electronics for range system prototype tests

12
Electronics for Range System Prototype Tests A. Piskun ITEP, Moscow, 28 April, 2010

Upload: susane

Post on 15-Jan-2016

41 views

Category:

Documents


0 download

DESCRIPTION

Electronics for Range System Prototype Tests. A. Piskun ITEP, Moscow, 28 April, 2010. DAQ VME crate 9U. VME crate 6U. VME crate 6U. COMPASS CATCH. MWDB units. Hot link cables. WIRE R/O analog & digital. STRIP R/O digital. to DAQ crate. RW-TDC QTC–16. ADB-32 (A-32). analog. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Electronics for Range System Prototype Tests

Electronics for Range System Prototype Tests

A. Piskun

ITEP, Moscow, 28 April, 2010

Page 2: Electronics for Range System Prototype Tests

VME crate 6U VME crate 6U

STRIP R/O digital

WIRE R/O analog & digital

RW-TDCRW-TDC QTC–16QTC–16

ASum-96

ADB-32 (A-32)

A2DB-32

analog

digital

COMPASS CATCH

DAQ VME crate 9U

MWDB unitsHot link cables

Range System Prototype Readout Scheme

to DAQ crate

Page 3: Electronics for Range System Prototype Tests

Digital R/O Block Diagram

A-32A-32

Strip R/O

ADB-32ADB-32 MWDBMWDB

STRIP SIGNALS(2304 channels)

CATCHCATCH

MWDBMWDB

WIRE SIGNALS(2304 channels)

CATCHCATCHWire R/O

Preamplifier Board (72)Amplifier-Discriminator

Board (72)

Muon Wall Digital Board (24 total)

1 unit

1 unit

Double Amplifier-Discriminator Board (72)

(Digital output)A2DB-32A2DB-32

Page 4: Electronics for Range System Prototype Tests

Analog (wire) R/O Block Diagram

WIRE SIGNALS(2304 channels / 96 per layer)

ASum-96ASum-96

A2DB-32A2DB-32

A2DB-32A2DB-32

A2DB-32A2DB-32

3 boards per layer1 board per layer

24 total

QTC-16QTC-16

Charge-to-Time Converter

2 boards total

RW-TDCRW-TDC

2 boards total

CATCH

Analog output

Page 5: Electronics for Range System Prototype Tests

Double Amplifier-Discriminator Board (A2DB-32)

2 modes of amplification:

K1= 65 mV/uA

K2=420 mV/uA

Designed both for wire and strip R/O

Analog and 2 digital (ECL, LVDS) outputs

Low noise: I noise r.m.s = 38nA

Low cross talk < -45 dB

Status: “table-top” tested, ready for production (80 with spares)

Page 6: Electronics for Range System Prototype Tests

Front-end Electronics for Strip R/O

32-channel preamplifier 32-channel preamplifier board A-32 v.3;board A-32 v.3; prototype prototype manufactured and tested;manufactured and tested; ready for productionready for production (80 (80 with spares)with spares)

32-channel amplifier-32-channel amplifier-discriminator board discriminator board

ADB-32ADB-32; ; tested in tested in D0/FNAL and D0/FNAL and COMPASS/CERN (MW1);COMPASS/CERN (MW1); ready for productionready for production (80 (80 with spares)with spares)

Page 7: Electronics for Range System Prototype Tests

Analog Summator Board (ASum-96)

Status: designed and being manufactured, need to produce 30 (with spares)

Page 8: Electronics for Range System Prototype Tests

ASum-96 Schematic Circuit Diagram

Page 9: Electronics for Range System Prototype Tests

ASum-96 PSpise Modeling

Yellow – Yellow – input signal input signal (from A2DB-32 analog (from A2DB-32 analog output)output)

Red – Red – 11stst summing stage summing stage outputoutput

Blue – Blue – 22ndnd summing summing stage outputstage output

Green – Green – output buffer output buffer signalsignal

Page 10: Electronics for Range System Prototype Tests

Charge –to-Time Converter (QTC-16)

Status: “table-top” tested, 2 boards manufactured, 1 spare needed

Page 11: Electronics for Range System Prototype Tests

Muon Wall Digital Board (MWDB)

Status: tested in COMPASS (MW1), 5 ready, need to produce 21(with spares)

192-channel register based on 6 F1 chips

Page 12: Electronics for Range System Prototype Tests

Status of Units:

A2DB-32 “Table-top” tested, 72 boards needed, to produce 80 (with spares)

A-32 “Table-top” tested, 72 boards needed, to produce 80 (with spares)

ADB-32 Tested in D0/FNAL and COMPASS/CERN (MW1), 72 boards needed, to produce 80 (with spares)

ASum-96 Designed and being manufactured, needs final test, to produce 30 (with spares)

QTC-16 “Table-top” tested, 2 boards produced, to produce 1 spare

RW-TDC Tested in COMPASS/CERN (RW), need to borrow 2 units (from Rich Wall)

MWDB Tested in COMPASS/CERN (MW1), 24 needed, 5 boards produced, need to produce 21 (with spares)

CATCH Need to borrow 2 units (from COMPASS)