environmental compliance audit report and corrective ... · project duration six weeks from signing...

66
Environmental Compliance Audit Report and Corrective Action Plan Project Number: 47381-005 December 2019 SRI: Mahaweli Water Security Investment Program Upper Elahera Canal Project (Part 2 of 4) Prepared by Ministry of Mahaweli Development and Environment for Democratic Socialist Republic of Sri Lanka and the Asian Development Bank. This environmental compliance audit report and corrective action plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Upload: others

Post on 12-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Environmental Compliance Audit Report and Corrective Action Plan

Project Number: 47381-005 December 2019

SRI: Mahaweli Water Security Investment Program

Upper Elahera Canal Project (Part 2 of 4)

Prepared by Ministry of Mahaweli Development and Environment for Democratic Socialist Republic of Sri Lanka and the Asian Development Bank. This environmental compliance audit report and corrective action plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Annex 3

Page 3: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 4: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 5: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 6: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 7: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 8: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Annex 4

Page 9: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 10: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 11: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Annex 5

Page 12: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 13: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 14: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Annex 6

Page 15: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 16: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 17: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 18: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 19: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Annex 7

Page 20: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 21: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 22: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Annex 8

Page 23: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 24: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review
Page 25: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Annex 9

Page 26: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

® 5 £ > £ )t@ d o ^ d 2 5 S § 2 5 3 2 » D e f3 @ csM 2 5 3 0 i© e3 O S 3 3 2 5 3l d*iT6^6i51 r£ iru uiT|j/<slTUL|<&<9i.TSiJT (y )d5G & >L_({j)d?> ^Il Ll u d A

uIMS M ah aw e li W ate r S ecu rity In v e s tm en t P ro g ram

«s e ao 0 ^ o )2 5 ) enj a6 e ad ep < § b s5 c so o c& cs 9i£>s 3c >k >25$ 2 5 i,e ,< § )2 5 3 3 2 5 3 d -g 6 ) d ’z szo c s

io a r ifc ii6 v J l ^)l Sq 5I0^ iD fr ig iii i) ev rr)n 3 m _ 6 U ^ n o m o ffav g jili ( ip * iT 6 ijH o g > g jj« u 'i i i t5 Jo fliD 8» < a i

M in is try o f M ah aw e li D ev e lo p m en t & E n v iro n m en t P ro g ram M an ag em en t U n i t .MWSI P

@ 2 5 3 3 . 4 9 3 1 /1 , 9 . 1 3 . d cS O @ 3 0 2 5 3 , @ 2 5 3 3 6 ® 1 0 . N o . 4 9 3 1 /1 , T . B . Jay ah M aw a th a .£§)6U.493 1/1. (fl. J). G lfom r u)(r«i®6n® Q&rr(mu)Li 10.

? l?P ro g ram D ire c to r : 0 1 1 2 6 7 5 8 1 1 C o n su lta n t: 0 1 1 2 ^ 5 G en e ra l O ffic e : 0 1 1 2 6 7 5 8 1 0 (S )O ff ic e F ax : 0 1 1 2 6 7 5 8 1 0 @ - p d ad b p ro je c t@ g m a il.c o m

® @ G 5 ep o 2 S C 3

6 I6 tfT g l @ 6 0

My No

©@© e fowa

a-togj @6o

Your No

MMDE/MWSIP/PMU/ENV/

UECP-NWPCP/Gen-Vol 2

25th February 2019

Team Leader,

PMDSC

Recommendations of Forest Department on

Clearing a Forest Land Beyond the Approved Trace at Kambara under ICB 2B of UECP

This is further to my even number letters dated 05/02/2019 on the same subject.

On the PMU request from the International Union for Conservation of Nature (IUCN), as per the

instructions of the Forest Department letter No. FD/EC&M/ID/UEC/2012(Vol III) dated 01/02/2019,

the IUCN submitted a proposal together with cost estimate totaling to Rs. 1,466,080.00 on

14/02/2019.

The PMU send the comments in consultation with the PMDSC (Environment specialist) and the Forest

Department (Conservator of Forests-EC&M) and accordingly the IUCN has submitted the revised

proposal addressing comments with cost estimate totaling to Rs. 1,258,880.00 on 25/02/2019

(Attached herewith).

Please instruct the Contractor (Sinohydro) that the cost of IUCN study (Rs. 1,258,880.00) will be

deducted from their next payment as per the aforementioned instructions of the FD as well as agreed

by Sinohydro at meetings held by PD-PMU and Secretary/ MMDE respectively on 03/01/2019 and

14/01/2019. ___ MWSIP - PMDSC ___

49X T.D in ynh Mawatha. Colombo 10

Registered I..coming By 0*"

riLjmzSeen: iotlnf

2 5 FEB 2019 ___Action By: j M"l^ " A

-------- 1 uug-

Date:ftgTlC R. Neil Bandara

frogram Director

/lahaweli Water Security Investment ProgramCopies to: ____~pTimary File Location^ l& > • V'

[Copy to Files: I

C:

1. Secretary, Ministry of Mahaweli Development & . Environment

2. Conservator of Forests (EC&M)

3. Project Director, PIU-UECP - Please coordinate with RE-PMDSC to expedite the task.

For your information please

P IU O ffic e : (U E C P )

U p p e r E lah e ra C an a l P ro je c t A d d re ss - U E C P ro je c t O ffic e

M ah aw e li A u th o rity o f S ri L an k a , M ad a tu g am a .

T e le p h o n e N o . 0 2 5 -3 2 4 8 6 0 4 F ax N o .

e -m a il -d a rm a s iri_ 2 00 0 @ y ah o o .c o .uk

P IU O ffic e : (NWPCP)N o rth W este rn P rov in ce C an a l P ro je c t A d d re ss - I r r ig a tio n D ep a rtm en t

P .O . B o x . 4 4 , K u ru n eg a la .

T e lep h o n e N o . 0 3 7 -3 9 7 0 7 8 3 F ax N o .

e -m ail - ra ja so k a3 @ y ah o o .c o m

P IU O ffic e : (M L B C R P )

M in ip e L B C an a l R eh ab ilita tio n P ro jec t A d d re ss - D IE O ffic e

P D O ffic e : (ISEWPIP)Im p rov in g S y s tem E ffic ie n cy & W ate r P ro d u c tiv ity Im p ro v em en t P ro je c t A d d re ss -1 1 , Jaw a tta R o ad ,

C o lo m bo 0 5 .

T e le p h o n e N o . 0 7 1 8 -1 0 1 6 2 8 F ax N o .

e -m ail -d e a lw is .la lith@ y ah o o .co m

Irrig a tio n D ep a rtm en t,H a sa la k a .

T e le p h o n e N o . 0 5 5 -22 5 7 2 0 5 / 0 7 1 8 1 9 9 5 1 9 0 5 5 -2 2 57 2 0 5

e -m ail -m cd iw ak a .su san th a@ y ah o o .c o m

025-3248604 037-2222532 F ax N o . 0 1 1 2 -5 5 4 0 6 3

Page 27: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

^KJCN

Proposal for Ecological Assessment of a Forest Land in Beligoda

Forest reserve, Naula, Matale under the Mahaweli Water Security

Investment Program

Preamble

The Moragahakanda Agricultural Development Project (MADP) involves harvesting water

from Amban Gangs, one of the main tributaries of the Mahaweli Ganga which flows through

the knuckles mountain range, by constructing a very large reservoir. Furthermore, this project

resulted in the establishment of new settlements along the right and left banks and associated

infrastructure. As part of the investment, Kaluganga reservoir was also being built damming

Kalu Ganga to get excess water to Moragahakanda reservoir.

As part of Upper Elehera Canal Project under the Mahaweli Water Security Investment

Program (MWSIP), there is a construction of Kaluganga-Moragahakanda Transfer Canal

(KMTC). The contractor commissioned for the task - Sinohydro has cleared patch of forest

outside of the approved area during the construction of access road to the proposed outlet

portal of KMTC. Followed by immediate responsive actions, the MWSIP has requested (the

through the letter “MMDE/MWSIP/PMU/ENV/UECP /Gen-Vol 2” dated 5'h February 2019)

IUCN to undertake an assessment of ecological damage to assess the cost of damage related

to said unauthorized forest clearance and provide a restoration plan for the area.

After a preliminary site visit undertaken by IUCN, the following proposal is presented for

MWSIP’s consideration.

Objectives

• To assess the present biodiversity around the cleared area.

• To document the threats pertaining with above forest clearances to ecosystem.

• To identify the short and long term measures to ecologically improve the degraded

land.

• To calculate the cost of damage to the ecosystem.

• To prepare a restoration plan including above findings.

Project duration

Six weeks from signing the contract between MWSIP and IUCN, except the time taken by

MWSIP for review draft report.

Project activities

Literature survey to document the previous biodiversity related data around the site.

Five day field assessment will be conducted and during the field following sub-activates will

be carried out.

1. Conduct a rapid biodiversity assessment of the site in order to ascertain species

richness of flora and fauna, and identify endemic or threatened species found in the

area.

2. Identify the ecosystem services provided by the ecosystem.

l

Page 28: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

3. Identify the threats pertaining due to forest clearance to sustainability of the ecosystem.

4. Identify the recommendations related to sustainable restoration of the cleared area.

5. Finally prepare a restoration plan including ecological value, cost of damage, and

restoration methodology.

Methodology

Review of any existing published information and maps on the study areas, and gathering of

baseline information.

Study Area

10m either side of the cleared road will be sampled to understand the biodiversity of the

cleared forest stretch (approximately 0.3ha). Four key separate areas to be covered by the

study are (see map 01); (i) Left bank of Kambarawa stream, where road was made clearing

vegetation, (ii) Right bank of Kambarawa stream, where some trees & shrubs were cleared

making a foot path, (iii) Causeway across part of Kambarawa stream by placing boulders and

(iv) Island after the causeway at the bifurcation of Kambarawa stream.

A: N

\i

\

\

I'mI3 iImIv .v i.'I i

' ill:.: t '| II

}{

//.I ...»

.'ll. .•Jl Ml

lil 4 l l! l! iv !

1 1 .. t :< ,, ;-i IIi

*;

Ii

|: ; |h > .n vr .

\ Lly.,

Map 01. Newly cleared area subjected to Noncompliance incident (Marked in red and

green) (source: MWSIP).;

5

F lo ra su rvey m ethodo logy

Species/population (higher plants) parameters of diverse vegetation types in the given forest

areas will be studied using standard scientific techniques, with appropriate modifications to

suit field conditions. The surveys will concentrate on documenting the plant species in and

either side of the cleared stretch. The natural vegetation types will be surveyed under two

major categories - tree dominated vegetation types / degraded forests; and non-forest

vegetation types such as shrub lands, and grasslands, dominated by shrubs and herbaceous

I

2

Page 29: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

life forms). Forest vegetation will be sampled using 2 x 50 m belt transect sampling technique

with appropriate dimensions as recommended in standard methods.

Fauna survey methodology

All groups of vertebrates (freshwater fish, amphibians, reptiles, birds and mammals) and

selected invertebrate taxa (butterflies, dragonflies, land snails and aquatic snails) will be

identified, and documented. The same floral sampling belt transects will be used to sample

different groups of fauna in the project area (Table 1). Two to three night visits are also planned

along the cleared road using flashlights, depending on the ground situation in the area. All

efforts will be made to document the animals in a non-destructive manner.

Table 1. Summary of sampling techniques for fauna

mm■ .): -i «io«

Fish Direct/indirect Bank counts; hand nets; communication with

surrounding villagers

Visual encounter survey within the transect; night

observation using touch lights, if possibleAmphibians Direct

Visual encounter survey within the transect;

communication with surrounding villagers

Reptiles Direct

Point transects (visual and auditory observations)Direct and indirectBirds

Mammals Direct and indirect Belt transects (including presence indicated by

tracks, fecal matter, feeding signs, carnivore scat

analysis and calls); night sampling, if possible;

communication with surrounding villagers

Visual encounter survey within the transectButterflies and

dragonfliesDirect

Visual encounter survey within the transectLand and

aquatic snails

Direct

Identification of taxa

The species of plants and animals will be identified and classified using the latest standard

published guides and keys available in Sri Lanka. In addition, the specimens deposited in the

National Herbarium and the National Museum will be referred to for species authentication.

Some of the key references that will be used to identify flora and fauna are given below in

Tables 2 and 3. Threat statuses of species will be obtained from the 2012 National Red List

of Sri Lanka.

3

Page 30: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Table 2. Sources used for the identification and classification of flora

Subject Sourcej

,denhficatk,n

i

BDS, MMD&E, 2016Invasive species

io.V -

. _____

my

\;■

iSi

Table 3. Sources used for the identification and classification of fauna

Purpose Group Reference

mm: :-YmiNaggs and Raheem (2000) : .

mummiiiiiPeiris etal., (2014)Aquatic

snail

Bedjanic et al, (2007) __________liftm

van de Poorten and van der Poorten, (2018)Butterflies

i'llr. Y4

ill .v

1 ■K

Manamendra-arachchi & Pethiyagoda (2006)AmphibiansmWc

-r-

>l

;;m ii & 2 i

m@m; Harrison (1999); Kotagama & Ratnavira (2010)Birds*

tS k Mammals

-i. - ■ ■ ■

Kotagama & Gbdnatilake (2017) ..............

Fauna classification

and threatened status

All of the

above

MoE, 2012

4

Page 31: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Identification of Ecosystems

Fauna, flora and other physical characteristic will be used to identify the ecosystems of the

area. Wildlife Management Plan of NWPCP will be used as a key document for identify

ecosystem types while National Biodiversity Strategic Action Plan 2016-2022 will be used for

ecosystem nomenclature.

Ecological damage calculation

Given the limited time for assessment, value of ecological damage of the unauthorized forest

clearance will be assessed using benefit transfer methods where previously conducted

primary valuation studies elsewhere will be used to derive the value of the damage in the given

situation. This is the internationally accepted way of assessing value of environment when

the baseline information, resources or time becomes a constraint while a decision is needed

urgently. As given in the project team services of Environmental Economists including one

International expert is built in for this component.

Expected outputs

A restoration plan containing the following:

■ Biodiversity (ecosystem and species richness, endemicity, threatened status);

■ Details of the ecosystem services provided by the project area;

■ Threats identify due to forest clearance

■ Cost of damage to the ecosystem

■ Recommendations and mitigations to restoration,of cleared site

■ Restoration plan with budget;

This work is expected to deliver within 6 weeks from the date of signing the agreement

between MWSIP and IUCN. It is estimated 2 days for review the draft report by MWSIP any

additional time taken by MWSIP for review will be counted outside of the said 6 weeks as it is

beyond IUCN control,

Activity plan

Description Month 1 Month 2

61 2 3 4 5

week week weekweek week week

1 Literature survey

2 Rapid field assessment

3 Data analysis

Report preparation4

Submission of Draft report5

6 Submission of Final report

5

Page 32: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Proposed budget

Financial Proposal for Ecological Assessment of a Forest Land in Beliaoda Forestreserve. Naula. Matale

H nm (I

Total Personnel Cost 867,500

Key Experts

Prof.Devaka Weerakoon - Biodiversity

expert_________________________25,000Day 6 1 5 0 ,0 0 0

Dr.Shamen Vidanage - Environment economist

25,000Day 8 200,000

Mr.Sampath Goonatilake - Field team

leader/ Fauna ecologist1 0 1 7 ,5 0 0 1 7 5 ,0 0 0Day

Mr.Naalin Perera - Fauna Ecologist Day 1 0 1 2 ,5 0 0 1 2 5 ,0 0 0

Mr.Sarath Ekanayake - Plant Ecologist 1 0 80,000Day 8,000

Mr.Rohana Jayasekara - Fauna

Ecologist__________________Day 5 5,000 25,000

Mr.Ananda Lai Peiris - Fauna and Flora

AssistantDay 5 4,500 22,500

Ms.Darshani Wijesinghe - GIS Expert 1 0 ,0 0 0 20,000Day 2

Support Staff

Technical Assistance Day 1 0 5,000 50,000

Secretarial Support Day 2 1 0 ,0 0 0 20,000

Other Expenses 256,500

T ravel KM 6 0 1 ,7 0 0 1 0 2 ,0 0 0

Perdiem 129,500Day 3,500 37

Field Consumables Lump 1 1 0 ,0 0 0 1 0 ,0 0 0

Printing, Stationery and communication Lump 1 1 5 ,0 0 0 1 5 ,0 0 0

Sub Total 1,124,000

IUCN Management Fee 12% 134,880

All Inclusive Grand Total 1,258,880

Payment Schedule

1. 40% advance payment on signing the contract

2. 40% once the draft report has submitted

3. Final 20% once the final report has submitted

; 6

Page 33: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Project partner

• Mahaweli Water Security Investment Program (MWSIP)

• Forest Department

Requirements from Mahaweli Water Security Investment Program

■ Obtaining permission from Department of Wildlife Conservation and Forest

Department to carried out the survey

• Support from DWC and FD field officers with thunders and firearms for protection (day

and night sampling1)

Project team

Three faunal experts will be gathered the faunal diversity, habitats and ecology of the species

and flora expert will be gathered the information regarding flora species diversity, ecosystem

damage and restoration plan. Field assistant will be support to both faunal and floral sampling.

The data collected by the field team will be used by Biodiversity expert and Environment

economist to calculate the ecological damage and cost of damage respectively.

Task (Expertise)Field staff Qualification

i«!HlDr. Shamen Vidanage2 Environment economistPhD

ISBaisisi

4 Mr. Sarath Ekanayake MPhil Plant ecologist

Ǥf

■——SpnniEllm

i

mi

Mmasm7mMr. Rohana Jayasekera6 MSc Fauna ecologist (Land snails and

Herpetofauna)_______________

SailMB—Mr. Sampath Bandara8 BSc Technical Assistance

19 1Forest Officer from llukkumbura1 0

Wmmmmmmm Field assislanl_________________

A.R. Premasiri12 Driver

1 According to situation night sampling will be under take with the supervision of relevant authorities.

7

Page 34: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

References

1. Ashton, P.M., Gunatilleke, C.V.S., Zoyza.N., Dassanayake.M.D., Gunatilleke, I.A.U.N.,

& Wijesundara, S. (1997). Afield guide to the common Trees and Shrubs of Sri Lanka.

WHT Publications & Pvt, Sri Lanka.

2. Bedjanic, M., Conniff, K. and Wijeyeratne, G. de S. (2007) A pho tog raph ic G u ide to

the D ragon flies o f S ri Lanka . Jetwing Eco Holidays, Colombo, Sri Lanka. 248pp.

3. Dassanayake, M.D., & Clayton, W.D. (1996 - 2000). A revised hand book to the Flora

of Ceylon, X - XIV, Oxford and IBH Publishing Co., New Delhi.

4. Dassanayake, M.D., & Fosberg, F.R. (1980 -1991). A revised hand book to the Flora

of Ceylon, I - VII, Amerind Publishing Co., New Delhi.

5. Dassanayake, M.D., Fosberg, F.R., & Clayton, W.D. (1994-1995). A revised hand book

to the Flora of Ceylon, VIII- IX, Amerind Publishing Co., New Delhi.

6. Department for Environment, Food and Rural Affairs, (2007) An introductory guide to

valuing ecosystem services, London. 68pp.

7. Freeman III, A. M., Herriges, J., & King, C. (2014). The M easu rem en t o f Env ironm en ta l

and R esou rce Va lues , Theory and M ethods . Oxon: RFF Press.

8. Goonatilake, S. de A. (2007) F reshw ate r fishes o f S ri Lanka. Biodiversity Secretary of

Ministry of Environment and Natural Recourses. (S inha la book). 133pp.

9. Harrison, J. (1999). Afield guide to the Birds of Sri Lanka. Oxford University Press Inc.,

New York.219pp.

10. IUCN and MMD&E (2017). The W ild life M anagem en t P lan , in c lud ing H um an-

E lephan t C on flic t M anagem en t and M itiga tion , fo r the N orth W este rn P rov ince C ana l

P ro je c t (N W PC P ). Colombo: IUCN and MMD&E. xxviii+348 pp.

11. Kotagama, S.W. and Ratnavira, G. (2010) An illu s tra ted gu ide to the b irds o f S ri Lanka .

Field Ornithology Group, Colombo, xviii + 357 pp.

12. Kotagama, S. and S de A Goonatilake (2017) P ic to ria l Pocke t G u ide to the M am m als

o f S ri Lanka (3 rd rev ised & expanded ). Field ornithology Group of Sri Lanka. 154pp.

13. Manamendra-arachchi K & R Pethiyagoda (2006) S ri Lankave U baya jeeveen . Wildlife

Heritage Trust (Pvt) Limited, Colombo, Sri Lanka. (Sinhala text). 400pp.

14. Ministry of Environment (MOE) (2012) The National Red List 2012 of Sri Lanka;

Conservation Status of the Fauna and Flora. Ministry of Environment, Colombo, Sri

Lanka. Biodiversity Secretariat, Ministry of Mahaweli Development and Environment,

xxi + 284 pp.

15. MoMD&E (2016). National Biodiversity Strategic Action Plan 2016-2022. Colombo, Sri

Lanka:

16. Naggs, F. and Raheem, D. (2000) Land sna il d ive rs ity in S ri Lanka . The Natural History

Museum, London. 214 pp.

17. Peiris, A. Naggs, F., Preece, R.C., Taylor, H., and White T.S.,(2014) An Illu s tra ted

gu ide to the F reshw a te r M ollusca o f S ri Lanka . The Natural History Museum, London.

8 pp.

8

Page 35: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

18. SomaWeera, R. (2006) S ri Lankave Sarpayan . Wildlife Heritage Trust (Private) Company Limited, Colombo, Sri Lanka. (Sinhala text). 297pp.

19. SomaWeera, R. and SomaWeera, N. (2009) L iza rds o f S ri Lanka , A co lou r gu ide w ith

F ie ld Keys . Andreas S. Brahm, Heddernheimer Landstre. Germany. 303pp.

20. TEEB, (2013). The Economics of Ecosystems and Biodiversity: Guidence Manual for TEEB Country Studies Version 1.0. web publication: UNEP.

21. van der Poorten, N. & van der Poorten, G. (2018). Field Guide to the Butterflies of Sri Lanka. Fauna of Sri Lanka. London Books. 250pp.

9

Page 36: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

CVs of the key team members

CURRICULUM VITAE

Biodiversity Expert

Devaka Kirthi Weerakoon

IUCN, International Union for Conservation of Nature

26lh February 1963

Sri Lanka

• Illinois State University, USA, 1991-1995, Ph.D. Biological Sciences• Illinois State University, USA, 1988-1990, M.Sc. Biological Sciences

• University of Colombo, Sri Lanka, 1982-1985, B.Sc. Biological Sciences ’

Position Title and No

Name of Expert

Name of Firm

Date of Birth

Nationality

• Education

• Employment Record

Activities PerformedPeriod Employing Agency, Title and

ReferenceCountry

05/2015 ■ 02/2017

(sabbatica

I leave)

IUCN Sri LankaCoordinator Ecosystems & Biodiversity

DrAnanda Mallawatantri Ananda.mallawatantri @iucn.org

Overseeing the research work conducted by

the ecosystems and biodiversity group, report preparation, representing IUCN at national and international level meetings_________

S ri

Lanka

2009 to University of Colombo

Professor in Zoology

Prof D.D. Wickramasinghe

[email protected]

Conducting lectures and laboratory classes, curriculum design and development, providing

academic advise to students, student counseling, setting and marking examination

papers, and other administrative duties

Sridate Lanka

04/2008 - 11/2009

(sabbatica

I leave)

IUCN, Asia Regional Species and

Biodiversity Conservation Programme

Biodiversity Consultant Mr Ali Raza [email protected]______________

Providing technical backstopping to lUCN's

biodiversity conservation programmes in the

Asia region

S ri

Lanka

09/1995 - 10/2009

Sri Conducting lectures and laboratory classes, curriculum design and development, providing

academic advise to students, student counseling, setting and marking examination

papers, and other administrative duties

University of ColomboSenior LecturerProf D.D. Wickramasinghe

Lanka

08/1986 - 09/1995

Sri Conducting lectures and laboratory classesUniversity of Colombo

Probationary Lecturer Prof D.D. Wickramasinghe

Lanka

08/1988 - 09/1995

UnitedStates

Conducting research towards a postgraduate

degreeIllinois State University

Fullbright Fellow (08/88 -12/90) Teaching Assistant (01/91 - 08/93) American Heart Fellow (08/93-08/95) ProfTak [email protected]___________

Membership in Professional Associations

• Institute of Biology

• Sri Lanka Association for the Advancement of Science

Adequacy for the AssignmentReference to Prior Work or Capabilities that Best Illustrates Capability to Handle the Assigned TasksConsultancies undertook1. Team Leader in preparation of NBSAP 2016-2022 in 2016.2. Team Leader in developing an ecotourism plan for Pottuvil and Panama region in the Ampara district with

special emphasis on Urani, Kottukal and Panama lagoons 2016_____________________________

10

Page 37: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

3. Deputy Team Leader in preparing Wildlife Management Plan for Yan Oya Reservoir and Irrigation Project in

2015.4. Deputy Team Leader in preparing Wildlife Management Plan for Upper Elahera Canal Project, 2017.5. Deputy Team Leader in preparing Wildlife Management Plan for North Western Province Canal Project, 2017.6. Deputy Team Leader and 8iodiversity Expert in delivering capacity building and preparation of Training

Manual for Biodiversity Integrated Planning at Landscape Scale for the Environmental Sensitive Area Project of the MMDE, with GEF UNDP funding delivered in 2016.

7. Deputy Team leader in preparation and implementation of the Biodiversity Action Plan for Moragahakanda

Agricultural Development Project (MADP) and the Kalu Ganga Reservoir and Agricultural Extension Project (KR&AEP) in 2014

8. Ecological Assessment of the Conflict Affected Region Emergency Project; Employer: Central Engineering

Consultancy Bureau / Ministry of Provincial Council; Position/ Duration: Ecologist (2010/11 - 2 man months); Description of duties: Assessment of the present status of the environment affected by the project, identification of environmental impacts of the project and proposed alternatives; recommend strategies for mitigation of impacts and development of an environmental monitoring plan for the project

9. Detailed biodiversity study on abundance and biological Patterns/ wildlife in the Moragahakanda and

Kaluganga; Employer: Environmental Management Limited/ Mahaweli River Basin Authority; Position/ Duration: Terrestrial Ecologist (2010 - 6 man months); Description of duties: Preparing an inventory of the

fauna present in the project area, identification of critical species and ecosystems, identification and

documentation of current level of human dependency and major threats to the species and habitats within the

river basin and assist the River Basin Authority to prepare a combined wildlife management plan for the Kalu

Ganga and Morgahakanda development project.10. Supplementary survey on environmental and social consideration for the preparatory survey for the

Moragahakanda Development project; Employer: Environmental Management Limited/ Mahaweli River Basin

Authority; Position/ Duration: Terrestrial Ecologist (2010 - 2 man months); Description of duties: Development of an environmental management and an environmental monitoring plan for the Morgahakanda development project and conduct a stakeholder survey on possible wildlife management issues that may arise due to the

implementation of the project,11. Updating the List of Nationally Threatened Fauna of Sri Lanka; Employer: Biodiversity Secretarial; Position/

Duration: Chief Technical Advisor (Fauna) (2010/2011 - 3 man months); Description of duties: Providing

technical support to the Biodiversity Secretariat on reviewing and compilation of data available on Sri Lankan

fauna, conducting workshops for taxonomic experts to develop the list of Nationally threatened fauna of Sri Lanka, compilation of list of Nationally threatened faunal of Sri Lanka

12. Development of an environmental and. social management framework for the Sri Lanka sustainable tourism

development project; Employer: Infotechs Pvt. Ltd./ Ceylon Tourist Board; Position/ Duration: Team Leader/ Environmentalist (2009 - 1 man month); Description of duties: Review environmental and sociological impact of tourism and develop an environmental and social management strategy and guidelines for screening future

tourism development projects in Sri Lanka13. Project on Strengthening Capacity to Control the Introduction and Spread of Invasive Alien Species in Sri

Lanka; Employer: Biodiversity Secretariat/ GEF/ UNDP; Position/ Duration: Communication Specialist (2009

- 4 man months); Description of duties: Development of an communication strategy and communication tools

for the management of Alien Invasive Species in Sri Lanka14. Protected area Management and Wild Life Conservation Project; Employer: Greentech Limited/ Department

of Wildlife Conservation; Position/ Duration: Ornithologist (2006/8 - 20 man months); Description of duties: Conducting field surveys to document the biological diversity and distribution patterns of birds in Wasgomuwa, Ritigala, Udawalawe, Minneriya, Horton Plains, Peak wilderness and Bundala; establish sound repeatable

field sampling methodologies that are appropriate and topical for local conditions; assist Department of Wildlife

Conservation to prepare site conservation plans for these sites15. Breeding birds survey of the Yala East (Kumana) National park; Employer: Field Ornithology Group of Sri

Lanka/ University of Colombo; Position/ Duration: Ecologist/ Team leader (2005 -1 man month); Description

of duties: Inventorying the wetland birds present in the various aquatic habitats in the Yala East National park

and monitoring the breeding birds found in the Kumana lagoon16. Assessment of the Impact of Tsunami on the Coastal Protected Areas with special reference to Ruhuna and

Yala East National Parks; Employer: Department of Wildlife Conservation; Position/ Duration: Ecologist (2005

-1 man month); Description of duties: Documenting the impact of Tsunami on the coastal ecosystems

ll

Page 38: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

present within the protected areas managed by the Department of Wildlife Conservation and providing

recommendations for assisting the recovery of coastal ecosystems17. Buffer zone community development & habitat enrichment of Lunugamvehera National Park through

development of water resources of Menik Ganga; Employer: Central Engineering and Consultancy Bureau/ Irrigation Department; Position/ Duration: Ecologist (2003/4 ■ 1 man month); Description of duties: Assessment of the present status of the environment affected by the project, identification of environmental impacts of the

project and proposed alternatives; recommend strategies for mitigation of impacts and development of an

environmental monitoring plan for the project18. Kala Oya River Basin - survey of biodiversity and wetland issues and options for their sustainable

management; Employer: Environmental Management Limited/ Mahaweli River Basin Authority; Position/ Duration:Terrestrial Ecologist (2003/4 - 6 man months); Description of duties:Preparing an inventory of the

fauna present in the river basin, identification of critical species and ecosystems, identification and

documentation of current level of human dependency and major threats to the species and habitats within the

river basin and assist the River Basin Authority to prepare a management plan for Kala Oya River Basin19. Protected area Management and Wild Life Conservation Project; Employer: Infotechs IDEAS Private Limited/

Department of Wildlife Conservation; Position/ Duration:Ecologist (2003 to 2007 - 12 man months); Description of duties: Assist Department of Wildlife Conservation to prepare and implement protected area

management plans, development of research agenda and supervision of research conducted by and for the

Department of Wildlife Conservation, Review of current status of threatened species and assist species

recovery planning process of the Biodiversity Secretariat, monitoring and evaluation of habitat mapping and

biodiversity inventory preparation in selected protected areas, assist to carry out a gap analysis and

development of a protected area portfolio, provide training to members of the Department of Wildlife

Conservation on basic skills needed for Wildlife Conservation and Management20. Compilation of the national list of threatened fauna of Sri Lanka; Employer: IUCN Sri Lanka; Position/ Duration:

Team Leader (1997-12 man months); Description of duties: Preparation of national criteria for determination

of threatened species with stakeholder participation; literature review and compilation of national list of threatened fauna and adoption of the list through a stakeholder participatory process________________

Languages:SpeakingExce llen t

E xce llen t

WritingExce llen t

E xce llen t

Languages :

EnglishS inha la

R ead ing

Exce llen t

E xce llen t

Certification:

I, the undersigned, certify that to the best of my knowledge and belief, this CV correctly describes myself, my

qualifications and my experience. I understand that any willful misstatement described herein may lead to my

disqualification or dismissal, if engaged.Date.

[Signature of staff member]

Date 22nd February, 2019

[Signature of authorized representative of the client]Full name of authorized representative: Shamen Vidanage

1 2

Page 39: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

CURRICULUM VITAE (CV)

Proposed Position

Name of Expert:

Name of Firm

Environment Economist

Dr Shamen Vidanage

IUCN, International Union for Conservation of Nature

19 October, 1965

Sri Lankan '

Date of Birth:

Nationality

Education:

■ PhD in Economics (Natural Resource and Environmental Economics) at University of Colombo, Sri Lanka,

1st February 2018

■ M.A (Economics), University of Colombo, Sri Lanka, 1st December 1999.

■ M.Sc (Agricultural Economics with Environmental Economics major), Postgraduate Institute of

Agriculture, University of Peradeniya, Sri Lanka 27th January 1996. GPA 3.76

■ B.Sc (Agriculture) Honours • Second Class Upper Division, specialized in Agricultural Economics,

University of Peradeniya, Sri Lanka, 1sl September 1992.

Other related training:

Received short training on Environmental and Natural Resource Economics at various International

Universities including a 5 week programme at Harvard Institute for International Development (HIID),

Harvard University, USA on Environmental Economics and Policy Analysis - Analytical Methods

Track, 10th June - 12th July 1996.

Economic tools for Ecosystem conservation conducted by Conservation Strategy Fund (CSF) in

collaboration with University of California, in California USA, 16th to 29th June 2002.

Environmental and Natural Resource Economics conducted by South Asia Network for Development

and Environmental Economics (SANDEE) in Bangladesh, 29th April - 16th May 2002.

Capacity building on Environmental Economics Conducted by University of Bath, UK in collaboration

with Ministry of Environment, Colombo, Sri Lanka, 19th - 24th April 2000,

Regional Training Course on Environmental and Resource Economics conducted by Economy and

Environment Programme for South East Asia (EEPSEA), University of Philippines, Los Banos the

Philippines, 10th June - 3rd July 1998.

international exposure on Forest Landscape Restoration (FLR) and Restoration Opportunities

Assessment Methodology (ROAM) by taking part in, IUCN Regional FLR Consultation, Delhi 29th &

30th August, 2017 and Asia ROAM Learning and Sharing workshop, Bangkok, 15th & 16th March,

2018.

Diploma in River Basin Management, Online course conducted by CEDDET Foundation, Spain with

ADB and Network of Asian River Basin Organisations (NARBO), during 20th January to 6th April

2014 (equivalent to 120 teaching hours),

Strategic Environmental Assessment, organised by World Bank, EEPSEA and SEARCA, Los Banos,

Philippines, 5th-8th July 1998.

Strategic Environmental Assessment - International Experience and Perspectives in Strategic

Environmental Assessment (SEA), Prague, Czech Republic, 26th - 30th September 2005.

Employment record relevant to the assignment:

Period Employing organization and your title/position. Contact infor for

references

Country Summary of activities performed

• relevant to the Assignment

13

Page 40: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Sri Lanka Coordinating the overall programme

development, portfolio management covering thematic programmes.

IUCN, International Union for Conservation of Nature, Sri Lanka

officeCurrently the Pogramme Coordinator, Held various positions at IUCN

including a three year stint as the Acting

Country Representative

2002 to date

For references:DrAnanda Mallawatantri Country Representative, IUCN

Sri Lanka53, Horton Place, Colombo 07

[email protected]

Sri Lanka Responsibilities included, conducting

research in socio-economic aspects

of fisheries and aquatic resources

and overall co-ordination of the

research in socio-economic and

market research in the area of fisheries and aquatic resources at NARA.

September

1 9 9 8 -

February2002

National Aquatic Resources Research

and Development Agency (NARA) Head / Economist, Socio-economic

and Market Research Division

During my stay at NRM Division of CEA fwww.cea.lk1.1 managed the

EIA process related to following

subjects as the officer in charge (at different time intervals); Hotels and

Tourism, Agriculture, Minerals and

Mining, Transport and Highways

Development (includes 1st express

highway of Sri Lanka). The work

includes the entire range of EIA

process administration (drafting

Terms of Reference and technical evaluation of Environmental Impact Assessment (EIA) studies, evaluation

of reports related to cost benefit analysis of environmental impacts. Finally), I was handling energy sector projects (includes 1st coal powered

thermal power plant in Sri Lanka).

Central Environmental Authority

Assistant Director, Natural Resources

Management (NRM) Division,

Sri LankaFebruary

1995 to

September 1998

i

Department of Agricultural Economics

and Extension, Faculty of Agriculture

Assistant Lecturer (Temporary)

Sri Lanka Assisting senior staff of the faculty in

teaching Agricultural Economics to

undergraduates in B.Sc (Agriculture) University of Peradeniya________

February

1993 -

March 1994

Institute of Applied Economics

Part time Researcher / EconomistSri Lanka This work included environmental

economic valuation of development projects, data analysis using

computer software, and report writing

and agricultural project analysis.

October1 9 9 2 -November1 9 9 3

1 4

Page 41: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Membership in Professional Associations and Publications:

• Member Association of Environmental and Resource Economists, USA (2019)

• Life member Sri Lanka Association for Advancement of Science (SLAAS), Committee member and the Rapporteur for the Section F for the current year (2019)

■ Life member Sri Lanka Agricultural Economics Association

■ Life member Sri Lanka Economics Association

■ Member of the South Asia Network for Development and Environmental Economics

(SANDEE)

■ Member Institute of Environmental Professionals in Sri Lanka, previously served as a council

member

■ Member of the IUCN Commission on Environmental Economics and Social PolicyLanguages:

Languages: English

S inha la ■

SpeakingExce llen t

E xce llen t

ReadingExce llen t

E xce llen t

WritingExce llen t

E xce llen t

Adequacy for the Assignment:

Reference to Prior Work/Assignments that Best Illustrates Capability to Handle the Assigned Tasks

Overall coordination of the project on “Integrating biodiversity considerations into spatial planning at landscape

scale, Kala Oya Environmental Sensitive Areas (ESA) “ - UNDP funded project

• Preparation of a training manual on methodology, guidelines, formats and tools to integrate biodiversity

conservation and sustainable use into land use planning in Sinhala, Tamil and English.• Conduct about 10 trainings progrqmmes for district and divisional level technical planning teams to build

their capacity in developing biodiversity conservation integrated land use plans and inter-sectoral plans.• Report on completion of trainings for national level planners for the awareness of resources its utility

towards mainstreaming BDS in ESA management• Guidelines, procedures and methodology for developing biodiversity conservation integrated inter­

sectoral plans and the recognition and acceptance (declaration) of the land use plans and developed for the Kala Oya 2 sites.

Preparation Wildlife Management Plans for Upper Elahera Canal and North Western Province Canal Projects

(August 2016- August 2017) - Environmental Economist / overall coordination - funded by the Mahaweli Water Security Investment Program (MWSIP) of Mahaweli Development and Environment, with a special emphasis

on mitigation of human-elephant conflict in the project area. Thus, the aim of this consultancy contract would be

to prepare the said wildlife management plans for the Upper Elahera Canal Project and Northwestern Province

Canal Project.

Team Leader and overall lead of the project on The Biodiversity Finance Initiative (BIOFIN) funded by UNDP. Biodiversity Expenditure Review, The Environmental Economic Valuation Review, and the Finance Needs

Assessment were successfully completed for the development of the Biodiversity Finance Plan for the country.

Team Leader and Overall Lead of the assignment - Value addition to BIOFIN: Promoting innovative financing

mechanisms for biodiversity conservation in Sri Lanka (July - December 2018)-which is a continuation of the

BIOFIN project - funded by UNDP: A field level demonstration of Payment for Ecosystem Services (PES) mechanism for watershed services using a mini hydro power plant with all essential biophysical and

socioeconomic studies are proposed to cover in this project. Required institutional support within the existing

framework, the barriers and the mechanisms to overcome them for upscaling and upscaling plan for other potential mini hydros in operation have been studied in this component. Also assessed the institutional and legal framework required for benefiting from the .15 prioritised financing solutions for conserving biodiversity in Sri Lanka as proposed by the BIOFIN project.

1 5

Page 42: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Natural Resources Management specialist for the international consultancy for the Government of Lao Peoples’ Democratic Republic for Independent Third Party Monitoring of Rural Access Roads Project - ADB/9. Project duration 2003 April to 2007 April - with 6 months of inputs, environmental monitoring guidelines were prepared, training programmes were conducted at National and Provincial level and first mission of the third party

monitoring conducted in the first tear of the project.• Member of many Technical Evaluation Committees for evaluating EIA reports appointed by Central

Environmental Authority (CEA) since 1999• Diploma in River Basin Management, Online course conducted by CEDDET Foundation, Spain with ADB

and NABRO, during 20th January to 6th April 2014 (equivalent to 120 teaching hrs),• Environmental Impact Assessment, 10 day Intensive programme, Central Environmental Authority and

University of Peradeniya, 10-14 and 24-28 February, 1995 Kotmale, Sri Lanka.• Environmental Monitoring: Principles and Use in EIA, Central Environmental Authority and the University

of Peradeniya, 3-7, April 1995, Hikkaduwa, Sri Lanka,• Strategic Environmental Assessment, organised by World Bank, EEPSEA and SEARCA, Los Banos,

Philippines, 5-8 July 1998• Strategic Environmental Assessment - International Experience and Perspectives in Strategic

Environmental Assessment (SEA), Prague, Czech Republic, 26-30 September 2005• Incorporating Environmental Safeguards into Disaster Risk Management conducted Ecosystems and

Livelihoods Group of IUCN Asia, 16-19 March 2009, Waikkala, Sri Lanka

• International Economic and Finance Specialist, ADB Manila for the preparation of Greater Mekong Sub­region Biodiversity Corridors Investment Project, Covers 44 days of work in Lao PDR, Cambodia, Vietnam

and Thailand with a visit to the Philippines and 20 days home based, 28 June 2010 to 31st October 2010.• Natural Resource Management Expert in two member IUCN Internal Review Team for end of the project

review of Ecosystems for Life: Bangladesh India Water Initiative by Royal Netherlands Embassy of Bangladesh, Project implemented by IUCN Bangladesh and IUCN India. June 2014. Total number of days

15 (2 desk, 8 field and 5 writing).• Natural Resource Management Expert in three member IUCN team for Lao Peoples’ Democratic Republic

in the ADB/9 (Loan no 1795 - Lao) Rural Access Roads Development project. 6 months of consultancy

services staggered over 2 a period of 2 years. April 2003 - May 2005. 6 visits were made during the

consultancy.Reports produced;

Key contributor to all projects that IUCN Delivered in last 10 years on ecosystem based and landscape scale

planning and management. These include being the coordinator of the Wildlife management plans prepared

for Yan Oya, Upper Elahera Canal, North Western Province Canal, Biodiversity Action Plan for Moragahakanda and Kaluganga reservoir projects, designing of GEF 6 project on Managing together on

integrated planning of selected landscapes for biodiversity and livelihoods and preparation of training manual for the ESA project on biodiversity inclusive planning at landscape scale,_______________________

Certification:

I, the undersigned, certify that to the best of my knowledge and belief, this CV correctly describes myself, my . qualifications and my experience. I understand that any willful misstatement described herein may lead to my

disqualification or dismissal, if engaged.Date.

[Signature of staff member]

Date 22nd February, 2019

[Signature of authorized representative of the client]Full name of authorized representative: Shamen Vidanage

1 6

Page 43: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

?• -

CURRICULUM VITAE (CV)

Proposed Position: Field Team Leader / Fauna Ecologist

Name of Firm ; IUCN, International Union for Conservation of Nature

Name of Staff : Warahene Liyanage Don Pradeep Thushar Sampath DeAlwis Goonatilake

Date of Birth 20 April, 1972 Nationality: Sri Lankan

Education:

• Master of Science (MSc in Archaeology), at Postgraduate Institute of Archeology, University of Kelaniya, Sri Lanka in 2011. (Duration: 2 years) - As a part of Master programme the following research was done:“Ecological Background and Archaeological Evidences in Vilpattu National Park."

• Post Graduate Diploma in Archeology (with MERIT PASS) at Postgraduate Institute of Archeology, University of Kelaniya, Sri Lanka in 2003. (Duration: one year) - As a part of the diploma program the following

subjects were followed, Archeological methods and techniques; Art History; Pre-history and proto­history; Architectural history and landscape archeology; Environmental Archeology

• Bachelor of Science degree (BSc in Biological Sciences), The Open University of Sri Lanka in 1998. As a

part of the degree program the following subjects were followed, Zoology, Botany, and Chemistry. (Duration: Four years) - As a part of degree Programme the following research was done: "A preliminary study of freshwater stream fishes in selected streams at Eratne; to show abundance, diversity, and habitat usage."

• Training course on "Master class in Biodiversity Assessment” conducted by the Crawford fund,DIVERSITAS Western Pacific and Asia, Griffith University and James Cook University in Australia, 2000

March. •

Membership of Professional Associations:

• Life member of IUCN SSC Freshwater Fish Specialist Group (FFSG), since 2012;• Life member of IUCN SSC Bat Specialist Group (BSG), since 2012.

• Life member of Royal Asiatic Society Ceylon Branch, since 2005.• Life member of the Sri Lanka Archeology Society, since 2003.• Associate member of Institute of Biology, Sri Lanka, since January 2001. Life Member of the Sri

Lanka Association for the Advancement of Science, since December 2001.

Position Hold in National Committees:

• National Committee of Mangrove Conservation - Ministry of Environment, Rajamalwattapata,

Battaramulla (Since 2015 to date)

• National Palaeo»biodiversity Advisory Committee - Ministry of Environment, Rajamalwatta

road, Battaramulla (Since 2007 to date)

• National Wetland Steering Committee- Central Environmental Authority, Ministry of

Environment, Rajamalwatta road, Battaramulla (since 2011 to date)

• National Committee of Organic Agriculture & Agro Forestry. Council of Agricultural Research

Policy. Ministry of Agriculture, Colombo 07. (2011 to 2012)

Other Relevant Qualifications:

■ "Environmental law and Justice" Faculty of Law, General Sir John Kotelawala Defence

University, Kandawala Estate, Rathmalana, Sri Lanka.(February, 2014).■ “Small Mammal Field techniques Training” Held at College of forestry, Kerala Agricultural

University, Thrissur, Kerala, India. Organized by CCINSA, RISCINSA, Zoo Outreach Organization, Wildlife Information Liaison Development, India Hosted by College of Forestry, Kerala Agricultural University.(November 2011),

1 7

Page 44: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

■ T ra in ing w orkshop on " The BO BLM E_M FF W orkshop on Sc ien tific P resen ta tion" Held at Male, Maldives. Conducted by Mangrove for the Future, and BOBLEME. (October, 2011),

■ T ra in ing w orkshop on " The BO BLM E_M FF W orkshop on Sc ien tific W riting " Held at Phuket Thailand. Conducted by Mangrove for the Future, and BOBLEME, (August, 2011),

■ "T ra in ing w orkshop on IU CN R ed lis t C atego ries , C rite ria and Spec ies in fo rm a tion Serv ice

(S IS )" held at Colombo Sri Lanka. Conducted by IUCN SSC, Redlist Unit, IUCN Species

Programme. IUCN Species Information Service (SIS), Ecosystem Livelihoods Group II, (December 2010),

Languages:Languages :

EnglishS inha la

Speak ing W riting

GoodExce llen t

R ead ing

GoodExce llen t

GoodExce llen t

Employment Record:

• Field Ecologist / Seiner Programme Officer, 53, Horton Place, Colombo 07, Sri Lanka, (Since 2004 to

date)

• Visiting Lecturer, Postgraduate Institute of Archeology, University of Kelaniya, Sri Lanka (year 2012 &

2016 to date)• Research Assistant, Department of Zoology, University of Colombo (1999-2004)

Professional / Working Experiences: I possess approximately 20 years of research and teaching experience in

the field of Ecology and Biodiversity. I have knowledge of collecting, preserving and identification of

animals; direct and indirect methods used for determination of population density of fauna; methods used

for studying presence and distributions of animals in a given region.

Detailed Tasks Assigned __________________

Projects in IUCN Sri Lanka Nature of the Job

A Project Manager

1 Animal and plant rescue and release

programme along the Access roads and

the Electric (Elephant) fence at proposed

sanitary landfill and transfer station -

Phase I

Location: Aruvakalu,Duration: 2018 Feb-April Position held: Project manager and field Ecologist Duties: Field surveys and preparation of final reports. Client: Ministry of Megapolis and Western Devolopment

Location: Lenadora to Kahalla-pallekele, Upper Mi Oya and hakwatuna

Oya basinDuration: 2016-2017Position held: Project manager and field Ecologist Duties: Field surveys and preparation of Management Plan.Client: Ministry of Mahaweli Development and Environment.______

2 Human- Elephant Conflict Management and Mitigation, for the North Western

Province Canal Project (August 2016 -

October 2017)

Location: Aruvakalu, llluvankulama area at Northwestern Province

Southern border of Wilpattu Notational park

Duration: 2016

3 Recommendations to reduce Human- Elephant Conflict in the Aruakalu quarry

areaPosition held: Project manager and field Ecologist Duties: Field surveys and preparation of Management Plan. Client: HOLCIM Lanka PLC (Siam City Cement PLC)

Preparation of Ecotourism Management Plan for Pothuvil Lagoon

Location: Pothuvil to Panama Eastern Province4Duration: 2016Position held: Project manager and field Ecologist and Archaeologist Duties: Field surveys and preparation of Management Plan.Client: Coast Conservation Department___________________

1 8

Page 45: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

5 Preparation of Wildlife Management Plan

for Proposed Yan Oya reservoir.Location: Yan Oya Basin

Duration: 2015-2016Position held: Project manager and field Ecologist and Archaeologist Duties: Field surveys and preparation of Management Plan.Client: Ministry of Mahaweii Development and environment.

6 Preparation of Wetland Manual Location: Environmental Protected Area

Duration: 2014Position held: Project manager and field Ecologist and Archaeologist Duties: Preparation of Wetland training manual and presentation. Client: Central Environmental Authority____________________

7 Implementation of the Biodiversity

Action Plan of the Moragahakanda

Agricultural Development Project and the

Kalu Ganga Reservoir and Agricultural Extension Project

Location: Mahaweii Authority

Duration: 2012-2014Position held: Project manager and field team leader, field Ecologist Duties: Development of methodology, field work, collection of ethnobiological data, Fish rescue and Translocation, conducting

awareness programme, Inventorying the Mammal, birds, reptiles

diversity in selected Habitat types. -Client: Sri Lanka Mahaweii Authority______________________Location: Maragala Environmental Protected Area

Duration: 2014Position held: Project manager and field Ecologist and Archaeologist Duties: Inventorying the Mammal, birds, reptiles diversity in selected

Habitat types,.Client: Central Environmental Authority____________________

8 Management Plan for Margala EPA, Monaragala

9 HOLCIM/INSEE quarry site (Aruakalu) Monitoring and Species rescue and

release project.

Location: Aruvakkalu Quarry site, Eluvamkulama

Duration: Since 2010 to date (2019)Position held: Project manager and field Ecologist and Archaeologist Duties: Inventorying the Mammal, birds, reptiles diversity in selected

Habitat types, carried out rescue operations within the proposed quarry

sites, in the HOLCIM Aruakalu quarry site report writing, preparation of concept notes and budgets

Client: HOCIM Lanka.

10 Floral Assessment in and around the

Proposed New Clinker Plant Site at Aruwakkalu Holcim Quarry

Location: Aruvakkalu Quarry site, Eluvamkulama

Duration: 2010-2016Position held: Project manager and field EcologistDuties: Field activities, report writing, preparation of concept notes andbudgetsClient: HOCIM Lanka.

11 Addendum of Biodiversity Study on

Access Roads Construction Areas within

HLL lands

Location: Aruvakkalu Quarry site, Eluvamkulama

Duration: 2012Position held: Project manager and field EcologistDuties: Field activities, report writing, preparation of concept notes andbudgetsClient: HOCIM Lanka.

12 Biodiversity Assessment of the

Mangroves within and surrounding

the Holcim Ruhunu Cement Plant -

Location: HOLCIM Galle Clinker Plant Duration: 2012Position held: Project manager and field Ecologist and Archaeologist Duties: Inventorying the Mammal, birds, reptiles diversity in selected

Habitat types, in the HOLCIM Galle Clinker Plant and report writing, preparation of concept notes and budgets

Client: HOCIM Lanka.

2012

1 9

Page 46: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

•>

Location: Haycok Forest Reserve

Duration: 2012Position held: Project manager and field Ecologist and Archaeologist Duties: Inventorying the Mammal, birds, reptiles diversity in selected

Habitat types,.Client: Biodiversity Secretariat, Biodiversity Secretariat, Ministry ofEnvironmental and Natural Recourses, Sri Lanka.______________Location: Galapitamada, Sri Lanka

Duration: 2013Position held: Freshwater Fish expertDuties: Inventorying the fish survey, conducting awareness programs, Supervision field works,.Client: TOYOTA Foundation, Japan.______________________

Biodiversity Inventory of the

Haycock National Biosphere

Reserve

1 3

Preventing the Extinction of the Critically

Endangered Point Endemic Fish: The

Bandula Barb (Puntius bandu la )

14

Biodiversity Baseline Survey in

the Hantana Mountain Range

Environmental Protection Area

Location: Hantana Environmental Protected Area

Duration: 2013Position held: Project manager and field Ecologist and Archaeologist Duties: Inventorying the Mammal, birds, reptiles diversity in selected

Habitat types,.Client: Central Environmental Authority____________________

1 5

Biodiversity Assessment of the Estates (Rilhena, Hunuwela, Kahawatta) of Kahawatte

Plantations PLC, Pelmadulla

Location: Kahawatta Plantation estates at Pelmadulla, Kahawatta, and

OpathaDuration: 2010-2012Position held: Project manager and field EcologistDuties: Inventorying the Mammal, birds, reptiles diversity in selectedHabitat types,.Client: Dilmha Conservation

1 6

Sustainable Development of the Delft Island: A Biodiversity, Socioeconomics

and Archaeological Assessment for Recommendations

Location: Delft Island

Duration: 2011Position held: Project manager, Archaeologist and field Ecologist Duties: Inventorying the Mammal, birds, reptiles diversity in selected

Habitat types,. Compilation of Archaeological information and report writingClient: Ministry of Economic development__________________

1 7

Member as a Field Ecologist/ArchaeologistB

1 Assessment of sea Turtle nesting

habitats from Tangalle (Anantara

Tangalle Resort) to Ruhuna (Yala) National Park (Kumbukkan Oya

estuary) in South-eastern Sri Lanka

(December 2017-June 2018)

Location: Tangolle to Kumbukkan Oya

Duration: 2017-2018Position held: Field Ecologist/GIS field assistantDuties: Collecting ecological data and Verifying Maps and collectingGPS points along the coastal habitat in Ihe study area

Preparation of a Wildlife Management Plan, including Human- Elephant Conflict Management and Mitigation, for the Upper Elehara Canal Project (August 2016 - October 2017)

Location: Moragahakanda to Mahakandarawa

Duration: 2016-2017

Position held: Field EcologistDuties: Field surveys and preparation of Management Plan. Client: Ministry of Mahaweli Development and Environment.

2

3 Preparation of a communication

strategy for the National Strategic

Biodiversity Action Plan for Sri Lanka

(November 2015- April 2016)

Location: Colombo base

Duration: 2015-2016

Position held: EcologistDuties: Preparation of relevant text and assist to project manager and

team leader to preparation of report.Client: Ministry of Mahaweli Development and Environment_______

20

Page 47: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

4 Biodiversity Survey of Northern Islands

Northern Sri LankaLocation: Northern island in Northern province

Duration: 2016Position held: Field team leader (biodiversity) and field Ecologist and

ArchaeologistDuties: Inventorying the Mammal, birds, reptiles diversity in selected

Habitat types, report writingClient: Mangrove for Future- IUCN________________________

5 Biodiversity Survey of the Nainamadu

Forest ReserveLocation: Nainamaduava Forest Reserve, Nadunkerni Duration: 2013Position held: Project Field team leader and field Ecologist and

ArchaeologistDuties: Inventorying the Mammal, birds, reptiles diversity in selected

Habitat types, report writing, preparation of concept notes and budgets

Client: Sevalanka Foundation

6 Study on Gulf of Mannar Location: Sri Lanka

Duration: 2012Position held: Ecologist (Mammalogist) & Archaeologist Duties: Inventorying the Mammal diversity and Archaeological Monuments at Gulf of Mannar Client: FAO

7 Wilpattu National Park Resource

Inventory Project (Fauna Flora and

Archaeology)

Location: Wilpattu National Park

Duration: One Year (June 2005 to April 2006)

Position held: Ecologist (Mammalogist) & ArchaeologistDuties: Inventorying the Mammal diversity and Archaeologicalmonuments at Wilpattu national Park.Client: Project implemented by The World Conservation Union (IUCN) in collaboration with the Department of Wildlife Conservation.

8 National threatened Species Project. Location: Sri LankaDuration: Two and half years (2004-2007)Position held: Redlist Compiler (Fauna)Duties: Collection and analysis of data, preparation of reports/publications and Assisting the workshops of the list of nationally

threatened fauna in Sri Lanka.Client: Project jointly implemented by IUCN Sri Lanka and Biodiversity

Secretariat, Ministry of Environmental and Natural Recourses, Sri Lanka.

2007

9 Moragahakanda Proposed Reservoir Biodiversity Assessment Project (Fauna

and Flora)

Location: Moragahakanda, Elahera

Duration: One Year (2007)Position held: Ecologist (Mammalogist)Duties: Inventorying the Mammal diversity in selected Habitat types in

the Moragahakanda Proposed Reservoir area.Project implemented by The World Conservation Union (IUCN).Client: Mahaweli Authority.

1 0 HOLCIM quarry site (Aruakalu) Monitoring and restoration.

Location: Aruvakkalu Quarry site, Eluvamkulama

Duration: Since 2007 to up to now

Position held: Ecologist and Archaeologist Duties:2007 tO 2010- Inventorying the Mammal diversity in selected Habitat types in the HOLCIM Aruakalu quarry site___________________

2 1

Page 48: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

2010 to present - Project Coordinator & field ecologist Documentation of Miocene fossils, and other archaeological monuments recorded in the project site.Client: HOCIM.

1 1 Dissemination of Biodiversity Information, and Collection and Dissemination of SocioeconomicInformation on the Gulf of Mannar

Location: Coastal belt of the Gulf of Mannar Duration: 2011Position held: Fauna Ecologist and Archaeologist Duties: Inventorying the faunal diversity in selected Habitat types in the

area and compilation of the Archaeological information and report writing.Client: Bay of Bengal Large Marine Ecosystem(BOBLME) Project of the Food & Agriculture Organization (FAO),.

1 2 Biodiversity Assessment of the

High Security Area of the Zone 5

Development Area

Location: Sampur at Trincomalee

Duration: 2010Position held: Fauna Ecologist and Archaeologist Duties: Inventorying the faunal diversity in selected Habitat types in the

area and compilation of the Archaeological information and report writing.

1 3 Enhancing the Ecological Integrity and

Ecological Services of Halgolla Estate: Draft Watershed Management Plan

Location: Halgolla estate at Kelaniweli Plantation

Duration: 2012Position held: Fauna EcologistDuties: Inventorying the faunal diversity in selected Habitat types in the

area and compilation of the Archaeological information and report writing.Client: Kelani Velly Plantation PLC

C Projects participated/handled in Other organizationsLocation: Kala Oya BasinDuration: Nine month (Octo-2003 to July 2004)Position held: Research Assistant Faunal Survey.Duties: Data collecting, identification of species, analysis and

reparation of reports/publications. For EML Ltd. And

Mahaweli Authority,

1 Kala Oya Basin Management Project, Biodiversity Survey

D Projects participated/handled/ appointed in Government Institutes

1 Ecological & Archaeological Expert committee for Proposed Dedduwa Lake

(Tourism development) Resort Project (STAGE1)

Has been involved with the activities of Ministry of Agriculture, Livestock, Lands & IrrigationName of committee: Ecological & Archaeological Expert committee for Proposed Dedduwa Lake (Tourism development) Resort Project (STAGE1)Duration: 2004Position: Member of the Ecological & Archaeological adversary

CommitteeDuties: Identify and make recommendations on Ecological and

Archaeological Sensitive Areas within the Proposed Dedduwa Lake

Resort (STAGE1) Project Area future species conservation and

management__________________________ ;___________2 Small Mammal specialist 1. Name of committee: Threatened species expert committee

Duration: November 2003

Position: Small Mammal specialistDuties: Preparation of threatened species profiles for future species

conservation and management__________________________

22

Page 49: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Recovery Plan for Bandula Barb (Pun tius

bandu la )

Location: Sri Lanka

Duration: 1 years (2007)Position held: Main investigator with co-researchers: Dr. Deveka

Weerakoon, Ms. Hasula RajapakshaDuties: Field and literature Collection and analysis of data, preparation

of recovery plan.Client: Project implemented by Biodiversity Secretariat, Biodiversity

Secretariat, Ministry of Environmental and Natural Recourses, Sri Lanka. '

3

4 2012 National Redlist Compilation Location: Sri Lanka

Duration: 2011 to 2012Position held: Technical review of freshwater fish data

Duties: Technical support for evaluate other faunal groups

Client: Project implemented by Biodiversity Secretariat, Biodiversity

Secretariat, Ministry of Environmental and Natural Recourses, Sri Lanka.

Activities related to undertaking biodiversity and ecosystem inventories (Identify and document technical issues related to habitat management and wildlife conservation)A preliminary study of freshwater stream Location: Peak Wilderness Sanctuary

fishes in selected streams at Eratne: to Duration: 6 months (1997) show diversity, abundance, and habitat Position held: Research assistantusage Duties: Inventorying the fish diversity in selected freshwater streams in

Peak Wilderness Sanctuary (B.Sc. degree project)

E

1

F Artworks and designs made for institutesDesign for Flag poles I For Sri Lanka Army . •1 .

For Sri Lanka Army2 Design for Kataragama Devalaya main

door decorationDesign logo for Logistic school at Trincomalee, SL Army_______

3 For Sri Lanka Army

Certification:

I, the undersigned, certify that to the best of my knowledge and belief, this CV correctly describes myself, my

qualifications and my experience. I understand that any willful misstatement described herein may lead to my

disqualification or dismissal, if engaged.Date.

[Signature of staff member]

Date 22nd February, 2019

[Signature of authorized representative of the client]Full name of authorized representative: Shamen Vidanage

CURRICULUM VITAE (CV)

23

Page 50: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Proposed position: Plant Ecologist

Name of firm: IUCN, International Union for Conservation of Nature

Name of staff: Sarath Polgasdeniya Ekanayake

Date of birth: 23 June 1962 Nationality: Sri Lankan

Education

• B.Sc.(Botany Special), University of Peradeniya, Sri Lanka, 1988• MPhil (Plant Ecology) University of Peradeniya, Sri Lanka, 1994N on-deg ree educa tiona l qua lifica tions : Soc io logy and anthropology (one year credit certificate course of Open University), Information management systems/ IT (one year credit certificate course of Open

University) & Human Resource Management (one year post graduate credit certificate course of Open

University).

Memberships of professional associations:

• Life member • Sri Lanka Association for the Advancement of Science.• Life member - Wildlife and Nature Protection Society of Sri Lanka.• Life member - Royal Asiatic Society of Sri Lanka• Member ■ National Environmental Forum• Member & Secretary - Field Botanists Association of Sri Lanka• Member & Secretary - Ecological Association of Sri Lanka.• National Board member - Climate Action Network South Asia• Member - Species specialist group of Ministry of Environment

Other Training• Ecological analysis, 3 months, 1993, Austria; University of Bodenkulture, Vianna, Austria.

• Human Resources Management, 1996, Post Graduate credit certificate, OUSL.• Short course on GIS applications, 2002, University of Peradeniya.• Short training on Project Evaluation and Monitoring, 2003, IUCN - Sri Lanka.• Introduction to GIS/Arc View computer software conducted by Natural Resources Institute of UK,

1997, Mahaweli Authority of Sri Lanka, Polgolla.• Short course on Environmental Impact Assessment conducted by Central Environmental Authority

and Centre for Environmental studies, University of Peradeniya, 1994.

LanguagesSpeaking WritingLanguages:

EnglishS inha la

ReadingG o o dGood G o o d

G oodG ood G ood

Expertise in kev words: Botanical surveys, EIA studies, Invasive flora, Restoration ecology, Species rescue works, Watershed management Coastal and Mangrove ecology, Protected area management, Natural resource

management and livelihoods, Ecological assessments, Wildlife management wetland management social botany / ethno-botany & medicinal plants.

Kev involvements as botanical lead person in botanical surveys done in northern and eastern provinces of SriLanka:

Botanical surveys in Tirukkovil, Potuvil & Panama - marine and terrestrial ecosystems (IUCN & SIOA) Botanical survey of Nainamadu Forest (IUCN & CARE international).Botanical survey of Dleft Island (IUCN & Ministry of tourism).Botanical survey of Chundikulam Wildlife Sanctuary (Funded project by Ministry of Environment). Botanical survey of Mangrove and sea grass communities of Vedithalathivu (GEF funded project).

24

Page 51: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Botanical survey of Pulmodai estuary (IUCN & Irrigation Department).Botanical survey of Muthiyakdu (Mulativu) forest and wetlands (EIA study under Dam Safety Project).

Professional experience (27 years plus):Consultant Plant Ecologist (IUCN), September 2011 onwards; Forest biodiversity assessment at Naianmadu

forests, Biodiversity survey of Delft Island, Plant rescue and translocation in Moragahakanda development area, Holcim biodiversity survey, Pollution assessment at Galle cement factory surroundings, Water shed management project at Halgolla estate & Hunuwela estate, Implementation of environmental compliance of YanOya irrigation

project, environmental restoration of Kapirikkgama village tank cascade development project and FAO/PGRC

agrobiodiversity conservation project.

Director (Project Development), (February 2010-August 2011), National Environmental Forum, Project Management Office, 10/8, Mahamaya Road, Kandy, Involved in Project formulation, liaising with donor agencies, budgeting, fund raising, co-ordination & project implementation, progress review, project documentation, post­project monitoring and evaluation, expedite community based agro forestry/environmental management projects

with particular reference to human-elephant conflict disaster/climate change impacts, Environmental Impact Assessments and environmental outreach programmes.

Senior programme Officer, (May 2002 - January 2010), Forestry and Biodiversity group, International Union forConservation of Nature( IUCN)- Sri Lanka country office, 53, Horton Place, Colombo 7Involved in forestry and biodiversity assessments, wildlife management support projects, Environmental ImpactAssessments, eco friendly landscaping, project formulation, budgeting, fund raising, co-ordination & projectimplementation, progress review, project documentation, managing teams, outsourcing and contract management,post-project monitoring and evaluation, event management, and representation in professional forums (local &foreign),

Ecologist (July 1999 - April 2002), Natural Resources Management Services Pvt,Ltd., Environment and Forest Conservation Division, Mahaweli Authority of Sri Lanka, Polgolla. -Involved in developing Mahaweli biodiversity information system, field surveys for plant biodiversity assessments, formulation of guidelines for artificial flood releases from reservoirs to maintain downstream wetland ecosystems and

dependent livelihoods, environmental outreach programmes, project formulation, implementation and documentation

and managing teams.

Environmental Planner (January 1996 - June 1999), DFID/U.K / ENDEV Project, Environment and Forest Conservation Division, Mahaweli Authority of Sri Lanka, Polgolla.Involved in development of biodiversity information system for Upper Mahaweli River Basin, field surveys for plant ecological studies and land use mapping, environmental outreach programmes, Vegetative interventions in watershed

management, project formulation, implementation and documentation and managing teams.

Research Officer (June 1988-December 1995), British ODA Project, Department of Agriculture, Division of Botanic

gardens, Royal Botanic Gardens, Peradeniya, Sri Lanka.Involved in forest ecological studies in the Knuckles region (Research component of MPhil degree), field research in

plant ecology in diverse habitats in the country, compiled data for publication of two books on local plants, agronomic

works on horticultural plants, development of computer data bases, ethno botanical studies on medicinal plants &

Kandyan homegardens, environmental assessments, producing audio-visual productions, publication works, project documentation, co-ordination of local & foreign professionals.

Ancillary posts:External supervisor - MSc course, Post Graduate Institute of Science, University of Peradeniya (2005-2006) Co-Principal investigator. Community based Sandalwood project, PGIS, University of Peradeniya. (1999-2002) Visiting Lecturer in Ecology, Sabaragamuwa University of Sri Lanka. (2000)Consultant Plan! Ecologist, lUCN-The World Conservation Union. (1999-2002).Principal investigator (Floristic studies), GEF/UNDP/DWLC (1996-1997).Consultant Botanist, Homegarden Reseroh Project in Sri Lanka, University of Bodenkulture, Austria. (1992-1993) Technical Advisor, Born free (UK)/NEF Sri Lanka, Project on managing elephant crop raids (2009)Plant ecologist for a number of Environmental Impact Assessment assignments.

25

Page 52: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

PUBLICATIONS: 60 plus

Books:Ratnayake, HD., Ekanayake, SP., 1995, C om m on w ays ide trees o f S ri Lanka , Royal Botanic Gardens, Peradeniya.Sumiththrrachchi, DB, Ratnayake, HD, Ekanayake, SP, 1995 Beau tifu l w ild flowe rs o f S ri Lanka , Royal Botanic Gardens, Peradeniya.Tennakoon, KU, Ekanayake, SP, 2000, H and book o f Sanda lwood nu rse ry techn iques (In S inha la ),

Department of Botany, University of Peradeniya.Bambaradeniya, CNB, Ekanayake, SP, 2003, A gu ide to b iod ive rs ity o f Knuck les R eg ion , IUCN, Colombo, Ekanayake, SP, Bambaradeniya, CNB, 2003, T rekk ing in the Knuck les Fores t, IUCN, Colombo. Bambaradeniya, CNB, Ekanayake, SP, Fernando, RHSS, Perera, WPM, Somaweere, R, 2002, A

B iod ivers ity S ta tus P ro file o fBunda la N ationa l Park , IUCN, Colombo.Bambaradeniya, CNB, Ekanayake, SP, Fernando, RHSS, Perera, WPM, Somaweere, R, 2002,An

Assessm en t o f the S ta tus o f B iod ive rs ity in the M uthu ra jaw e la W etland Sanctua ry , IUCN, Colombo. Bambaradeniya, CNB, Ekanayake, SP, Kekulandala, CDCB, Fernando, RHSS, Samarawickrama, VAP, Priyadharshana, TGM, 2002, An assessm ent o f the s ta tus o f b iod ive rs ity in the M aduganga m angrove

es tua ry , IUCN, Colombo,Jayasinghe, CD, Ekanayake, SP, Bambaradeniya, CNB, Amarasinghe, S, 2005, T rop ica l ra in fo res ts - a

resou rce book fo r seconda ry schoo lteache rs , IUCN, Colombo, lo. Ekanayake, SP, Bambaradeniya, CNB, Perera, WPN, Perera, MSJ, Rodrigo, RK, Samarawickrama, VAP,

Peris, TN, 2005, A B iod ivers ity s ta tus p ro file o fLunam - Ka lam e tiya W atland Sanctuary , IUCN, Colombo. u . Bambaradeniya, CNB, Ekanayake, SP, Amerasinghe, S., 2006, G u ide to S inhara ja : A b iod ive rs ity ho tspo t

o f the w orld , IUCN, Colombo.

l.

2

3.

4.

5.

6.

7.

8.

9.

Technical papers, communications and disseminations:Balasubramaniam, S., Ekanayake, SP, Kalansooriya, S., Ratnayake, H.D., Sumithraarachchi, D.B.,1991, Phytosoc io log ica l S tud ies o f Three Fores t Types o f the Knuck les R eg ion , Proceedings of the

workshop for the preparation of Management plan for conservation of Knuckles, Forest Department of Sri Lanka.Balasubramaniam, S., Sumithraarachchi, DB, Ekanayake, SP, Ratnayake, H.D., Kalansooriya, S.,1992, Fores t gene tic resou rce conse rva tion , p ro tec ted a reas and bo tan ic ga rdens in S ri Lanka , Paper presented at the world congress on national parks and protected areas, Caracas, Venezuela, Feb.10- 20,1992.Hochegger, K., Ekanayake, SP, 1992, Kandyan Forest

MPTS network-Sri Lanka, Vol. 1, No,3.Ekanayake, S.P, 1992, Sem i-eve rg reen fo res ts o f Knuck les , Proceedings of the workshop on Current Research Activities of Royal Botanic Gardens, Peradeniya,Hochegger, K., Ekanayake, SP, 1993, Kandyan Forest G ardens o f S ri Lanka , Paper presented at the

Postgraduate students seminar, the Department of Applied Botany, Munster University, Germany, 2 nd

November, 1993.Ekanayake, SP, 1993, The na tu ra l vege ta tion o f S ri Lanka , A review paper presented at the Institute of Forest Ecology, Bodenkulture University, Vienna, Austria, 9 th November, 1993.Ekanayake, SP, Abeygoonawardena, R.M.K., 1993, O ccu rrence o f VAM fung i in som e legum es exam ined

and the ir re la tion to nodu la tion , Proceedings, 49 th annual session of Sri Lanka Association for the

Advancement of Science.Ekanayake, SP, Ratnayake, H. D„ 1994, U nderexp lo ited w ild trees o f S ri Lanka - a case s tudy in sem i­

eve rg reen fo res ts in the Knuck les reg ion , Proceedings, 5th National Workshop on Multi-purpose Tree

Species, 1-4 April, PGRC, Sri Lanka.Ekanayake, SP, Ratnayake, HD, Kalansuriya, S, 1994, F lo ra o f Knuck les reg ion : an ana lys is ,

Proceedings of the golden jubilee session of Sri Lanka Association for the advancement of science, Colombo.

10. Ekanayake, SP, 1994, A Phytosoc io log ica l s tudy o f sem i-eve rg reen fo res ts o f Knuck les and

U dawa lawe , S ri Lanka , M.Phil. thesis University of Peradeniya, Sri Lanka.11. Ekanayake, SP, 1994, W oody flo ra o f sem i-eve rg reen fo res ts o f Knuck les reg ion , Proceedings of the

golden jubilee session of Sri Lanka Association for the advancement of science, Colombo.

l.

2.

G ardens - in trans ition , MPTS news,3.

4.

5.

6.

7.

8.

9.

26

Page 53: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

12. Jayasekara.P., Ekanayake, SP, Weerasinghe, U, 1994, Ecological study of riverine ferns ofHantana, Proceedings of the golden jubilee session of Sri Lanka Association for the advancement of science, Colombo.

13. Ekanayake, SP, Ratnayake, HD, Harischandran, S, 1995, An analysis of flora ofUda Walawe National Park, Proceedings of the annual session of Sri Lanka Association for the advancement of Science, Colombo.

14. Ratnayake, HD, Ekanayake, SP, Harischandran, $., 1995, A study of upper montane flora of the

Knuckles region, Proceedings of the annual session of Sri Lanka Association for the advancement of Science, Colombo.

is. Ekanayake, SP, Harischandran, S,r Ratnayake, HD, 1995, A study of m orpho log ica l d ive rs ity o f leaves

o f trees in S inha ra ja forest, Proceedings of the annual session of Sri Lanka Association for the

advancement of Science, Colombo.16. Ekanayake, SP, Ratnayake, HD, 1995, Multipurpose live fences in Sri Lanka , MPTS News, Vol.4,

Sept.-Dec., University of Peradeniya.17. Ekanayake, SP, Ratnayake, H.D., 1995, Areca nut palm under threat o f ex tinc tion , MPTS News, Vol.4,

Sept,-Dec,, University of Peradeniya.is. Ratnayake, HD, Ekanayake, SP, White, R„ Harischandran, S„ 1996, D is tribu tion o f fam ily :

Dipterocarpaceae in Knuckles and Randenigala, Proceedings od annual session of Sri Lanka

Association for the advancement of Science, Colombo,19. Ekanayake, SP, Ratnayake, HD, 1996, P lan t invasion - threat to Lanka's b iod ive rs ity (Part i &ii), Daily

News (Mid-page article), 05-06 April.20 Ekanayake, SP, 1997, Development of management support GIS for b io -resou rces o f uppe r M ahawe li

catchment, Paper presented at the symposium on upper Mahaweli catchment conservation - status and

trends, Sri Lanka Association for the advancement of Science, 03,05.97, Colombo.21. Ekanayake, SP, 1997, App lica tion o f G IS in b io log ica l research, Presentation at the seminar on GIS,

18.09.1997, NARESA, Colombo.22. Bambaradeniya, CNB, Meegaskumbura, MPP, Ekanayake, SP, Gunewardena, J, 1998, B iod ive rs ity o f

Sri Lanka and the g row ing th rea t o f in vas ive biota, Loris, XXI(6), Wildlife and Nature protection Society, Colombo.

23. Bambaradeniya, CNB, Ekanayake, SP, Gunewardena, J, 1999, Preliminary observations on the status

o f a lien in vas ive b io ta in Sri Lanka, Proceedings of Global Biodiversity forum- south and south east asia, 24-26 October, 1999, Colombo.

24 Tennakoon, KU, Ekanayake, SP, Etampawela, ERLB, 2000, An overview of Santalum album research

in Sri Lanka, Sandalwood Research Newsletter, Issue -11 (Lead Article), Department of conservation

and Land management, Western Australia.25. Bambaradeniya, CNB, Ekanayake, SP, Fernando, MMJ, Kekulandala, B, Samarawickrama, P,

Ratnayake, N, Assesment of biodiversity in the Muthurajawela wetland sanctuary, Proceedings of the

6th annual Forestry and Environmental symposium, 29-30, December, 2000, Kandy.26 Tennakoon, KU, Ekanayake, SP, Etampawala, ERLB, 2000, An over veiw of Santalum album research

in sri ianka. international Sandlwood Research Newsletter Vol. 11,2-3.27 Etampawala, ERLB, Tennakoon, KU, Gunathileke, IAUN, Gunathileke, CVS, Ekanayake, SP, 2000,

Germination and seedling ecology of Santalum album. Proceedings of the Annual Sessions 2000, Universitiy of Peradeniya. Pp. 196.

28 Tennakoon, KU, Etampawala, ERLB, Gunathileke, CVS, Gunathileke, IAUN, Ekanayake, SP, 2001, Some biological aspects of economically important woody hemiparasite Santlam album L, Proceedings

of the 7th International Parasitic Weed Symposium 2001. Nantes, France. Pp. 15-18.29. Bambaradeniya, CNB, Ekanayaka, SP, Kekulandala, B, Fernando, MJJ, Samarawickrama, P,

Ratnayaka, N, 2000, Assessment of biodiversity in the Muthurajawela Wetland Sanctuary, Proceeding

of the sixth Annual Forestry and Environment Symposium 29 - 30 December, 2000, University of Sri Jayawardenapura, Colombo.

30 Bambaradeniya, CNB, Ekanayake, SP, Kekulandala, LDCB, Fernando, RHSS, Samarawickrama, VAP, Priyadarshana, TGM, Ranawana, KB, 2001, Biodiversity oftheMaduganga mangrove wetland, Proceedigs of the seventh annual forestry and environmental symposium, 28-29, December, 2001, University of Sri Jayawardenepura, Colombo.

31 Bambaradeniya, CNB, Ekanayake, SP, Fernando, Somaweera, R, Perera, N., 2001, Biodiversity of the Bundala national park and RAMSAR wetland, Proceedings of the seventh annual forestry and

27

Page 54: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

environmental symposium, 28*29, December, 2001, University of Sri Jayawardenepura, Colombo.32 Ranawana, KB, Ekenayake, SP, 2001, Impact ofMahweli Diversion scheme on biological diversity of

downstream flood plains and associated Villus, Proceedings of Seventh Annual Sympsium on Forests

and environment, 28-29, December, 2001, organized by Department of Forestry and Environmental Science, University of Sri Jayawardanapura, Colombo, Sri Lanka.

33. Bambaradeniya, CNB Ekanayake SP, Fernando RHSS, Somaweera, R, Perera, N, 2001, Biodiversity

o f Bunda la N ationa l Park and Ramsar wetland, Proceedings of Seventh Annual symposium of the

Department of Forestry and Environmental Science, University of Sri Jayerwardenepura, Colombo, Sri Lanka.

34. Bambaradeniya, CNB, Ekanayake, SP, Kekulandala, LDCB, Fernando, RHSS, Samarawickrema,VAP, Priyadhadharshana, TGM, Ranawana, KB, 2001, Biodiversity ofMaduganga wetland,Proceedings of Seventh Annual Sympsium on Forests and Environment organized by Department of Forestry and Environmental Science, University of Sri Jayerwardenepura, Colombo, Sri Lanka.

35. Kumararathne, A, Dayananda, LPD, Ekanayake, SP, Bambaradeniya, CN8, Wijesooriya, A, 2003, Innova tions and app lica tion of participatory economic planning for conservation of biodiversity and water resou rces in the Knuck les Man and Biosphere Reserve, Sh Lanka, Paper presented at the Global Biodiversity Forum held in Bangladesh, Dhaka, 16-18 June, 2003,

36. Ekanayake, SP, Bambaradeniya, CNB, Perera, WPN, Perera, MSJ, Rodrigo, RK, Samarawickrama, VAMPK, Peiris, TN, 2005, A B iod ive rs ity S ta tus P ro file o fLunam a - Kalametiya Wetland Sanctuary, Occasional Papers of IUCN Sri Lanka, No. 8, July 2005, IUCN - The World Conservation Union, Sri Lanka Country Office, Colombo,

37. Ekanayake, SP, Angammana.D., Fernando, S., Samarawickrama, P., Perera., N., Perera,S., 2005, Sustainable of ex traction o f non -tim ber fo res t p roduc ts (N TFP ) in Dipterocarp-dominant lowland rain

forests - a case s tudy in sou thw este rn low land ra in fo res t in Sri Lanka, Proceedings of 8th Round-Table

Conference on Dipterocarps, 15-17 November 2005, Ho Chi Minh City, Vietnam, Asia Pacific

Association for Forestry Research and Information, Malaysia.38. Ekanayake, SP, Perera, MSJ, Bambaradeniya, CNB, Rodrigo, RK, Samarawickrama, VAP, Asela,

MDC, 2006, Protective func tion o f natural coastal ecosystems against the impact of tsunami: A case

study from Medilla to Godawaya in South-eastern Sri Lanka, Proceedings of of 10th Anniversary

International symposium, Sabaragamuwa University of Sri Lanka, Belihuloya, Sri Lanka.39 . Ekanayake, SP, Kekulandala, B, Perera, N, Goonatilleke, S, Chandranimal, D, Asela, C,

Wickrqmasinghe, M, Karunaratne, S, Samarawickrama, VAP, Bambaradeniya, CNB, 2007, An

assessment of biological, archeological and hydrological resources of Wilpattu National Park, Proceedings of Wildlife symposium (July 2007) of Protected area management and wildlife

conservation project, Department of wildlife conservation, Colombo.

s

28

Page 55: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Project reports:Ekanayake, S.P., 1986. In-vitro propagation of potato and cassava. A report submitted to the Department of Botany, University of Peradeniya, based on Undergraduate Laboratory Training Programme at Central Agricultural Research Institute, Gannoruwa (September-October, 1986),

Ekanayake, S.P., 1991, Documentary survey on Artocarpus heterophyifus, a report submitted to the Dean

Faculty of Agriculture, University of Peradeniya,

Sumithraarachchi, D.B., Ekanayake, S.P., Ratnayake, H.D., 1991, Floristic composition of Randenigala Islands

(Part 1), a report submitted to the Department of Wildlife Conservation, Colombo.

Balasubramaniam, S., Sumithraarachchi, D.B., Ekanayake,Floristic survey of Knuckles region, Final report based on field survey in Knuckles region submitted to the Forest department/IUCN, Colombo.

S.P., Ratnayake, H.D., Kalansuriya, S., 1992,

Sumithraarachchi, D.B., Ekanayake, S.P., Ratnayake, H.D., 1993, Survey on medicinal plants * intermediate &

montane zones of Sri Lanka. A report submitted to WWF/ Medicinal plants project, Colombo,

Ekanayake, S.P., 1994, Fundamentals of conservation of medicinal plants (in Sinhala); a practical guide to

middle level officers, a manuscript submitted to the Director, National Botanic Gardens, Peradeniya.

GEF/UNDP/DWLC, 1998, Resource inventory of Victoria- Randenigala- Rantembe sanctuary, A consultancy

report submitted to the Department of Wildlife Conservation in Sri Lanka (DWLC), (Co-Author of the floristic

study).

Rjapakse, H.A., Ekanayake, S.P, Adikari, S.B., Tennakoon, N., 1998, Reconnissance survey of land use and

land ownership in Hambantota district., DFID(UK) / ENDEV and Environment and Forest Conservation Division, Mahaweli Authority, Polgolla. (A project report done for DFID office in Thailand,)

Ekanayake, S.P, Ranawana, K.B., 1999, Guidelines for artificial flood release from reseviors to maintain

downstream wetland ecosystems and dependent livelihoods- Case study: influences of biodiversity of Mahaweli system in Sri Lanka.[A project report submitted to DFID(UK), Institute of Hydrology(UK) and NRMS Pvt.Ltd.,Polgolla].

Ekanayake, S.P., 2000, A plant ecological study of Muthurajawela wetlands, A report submitted to The World

Conservation Union (IUCN), Colombo.

Ekanayake, S.P., Helarawa, H.M.C.A.B, Ubayawardena, K., Karunaratne, S., Biodiversity GIS database of Mahaweli River 8asin of Sri Lanka, Technical Reports 4 volumes, EFCD/MASL/ NRMS, Polgolla.

Ekanayake, S.P, Ranawana, K.B., 1999, Guidelines for artificial flood release from reseviors to maintain

downstream wetland ecosystems and dependent livelihoods- Case study: influences of biodiversity of Mahaweli system in Sri Lanka.[A project report submitted to DFID(UK), Institute of Hydrology(UK) and NRMS Pvt.Ltd.,Polgolla).

Ekanayake, S.P., 2000, A plant ecological study of Muthurajawela wetlands, A report submitted to The World

Conservation Union (IUCN), Colombo.

Ekanayake, S.P., 2001, A plant ecological study of Maduganga wetlands, A report submitted to The World

Conservation Union (IUCN), Colombo.

Ekanayake, S.P., 2001, A plant ecological study of Bundala sanctuary, A report submitted to The World

Conservation Union (IUCN), Colombo.

Ekanayake, S.P., Helarawa, H.M.C.A.B, Ubayawardena, K., Karunaratne, S., 2000-2001, Biodiversity GIS

database of Mahaweli River Basin of Sri Lanka, Technical Reports 6 volumes, EFCD/MASL/ NRMS, Polgolla.

2 9

Page 56: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Ekanayake, S.P., Helarawa, H.M.C.A.B, Ubayawardena, K., 2001, Executive report of the projector! development of a natural resources GIS data base to facilitate effective ecological assessment of Mahaweli River Basin (MRB), EFCD/MASL/ NRMS, Polgolla.

E lec tron ic m ed ia :

Ekanayake, S.P., Helarawa, H.M.C.A.B, Ubayawardena, K., Plant biodiversity GIS database of Victoria -

Randenigala - Rantembe sanctuary of Sri Lanka, Data base at EFCD/MASL, Polgolla.

Ekanayake, S.P., Helarawa, H.M.C.A.B, Ubayawardena, K., Karunaratne, S., Plant biodiversity GIS database of Mahaweli River Basin of Sri Lanka, Data base at EFCD/MASL/ NRMS, Polgolla.

Certification:

I, the undersigned, certify that to the best of my knowledge and belief, this CV correctly describes myself, my

qualifications and my experience. I understand that any willful misstatement described herein may lead to my

disqualification or dismissal, if engaged.Date.

[Signature of staff member]

Date 22nd February, 2019

[Signature of authorized representative of the client]Full name of authorized representative: Shamen Vidanage

30

Page 57: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

CURRICULUM VITAE (CV)

Proposed position:

Name of firm:

Name of staff:

Date of Birth:

Fauna Ecologist

IUCN, International Union for Conservation of Nature

Naalin Perera

09 November, 1975 Nationality: Sri Lankan

Education

■ Master of Art of Management and Leadership (conferred 2011)YORK ST-JOHN UNIVERSTY

■ Bachelor of Science Degree (conferred 2005) -Subjects - Botany, Zoology

OPEN UNIVERSITY OF SRI LANKA

Memberships of professional associations:■ IUCN Commission of Ecosystem Management Group (since January 2012)■ Sheffield Bird Study Group (2012)■ Young Zoologists' Association of Sri Lanka (from 1993 to 2002)- President (2000), Vice President-

Research (2002), Vice President- Environmental Action (1999) and Committee member (1997)

Other TrainingMedia Training - Conducted by IUCN Asian Regional office on 18 August 2008 to 22 August 2008

at Windsor Hotel, Sukhumvit in Thailand. (Resource Personals Ms. P. Borjana and Mr. Brian

Thomson from IUCN HQ)Use of Environmental Economics for Watershed management - workshop organised by Post­graduate Institute of Agriculture, University of Peradeniya and lUCN-The World Conservation

Union, 28th -30th June2005.Followed the Environmental Education Program of the Young Zoologists’ Association in the fields

of Aquatic Fauna (1994-1995) and passed final examination with Distinction. .Sixteen year experience in conducting biodiversity surveys for both terrestrial and aquatic eco

systems.Experience in conducting Biodiversity and other relevant training and lectures for School Children, Communities and Government officers.Project management and implementation.

Countries of Work Experience: Sri Lanka and UK

Languages: Speak ing Read ing

GoodW riting

GoodEnglishSinhalese

GoodMother tongue

Employment record:

IUCN, Sri Lanka country office from January 2001 to January 2010

(From January 2001 to April 2004 consultancy basis

Since April 2004 to January 2010 full time basis as Assistant Programme officer)

IUCN - International Union for Conservation of Nature - Communication Focal Point from July 2008 to January

2010.1 had to coordinate all scientific and general media and communication work while carry out other project level activities.

IUCN - Puttalam Lagoon Ecosystem Restoration Project (BMZ) - Communication, Biodiversity assessment and

Fisheries activity

3 1

Page 58: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

IUCN - East Coast Ecosystem Restoration Project (CIDA) - Biodiversity assessment, Ecosystem Restoration

and Communication

IUCN - International Union for Conservation of Nature - Red list Compiler 2004 - 2007 (Preparation of the 2007

Red list of Threatened Fauna and Flora of Sri Lanka -

Reptiles, Mollusk)

IUCN - International Union for Conservation of Nature - Field Ecologist December 2007 (Biodiversity

Assessment of the Panama Coastal Lagoon System - Fishes and Butterflies)

IUCN - International Union for Conservation of Nature - Field Ecologist December 2006 (Biodiversity

Assessment of the Moragahakanda Irrigation Extension Project-Freshwater fishes, Butterflies, Freshwater Crabs, Dragonflies)

IUCN - International Union for Conservation of Nature - Field Ecologist December 2004-2005 (Preparation for Resource Inventory for the Wilpattu National Park- Freshwater fishes, Butterflies, Dragonflies)

IUCN - International Union for Conservation of Nature - Field Ecologist 2004 (Biodiversity Assessment of the

Puttalam Lagoon area- Lagoon fishes, Butterflies)

IUCN - International Union for Conservation of Nature - Field Ecologist December 2003- February 2004 (Bio

Diversity Monitoring of Rakawa Kalamatiay Ussangoda wetland systems- Fishes, Butterflies)

IUCN - Field Ecologist December 2003- February 2004

(Bio Diversity Monitoring of Rakawa Kalamatiay Ussangoda- Fishes and Butterflies)

IUCN- International Union for Conservation of Nature - Field Ecologist20Q3 October- 2004 February (Bio

Diversity Assessment of Anawilundawa Santuary and Ramsar site - Fishes, Aquatic Mollusk, Butterflies, Dragonflies)

IUCN- International Union for Conservation of Nature - Field Project Coordinator 2002-2003 (Bio Diversity

Assessment of Rakawa Kalamatiay Ussangoda - Fishes, Butterflies)

IUCN- International Union for Conservation of Nature - Field Ecologist 2003

(South-east Rain Forest Conservation Project - Fishes and Butterflies)

IUCN- International Union for Conservation of Nature - Mobile Unit Coordinator 2002- July (Small Cetacean

Conservation Project II Phase) Sinhalese

IUCN- International Union for Conservation of Nature - Field Technical Assistant 2001 (January to April) (Bio

Diversity Assessment of Bundala National Park - Fishes and Butterflies)

NSRC -1998 to1999 Field Ecologist for Nikapotha Analog Forestry Project

Fresh-water fishes, Butterflies, Serpentoied

Certification:

I, the undersigned, certify that to the best of my knowledge and belief, this CV correctly describes myself, my

qualifications and my experience. I understand that any willful misstatement described herein may lead to my

disqualification or dismissal, if engaged.Date.

[Signature of staff member]

Date 22nd February, 2019

[Signature of authorized representative of the client]Full name of authorized representative: Shamen Vidanage

!32

Page 59: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

CURRICULUM VITAE (CV)

Proposed position: Name of firm:Name of staff:

Fauna EcologistIUCN, International Union for Conservation of Nature

Attanayaka Mukaweti Sahabandu Mudiyanselage Rohana Wasnatha

Jayasekara

Date of Birth: 30th July 1971 Nationality: Sri Lankan

Education

• Master of Environment Management, (MEM). Faculty of Graduate Studies - University of Colombo, Sri Lanka, (2015-2016).

• Post Graduate Diploma in Environment Management, (PGDEM) Faculty of Graduate Studies - University of Colombo, Sri Lanka, (2013-2014),

• Diploma in Biodiversity Management at the University of Colombo, Sri Lanka (2008).• Certificate in Wildlife Conservation & Management, from the Open University of Sri Lanka (2003).• Scuba Diving Ministry of Fisheries and Aquatic Resources Development-National institute of fisheries

training: conducted by the Fisheries Training Centre Negambo (1998).

Memberships of professional associations:■ IUCN Commission of Ecosystem Management Group (since January 2012)■ Sheffield Bird Study Group (2012)■ Young Zoologists' Association of Sri Lanka (from 1993 to 2002)- President (2000), Vice President-

Research (2002), Vice President- Environmental Action (1999) and Committee member (1997)

Other TrainingMedia Training - Conducted by IUCN Asian Regional office on 18 August 2008 to 22 August 2008

at Windsor Hotel, Sukhumvit in Thailand. (Resource Personals Ms, P. Borjana and Mr. Brian

Thomson from IUCN HQ)Use of Environmental Economics for Watershed management - workshop organised by Post­graduate Institute of Agriculture, University of Peradeniya and lUCN-The World Conservation

Union, 28th -30th June2005.Followed the Environmental Education Program of the Young Zoologists' Association in the fields

of Aquatic Fauna (1994-1995) and passed final examination with Distinction,Sixteen year experience in conducting biodiversity surveys for both terrestrial and aquatic eco

systems.Experience in conducting Biodiversity and other relevant training and lectures for School Children, Communities and Government officers.Project management and implementation.

Countries of Work Experience: Sri Lanka and UK

Languages: Speak ing R ead ing

GoodW riting

GoodEnglishSinhalese

GoodMother tongue

Professional / Working Experience

• I possess approximately 25years of research experience in the fields of ecology and biodiversity. My specific

experiences include:

33

Page 60: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Works Carried Out

• Conducting field Research on Land snail/ marine fauna and flora which include systematic surveys, fauna

and flora identification, data collection and data analyzing.• Preparing regular progress reports and research publications and scientific communication.

• Conducting awareness program and lectures for schools and general public.

• Field level communication with all related sectors

• Worked as an Ecologist, Fauna and Flora Survey of Proposed Elevated Highway from Rajagiriya to

Athurugiriya, under,RDA 2019.• Worked as an Ecologist Ecological Baseline survey and Critical Species rescue in Kaluganga,

Moragahakanda transit cannel project.(KMCT), under Mahawali Water Security Investment Project (MWSIP) 2018.

• Worked as an Ecologist,, Fauna and Flora Survey of Colombo suburban Railway Project, KV Line, under, Department of Railway.2018

• Worked as an Ecologist, Initial environmental examination (IEE) of the proposed town east of Polonnaruwa

- water supply project.2018• Worked as an Ecologist, Environment Assessment for the Proposed Hemmathagama Water Supply Project,

under EML(PVT) LTD.2017• Worked as Flora Specialist, Fauna and Flora Survey of Southern Expressway Extension Project, Section 3,

From Wetiya to Andarawewa, Matara District and Hambanthota District, Land Owners Restore Rainforests in

Sri Lanka (LORRISL) 2016• Worked as Flora Specialist, Fauna and Flora Survey of Southern Expressway Extension Project, Section 4,

From Hambanthota Port to Mattala Airport, Hambanthota District, Land Owners Restore Rainforests in Sri Lanka (LORRISL) 2016

• To conduct district level training programmers on control and management of Invasive Alien Species.Under Janathakshan (Guarantee) Limited. 2016.

• Worked as an Ecologist, Invasive species assignment in North Western province under EML (PVT) LTD.2016.

• Worked as Flora Specialist, Fauna and Flora Survey of Southern Expressway Extension Project, Section 1, From Matara to Beliatta, Matara District, China National Aero-Technology International Engineering

Corporation (CATIC), Land Owners Restore Rainforests in Sri Lanka (LORRISL) 2015• Preparation of invasive Fauna list Biodiversity secretariat (BDS) of the State Ministry of Environment.Sep-

2015• Worked as a Fauna specialist for the Metro Colombo Urban Development Project (MCUDP),Under the

Ministry of Defense and Urban Development. 2015,Q Worked as a Fauna specialist forthe Per Aru biotic survey and Threatened species rescue and translocation

program at Vauniyawa, Conducted by Dry zone urban water and sanitation project, funded by Asian

development bank (ADB), Jan-Apr 2011, Jan 2013 and Sep-Oct 2015.

WORKED AS A FIELD ECOLOGIST FOR THE (IUCN), THE WORLD CONSERVATION UNION,• INSEE- Arwakkalu Quary biodiversity survey and animal rescue programme, Fauna expert!

; 2 0 1 8 .

• Megapolis-Aruwakku Animal rescue Programme, fauna expert.2018• INSEE- Arwakkalu Quary biodiversity survey and animal rescue programme. Fauna expert

• 2 0 1 7 .

• The Preparation of Wildlife Management Plan with special emphasis on Human Elephant Confict

Management Plan for Northwestern Province Canal Projects.2017

34

Page 61: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

The Preparation of Wildlife Management Plan with special emphasis on Human Elephant Confict

Management Plan Upper Elahera Canal. (UEC) 2017

Annual Ecological assessments of mining areas and animal rescue programe of Aruwakkalu

site of Holcim lanka limited, (2016).Annual Ecological assessments of mining areas and animal rescue programe of Aruwakkalu

site of Holcim lanka limited, (2015).Preparation of a Wildlife management Plan (WMP) and a Monitoring Programme for the Yan Oya

Reservoir Project, (2014).Annual Ecological assessments of mining areas and animal rescue programe of Aruwakkalu

site of Holcim Lanka limited, (2014).Annual monitoring of ecological recovery of restored areas and establishment of new sapling plots in the

newly restored areas and provide basic training to Holcim lanka limited staff on ecological monitoring of the plots.of Aruwakkalu quarry site of Holcim Lanka limited, (2014).Worked as a Data Compiler in preparation of the ‘Moragahakanda and Kalu Ganga Biodiversity Action

Plan Implementation project, final report. Conducted by the IUCN - The World Conservation Union, (20.1.4). - .Monaragala biodiversity survey, Monaragala district. In collaboration with Central environmental authority,(2014),Hantana biodiversity survey, Kandy district. In collaboration with Central environmental authority, (2013). Annual Ecological assessments of mining areas and animal rescue programe of Aruwakkalu quarry site

of Holcim lanka limited, (2013).Threatened species rescue and translocation program of Moragahakanda Reservoir and Agriculture

Development Project (MADP) of Mahaweli authority, Matale district. (2012-2013).

Threatened species rescue and translocation program of Kalu Ganga Reservoir and Agricultural Extension Project (KAEP) of Mahaweli authority, Matale district. (2012-2013).Annual Ecological assessments of mining areas and animal rescue programe of Aruwakkalu quarry site

of Holcim lanka limited, (2012).

Biodiversity assessment of Mangrove ecosystem around the Galle Holcim cements plant, Holcim Lanka

Limited. Galle district, (2012).

Biodiversity assessment of the Old quarry area and northern artificial water body at Aruwakkalu quarry

site. Puttlam district. Holcim Lanka Limited, (2012).Biodiversity assessment of Nainamadu forest reserve in Vavuniyawa district. August, (2012),Biodiversity assessment of proposed road construction work under new clinker plant at Aruwakkalu quarry

site, Holcim Lanka Limited, (2012),Biodiversity Assessment of Haycock forest reserve, Hiniduma, (2011 - 2012).Annual monitoring of ecological recovery of restored areas of Aruwakkalu quarry site of Holcim lanka

limited, (2011).Annual Ecological assessments of mining areas and animal rescue programe of Aruwakkalu quarry site

of Holcim lanka limited, (2010).Biodiversity Assessment in the Moragahakanda Agriculture Expansion Project (MAEP). Matale district. Conducted in collaboration with the Mahaweli Authority of Sri Lanka, (2006 - 2007),GEF/RUK Biodiversity Assessment Monitoring Component (Sub-tidal) in the Southern Coast of Sri Lanka, GEF/RUK Biodiversity Assessment Monitoring Component-First Phase, in the Southern Coast of Sri Lanka.Conservation and sustainable use of the Anawilundawa Sanctuary, Puttlam, Sri Lanka

GEF/RUK Biodiversity Assessment Project in the Southern Coast of Sri Lanka-A base line survey, (2002­2006).Biodiversity Monitoring Project in Rekawa, Ussangoda and Kalamatiya Areas in Southern Sri Lanka

carried out by IUCN - The World Conservation Union, (2005).Worked as a Marine and Terrestrial Ecologist at The world conservation union (IUCN) (2003-2004), Worked as a Biodiversity Assessment in Rekawa, Ussangoda and Kalamatiya Areas by the The world

conservation union (IUCN), (2003),

quarry

quarry

quarry

35

Page 62: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

• Field Ecologist, SMEC International Pvt.Ltd. ADB Assisted Dry Zone Urban Water Supply and Sanitation

Project: Design, Construction, Supervision and Management Support (Package A), Per Aru Biotic Survey, Funded by Asian Development Bank (ADB), (2011).

• Working as a Field Ecologist - Research Assistance in Seahorse diversity and ecological survey in coastal marine habitats in Sri Lanka conducted by the Project Seahorse UK and Linnaeus University of Sweden. (2009-2010)

• Worked as a Research Assistance in project "Wild related plant" at Royal Botanical Garden, Peradeniya, Sri Lanka (2007-2008).

• Sociological survey enumerator- Community surveys for Anuradhapura-Trincomalee (A12) road and

Hatlon-Nuwara eliya (A7) road conducted by the Environment Management Limited (EML), Colombo 4. (2007).

• Worked as a Technical Assistance (Fish Fauna) to the Protected Area Management and Wildlife

Conservation Project, InfoTech Ideas Pvt. Ltd. Sri Lanka, funded by, (ADB), (2006-2007).• Worked as a Technical & Field Researcher on the UK Government funded Darwin Initiative Project on Sri

Lankan land-snail diversity, a three year collaborative program between the Department of National Museums, the Postgraduate Institute of Science, Peradeniy, The Department of Zoology, University of Peradeniya and the Natural History Museum, London (1999 - 2002).

• Worked as a "Community & extension Officer" on the Upper Watershed management Project of the

Ministry of Forest & Environment (1999),• Worked as a “Community & Environmental Officer” on a coral reef project (Bonavista coral reef in Galle)

run by the Neo Synthesis Research Centre (NSRC), Mirahawatta, Bandarawela (1998).• Worked as a Field Officer Promoting Analog forestry & Organic, at the Neo Synthesis Research Centre

(NSRC), Mirahawatta, Bandarawela (1997).• Worked as a "Community & extension Officer" in the “Small Forest Conservation and Analog Forestry

Extension Project in Rathnapura District", which was jointly conducted by the Young Zoologists

Association (YZA), Neo Synthesis Research Centre (NSRC) and Asia Foundation in (1995).• Worked as an Organic farming and community Development instructor at Sarvodaya, 47, Springvally

Road.t Badulla, (1993).• Worked as a Community Development and External Environmental Instructor at Plan International,

Badulla (1992- 1994).

PARTICIPATED lEE'S AND EIA’S

• Southern province road upgrade project conducted by road development authority (RDA), funded by Asian

development bank (ADB), April 2014.• Biodiversity survey and forest patch inter connecting project of Endana estate of Kahawatta plantations, MJF

group of companies, (Dilma). December, 2013• Threatened species rescue and translocation program of Per Aru biotic survey area Vavuniyawa, Conduted

by Dry zone urban water and sanitation project, funded by Asian development bank (ADB), June-Aug 2013. Maduru oya biodiversity survey, conducted by the Mahaweli consultancy bureau (MCB), May 2013

Biodiversity survey of MAS industrial zone, warakapola. May 2013IEE for the Ella eco village park, Conducted by Green Taproben (Pvt.) Ltd. Ella gap hotel, Ella, September, 2011.Detailed biodiversity study on abundance and biological Patterns / wildlife in the proposed Kalu Ganga

reservoir under Environmental Management Limited (EML) and Mahaweli River Basin Authority, 2010.o

EXTRA CURRICULAR ACTIVITIES

o Member of Young Zoologists Association (YZA), National Zoological Gardens, Sri Lanka, Since 1997 and

as such participated in following:o Followed the course on “Wildlife and Environmental Conservation” conducted by the YZA. o Participated in various research and educational programs conducted by the YZA.

36

Page 63: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

Participated in School awareness programs conducted by the YZA.Volunteer in Fire Fighting program at the Horton’s plains national Park in 1998, a collaboration between

the YZA and the Department of Wildlife Conservation.Participated in annual photography exhibitions -YZA - since 1997.Followed a Six month Professional photographic Course held by the UVA photographic Art Society Since

1997.Participated in the “Kacha Sithuam" annual photographic exhibition held by the society.Presently working as a senior photography instructor at YZA since 2005.

oo

OTHER RESEARCH EXPERIENCE

o A study of Land Snail Fauna in Kanneliya Forest Reserve and Their Conservation Extended Essay submitted

in Partial fulfillment of the Course of Study leading to the Postgraduate Diploma in Environment Management (PGDEM). University of Colombo.2012.

o Participated in the Elephant Survey carried out in the central region, conducted by the Department of Wildlife

Conservation (DWC), 2011. •o A Literature Review of Studies on Diversity of land snail fauna in sir lanka. The dissertation submitted to the

University of Colombo as a fulfillment of the part of Diploma in Biodiversity management 2008.

• Voluntary participated in the project on Effect of forest patch size on the abundance and diversity of mammalian carnivores and ecosystem awareness and Attitudes towards wildlife: a comparison of children

from rural areas and cities, Projects conducted by the American Institute for Lankan Studies, Suleiman terrace, Jawaththa, Colombo 7, Sri Lanka. 2004-2006,

• Participated in the Elephant Survey carried out in the north-western region, conducted by the Department of Wildlife Conservation (DWC), 2005.

• Participated in the project on Elephant Conservation in South-east Dry Zone of Sri Lanka conducted by the

Environmental Studies Unit of the Open University of Sri Lanka (OUSL), 2004.• Voluntary participated in the project on Distribution of Wild Cats in Different Bio-climatic Regions of Sri

Lanka conducted by the Environmental Studies Unit of the Open University of Sri Lanka (OUSL), 2003-2004.• A study of Land Snail Diversity in Kanneliya Rain Forest The dissertation submitted to the Open University of

Sri Lanka (OUSL), for the certificate course in wildlife conservation and management, 2003.• Worked as a resource person for the Survey Project of the Fish Species, Pun tius bandu ta in Wet Zone, Sri

Lanka conducted by the Young Zoologist Association of Sri Lanka (YZA) and the Department of wildlife

Conservation (DWC), 2000.• Participated in the Assessment of Invasive Plants of Horton Plains National Park carried out by Young

Zoologist Association of Sri Lanka (YZA), 1999.• Volunteered as a Field Researcher / resource person in biodiversity assessments and other Environmental

programs conducted by the Young Zoologist Association of Sri Lanka (YZA) of Sri Lanka since 1997

Workshop and Symposium Attended

INTERNATIONALParticipation on 3rd Asian Lepidoptera Conservation Symposium and Training Programmed Held

at Bharathiar University. Coimbatore 25-29 October (2010).Participation on Ninth Annual Conference of The South Asian Zoo Association for Regional Cooperation"fSAZARC) held in National zoological Garden. Sri Lanka in (2009).I have attended a three week course of training in land snail curation and preservation techniques at the National History Museum, London, UK, (2001).

o

o

LocalNational Symposium on Invasive Alien Species. Sri Lanka Association of Advancement of Science, National Science Foundation (IAS 2008).

37

Page 64: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

National Workshop on Current Status of Marine Fauna in Sri Lanka, Organized by The Ministry ofEnvironment and Natural Resources in collaboration with, The World Conservation union (IUCN), 17th

August (2004).Forest Garden Product Certification Workshop. Conducted by the Neo Synthesis Research Centre

(NSRC), Bandarawela, Sri Lanka, (1999),Participated in Workshop on Analog Forestry, landscape Designing and Integrated Resource

Management held by the Neo Synthesis Research Centre (NSRC), Asia Foundation, and Natural Resource & Energy Policy Project in (1997).Followed six month Training course in participatory Rural Appraisal held by the Integrated Rural development project (IRDP), Badulla, in (1996).

o

o

PUBLICATIONS ON NATIONAL AND INTERNATIONAL

• Worked as a Land snail group in preparation of The National Red List 2012 of Sri Lanka,"C onse rva tions !

s ta tus o f the Fauna and F lo ra”. This publication has been prepared by the Biodiversity Secretariat of the

ministry of Environment in Collaboration with the National Herbarium, Department of National Botanic

Gardens, (2012).• Worked as a Preparation of the A guide to the Pest and Exotic Gastropods of Sri Lanka, From 1999 to

2002 the Darwin Initiative funded the project Land sna il d ive rs ity in S ri Lanka , run by The Natural History

Museum in London, The Department of National Museums and The University of Peradeniya,(2003).• Worked as a Preparation of the Sri Lankan Snail photography guide. From 1999 to 2002 the Darwin Initiative

funded the project Land sna il d ive rs ity in S ri Lanka , run by The Natural History Museum in London, The

Department of National Museums and The University of Peradeniya, (2002).• Worked as a preparation of the Land snail diversity in Sri Lanka, An illustrated guide prepared for the launch

of the Darwin Initiative programmer, The Natural History Museum London, SW7,5BD.UK (2000).

PAPERS APPEARED IN JOURNALS• Subhani Ranasingha, Richard Milne, Rohana Jayasekara, Sumudu Rubasingha and Michael Moller.2016.

H ancke lia w ijesunda rae. A new Endemic species (Gesneriaceae) from Sri Lanka, and lectotypification of C h irita w atke rae and C, w atke rae var.pa/viflora.Willdenowia.46(2);213-224,DOI:10.3372/wi.46.46202

• FIRST SUBSTANTIATED RECORD OF C eriops decandra (RHIZOPHORACEAE) IN SRI LANKA.S. P. Ekanayakel, 2, W. L. D. P. T. S. deA. Goonetiltekel, A. M. S. M. R.W. Jayasekeral, M. D. C. Aselal, A. L, Pierisl & K. M. A. Bandaral

• Asela, M. D.C., R.A.K. Peiris, S.K.I.U. Priyankara, R.W. Jayasekara & D.M.S.S. Karunarathna (2007). Some

notes on the butterflies (Lepidoptera: Papilionidea) of Tantirimale Archaeological site, Anuradapura District in

Sri Lanka. Journal of threatened taxa 1(7): 392-394• Faunal diversity of the Nainamadu Forest Reserve, Vavuniya District, Avanti Wadugodapitiya, Sampath de A

Goonatilake, Chandana Asela and Rohana Jayasekera (2013), IUCN Sri Lanka Country Office, 53, Horton

Place, Colombo 7• Euphorb ia n ivu lia Buch.-Ham. (Euphorbiaceae) - A new addition to the flora of Sri Lanka S.P. Ekanayakel,

M.D.C. Asela5, A. LT.N. Pieris2, W.L.D.P.T.S. de A. Goonetilleke3, A.M.S.M.R.W. Jayasekera4, Pieris6 and A. Bandara7(2015),ZOO’s PRINT,

CURRENT RESEARCH INTEREST• Ecology and conservation of Sri Lankan land snails and Herpetology.• Ecology and conservation of coral reef fishes.• Environmental conservation / Habitat restoration.• Human impact on Biodiversity• Ecosystem restoration and remediation

Certification:

I, the undersigned, certify that to the best of my knowledge and belief, this CV correctly describes myself, my

3 8

Page 65: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

ff

qualifications and my experience. I understand that any willful misstatement described herein may lead to my

disqualification or dismissal, if engaged.

Date.

[Signature of staff member]

Date 22nd February, 2019

[Signature of authorized representative of the client]Full name of authorized representative: Shamen Vidanage

3 9

Page 66: Environmental Compliance Audit Report and Corrective ... · Project duration Six weeks from signing the contract between MWSIP and IUCN, except the time taken by MWSIP for review

IUCN, International Union for Conservation of Nature

IUCN, International Union for Conservation of Nature was founded in 1948, IUCN helps the

world find pragmatic solutions to our most pressing environment and development challenges,

It supports scientific research, manages field projects all over the world and brings

governments, non-government organizations, United Nations agencies, companies and local

communities together to develop and implement policy, laws and best practice.

IUCN is the world’s oldest and largest global environmental network - a democratic

membership union with more than 1,000 government and NGO member organizations, and

almost 11,000 volunteer scientists in more than 160 countries.

lUCN's work is supported by more than 1,000 professional staff in 60 offices and hundreds of

partners in public, NGO and private sectors around the world. The Union’s headquarters are

located in Gland, near Geneva, Switzerland.

In Sri Lanka, through its Country Programme the Union seeks to fulfil this mission in

collaboration with its various Commission Members, National Committee Members and

Partners in Sri Lanka. IUCN in Sri Lanka commenced its operations since August 1988.

^IIJCN

INTERNATIONAL UNIONFOR CONSERVATION OF NATURE

Sri Lanka Country Office

No.53 Horton Place

Colombo 7

Sri Lanka

f>}Tel. +94 11 2682418, 2682488,

5734786 Fax +94 11 2682470

[email protected]

http://www.lucn.ora/srilanSystomus martenstyni, an endemic and Critically

Endangered fishka

40