environmental and social management plan construction of a
TRANSCRIPT
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 1 of 41
Environmental and Social Management Plan
Construction of a new Dormitory at Ilukkumbura,
Knuckles Forest Reserve
Ecosystem Conservation and Management project - (ESCMP)
Ministry of Wildlife and Forest Conservation
Forest Department
Sampathpaya, Rajamalwatta Road, Battaramulla
Forest Department
Samapathpaya
Rajamalwatta Road
Battaramulla
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 2 of 41
Content
Summary 4
1 Background of the project area 6
1.1 Introduction 6
1.2 Ecological importance of the site 7
2 Project Description 8
2.1 Project Objectives 9
2.2 Project Activities 9
2.3 Alternatives proposed by IUCN study for the design 13
3 Community Consultation 13
4 Potential Environmental Impacts of the Project and proposed mitigation 13
4.1 Pre-construction stage 13
4.2 Impacts during construction stage 14
5 Environmental Monitoring and Reporting 21
5.1 Construction Stage 21
5.2 Post-Construction Stage 22
6 Public Consultation 23
6.1 Consultation and Information Disclosure 23
6.2 Grievance Redress Mechanism 23
7 Conclusion and Recommendations 23
List of Tables
1 Summary of the level of impacts of different environment and social
parameters associated with the interventions
4
2 Identified Endemic and threatened faunal species in proposed activity
areas
7
3 Endemic and threatened flora species recorded within in proposed
activity areas
7
4 Summary of the sub project activity 9
5 Summary of key social and environmental impacts associated with the
subproject during construction stage
16
6 Construction Phase Monitoring 21
7 Sample Post – Monitoring Chart 22
List of Figures
1 Google map of the Illukkubura Conservation Center (Proposed site for
dormitory)
6
2 Old Dormitory and the Garage (Upper Picture) and The earmarked site
for the for the new dormitory (Below Picture)
9
3 Design of the ground floor of the building 11
4 Design of the first floor of the building 12
5 Design of the second floor of the building 12
Abbreviation
ADFO Additional District Forest Officer
BFO Beat Forest Officer
DFO Divisional Forest Officer
DWC Department of Wildlife Conservation
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 3 of 41
E Endemic
EN Endangered
ESCAMP Ecosystem Conservation and Management Project
EX Extinct
FD Forest Department
FPAM Field Based Protected Area management
LC Least Concern
NT Near threaten
PMU Project management Unit
RFO Range Forest officer
TO Technical Officer
VU Vulnerable
Contact Details of Responsible Officers
Position Name Contact No
Contractor
Divisional Forest Officer Mr. W.D.N.R. Prasad 0718319560
Additional Divisional Forest Officer Mr. T.A.K.J. Tennakoon 0712753076
Forester Mr. R.M.K.R. Ilukkumbura 0718064842
Range Forest Officer Mr. A.V.D. Amarasinghe 0763860222
Additional RFO R.D.S.C. Chandrasiri 0769880287
Beat Forest Officer A. A.A.D.R. Wasantha
Kumara
0776396858
Extension Officer Mr. A.M.U. Rangbanda 0716550151
Project Engineer (ESCAMP) Mr. S.K. Senadheera 0713052623
Technical Officer (ESCAMP) Mr. J.B.G. Manjula Dias 0713005595
Environment Officer (ESCAMP) Mr. Sameera Pemarathne 0719938138
Social Safeguard Officer (ESCAMP) Mrs. Srimathi Somathunga 0718072558
Environmental and Social Safeguard
Consultant / Specialist (ESCAMP)
Dr. Dunstan Fernando 0773021095
Note: Field Based Protected Area Managers (FPAM) of Knuckles are responsible together
with assigned Officers from the PMU, for supervision and monitoring of implementation of
the below mentioned ESMP. The PMU is further expected to provide a monitoring format to
the FPAM to keep records on monitoring and supervision.
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 4 of 41
Summary
The proposed site for the dormitory is located at Illukkubura in adjacent to the main road of
Mathale – Laggala through Riverstern, about 24km from the Mathale town within the Knuckles
Conservation Forest (KCF). The area represents unique ecological zone with the wet evergreen
forest in hilly terrain. The circuit bungalow located at the site
the center had high demand among local visitors. The bungalow was established in 1980s for
the use of Park Superintend before the area was declared as a Conservation Forest in 2000. The
building was renovated in 2001 and then it has been used as a circuit bungalow by the Forest
Department (FD) and open for visitors for overnight stay.
However, after 2001 the building was not renovated other than the small-scale annual
maintenance; resulting the quality of the building deteriorated and the number of visitors
reduced during the past few years.
The bungalow is located by the road to Meemure which is high demanded tourist destination.
Therefore, the demand of the bungalow could still be maintained if the building is renovated
properly. Increasing the visitation, it is obvious that it will directly and indirectly help uplift
the living condition of the local community. The villagers could have opportunities to sell local
products and rendering services to the visitors as an additional livelihood. With this background
FD has proposed renovation of the bungalow while improving the facilities for overnight
visitors.
The bungalow is located within the premises of KCF which has been recognized as highly
sensitive ecosystem. The renovation activities could course negative impact to the surrounding
environment of the KCF. Therefore, the possible environmental and social impact has been
assessed prior to launch the development and presented in this report with suitable mitigatory
measures.
The indigenous people or marginalized groups are not present within the area. Archeologically
significant places are also not present. Any land acquisition shall not be required for the
proposed renovation. Also, the project activities will not lead to any resettlement or loss of
livelihoods of villagers in the surroundings.
It is expected that the general public will not be disturbed since socio-economic activities are
not happening in the proposed project impact zone during the construction period. However,
locating the building in adjacent to a public road, precautions should be taken to control any
effect to the people who are passing the locality.
The level of impacts of different environment and social parameters associated with the
interventions are summarized in Table 1.
Table 1: Summery of the level of impacts of different environment and social parameters
associated with the interventions
Parameter Level of
Impact
Reason
Air Quality Low Most of the activities would be carried out
manually. and on a minor scale for a shorter
period of time. However material transportation
and site preparation could generate some air
pollution.
Water Quality Medium The project site is a prime water catchment and
perennial streams are flowing near by the project
sites.
Surface & ground water
quality
Low Sealed type septic tanks will be constructed away
from water sources
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 5 of 41
Private Lands and PA
Lands
Private Land
No impact
PA Land - Low
The activity will be carried out within the
boundary of KCF. No additional land is required.
Private land shall not be acquired.
Noise & Vibration Medium Construction activities may lead to certain amounts
of noise pollution when use machines for tilling,
fixing ceiling and roof. Vibration impacts are not
expected.
Fauna/Flora Low According to the IUCN study and
recommendation the species recorded at the site
is common to the area.
Erosion and
sedimentation
Medium Soil work and land preparation would cause the soil
erosion and sediment at the Thelgamuwa oya
flowing nearby.
Archeological heritage Low Earth removal or excavation will not be done
Waste Low No additional wastes generated otherthan the
domestic waste of the workers
Hazardous materials Low Hazardous materials will not be used
Traffic and
accidents
Medium Material transportation would be by heavy
vehicles along the public road.
Indigenous people No Impact Indigenous or marginalized ethnic groups are not
inhabiting or around the project area.
Occupational
Health and Safety
High Large animal attack would not be expected. But
insect, bees and other small animal could course
some injuries to the workers. Health hazards would
also be possible while using cement, paints and lime
and in carpentry and mason works
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 6 of 41
1. Background of the project area
1.1 Introduction
The Knuckles Conservation Forest (KCF) lies in central Sri Lanka, in the administrative
districts of Matale and Kandy. The above 1500 m of the sea level of KCF was declared a
climatic reserve in 1873 and subsequently declared as a conservation forest in 2000. Later, a
part of the KCF was recognized as a UNESCO Natural World Heritage site in 2010 with the
Central Highlands of Sri Lanka. KCF has been recognized as a distinct and isolated range and
as a key biodiversity hotspot of the Island which records high point endemism. A unique
evolutionary assemblage of fauna and flora were recorded within KCF and related adjacent
areas thus considered as environmentally highly sensitive and vulnerable.
The vegetation of the KCF consists mainly of semi-evergreen types with larger trees, the upper
slopes of the mountain contains tropical montane humid evergreen rain forest, possessing a
kind of cloud forests with various endemic species of ferns, orchids, lichens, and mosses. Also
the KCF is considered a vital water catchment with many of its streams feeding important
downstream rivers such as River Mahaweli, Heen ganga, Kalu Ganga, and Hulu ganga.
Also, the KCF considered as a high biodiversity landscape settings including montane, sub
montane and intermediate zone forest etc. Also, it has been recorded more than 1,000 flora
species in the forest reserve with some rare, threatened and endemic species. In addition, more
than 100 species of birds with many endemics, more than 30 species of mammals, more than
20 species of amphibians, more than 50 species of buterflies and over 50 species reptile are
inhbited in this forest.
Figure1: Google map of the Illukkubura Conservation Center (Proposed site for dormitory)
Two entrances are commonly used to enter the Knuckles Reserve, one through the
Hunnasgiriya - Deanston and the other through the Matale - Ilukkumbura. Both entrances have
office facilities, accommodation and research and educational facilities. Infrastructure
development work on both of these entrances is currently underway under the ESCAM Project.
The Department of Forest Conservation has proposed to establish the institutional
infrastructure at the Knuckles Illukkubura Conservation Center. The proposal submitted was
for a new hostel to increase internal capacity under subcomponent 3 (c). According to the
proposal, the new building will facilitate a group of 40 people with an auditorium facility.
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 7 of 41
Eventually, a team of about 80 people can be accommodated in both old building and the
proposed new building.
1.2 Ecological importance of the site
Fauna
There were several species observed at the locality which can be considered as conservation
importance. Some critically endangered (CR) species such as Cnemaspis clivicola (Montain
day gecko) could be seen under the rocks and crevices. Cereatophora tennenttii (Leafnose
lizard) which is another endemic and CR species, inhabit in rather undisturbed habitats with
shade and proper under growth. Also, there are several shrubs frog species could be identified
associated with the locality and the identified Endemic and threatened species list is given in
table 2.
Table 2: Identified Endemic and threatened faunal species in proposed activity areas
Scientific name Common name Conservation
status
1. Ceratophora tennenttii Leaf-horned lizard CR
2. Cyrtodactulus soba Knuckles Forest Gecko CR
3. Pseudophilautus fulvus Knuckles shrub frog CR
4. Pseudophilautus sarasinorum Muller’s shrub frog EN
5. Indosylvirana temporalis Bronzed frog NT
6. Lankanectes corrugatus Corrugated water frog VU
7. Cnemaspis clivicola Mountain day gecko CR
8. Schistura notostigma Mountain loach NT
9. Paradoxururus aureus E. Golden palm civet EN
10. Ratufa macroura E. Giant squirrel LC
Flora
The topographic and climatic variation in the Knuckles region has resulted in the occurrence
of several natural vegetation types. These include “Montane forest, sub montane forest and
Semi evergreen forest types”. Some areas that consist of a rocky substratum and thin layer of
soil harbor rock outcrop forest. In addition to these natural vegetation types, man-influenced
semi natural vegetation types present in the area include “wet pathana grassland” and “scrub
lands” dominated by Cymbopogon nardus. A wide range of hardwood as well as herbal plants
are found herein. Symplocos cochinchinensis, Ficus hispida are some of the common plants
observed in the area. Some of the red listed species besides the roadside was observed and
included in the table 3.
Table 3: Endemic and threatened flora species recorded within in proposed activity areas
No Scientific Name Common Name Conservation
Status
1 Albizia lebbeck Sooriyamara NT
2 Calophyllum trapezifolium Keena VU
3 Careya arborea Kahata LC (Native)
4 Caryota urens Kithul LC (Native)
5 Cinnamomum litseafolium Kudu kurudu EN
6 Dimocarpus longan Mora LC (Native)
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 8 of 41
No Scientific Name Common Name Conservation
Status
7 Elaeocarpus glandulifer Gal weralu VU
8 Macaranga peltata Kanda LC
9 Melia azedarach Luunumidella Introduced
10 Meliosma pinnata Nika daula Native
11 Osbeckia octandra Heen bovitiya E
12 Psychotria gardneri Kalu kuratiya E / NT
Physical Environment
The Physical features of the locality that the proposed site is located is mainly undulated hilly
terrain with thick vegetation. Dense ground cover would protect the surface water runoff for
throughout the year except extreme dry period. The canopy trees are grown up to 30-40m and
with emerge up to 60-80m. The Telgamu oya is flowing in adjacent to the proposed site is fed
with small streamlets flowing through the locality.
Socio
2. Project Descriptions
The existing building commonly known as “Illukkubura Wana Nivahana” was built in 2007. It
provides facilities for 40 overnight visitors. In addition to the visitors, this has been used as a
regional training center of the FD. Field components of officer training programmes have been
conducted at the center.
The center has high visitor demands. Especially the groups from universities and school nature
groups reserve the center for their educational visits. In addition to the overnight
accommodation facilities, several nature trails are also present at this locality. It seeks to
increase the number of tourists by increasing tourism facilities and thereby creating an
opportunity to increase the income of the people of the area.
However, the existing building does not provide all requires facilities for the training group.
Also it has not facilities for the group consisting more than 40 people. Many request received
by the FD for larger group.
To fulfill these requirements and provide more facilities for visitors and training groups, the
new dormitory building has been proposed by the FD and it has been approved by the
ESCAMP/World Bank under the component 3c
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 9 of 41
Figure 2: Old Dormitory and the Garage (Upper Picture) and The earmarked site for the for the
new dormitory (Below Picture)
. 2.1 Project objectives
The income of the peripheral communities of knuckles conservation forest is enhanced
by 50% within 5-year period.
Providing of optimum facilities and services for the nature-based tourists while
conserving the forest.
The income of the Forest Department through ecotourism activities is increased by 50%
within 5-year period.
2.2. Project Activities
The activities proposed under this renovation are summarized in table 4 below.
Table 4: Summery of the sub project activity
GRAND SUMMARY
1 Preliminaries. 600,000.00
2 Works up to D.P.C 4,341,328.60
3 Works From D.P.C to First floor 15,961,789.66
4 Works From First floor to Roof top 14,951,252.88
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 10 of 41
TOTAL 1 35,854,371.14
Allow for contingencies (approx. 6%) 2,015,999.23
TOTAL 2 37,870,370.37
Allow for VAT 8% 3,029,629.63
GRAND TOTAL 40,900,000.00
B.O.Q. FOR PROPOSED DORMITORY COMPLEX FOR DEPARTMENT OF
FOREST
AT KNUKLES CONSERVATION CENTRE
1.PRELIMINARIES
PR1 TO PR3 Preliminaries. 600,000.00
TOTAL CARRIED TO GRAND SUMMARY 600,000.00
2. WORKS UP TO D.P.C LEVEL
A-1 TO A-7 Excavator. 1,852,785.61
B-1 TO B-18 Concretor. 2,639,594.11
C-1 TO C-2 Masonary. 406,178.58
D-1 Pavior. 442,770.30
TOTAL CARRIED TO GRAND SUMMARY 5,341,328.60
3. WORKS FROM D.P.C. TO FIRST FLOOR LEVEL
E-1 TO E-21 Concretor. 5,832,749.63
F-1 TO F-3 Masonary. 1,583,316.67
G-1 TO G-12 Carpentry and joinary. 2,220,049.18
H-1 TO H-2 Iron mongary. 391,995.00
I-1 R.C.C Coping. 22,100.00
J-1 TO J-2 R.C.C Stifner coloumns. 77,450.00
K-1 TO K-15 Finishes. 4,542,732.98
L-1 TO L-14 Interna drainage. 305,210.00
L-15 TO L-24 External water supply and
drainage. 592,896.20
M-1 TO M-6 Electrical installation 393,290.00
TOTAL CARRIED TO GRAND SUMMARY 15,961,789.66
4. WORKS FROM FIRST FLOOR TO ROOF TOP
N-1 TO N-20 Concretor. 4,892,882.78
O-1 TO O-3 Masonary. 1,354,939.81
P-1 TO P-10 Carpentry and joinary. 2,548,642.68
Q-1 TO Q-4 Iron mongary. 521,900.00
R-1 R.C.C Coping. 105,950.00
S-1 TO S-2 R.C.C Stifner coloumns. 68,100.00
T-1 TO T-14 Finishes. 4,511,440.11
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 11 of 41
U-1 TO U-14 Internal water supply and
drainage. 615,457.50
V-1 TO V-5 Electrical installation 331,940.00
TOTAL CARRIED TO GRAND SUMMARY 14,951,252.88
Figure 3: Design of the ground floor of the building
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 12 of 41
Figure 4: Design of the first floor of the building
Figure 5: Design of the second floor of the building
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 13 of 41
2.3. Alternatives proposed by IUCN study for the design
The original design of the proposed visitor facility included a viewing deck that would overlie
the Manigala nature trail. After the discussion held with the architect and the Forest Department
officials, during the IUCN study, the design of the building has been modified. The viewing
deck has been modified in a manner that it will not be visible from the Manigala Nature trail
and thereby the impact has been avoided. Extract of the IUCN study report with their
recommendation is given in Annex 2.
Considering the sensitivity of the locality that the bungalow is located, the renovation activities
could course negative impact to the surrounding environment of the KCF. Therefore, the
possible environmental and social impact has been assessed prior to launch the development
and presented in this report with suitable mitigatory measures.
3. Community Consultation
Enhancement of the income of the peripheral communities of knuckles conservation forest by
50% within 5-year period is an objective of the project. By renovating the circuit bungalow,
annual visitation would have expected to be increased thus would have increased the income
of peripheral community. However, the increasing the number of tourists would directly effect
to the social condition of the surrounding communities.
Community consultation meeting will be held to make aware the possible impacts to the
surrounding community. A Social impact monitoring team consisting of community
representatives will be established and frequent monitoring will be done by them. The
monitoring will be continuing during the construction phase and in operational phase as well.
Any negative impact will be address by the established GEM system that has been described
under the section 6 of this report.
4. Potential Environmental Impacts of the Project and proposed mitigation
The potential environmental and social impacts of the proposed sub-project describe under this
Chapter related to the pre-construction, construction and operation phases including the
proposed mitigation measures.
4.1. Pre-construction stage
Potential impact during pre-construction stage will be due to surveying and setting out of the
buildings. To avoid damages to the ecologically and significant tree species, setting out surveys
shall be carried out under strict supervision of the engineer and the environmental expert.
A sufficient area around the construction site is also required to be cleared for the facilitation
of construction activities, which is usually around 3m. This area could be arranged with
minimal damage to the flora. However, all the trees in that stretch of 3m around the construction
site need not be removed. Selected valuable trees shall be translocated and plant in the same
location.
In order to avoid damages to the ecology, endemic, threatened or endangered fauna / flora
species, surveys and setting out works shall be carried out under strict supervision of an
engineer and the environmental officer. The contractor should adhere to the guidance given on
air and water quality checks and waste disposal systems too. Identification of waste disposal
method with a dumping site is the responsibility of the contractor at this stage.
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 14 of 41
Contractor shall prepare detailed Environmental Management Action Plan (EMAP) –
Site Specific EMPAs) clearly stating the approach, actions and manner in which the
ESMP is implemented. The EMAP shall be updated regularly and submit for Engineers’
review and monitoring. The environmental officer is encouraged to contact
Environmental & Social Safeguard Section of ESCAMP for any clarification or
assistance.
The Contractor shall appoint a suitably qualified Environmental Officer (with
community consultation experience) following the award of the contract. The
Environmental Officer will be the primary point of contact for assistance with all
environmental and social issues during the pre-construction and construction phases.
He / She shall be responsible for ensuring the implementation and monitoring of this
ESMP and Environment Management Action Plan (EMAP) which has to be developed
by the contractor.
He/she will also be responsible for community liaison and to handle public complaints
regarding environmental / social related matters. All public complaints should be
handled as per the ESCAMP Grievance Redress Mechanism (GRM). The
Environmental Officer will promptly investigate and review environmental and social
complaints and implement the appropriate corrective actions to mitigate adverse
impacts. A register of all complaints is to be registered and forward to the Site Manager
/ Engineer within 24 hours they are received, with the action taken by the
Environmental Officer on complains thereof.
4.2. Impacts during construction stage:
Removal or Damages to the vegetation
The impact on the vegetation of the project site could be rated as minimal as most
construction / renovation will be done adjacent to the existing building locations.
Therefore, less disturbance could be expected in the proposed site.
However, site clearance and clearance of 3m stretch need to remove the existing trees.
The tree species (10> cm dbh) that will have some effects from the proposed
construction are Kaluhabaraliya (Diospyros ebenoides), Sooriyamara (Albizia lebbeck)
Kanda (Macaranga peltata), Kahata (Careya arborea), Luunumidella (Melia
azedarach), Nika daula (Meliosma pinnata), Mora (Dimocarpus longan) and Kithul
(Caryota urens). The plants that have been recognized as conservation importance (Ex:
Kaluhabaraliya (Diospyros ebenoides) should be translocate to the nearest place under
supervision of the officers of FD and E PMU.
Noise and Air Pollution
Noise levels around the construction site would temporarily increase. The noise levels
generated should be limited to workday daylight hours for the duration of the work.
High noise generating equipment should be discouraged, especially vibrating machines
and earth compactors in the site.
Pollutant emissions from construction equipment could generate minor effects to air
quality in the area and immediate surrounding the construction activity. Fugitive dust
particles could release to the atmosphere during construction, transportation and
subsequent storage and handling.
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 15 of 41
The contractor would be required to keep all equipment in good order to minimize air
pollution and noise generation. Construction materials should be covered to avoid
erosion, especially fill material such as gravel and earth. Material transport vehicles
while transporting materials should be covered in order to avoid any air-borne dust in
the area. Since gravel and unpaved roads create air-borne dust, frequent watering the
road surface is essential.
Removal of top soil
Top soil of the site shall be stripped to a specified depth of 150 mm and stored in
stockpiles of height not exceeding 2m without blocking the path. Such stockpiled
topsoil may be returned to cover the areas including cut slopes where the topsoil has
been removed due to project activities. Residual topsoil will be distributed on adjoining
/ proximate barren areas as identified by the Engineer and the environmental officer in
a layer of thickness of 75mm – 150mm.
Hydrology and Water Quality
Natural drainage patterns through the land area will be disturbed due to construction
activities. Provision of streams and canals within the site is necessary to facilitate proper
drainage while controlling erosions.
Disturbance to the soil, cutting & filling, and storage of construction material within
the site could potentially contaminate the surface runoff, notably increasing the
turbidity during construction. Erosion control practices should be implemented during
the construction to limit turbidity and silt transport off site. Safe handling of
construction material would minimize the potential contamination of surface runoff and
thereby prevent affecting the quality of the water bodies nearby.
Operation of borrow sites
Contractor shall procure material only from borrow sites having approved license from
GSMB or other relevant authorities. Borrow sites / pits should be properly managed so
that material will not be eroded due to surface runoff. Slopes and embankments should
be turfed or protected from erosion by other means after cutting, to prevent wash away
of soil. Similarly, any earth heaps should be covered so that material will not be washed
away causing contamination of nearby water courses. If materials getting from outside,
special precautions to be taken to check the license and quality of borrow sites, in order
to avoid entering invasive or alien materials to the site.
Social impact
Thelgamuwa Oya which is flowing adjacent to the contract site is quite popular place
for bating of general public. Many visitors used to get rest at this site. The construction
activities would effect to the people who will be getting at this location and the people
who are passing this location.
To avoid any such impact to the community that are using the Telgamuwa Oya,
additional precautions to be made to prevent from any contamination to the
Thelgamuwa Oya due to the construction activities. Material transportation to the site
could cause road traffic. To avoid the possible road traffic, heavy vehicles and
machinery transportations should be limited as much as possible. Noise, vibration and
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 16 of 41
dust emission has to be controlled by adopting the measures described in the table 5
below.
Table 5 - Summary of key social and environmental impacts associated with the subproject
during construction stage
Project aspect
/ Cause of
impact
Potential impact Significance
of the
impact
Mitigation measures
Removal of
Topsoil
Impact on fauna –
especially
endemic/threatened
land snail species,
reptiles, amphibians
can be affected
Soil erosion in the
construction area
result sedimentation
in the streams,
waterways which will
affect the fauna/flora
inhabit in sensitive
ecosystem
Habitat loss and
fragmentation
Loss of critical
species
Obstructions to
movements/migratory
routes of the animals
Spreading invasive
species
Disturbances to the
drainage and natural
stream flow
Medium Removal of any critical
species found during
topsoil removal which
can be inhabiting in the
area, and ensure no
damage will occur to
endemic/threatened
species due to the work
Avoid rainy season to
reduce impact due to
erosion, siltation
Implement erosion
protection measures, silt
traps etc.
Removed topsoil could
be used as a productive
soil when
replanting/establishing
vegetation
Stockpiled topsoil must
be returned to cover the
areas including cut
slopes where the topsoil
has been removed due to
project activities.
Residual topsoil must be
distributed on
adjoining/proximate
barren areas as
identified by the
engineer in a layer of
thickness of 75mm –
150mm.
Removal of
vegetation
Impact on Endemic
or threatened flora
and fauna species
inhabiting in the area
Loss of habitats
Disturbance to the
wildlife migratory
paths and their
movements
Low All work to be carried out
complying with FFPO/FO
Prior baseline ecological
screening to be conducted
to understand whether any
critical species will be
affected
If such species to be
affected, appropriate
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 17 of 41
Habitat deterioration
and threat to the
fauna and flora
measures to be taken to
protect such species
No tree removal is
allowed without FD
approvals. FD needs to
supervise development
activities.
Section wise vegetation
clearing to minimize
disturbances to the animal
movements
As much as possible
manual clearing to be
encouraged as machinery
can over damage the
protected area / sensitive
habitats
Construction workers shall
be instructed to protect
fauna, including wild
animals and aquatic life as
well as their habitats.
Hunting, poaching and
unauthorized fishing by
project workers is not
allowed.
Activities
related to
significant
noise and
vibration
(machinery
movements,
material
handling,
transportation
of vehicles and
related earth
work etc)
Disturbances to the
wildlife in the area,
and distraction
Medium Control noise in the site.
Noise generating work
should be limited to
daytime (7:00AM to
6:00PM).
All equipment and
machinery should be
operated at noise levels
that do not exceed the
permissible levels as per
CEA regulations.
All equipment should be
in good serviced
condition.
Regular maintenance of
all construction vehicles
and machinery to meet
noise control regulations
stipulated by the CEA in
1996 (Gazette Extra
Ordinary, No 924/12)
Labour gangs should be
warned to work with
minimum noise. Strict
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 18 of 41
labour supervision should
be undertaken in this
respect.
Activities
related to the
emission of
dust
Impact on sensitive
habitats, inhabitant
fauna/flora species
Significant levels of
noise and dust
produced during
construction work,
there may be
temporary
disturbances to the
animals (especially
migratory birds)
inhabiting in the area
Construction area to be
barricaded properly to
avoid spreading
dust/emissions etc
Trucks to be operated
using covers
Material stored under
cover using proper
anchoring systems
Tires of trucks /
machineries are cleaned
before entering city roads
Regular watering of
access roads and the
construction site
Turfing of finished
earthen structures
Dust masks are provided
for the workers and using
at the required time
If any significant dust
issues occurred, Ambient
air quality including dust
levels monitored through
an accredited laboratory
and understand the
compliance status. If any
non-compliance noticed,
required corrective
actions, compensations to
be made by the contractor
as directed by the PIA
Activities
related to the
hindrance of
surface runoff
and soil
erosion,
pollution due
to oil spills,
and other
pollutants
result during
the
construction
work /
Impact on aquatic fauna
and flora due to possible
disturbances Pollution
water bodies close to the
site
Water logging and Vector
proliferation
Medium Natural water paths and
valleys should be kept free
from any obstruction
through any kind of
construction or disposal of
soil/rocks etc.
The project area must be
barricaded properly using
sandbags to avoid
disturbances to the
naturalized habitats
Construction work to be
carried out in the dry spell
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 19 of 41
contractor
facilities
Do not dispose spoil water
to drainage path or
streams.
Prohibit direct disposal of
solid and liquid waste into
nearby water bodies.
Waste management plan
to be developed and
implemented.
Material
sourcing
including
operation of
borrow pits,
quarry sites
etc.
Resource depletion
Damage to wildlife, forest
resources
Environment Pollution
Health & safety issues
Medium The contractor is required
to ensure that sand,
aggregates, and other
quarry material is sourced
from licensed sources,
away from the protected
areas/ sensitive habitats
The contractor is required
to maintain the necessary
licenses and
environmental clearances
for all borrow and quarry
material they are sourcing
–including soil, fine
aggregate, and coarse
aggregates
Sourcing of any material
from protected areas
and/or designated natural
areas, including tank beds,
are strictly prohibited
unless it is approved by
the relevant approving
agencies carrying out an
Environment Assessment
Use of borrow material
from tank beds to be
excavated as per the
conditions laid by relevant
authority to a maximum
death which will not cause
animal trapping/ falling
into the excavated borrow
pits
Ensure to cover such areas
with proper fencing to
avoid animal trapping /
falling into the pits
If the contractor uses a
non-commercial
borrow/quarry sites, the
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 20 of 41
sites should be remediated
accordingly once material
sourcing has been
completed
The contractor should
submit in writing all the
relevant numbers and
relevant details of all pre-
requisite licenses etc. and
report of their status
accordingly.
Selected quarry sites
should have proper safety
measures such as
warnings, safety nets etc.,
and third-party insurance
cover to protect external
parties that may be
affected due to blasting.
It is recommended not to
seek material from
quarries that have ongoing
disputes with the
community.
The maintenance and
rehabilitation of the access
roads in the event of
damage by the
Contractor's operations
shall be a responsibility of
the Contractor.
Copies of all relevant
licenses should be
maintained by the
Contractor for review and
documentation by the
implementing/monitoring
agencies
Transportation
and storage of
materials
Spreading dust and impact
due to hazardous material
Medium All material should be
transported in fully
covered trucks.
Overloading of vehicles
with materials should be
controlled and done in a
manner to suit the truck
capacity and tailgates of
the trucks should be
closed.
Construction material such
as cement, sand and metal
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 21 of 41
should be stored in closed
structures or in a
contained manner.
Material haulage routes
and stockpiling areas to be
well defined with the prior
approval of the respective
authorities, and all the
measures to be followed
by the suppliers to avoid
any environmental issues
(dust, noise, nuisance to
public, traffic etc.)
Safety
measurements
for workers
Injuries during the
construction. Safety from
wild animals and accidents
Medium Construction work shall be
limited to day light hours.
Workers must use relevant
Personnel Protective
Equipment (PPEs) as
appropriate for the work
9Refer Annex 4: Safe
Operating Procedures for
Working in Protected Areas
Precautions
for COVID-19
Possible infections at the
site
High Follow all actions and
instructions given by PHI and
the PMU. (Refer PMU
handbills – Annex 3)
5. Environmental Monitoring and Reporting
5.1. Construction Stage:
The environmental monitoring plan forms the basis for verifying the extent of compliance
during the implementation stages of the project. The objectives of an environmental monitoring
program are:
i. to evaluate the performance of mitigation measures proposed in the ESMP / EMAP;
ii. to provide information which could be used to verify predicted impacts and thus
validate impact prediction techniques;
iii. to suggest improvement in environmental mitigation measures if required;
iv. to provide information on unanticipated adverse impacts or sudden change in impact
trends;
Implementation of mitigation measures will be ensured through both routine and periodic
monitoring. A sample monitoring framework is given in Table 6 as guidance for site
environmental officers. In addition, attached ESMP Matrix (Refer Annex 1) also could be used
to monitor whether proposed safeguard measures are being carried out during different
construction stages.
Table 6 - Construction Phase Monitoring
No. Indicators of Monitoring Types of
Monitoring/ Method
of Monitoring
Monitoring
Frequency
Responsibility
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 22 of 41
1 Transportation of
construction material in
covered condition, and safe
loading & unloading.
Direct Observation Regular
during
construction
FD, &
Contractor
2 Stockpiling of excavated
materials
Direct Observation Daily FD &
Contractor
3 Reuse of excavated
materials
Direct Observation Daily FD &
Contractor
4 Solid waste segregation
and disposal
Direct Observation Daily FD &
Contractor
5 Damages to
trees/vegetation
Direct Observation
& records
Daily FD &
Contractor
6. Impacts for Fauna Direct Observation
& records
Daily FD
/Contractor
7 Occupational health and
safety, use of safety gears
Direct observation &
record of injury
Daily FD &
Contractor
8 Safety measures on
COVID-19
Direct observations
& temperature
checking
Daily Contractor
9 Dust and Air Quality issues Direct observations Once in two
days
FD &
Contractor
10 Water logging and vector
proliferation
Direct observation &
records (of illness)
Once a week FD &
Contractor
5.2. Post-Construction Stage:
Post construction monitoring is the main activity during this stage to check whether the all
ESMP and EMAP requirements were fulfilled or to study drew backs. Table 7 provides
guidance to develop a post-monitoring tool.
Table 7 – Sample Post – Monitoring Chart
N
o
Activity Measures
suggested by
the original
ESMP
Measures
Implementation
Observations /
Impacts / Risks
Level of
success
1. Landscapin
g
The site should
be reinstated
similar to the
pre-project
conditions
using native
species.
Landscaping was
done.
Turfing should equally
spread over the site.
Need to level the
ground in some
locations (inside
the garden).
Turfing should
spread over the
site.
2. Rehabilitati
on of site
vegetation
Trees were planted but
can grow more useful
trees and suit to the
ecological condition to
the site. Planted trees:
Halamba, Mee,
Need to consider
survival rate and
at present it is
around 60%.
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 23 of 41
Karapincha, Dambe,
Suuriya maara and
kithul
Grass cover is
essential over the
ground.
Completion of landscaping is the key responsibility of the contractor at this stage. Only native
plants should be used for landscaping. Site should be free of debris, painting marks and eroded
patches. Turf with grass provide an attraction to the location. Disability access should be
available for all sections of the building. Safety of workers and visitors should be ensured with
possible ways. Appropriate signage is essential to guide visitors for easy access to the services
with less risk factors.
6. Public Consultation and Grievance Redress Mechanism (GRM)
6.1. Consultation and Information Disclosure
Consultation and information disclosure will be a continuous process during the preparation of
the environmental and social assessment document and implementation of such plans. These
assessments will ensure to conduct meaningful consultations with affected people and
concerned stakeholders, including civil society and facilitate their active participation. The
meaningful consultation shall begin early in the project preparation stage and carried out in an
ongoing basis throughout the project cycle. Consultation should be organized in a congenial
environment without intimidation, and should be gender sensitive as well.
6.2. Grievance Redress Mechanism
The main objective of the Grievance Redress Mechanism (GRM) is to provide a time bound
and transparent mechanism to voice and resolve complaints of stakeholders. The environment
officers engage through the Consultants (Ex. design and supervision consultants) are
responsible for handling grievances. They will (i) accept and record the complaints, categorize
and prioritize them; (ii) consult with all relevant stakeholders (including contractors), visit the
project site, and do the required examination; (iii) settle the grievances in consultation with the
complainant and the project staff; (iv) report to the aggrieved parties about the
decision/solution; and (v) forward the unresolved cases to higher authorities for resolution. In
case of complex complaints, the authorities and consultants will inform the Project Director
and guide him about practical options for resolving the grievances.
Grievances should be addressed within two to four weeks from the date of lodging the
complaints. If resolution attempts at the FD field level fail, the FD will refer the complaints to
the relevant DFO along with the minutes of the hearings. If a decision made at this level is
found unacceptable by the aggrieved person(s), DFO could refer the case to PSE with the
minutes of the hearings at both grass root and district levels. The FD/DFO will keep records of
all resolved and unresolved complaints and grievances and make them available for review as
and when asked for by PMU and WB Resident Mission in Colombo, Sri Lanka. Information
about GRM will be made public through project website and other relevant sources.
7. Conclusion and Recommendations
The environmental and social impacts / issues identified during the study in Ilukkumbura
(Knuckles) dormitory area could be mitigated and manageable. The study findings indicate
possible impacts on physical, ecological, socio-economic and environmental aspects to the
proposed development. No households will be directly affected or no land acquisition is
envisaged due to the proposed project as proposed building complex will be constructed within
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 24 of 41
the land of existing facility owned by the Forest Department. However, indirect impacts will
be possible for communities passing and touring this place and work in a close proximity.
It is the responsibility of project implementers and contractors to address identified issues
before the commencement of project and during the construction period. Services from PMU
and the World Bank could be obtained to train identified stakeholders. Mitigation measures
have been proposed for all identified / predicted adverse impacts and enhancement of project
benefits.
However, there may be some impacts / issues not predicted at this stage but might appear later.
In such cases, project authorities and contractors could obtain services of consultants,
environmental experts, PMU and World Bank to mitigate such impacts or issues.
Site Managers have obligation to carry out mitigation, enhancement and monitoring activities
in appropriate stages and time. ESMP / EMAP should be a live document and environmental
mitigation measures should be incorporated or upgraded in the ESMP as and when necessary.
The study noted more benefits in the proposed program. If the identified issues and impacts are
managed properly with proposed mitigation measures, this will be a successful project.
Recommendations given by the independent report prepared by the IUCN are as follows:
It is necessary to closely monitor the construction work as this visitor facility will be
built in the boundary of KCF, which is a sensitive habitat.
The construction work needs to be closely monitored by the officials of the Forest
Department to ensure best practices by the contractor at all times and to ensure that the
contractor follows the guideline provided by the ESCAMP project to avoid or minimize
impacts arising due to construction work, such as noise, construction debris and other
solid waste generated within the construction site.
Following measures need to be taken during the preconstruction, construction, and
post-construction period:
(i) Before the commencement of ground preparation of the site, the single Diospyros
ebenoides (Kalu-habaraliya) plant (approximately 1m height individual) must be
translocated from the construction site to a suitable habitat nearby.
(ii) Construction work should not be undertaken at nighttime or during heavy rains
(iii) Construction materials should be safely stored away from the Theligamu Oya
(iv) Use of heavy machinery should be avoided
(v) Construction waste and solid waste should be disposed at sites identified by the
Forest Department, and such sites should not be established near the forest or
Theligamuoya stream.
(vi) Right bank of the Theligamu oya and the nature trail is located immediately
adjacent to the construction site and therefore, construction activities should not
cause any disturbance to the right bank of the Theligamu oya or the nature trail.
(vii) After construction, a natural vegetation belt should be established between
Manigala nature trail and the visitor facility to avoid visual impact on the
Manigala nature trail.
(viii) Only native plant species should be used for landscaping (Annex 3 of IUCN
Report). The trees for landscaping should be selected to enhance the biodiversity
of the site such butterfly feeding plants and other plants that can serve as food
plants or roosting plants for native animals.
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 25 of 41
(ix) Neutral colours should be used on the outside walls and roof of the visitor facility
to avoid visual pollution.
Annex 01: ESMP Matrix
MITIGATION PLAN
No. Mitigation Measures Locations/
Project
phase
Mitigatio
n cost
Institutional Responsibility
Implementatio
n
Supervisio
n
CONCERN 1: IMPACTS ON FAUNA
1.1 Since most of the animals living in
the reserve are crossing the road
and accidents may occur due to
narrow slopes, the maximum
speed of all vehicles transporting
construction materials should be
maintained at a maximum speed of
20 km per hour.
If some animal or group is
blocked, they must wait quietly
until they are completely
evacuated.
Entire
construction
period and
construction
sites.
No
additional
cost
Contractor
Respective
Forester /
RFO
1.2 The contractor should avoid
overloaded vehicles to transport
material to construction sites in
and out of the knuckles forest area.
The materials should be covered
with a tarpaulin during
transportation.
Entire
construction
period and
construction
sites.
NA Contractor
Respective
Forester /
RFO
1.3 All works should be carried out in
such a manner that destruction or
disruption to the fauna and their
habitats is minimized.
Entire
construction
period and
construction
sites.
NA Contractor
Respective
Forester /
RFO
1.4 The sound of the horn (tooting of
wehicle horns) is prohibited in the
vicinity of the protected area and
in the vicinity of the Knuckles
Conservation Centre.
Entire
construction
period and
construction
sites.
NA Contractor Respective
Forester /
RFO
1.5 Limit activities to day light
working hours from 8.00 am to
5.00 pm
Entire
construction
period and
construction
sites.
NA Contractor
Respective
Forester /
RFO
1.6 Equipment that may produce noise
and vibration, used for
earthmoving and concrete mixing
Entire
construction
period and
NA Contractor
Respective
Forester /
RFO
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 26 of 41
shall be limited, as much as
possible within the PA/Forest
area.
construction
sites.
1.7 Construction workers should be
advised to protect wildlife, aquatic
life as well as their habitats.
Project workers do not allow
hunting and unauthorized fishing
in other waterways, including
Thelgamu Oya.
Entire
construction
period and
construction
sites.
Awarenes
s under
the
monitorin
g and
supervisio
n cost –
Rs.80,000
.00
RFO
EO-PMU
Respective
Forester /
RFO
CONCERN 2: IMPACTS ON FLORA
2.1 All works shall be carried out in a
manner that the destruction to the
flora and their habitats are
minimised. Trees and vegetation
shall be felled /removed /pruned
only if that impinges directly on
the permanent works or necessary
temporary works. In all such cases
contractor shall take prior
approval from the Forester or
RFO.
Entire
construction
period and
construction
sites and
immediate
surrounding
s.
NA Contractor
Respective
Forester /
RFO
EO-PMU
ESSS-
PMU
2.2 Endemic/point endemic / rare
/threatened /endangered plant and
tree species shall not be permitted
to fell /remove or prune.
Entire
construction
period and
construction
sites and
immediate
surrounding
s.
Awarenes
s under
the
monitorin
g and
supervisio
n cost
RFO
EO - PMU
Respective
Forester /
RFO
2.3 Material transport vehicles,
machinery and equipment shall be
used and stationed only in the
areas of work under the
recommendation of the Forester or
RFO and in any other area
designated/approved by the
Forester within the premices.
Entire
construction
period/
material
transportatio
n period and
construction
sites.
NA Contractor
Respective
Forester /
RFO
2.4 Measures to avoid/minimize the
airborne dust have to be taken as;
Covering the vehicles
carrying dusty materials.
Wetting down/spraying of
road construction areas if
necessary.
Material
Transport
and Entire
construction
period and
construction
sites.
Engineeri
ng cost is
allowed. –
Rs.
20,000.00
Contractor
Respective
Forester /
RFO
2.5 Wheel washing of vehicles are
not allowed inside the PA/Forest
area.
Entire
construction
period and
NA Contractor
Respective
Forester /
RFO
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 27 of 41
construction
sites
2.6 Ensure that any vegetation
clearing occurs within the limits of
an approved construction area,
before the site preparation, under
the supervision of Forester / RFO.
Entire
construction
period and
construction
sites.
NA Contractor Respective
Forester /
RFO
2.7 Ensure all plant/planting
materials, equipment & vehicles
coming to sites of PA/Forest area
have been cleaned and free from
weeds and invasive seeds.
Entire
construction
period and
construction
sites
NA Contractor
Respective
Forester /
RFO
2.8 Ensure no activities outside the
work zones through clear
delineation of the works area.
Entire
construction
period,
including
material
transport.
NA
Contractor Respective
Foreser /
RFO
EO-PMU
CONCERN 3: CONSTRUCTION WORKS
3.1 The contractor is required to
ensure that sand, aggregates and
other quarry material is source
from licenced sources.
Entire
construction
period and
construction
sites.
NA Contractor
Respective
Forester /
RFO
3.2 Sourcing from any material from
PA/Forest areas and or designated
natural areas including water
streams shall not be done.
Entire
construction
period and
construction
sites.
NA Contractor
Respective
Forester /
RFO
3.3 Contractor shall use lead-free
paints in every construction site
and No asbestos will be allowed to
use.
Entire
construction
period and
construction
sites.
NA Contractor
Respective
Forester /
RFO
3.4 Waste disposal system to be
established where ever necessary
under the recommendation of
project engineer or Forester.
Entire
construction
period and
construction
sites.
Engineeri
ng cost
Rs.
10,000.00
Contractor
Engineer – FD
(ESCAMP)
Respective
Forester /
RFO
CONCERN 4: PROTECTION OF GROUND COVER AND VEGETATION
4.1 Contractor should provide
necessary instructions to drivers,
operators and other construction
workers not to destroy ground
vegetation cover unnecessarily.
Entire
construction
period and
construction
sites.
NA Contractor
Respective
Forester /
RFO
EO - PMU
CONCERN 5: SOIL PROTECTION
5.1 Top soil of any construction area
shall not be removed without
written permission form the
Forester. If it is essential to
Entire
construction
period and
within the
NA Contractor Respective
Forester /
RFO
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 28 of 41
remove under the written
permission of the Forester, such an
activity must be carried out under
the supervision of the respective
RFO.
project sites
where
topsoil has
to be
removed
5.2 Areas where top soil has to be
removed for the purpose of these
works, contractor shall obtain the
instruction/directions from the
Engineer – FD (ESCAMP) and the
Forester and the removed top soil
should not bring outside of the
PA/Forest area.
Entire
construction
period and
within the
project sites
where
topsoil has
to be
removed
NA Contractor
Engineer –
FD
(ESCAMP
)
Respective
Forester /
RFO
5.3 Soil conservation measures should
be implemented in the soil erosion
sensitive areas along with the
construction works.
(In particular, in particular, one
side of the selected area has a steep
slope and talcum flows, so special
attention to soil conservation is
very important. At the start of the
rainy season, the problem will
double. Therefore, it is
recommended to start construction
before or after the rainy season.
Places where runoff from
the site is required, it will
be via the longest flow
path possible to ensure
maximize sediment
retention. Flows to
thelgamu oya and
undisturbed areas (where
no construction is
happening) will be
prioritized.
Where required, sediment
controls will be put in
place. These will include,
but not be limited to, rock
check dams, sediment
basins, sediment fences
and silt socks.
Sediment controls will be
reviewed during site
inspections and/or after
rainfall.
Site
preparation
period and
sites
identified as
soil
conservatio
n measures
are needed.
Engineeri
ng cost
Rs…20,0
00.00
Contractor
Engineer – FD
(ESCAMP)
Respective
Forester /
RFO
EO - PMU
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 29 of 41
Review flow path and
determine most
appropriate controls are in
place, additional controls
which can be place in-
stream and/or changes that
can be made to flow path.
5.4 Ensure effective sediment and
erosion control measures to
reduce potential impacts during
the site clearing for proposed
infrastructure development.
Entire
construction
period and
construction
sites.
Engineeri
ng cost
Rs.
10,000.00
Contractor
Engineer – FD
(ESCAMP)
Respective
Forester /
RFO
EO - PMU
CONCERN 6: WATER – PROTECTION OF WATER SOURCES AND QUALITY
6.1 The contractor is responsible for
arranging adequate supply of
water for the project purpose
throughout the construction
period. Contractor shall not obtain
water from natural springs and
waterways inside PAs for this
purpose without receiving written
permission from the DFO or
respective Forester.
Entire
construction
period and
waterways
located in
the
surrounding
areas of the
construction
site/s.
Engineeri
ng cost is
allowed.
Contractor
Engineer –
FD
(ESCAMP
)
Respective
Forester /
RFO
EO - PMU
6.2 The Contractor shall not extract
water from groundwater or from
surface water-bodies without
permission from the DFO or
respective Forester. Such
extraction (if approved) should be
carried out under the direct
supervision of the respective
Forester/RFO/BFOs.
Entire
construction
period and
waterways
located in
the
surrounding
areas of the
construction
site/s.
Engineeri
ng cost is
allowed.
Contractor
Engineer –
FD
(ESCAMP
)
Respective
Forester /
RFO
EO - PMU
6.3 Contractor shall not divert, close
or block existing canals/streams
within the PA for any purpose
during the construction work.
Entire
construction
period
NA Contractor
Respective
Forester /
RFO
EO - PMU
6.4 All above the works under this
EMP over or closer to the water
streams, rivers, rivulets within
Forest area/Protected area, thus
activities may be undertaken
during dry season.
If the work is carried out during
the rainy seasons, the contractor
shall avoid storing materials such
as cement, lime, chemicals and
other items of work in areas where
those can be washed away by the
rain/surface runoffs.
Entire
construction
period and
construction
sites.
NA Contractor
Respective
Forester /
RFO
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 30 of 41
6.5 Contractor shall protect the water
sources in/around, (streams
(Thelgamu oya) and surface
runoffs in the PA) from various
contaminants (dust, sand, cement,
soil, polythene, plastic, or any
other waste) derived from the
works or workers.
Entire
construction
period
NA Contractor
Respective
Forester /
RFO
EO - PMU
CONCERN 7: SOLID WASTE MANAGEMENT
7.1 Demolished materials of the
garage/construction sites should
be reuse or taken away from the
PA/forest areas under the approval
of Engineer of FD (ESCAMP) and
the Forester.
Any other organic or inorganic
solid waste material should be
collected in covered bins and
arrangements should be made for
removal of solid waste from the
sites of PA/Forest area.
Entire
construction
period and
construction
sites.
Engineeri
ng cost
Rs.
30,000.00
Contractor
Engineer –
FD
(ESCAMP
)
Respective
Forester /
RFO
EO - PMU
CONCERN 8: FIRE PROTECTION
8.1 No storage facilities will be
established inside the PA for more
than one week for materials such
as cement, sand or any other
construction material.
In any case, any lubricant, fuel or
any chemical substance, any other
solvent should not be brought to
the site for any purpose without
receiving written permission from
the and under supervision of
Forester.
Waste oil, other petroleum
products and untreated wastewater
shall not be discharged on
ground/within the PA.
Collect all waste/spoils and taken
away from the PA/Forest area,
under supervision of Forester.
Entire
construction
period and
construction
sites
NA Contractor
Respective
Forester /
RFO
8.2 No one will be allowed for
cooking, smoking during working
hours or bringing cigarettes,
lighters, matchboxes or any other
smoking material/apparatus etc.
into the sites of PA/Forest area.
Entire
construction
period and
PA.
NA Contractor
Respective
Forester /
RFO
CONCERN 9: LABOUR CAMPS
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 31 of 41
9.1 The contractor should give
priority to hiring labour from the
surrounding areas to avoid the
need for labour camps.
Entire
construction
period and
construction
sites
NA Contractor
Respective
Forester /
RFO
9.2 If labour camps are required to
house migrant workers, they
should be placed well away from
Forest area/PA boundaries and
buffer zones whenever possible.
The construction camps, office
and storage areas shall have
provision of adequate water
supply, sanitation and all requisite
infrastructure facilities
Site restoration - All construction
camp/temporary office/material
storage areas should be restored to
its original conditions or as agreed
with the land owner.
Entire
construction
period and
construction
sites
NA Contractor
Respective
Forester /
RFO
9.3 Other biological waste materials
from the camping sites shall not be
dispose/decompose within the
PA/Forest area and they should be
taken away from the PA/Forest
area to dispose/decompose.
Labour camp sites after use should
be cleared and the site should be
reinstated to previous condition at
the close of the construction work.
No any plastic or polythene
materials shall be brought into the
project sites in PA/Forest area
Entire
construction
period and
camping
sites
Engineeri
ng cost
Rs.
20,000.00
Contractor
Respective
Forester /
RFO
EO-PMU
ESSS-
PMU
CONCERN 10. APPROVALS, LICENCES AND PERMITS
10.
1
All necessary approvals, permits
and licenses required by the state
and local legislation will be
obtained prior to construction
commencing.
All approvals, permits and
licenses shall be maintained and
complied with during the
construction period. Should there
be any changes to the project
which would require additional
permits or licenses, these shall be
obtained.
Entire
construction
period and
construction
sites.
NA Respective
DFO / Forester
Contractor
Respective
Forester /
RFO
EO-PMU
SDO-PMU
CONCERN 11: PUBLIC SAFTY
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 32 of 41
11.
1
Contractor shall take necessary
actions to prevent breeding of
mosquitoes at the areas of work by
preventing stagnation of water
(including gutters, used and empty
cans, containers, tires etc.).
No construction along community
areas will be permitted during
night time.
all keep all places of work clean,
devoid of garbage to prevent
breeding of rats and other vectors
such as flies.
Burrow sites, if any, should be
rehabilitated at the end of their use
by the contractor under the
supervision of the respective RFO.
Entire
construction
period and
construction
sites &
material
storage sites
Engineeri
ng cost
Rs.
50,000.00
Contractor Respective
Forester /
RFO
11.
2
Avoid peak hours in roads, if
local/public roads are used for
bringing materials, especially
during the hours of school children
use the roads. The speed of the
vehicles should maintain less than
20 kmh-1 when transporting the
construction materials.
Entire
construction
period and
Public/acces
s roads
NA Contractor Respective
Forester /
RFO
11.
3
Any noise pollutions should be
controlled/minimized
Entire
construction
period and
construction
sites
NA Contractor Respective
Forester /
RFO
11.
4
Should be exhibited a notice
/awareness board as a “working
place” at the in front of main
construction sites before
commencement of building
construction works.
Entire
construction
period and
construction
sites
Engineeri
ng cost
Rs.
20,000.00
Contractor Respective
Forester /
RFO
CONCERN 12: WORKERS SAFTY - ACCIDENTS AND RISKS
12.
1
The Contractor shall comply with
requirements for the safety of the
workmen and all reasonable
precautions shall be taken to
prevent danger of the workers
from accidents causes due to
falling, heavy loads, snake bites,
insect bites, stuck by objects,
contact with unsafe energy
sources/power supply line etc.
Entire
construction
period and
construction
sites &
material
storage sites
NA Contractor Respective
Forester /
RFO
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 33 of 41
Records on health and safety
related accidents must be
maintained properly.
12.
2
All workers employed in
construction activities shall be
provided with necessary
protective gear such as hand
gloves, boots, helmets. These
activities include mixing cement,
lime mortars, concrete etc.
Entire
construction
period and
construction
sites
Engineeri
ng cost
Rs.
50,000.00
Contractor Respective
Forester /
RFO
12.
3
Precautionary measures to protect
from attacks by the wild animals
(snakes) during working times
inside the forest shall be taken as
mentioned below.
Contractor has to make
sure to dispose organic
waste properly. None of
the solid waste is discarded
into the forest
area/working.
Keep a environmental
officer to monitoring the
construction activities.
Throughout
the
construction
period &
material
transporting
sites.
NA Contractor
Respective
Forrester /
RFOs
Respective
Forester /
RFO
EO-PMU
SDO-PMU
12.
4
Where materials need to transport
using laborers, less than 40kg shall
allow per labour, per time.
Entire
construction
period and
Constructio
n sites
NA Contractor Respective
Forester /
RFO
CONCERN 13: ARCHAEOLOGICAL CHANCE FINDS
13.
1
Archaeological remains in the
Forests area/PA and adjacent areas
must not destroy/disturb or
remove by the contractor or by any
workman.
Throughout
the project
period
NA Contractor Respective
Forester /
RFO
SDO-
ESCAMP
13.
2
In case of chance finds, the
contractor is obliged to stop the
works immediately and inform the
DFO, Forester or respective
RFOs, Engineer – FD (ESCAMP)
or any other officers available at
the immediate vicinity at that
moment.
All fossils, coins, artifacts of value
of antiquity and structures and
other remains or things of
Geological, Paleontological or
archaeological interest etc.
discovered on the site and/or
during construction/rehabilitation
Entire
construction
period and
Constructio
n sites
NA Contractor Respective
Forester /
RFO
SDO-
ESCAMP
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 34 of 41
work shall be returned to the
respective RFO, Forester or DFO
or Engineer-FD (ESCAMP).
CONCERN 14: FIRST AID
14.
1
At every workplace, first aid kit
and treatment facilities shall be
provided
Entire
construction
period and
Constructio
n sites
Engineeri
ng cost
Rs.
5,000.00
Contractor Respective
Forester /
RFO
CONCERN 15: OTHER SOCIAL CONSERNS
15.
1
No child labour is not allowed for
any purpose of the contract
Throughout
the project
period
NA Contractor Respective
Forester /
RFO
15.
2
Local people shall be employed in
the project activities where
possible and no gender
discrimination is expected.
Throughout
the project
period
NA Contractor Respective
Forester /
RFO
CONCERN 16: GRIEVANCE REDRESS
16 Maintaining records of all
environment, social related
grievances raised, if any, and the
actions taken to address them
throughout the construction
period.
Throughout
the project
period
NA Contractor Respective
Forester /
RFO
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 35 of 41
Annex 02: Extract from the IUCN Study report and recommendations
Impact on existing Ecosystem and Species
Proposed visitor centre will be on a disturbed and open area considered as an abandoned chena land
that is in the early stages of secondary succession (Figure 02). Further, the area affected is around
0.05 ha which is insignificant when compared to the total extent of the Knuckles Conservation
Forest (31,305 ha). Therefore, this construction will not significantly impact the ecosystem diversity
of KCF. Further, the site was inhabited by species commonly observed in such human-disturbed
sites which were also recorded in the area surrounding the construction site. None of the species
seen are listed as range-restricted species or species restricted to Knuckles Range. During the
construction stage, there could be a temporary reduction in numbers. Still, during the operational
phase, most of the species should return to the site as evident by the fact that almost all of the faunal
species recorded was also observed within the premises of the old visitor facility located next to the
site selected for construction, which indicates that the species found are habituated to the presence
of humans. Therefore, the construction of the building will not displace any of these species from
the area.
Among the recorded 40 animal species, only seven endemic species are within site selected for
construction work. These endemic species are locally as well as regionally common, and therefore
the construction will not significantly affect such species.
Endemic fauna observed within the study area
Species Name Common Name Sinhala Name DS NTS
Macaca sinica Sri Lanka toque monkey Rilawa E LC
Moschiola meminna Sri Lanka Meminna Meminna E LC
Ocyceros gingalensis Sri Lanka Grey Hornbill Sri Lanka Alu
Kandaththa E LC
Treron pompadora Sri Lanka Green-pigeon Sri Lanka Batagoya E LC
Gallus lafayettii Sri Lanka Junglefowl Sri Lanka Vali-kukla E LC
Pycnonotus
melanicterus
Sri Lanka Black-capped
Bulbul
Kalu Isasi Kondaya E LC
Pellorneum
fuscocapillus
Brown-capped Babbler Mudunbora
Demalichccha
E LC
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 36 of 41
Among the recorded 47 plant species, only four endemic species were observed within site selected
for construction work. Three endemic species (except Diospyros ebenoides) are locally as well as
regionally common, and therefore the construction will not significantly affect such species. A
single seedling of Diospyros ebenoides was observed in the area that will be disturbed due to the
construction work. It is recommended to translocate the plant before the commencement of the
ground preparation for the proposed building.
Endemic flora observed within the study area
Species Name Common Name DS NTS
Semecarpus nigroviridis Geta Badulla E LC
Diospyros ebenoides Kaluhabaraliya E EN
Derris parviflora Kalawel E LC
Strychnos benthami E NT
Impact on the cultural value of the Knuckels Conservation forest
The proposed visitor facility will not have a significant impact on the cultural values of the
community that live around Knuckles Conservation Forest. The Forest Department established the
existing visitor facility in 2003, and they have been operating to date without developing any
conflicts with the local community. The new visitor facility too will be managed by the Forest
Department. Therefore, it can be expected that the proposed facility too will be maintained in the
same manner without having any impact on the local community or their cultural values. Further,
the propose visitor facility is also located away from the village and therefore, those who will use
the facility will have minimum interactions with the local community. Positive impact provides
livelihoods for the local community.
The site selected for the proposed visitor facility is not visible within the broader landscape, and
therefore, it will not have any impact on the aesthetic value of the KCF. Further, this building will
be covered by the vegetation as well as the existing dormitory. However, the original design of the
proposed visitor facility included a viewing deck that would overlie the Manigala nature trail. After
the discussion held with the architect and the Forest Department officials, the design of the building
was modified. The viewing deck was modified in a manner that it will not be visible from the
Manigala Nature trail and thereby the impact has been avoided (see annex 2a for the original design
and 2b for the modified design).
Conclusion and recommendations
The proposed construction site is located next to the existing dormitory/office complex area of the
Knuckles Conservation Centre and within the forest-village boundary. Further, this area had been
previously used for Chena cultivation before the declaration of Knuckles Conservation Forest. As
per the evidence presented above, the proposed visitor facility will not have a significant negative
impact on the outstanding universal values of the KFC. Specifically, it will not have any significant
effect on
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 37 of 41
Biodiversity (fauna/flora/ecosystem) of the KFC
Cultural and aesthetic values of the KFC
Further, the potential benefits of educational and conservation outweigh the minimal negatives
during construction.
Even though proposed construction will not have a significant impact on the outstanding universal
values of KCF, it is necessary to closely monitor the construction work as this visitor facility will
be built in the boundary of KCF, which is a sensitive habitat.
It is recommended that the construction work is closely monitored by the officials of the Forest
Department to ensure best practices by the contractor at all times and to ensure that the contractor
follows the guideline provided by the ESCAMP project to avoid or minimize impacts arising due
to construction work, such as noise, construction debris and other solid waste generated within the
construction site.
Also, it is recommended that the following measures are taken during the preconstruction,
construction and post-construction period
Before the commencement of ground preparation of the site, the single Diospyros
ebenoides (Kalu-habaraliya) plant (approximately 1m height individual) must be
translocated from the construction site to a suitable habitat nearby.
Construction work should not be undertaken at nighttime or during heavy rains
Construction materials should be safely stored away from the Theligamu Oya
Use of heavy machinery should be avoided
Construction waste and solid waste should be disposed at sites identified by the
Forest Department, and such sites should not be established near the forest or
Theligamuoya stream.
Right bank of the Theligamu oya and the nature trail is located immediately
adjacent to the construction site and therefore, construction activities should not
cause any disturbance to the right bank of the Theligamu oya or the nature trail.
After construction a natural vegetation belt should be established between Manigala
nature trail and the visitor facility to avoid visual impact on the Manigala nature
trail.
Only native plant species should be used for landscaping (see annex 3). The trees
for landscaping should be selected in order to enhance the biodiversity of the site
such butterfly feeding plants and other plants that can serve as food plants or
roosting plants for native animals.
Neutral colours should be used on the outside walls and roof of the visitor facility
to avoid visual pollution.
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 40 of 41
Annex 04:
Safe Operating Procedures for Working in Protected Areas
Purpose
To define the safe operating procedures in a manner that informs and instructs employees of
implementing authorities and contractors/work force of the key health and safety points and
controls to remember when working in areas where wildlife can be found.
Background
People and wildlife live side by side in a PA, therefore, encounters with wild animals are
common. Most small animals are not aggressive; however, conflict may occur when they are
trying to meet their basic needs of finding food, water and shelter. It is important to understand
and recognize basic animal behaviors, in order to prevent injuries to both animals and humans.
The following hazards may occur when working in close proximity to wildlife creatures:
Infectious disease transmission from mosquito or small animal bites swelling, mild or
severe allergic reactions from stinging insects.
Serious injury or death from contact with other wild animals such as snakes, bears,
leopards etc.
Personal Protective Equipment (PPE)
Insect repellant Long-sleeved shirts and pants,
safety boots (no sandals) Insect spray designed for bees/wasps/hornets
any other appropriate PPEs
Safe Operating Procedure
General
Always carry a cellular phone, or other two-way communication device, in case
emergency medical help is required.
Be aware of your surroundings and note any wild or suspicious acting animals in your
work area. If necessary, seek safe shelter from these animals and contact the appropriate
authorities.
Avoid reaching or stepping into or over hidden areas that may contain wildlife.
Be aware of signs that indicate above or below ground animal nests and take appropriate
action to prevent contamination.
Avoid direct contact with bird, bat or other animal droppings.
Avoid direct contact with animal blood. If contact cannot be prevented, wear rubber
gloves, and dispose properly.
Biting and Stinging Insects
Know what kind of biting and/or stinging insects to expect in the area or work location.
Ensure there is a ready supply of insect spray in work area.
If you are allergic to bee or wasp stings, always notify the work supervisor. Understand
and know how to administer the medication yourself.
Do not wear perfumes, colognes, scented soaps or powders.
Tuck pants into your socks or work boots. Wear light-colored clothes (camouflaged),
if possible.
Look out for stinging-insect nests – any visible signs of activity around a particular hole
or place.
Destroy standing water for mosquitoes
Do not swat at or make fast movements around stinging insects – most bees and wasps
will not sting unless they are provoked or startled.
ECOSYSTEM CONSERVATION AND MANAGEMENT PROJECT Page 41 of 41
If a bee or wasp nest must be removed from your immediate work area, notify the
relevant people immediately.
Small Wild Animals
Never touch or handle wild animals – healthy, sick or deceased. Parasites and other
infectious diseases may be present.
If bitten by a wild animal, clean the wound with soap and water, and obtain medical
assistance immediately, advising medical staff of the potential for infectious diseases,
such as rabies.
Bears
Bears are naturally shy, but extremely curious animals. If that curiosity is rewarded with food,
they become conditioned to be increasingly forward, even aggressive. They can cause injury
or death.
Confirm with the wildlife staff if there have been any recent bear sightings or incidents in the
respective work area. If working in an area with known bear activity, always be prepared.
Elephants / leopards:
Instructions of the Forest Department is always necessary for the protection from Wild
elephants & leopards.