environmental compliance monitoring report€¦ · damar - arunathakur 13.011 badbhanjyang -...
TRANSCRIPT
Environmental Compliance Monitoring Report
Semi-Annual Report No. 1
Loan Number: 3620 NEP Project Number: 48218-003 December 2018
Nepal: Rural Connectivity Improvement Project
Prepared by the Government of Nepal for the Asian Development Bank.
This Environmental Compliance Monitoring Report is a document of the borrower. The views expressed
herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be
preliminary in nature. Your attention is directed to the “terms of use” section of this website.
In preparing any country program or strategy, financing any project, or by making any designation of or
reference to a particular territory or geographic area in this document, the Asian Development Bank does
not intend to make any judgments as to the legal or other status of any territory or area.
Rural Connectivity Improvement Project 2
Abbreviations ADB – Asian Development Bank
AP – Affected People
CC – Construction Contractor
CDO – Chief District Officer
CSC Construction Supervision Consultant
CTEVT – Council for Technical Education and Vocational Training
DBST – Double Bituminous Surface Treatment
DFO – District Forest Office
DOF Department of Forest
DOLIDAR – Department of Local Infrastructure Development and Agricultural Roads
EA – Executing Agency
EMP – Environmental Management Plan
EMoP Environmental Monitoring Plan
ES Environment Specialist
ESMP Environmental and Social Management Plan
GESI – Gender Equality and Social Inclusion
GoN – Government of Nepal
GRM – grievance redress mechanism
Ha – Hector
IA Implementing Agency
IEE – initial environmental examination
IUCN – International Union for Conservation of Nature
KM – Kilometer
kV – Kilovolt
M – Meter
Masl – meter above sea level
MOFE – Ministry of Forest and Environment
MoFAGA – Ministry of Federal Affair and General Administration
MOFALD – Ministry of Federal Affair and Local Development
NCB – National Competitive Bidding
NEA – Nepal Electricity Authority
NRS – Nepal Road Standard
PCU Project Coordination Unit
PIU – Project Implementation Unit
RCC – Reinforced cement concrete
RCIP – Rural Connectivity Improvement Project
Rural Connectivity Improvement Project 3
TABLE OF CONTENTS
1. INTRODUCTION ........................................................................................................... 5
2. Brief Project Description ............................................................................................. 5
3 COMPLIANCE TO NATIONAL REGULATIONS .......................................................... 12
3.1 Environmental Protection Rules 1997 ................................................................... 12
4 COMPLIANCE TO ENVIRONMENTAL COVENANTS FROM THE ADB LOAN AGREEMENT ..................................................................................................................... 12
a. Schedule 5 Environment .......................................................................................... 12
5. COMPLIANCE TO ENVIRONMENTAL MANAGEMENT PLAN ................................... 13
5.1 Institutional Arrangement for Safeguards Implementation ..................................... 13
5.2 Clearance for Major Construction Work ................................................................ 14
6. SAFEGUARD MONITORING RESULTS AND UNANTICIPATED IMPACTS ............... 14
6.1 Pre- construction Activities ........................................................................................ 14
6.1.1 Baseline Monitoring ............................................................................................. 14
6.1.2 Compliance Monitoring .................................................................................. 20
7. PLEMENTATION OF GRIEVANCE REDRESS MECHANISM AND COMPLAINTS RECEIVED FROM STAKEHOLDERS ................................................................................ 21
7.1 Establishment of GRM ............................................................................................... 21
8. OTHERS ACTIVITIES ..................................................................................................... 21
9. CONCLUSION ................................................................................................................ 21
List of Figure Figure 1: Location Map of RCIP Districts and Roads 5 List of Table Table 1: List of Roads 6 Table 2: District/ Package wise contract Agreement date and Commencement date and 10
Completion date Table 3: Compliance Status with Environmental Loan Covenants 11 Table 4: Status of Forest Clearance/Tree Cutting 15 Table 5: WHO Ambient Air Quality Guidelines 17 Table 6: Status of Existing Road Condition 18
Status of Existing Road Condition Appendices Appendix I: Compliance to Environmental Management Plan Appendix II: Environmental Monitoring Plan
Rural Connectivity Improvement Project 4
Appendix III : Environmental Safeguard Compliance Matrix Appendix IV: Air and Water Quality Monitoring Locations Appendix V : Photographs of Progress Activities Appendix VI: Issued letters related to Environmental Management AppendixVII: Sample Contractor’s Environmental Management Plan
Rural Connectivity Improvement Project 5
1. INTRODUCTION 1. The Rural Connectivity Improvement Project (RCIP) will construct about 380.6 kilometers of rural roads to all-weather standard covering 16 priority rural development districts throughout the country. The project will also focus on improving institutional arrangements, business processes, and associated capacity building, particularly on road asset management and road safety. The Project aims to improve transport efficiency of the rural road network, which will contribute to expansion of economic opportunities and poverty reduction. This will be realized by: (i) improving the district road network, (ii) facilitating safe and appropriate road usage, (iii) increasing efficiency of transport services and (iv) enhancingDOLIDAR capacity for road asset development and management. Project immediate outcomes will be improved accessibility to social services and markets, increased fuel efficiency, reduced travel time, accidents, vehicle emissions and better employment opportunities outside agriculture, both through improved access to economic centers and increased industrial activities in the project districts. The Project is funded by Asian Development Bank (ADB).
2. Brief Project Description 2. Under the project there are 27 road subprojects. The total length of the road is 380.686 km and these roads are located in 16 districts. Jhapa, Ilam, Panchthar, Morang, Sunsari, Dhankuta (Eastern Cluster 13 Roads); Dolakha, Kavre, Sindhuli, Sindhupalchowk, Kathmandu, Bhaktapur (Central/ East Cluster: 7 Roads), Chitawan (Central/ West Clusters: 1 Road); Parbat (Central/ West Cluster: 2 Roads); Rukum (West Cluster: 2 Roads) and Rolpa (West Cluster: 2 Roads). These roads are in 11 packages (or 11 NCB contracts). The civil work contracts are being awarded to contractors by PCU in various dates. Until June, 7 NCB contracts have been materialized. Remaining 4 is expected to be awarded in September 2018. The construction period of each of the contracts is 2 years with additional 3 years of maintenance 1 year DLP of the constructed road and 2 years for PBM. The Project started on April, 2018.
3. The RCIP is being financed by the Asian Development Bank. MoFAGA through
DoLIDAR is responsible for implementation of this Project. DoLIDAR is the executing
agency and the Project Coordination Unit (PCU) headed by Project Coordinator under
DoLIDAR is the central office for overall project management, contract administration and
implementation through its regional PIUs headed by the PMs established at Jhapa (PIU1),
Lalitpur (PIU2), Parbat (PIU3), Rolpa (PIU4) and Rukum (PIU5) and with support of the
Consultant, CSC.
4. RCIP, PCU has appointed Yooshin Engineering Corporation, Korea in Association
with Environment & Resource Management Consultant (P) Ltd, Nepal &BDA, Nepal (P) Ltd,
Nepal as a Construction Supervision Consultant for all contract packages.
The target of the Project is to improve the existing grave/earthen rural road to asphalt paved
road with gravel shoulder on either sides. The Project work mainly comprises of 30 mm of
Asphalt pavement, 150 mm of crushed stone base course, 200 mm of granular sub base
course and 350 mm gravel on either side of shoulder. The construction work also includes
cross drainage, side drain, masonry and gabion structure, bio-engineering, traffic safety
works and maintenance work on Performance Based Maintenance.
Rural Connectivity Improvement Project 6
Figure1: Location Map of RCIP Districts and Roads
Table 1: List of Roads
A. Eastern Cluster (Province 1)
Package & Civil Contract
(NCB) No. Road Section
Length of Road Section (km)
District
Under PIU1:
Package No. 1 (NCB - 01)
Amaldagi - Samayaghad -Babwari - Solmari road
11.509
Jhapa
Charpane - Chaitubari-Matigada-Sadhukuti - Khodamara-Rajgadh
15.484
Kharsangwari - Jalthal -Mangalware - Baundoka -AdhikariChowkSadak
6.519
Padajungi (Lakhanpur) -Guhawari-Laladhbandra - Jharka-BaluwathanChapramari -Khajurgachhi
10.003
Total Length (Km) 43.515
Under PIU1:
Package No. 2 (NCB - 05)
Nepaltar-Shantidada - Gagrebhangyang - MangalbareDhuseni - Gajrmukhi - Ebhang -ChaturmoadAadipur - Larmwa-GhartiDobhan - Chapeti - BeldagiDamak Road (Ebhang -Chature road Sector)
13.279 Ilam
Mangalbare - Phungfung - EktappaSikariBhanjyang - Phakphok - Ra.Ma.Bi. KhambangChowk - Thingepur - Aamchok - Jungetar - Phuyatappa - Rabi road (Surubindukhanda)
9.510
Rural Connectivity Improvement Project 7
Package & Civil Contract
(NCB) No. Road Section
Length of Road Section (km)
District
Total Length (Km) 22.789
Under PIU1:
Package No. 3 (NCB - 02)
Phidim - Nagin - Sidin -Prangbung - Falot Road (Phidim -Ludintar Road)
24.46 Panchthar
Samdin - Chokmangu - Nawamidada - FaktepGhurbisepanchami Road (Samdin - Nawamidada Sector)
14.847
Total Length (Km) 39.307
Under PIU1: Package No. 4
(NCB - 06)
Khorshane - Kerawari -Singhadevi Road (23 km left to be upgraded out of 38 km) 13.615
Morang Laxmimarga - Dangihat - Banaul- Babiyabirta -
Amahi Road (29 km left to be upgraded out of 31 km)
28.135
Total Length (Km) 41.75
Under PIU1: Package No. 5
(NCB - 03)
Jhumka - Shinghiya - Ramdhuni - Prakashpur - Madhuwan - Shukrabare - Paschimkushaha - Laukahi - Boarder Road
17.35 Sunsari
Inaruwa - Satterjhoda - Chhitaha - Purbakushaha - Biratnagar Road
12.787
Mudheshanischare - Dadagaun - Chanuwa Road
10.342 Dhankuta
Total Length (Km) 40.479
B. Central/ East Cluster (Province 3)
Package No. Road Section Length of Road
Section (km) District
Under PIU2: Package No. 6
(NCB – 07)
Nayapul – Pawati – Dadakharka Road 12.083 Dolakha
Barhabise – Maneswara – Ghumthang – Listi – Bhairabkunda
12.377 Sindhupalchowk
Dolalghat – Phalate – KolatiDhadkharka- Pokharichauri - Gurase Road
18.629 Kavre
Total Length (Km) 43.089
Under PIU2: Package No. 7
(NCB - 08)
Tallo - Ranibas - Harshadi - Tadi - Dhanshari 12.776
Sindhuli Dhudhuli - Lakhima - RatmataKartha - Thakur Damar - Arunathakur
13.011
Badbhanjyang - Sanomasino - Thulomasino - Satghumti Road
6.403 Kathmandu
From Bansbari–BagesworiPurano Health Post to MUNICIPALITY Building
4.461 Bhaktapur
Total Length (Km) 36.651
Rural Connectivity Improvement Project 8
C. Central /West Cluster (Province 3 & 4)
Package No. Road Section Length of Road
Section (km) District
Under PIU2: Package No. 8
(NCB - 09)
Phisling - Tolang - Baspur - Oralang - Mayatar - Tarse - Upradanggadi - Shaktikhor bazar Road
37.566 Chitwan
Total Length (Km) 37.566
Under PIU3: Package No. 9
(NCB - 10)
Lunkhu - Mudikuwa Road 13.003
Parbat Armadi - Banau Road
12.801
Total Length (Km) 25.804
D. Western Cluster (Province 5)
Package No. Road Section Length of Road
Section (km) District
Under PIU4: Package No. 10
(NCB - 04)
Mijhing -Ruinibang -Badachaur - Ghumchaal - Harjang-Syuri-Gaam Road 13.697
Rolpa
Mijhing - Dhulewodaar - Namjaa - Sirp - Pang Road 5.966
Total Length (Km) 19.693
Under PIU5: Package No. 11
(NCB -011)
SitalPokhari - Jhulkhet-Chunwang Road 18.417
Rukum Solawang - Raule - BaluwaNaigadpul - Jamaabagar - Simalchaur - Hukaam - Ranmamaikot Road's (Naigadpul - Jamabagar Sector)
11.626
Total Length (Km) 30.043
2.1. Contract Status
5. Package DoLIDAR/RCIP/NCB-O1/2074/075: This contract falls under the purview of Project Implementation Unit 01. The Office of PIU-01 has been established at Damak, Jhapa, Province no. 01. Similarly the Consultant site office is also established at Damak, Jhapa. Works for this contract consists of improving of 4 roads located at different locations of Jhapa district with 5.00 m carriageway and 0.875 m wide shoulders on either side of road.The Contractor has established site camps and material testing laboratory. The survey work of all roads has been completed and design drawing work of roads are being carried out. 6. Package DoLIDAR/RCIP/NCB-O2/2074/075: This contract falls under the purview of Project Implementation Unit 01. The Office of PIU-01 located atDamak, Jhapa, Province no. 01.The Consultant has established site office at Phidim. Works for this contract consists of improving of 2 roads located at different locations of Panchtar district with 3.75 m carriageway and 0.75 m wide shoulders on either side of road.The Contractor has established site camps and material testing laboratory. The survey and drawing work of roads have been completed. The Engineer has forwarded with his recommendation the submitted drawing for approval from the Project Manager. 7. Package DoLIDAR/RCIP/NCB-O3/2074/075:
Rural Connectivity Improvement Project 9
This contract falls under the purview of Project Implementation Unit 01. The Office of PIU-01 located at Damak, Jhapa, Province no. 01. The Consultant has established his site office at Itahari. Works for this contract consists of improving of 3 roads located at Morang and Dhankuta districts. Out of 3 roads, 2 roads located at different location of Morang district with 5.00 m carriageway and 0.875 m wide shoulders on either side of road. Remaining 1 road located in Dhankuta district with 3.75 m carriageway and 0.75 m shoulder on both sides of road. Both roads under this package lies in Province 1.The Contractor has established site camps and material testing laboratory.The survey work of roads have been completed and design-drawing being carried out. 8. Package DoLIDAR/RCIP/NCB-O5/2074/075: Contract not awarded yet. Proposal under evaluation. 9. Package DoLIDAR/RCIP/NCB-O6/2074/075: Contract not awarded yet. Proposal under evaluation.
10. Package DoLIDAR/RCIP/NCB-O7/2074/075: This contract falls under the purview of Project Implementation Unit 02. The Office of PIU-02 located at Sanepa,Lalitpur, Province no. 03 and the Consultant's site office located at Dolalghat. Works for this contract consists of improving of 3 roads located at 3 different districts, namely Dolakha, Sindupalchowk and Kavre. Roads comprise of 3.75 m carriageway and 0.75 m wide shoulders on either side of road.The Contractor has established site camps and material testing laboratory.The survey work of roads have been completed and design-drawing being carried out. 11. Package DoLIDAR/RCIP/NCB-O8/2074/075 Contract not awarded yet. Proposal under evaluation. 12. Package DoLIDAR/RCIP/NCB-O9/2074/075: Contract not awarded yet. Proposal under evaluation. 13. Package DoLIDAR/RCIP/NCB-10/2074/075: This contract falls under the purview of Project Implementation Unit 03. The Office of PIU-03 located at Kusma, Parbat, Province no. 04 and the Consultant's site office also located at Pardabat. Works for this contract consists of improving of 2 roads located at different locations of parbat district with 3.75 m carriageway and 0.75 m wide shoulders on either side of road.The Contractor has established site camps and material testing laboratory. He has also submitted the Insurance policy and received the Mobilization Advance. The survey work of both roads has been completed. The Contractor has submitted the design-drawing of Lunkhu-Mudikuwa road to the Engineer and it is under process of verification. The design work of Armadi-Banau roads is being carried out by the Contractor. 14. Package DoLIDAR/RCIP/NCB-O4/2074/075: This contract falls under the purview of Project Implementation Unit 04. The Office of PIU-04 located atMijhing, Rolpa, Province no. 05 and the Consultant's site office located at Mijhing. Works for this contract consists of improving of 2 roads located at different locations of Rolpa district with 3.75 m carriageway and 0.75 m wide shoulders on either side of road.The
Rural Connectivity Improvement Project 10
Contractor has established site camps and material testing laboratory. The survey work of roads have been completed and design-drawing being carried out. 15. Package DoLIDAR/RCIP/NCB-11/2074/075: This contract falls under the purview of Project Implementation Unit 05. The Office of PIU-05 located at Rukum, Province no. 05 and the Consultant has not been established yet his site office. Works for this contract consists of improving of 2 roads located at different locations of Rukum district. Roads comprise of 3.75 m carriageway and 0.75 m wide shoulders on either side of road. The Contractor has established site camps and material testing laboratory. The survey work of roads have been completed and design-drawing being carried out.
Rural Connectivity Improvement Project 11
Table 2: District/ Package Wise Contract Agreement Date and Commencement Date and Completion Date
Province
(PIU)
District Contract No. Contractor
Name
Length (Km)
Agreement Date
Commencement Date
Original Contract
Amount (with VAT &PS)
1
(1)
Jhapa DoLIDAR/RCIP/NCB-
01/2074/075 M/S ZCGIEC – Ashish – Prera JV
43.515 30 March, 2018
20 April, 2018 679,379,995.74
Panchthar DoLIDAR/RCIP/NCB-02/2074/075
M/S Swachhanda – Kankai JV
39.307 30 March,
2018 20 April, 2018 928,335,587.20
Sunsari DoLIDAR/RCIP/NCB-03/2074/075
M/S JJECCL – Pappu JV
40.479 30 March,
2018 20 April, 2018 883,252,953.16
Illam DoLIDAR/RCIP/NCB-05/2074/075
NA 22.789
Morang DoLIDAR/RCIP/NCB-06/2074/075
NA 41.750
3
(2)
Dolakha Sindupalchowk Kavre
DoLIDAR/RCIP/NCB-07/2074/075
M/S AIPL – NANC JV
43.089 31 May, 2018 21 June, 2018 1,072,017,561.96
Sindhuli Kathmandu
DoLIDAR/RCIP/NCB-08/2074/075
NA 36.651
Chitwan DoLIDAR/RCIP/NCB-09/2074/075
NA 37.566
4 (3)
Parbat DoLIDAR/RCIP/NCB-10/2074/075
M/STundi Construction
25.804 13 June,
2018 03 July, 2018 616988089.78
5 (4)
Rolpa DoLIDAR/RCIP/NCB-04/2074/075
M/S JJECCL – Pappu – Koshi&Neupane JV
19.693 30 March,
2018 20 April, 2018 442,304,593.28
5 (5)
Rukum DoLIDAR/RCIP/NCB-11/2074/075
M/S PH – SMNS JV
30.043 31 May, 2018 21 June, 2018 898,040,323.16
Rural Connectivity Improvement Project 12
3 COMPLIANCE TO NATIONAL REGULATIONS
3.1 Environmental Protection Rules 1997 16. As per Environmental Protection Act and Rules 1997 of Nepal, Environmental Initial Environmental Examination (IEE) is required rural road. IEEs of all 27 roads were approved. 17. According the ADB Safeguard Policy Statement, the project is classified as category B with respect to environment.
4 COMPLIANCE TO ENVIRONMENTAL COVENANTS FROM THE ADB LOAN AGREEMENT
18. There are loan covenants specified for this project. Environmental safeguard related project activities are in compliance with covenants as regular follow up actions are being taken. The following covenants to the financing agreement with ADB are to be complied during implementation of the project.
a. Schedule 5 Environment
Table 3: Compliance Status with Environmental Loan Covenants
Reference in
Financing Agreement
Covenant Status of Compliance
Schedule 4 Para 7. The Borrower shall not award any works contracts until MOFALD has: (a) approved the IEE, and (b) Incorporated the relevant provisions from the EMP into the Works contract.
Complied with /Being complied with. All 27 road’s IEE approved.
Schedule 5 Para 6. The Borrower shall ensure, or cause DOLIDAR to ensure, that the preparation, design, construction, implementation, operation and decommissioning of the Project and all project facilities comply with (a) all applicable laws and regulations of the Borrower relating to environment, health and safety; (b) the Environmental Safeguards; and (c) all measures and requirements set forth in the IEE, the EMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.
Complied/being complied with. Will be followed.
Schedule 5
Para 11. Safeguards-Related Provisions in Bidding Documents and Works Contracts The Borrower shall ensure or cause DoLIDAR to ensure thatall bidding documents and contracts for Works contain provisions that require contractors to. (a) Comply with the measures relevant to the contactor set forth in the IEE, and the EMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report; (b) Make available a budget for all such environmental and social measures;
(a) Being part of the documents, the Contractors are being complying the measures during the course of construction. (b) It is made available for compliance of environmental
Rural Connectivity Improvement Project 13
Reference in
Financing Agreement
Covenant Status of Compliance
(c) Provide the Borrower with a written notice of any unanticipated environmental, resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, or the EMP; (d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and (e) Reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction.
social measures. (c) Not applicable at present (d) Being recorded as required. (e) It is very early to assess as the construction work is going very slowly not smoothly
Schedule 5
12. Safeguards Monitoring and Reporting The Borrower shall do the following or cause DoLIDAR to do the following: (a) Submit semi-annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to affected persons promptly upon submission; (b) If any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in the IEE, or the EMP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and (c) Report any actual or potential breach of compliance with the measures and requirements set forth in the EMP promptly after becoming aware of the breach.
a) Regularly will be submitted semi- annual Safeguards Monitoring Reports to ADB. b) All the considerations have been made. If arise, it shall be accordingly worked out. c) Not required at present
5. COMPLIANCE TO ENVIRONMENTAL MANAGEMENT PLAN 19. Most of the environmental safeguards related activities have not been undertaken yet. Updated environmental management plan is presented in the Appendix-I.
5.1 Institutional Arrangement for Safeguards Implementation 20 - Ministry of Federal Affairs and General Administration (MoFAGA) will be the Executing Agency (EA) and DOLIDAR will be the Implementing Agency (IA) for the project. 21 - Implementation arrangements for environment safeguards. The responsibilities of various agencies and parties for implementing environment safeguards are provided below. 22 -Project Coordination Unit: The PCU is the project management unit and responsible for the overall compliance with ADB’sSPS and the applicable laws and rules under the Ministry of Forest and Environment. The PCU will have an environmental consultant (PCU-ES) to coordinate with the PIUs and ensure project implementation complies with the PAM and EMP.
Rural Connectivity Improvement Project 14
23 - Project Implementation Unit (PIU): The PIUs through the Executing Engineer will be responsible for supervising implementation of the EMP and environmental monitoring plan (EMoP) by the contractor. 24 - Construction Supervision Consultant: Environment Specialist (CSC-ES). The main responsibility of the CSC-ES is to support the PCU and PIU and ensure that the construction works are in accordance with the environmental management plan and other environment-related stipulations of the construction contract documents. 25 - Contractor: The Contractor is the principal agent to implement the EMP and EMoP during the pre-construction and construction stages. 26 - The PCU will be the key institution for the successful implementation of the project and ensure compliance to ADB safeguards as contemplated in the environmental management and monitoring plans. The PCU will provide both technical advisory and independent audit roles to the Project to ensure the project stays in compliance. The CSC Environmental Specialist and the PCU Environmental Consultant will monitor environmental management plans (EMP) to be implemented by the contractors.
27 - Currently, RCIP/PIU has Sociologist, CSC has Environmental Specialist and Social Specialist.
5.2 Clearance for Major Construction Work
28 RCIP has been following-up with the concerned government agencies to provide clearance before start major construction work. Progress of forest area clearance for all 27 roads is given in Table 4.
6. SAFEGUARD MONITORING RESULTS AND UNANTICIPATED IMPACTS
6.1 Pre- construction Activities
29 Based on IEE and EMP of project, the environmental monitoring plan has been developed. The detailed monitoring plan according to the EMPis given in Appendix-II. The baseline and compliance monitoring progress noticed during the reporting period are:
6.1.1 Baseline Monitoring 30 - Verification and Approval of Forest area and Tree Cutting: Out of 27 roads, 7 roads do not require tree clearance. Trees cutting of 1 road had been approved by the Ministry of Forest and Environment. Verification of required number of trees cutting of 8 roads has been completed by District Forest Office (DFO) and report submitted to Department of Forest (DoF) and trees cutting for remaining 11 roads are to be verified and submitted to the DOF. The detail is given in Table 4.
Rural Connectivity Improvement Project 15
Table 4: Status of Forest Clearance/Tree Cutting
S.No
. Road Name District IEE
Approval
Forest Clearance/ Tree cutting
Request
Letter from MoFAGA to MoFE
Verification by of DFO
Approval From MoFE
Notify DFO
1
Padajungi (Lakhanpur)-
Guhawari-
Laladhbandra-Jharka-
Baluwathan-
Chapramari-
Khajurgachhi
Jhapa
Approved Not
Required
2
Charpane-Chaitubari-
Matigada-Sadhukuti-
Khodamara-Rajgadh
Approved Required Done
Done Letter sent to DoF with verification report of
DFO
3
Amaldagi -
Samayaghad -Baswari -
Solmari road Approved Not
Required
4
Kharsangwari-Jalthal-
Mangalware-
Baundoka-
AdhikariChowkSadak Approved Not
Required
5
Nepaltar - Shantidada -
Gagrebhangyang -
Mangalbare - Dhuseni -
Gajurmukhi - Ebhang -
ChaturemoadAadipur -
Larumwa -
GhartiDobhan - Chapeti
- BeldagiDamak Road
(Ebhang -
Chaturemoad Sector) Ilam Approved Required Done
Done
Letter sent to DoF with verification report of
DFO
6
Mangalbare - Pungfung
-
EktappaSikariBhanjyan
g- Phakphok - Ra.ma.bi.
KhambangChowk -
Thingepur - Aamchok -
Jungetar - Phuyatappa -
Rabi road
(Surubindukhanda) Approved Not
Required
7
Phidim-Nagin - Sidin -
Prangbung - Falot Road
(Phidim - Ludintar
Sector )
Panchthar
Approved Required Done Done
Letter sent to DoF with verification report of
DFO
8
Samdin - Chokmangu -
Nawamidada -
FaktepGhurbisepancha
mi Road (Samdin -
Nawamidada Sector) Approved Required Done Done
Letter sent to DoF with verification report of
DFO
9
Khorshane - Kerawari -
Singhadevi Road (23
km left to be upgraded
out of 38 km)
Morang
Approved Required Done
verification
report awaited
Rural Connectivity Improvement Project 16
10
Laxmimarga - Dangihat
- Banaul- Babiyabirta -
Amahi Road (29 km left
to be upgraded out of
31 km) Approved Not
Required
11
Inaruwa - Satterjhoda -
Chhitaha -
Purbakushaha -
Biratnagar Road
Sunsari
Approved Not
Required
12
Jhumka - Shinghiya -
Ramdhuni - Prakashpur
- Madhuwan -
Shukrabare -
Paschimkushaha -
Laukahi - Boarder Road Approved Required Done
verification
report awaited
13
Mudheshanischare -
Dadagaun - Chanuwa
Road Dhankutta Approved Required Done
verification
report awaited
14
Nayapul - Pawati -
Dadakharka Road
Dolakha Approved
Required Done Done Approved by MoFE
15
Barhabise - Maneswara
- Ghumthang - Listi -
Bhairabkunda Sindhupalchok
Approved
Required Done
Done Letter sent to DoF with verification report of
DFO
16
Dolalghat - Phalate -
Kolati -Dhadkharka-
Pokharichauri - Gurase
Road
Kavre
Approved
Required Done
Completed
No need
additional tree
cutting
17
Tallo - Ranibas -
Harshadi - Tadi -
Dhanshari
Sindhuli
Approved
Required Done
verification
report awaited
18
Dhudhuli - Lakhima -
RatmataKartha -
Thakur Damar -
Arunathakur
Approved
Required Done
verification
report awaited
19
Badbhanjyang -
Sanomasino -
Thulomasino -
Satghumti Road
Kathman
du
Approved
Required Done
verification
completed
No need
additional tree
cutting
20
Bansbari-
BagesworiPurano
Health Post to
MUNICIPALITY/RURAL
MUNICIPALITY Building Bhaktap
ur
Approved
Not Required
21
Phisling - Tolang -
Baspur - Oralang -
Mayatar - Tarse -
Upradanggadi -
Shaktikhor bazar Road Chitwan
Approved
Required Done
verification
completed,
report awaited
Letter sent to DoF with verification report of
DFO
22
Lunkhu- Mudikuwa
Road
Parbat
Approved
Required Done
verification
completed
Letter sent to DoF with verification report of
DFO
Rural Connectivity Improvement Project 17
23
Armadi- Banau Road Approved
Required Done
verification
completed
Letter sent to DoF with verification report of
DFO
24
SolawangRauleBaluwa
NaigadpulJamaabagarSi
malchaurHukaamRanm
amaikot Road's
(Naigadpul-Jamabagar
Sector)
Rukum
Approved Required Done
verificatireport
awaited
25
SitalPokhari- Jhulkhet-
Chunwang Road Approved Required Done
verificati report
awaited
26
Mijhing-Ruinibang-
Badachaur-Gumchal-
Harjang-Syuri-Gaam
Road
Rolpa Approved Required Done
verification
completed,
report awaited
27
Mijhing-Dhulewodaar-
Namjaa-Sirp-Pang Road
Approved Required Done
verification
completed,
report awaited
31 -Air and Noise: Ambient air measurements are require to be recorded before, during and after construction work. Sampling locations are proposed at Major Settlement/School/Health Center. The parameters like total suspended particles (TSP), Particulate Matter (PM 10), Sulfur dioxide (SO2), Nitrogen Dioxide (NO2), Carbon monoxide (CO) will be measured. Results will be analyzed by comparing with Nepal standard and ADB SPS 2009 (Pollution Prevention and Abatement Para 33), the project should comply to the more stringent standards between the country’s regulations and World Bank Group’s Environment, Health and Safety Guidelines. The standard is given in Table 5. Table 5: WHO Ambient Air Quality Guidelines
Parameters Time Time Weighted
Average
Concentration
max (µg/m3)
WHO
Guidelines
(µg/m3)
TSP Annual - -
24 hours 230 120-230
PM10 Annual - -
24 hours 120 70
SOx Annual 50 -
24 hours 70 125
NOx Annual 40
24-hours 80 150
CO 8 -hours 10,000 100000
Rural Connectivity Improvement Project 18
Source: World Bank Group’s Environment, Health and Safety Guidelines Environmental, Health, and Safety Guidelines (GENERAL EHS GUIDELINES: ENVIRONMENTAL AIR EMISSIONS AND AMBIENT AIR QUALITY), 2007. 32 - Water Quality: River water of the major river of the Project has been sampled for baseline monitoring and analysis. The parameters like PH, Total Suspended Solids (TSS), and Oil will be measured. Results will be analyzed by comparing with Nepal standard and ADB SPS 2009 (Pollution Prevention and Abatement Para 33), the project should comply to the more stringent standards between the country’s regulations and World Bank Group’s Environment,
Health and Safety Guidelines. 33 As per World Bank Group’s Environment, Health and Safety Guidelines Environmental, Health, and Safety Guidelines indicative Values for Treated Sanitary Sewage Discharges: pH pH 6 – 9, BOD mg/l 30, COD mg/l 125, Total nitrogen mg/l 10, Total phosphorus mg/l 2, Oil and grease mg/l 10, Total suspended solids mg/l 50, Total coliform bacteria MPNb / 100 ml 400. 34 - Existing Road Condition and Land Use:
Table 6: Status of Existing Road Condition
S.No Road Name District Existing Road
Condition Land Use
1
Padajungi (Lakhanpur)-
Guhawari-Laladhbandra-
Jharka-Baluwathan-
Chapramari-Khajurgachhi
Jhapa
The road alignment is existing earthen
track
Most of the lands have been used for cultivation, which is followed by
settlement.
2
Charpane-Chaitubari-
Matigada-Sadhukuti-
Khodamara-Rajgadh The road alignment is existing earthen
track
The current land use in the project road is agricultural land, small market
area, forest and settlements alongside the road
3
Amaldagi - Samayaghad -
Baswari - Solmari road
The road alignment is existing earthen
track Mainly land use in the project site is
cultivated land, settlement
4
Kharsangwari-Jalthal-
Mangalware-Baundoka-
AdhikariChowkSadak
The road alignment is existing earthen
track
The current land use in the project site is forestland (8%), cultivated land
(78%), settlement (12%) and other (2%).
5
Nepaltar - Shantidada -
Gagrebhangyang -
Mangalbare - Dhuseni -
Gajurmukhi - Ebhang -
ChaturemoadAadipur -
Larumwa - GhartiDobhan -
Chapeti - BeldagiDamak
Road (Ebhang -
Chaturemoad Sector) Ilam
The road alignment is existing earthen
track of about 3.5 m width
The alignment passes through Agricultural land, forest and Shrub
land with some scattered barren land, crossing streams at 3+855, 4+236, 4+482, 4+553, 4+657 and 5+ 143
6
Mangalbare - Pungfung -
EktappaSikariBhanjyang-
Phakphok - Ra.ma.bi.
KhambangChowk -
Thingepur - Aamchok -
Jungetar - Phuyatappa - Rabi
road (Surubindukhanda)
The road alignment is existing earthen
track
The current land use in the project site is forestland (8%), cultivated land
(78%), settlement (12%) and other (2%)
Rural Connectivity Improvement Project 19
7
Phidim-Nagin - Sidin -
Prangbung - Falot Road
(Phidim - Ludintar Sector )
Panchthar
The road alignment is existing earthen
track of about 3.5 m width
Mainly hilly with few stretches rolling/hilly. Land use mainly
agricultural.
8
Samdin - Chokmangu -
Nawamidada -
FaktepGhurbisepanchami
Road (Samdin -
Nawamidada Sector)
The road alignment is existing earthen
track of about 3.5 m width
The alignment passes through forests, and cultivated land, crossing
streams (Khola/Kholsi) at several locations.
9
Khorshane - Kerawari -
Singhadevi Road (23 km left
to be upgraded out of 38
km) Morang
The road alignment is existing earthen
track
The land use patterns of formation width are categorized into cultivated land, forest land and built up area.
10
Laxmimarga - Dangihat -
Banaul- Babiyabirta - Amahi
Road (29 km left to be
upgraded out of 31 km)
The road alignment is existing earthen
track
The current land use in the project site is cultivated land, settlement and
others.
11
Inaruwa - Satterjhoda -
Chhitaha - Purbakushaha -
Biratnagar Road
Sunsari
The road alignment is existing earthen
track
Road crosses seven small streams, and in two occasions, passes
adjacent to irrigation canal. List of those streams. The current land use
in the project site is cultivation, settlements, small sized orchards,
and pond for various purposes
12
Jhumka - Shinghiya -
Ramdhuni - Prakashpur -
Madhuwan - Shukrabare -
Paschimkushaha - Laukahi -
Boarder Road
The road alignment is existing earthen
track
The road crosses six small streams and passes along side Koshi
irrigation canal. The current land use in the project site is forest, cultivated
land, settlement
13
Mudheshanischare -
Dadagaun - Chanuwa Road
Dhankutta
The road alignment is existing earthen
track
The current land use in the project site is comprised of farmland (both irrigated and rainfed), forest and
shrub lands, settlement areas and some scattered barren land
14
Nayapul - Pawati -
Dadakharka Road
Dolakha The road alignment is existing earthen
track
The road alignment comprises of 25% of forest, 40 % of settlement,
and 25 % cultivation land and remaining 10% of barren/bush land
15
Barhabise - Maneswara -
Ghumthang - Listi -
Bhairabkunda Sindhupalchok
The road alignment is existing earthen
track
The current land use in the project corridor is forest area, settlement,
cultivation, grass land.
16
Dolalghat - Phalate - Kolati -
Dhadkharka- Pokharichauri -
Gurase Road
Kavre
The road alignment is existing earthen
track
The land use pattern of the area through which the road passes have been classified into five categories: cultivation land, forest land, grass
land, bush and barren land
17
Tallo - Ranibas - Harshadi -
Tadi - Dhanshari
Sindhuli
The road alignment is existing earthen
track
The project road crosses few minor rivers at Ch. 00+500, 3+290, 3+610,
5+200, 6+750, 9+710, 11+000, 12+280. - The current land use in the project site is forest area followed by
cultivation land, and Barren land
18
Dhudhuli - Lakhima -
RatmataKartha - Thakur
Damar - Arunathakur
The road alignment is existing earthen
track
The current land use in the project site is forest area, cultivated land,
barren land.
19
Badbhanjyang - Sanomasino
- Thulomasino - Satghumti
Road
Kathmandu
The road alignment is existing earthen
track
The project road crosses Sikte Khola and Khani Khola.. - The current land use in the project site is forest land, cultivated land, builtup, barren land
and shrubs
20
Bansbari- BagesworiPurano
Health Post to
MUNICIPALITY/RURAL Bhaktapur
The road alignment is existing earthen
track
The current land use within the RoW is agricultural land (77.4%) as dominant land use followed by
Settlement (20%), forest and barren
Rural Connectivity Improvement Project 20
MUNICIPALITY Building land.
21
Phisling - Tolang - Baspur -
Oralang - Mayatar - Tarse -
Upradanggadi - Shaktikhor
bazar Road
Chitwan
The road alignment is existing earthen
track
Rhiddhi Khola (22+180), Shikhari Khola (39+520) and Darbetar Khola
(40+100) are the rivers which are crossed by the road alignment. The current land use in the project site is settlement areas, cultivation area,
forest area, and bush area and grass land.
22
Lunkhu- Mudikuwa Road
Parbat
The road alignment is existing earthen
track
The road crosses the streams at several locations at Ch. 0+269,
0+684, 0+879, 1+033, 1+750, 7+500, 7+553, 8+146, 8+681, 9+200,
10+000, 10+946, 11+230, 12+230, 15+565, and 16+220. - The current
land use in the project site is forestland (52.12%), cultivated land
(39.41%), barren land (0.65%), settlement (5.21%) and shrubs
(2.61%).
23
Armadi- Banau Road The road alignment is existing earthen
track
The current land use in the project area includes forests (37.5%),
agricultural land (25.8%), Kharbari (18.4%), settlement (9.3%), shrub
land (7.3%) and remaining other land use type.
24
SolawangRauleBaluwaNaiga
dpulJamaabagarSimalchaur
HukaamRanmamaikot
Road's (Naigadpul-
Jamabagar Sector)
Rukum The road alignment is existing earthen
track
Sani Bheri is the major river in the proposed road alignment and other minor streams are at Ch. 2+110, 3+580, 12+130, 12+790, 13+630, 14+00, 14+520, 15+210, 16+910,
17+210, and 17+880. - The land use along the project alignment mainly
comprises of forest (62%), agricultural land (3%), grassland (4%), water body 14% and other
17%.
25
SitalPokhari- Jhulkhet-
Chunwang Road
The road alignment is existing earthen
track
The main river in the project area is Sankh Khola. Other rivers & kholsi lies in the alignment are Ghorneta
Khola (5+860), Tyau Khola (3+900). - The landuse is dominated by
cultivation (53%), forest (35%), grass (10%), others (2%).
26
Mijhing-Ruinibang-
Badachaur-Gumchal-
Harjang-Syuri-Gaam Road
Rolpa
The road alignment is existing earthen
track
The project road crosses two major river of the area i.e. Lungri and
Bojang. - The current land use within the
RoW is forestland (55%), cultivated land (12%), built-up (11%), barren land (18%) and 4% other areas.
-
27
Mijhing-Dhulewodaar-
Namjaa-Sirp-Pang Road
The road alignment is existing earthen
track
The project road crosses minor streams at Ch. 0+226, 0+245, 0+260,
2+205, 2+786, 2+824 and 3+112. - The current land use in the project
site is forestland (53.64%), cultivated land (35.64%), barren land (7.94%)
and shrubs (2.78%).
6.1.2 Compliance Monitoring
Rural Connectivity Improvement Project 21
35 During the present reporting period, the construction work has not been started yet. All contractors are being involved in Joint Survey work, drawing preparation and Camp Establishment. As reported, theres is no any of the occurrences of construction-related injuries
and fatalities, and no any complaint was registered during reporting time. For the compliance monitoring result an environmental safeguard compliance matrix has been developed for the project during pre-construction, construction and operation stage which is given in Appendix III. The environmental Specialist has visited the project roads to facilitate to the PIU and DFO for preparation of forest clearance report. During field visit discussion was made in following topics:
• Contractor shall submit Environmental and Management Plan before start the construction work;
• Contractor shall submit Air quality and Water quality test report before start the construction work;
• All permit should be maintain (eg. Camp/ labour camp, stockpile, equipment yard establishment, Quarry operation, crusher plant, spoil disposal sites etc.);
• Contractor shall submit Occupational health and Safety Plan, Traffic management Plan;
• Contractor shall nominated Safety Officer, Environmental Focal Person;
• PIU shall be established Safeguard Desk with Focal Person, Maintain the register to address grievances.
7. IMPLEMENTATION OF GRIEVANCE REDRESS MECHANISM AND COMPLAINTS RECEIVED FROM STAKEHOLDERS
7.1 Establishment of GRM
36 The project will establish a grievance redress mechanism to voice and resolve social and environmental concerns linked to the project and ensure greater accountability of the project authorities towards all affected persons. GRM will be formulated by the Project and will be in two level committee. 37 Field-Level Committee: Comprise of Field engineer, Social mobilizers, Contractor’s Environmental/Social Focal Point 38 Project-Level Committee comprise of Project Manager PIU, Municipality/Rural Municipality Representative, Chief District Office Representative, District Coordination Committee Representative, CSC Social mobilize, CSC Social Expert and Environment Expert, 2 representatives designated by affected community local level (man/woman). During reporting period, no any complain was registered.
8. OTHERS ACTIVITIES 39 Other noticeable activities were not noticed during this period.
9. CONCLUSION
Rural Connectivity Improvement Project 22
40 Rural Connectivity Improvement Project is expected to enter into the major construction phase of the project cycle in the third quarter of the year 2018. The pre-construction phase activities are summarized as follows.
• Approval for Use of Government Forest Land and Tree cutting;
• Contractor shall submit Environmental and Social Management Plan Occupational health and Safety Plan, Traffic management Plan before start the construction work;
• Contractor shall submit Air quality and Water quality test report before start the construction work;
• All permit should be maintain (eg. Camp/ labour camp, stockpile, equipment yard establishment, Quarry operation, crusher plant, spoil disposal sites etc.);
• Contractor shall nominated Safety Officer, Environmental Focal Person;
• PIU shall be established Safeguard Desk with Focal Person, Maintain the register to address grievances.
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 23
Appendix I: Updated Environmental Management Plan
Environmental Issues/Component
Remedial Measures / Actions Location Time Frame Mitigation Cost (NRs.)
Responsibility Status
Implementation Supervision
[A] Pre-Construction Stage
Permits
• Obtain necessary permits for commencement of roadwork and provide a copy to the Contractor.
• Obtain written permission from landholders, Municipality, DCC and Rural Municipality under the Local Government Operation Act, 2017 prior to commencement of various activities related to construction work(eg. Camp and stockpile, quarry and borrow pit, Hotmix location, spoil disposal) and provide copies to the Supervising Consultant.
Throughout road corridor
Pre – Construction
Subproject preparation cost Construction contract
Contractor
PIU, CSC
Worksite survey, Pegging and
approval
• Conduct layout survey of the proposed road construction works.
• Locate, peg out and seek approval from the
• Supervising Consultant for each ancillary site prior to the commencement of related activities.
• Inspect and approve, if correct all ancillary sites.
Throughout road corridor
Pre - Construction
Construction contract
Contractor PIU, CSC
Air and Water quality test
River Water quality, camp facilities drinking water quality Major settlement/school area
Major Settlement, Major River
Pre - Construction
BoQ 3.2.10 Contractor PIU,CSC
[B] Construction Stage
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 24
Earthworks / Slope Stabilization
• Cover fresh cuts, take precaution on water pollution, construction of dyke around stockpiled material, spoil, fresh cuts, use bioengineering
• Plantation of containerized tree&shrubseedlings.
• Control water flow through construction sites or disturbed areas with ditches, berms, check structures, live grass barriers etc.
Throughout road Corridor (ChainageMMM)
Construction
Included in BoQ (S. No. 3.1.8, 3.1.10 (2))
Contractor CSC, PIU
Drainage &WaterManagement (Drainage, cross-drainage, Gully protection etc.)
• Provide side drains, cross-drainage as per detailed design.
• River training works to avoid depth and side erosion of stream beds.
• Public shall be consulted regarding location of drainage outfalls.
• Care shall be taken not to disrupt or contaminate the irrigation water supply or local public water supplies.
Throughout road alignment
(ChainageMMM)
Construction Construction contract
Contractor CSC, PIU
Operation and Closure of Quarries and Borrow Pits
• Locate and peg quarries and seek approval from the CSC
• Obtain permission/license for extraction of materialsfrom Stakeholders, Municipality, DCC or Rural Municipality as appropriate.
• Locate extraction sites restricted to small areas;preferably on existing quarry sites and sites withoutany tree cover; away
Location of selected quarries and borrow pits proposed during construction(Location >>>)
Construction
Construction contract
Contractor
CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 25
from dwellings, archeological,religious or cultural sites; sites which will not alter river flow regime and possess water logging problemin future; and sites where effects will be temporary.
• Restrict all extraction activities to approved sites with operations to the hours of 7:00 – 18:00.
• Prevent ponding of surface water through adequatedrainage.
• Restore the site maintaining natural contours and vegetation.
Construction Spoil Management
• Locate disposal sites on stable ground withoutexcessive slope; that avoids water courses andwetlands; that will not promote instability and result indestruction of property, vegetation and local services.
• Identify, peg and seek approval from CSC for permissible disposal sites.
• Obtain permission from local stakeholders,Municipality, DCC, RM where required as appropriate.
• Restrict disposal at approved locations with correct placement.
• Where required, apply bio-engineering measures for
Location of selected Spoil disposal sites (ChainageMMM)
Construction Included in BoQ (S. No. 3.1.2 (1))
Contractor CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 26
vegetative cover to prevent surface erosion.
• Measures shall be taken to prevent earthworks and gabion works from impeding rivers, streams, water canals, or drainage system.
Stockpiling of Construction Materials
• Locate, peg and seek approval from the CSC for the use of stockpile sites.
• Stockpile should not be located on water courses; should not be within 50m of schools, hospitals or public standpipes; and should not affect locals and their properties.
• Obtain written permission from landowners and local bodies for stockpiling on their land.
• Stockpiles subject to erosion by wind or water should be covered with tarpaulins. For large stockpiles, it should be enclosed with side barriers and also covered when not in use.
• Provide intervening vegetated buffer to control any un-expected run-off.
• Clean area properly after completion.
Location of identified stockpiling sites.
Construction Contractor cost
Contractor CSC, PIU
Traffic management • Frame appropriate traffic diversion schemes (in specific stretches as per progress of construction work) and implemented to
Project road corridor
Construction PS 3
Contractor CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 27
avoid inconvenience due to construction works to present road users.
• Provision of flag men where is necessary, The traffic diversion signs should be bold and clearly visible particularly at night.
Disruption in natural water flow due to construction of water related
structures
• Adequate no. of drainage structures will be provided in order to have minimum interference on natural drainage pattern.
• Drain water discharge into farmland will be avoided
• No diversion of water away from natural water course unless absolutely necessary
• Avoid any blockage or diversion of natural channels due to (intended or incidental) disposal of spoil
Along the road Corridor where such structures are to be constructed
Construction Construction Contract
Contractor CSC, PIU
Reinstatement of Services
• Inventory of all services to be reinstated.
• Locate and reach agreement with affected people
• landowners and local people / end users
• (Municipality, DCC, RM) regarding services (i.e.
• irrigation canal, water supply lines, standpipes,
• drainage ditches and walking trails, electrical poles,paved crossings to be maintained, temporarily cut and reinstated including timing and location of cuts and reinstatements.
Throughout road corridor
Construction Construction Contract (BoQ item PS 2, 3.1.7)
Contractor CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 28
Obtain written permission from affected landowners / local people regarding temporary cessation of services.
• Works shall be planned with timing to avoid /minimize impact to cultural festivals.
• Moving of religious structures shall be done based on the results of public consultation.
8. Use of Bitumen • Fuelwood shall not be used for heating bitumen.Bitumen shall be melted in heaters using kerosene,diesel or gas fuel.
• Bitumen drums should be stored in dedicated areas,not scattered along the road and any small accidentalspills should be cleared up immediately.
• No bituminous material shall be discharged into side drains.
• Bitumen shall not be applied in strong wind or rainy conditions.
Throughout roadcorridor
Construction Construction contract
Contractor CSC, PIU
9. Stone Crushing Plant / Hot mix Plant / Batching Plants
• Locate, stake out and seek approval from CSC for stone crushing plant.
• Locate plant site away from population centers,drinking water intakes, cultivated lands and sensitiveecosystem preferably at least 500m from settlementand habitation.
• Obtain permission from local
Location of selected Plant sites
Construction Stage
Construction Contract
Contractor CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 29
stakeholders,Municipality, Rural Municipality, DCC as appropriate.
• Stone crushing equipment / cement batching shall befitted with dust control devices and operated as perManufacturer’s Specification.
• Hotmix Plant should have in-built mechanisms for theabsorption of gases.
• The plant shall be operated during day time.
• Restore the site maintaining natural contours and vegetation after use.
10. Air Pollution • Stone crushing plant / Hotmix plant / Batching plant shall be appropriately located at least 500m fromsettlement& habitation fitted with dust suppressionequipment.
• Road construction area shall be maintained damp by periodical spray of water.
• Delivery vehicles shall be covered.
• Mixing equipment shall be well sealed and equippedas per existing standards.
• All construction vehicles should comply with Motor
• Vehicles and Transportation Management Act as amended and have green sticker for operation.
• Provide temporary hoardings
Project area, Crusher Plant sites Settlement areas
Construction
MMMtimes
Construction contract Included in BoQ (3.1.10 (3))
Contractor Through approved monitoring agency
CSC, PIU CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 30
where required tominimize dust impact on locations of temples andother cultural sites.
• Provision of speed control measures in settlementand working areas to limit traffic speed.
• Air pollutant parameters (TSPM, PM10, SO, NOx,CO) shall be monitored regularly during construction.
11. Water Pollution
• Hazardous materials shall not be stored near surfacewaters sources
• Used lubricants and oils shall be collected and recycled or disposed off site.
• Plastic sheeting shall be placed under hazardousmaterial storage area to collect and retain leaks andspills.
• Contaminated runoff from storage areas shall becaptured in ditches with an oil trap at theoutlet.
• Contaminated and worn plastic sheeting shall bepacked into drums and disposed off site.
Project area Stream crossings
Construction MM.. times during construction period
Construction Contract Included in BoQ (3.1.10 (4))
Contractor Through approved monitoring agency
CSC, PIU CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 31
• Water Quality (PH, TSS, Oil and Grease) monitored regularly during construction.
Noise Pollution • Ensure plant and equipment used for construction conforms to best practices.
• Vehicles and equipment used will be fitted withsilencer and maintained to keep noise at minimumlevels.
• Workers will be provided with appropriate earmuffs/plugs specially at crusher site
• Noise barriers will be placed in urban and sensitivelocations i.e. schools, hospitals etc.
• Cracks caused by vibration due to constructionactivities need to be monitored closely andalternative be sought where problem arises.
• Work shall be restricted to day hours specifically aturban and sensitive locations.
Project area, Crusher plant site
Construction Contractor Cost
Contractor CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 32
C2 Biological
1. Vegetation and Forest Resources
• Identify and seek approval from CSC for clearance of trees/vegetation.
• Fuel wood shall be banned for construction works.
• Wildlife hunting and poaching shall be prohibited
Throughout road alignment
Construction Construction Contract (BoQ item 3.1.1 (1 to 5))
Contractor CSC, PIU
Loss of forest area and trees
Compensatory plantation to be carried out
Project area PIU PIU/CFUG DFO, CSC
C3 Socioeconomic and Cultural
2. Labour Camp Location andManagement
• Canp shall be barricade
• Locate, peg and seek approval from CSC for labor camp sites.
• Camps shall not be located near settlements; near water supply intakes; or sites that affect the access by local people to drinking water.
• Camp shall not be in the vicinity of landslide and flood plains.
• Provide and maintain proper drinking water, sewerage and waste disposal facilities at the camps. Camp shall be barricade.
• Ensure no wood is burnt by any worker on or off site.
• Camps shall be provided free of cost, with electricity and regulator & adequate fuel supplies of LPG or Kerosene.
• Prohibit workforce from poaching wildlife and cutting trees.
• After use, sites shall be
Locations of selected labour camps
Construction Construction Contract
Contractor CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 33
cleared and restored to natural or stable conditions.
• Provide and maintain first aid medical facilities, toilet shall be male and female separately.
• Sock pit for waste water,Pit for waste collection
• Camp shall be established as per DoLIDAROHS guidelines
3. Work Camp Location and Operation
• Locate, peg and seek approval from CSC for workcamp sites.
• Camps shall not be located near settlements and;near water supply intakes; or sites that affects localsaccess to drinking water.
• Camp shall not be in the vicinity of landslide andflood plains.
• Provide and maintain proper drinking water,sewerage, waste disposal including first aid unitmedical facilities at the camps.
• Used oil, lubricants shall be recovered, re-used or removed form site.
• Explosives, oil, petrol, and grease shall be managed according to provisions of this Management plan.
• After use, the site shall be cleared and restored tonear natural or stable conditions.
• Toilet shall be male and female separately
Locations selected forwork camps
Construction Construction contract
Contractor CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 34
• Sock pit for waste water
• Pit for waste collection
• As per DoLIDAROHS guidelines
4. Occupational Health and Safety
• Adequate lighting and safety signal devices be installed for work safety.
• Adequate warning signs and safety barriers shall be provided for work safety.
• Protective clothing including helmets, masks, boots, gloves, ear plugs and goggles should be provided for workers safety.
• At every work place, a readily available first aid unit including an adequate supply of dressing materials shall be provided for emergency preparedness in case of accidents.
• Maintain health care system at construction camps.
• Strict rules and regulation be maintained in the labour and work camp to avoid alcoholic and other bad habits.
• Electrical Equipment shall be checked and certified regularly.
• Provide and install all road signs as per design.
• As per DoLIDAROHS guidelines
Project area Construction Construction Contract
Contractor CSC, PIU
Post Construction Activities
1. Camp site restoration(Change
• Camp site to be restored to its original condition as per
Campsite locations Post-construction Contractor’s cost
Contractor CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 35
of land use due to setting up of construction camp, Waste generation at the construction site, Generation of debris and silt)
the rehabilitation plan
• Restoration of top soil
• Disposal at waste at designated locations
• Cleaning of water channels
• Removal of debris and disposal
2. Quarry site/Borrow area restoration
• Quarry site/Borrow area to be restored to its original condition as per the rehabilitation plan
• Restoration of top soil&disposalofdebris/waste at designated locations
Designated Quarry/Borrow area
Post-construction Contractor’s cost
Contractor CSC/PIU
Note: COx = Oxides of Carbon, DCC = District Development Committee,PIU = Project Implementation Unit., RCIP = Rural Connectivity Improvement Project, NOx = Oxides of Nitrogen. ROW = Right of Way. CSC = Construction Supervision Consultant, SOx = Oxides of Sulfur, TSPM – Total Suspended Particulate Matter, RM= Rural Municipality
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 36
Appendix II: Environmental Monitoring Plan
SN Environmental Attributes
Mitigation Measures Location Additional Monitoring Indicator if applicable
Compliance status
Corrective action
proposed in case of delay
1 Land transfer Confirm if the Land acquisition, resettlement and rehabilitation, poverty alleviation programs for affected people and all other related issues are addressed in Social Impacts and Resettlement & Rehabilitation report.
All through the alignment of each rural road
Confirm the status of land transfer (% of total)
2 Biological environment - Tree planting
All efforts shall be taken to avoid tree cutting wherever possible. • Requisite permission from forest department shall be obtained for cutting of roadside trees. • Provision of Compensatory Afforestation shall be made on 1:25.ratio basis. • Permission shall be taken for diversion of any forest land if involved. Provision shall be made for additional compensatory tree plantation.
Throughout the project section of the road
Confirm issuance of Forest Clearance
One road approval, 7 roads, not required, 8 roads verified and 11 road remaining
3 Planning for land clearing
The road land width shall be clearly demarcated on the ground. • The utility and community structure shifting shall be planned in consultations and concurrence of the community. • Tree felling shall be limited to those, which could not be saved even by design measures. The tree shall be cut with a prior permission of Forest department. • The vegetable cover shall be removed and disposed in consultation with community. • All public utilities shifting shall be planned with prior concurrence of respective agencies/authority and to the adjacent location approved by them
All through the Rural roads excepting in stretches of habitations
Tree cutting permission from Forests Department Concurrence from community for utility, community structure, and vegetation cover removal
One road approval, 7 roads, not required, 8 roads verified and 11 road remaining, community approval for vegetation removal is included with verification report.
4 Shifting on Common Properties Resources
All efforts are made to minimize shifting of common utilities and community structures. • The community structures/utilities, which can not be saved, will be shifted to adjacent area with the concurrence and in consultation with community
As determined by contractor under approval of PIU and CSC
Assess compliance based on DOLIDAR’s Guidelines
Construction work not yet started.
5 Establishment of Construction
Construction camp sites shall be located away from any local human settlements (minimum 0.5 km away) and preferably located
As determined by contractor under
Location of construction camp
Will fallow DoLIDAR
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 37
Camp, temporary office and storage area
on lands, which are not productive barren/waste lands presently. • Similarly temporary office and storage areas shall be located away from human settlement areas (minimum 500 m). • The construction camps, office and storage areas shall have provision of adequate water supply, sanitation and all requisite infrastructure facilities. • The construction camps shall be located at a minimum 0.5 km from forest land/areas to deter the construction labour in trespassing. Similarly, temporary office and storage areas shall be located at a minimum 0.5 km from forest land/areas. • The construction camps, office and storage areas shall have provision of septic tank/soak pit of adequate capacity so that it can function properly for the entire duration of its use. • All construction camps shall have provision of rationing facilities particularly for kerosene/LPG so that dependence on firewood for cooking is avoided completely to the extent possible. • The construction camps, office and storage areas shall have provision of health care facilities for adults, pregnant women and children. • Personal Protective Equipments (PPEs) like helmet, boots, earplugs for workers, first aid and fire fightingequipments shall be available at construction sites before start of construction. An emergency plan shall be prepared to fight with any emergency like fire. • Provision shall be made for domestic solid waste disposal in a control manner. The recyclable waste shall be sold off and non-saleable and biodegradable waste shall be disposed through secured land filling. • Provision of paved area for unloading and storage of fuel oil, lubricant oil, away from storm water drainage.
approval of PIC/PIU/ (ref- Labelled: WASTE OIL; and hazardous sign be displayed at oil handling areas and sold off to authorized refiners).
with planning of requisite facilities and making provision of such facilities prior to start of construction. Compliance to DOLIDAR’s Guidelines for Water Management from Labor Camp Availability of consent to establish from pollution control board for setting up the camp
Guidelines
6 Traffic Movement
The contractor will prepare appropriate traffic diversion scheme approved by respective PIU. This shall be implemented prior to start of construction to avoid any inconvenience to the present road users. This shall be implemented in other stretches of the road as per the progress of the construction work. • The diversion plan should ensure smooth flow of traffic, minimize accidents to road users during construction works. • Adequate signboards shall be placed much ahead of diversion site to caution the road users. The road signs should be bold and retro reflective in nature for good visibility in day and night both.
As proposed under DPR and determined by contractor and approved by PIC/PIU
Construction work not yet started.
7 Cut and Fill and
The alignment design shall consider options to minimize excessive cuts and fills. • The cut and fill quantities shall be used for
All through the alignment of each
Contractor shall submit
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 38
Embankment Construction design and planning
embankment to minimize barrow earth requirement. • The design shall be as per relevant DOLIDAR Guideline provisions for cut and fill, slope protection and drainage. • Adequate provision shall be made for cross drainage structure for maintaining natural drainage pattern in the subproject area and preventing soil erosion. • Side drain for channelizing water to nearby natural drain in water stagnation /logging prone area. • The top soil of the cut and fill area shall be used for embankment slope protection • Embankment will be designed above High Flood Level wherever, area is prone to flood.
rural road access tipping locations for approval to PIU.
8 Hydrology and Drainage
Provision of adequate cross drainage structure shall be made to ensure smooth passage of water and maintaining natural drainage pattern of the area. The discharge capacity of the CD structure shall be designed accordingly. • Provision of adequate side drainage shall be made in water stagnant/logging areas. • The construction work near water body shall be planned preferably in dry season so that water quality of the water channel is not affected due to siltation and rain water runoff. • Elaborate drainage system shall be provided to drain the storm water from the roadway and embankment to ensure minimum disturbance to natural drainage of surface and subsurface water of the area. • Provision of additional cross drainage structure shall be made in the areas where nearby land is sloping towards road alignment on both the sides. • Provision of concrete road construction in habitat area with drainage of both side of the road shall be made as per the design provision and with adequate slope to prevent any water logging. • Road level shall be fixed above HFL. Embankment slope stabilization measures shall be planned. Stabilization measures may include vegetative treatment, stone pitching, retaining wall where feasible, and bioengineering
Near all drainage crossing , kholas and river crossings etc.
Yet to be started
9 Sourcing and transportation of construction material ( aggregates , earth)
Borrow Earth: • The borrow earth shall be obtained from identified locations and with prior permission for landowner and clear understanding for its rehabilitation. The DOLIDAR’s Guideline for Burrow Pit Management guideline should be used for selection of borrow pits and amount that can be borrowed. • Borrowing earth from agricultural land shall be minimized to the extent possible. Further, no earth shall be borrowed from already low-lying areas. • A 15 cm topsoil will be stripped off from the borrow pit and this will be stored
At Borrow sites and quarries (if required) location.
Compliance to DoLIDAR guidelines and stated criteria, Permission from land owners, Rehabilitation of borrow areas
Yet to be started
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 39
in stockpiles in a designated area for height not exceeding 2m and side slopes not steeper than 1:2 (Vertical: Horizontal). • Borrowing of earth will not be done continuously through out the stretch. • Ridges of not less than 8m widths will be left at intervals not exceeding 300m. • Small drains will be cut through the ridges, if necessary, to facilitate drainage. • The slope of the edges will be maintained not steeper than 1:4 (vertical: Horizontal). • The depth of borrow pits will not be more than 30 cm after stripping the 15 cm topsoil aside. • The borrow area shall be rehabilitated as per the understanding arrived with the land-owner. The re-habilitation plan may include the following: • Borrow pits shall be backfilled with rejected construction wastes and will be given a vegetative cover. If this is not possible, then excavation sloped will be smoothed and depression will be filled in such a way that it looks more or less like the original ground surface. • Borrow areas might be used for aquaculture in case landowner wants such development. Aggregate : • The stone aggregate shall be sourced from existing licensed quarries and the later should follow the DOLIDAR’s Guidelines for Quarry Area Management • Copies of consent/ approval / rehabilitation plan for use of existing source will be submitted to PIU. • Topsoil to be stockpiled and protected for use at the rehabilitation stage Transportation of Construction Material: • Existing tracks / roads are to be used for hauling of materials to the extent possible. • Prior to construction of roads, topsoil shall be preserved or at least shall be used for any other useful purposes like using in turfing of embankment rather than allowing its loss by construction activities. • The vehicles deployed for material transportation shall be spillage proof to avoid or minimize the spillage of the material during transportation. In any case, the transportation links are to be inspected at least twice daily to clear accidental spillage, if any.
Availability of valid consent of quarries
10 Loss of Productive Soil, erosion and land use change
• It shall be ensured that the land taken on lease for access road, construction camp and temporary office of the storage facilities is restored back to its original land use before handing it over back to land owner. • The top soil from the productive land (borrow areas, road widening areas etc.) shall be preserved and reused for plantation purposes. • It shall also be used as top cover of embankment slope for growing vegetation to protect soil erosion. •
Thought out the road section
Yet to be started
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 40
Cut and fill shall be planned as per “Work Norms for Agricultural and Rural Roads (1998)” and “Technical Specification for Agricultural and Rural Roads (1998)” provisions. • All steep cuts shall be flattened and benched. • Shrubs shall be planted in loose soil area. • Recommended practice for treatment of embankment slopes for erosion control shall be taken into consideration as instructed by the CSC. • Soil erosion shall be visually checked on slopes and embankment areas. In case soil erosion is found, suitable measures shall be taken to control the soil erosion
11 Compaction and Contamination of Soil
To prevent soil compaction in the adjoining productive lands beyond the ROW, the movement of construction vehicles, machinery and equipment shall be restricted to the designated haulage route. • The productive land shall be reclaimed after construction activity. • Septic tank or mobile toilets fitted with anaerobic treatment facility shall be provided at construction camp/temporary office/storage areas. • Domestic solid waste at construction camp shall be segregated into biodegradable and non-biodegradable waste. • The non-biodegradable and recyclable waste shall be sold off. • Fuel and lubricants shall be stored at the predefined storage location. • The storage area shall be paved with gentle slope to a corner and connected with a chamber to collect any spills of the oils. • All efforts shall be made to minimise the waste generation. Unavoidable waste shall be stored at the designated place prior to disposal. • To avoid soil contamination at the wash-down and re-fuelling areas, “oil interceptors” shall be provided. Oil and grease spill and oil soaked materials are to be collected and stored in labelled containers (Labelled: WASTE OIL; and hazardous sign be displayed) and sold off to authorized re-refiners.
Throughout the project section of the roads
Yet to be started
12 Construction Debris and waste
All excavated materials from roadway, shoulders, verges, drains, cross drainage will be used for backfilling embankments, filling pits, and landscaping. • Unusable debris material should be suitably disposed off at predesignated disposal locations, with approval of the concerned authority. • The bituminous wastes shall be disposed in secure manner at designated landfill sites only in an environmentally accepted manner. • For removal of debris, wastes and its disposal guidelines provided by the CSC should be followed. • Unproductive/wastelands shall be selected with the consent of the land owner and local authority. The dumping site
Throughout the project section of the road
Yet to be started
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 41
should be of adequate capacity. It should be located at least 500 m away from the residential areas. Dumping sites should be away from water bodies to prevent any contamination of these bodies.
13 Air and Noise Quality
Vehicles delivering loose and fine materials like sand and aggregates shall be covered. • Dust suppression measures like water sprinkling, shall be applied in all dust prone locations such as unpaved haulage roads, earthworks, stockpiles and asphalt mixing areas. • Mixing plants and asphalt (hot mix) plants shall be located at least 0.5 km away and in downwind direction of the human settlements. • Material storage areas shall also be located downwind of the habitation area. • Hot mix plant shall be fitted with stack of adequate height (30 m) or as may be prescribed by local authority to ensure enough dispersion of exit gases. Consent to establish and operate shall be obtained from MUNICIPALITY/RURAL MUNICIPALITY and comply with all consent conditions. • Diesel Generating (DG) sets shall also be fitted with stack of adequate height. Low sulphur diesel shall be used in DG sets and other construction machineries. Construction vehicles and machineries shall be periodically maintained. • The requisite PPE (helmet, mask, boot, hand gloves, earplugs) shall be provided to the construction workers. • Workers’ exposure to noise will be restricted to less than 8 hours a day. Workers duty shall be regulated accordingly. • Contractor shall comply with the DOLIDAR’sOH&SGudelines.
Throughout the project section of the road
Under progress for baseline data collection by the contractor (Parbat has completed, other are remaining)
14 Ground Water and Surface Water Quality and Availability
The contractor shall arrange for water required during construction in such a way that the water availability and supply to nearby communities remains unaffected. • Water intensive activities shall not be undertaken during summer period to the extent feasible. • Provision shall be made to link side drains with the nearby ponds for facilitating water harvesting if feasible • Where ponds are not available, the water harvesting pits shall be constructed as per the requirement and rainfall intensity. • Preventive measures like slop stabilisation, etc shall be taken for prevention of siltation in water bodies.
Near all drainage crossing , nalas and river crossings etc
Yet to be started
15 Occupational Health and Safety
Verification of implementation of provision made at planning stage. • Each worker is provided with requisite PPE • Directional sight board shall be installed on all sharp curves and bends • At a main road, intersection or crossing “STOP” sign and ‘Tintersection’ warning sign shall be installed on the village road.
Throughout the project section at the location determined by contractor and
No any injuries are reported
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 42
approved by PI
16 Grievance Redress
Obtaining information from Village level Grievance redress committee, PIU as applicable
No any complains till reporting period
Appendix III: Environmental Safeguard Compliance Matrix
District Road Name
Pre Construction Stage
Implementation Stage
OperationStage Total
Weightage
IEE
ap
pro
val
EM
P
En
v.
cla
use
in C
ontr
act
docu
me
nt
EM
P c
ost in
BoQ
To
tal o
f P
reco
nstr
ucti
on
Ap
pro
va
l o
f tr
ee c
uttin
g
Con
tra
cto
r'S
EM
P
Air a
nd w
ate
r qu
alit
y t
est
befo
re c
onstr
uctio
n
App
rova
l/p
erm
it f
or
ca
mp
esta
blis
hm
ent,
qu
arr
y
op
era
tio
n,
spo
il etc
.
Con
str
uction
S
ite s
afe
ty
mana
ge
ment
Occupatio
nal he
alth a
nd
safe
ty p
lan
Ca
mp s
ite
man
age
me
nt
Tra
ffic
ma
nag
em
ent
Re
insta
te o
f p
ub
lic a
nd
private
str
uctu
res
Spo
il m
anag
em
ent
Aw
are
ne
ss t
rain
ing
Esta
blis
hm
ent
of
Safe
gu
ard
unit
En
viro
nm
enta
l fo
ca
l P
rso
n
Esta
blis
hm
ent
of G
riva
mce
redre
ss m
echa
nis
m
Oth
er
EM
P C
om
plia
nce
Bio
-en
gin
eeri
ng
Month
ly m
on
itori
ng
re
port
sub
mis
sio
n
To
tal
Weig
hta
ge o
f
Imp
lem
en
tati
on
Re
sto
ration
of
all
cam
p
sites
Re
sto
ration
of
qua
rry/b
orr
ow
site
s
Com
ple
tio
n r
ep
ort
To
tal
Weig
hta
ge o
f
Op
era
tio
n
Acco
mp
lish
me
nt
(Po
or=
belo
w 5
0;
Goo
d=
50-8
0;
Exce
llent=
abo
ve 8
0)
Weightage 15 5 5 5 30 5 5 5 3 3 3 3 3 3 3 3 3 3 3 4 3 5 60 3 4 3 10 100
Jhapa
Amaldagi - Samayaghad -Babwari - Solmari road
15 5 5 5 30
30
Charpane - Chaitubari-Matigada-Sadhukuti - Khodamara-Rajgadh
15 5 5 5 30
30
Kharsangwari - Jalthal -Mangalware - Baundoka -AdhikariChowkSadak
15 5 5 5 30
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 43
Padajungi (Lakhanpur) -Guhawari-Laladhbandra - Jharka-BaluwathanChapramari -Khajurgachhi
15 5 5 5 30
30
Ilam
Nepaltar-Shantidada - Gagrebhangyang - MangalbareDhuseni - Gajrmukhi - Ebhang -ChaturmoadAadipur - Larmwa-GhartiDobhan - Chapeti - BeldagiDamak Road
15 5 5 5 30
30
Mangalbare - Phungfung - EktappaSikariBhanjyang - Phakphok - Ra.Ma.Bi. KhambangChowk - Thingepur - Aamchok - Jungetar - Phuyatappa - Rabi road
15 5 5 5 30
30
Panchthar
Phidim - Nagin - Sidin -Prangbung - Falot Road
15 5 5 5 30
30
Samdin - Chokmangu - Nawamidada - FaktepGhurbisepanchami Road
15 5 5 5 30
30
Morang
Khorshane - Kerawari -Singhadevi Road
15 5 5 5 30
30
Laxmimarga - Dangihat - Banaul- Babiyabirta - Amahi Road
15 5 5 5 30
30
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 44
Sunsari
Jhumka - Shinghiya - Ramdhuni - Prakashpur - Madhuwan - Shukrabare - Paschimkushaha - Laukahi - Boarder Road
15 5 5 5 30
30
Inaruwa - Satterjhoda - Chhitaha - Purbakushaha - Biratnagar Road
15 5 5 5 30
30
Dhankuta
Mudheshanischare - Dadagaun - Chanuwa Road
15 5 5 5 30
Dolakha Nayapul – Pawati – Dadakharka Road
15 5 5 5 30 5
30
Sindhupalchowk
Barhabise – Maneswara – Ghumthang – Listi – Bhairabkunda
15 5 5 5 30
30
Kavre
Dolalghat – Phalate – KolatiDhadkharka- Pokharichauri - Gurase Road
15 5 5 5 30
30
Sindhuli
Tallo - Ranibas - Harshadi - Tadi - Dhanshari
15 5 5 5 30
30
Dhudhuli - Lakhima - RatmataKartha - Thakur Damar - Arunathakur
15 5 5 5 30
30
Kathmandu
Badbhanjyang - Sanomasino - Thulomasino - Satghumti Road
15 5 5 5 30
Bhaktapur
From Bansbari - BagesworiPurano Health Post to VDC Building
15 5 5 5 30
Semi-annual Environmental Safeguard Report April-June, 2018
Rural Connectivity Improvement Project 45
CHITWAN
Phisling - Tolang - Baspur - Oralang - Mayatar - Tarse - Upradanggadi - Shaktikhor bazar Road
15 5 5 5 30
30
KAVRE
Khopasi-Taldhunga (Kamidada - Taldhunga section)
15 5 5 5 30
30
Parbat
Lunkhu - Mudikuwa Road
15 5 5 5 30
30
Armadi - Banau Road 15 5 5 5 30
30
Rolpa
Mijhing -Ruinibang -Badachaur - Ghumchaal - Harjang-Syuri-Gaam Road
15 5 5 5 30
30
Mijhing - Dhulewodaar - Namjaa - Sirp - Pang Road
15 5 5 5 30
30
Rukum
SitalPokhari - Jhulkhet-Chunwang Road
15 5 5 5 30
30
Solawang - Raule - BaluwaNaigadpul - Jamaabagar - Simalchaur - Hukaam - Ranmamaikot Road's
15 5 5 5 30
30
Appendix IV: Air and Water Quality Monitoring Locations
Air Quality Monitoring Location Of Mudikuwa- Lunkhu Road
High Volume Sampler is used for air quality monitoring
Semi-annual Environmental Safeguard Report
Environmental Management Plan for Mudikuwa Lunkhu Road
Water Sampling location and Water sample taken from Chirdi River of Mudikuwa Lunkhu Road
Semi-annual Environmental Safeguard Report
Environmental Management Plan for Mudikuwa Lunkhu Road
Semi-annual Environmental Safeguard Report
Environmental Management Plan for Mudikuwa Lunkhu Road
Semi-annual Environmental Safeguard Report
Environmental Management Plan for Mudikuwa Lunkhu Road
Appendix V: Photographs of Progress Activities
Tree measurement during verification by DFO, Parbat
Electric Pole and Resting place will affected during road construction, Midikuwa- Lunkhu Road
Joint survey: Samdin-Nawamidada Road Panchthar
Detail Survey in Kavre
Semi-annual Environmental Safeguard Report
Environmental Management Plan for Mudikuwa Lunkhu Road
Appendix: VI Issued letters related to Environmental Management
Semi-annual Environmental Safeguard Report
Environmental Management Plan for Mudikuwa Lunkhu Road
Appendix: VII Sample Contractor’s Environmental Management Plan
Semi-annual Environmental Safeguard Report
Environmental Management Plan for Mudikuwa Lunkhu Road
Semi-annual Environmental Safeguard Report
Environmental Management Plan for Mudikuwa Lunkhu Road
Semi-annual Environmental Safeguard Report
Environmental Management Plan for Mudikuwa Lunkhu Road
Semi-annual Environmental Safeguard Report
Environmental Management Plan for Mudikuwa Lunkhu Road
RURAL CONNECTIVITY IMPROVEMENT PROJECT
(SAMPLE) Site Specific Environmental Management Plan(SEMP)
Contract No:MMMM. Mudikuwa -Lunkhu Road, Parbat
PIU, Parbat
8/1/2018
Prepared by:EEEEEE..(Contractor)
Semi-annual Environmental Safeguard Report
Environmental Management Plan for Mudikuwa Lunkhu Road
Table of Contents ABBREVIATION .................................................................................................................... i
1. INTRODUCTION ........................................................................................................... 1
1.1 PROJECT DESCRIPTION ............................................................................................. 1
1.2 Salient features of road .................................................................................................. 3
2. Contractor’S SITE SPECIFIC Environmental Management Plan (SEMP) ...................... 4
2.1. Contractor’s Personnel and Their Roles ......................................................................... 4
2.2. Reporting and Documentation ........................................................................................ 4
2.3 Contractor responsibility for Environmental Management ............................................. 4
2.4 ENVIRONMENTAL Monitoring ...................................................................................... 16
Appendix
Semi-annual Environmental Safeguard Report
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat i
ABBREVIATION
ADB Asian Development Bank AP Affected Persons BoQ Bill of Quantity CDO Chief District Officer CFUG Community Forest Users Group CSC Construction Supervision Consultant DCC District Coordination Committee DFO District Forest Office DoLIDAR Department of Local Infrastructure Development and Agricultural Roads EMP Environmental Management Plan ESMP Environmental and Social Management Plan EMoP Environmental Monitoring Plan IEE Initial Environmental Examination IUCN International Union for Conservation of Nature LEST Livelihood Enhancement Skills Training MLD Ministry of Local Development MOEST Ministry of Environment, Science and Technology MOFSC Ministry of Forest and Soil Conservation MoFLD Ministry of Federal Affairs and Local Development NGO Non-Governmental Organizations PCU Project Coordination Unit RCIP Rural Connectivity Improvement Project PIU Project Implementation Unit RoW Right of Way SEMP Site Specific Environmental Management Plan
Semi-annual Environmental Safeguard Report
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 1
INTRODUCTION
1.1 PROJECT DESCRIPTION
Mudikuwa- Lunkhu Road is located in Parbat District, Dhaulagiri Zone, State 4 of Nepal. It starts from Lunkhu khola bridge of Lunkhu settlement and ends at Mudikuwa This road connects the settlements of Falebas Muncipality and Mahashila Rural Municipality and connects to district headquarters of Parbat district through Dobilla – Falebas Road and Pokhara - Baglung Road. The length of the proposed road is 13.003 km starting from Ch 6+700 to Ch 19+703. The road from Ch 0+000 to Ch 6+700 is under construction from the GON fund. The road section is proposed to be upgraded from earthen track to blacktop standard with improvement in horizontal and vertical alignment and introduction of new retaining and cross drainage structures. The alignment starts at Ch 6+700 of Falebas Municipality and passing through various settlements of Falebas Municipality and Lunkhu Mahashila Rural Municipality ends at Ch 19+703. It passes through Mudikuwa, Duktang, Kurgha, Dharapani, and Lunkhu settlement. The road crosses the streams at several locations Major river crossing is Lamahai river (Ch 7+000) and Chirdi River. The current land use in the project site is forestland (52.12%), cultivated land (39.41%), barren land (0.65%), settlement (5.21%) and others (2.61%). (eg, Forest area from 1+200 – 2+500, 4+200- 5+100, 7+200- 8+500, Cultivated land O+ 000- 1+200, 2+500 -4+200, 5+100 -7+200, Settlement Chainage M. To M., ). It lies in subtropical climate region. The road does not fall under any protected areas or their buffer zone, wetlands of biological importance or other ecologically sensitive areas.
Semi-annual Environmental Safeguard Report
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 2
Figure 1: Land use along the proposed road alignment
IEE of Mudikuwa-Lunkhu road had already been approved by the MoFLD and ADB. Existing conditions of the proposed road section have not been changed significantly after the preparation of the IEE. This EMP will guide the site specific environment problems arising from construction of road.
Semi-annual Environmental Safeguard Report
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 3
Figure 2: Location map of the proposed project The Summary Description of the main works, is as follows: i. Roadway excavation for widening and geometric improvement of road; ii. Formation of embankment of roadway geometric improvement of road; iii. Construction of side drains; iv. Construction of retaining structures for slope stability; v. Construction of cross-drainage structures; vi. Construction of structures and Laying of sub-base, base and Asphalt concrete; vii. Erection of traffic sign and road safety measures; viii. Implementation of mitigation measures as recommended in IEE and EMP, etc.
1.2 Salient features of road Description Project Features
Name of the Project Rural Connectivity Improvement Project
Name of the Sub-project Mudikuwa Lunkhu Road
Road Type / Design Parameters
Classification of Road District Road
Length of Road 13 km
Right of Way 20 m (10 meters on either side from centerline of the road)
Design Road Width for District Road
5.25 m (3.75 m carriage way and 0.75 m shoulder on either side)
Nature of Road Lane Single lane
Type of Work Upgrading, BITUMINOUS STANDARD
Semi-annual Environmental Safeguard Report
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 4
Description Project Features
Shoulder 1.5 m (0.75 m * 2)
Gradient
Limitation of Maximum Gradient Length above Average Gradient of 7%
300 m
Ruling 7%
Limiting gradient 10%
Exceptional gradient for up to 100 m length
12%
Minimum gradient on hill roads (for better drainage)
0.5 % (max 1%)
Project Costs
Total Project Cost NRs. 358,159,145.61
EMP Cost NRs. 24,375000
Contractor’S SITE SPECIFIC Environmental Management Plan (SEMP)
The SEMP is prepared to guide implementation of mitigation measures and monitoring requirements. It includes institution and their roles, environmental management activities, environmental management organizational structure and budget for mitigation measures. The SEMP will focus on i) forestlands where no tree cutting will be allowed without securing the necessary clearances, ii) community areas where regular dust suppression will be implemented, iii) names and location of rivers and ponds where water quality monitoring will be conducted, iv) quary sites and borrow area locations; v) camp sites, vi) disposal sites for debris and camp wastes; and vii) location of hot mix and batching plants including permits and clearance; viii) drainage management ix) community structures relocation and reinstate etc.
2.1. Contractor’s Personnel and Their Roles The main responsibility for Contractor’s Site Specific Environmental Management Plan (SEMP) implementation is The contractor. The contractor will nominate focal person for environmental management and monitoring and reporting. (Name of focal person is MMMMM).
2.2. Reporting and Documentation As part of SEMP, reports will be produced at regular time intervals. Monthly and Quarterly progress reports will be prepared and submitted to the CSC/PIU, and CSC/PIU will forward it to the PCU.
2.3 Contractor responsibility for Environmental Management The Contractor will be solely responsible for any remedial or mitigation measures required by the environment-related effects of any of his maintenance activities. The Contractor will demonstrate compliance with all environmental stipulations for this project in Contractor’s Site Specific Environmental Management Plan (SEMP). In case of an environmental problem, the Contractor will immediately notify the Employer and seek advice on his proposed corrective action. Among the situations that may arise are complaints or legal
Semi-annual Environmental Safeguard Report
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 5
actions by third parties on matters such as environmental damage to property and natural resources, ground subsidence, interruption of groundwater flow and surface or groundwater contamination.
Compliance with Environmental Laws and Regulations The Contractor will conform to the Government of Nepal’s laws for the protection of the environment and other relevant legislation in force, or in the absence of these, with Asian Development Bank requirements.
The contractor Prepare and submit Environmental Management Plan including Air and Water quality test report before construction work start. The contractor will submit monthly progress report and quarterly reports on the carrying out of such measures to the Employer.
PROVISION IN CONTRACT DOCUMENT The following are the provisions in Contract document and BoQ: Contractor will submit:
• Site Specific Environmental Management Plan (SEMP)
i. Compliance with Environmental Laws and Regulations The Contractor will conform to the Government of Nepal’s laws for the protection of the environment and other relevant legislation in force, or in the absence of these, with Asian Development Bank requirements. The Contractor will comply with all current environmental laws and regulations of the country.
ii. Environmental Reports The Contractor will submit regular environmental reports to the Employer as a requirement of the EMP. A summary report will be submitted as part of the Monthly Progress Report. Quarterly report will comprehensively address all relevant aspects of environmental management.
iii. Provision on General Condition of Contract: • Insurance of workers (Clause 19)
• Safety (clause 24)
• Child labor (clause 32)
iv. Provision on Particular Condition of Contract:
• IEE/EMP part of the contract (GCC2.3)
• Safety Security and Protection of the Environment (GCC80)
• Traffic diversion (GCC81)
• Maintenance of Other Services and Structures (GCC82)
• Reporting (GCC84)
v. Provision in BoQ:
• Provisional Sum SL No 2: Relocation, diverting, reconnecting, reinstalling and/or reinstatement including making good of any damages or short comings caused by the construction procedure and activities of any public and private utilities and services along with shifting and rehabilitation of water supply pipelines as instructed by the Project Manager and acording to the rules and regulations of the Service Providers.
• 3.1.2 Earth Works (1) Excavation in roadway, drains, retaining/ breast walls, longitudinal/ cross drainnage structures and other ancillary structures including foundations as per design and drawing in all type of soil and rock materials including transportation and disposal of excavated materials at environmentally safe tipping sites to be approved by the project manager. This item will also cover trimming and finishing to a reasonably good shape to the full satisfaction of the project manager and as per the DoR SP-900.
• SL No. 3.2.10 Environment Plan and EMoP
• Regular water sprinkling (2.8 Ltr/Sqm)(at least 2 times) per day at all settlement (6.5 Km) for suppression of dust levels as instructed by Project Manager.
Semi-annual Environmental Safeguard Report
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 6
• Periodic air quality monitoring during construction stage at major settlement areas along project road with all necessary test equipments & opertational arrangements. The parameters to be monitored are TSP, PM10, SO2, NOx,CO etc. Each monitoring schedule will be over duration of 24 hours (in 8 hour shifts). The tests are to be conducted as directed by Project Manager/CSC.
• Periodic water quality monitoring during construction stage at major settlement areas along project road with all necessary test equipments & opertational arrangements. and cover parameters as pH, TSS, oil and the tests are to be conducted as directed by Project Manager
Semi-annual Environmental Safeguard Report April-June, 2018
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 7
Table 2.1: Environmental Management Plan
Environmental Issues/Component
Remedial Measures / Actions Location Time Frame
Mitigation Cost (NRs.)
Responsibility
Implementation Supervision
[A] Pre-Construction Stage
Permits
• Obtain written permission from landholders, Municipality, DCC and Rural Municipality under the Local Government Operation Act, 2017 prior to commencement of various activities related to construction work(eg. Camp and stockpile, quarry and borrow pit, Hotmix location, spoil disposal) and provide copies to the Supervising Consultant.
Throughout road Corridor Location of Camp: Stockpile: Quarry: Spoil disposal:
Pre – Construction
Subproject preparation cost Construction contract
Contractor PIU, CSC
Worksite survey,
Pegging and approval
• Conduct layout survey of the proposed road construction works.
• Locate, peg out and seek approval from the Supervising Consultant for each ancillary site prior to the commencement of related activities.
• Inspect and approve, if correct all ancillary sites.
Throughout road corridor
Pre - Construction
Construction contract
Contractor PIU, CSC
Air quality test Major settlement/school area TSP: Total suspended particles (TSP) PM 10Particulate Matters SO2: Sulfur dioxide NOx nitrogen oxides CO carbon monoxide Each monitoring schedule shall be over duration of 24 hours
Kurga Duktang ( Major Settlement)
Pre - Construction
BoQ 3.2.10 Contractor PIU,CSC
Water quality test
River Water quality, camp facilities drinking water quality parameters as pH, TSS, oil other as directed by Project Manager
Lamahai River and Chirdi River
Pre - Construction
BoQ 3.2.10 Contractor PIU,CSC
[B] Construction Stage
Earthworks / • Cover fresh cuts, take precaution on water pollution, Throughou Constructio Included in Contractor CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 8
Environmental Issues/Component
Remedial Measures / Actions Location Time Frame
Mitigation Cost (NRs.)
Responsibility
Implementation Supervision
Slope Stabilization
construction of dyke around stockpiled material, spoil, fresh cuts, use bioengineering
• Control water flow through construction sites or disturbed areas with ditches, check structures, etc.
t road Corridor (ChainageMMM)
n
BoQ (S. No. 3.1.8, 3.1.10 (2))
Drainage &WaterManagement (Drainage, cross-drainage, Gully protection etc.)
• Provide side drains, cross-drainage as per detailed design.
• River training works to avoid depth and side erosion of stream beds.
• Public will be consulted regarding location of drainage outfalls.
• Care will be taken not to disrupt or contaminate the irrigation water supply or local public water supplies.
Throughout road
alignment (Chainage
MMM)
Construction
Construction
contract
Contractor CSC, PIU
Operation and Closure of Quarries and Borrow Pits
• Locate and peg quarries and seek approval from the CSC, Concern authorities.
• Obtain permission/license for extraction of materialsfrom Stakeholders, Municipality, DCC or Rural Municipality as appropriate.
• Locate extraction sites restricted to small areas; preferably on existing quarry sites; away from dwellings, archeological, religious or cultural sites; sites which will not alter river flow regime and possess water logging problem in future; and sites where effects will be temporary.
• Restrict all extraction activities to approved sites with operations to the hours of 7:00 – 18:00.
• Prevent ponding of surface water through adequate drainage.
• Restore the site maintaining natural contours and vegetation.
Location of selected quarries and borrow pits proposed during construction(Location >>>)
Construction
Construction contract
• Contractor (Obtain permission/license for extraction of materialsfrom Stakeholders, Municipality, DCC or Rural Municipality as appropriate.)
CSC, PIU
Construction Spoil Management
• Identify, peg and seek approval from CSC for permissible disposal sites. Obtain permission from local stakeholders, Municipality, DCC, RM where required as appropriate.
• Locate disposal sites on stable ground without excessive slope; that avoids water courses and wetlands; that will
Location of selected Spoil disposal sites
Construction
Included in BoQ (S. No. 3.1.2 (1))
Contractor (approval from CSC for permissible disposal sites.
CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 9
Environmental Issues/Component
Remedial Measures / Actions Location Time Frame
Mitigation Cost (NRs.)
Responsibility
Implementation Supervision
not promote instability and result in destruction of property, vegetation and local services.
• Where required, apply bio-engineering measures for vegetative cover to prevent surface erosion.
• Measures will be taken to prevent earthworks and gabion works from impeding rivers, streams, water canals, or drainage system.
(ChainageMMM)
Obtain permission from local stakeholders, Municipality)
Stockpiling of Construction Materials
• Locate, peg and seek approval from the CSC for the use of stockpile sites.
• Obtain written permission from landowners and local bodies for stockpiling on their land.
• Stockpiles subject to erosion by wind or water will be covered with tarpaulins. For large stockpiles, it will be enclosed with side barriers and also covered when not in use.
• Will clean area properly after completion.
Location of identified stockpiling sites.
Construction
Contractor cost
Contractor (approval from
CSC for permissible
disposal sites. Obtain permission
from local stakeholders, Municipality)
CSC, PIU
Traffic management
• Frame appropriate traffic diversion schemes (in specific stretches as per progress of construction work) and implemented to avoid inconvenience due to construction works to present road users.
• Provision of flag men where is necessary, put the traffic diversion signs that will be clearly visible particularly at night.
Project road
corridor
Construction
PS 3
Contractor CSC, PIU
Disruption in natural water flow due to
construction of water related
structures
• Adequate no. of drainage structures will be provided in order to have minimum interference on natural drainage pattern.
• Drain water discharge into farmland will be avoided
• No diversion of water away from natural water course unless absolutely necessary
• Avoid any blockage or diversion of natural channels due to (intended or incidental) disposal of spoil
Along the road Corridor where such structures are to be constructed
Construction
Construction
Contract
Contractor CSC, PIU
Reinstatement of Services
• Inventory of all services to be reinstated.
• Locate and reach agreement with affected people
Throughout road
Construction
Construction
Contractor (maintain
CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 10
Environmental Issues/Component
Remedial Measures / Actions Location Time Frame
Mitigation Cost (NRs.)
Responsibility
Implementation Supervision
landowners and local people / users
• (Municipality, DCC, RM) regarding services (i.e. irrigation canal, water supply lines, standpipes, drainage ditches and walking trails, electrical poles,paved crossings to be maintained, temporarily cut and reinstated including timing and location of cuts and reinstatements. Obtain written permission from affected landowners / local people regarding temporary cessation of services.
• Works will be planned with timing to avoid /minimize impact to cultural festivals.
• Moving of religious structures will be done based on the results of public consultation.
corridor
Contract (BoQ item PS 2, 3.1.7)
agreement)
8. Use of Bitumen
• Fuelwood will not be used for heating bitumen. Bitumen will be melted in heaters using kerosene,diesel or gas fuel.
• Bitumen drums will be stored in dedicated areas, not scattered along the road and any small accidental spills will be cleared up immediately.
• No bituminous material will be discharged into side drains.
• Bitumen will not be applied in strong wind or rainy conditions.
Throughout roadcorridor
Construction
Construction contract
Contractor CSC, PIU
9. Stone Crushing Plant / Hot mix Plant / Batching Plants
• Locate, stake out and seek approval from CSC for stone crushing plant.
• Locate plant site away from population centers,drinking water intakes, cultivated lands and sensitiveecosystem preferably at least 500m from settlementand habitation.
• Obtain permission from local stakeholders,Municipality, Rural Municipality, DCC as appropriate.
• Stone crushing equipment / cement batching will befitted with dust control devices and operated as perManufacturer’s Specification.
• Hotmix Plant will be in-built mechanisms for the absorption of gases.
Location of selected
Plant sites
ConstructionStage
Construction Contract
Contractor (seek approval from CSC for stone crushing plant. Obtain permission from local stakeholders,Municipality)
CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 11
Environmental Issues/Component
Remedial Measures / Actions Location Time Frame
Mitigation Cost (NRs.)
Responsibility
Implementation Supervision
• The plant will be operated during day time.
• Restore the site maintaining natural contours
10. Air Pollution • Stone crushing plant / Hotmix plant / Batching plant will be appropriately located at least 500m froms ettlement & habitation fitted with dust suppressionequipment.
• Road construction area will be maintained damp by periodical spray of water.
• Delivery vehicles will be covered.
• Mixing equipment will be well sealed and equipped as per existing standards.
• Provide temporary hoardings where required to minimize dust impact on locations of temples and other cultural sites.
• Provision of speed control measures in settlement and working areas to limit traffic speed.
• Air pollutant parameters (TSPM, PM10, SO, NOx,CO) will be monitored regularly during construction.
Project area, Construction sites, Crusher Plant sites Settlement areas (ChMM.)
Construction
6 times (Pre construction, construction and post construction)
Construction contract Included in BoQ (3.1.10 (3))
Contractor Through approved monitoring agency
CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 12
Environmental Issues/Component
Remedial Measures / Actions Location Time Frame
Mitigation Cost (NRs.)
Responsibility
Implementation Supervision
11. Water Pollution
• Hazardous materials will not be stored near surface waters sources
• Used lubricants and oils will be collected and recycled or disposed off site.
• Plastic sheeting will be placed under hazardous material storage area to collect and retain leaks and spills.
• Contaminated runoff from storage areas will be captured in ditches with an oil trap at the outlet.
• Contaminated and worn plastic sheeting will be packed into drums and disposed off site.
• Water Quality (PH, TSS, Oil and Grease) monitored regularly during construction.
Project area Stream crossings (NameM)
Construction 3 times during construction period
Construction Contract Included in BoQ (3.1.10 (4))
Contractor Through approved monitoring agency
CSC, PIU
Noise Pollution • Vehicles and equipment used will be fitted with silencer and maintained to keep noise at minimum levels.
• Workers will be provided with appropriate earmuffs/plugs specially at crusher site
• Cracks caused by vibration due to construction activities need to be monitored closely and alternative be sought where problem arises.
Project area,
Crusher plant site
Construction
Contractor Cost
Contractor CSC, PIU
C2 Biological
1. Vegetation and Forest Resources
• Identify and seek approval from CSC for clearance of trees/vegetation.
• Fuel wood will be banned for construction works.
• Wildlife hunting and poaching will be prohibited
Throughout road alignment
Construction
Construction Contract (BoQ item 3.1.1 (1 to 5))
Contractor CSC, PIU
Loss of forest area and trees
Compensatory plantation to be carried out Project area
PIU PIU/CFUG DFO, CSC
Semi-annual Environmental Safeguard Report April-June, 2018
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 13
Environmental Issues/Component
Remedial Measures / Actions Location Time Frame
Mitigation Cost (NRs.)
Responsibility
Implementation Supervision
C3 Socioeconomic and Cultural
2. Labour Camp Location and Management
• Camp will be barricaded
• Locate, peg and seek approval from CSC for labor camp sites.
• Camp will not be in the vicinity of landslide and flood plains.
• Provide and maintain proper drinking water, sewerage and waste disposal facilities at the camps.
• Ensure no wood is burnt by any worker on or off site.
• Camps will be provided free of cost, with electricity and regulator & adequate fuel supplies of LPG or Kerosene.
• Prohibit workforce from poaching wildlife and cutting trees.
• After use, sites will be cleared and restored to natural or stable conditions.
• Provide and maintain first aid medical facilities, toilet will be male and female separately.
• Sock pit for waste water, Pit for waste collection
• Camp will be established as per DoLIDAR OHS guidelines
Locations of selected labour camps
Construction
Construction Contract
Contractor ( seek approval from CSC for labor camp sites. Agreement with land owner)
CSC, PIU
3. Work Camp Location and Operation
• Locate, peg and seek approval from CSC for workcamp sites.
• Camp will not be located in the vicinity of landslide and flood plains.
• Provide and maintain proper drinking water,sewerage, waste disposal including first aid unit medical facilities at the camps.
• Used oil, lubricants will be recovered, re-used or removed form site.
• Explosives, oil, petrol, and grease will be managed according to provisions of this Management plan.
• After use, the site will be cleared and restored to near natural or stable conditions.
• Toilet will be male and female separately
• Sock pit for waste water
• Pit for waste collection
Locations selected for work camps (ChMM)
Construction
Construction contract
Contractor ( seek approval from CSC for labor camp sites. Agreement with land owner)
CSC, PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 14
Environmental Issues/Component
Remedial Measures / Actions Location Time Frame
Mitigation Cost (NRs.)
Responsibility
Implementation Supervision
• As per DoLIDAR OHS guidelines
4. Occupational Health and Safety
• Adequate lighting and safety signal devices be installed for work safety.
• Adequate warning signs and safety barriers will be provided for work safety.
• Protective clothing including helmets, masks, boots, gloves, ear plugs and goggles should be provided for workers safety.
• At every work place, a readily available first aid unit including an adequate supply of dressing materials will be provided for emergency preparedness in case of accidents.
• Maintain health care system at construction camps.
• Strict rules and regulation be maintained in the labour and work camp to avoid alcoholic and other bad habits.
• Provide and install all road signs as per design.
• As per DoLIDAR OHS guidelines
Project area
Construction
Construction
Contract
Contractor CSC, PIU
Post Construction Activities
1. Camp site restoration(Change of land use due to setting up of construction camp, Waste generation at the construction site, Generation of debris and silt)
• Camp site to be restored to its original condition
• Disposal waste at designated locations
• Cleaning of water channels
• Removal of debris and disposal approved locations
Campsite locations
Post-constructio
n
Contractor’s cost
Contractor CSC, PIU
2. Quarry site/Borrow area restoration
• Quarry site/Borrow area to be restored to its original condition as per the rehabilitation plan
• Restoration of top soil & disposal of debris/waste at designated locations
Designated Quarry/Borrow area
Post-constructio
n
Contractor’s cost
Contractor CSC/PIU
Semi-annual Environmental Safeguard Report April-June, 2018
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 15
Note: COx = Oxides of Carbon,. DCC = District Development Committee,PIU = Project Implementation Unit., RCIP = Rural Connectivity Improvement Project, NOx = Oxides of Nitrogen. ROW = Right of Way. CSC = Construction Supervision Consultant, SOx = Oxides of Sulfur, TSPM – Total Suspended Particulate Matter, RM= Rural Municipality
Semi-annual Environmental Safeguard Report
Contractor’s Site Specific Environmental Management Plan for Mudikuwa –Lunkhu Road, Parbat 16
2.4 ENVIRONMENTAL Monitoring The Contractor will submit regular environmental reports to the Employer as a requirement of the SEMP. Reports will comprehensively address all relevant aspects of environmental management. Report on Health and Safety Management, Environmental and Social Management, Emergency Procedures and Traffic Management, Summary of incident etc.
Semi-annual Environmental Safeguard Report April – June 2018
Rural Connectivity Improvement Project 17
Annex- I (Include Permit, Agreement with local, Layout plan, Drawing, Air/Water quality test report, Photographs etc.) (Permit, Agreement with local For Camp, Spoil disposal locations, Quarry and Borrow pit, Hot mix plant, Stockpile )
(Include: Photographs of all affected private and public structures with chainage, Land use )
Annex-II Map showing the locations of construction, camp sites, spoil disposal locations, quarry, stockpile, air and water monitoring sampling areas.
Annex-III List of tree to be removed from Mudikuwa-Lunkhu Road
Name of Forest and Chainage
Name of Plant Species
No of Tree No. of poles Remarks