Guiyang World Bank Financed Transport Project
Sub-project 1: Youxiao Road
ENVIRONMENTAL MANAGEMENT PLAN
Constructor: Guiyang Project Management Office
Author: Guizhou Institute of Environmental Science and Designing
December 2006
E1632v 3
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
World Bank Financed Guiyang Traffic Project EMP Sub-project 1Youxiao Road Project
2
Compiler: Guizhou Institute of Environmental Science and Designing�
Certificate: No.3302, Grade 1, National Environmental Assessment
Legal person: Zhang Wei
Institute’s technical chief: Zhang Tao
Environment assessment project chief: Zhang Junfang (Engineer)
Outline Compilers
Name Title Tu Zhijiang Senior Engineer Zhu Keyong Engineer Luo Jing Engineer Xie Yun Engineer Zhang Junfang Engineer
ReviewerName Title Yang XieKe Senior Engineer Shi Lunxuan Senior Engineer
World Bank Financed Guiyang Traffic Project EMP Sub-project 1Youxiao Road Project
3
List of Abbreviations
EA Environmental Assessment
EIA Environmental Impact Assessment
EMP Environmental Management Plan
BOD Biological Oxygen Demands
COD Chemical Oxygen Demands
TP Total Phosphor
dB(A) Decibel (Acoustic)
NH3-N Ammonia Nitrogen
pH Acidity unit
SS Suspended Solids
NO2 Nitrogen Dioxide
OP (World Bank) Operational Policies
PMO Project Management Office
PRC The People’s Republic of China
EPB Environmental Protection Bureau
TOR Terms o f Reference
World Bank Financed Guiyang Traffic Project EMP Sub-project 1Youxiao Road Project
4
CATALOGUE
1 Foreword and Project Background........................................................................................... 5
1.1 Project Background............................................................................................................... 5
1.2 Project Content...................................................................................................................... 5
1.3 EMP purpose, guideline and requirements............................................................................ 6
1.3.1 EMP purpose...................................................................................................................... 6
1.3.2 Action guideline and requirements..................................................................................... 7
1.4 EA Basis and implementary standard.................................................................................... 8
1.4.1 EA Basis.................................................................................................................... 8
1.4.2 Standards for EIA...................................................................................................... 8
2 Environmental impacts and mitigations................................................................................. 11
2.1 Environmental impacts and mitigations during design phase ............................................. 11
2.2 Environmental impacts and mitigations during construction phase.................................... 12
2.3 Environmental impacts and mitigation measures during operation phase .......................... 15
3 Environmental management and supervision....................................................................... 17
3.1 Frame structure of environmental management organ........................................................ 17
3.2 Purpose................................................................................................................................ 17
3.3 Environmental management................................................................................................ 18
3.3.1 Work scope of environmental management ............................................................ 19
3.3.2Work scope of supervision ....................................................................................... 19
4 Environmental monitoring plan............................................................................................... 21
4.1 Purpose and base of making monitoring plan ..................................................................... 21
4.2 Monitoring items................................................................................................................. 21
4.3 Environmental monitoring program.................................................................................... 21
4.4 Procedure of monitoring ..................................................................................................... 23
4.5 Environmental monitoring report........................................................................................ 24
4.6 Monitoring cost ................................................................................................................... 25
5 Training plan................................................................................................................................ 26
6 Environmental protection investment..................................................................................... 27
6.1 Environmental protection cost estimation........................................................................... 27
6.2 Environmental protection cost estimation for construction phase....................................... 28
6.3 Environmental protection cost estimation for construction phase....................................... 28
6.4 Ratio of environmental protection investment to the total .................................................. 29
World Bank Financed Guiyang Traffic Project EMP Sub-project 1Youxiao Road Project
5
1 Foreword and Project Background
1.1 Project Background
For the purpose of pushing forward the social and economic development for
Guiyang City in a manner of full scale, harmony, sustainable and leaping, CPC Guiyang
Municipal Committee and Guiyang Municipal People’s Government have co-defined
the strategic blueprint for the Guiyang’s future, Construction of Big Guiyang City. The
construction of urban road from Youzha street (Guiyang city) to Xiaobi township, is
right derived from this great strategy. This proposed road will connect 3 districts
directly, Xiaobi township, Longdongbao district, and Ergezhai district, and provide
huge possibility for the migration of Nanming district administrative center from its
original place to Longdongbao district. On the other hand, the passenger and freight
transportation demands have rise significantly along with the rapid social and economic
development, and subsequently conflicts between traffic supply and demand surfaced.
As a result, the southeast traffic external hub has been shifted to Youzha street. Under
this condition, the construction of this proposed You-Xiao road will alleviate the traffic
pressure and contribute a lot to build an express for the urban areas. This project is a
member of Guiyang World Bank Financed Project—construction and upgrade of urban
and country road network in Guiyang city.
1.2 Project Content
This proposed road starts at the conjecture of Shinan road and Baoshan south road,
then runs into a tunnel spanning the Forest Park, and comes out at the north side of
Party School of CPC Guiyang Municipal Committee (position K2+728 within the
Forest Park), then overstrides Yuliang River, and via Xingzheng road of Longdongbao
joins the Southwest ring road which is under construction. Parameters of the road are,
vertical slope at 4%, minimum radius of plane arc at 300 m, total length at 6592.577 m
(including 1186.55 m of the Grade 1 urban trunk road in downtown area of Guiyang
city, 2489.131 m of highway, and 2916.891 m of the Grade 1 urban trunk road in
Longdongbao district). The section linking Jianlong road has a length 423.071m,
including 1 bridge of 371.7m long, 1 tunnel of 1793 m long, 1 flyover. The area
involved in house relocation is 27759 sq meters. The technical and economic
parameters of this project are listed in Table 1-1.
World Bank Financed Guiyang Traffic Project EMP Sub-project 1Youxiao Road Project
6
Table 1-1 General description of the project components No Name of the index unit Index or abstracts Note: 1 Project owner Guiyang Municipal Administration
of Transportation
2 Proposed project site Nanming District, Guiyang City 3 Project category Urban infrastructural facilities
project(Road)
4 Project scale Trunk line M 6592.577 (1) Total length Connecting line
M 423.071
Trunk line M 25 Double ways and 6 traffic lanes
(2) Width of the traffic lane
Connecting line
M 24 Double ways and 6 traffic lanes
(3) Length of drainage pipe networks
M 19643.81
(4) bridge M/per bridge 371.7/1 (5) Tunnel M/per tunnel 1793/1 (6) Cloverleaf junction 1 unit 2 (7) Total areas of red line area M2 313349 5 Total investments of the project Ten thousand
Yuan 104487.11
6 Construction period of the project
year 3.3
The EIA revealed that this project will contribute to the improvement of traffic
condition for Guiyang city, especially to Longdongbao district’s development although
undeniably it will bring some negative impacts to small scope of areas during
construction and operation phases. As a part of EIA document, this EMP is also
required by World Bank, and intends to ensure the environmental impacts mitigations,
proposed in the EIA be put into practice indeed.
1.3 EMP purpose, guideline and requirements
1.3.1 EMP purpose
As predicted by the EIA, major project-involved pollution is from vehicle noise
and exhaust. This EMP has detailed contents such as environmental impact mitigations,
environmental management, supervision and monitoring. It will act as the instructive
document in implementing those actions in ways of:
(1) to identify the environmental impact mitigations for affected objects. The
PMO, EIA compiler, and design party have conducted field investigation and
confirmation towards the environmental sensitive objects and make out effective
environmental impact mitigations which have been enclosed into the engineering design
document.
World Bank Financed Guiyang Traffic Project EMP Sub-project 1Youxiao Road Project
7
(2) to provide an instructive document regarding environment-related issues. This
EMP will be distributed to construction supervision agency, and environmental
management agency and other parties concerned after it has been evaluated and
approved by World Bank.
(3) to sort out the role and responsibilities for each party. This EMP has clearly
defined the role and responsibilities for involved administrative and operating
departments or agencies, and presented the channels and methods by which these
departments communicate with each other.
(4) to propose the monitoring plan for construction and operation phases. This
EMP has drafted out the environmental monitoring plan in order to ensure the
environmental mitigations be put into practice and to do the preparing work to prevent
and control the unpredictable or accidental pollutions.
1.3.2 Action guideline and requirements
World Bank officials, international consultation professionals, EIA party and PMO
have co-worked to promulgated the overall goal of the environmental management for
this project: to keep the sustainable development in social, environmental and economic
aspects for Guiyang city, and improve Guiyang city’s traffic condition, and reduce or
eliminate and compensate the negative impacts, arising from this project
implementation, to rural group and environments.
Action:
(1) to propose and perform the environmental management and monitoring plan;
(2) to propose and perform the strategy of vehicle emission mitigations in order to
alleviate the impacts to ambient air.
Requirements:
(1) to examine the monitoring results towards each pollutant listed in the
monitoring plan during construction and operation phases;
(2) to implement the environmental impact mitigations proposed by the EIA
according to the specified procedure.
World Bank Financed Guiyang Traffic Project EMP Sub-project 1Youxiao Road Project
8
1.4 EA Basis and implementary standard
1.4.1 EA Basis
Relevant regulatory, policy and administrative requirements for environmental assessment of
development projects in China, both at state and municipal levels, were followed during the
preparation and evaluation o f environmental assessment, as were the Bank’s safeguard policies.
Major laws and regulations applied in the EA are as follows:
Laws of Environmental Protection o f the PRC of December 26, 1989;
Law of Air Pollution Control o f the PRC of September 1,2000;
Law of Water PollutionControl o f the PRC of May 15, 1996;
Law of Environmental Noise PollutionControl of the PRC o f March 1, 1997;
Law of Cultural Property Protection o f the PRC of October 28, 2002;
Guizhou Environmental Protection Regulations of 1992;
Management Regulations on Environmental Protection for Construction Projects of
November, 1998;
Technical Specifications for Environmental Impact Assessment; and
Various applicable regulatory standards for air, water, noise and non-contaminated biological
fields;
World Bank safeguard policies: Environments Assessment (OP/BP/GP4.0l), Natural Habitats
(OP/BP4.04), Cultural Property (OP4.1l).
The EA also makes the reference to various project preparation documents,
including project feasibility study reports, Guiyang City Master Plan (1996-2010), and
expert opinions and review comments for the EA TOR. Various graded plans for road
net related with the project have also been the basis for the EA..
1.4.2 Standards for EIA
1) Aquatic environment
Major affected river by the project is Yulianghe River. According to
“Environmental Functional Area Classification of Surface Water Area in Guiyang
City”, Water bodies involved in the project area belongs to water environmental
functional area class II. Therefore, the “Environmental Quality Standard For Surface
Water” (GB3838—2002) Class II is the proper standard for the assessment of water
quality. Relevant standards see table 1-1�
Table1-1 Water environmental quality standards�
World Bank Financed Guiyang Traffic Project EMP Sub-project 1Youxiao Road Project
9
standards
items pH
NH3-N
mg/L
CODcr
mg/L
Permanganate
index
mg/L
BOD5
mg/L
Petrol
eum
Oils
mg/L
TP
mg/L
Fecal
coliform
group
unit/L
GB3838-2002
Class�6 9 0.5 15 4 3 0.05 0.1 �2000
2) Ambient air environment�
The project area is located in the ambient air quality functional area class 2. The
correspondent air quality standards is “Ambient Air Quality Standard” GB3095-1996
Class 2. The correspondent standard for asphalt gas during the construction phase is
“Integrated emission standard of air pollutants” GB16297-1996. Details see table 1-2
and 1-3.
Table 1-2 Ambient Air Quality Standard�Unit mg�m3�
Pollutants Nitrogen dioxide (NO2) Total suspended
particulate (TSP)
Values Daily average 0.12 0.30
Table 1-3 Standards for Asphalt Gas Emission Unit mg/m3
Pollutants Production process Maximum allowed concentration
for emission
Concentration limits for
non-organized emission
Asphalt Gas Asphalt smelting and
mixing
40~75 The obvious non-organized
emission is not allowed
3) Noise environment
The area 35m outside the two wings of red line of the road should carry out “Urban
environmental noise standard” �GB3096-93�Class 2, and noise sensitive buildings
such as hospital, schools in the area 35m inside the two wings of red line of the road
should carry out “Urban environmental noise standard” �GB3096-93�Class 2, while the rest area should carry out “Urban environmental noise standard” �GB3096-
93�Class 2. Details see table 1-4�
7DEOH1-4 �1RLVH�HQYLURQPHQWDO�TXDOLW\�VWDQGDUG��unit dB A
No Areas Standard and document
No Class Daytime Night
1
35m inside the two
wings of red line of the
road
“Urban environmental
noise standard”
�GB3096-93�
4 70 55
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
10
2
noise sensitive
buildings such as
hospital, schools in the
area 35m inside the two
wings of red line of the
road
2 60 50
��
35m outside the two
wings of red line of the
road
2 60 50
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
11
2 Environmental impacts and mitigations
This is an urban traffic upgrade project, with the principle of People-Oriented, the
construction of this project aims to provide a convenient, comfortable, and fast
transportation for the people, so that to improve their living quality, and refresh the
city’s environment as well as landscape. However, it is unavoidable that there will be
some negative environmental impacts generated during project design, construction and
operation phases. Based on the EIA report of this project, this EMP concluded the
mitigation measures towards such environmental impacts.
2.1 Environmental impacts and mitigations during design phase
Table 2-1 Environmental impacts and mitigations during design phase
Category Impacts Mitigations Execution agency
Resettlement To compile social impact assessment report, and resettlement action plan; make out resettlement compensation policy and implementation procedure.
Local government, Project management office
Concerns about weak group To deliberately design the road and its width, and set up blind road; and crossing road should be accessible for wheel chairs.
Design agency
Social environment
Passage separation To set up 5 street-crossing systems at the positions of K0+340, K0�380�K3�600, K4+720�K5+480, among which the latter two are built especially for farmers use, to pass their agricultural machineries.
Design agency
Noise environment
Noise impacts: operation noise will impose effects on environmental sensitive objects.
· To skip the road routine from villages, schools, hospitals and other sensitive objects. · To lower the vertical slope, in order to obtain least increase of noise level due to vehicles climbing up; · To select lower noise generation material to pave the road surface, to reduce the tire-ground fraction noise. · To use heavy-density materials to make bars of central separating belts and fences; thickening material(more than 3mm thick) is preferred. · to modify road warning signs, to reduce noise level arising from vibrating, braking, speeding up and etc. · Environmental sensitive buildings should not be arranged within 40 m to both sides of the road. For the existing sensitive buildings less than 50 m away from the road sides, they should be removed away gradually in compliance with Urban Plan. · To install noise screening walls, 3.5m high, 500m long on the flyover. To install ventilation and noise separating windows for the 60 households of Youzha village.
Design agency, Planning department
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
12
Vehicle emission: Vehicle Exhaust will disperse and cause pollution to the environmental sensitive objects which inhabit along the routine.
To arrange skyscrapers which will be built in future at the places further than 20m from the road restriction line. Schools, hospitals and other sensitive objects should not be built within 40 m from road restriction line.
Planning department
Dust from construction material mixing sites: This part of dust will bring pollution to environmental sensitive objects which inhabit at its downwind.
To set concrete and asphalt mixing sites at the downwind, and at least 200m from environmental sensitive objects
Design agency
Ambient air
Flying dust arising from transportation. This part of dust will contaminate the ecological environment of the Forest Park.
To forbid using the Yuanlin Road within the Forest Park as transportation route in hauling construction materials
Design agency
Life sewage discharge To use septic tank to treat the life sewage generated by construction workers
Design agency
Bridge surface rain drainage To install rain collection pipes to convey the bridge surface rain to sewage interception ditch of Yuliang River
Design agency
Water environment
Water intake spot at the bridge site
To move the water intake spot upward 100 m. Design agency
Solid waste dumping grounds To initialize the fir forest at Mutouzhai village as the solid waste dumping ground. It is 1.5km away from the tunnel exit which is the major solid waste source. The proposed dumping ground has an area of 15 hm2, with the design capacity of 400,000 m3.
Design agency
Ecology
Water and soil loss in the solid waste dumping ground
To build solid embankments at the depressions facing Yuliang River.
Design agency
Landscape Incompatibility: Roads, flyovers, and bridges are not compatible with their surrounding landscape.
· To grow parterres or lawns in the areas near the buildings, or in the isolation strips of the newly built roads; · To plant green belts, for example, lawns or green tree fences along the both sides of the road; · To decorate sculptures, and green parergons at the road crossing, or in the space between buildings and streets.
Design agency
2.2 Environmental impacts and mitigations during construction phase
The construction will generate impacts to social, sound, air, water and ecological
environments. Although majority of such impacts is transient and recoverable, sufficient
attention is still needed to be paid on them during environmental impact assessment.
The environmental protection liabilities of construction party should be enclosed in the
bidding document, to make sure the construction party has a full understanding about
that. The environmental impacts and mitigations during construction phase are listed in
Table 2-2.
Table 2-2 Environmental impacts and mitigations during construction phase
Category Impacts Mitigations Execution agency
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
13
Disturbance to traffic condition of concentrated residential areas
· To apply semi-enclosed construction style during road reconstruction, to leave passage for walkers, bicycles and public buses. · To build temporary roads and simple bridges and set necessary safety assuring facilities, in order to facilitate going in-and-out for people and groups who inhabit along the routine. · To stockpile construction materials in order, and employ special person to manage this; to clear and deliver out waste materials timely. By doing so, the impacts of land occupation and traffic blocking due to material dumping can be reduced.
Construction party
Migration of power and communication lines
A safety supervisor should be present at the site where the power line is being relocated. At such site, obvious warning lines and night flashing indicators should be installed.
Construction party
Obstruction to local traffic and transportation
· To make reasonable construction plan, arranging neighboring or intersecting sections in different construction stages as possible as it can. · To supply illumination for sections where require un-broken lighting. · To strengthen traffic management and organization.
Construction party, project management office
Damage to the roads used as material transporting line
Before the construction begins, to consolidate the roads which are used as transportation lines. If such roads are damaged due to the construction material transportation, the construction party should recover the roads or offer compensation to local residents.
Construction party
Land use · To strengthen management on construction behavior. The construction activity can only take place in designated sites, randomly occupying farmlands or forests is not permitted. · To forbid construction vehicles exploring passages through farmlands randomly.
Construction party
Cultural and historic sites along the routine
The Tuyunguan Cultural Relics Protection unit is located within the Forest Park. Estimated from the space position, impacts caused by this project construction will not approach this unit. However, if new cultural relics or historical sites are found during the construction activity, the construction party should inform the cultural relic management departments at the first time, and take protection measures at the same time.
Construction party
Impacts to tourism due to enclosed construction, flying dust and noise in the Forest Park section
· Enclosing of the roads will affect the traffic fluency within the Forest Park. So the construction party should do their best to quicken their action and shorten the construction term. · To clear and deliver the discarded earth work out timely; to increase the water-spray frequency, install temporary noise-screening facilities, and forbid night construction activity. · To place bulletin boards on the construction site, marking information such as construction content, contact person, and complaint telephone number.
Construction party
Social environment
Issues on social safety and self-protection of the construction workers
· To train the construction workers on subjects of law and environmental protection. · To prompt safety and health education(especially precautions of infectious diseases, HIV/AIDS and etc) towards construction workers, in order to protect their operation safety and physical health. · The employer or the construction party should spread safety-issued flyers, posters or brochures.
Construction party
Sound environment
Noise generated by construction machines and transportation vehicles
· To select lower noise-generating construction machines; in the sensitive sections, speed limit and no bugle should be observed by construction-material transportation vehicles. · To forbid night construction activity. If unavoidable,
Construction party
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
14
the construction party should open this application to the public, and achieve their approval prior to doing so. · To adopt static-state blast in the tunnel construction.
Flying dust generated from earth work excavating and refilling, material loading and unloading, and house demolition.
· In the construction site, to spray water 4~5 times per day to inhibit dust. · To increase the frequency of water spray, and pack firmly the newly built embankments as soon as possible in the case construction activity taking place in areas near environmental sensitive objects. · To keep the construction roads flat and neatly, and employ special persons to do the work of maintaining and cleaning such roads. · To offer labor-protection appliances to construction workers. · To pile up the excavated earth works in concentrated places.
Construction party
Ambient air
Transportation vehicles · To use the modified vehicles with covers to transport the construction materials, including lime, sand, earth works, and etc.
· To forbid using the pavements(Yuanlin Road) within the Forest Park as transportation lines in hauling construction materials.
Construction party
Life sewage discharge in the construction area
· To set up a septic tank at the position K0+937, leading to municipal sewer; to set up another septic tank at the position K4+250, leading to the interception ditch of Yuliang River. · To clear and dredge the septic tanks periodically. This will be performed by the environmental sanitation department.
Construction party
Production wastewater discharge in the construction area
·To recycle the material-washing wastewater. After treated by staged sediment, the wastewater can be reused. · To use sediment tank and oil-water separating system to treat machinery and vehicle flushing wastewater.
Construction party
Water environment
Contamination to Yuliang River due to construction of bridge pile foundation and bridge surface
·To locate the stockpile ground of construction material far from water bodies to avoid runoff flushing. · To forbid dumping solid waster generated from the construction of abutments into water. Instead it should be transferred to the bank and get proper disposal, for example used as roadbed material. ·To strengthen the management on construction machines, to avoid any oil running off, spilling, dripping, and leaking.
Construction party
Destruction to land resource
· To reduce land occupation, especially for fertile soils, and by pass basic farmlands; · To forbid dumping grounds, temporary construction site and roads occupying basic farmlands. · Soil in the arable layer of the occupied farmlands should be set aside, and later reused in new reclamation or soil improvement.
Construction party
Potential damage to forest resource
To carefully protect surrounding vegetation and transplant the trees which stand right on the line of the road during the construction of the Forest Park section
Construction party
Impacts to water supply for the Forest Park
To plug or drain the water according to its flux, and adopt more mitigations, for example environmental monitoring, pre-drilling, geological radar detection, and curtain grouting, to reduce water loss.
Construction party
Ecological environment
Water and soil loss in the dumping ground
· To build retaining walls for the dumping ground, adhering to the principle of retaining first, if retaining can not work, then consider discarding. Drainage ditches should be set on the top and side of the discarded soil dump. On the bare area of the dumping ground, to spread grass seeds to address it with green. · After the dumping ground comes to the end of its service life, to reclaim or plant vegetation on it.
Construction party
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
15
Damage to natural landscape along the routine during construction
· To install visually obvious boundary or fence around the construction site · To clear and recover the construction sites immediately after the complete of construction. · To forbid random chopping trees, digging pits, or dumping solid waste. · To eliminate any visible scattered soil dumping spot within the eyesight scope along the routine
Construction party
Water pipes in the dumping ground may be buried.
To protect or re-install water pipes in the dumping ground.
Construction party
Methane gas released from the construction of tunnels
To install methane indicator, which will activate the ventilation equipment when methane concentration is detected to overrun the standard limit.
Construction party
A large amount of construction garbage due to house demolition, industrial factories relocation
To reuse the old construction material in the construction of resettled houses. For the un-reusable part, to convey them to the landfill for proposal.
Construction party
Life garbage of construction workers
To dump in a fixed place. In the rural area, they can be reused as agricultural fertilizer; in urban area, they should be collected and then sent to landfill by local environmental sanitation department.
Construction party
Solid waste
Discarded earthwork from tunnel excavating
To reuse part of them in ground leveling or soil covering for the temporary construction site in bridge construction; to send other parts which can not be reused, to the specified dumping ground.
Construction party
Water and soil loss
Water and soil loss will be deduced from tunnel excavating, roadbed refilling, and road surface pavement.
· To clear the excavated earth work daily, if not achievable, they should be dumped and packed tightly into a slope ratio of 1.5. · To avoid digging or filling earth works in raining weather; · To plant trees or grass as required by the green design, immediately after the roadbed comes into form.
Construction party
2.3 Environmental impacts and mitigation measures during operation phase
The project operation will generate impacts to social, sound, air, water and
ecological environments. The environmental protection liabilities of implementation
party should be enclosed in the bidding document, to make sure the implementation
party has a full understanding about that. The environmental impacts and mitigations
during operation phase are listed in Table 2-3.
Table 2-3 Environmental impacts and mitigations during operation phase Category Impacts Mitigations Execution
agency Noise environment It is predicted that in the far
future the noise level in the day time exceeds the standard limit by 1.3�14.7dB; the noise level at night exceeds the standard limit by 4.9�20.6dB.
· To strengthen the road surface maintenance and keep the road surface flat and neatly. · To require the vehicles to observe the rule of speed limit and no bugle when running through sensitive sections. · To build noise screening walls(3.5m high and 500 m long) for the flyover, and install ventilation and noise separating windows for 60 households of Youzha village.
You-Xiao urban road service company
Ambient air It is predicted that in the far future, NO2 level within 40 m
· To specify driving speed in the plan in order to alleviate vehicle emission
Guiyang municipal
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
16
to the both sides of many road sections exceeds the class 2 standard limit.
pollution. · To forbid the passing-by of vehicles whose exhaust exceeds the standard limit; to reinforce the vehicle inspection and maintenance; to reduce the dust on the road surface; and to support and cooperate with local government in control of motor vehicle emission. · To arrange no new building of school, hospital or other sensitive objects within 40m to the both sides of the road.
government
Accidents of vehicles transporting dangerous substances will cause contamination to Yuliang River.
To set up a buffer tank with a capacity of 10 m3 at each end of the Yuliang River bridge.
Design agency Water environment
Drainage of bridge surface runoff will cause impacts to Yuliang River
To collect runoff(rain) from the bridge surface and then deliver to sewage interception ditch of Yuliang River
Design angecy
In the initial phase of operation, the leakage of tunnel walls will affect the growing of the plants on the tunnel top, or deduce the decrease or drying out of surrounding water supply.
To conduct periodic monitoring towards the tunnel, and adopt effective protection to treat such leakage.
You-Xiao urban road service company
Ecological environment
Reforestation and maintenance during the operation phase
· To plant trees and grass in the slope of the road side, and in the available area of occupied lands. · To recover and maintain the vegetations in the dumping ground and temporarily occupied lands.
You-Xiao urban road service company
Traffic administration
Traffic issue during operation phase
· To strengthen traffic administration, in order to provide a good driving condition; to periodically investigate vehicles’ noise and exhaust with random sampling, and cut the passing-by of ones whose emission exceeds the standard limit. · To conduct public propaganda and education.
You-Xiao urban road service company
Management and emergency response for accidental discharge
Accidental pollution discharge · To start up emergency response system Guiyang municipal government, and You-Xiao urban road service company
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
17
3 Environmental management and supervision
3.1 Frame structure of environmental management organ
6HH�)LJ�����IRU�IUDPH�VWUXFWXUH�RI�HQYLURQPHQWDO�PDQDJHPHQW�RUJDQ���
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�����
�
3.2 Purpose
For the purpose of protecting the environment along the road routine, and
effectively controlling and alleviating the negative impacts arising from this project
design, construction or operation, close and scientific tracking, normative environmental
management and monitoring should be performed throughout the whole process of this
project implementation.
Fig 3-1 Frame structure of environmental management organ
Management and execution organs Supervising organs
Transportation Bureau of Guiyang City
EIA agency
Operation company
Monitoring
department
Design agency Contractor
Design and construction phases
Local EPB
EPB of Guizhou province
Project management
Environmental protection sector
Operation phase
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
18
3.3 Environmental management
Individual organ should be established to take the task of environmental
management for each stage-- feasibility study, design, construction and operation, since
the environmental management has different implications for the four stages. For this
road reconstruction project, its environmental management and supervision plan is
shown in Table 3-1.
Table 3-1 Environmental management and supervision plan
Stage Supervisor Content of supervision Purpose of supervision Feasibility study stage
EPB of Guizhou province
1. To evaluate the EIA outline, 2. To evaluate the EIA report.
1. To ensure the EIA covers all the needed points, subjects are set properly, and key points are highlighted. 2. To ensure the EIA presents all the potential, significant environmental issues. 3. To ensure the environmental mitigations are accessible, and have practical implementation plan.
EPB of Guizhou province
1. To check whether the environmental protection funds has been put into the right place
1. To ensure the environmental protection funds are really injected.
2. To inspect the dumping and disposal of the solid waste from bridge and tunnel construction. 3. to inspect the discharge and treatment of life sewage from construction workers and waste oil from construction machines
2. To ensure the surface water is kept free from contamination. 3. To ensure the solid waste from the construction will not jam or contaminate the surface water.
4. To inspect the restoration and treatment of the earthwork taking and discarding ground.
4. To ensure the landscape and land resources along the routine are free from serious destruction, and get recovery.
5. To inspect whether the sites of material piling, asphalt and concrete mixing are located in appropriate places.
5. To ensure such sites meet the environmental protection requirements.
EPB of Guizhou province, and EPB of Guiyang city
6. To inspect the performance of dust and noise control, and determine the construction time.
6. To reduce the environmental impacts deriving from the construction activity, and act upon the requirements stated in corresponding environmental protection laws and regulations.
7. To inspect the implementation of the Three-At-The-Same-Time of the environmental protection facilities.
7. To ensure the Three-At-The-Same-Time has been put into practice.
Design and construction stage
EPB of Guizhou province
8. To inspect whether the environmental protection facilities can reach the standard requirements.
8. To test the environmental protection facilities.
Operation stage
EPB of Guizhou province
1. To inspect the implementation of monitoring plan 2. To identify whether further environmental protection measures are needed to be taken (when unpredicted environmental problems occur).
1. To ensure the monitoring plan has been executed. 2. To ensure the environmental protection measures have been taken.
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
19
EPB of Guizhou province, and EPB of Guiyang city
3. To inspect whether the environmental quality at the sensitive areas can meet the corresponding standard limits. 4. To inspect the dumping, delivering out, and landfill of the solid waste.
3. To strengthen the environmental management, and protect human health indeed.
3.3.1 Work scope of environmental management
The work scope of the environmental management in construction phase includes:
to draft out detailed environmental protection management method and plan,
especially to make and execute the plan of training on subjects of environmental
knowledge and environmental monitoring towards project contractor and environmental
protection supervisor.
to examine the construction sites periodically, supervise how far the
construction party has implemented the environmental protection management method,
and stop and correct any wrong construction behaviors at the first time.
� to investigate and handle any problems, for example, disturbance to people or
pollution arising from the construction period.
to submit the staged report of environmental management to local
administrative department who is in charge of environmental protection.
3.3.2Work scope of supervision
In order to have an effective control on pollution arising from construction
activities, the supervision in construction phase should not only cover the management
on construction quality and progress, and also should involve the inspection on
civilization level of the construction behavior, how far the environmental mitigations
have been executed, and the implementation status of articles specified in project
contract regarding environmental protection responsibilities.
the employer should enclose the articles of environmental protection measures
in the contract when awarding the overall contract. The construction party is required to
act such articles strictly and apply the rewards and penalties system.
the construction behavior of the construction party should be in compliance
with the requirements defined in the State or local government-made regulations,
contract articles, and EIA environmental protection suggestions. A civilized and
environmental-friendly construction will be highly appreciated.
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
20
the employer should consign qualified supervision agency to designate special
supervisor of environmental protection who will be responsible for supervising the
construction party to implement the environmental protection measures.
� the construction party should appoint full-time or part time personnel to be in
charge of environmental management, who will be present in the construction site to
manage the pollution source control. Especially for high noise and vibrating
construction machines, their operation time should be limited strictly.
� the construction party should be honest to publish the environmental impacts information. Constricted by technology and construction conditions, it is unavoidable
that construction activities will generate environmental pollution even with mitigations
taken. So the information release should be done towards the affected residents who live
along the routine, in order to obtain their understanding and support in advance, so that
the construction can go ahead without obstruction.
� the selection of new sites where are proposed to accept the relocated households
should be evaluated in terms of environmental impact assessment. Once the sites have
been identified, they should be planned scientifically, and equipped with a complete set
of utilities, to make sure the resettled group lead a good life.
� A complaint office should be established by the employer or the construction party. The complaint office should release a hot line to hear the public’ voice and once
receiving the complaint they should arrange special personnel to handle it within a
specified term.
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
21
4 Environmental monitoring plan
4.1 Purpose and base of making monitoring plan
The purpose of making a monitoring plan is: to supervise whether each
environmental protection program has been taken into practice; to provide realtime
monitoring results based on which to adjust environmental protection action; to provide
basis for drafting time schedule and implementation mode for environmental protection
program. Preparing of the monitoring plan is based on the predicted environmental
impacts in every phase (construction and operation phases).
4.2 Monitoring items
The environmental impacts are mainly brought out in construction and operation
phases. In construction phase, the dominating environmental pollutants are TSP and
construction noise; while in the operation phase, the dominating environmental
pollutants are traffic noise and NO2.
4.3 Environmental monitoring program
According to the engineering character of urban transportation project, the
environmental monitoring program is divided into two parts towards the construction
and operation phases respectively, as shown in Table 4-1.
Table 4-1 environmental monitoring program in construction and operation phases
Monitoring program (divided into two phases ) Category Item Construction phase Operation phase
Pollution source Flying dust from construction
activity Vehicle exhaust
Monitoring item TSP NO2 Environmental quality standard
Ambient air quality standard�GB3095-1996�
Ambient air quality standard�GB3095-1996�
Applied standard Pollutant
discharge standard
—
Limits and measurement methods for emissions from
light-duty vehicles (GB18352.1-2001)
Monitoring spot Boundary of the construction site, and sensitive spots nearby
Yuanlin road, and Xingzheng road
Monitoring frequency
Once per month for busy construction period; for each time, the sampling should be
done at morning and afternoon respectively.
Once in winter, and once in spring; for each time, the
sampling should last 1 or 2 days (continuous 24-hour monitoring)
Ambient air
Performed by Environmental monitoring station
of Guiyang city Environmental monitoring
station of Guiyang city
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
22
Supervised by
Pollution source Noise from construction
machines Traffic noise
Monitoring item LAeq(dB) LAeq(dB) Environmental quality standard
Standard of environmental noise of urban area�GB3096-93�
Standard of environmental noise of urban area�GB3096-93�
Pollutant discharege standard
Noise limits for Construction Site�GB12523-93�
— Applied standard
Measuring method
Measuring method of environmental noise of urban
area�GB/T14623-93�
Measuring method of environmental noise of urban
area�GB/T14623-93�
Monitoring spot Boundry of the construction
site and sensitive spots nearby
Hospital of Guizhou Steel Group, and Jinxiu jiayuan residential area
Monitoring frequency One day per month, twice per day
(at day time and at night)
Two times per year, two days per time (at day time and at night for
each sampling)
Performed by Environmental monitoring station
of Guiyang city
Environmental monitoring station of Guiyang city or a
monitoring station newly built Administrated by EPB of Guiyang city EPB of Guiyang city
Noise environment
Supervised by World Bank Office of Guiyang
city World Bank Office of Guiyang
city
Pollution source Wastewater from construction
activities
Monitoring item pH, NH3-N, CODcr, CODMn,
BOD5, petroleum, TP, coliform bacteria
pH, NH3-N, CODcr, CODMn, BOD5, petroleum, TP, coliform
bacteria
Environemtal quality standard
Environmental quality standard for surface water (GB3838-2002),Quality standard for
ground water�GB/T14848-93�
Environmental quality standard for surface water (GB3838-2002),Quality standard for
ground water�GB/T14848-93� Applied standard
Pollutant discharge standard
— —
Monitoring spot
Yuliang River at the water intake port of Party School of CPC Guiyang Municipal Committee
Yuliang River at the water intake port of Party School of CPC Guiyang Municipal Committee
Monitoring frequency Twice per month in construction
phase Twice per year
Performed by Environmental monitoring station
of Guiyang city Environmental monitoring
station of Guiyang city Administrated by EPB of Guiyang city EPB of Guiyang city
Water environment
Supervised by
Except the above compulsive monitoring program, the construction party should
train personnel to take the burden of routine monitoring, for example, to sense the flying
dust and judge them exceeding standard or not by eyesight; or to smell the vehicle
exhaust and tell them acceptable or not; and so forth for noise and other pollutants. By
doing so, problems can be shot and solved at the first time, and the environmental
impacts caused by the project can be minimized.
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
23
4.4 Procedure of monitoring
The employer should draft out the environmental monitoring procedure for
construction and operation phases, after referring to the project’s features, other’s
experiences on operation and management of same type of project, and requirements of
environmental management system ISO14004. The environmental monitoring
procedure should cover the following contents:
(1) to establish an environmental management organ with sufficient funds and
human resource allocated.
(2) to define environmental management system, monitoring program, personnel
training plan, and pollution mitigations for this project.
(3) to conduct training according to the above training plan, to make sure all the
workers own required environmental protection acknowledge and operation skills,
including pollution prevention and control skill.
(4) to assign works to individuals; to process daily affairs(including site
supervision) according to the plan, and execute environmental monitoring for this
proposed project.
(5) to build a fluent channel for information communication, especially to build an
effective response approach towards public’s complaints.
(6) to organize the corresponding monitoring agency to perform periodic
monitoring, and duly report the monitoring results to relevant departments in charge.
(7) to correct the articles which can not stop the re-occuring of some environmental
regulation violation or disturbance to civilians in both construction and operation
phases, and draft out prevention measures; if necessary, to amend relative management
method.
(8) to manage the important records, for example, monitoring report, civilian’s complaint, form
on requiring the responsible agency to treat the pollution within a specified term, and etc.
(9) the environmental management organ should conduct periodical supervision on
implementation progress, and prepare and submit the Environmental Monitoring Report
to relative administrative departments in charge, who will then give comments after
examining the monitoring report. The environmental management organ then should
amend the problem parts of the management procedure after considering such
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
24
comments and civilian’s complaints. With such effort, it is hopeful to achieve better
environmental management for this project.
4.5 Environmental monitoring report
�1�Environmental monitoring report in the construction phase
The construction work will last for 3 years, which can be divided into various
stages, such as demolition, pipes dismantlement, pipes migration, construction of
drainage works, construction of road works, install of traffic signs and road markings,
test and acceptance, and etc. According to requirements of Chinese management
policies and regulations towards construction projects, and stipulations of World Bank
business, the environmental monitoring agency should prepare the Staged Report of
Environmental Monitoring, which convinced the administrative department of
environmental protection that the environmental protection program has been taken into
practice, and that special measures will be taken soon in order to eliminate some other
predicted negative impacts. Staged monitoring report should be prepared twice per year
for construction phase.
Staged Environmental Monitoring Report should cover the following contents:
configuration of the environmental management organs, progress of the construction,
elements and method of construction, environmental impacts caused by construction
activity and relief measures, how the relief measures have been implemented, if
necessary, civilian’s complaints and addressing status should be included.
Aside from the staged monitoring report, daily report and monthly report are the
necessary materials to be prepared by the construction party. Such reports should be
submitted to superior departments in charge and local administrative departments of
environmental protection.
�2 Environmental monitoring report in the operation phase
When the project is put into operation, it is the duty of environmental monitoring
agency to prepare the Environmental Monitoring Report periodically (generally once
per year), which should include the following contents: configuration and changes of
environmental management organs, how the comments, which are issued by the
administrative department of environmental protection regarding the previous
monitoring reports, have been implemented, monitoring program (including monitoring
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
25
time, frequency, spot, instruments and equipments, applied standards, and etc), analysis
and result of monitoring data, proposed further pollution mitigations, and etc.
4.6 Monitoring cost
The monitoring cost at the first year of construction and operation phases
respectively is shown in the Table 4-2.
Table 4-2 monitoring cost in the construction and operation phases
(Unit: 10,000 Yuan per year)
Project Monitoring category
Ambient air
Noise Surface water
subtotal
In construction
phase 8.4 0.7 3 9.4
Road and transportation
In operation phase
3.6 1.2 - 4.8
Total 14.2
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
26
5 Training plan
Personnel training plays a big role in achieving fluent and effective project
implementation. The training should focus on environmental protection knowledge and
environment-friendly work skills towards the construction workers. In addition to
explaining the importance and implications of the project construction to all the
workers, the training will also take different forms and apply different courses towards
different groups who have been sorted out according to their posts. Generally the
training locations have two alternatives, in domestic and abroad. The detailed training
plan is shown in Table 5-1.
Table 5-1 training plan for environmental protection technicians
Personnel Training course Method Number of trained persons
Term(days) Cost (10,000 Yuan)
Technicians in charge of construction-related environmental protection
Basic theories about environmental protection, monitoring method, monitoring report compiling, and post training
Training in domestic
2 from each construction section
2 5
Regulations on environmental protection, construction plan, environmental monitoring guideline and specification
Training in domestic
1~2 persons from each construction section, 2~4 persons from the employer’s party
3 supervising engineers of environmental protection, environmental managers from employer’s party
Air monitoring and air pollution control technology, noise monitoring and noise pollution control technology
Training in domestic
6 4
5
Senior environmental managers, environmental engineers
International advanced technology on traffic environmental management, and noise control method
Training abroad
4 15 10
Total -- 24 20
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
27
6 Environmental protection investment�
On the base of environmental impact prediction and impact mitigation analysis, this chapter listed
the finance budget for each stage of project implementation, and provided a brief analysis regarding
this project’s environmental and economic benefits.
6.1 Environmental protection cost estimation�
Elements and cost of multiple-purpose environmental protection works are listed in
Table 6-1, and those of direct environmental protection works are listed in Table 6-2.
7DEOH�����Elements and cost of multiple-purpose environmental protection works�
No. Environmental protection
works
Elements Amount Cost (10,000
Yuan)
Remark
1 Reforestation Planting trees and grass 7.020km 166.92
2 Drainage works Sewage interception and drainage
ditches
7.020km 3400
3 Environmental sanitary
facilities
Garbage station 118 9.44
4 Land occupation Lands requisition 405Mu
5 Resettlement Demolishing and relocating
houses
27759m2
16334.4
Total 19910.76
Project feasibility
study
Table 6-2 Elements and cost of direct environmental protection works
No. Environmental
protection works Location Amount
Cost (10,000
Yuan) Remark
1 Life sewage treatment
facilities In construction site At 2 spots 120
2 Bridge surface drainage
collection
On bridge over Yuliang
River 1 set 50
3 Collection and disposal
of solid waste
Environmental sanitary
facilities At 118 spots 9.44
In order to protect
water environment
Noise screening walls 500m 500 In the flyover section
4 Noise insulation doors
and windows
For 60
households 170
Households belong to
Youzha village
Noise control
Green belt to separate
noise 550m 132
Total 981.44
Note: cost for water and soil preservation not included.
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
28
6.2 Environmental protection cost estimation for construction phase�
In the construction phase, the environmental protection cost estimation is listed in
Table 6-3.
7DEOH�����environmental protection cost estimation�
Category Environmental protection works Cost (10,000
Yuan)
1. to control construction time --
2. to locate the camp of construction works, material stockpile ground, mixing
sites and etc at least 100 m away from the environmental sensitive objects --
3. to deliberately select construction machines and maintain them carefully, and
adopt temporary fence to screen noise 50.0
Noise
environment
4. to offer health protection to machine operators and site supervisors 90.0
1. to build septic tank for the camp of construction workers, and to clear and
deliver out their garbage 15.0
2. to treat the construction wastewater 25.0
3. to prevent bridge construction contaminating the river (mud pit) 80.0
4. to stockpile construction materials in a way avoiding rain flushing 20.0
5. to clean the construction site 10.0
6. to control water and soil erosion 40.0
Water
environment
7. to migrate the water intake port at the bridge and lay pipes 200.0
1. to spray water in the construction site 10.0
2. to put the powder materials into package or cans prior to transportation, and put
up a tent to shield their dumps 15.0
3. to offer health protection for operators engaging in concrete and asphalt mixing
sites 20.0
4. to add the enclosure to the vehicles which transport soil, sand, and stones, in
order to prevent dropping off 15.0
Ambient air
5. to deliberately select the sites and equipments for concrete and asphalt mixing --
Environmental
management
1. to conduct environmental monitoring, management, and supervision in
construction phase 60.0
Training 1. to provide trainings for construction workers, supervisors of environmental
protection, project managers, and environmental protection engineers 20.0
Total 670
6.3 Environmental protection cost estimation for construction phase
In the operation phase, the environmental protection cost estimation is listed in Table 6-4.�
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
29
Table 6-4 environmental protection cost estimation
Category Elements of environmental protection
works
Annual cost
(10,000
Yuan/year)
Cost
(10,000
Yuan)
Execution agency
Routine management on environmental
protection (employees’ salary, office cost
and etc)
2.0 40
Cost for equipment operation, maintenance,
and depreciation 3.0 60
Cost for reforestation and maintenance 10.0 200
Management
on
environmental
protection
Cost for solid waste collection and
environmental sanitation 4.0 80
Environmental
monitoring
Cost for environmental monitoring in
operation phase 1.0 20
Personnel
training Cost for personnel training 1.0 20
Other
environmental
protection
works
Unpredicted additional cost for
environmental protection works 1.5 30
Total It is estimated that the project will operate
for 20 years(2010~2030) 22.5 450
Local road
management bureau
and environmental
protection bureau
6.4 Ratio of environmental protection investment to the total�
Through the above analysis, we draw the following conclusions regarding
environmental protection investment (multiple-purpose environmental protection works
and operation cost for the environmental protection works are not included):
(1) the investment for direct environmental protection works is 9,814,400 Yuan.
(2) in the construction phase, the investment for environmental protection works is
6,700,000 Yuan.
(3) in the operation phase, the investment for direct environmental protection works
and their management and operation is 6,700,000 Yuan.
The total investment for this project is 1,044,871,100 Yuan, of which the environmental protection
accounts for 21,014,400 Yuan, that is 2.01% of the total.
World Bank Financed Guiyang Traffic Project EMP Sub-project 1 Youxiao Road Project
30