![Page 1: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/1.jpg)
1
CITY OF PHOENIX REQUEST FOR BIDS
AVIATION DEPARTMENT
PHOENIX SKY HARBOR AIRPORT TERMINAL 3 NORTH INNER APRON RECONSTRUCTION
DESIGN-BID-BUILDPROJECT NO. AV08000081-1 FAA
AIP NO. 30-04-0029-087-2018
June 7, 2018
Pre-Bid Meeting
![Page 2: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/2.jpg)
2
Emeka Ekpe, Contracts Specialist Point of Contact for RFB QuestionsOffice of the City [email protected] (602) 273-3488
John Ojeda, Equal Opportunity CompliancePoint of Contact for DBE RequirementsEqual Opportunity Department [email protected] (602) 262-6690
Mario Mejia, Labor Compliance Specialist Point of Contact for Labor Compliance / Davis Bacon RequirementsStreet Transportation Department [email protected] (602) 534-9269
Rubben Lolly, Project ManagerAviation Department Representative
Welcome and Introductions
![Page 3: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/3.jpg)
3
Sign-in please
Sign-in sheet and PowerPoint will be posted on Procurement’s website:http://phoenix.gov/streets/procurement/current-opportunities
Click on respective project, then click on:■ Planholder List ■ RFQ / RFB ■ Addendums / Notifications (if applicable)
Please hold questions until Q&A period
This is the ONLY opportunity to discuss this project with City staff
Meeting Overview
![Page 4: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/4.jpg)
4
Project Description and Scope of Work Questions?
DBE Program Requirements Questions?
Labor Compliance / Davis Bacon Requirements Questions?
Submittal Requirements Questions?
Agenda
![Page 5: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/5.jpg)
5
Project Description & Scope of Work
Project Location
Project Description & Scope of Work Phasing, Job Site Access & Restrictions Miscellaneous Project Information Questions
![Page 6: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/6.jpg)
6
Project Location
![Page 7: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/7.jpg)
7
PSHIA Terminal 3 North Concourse
Proposed Project Area
![Page 8: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/8.jpg)
8
Project Description & Scope of WorkProvide new Inner Apron Portland Cement Concrete Pavement
(PCCP), Drainage and Hydrant fuel line improvement .
Major work elements include but not limited to:
Demolition of existing PCCP
Construct nearly 35,000 SY of new PCCP of varying
thickness
Install new storm drain system of pipes, trench drains and
interceptor to collect apron and roof storm run-off
![Page 9: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/9.jpg)
9
Project Description / Scope of Work (Cont)
Remove fuel pits and laterals that are no longer in use
Replace bottom entry pits with side entry pits
Relocate some pits to new location to match current/future
aircraft perking positions
Adjust existing pits to new apron grades
![Page 10: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/10.jpg)
10
Project Description / Scope of Work (Cont.)
Pavement Sections vary with the apron as shown
![Page 11: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/11.jpg)
11
Construction will be concurrent with T-3 Modernization North Concurs renovation/Expansion Project
With respect to airfield impacts there will be one Single phase fenced off with a fence
Fence will be installed and removed by T3 Modification Contractor
Barricades within the fenced area will be set by the Inner Apron Contractor
Within the Fenced area the project has 4 phases with subsequent sub phases
Total duration to complete the inner apron project is 264 calendar days
Phasing, Job Site Access & Restrictions
![Page 12: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/12.jpg)
12
Site Access
Site Egress
Storage andstaging area
Phasing, Job Site Access & Restrictions Cont.
![Page 13: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/13.jpg)
13
Phasing, Job Site Access & Restrictions Cont.
![Page 14: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/14.jpg)
14
Site access will be from Sky Harbor Boulevard (SHB) on the northwest corner of the triangle area
Site egress will be via a temporary connection to Terminal 2 down ramp onto SHB.
Storage will be in the triangle area west of the outer apron
Contractor shall limit activities to designated haul routes and staging areas
Phasing, Job Site Access & Restrictions Cont.
![Page 15: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/15.jpg)
15
Miscellaneous Project Information Contractor is responsible for locating utilities
Contractor provide quality controls – City QA
Follow all federal, state and local permitting
requirements
Coordinate with Owner on Project issues
![Page 16: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/16.jpg)
16
Maintain a safe & secure work site at all times
Must use the City’s web based project management
system: UNIFIER - Training provided at no cost
NTP will be issued for the Contract once the NTP from
FAA has been issued.
Miscellaneous Project Information Cont.
![Page 17: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/17.jpg)
17
Miscellaneous Project Information Cont.
Lead Base Paint:
Contact David Stefl (602) 339-3555.
Removal and disposal by others.
Removal during start of each phase.
Contractor to cooperate and provide access.
![Page 18: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/18.jpg)
18
Miscellaneous Project Information Cont.
COP Planning and Environmental: Test for lead and asbestos containing materials Remove any lead and asbestos containing materials
discovered onsite. Review all Safety Data Sheets. Approve locations of all disposal sites. Approve all materials disposed offsite. Approve paint materials. P&E Contact: David Stefl (602) 339-3555
![Page 19: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/19.jpg)
19
QUESTIONS?
![Page 20: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/20.jpg)
20
DBE REQUIREMENTS
![Page 21: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/21.jpg)
The City of Phoenix strives to advance the economic growth of businesses through its
Disadvantaged Business Enterprise (DBE) Program.
The City ensures compliance with federal regulations on all federally funded projects.
The City encourages the participation of DBE firms throughout ALL phases of contracts.
DBE Program
![Page 22: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/22.jpg)
.
The DBE Program provides socially (minority and woman-owned firms) and economically disadvantaged business owners: • Certification• Procurement opportunities• Construction subcontracting utilization• Small business development services • Technical assistance/educational services • Networking opportunities
DBE Program
![Page 23: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/23.jpg)
DBE Requirements
The City has not established a race-and gender-conscious DBE participation goal
Current focus is Small Business Outreach
The FAA approved a triennial DBE goal of 4.44%for fiscal years 2016-19, to be achieved through fosteringSmall Business participation and outreach requirements.
Project is in part funded by FAA and is subject to 49 CFR Part 26 and USDOT DBE Program
![Page 24: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/24.jpg)
Certified DBE Firms
To participate in this opportunity as a DBE, only firms certified by the City or
another AZUCP member in the specified scopes of work shall be
considered in calculating DBE participation.
Eligible DBEs can be found at: https://utracs.azdot.gov
![Page 25: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/25.jpg)
www.azutracs.azdot.govDBE Firms
![Page 26: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/26.jpg)
OUTREACH EFFORTS-ATTACHMENT AAll Submitters must provide at submittal: Documents in a separate sealed envelope Must complete and submit Columns A – D Failure to submit = Non-Responsive
Above are due at the time of the bid, statement of qualifications,
or proposal submittal.
DBE Requirements
![Page 27: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/27.jpg)
OUTREACH EFFORTS - ATTACHMENT AAll Submitters must provide within
3 Business Days of the bid deadline:Documents in a separate sealed envelopeMUST complete and submit Columns E and F Submittal of all related Supporting Documentation MUST include:
Copies of the actual solicitations sent to DBEs & Small Businesses Names of the DBEs & Small Businesses whom bidder negotiated with
and the firms that have been selected to participate in the contract MUST demonstrate how, when, and the name of the person to whom
the bidder specifically communicated its selection decisions Outcomes to each DBE and Small Business NOT selected Documentation may be in the form of a letter, e-mail, telephone log, or
other acceptable communication
DBE Requirements
![Page 28: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/28.jpg)
OUTREACH EFFORTS - ATTACHMENT BSmall Business Utilization Commitment
All Submitters must provide within3 Business Days of the bid deadline:
Documents to be included in the separate sealed envelope
The successful bidder must ensure the DBE and SmallBusiness participation percentages proposed inAttachment A add up to the TOTAL percentage stated inAttachment B
The successful bidder will be contractually obligated toachieve the participation percentage in Attachment B
DBE Requirements
![Page 29: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/29.jpg)
For more information please contact:
John OjedaDBE Compliance Officer [email protected]
602-262-6690
Equal Opportunity Department
![Page 30: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/30.jpg)
30
QUESTIONS?
![Page 31: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/31.jpg)
31
LABOR COMPLIANCE REQUIREMENTS
![Page 32: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/32.jpg)
CITY OF PHOENIX LABOR COMPLIANCE OFFICE
Monitors and enforces the federal labor standards on federally funded Capital Improvement Construction.
Applies to all federally funded contracts in excess of $2000 with few exceptions
All contractors and subcontractors, including lower-tiers, working on the project are covered
![Page 33: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/33.jpg)
DBRA (Davis-Bacon & Related Acts)
Davis-Bacon Act (DBA)
Copeland Anti-Kickback Act
Contract Work Hours and Safety Standards Act (CWHSSA)
![Page 34: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/34.jpg)
FEDERAL REGULATIONS
Code of Federal Regulations, Title 29 Part 3
Code of Federal Regulations, Title 29 Part 5
LCP Tracker
Wage Decision
![Page 35: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/35.jpg)
Labor Compliance Pre-Construction Conference
Labor Compliance Office, (602) 261-8287
Websites available: http://www.dol.gov/dol/esa/programs/dbra
TECHNICAL ASSISTANCE
![Page 36: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/36.jpg)
36
QUESTIONS?
![Page 37: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/37.jpg)
37
Bidders Should Review: Information for Bidders (IFB) Section:
Bid Submittal ChecklistItems due at time of bid submittal
Post-Bid Submittal ChecklistItems due 3 days after bid opening by 5:00 p.m. Phoenix Time
E-mail to: [email protected]
Non-Responsive =Failure to provide Bid Bond
Failure to submit all required Bid-and-Post Bid documentsFailure to acknowledge / signatures as required
![Page 38: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/38.jpg)
38
Receipt of Bid after the specified cut-off date and time
Deposit of Bid in the wrong location
Violating the “Contact with City Employees” policy
Failure to provide Bid Bond
Grounds for Disqualification
![Page 39: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/39.jpg)
39
2:00 P.M. Phoenix time
Tuesday, June 26, 2018
City Hall, 200 W. Washington Street
6th Floor, Submittal Box
Bid Due Date
![Page 40: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/40.jpg)
40
https://www.phoenix.gov/streets/procurement/current-opportunities
Request for Qualifications / Request for Bids
Notifications / Addendum (if any)
Plan Holder List
Award / Bid Tabulation
Pre-Bid / Pre-Submittal Power Point Presentation
Pre-Bid / Pre-Submittal Sign-in sheet
Sign up for Procurement Newsletter
Street Transportation DepartmentProcurement Section WEBPAGE
![Page 41: FINAL - 6-7-18 Pre-Bid Presentation - AV08000081-1 1 FAA PSHIA...2 Emeka Ekpe, Contracts Specialist Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov](https://reader033.vdocuments.site/reader033/viewer/2022043008/5f97ce27899c6f4d020cb804/html5/thumbnails/41.jpg)
41
E-mail your questions to:
[email protected] Ekpe
Contract Specialist(602) 273-3488
OPEN FOR QUESTIONS&
Thank You for Attending!!!
Questions After Today