated to remove hydrocarbons and other chemicals, wastes or contaminants. Other

components such as flow lines and production components are often left in place or rendered

safe to avoid environmental disturbances associated with removal. The downhole equipment is

removed and the perforated parts of the wellbore are cleaned of mud, scale, and other debris

before wells are plugged and abandoned to prevent fluid migration within the wellbore or to

the surface. Fluids with an appropriate density are placed between the plugs to maintain

adequate pressure. During this process, the plugs are tested to verify their correct placement

and integrity. Finally, the casing is cut off below the surface and capped with a cement plug. It

is prudent to plan for abandonment from the outset, and ensure minimal environmental

disruption.

The following figures show the plugged and abandoned for open-hole completion and for

cased hole respectively.

202

Page 218: Final Report-Group 1

Figure 103: Well Abandonment for Open Hole Completion*

Figure 104: General Well Abandonment for Cased Hole

* Retrieved from http://decarboni.se/publications/guideline-risk-management-existing-wells-co2-geological-storage-sites/appendix-d

203

Page 219: Final Report-Group 1

CHAPTER 7 ECONOMIC ENGINEERING

204

Page 220: Final Report-Group 1

CHAPTER 8 HEALTH, SAFETY AND ENVIRONMENT

CHAPTER 9

205

Page 221: Final Report-Group 1

REFERENCES

[1] Ali Danesh, PVT and Phase Behavior Of Petroleum Reservoir Fluids, Elsevier Science & Technology Books,1998, Chapter 9, p. 325.

[2] Ronald E. Terry , J. Brandon Rogers, Applied Petroleum Reservoir Engineering, 3rd

Edition, Published Aug 1, 2014 by Prentice Hall.

[3] Fanchi, J. R. Principle of Applied Reservoir Simulation, 3rd Edition. Published in 2006

by Elsevier.

[4] (Houston Meeting, May 1944), Analysis of Decline Curves By J. J. Arps,

[5] BoyunGuo, William C. Lyons & Ali Ghalambor, Petroleum Production Engineering,

Elsevier Science & Technology Books, February 2007, Chapter 8 Production Decline

Analysis, p. 98-99 .

[6] Don W. Green& G. Paul Willhite, Enhanced Oil Recovery, SPE Textbook series,

Richardson, Texas 1998, Chapter 1 p.12,

[7] Taber, J.J., Martin, F.D., and Seright, R.S.: "EOR Screening Criteria Revisited," paper

SPE 35385 presented at the 1996 SPE Improved Oil Recovery Symposium, Tulsa,

April 21-24.

[8] Thakur, G.C, “Implementation of a Reservoir Management Program.” SPE Paper

20748 presented at the SPE Annual Technical Conference and Exhibition, New

Orleans, LA, 1991.

[9] Sinha and Raghad, “Quantifying the Value of Surveillance and Developing an

Integrated Surveillance, 2004.

[10] Nalli, K. (2010). Corrosion and Its Mitigation in the Oil & Gas Industry- An

Overview. PetroMin Pipeliner.

[11] Production Operations Engineering ( volume 4)  by Joe Dunn Clegg

[12] Sahu, G. K. Pumps: Theory, Design And Applications,by  Sahu, G. K, 2007

[13] Progressing Cavity Pump. Editions Technip, by Henri Cholet, 1997

[14] Canadian Oilwell Systems Company Ltd. (2013). Basic Artificial Lift. Retrieved

March 17, 2013, from http://www.coscoesp.com/esp/basic%20artificial%20lift

%20tech%20paper/Basic%20Artificial%20Lift.pdf

206

Page 222: Final Report-Group 1

[15] New Mexico Tech (2013). Advanced Artificial Lift Methods. Retrieved March 17,

2013,from https://www.google.com.my/url?

sa=t&rct=j&q=&esrc=s&source=web&cd=2&cad=rja&ved=0CDgQFjAB&url=http

%3A%2F%2Fwww.nmt.edu%2F~petro%2Ffaculty%2FNguyen

%2FPE571%2FPresentation

%2FC1%2F1_IntroductionToArtificialLiftMethods.ppt&ei=AvFGUa_MLIvRrQeSgI

GoDw&usg=AFQjCNFFnF451OyMaeHgvR_NQIg8Sl_HtA&bvm=bv.43828540,d.b

mk

[16] Petroleum Production Engineering: A Computer-Assisted Approach .By BoyunGuo,

PhD, William C. Lyons, Ali Ghalambor. Gulf Professional Publishing 2007

[17] Downhole Tubing & Casing Material Selection: Offshore Production Wells. Retrieved

from http://www.gateinc.com/gatekeeper/gat2004-gkp-2014-08

207

Page 223: Final Report-Group 1

APPENDICES

Production Technology Appendices

Major Risk How each one could add to the

uncertainty of this assessment

Necessary steps that need to be

taken to account for their effects

1. Reservoir Formation

Strength

The formation could damage of

became less integrity during the

production period.

Flow through a gravel packed

completion in a weak sand.

Sand production as the fluid

production increases.

Proper design should be considered

such as the placement of cementing

area to support the borehole

especially.

When conducting the perforation

job, several factors should be

considered in order to have desired

perforated areas. The type of

perforations also need to choose as

optimal as possible, taking the

formation strength into account and

as well as the time and money

factors.

Sand screening tools can be

installed at the bottom hole

assembly of the completion

equipment to avoid higher

production of sand which is

dangerous to some equipments and

as well as inefficient operating

cost.

208

Page 224: Final Report-Group 1

2. The Reservoir

Pressure Decline

Pattern

As the production started, the

reservoir pressure will start to

decline.

It will sometime change the

reservoir type, from a initially oil-

water reservoir to gas-oil-water

reservoir, due to solution gas

liberated into the reservoir,

forming a gas cap portion.

Proper installation of completion

equipments at it optimal and best

selection.

Available reservoir data should be

reconsidered and taken into

account while designing the

completion equipments. The gas

liberated and forming a gas cap

portion will make the oil shrink

and thus reducing the production of

oil.

3. Volume of oil

initially in place

The initial volume of oil in place

is usually estimated at the early

stage of production in order to

estimate the possible hydrocarbon

that could be recovered.

The volume will affect the

economical factor of the field

development.

Maximize the use of available data

such as from the exploration and

logging activities.

The most appropriate correlation

should be applied in order to get

higher recovery factor to the

nearest true value produced.

4. Shallow gas Blowout / gas kick Drill pilot hole

5. Clay swelling Reduces wellbore diameter Use SBM / OBM

6. Wax deposition Decreases production rate Inject hot oil through tubing

7. High CO2 content Facilities corrosion Add corrosion inhibitor

CO2 removal at CPP

209

Page 225: Final Report-Group 1

8. Emulsion Ineffective oil-water separation

process

Add demulsifier

9. Sand production Reduces production and causes

facilities problems

Sand control e.g. gravel pack,

stratapac

10. Scale formation Decreases porosity Add scale inhibitor

11. Reservoir Continuity Reserve Estimation Detailed study on G&G Data

210

Page 226: Final Report-Group 1

211