    Estimating the Cost

    of New Construction

    Using PERCEPTION

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    2/39

    Computerized Cost Estimating

    Computer-based tools to quickly

    formulate a cost estimate

    Manage cost data from central database Maintain current catalog of actual costs

    Maintain catalog of prior estimates

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    3/39

    Establish Libraries ofCentrally Available Cost Data

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    4/39

    Benefits

    Fewer cost surprises

    Faster bid response

    Lower cost risk Greater profit potential

    More competitive bids

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    5/39

    Basic Tool Set:

    Application of learning curvesComplexity & productivity factors

    Cost escalation

    os r s ana ys sCost trade-off

    Global edits and update features

    Return cost data analysisUser documentation of cost estimate

    Tracking of estimate sources and changes

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    6/39

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    7/39

    Identify Work Items

    Work Items may be cataloged by Ship System WBS (SWBS)

    Ship Owners WBS

    Government Contract Line Item (CLIN)

    Each structure can be customized by shipyard, by contract.

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    8/39

    Identify Work Process

    Work Process may be cataloged by Stage of Construction (Rip-Out, Shop Work,

    - , - , - ,

    Shipyard Department (COA)

    Each structure can be customized by shipyard, by contract.

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    9/39

    Cataloging Standard Costs

    CatalogStandard Cost

    Estimating

    Relationships (CERs)onto Computer

    Database

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    10/39

    What is a CER?

    A Cost Estimate Relationship (CER) is a formula relating thecost of an item to the items physical or functionalcharacteristics or relating the items cost to the cost of

    another item or group of items.Examples:

    a) for steel block assembly, 25 man-hours/ton;

    b) for pipe material, $25/meter; and

    c) for shipyard support service, 10% productionhours.

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    11/39

    Cataloging Standard Costs ByWork Sequence

    LOFT

    PLAN

    PREP FAB ASS'M P/OHOT

    ERECTP/O

    COLDBLASTPAINT

    Pre-Outfitted Hull Block Construction

    Equipment & OutfitSystem Modules

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    12/39

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    13/39

    Complete Equipment Packages

    Cargo Zone Packages

    Develop Standards of Labor &Material Cost Packages

    Accommodations Outfit PackagesSafety Equipment Packages

    Electronics Packages

    Shipyard Services Packages

    .....and more.

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    14/39

    Cataloging Standard Costs BySequence

    Rip-Out Replace

    Engineer Fabricate

    Install

    Test

    Install

    TestEngineering

    SpecificationsProductionDrawings

    ShopFabrication

    ComponentInstallation

    SystemTests

    Rip-Out Repair Re-Install Test

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    15/39

    Possible Levels ofProduct-Based CERs

    Cargo Hold

    Block Erection

    Outfit Fittings

    Mhrs/BBL

    Mhrs/Ton

    Mhrs/EA

    Outfit Pipe

    Block Paint

    Block Assembly

    Steel Fab

    Steel Prep

    Mhrs/IN-FT

    Mhrs/SQFT

    Mhrs/Ton

    Mhrs/Ton

    Mhrs/Ton

    Product&

    Process

    Sequenc

    e

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    16/39

    Outfit CERs byStage of Construction

    Pipe Work

    450,000

    -

    50,000

    100,000

    150,000

    200,000

    250,000

    300,000350,000

    400,000

    1 2 3 4 5 6

    Ship Number

    LaborHours Total

    On-Ship

    On-Block

    Pipe Fab

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    17/39

    Cataloging Standard Costs ByShip System (SWBS)

    Structural Work Electrical

    Machinery

    Piping

    HVAC

    Paint

    Outfit

    Shipyard Services

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    18/39

    Bow Construction Zone Cargo Construction Zone

    Cataloging Standard Costs ByShip Zone (PWBS)

    Machinery Construction Zone

    Deckhouse Construction Zone

    Stern Construction Zone

    Ship-Wide Construction Zone

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    19/39

    Variations of CERs:

    Single V-butt weld size 3/16" - 5/16" (2 pass) 0.250 MH/FT

    Line Item CER:

    Welding Repairs:Cracks Labor CERLabor UoMMaterial CER

    Drill Out 0.500 MH/FT -$

    Welding Repairs: 0.250 MH/FT 1.4680$

    Gen Labor: 0.250 MH/FT -$

    Total: 1.000 MH/FT 1.4680$

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    20/39

    Variations of CERs:

    CERs Based Upon Ship Design &Performance Characteristics:

    Labor Hours Material Cost UoM

    CER CER CER

    Cargo Transfer Pumps 0.0606 $22.93 GPMPaint 15.59 $425.17 CuNo

    Shafting 0.1695 $20.26 kW

    Dry Docking $0.27 Days-GRT

    Hauling $0.50 Days-LOA

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    21/39

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    22/39

    Cost Adjustments

    a us

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    23/39

    Automating Cost Adjustments

    Work ProductivityWork Site

    ork Access

    Economic Cost Escalation

    Learning Experience

    Standard Material SavingsMaterial Waste Adjustments

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    24/39

    Impact of Work Productivity

    Alternate Methods: Expensive staging versus mobilelift

    Automation: Manual versus automated weldin

    Alternate Resources: In-House versus Sub-Contract Worker Skill Level

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    25/39

    Impact of Work Site

    Added Cost Factor

    500%

    600%

    0%

    100%

    200%

    300%

    400%

    In Shop On Block On Board

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    26/39

    Impact of Work Access:

    Added Cost Factor

    50%

    60%

    0%

    10%

    20%30%

    OnWeatherD

    eck

    OilTanks

    EngineR

    oom

    Superstru

    cture

    PumpR

    oom

    H

    olds

    DoubleBot

    toms

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    27/39

    Impact of Work Access:

    Over-Head Down-Hand

    More Difficult = More Expensive

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    28/39

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    29/39

    Impact of Cost Escalation:

    Cost Escalation Index

    1.35

    1.40

    1.00

    1.05

    1.10

    1.15

    1.20

    1.25

    1.30

    1995 1996 1997 1998 1999 2000 2001

    Year

    EscalationInde

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    30/39

    Impact of Learning:

    Cost Reductions From Repeatability

    120%

    ost

    0%

    20%

    40%

    60%

    80%

    100%

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

    Number of Similar Items Worked

    Perc

    entofFirstItem

    C

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    31/39

    Impact of Standard Materials:

    Standard material items typically less

    expens ve an non-s an ar ems.Standard material deliveries less

    expensive than high-priority rush orders

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    32/39

    Cost Risk Analysis

    $1,600

    $1,800

    Cost Risk

    MinimumExpected

    Maximum

    $0

    $200

    $400

    $600

    $800

    $1,000$1,200

    $1,400

    Range of Costs

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    33/39

    Cost Risk Analysis

    Cost Probability

    100%

    120%

    0%

    20%

    40%

    60%

    80%

    $0 $500 $1,000 $1,500 $2,000

    Cost Range

    Probability

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    34/39

    Hardware Options

    Single User Laptop Single User Desktop

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    35/39

    Hardware Options

    Multi-User Network

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    36/39

    Many Report Formats

    Detail Cost Item Reports

    WBS Summary Reports Major Equipment Lists

    Detail Bills of Material

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    37/39

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    38/39

    Other Capabilities:

    Import/Export: Spreadsheets & Databases Data Analysis Module: statistical analysis of

    cost information to develop CERs

    e urn os o u e: n o s pyarproduction management systems

    Link to CAD systems: automated costestimating from design process

    Link to CAD systems: automated down-loadingof bills of material

  • 8/11/2019 Estimating the Cost of New Construction Naval Ship

    39/39