economic feasibility study for highway 640

34
ECONOMIC FEASIBILITY STUDY FOR HIGHWAY 640

Upload: sadegh-tabatabaei

Post on 22-Jan-2018

381 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Economic Feasibility Study for Highway 640

ECONOMIC FEASIBILITY

STUDY FOR HIGHWAY

640

Page 2: Economic Feasibility Study for Highway 640

Objective of Study

to provide a decision-making tool between our two investment alternatives

to study and analyze alternatives and recommend the best choice of

investment. Finally to perform an assessment analysis for the alternative

through sensitivity analysis.

Moreover, the objective of choosing the Sustainable Highway as one of the

alternatives is to play a leading role in a sustainable future. In addition, to

improve the quality of highway design and so reduce to the cost of operations

on the long term.

Page 3: Economic Feasibility Study for Highway 640

Alternative Consideration

Alternative 1

Traditional Highway Design

Alternative 2

Sustainable Highway Design

Page 4: Economic Feasibility Study for Highway 640

Alternative Consideration

Alternative 1

Regular Asphalt Pavement

Electric Lightning Poles

No Environmental landscaping

Regular Tolls Machines

Alternative 2

Concrete PCCP Pavement

Solar Panel Lightning poles

Environmental landscaping

Electronic Toll Collection System

Higher useful life

Higher traffic capacity

Lower O&M costs

Page 5: Economic Feasibility Study for Highway 640

Data & Assumptions- Alternative 1 Initial Cost = $407,176,368 CAD

Alternative 1- INTIAL

COSTS Description Unit

Unit

cost ($) Cost ($)

Clearing of vegetation Clearing and grubbing m^2 3 9720000

Grading; Earth worksEarth excavation or fill

m^327.06 14650000

%

LandscapingSodding and top soil m^2 3.52 11404800

Top soil m^3 2.67 2560000

Drainage of the right of

the way

Curb and Gutter m 360 38880000

500 mm pipe culvert + end

sections m249 26892000

1500 mm wide box culvert m 350 37800000

storm water sweres m 65 7020000

Guard rails and safety

appurtenant

Concrete median m 313 33804000

Steel guardrail at shoulder m 56 6048000

3 cable guard rail at

shoulder m10 1080000

Fencing and gates Chain link fence m 15 1620000

Wire fence m 9.03 975240

Lighting PolesHight mast Piece 3000 600000

Standard Piece 1300 10920000

Toll Booth and Gates

Traffic controlPainting of taraffic control

lines Km 576 62208

TOTAL 204036248

Pavement

layers

Description of payment

layerAmount

Quantit

y per

Km

Price per

unit per

2 lane

8 lane

total in

HIGHWAY

407

Cost/ Km Total cost

surface H1-1. Mm(t) 40 750 84.75 339 254250 27459000

BinderMedium Binder Duty,

mm(t)60 1125 66.2 264.8 297900

32173200

Extra

layer

Medium Binder Duty,

mm(t)60 1125 66.2 264.8 297900

32173200

Base Granular A, mm(t) 150 6991 16.04 64.16 448542.5648442596.4

8

Subbase Granular A, mm(t) 450 15206 8.27 33.08 503014.4854325563.8

4

Shoulder H1-1 . Mm(t) 40 100 84.75 339 33900 3661200

ShoulderMedium Binder Duty,

mm(t)50 125 66.2 264.8 33100

3574800

Subgradesubgrade improvement,

% area(m^2)500 6.16 24.64 12320

1330560

TOTAL203140120.

3

Page 6: Economic Feasibility Study for Highway 640

Data & Assumptions- Alternative 2 Initial Cost = $459,123,752 CAD

Pavement

layers

Description of payment layer,

Amount ( quantity)

Quantity

per Km

Price per

unit per

2 lane

8 lane

total in

HIGHWAY

407

Cost per Km Total cost Total cost

surface PCCP ( 120mm ) (t) 750 94.92 379.68 284760 30754080 27459000

Binder Medium Binder Duty, mm(t) 1125 66.2 264.8 29790032173200 32173200

Extra layer Medium Binder Duty, mm(t) 1125 66.2 264.8 29790032173200 32173200

Base Granular A, mm(t) 6991 16.04 64.16 448542.5648442596 48442596.48

Subbase Granular A, mm(t) 15206 8.27 33.08 503014.4854325564 54325563.84

Shoulder PCCP ( 120mm ) (t) 100 94.92 379.68 37968 4100544 3661200

Shoulder Medium Binder Duty, mm(t) 125 66.2 264.8 331003574800 3574800

Subgradesubgrade improvement, %

area(m^2)500 6.16 24.64 12320

1330560 1330560

TOTAL 206874544 203140120.3

INTIAL COSTS Description Unitunit cost

($)quantity Cost

Cleraring of

vegeterianClearing and grubbing m^2 3 9720000

Grading; Earth

works

Earth excavation or fill m^3 27.06 14650000

Percent of rock excavation or

fill%

LandscapingSodding and top soil m^2 4.22 13685760

Top soil m^3 3.2 3072000

Drainage of the

right of the way

Curb and Gutter m 360 108000 38880000

500 mm pipe culvert + end

sectionsm 249 108000 26892000

1500 mm wide box culvert m 350 108000 37800000

bioretention swale drain km 50000 108 5400000

Guard rails and

safety appurtenats

Concrete median m 313 108000 33804000

Steel guardrail at shoulder m 56 108000 6048000

3 cable guard rail at shoulder m 10 108000 1080000

Fencicng and gatesChain link fence m 15 108000 1620000

Wire fence m 9.03 108000 975240

Lighting Solar Panel Lights Piece 1700 16800 28560000

Electronic Tolling

SystemPiece 50 600000 30000000

Traffic controlPainting of taraffic control

linesKm 576 108 62208

TOTAL 252249208

Page 7: Economic Feasibility Study for Highway 640

Annual Operation & Maintenance Expenses –

Alternative 1Operation and Maintenace Costs for Traditianl Highway Construction Option

year

System Operation

Expenses

Customer

Operation

Expenses

Highway

Maintenance

Expenses

General and

Admistration

Expenses

Contract

Expenses Total Expense year EOY

2015 0 2015 0

2016 37,513,000.00 77,400,000.00 3,513,407.79 23,000,000.00 6,900,000.00 (148,326,407.79) 2016 1

2017 38,214,493.10 78,847,380.00 3,579,108.51 23,430,100.00 7,029,030.00 (151,100,111.61) 2017 2

2018 38,929,104.12 80,321,826.01 3,646,037.84 23,868,242.87 7,160,472.86 (153,925,683.70) 2018 3

2019 39,657,078.37 81,823,844.15 3,714,218.75 24,314,579.01 7,294,373.70 (156,804,093.98) 2019 4

2020 40,398,665.73 83,353,950.04 3,783,674.64 24,769,261.64 7,430,778.49 (159,736,330.54) 2020 5

2021 41,154,120.78 84,912,668.90 3,854,429.35 25,232,446.83 7,569,734.05 (162,723,399.92) 2021 6

2022 41,923,702.84 86,500,535.81 3,926,507.18 25,704,293.59 7,711,288.08 (165,766,327.50) 2022 7

2023 42,707,676.08 88,118,095.83 3,999,932.87 26,184,963.88 7,855,489.16 (168,866,157.82) 2023 8

2024 43,506,309.63 89,765,904.22 4,074,731.61 26,674,622.70 8,002,386.81 (172,023,954.98) 2024 9

2025 44,319,877.62 91,444,526.63 4,150,929.09 27,173,438.15 8,152,031.44 (175,240,802.93) 2025 10

2026 45,148,659.33 93,154,539.28 4,228,551.47 27,681,581.44 8,304,474.43 (178,517,805.95) 2026 11

2027 45,992,939.26 94,896,529.17 4,307,625.38 28,199,227.01 8,459,768.10 (181,856,088.92) 2027 12

2028 46,853,007.22 96,671,094.26 4,388,177.97 28,726,552.56 8,617,965.77 (185,256,797.78) 2028 13

2029 47,729,158.46 98,478,843.72 4,470,236.90 29,263,739.09 8,779,121.73 (188,721,099.90) 2029 14

2030 48,621,693.72 100,320,398.10 4,553,830.33 29,810,971.01 8,943,291.30 (192,250,184.47) 2030 15

2031 49,530,919.39 102,196,389.55 4,638,986.96 30,368,436.17 9,110,530.85 (195,845,262.92) 2031 16

2032 50,457,147.59 104,107,462.03 4,725,736.02 30,936,325.93 9,280,897.78 (199,507,569.34) 2032 17

2033 51,400,696.25 106,054,271.57 4,814,107.28 31,514,835.22 9,454,450.57 (203,238,360.88) 2033 18

2034 52,361,889.27 108,037,486.45 4,904,131.08 32,104,162.64 9,631,248.79 (207,038,918.23) 2034 19

2035 53,341,056.59 110,057,787.45 4,995,838.34 32,704,510.48 9,811,353.14 (210,910,546.00) 2035 20

2036 54,338,534.35 112,115,868.07 5,089,260.51 33,316,084.83 9,994,825.45 (214,854,573.21) 2036 21

2037 55,354,664.95 114,212,434.80 5,184,429.68 33,939,095.61 10,181,728.68 (218,872,353.73) 2037 22

2038 56,389,797.18 116,348,207.33 5,281,378.52 34,573,756.70 10,372,127.01 (222,965,266.75) 2038 23

2039 57,444,286.39 118,523,918.81 5,380,140.30 35,220,285.95 10,566,085.79 (227,134,717.23) 2039 24

2040 58,518,494.54 120,740,316.09 5,480,748.92 35,878,905.30 10,763,671.59 (231,382,136.45) 2040 25

2041 59,612,790.39 122,998,160.00 5,583,238.93 36,549,840.83 10,964,952.25 (235,708,982.40) 2041 26

2042 60,727,549.57 125,298,225.60 5,687,645.49 37,233,322.85 11,169,996.86 (240,116,740.37) 2042 27

2043 61,863,154.75 127,641,302.41 5,794,004.47 37,929,585.99 11,378,875.80 (244,606,923.41) 2043 28

2044 63,019,995.74 130,028,194.77 5,902,352.35 38,638,869.25 11,591,660.77 (249,181,072.88) 2044 29

2045 64,198,469.66 132,459,722.01 6,012,726.34 39,361,416.10 11,808,424.83 (253,840,758.94) 2045 30 (300,000,000.00)

(250,000,000.00)

(200,000,000.00)

(150,000,000.00)

(100,000,000.00)

Page 8: Economic Feasibility Study for Highway 640

Annual Operation & Maintenance Expenses –

Alternative 2Operation and Maintenace Costs for Traditianl Highway Construction Option

year

System

Operation

Expenses

Customer

Operation

Expenses

Highway

Maintenance

Expenses

General and

Admistration

Expenses

Contract

Expenses Total Expense year EOY

2015 - 2015 0

2016 16,300,000.00 77,400,000.00 4,797,407.79 23,000,000.00 6,900,000.00 (128,397,407.79) 2016 1

2017 16,604,810.00 78,847,380.00 4,887,119.31 23,430,100.00 7,029,030.00 (130,798,439.31) 2017 2

2018 16,915,319.95 80,321,826.01 4,978,508.44 23,868,242.87 7,160,472.86 (133,244,370.13) 2018 3

2019 17,231,636.43 81,823,844.15 5,071,606.55 24,314,579.01 7,294,373.70 (135,736,039.85) 2019 4

2020 17,553,868.03 83,353,950.04 5,166,445.59 24,769,261.64 7,430,778.49 (138,274,303.79) 2020 5

2021 17,882,125.36 84,912,668.90 5,263,058.12 25,232,446.83 7,569,734.05 (140,860,033.27) 2021 6

2022 18,216,521.11 86,500,535.81 5,824,381.93 25,704,293.59 7,711,288.08 (143,957,020.52) 2022 7

2023 18,557,170.05 88,118,095.83 5,461,736.94 26,184,963.88 7,855,489.16 (146,177,455.86) 2023 8

2024 18,904,189.13 89,765,904.22 5,563,871.42 26,674,622.70 8,002,386.81 (148,910,974.29) 2024 9

2025 19,257,697.47 91,444,526.63 5,667,915.81 27,173,438.15 8,152,031.44 (151,695,609.51) 2025 10

2026 19,617,816.41 93,154,539.28 3,466,469.11 27,681,581.44 8,304,474.43 (152,224,880.67) 2026 11

2027 19,984,669.58 94,896,529.17 5,881,877.88 28,199,227.01 8,459,768.10 (157,422,071.74) 2027 12

2028 20,358,382.90 96,671,094.26 5,991,868.99 28,726,552.56 8,617,965.77 (160,365,864.48) 2028 13

2029 20,739,084.66 98,478,843.72 6,103,916.95 29,263,739.09 8,779,121.73 (163,364,706.15) 2029 14

2030 21,126,905.54 100,320,398.10 65,221,924.71 29,810,971.01 8,943,291.30 (225,423,490.67) 2030 15

2031 21,521,978.68 102,196,389.55 6,334,337.92 30,368,436.17 9,110,530.85 (169,531,673.16) 2031 16

2032 21,924,439.68 104,107,462.03 6,452,790.04 30,936,325.93 9,280,897.78 (172,701,915.45) 2032 17

2033 22,334,426.70 106,054,271.57 6,573,457.21 31,514,835.22 9,454,450.57 (175,931,441.27) 2033 18

2034 22,752,080.48 108,037,486.45 6,696,380.86 32,104,162.64 9,631,248.79 (179,221,359.22) 2034 19

2035 23,177,544.38 110,057,787.45 6,821,603.18 32,704,510.48 9,811,353.14 (182,572,798.64) 2035 20

2036 23,610,964.46 112,115,868.07 13,291,000.01 33,316,084.83 9,994,825.45 (192,328,742.82) 2036 21

2037 24,052,489.50 114,212,434.80 7,079,116.59 33,939,095.61 10,181,728.68 (189,464,865.19) 2037 22

2038 24,502,271.05 116,348,207.33 7,211,496.07 34,573,756.70 10,372,127.01 (193,007,858.17) 2038 23

2039 24,960,463.52 118,523,918.81 7,346,351.04 35,220,285.95 10,566,085.79 (196,617,105.11) 2039 24

2040 25,427,224.19 120,740,316.09 7,483,727.81 35,878,905.30 10,763,671.59 (200,293,844.98) 2040 25

2041 25,902,713.28 122,998,160.00 7,623,673.52 36,549,840.83 10,964,952.25 (204,039,339.88) 2041 26

2042 26,387,094.02 125,298,225.60 7,766,236.21 37,233,322.85 11,169,996.86 (207,854,875.54) 2042 27

2043 26,880,532.68 127,641,302.41 7,911,464.83 37,929,585.99 11,378,875.80 (211,741,761.71) 2043 28

2044 27,383,198.64 130,028,194.77 84,536,039.43 38,638,869.25 11,591,660.77 (292,177,962.86) 2044 29

2045 27,895,264.45 132,459,722.01 8,210,120.18 39,361,416.10 11,808,424.83 (219,734,947.57) 2045 30 (350,000,000.00)

(300,000,000.00)

(250,000,000.00)

(200,000,000.00)

(150,000,000.00)

(100,000,000.00)

Page 9: Economic Feasibility Study for Highway 640

Revenues- Alternative 1

Alternative 1 Alternative 2

0

50000000

100000000

150000000

200000000

250000000

300000000

350000000

400000000

450000000

500000000

Annual

Revenues

($)

Year

TOTAL REVENU Over Life Cycle of Project- Traditional Highway

0

100000000

200000000

300000000

400000000

500000000

600000000

700000000

Annual

Revenues

($)

Year

TOTAL REVENU Over Life Cycle of Project- Sustainable Highway

Page 10: Economic Feasibility Study for Highway 640

General Project Assumptions

Assumption Reference

MARR 3.95%

Based on the Inflation rate & Real

interest rate

Inflation Rate 1.07 Inflation Canada

Depreciation Rate 8% CCA Classes- Canada Revenue Agency

Corporate Tax

Rate 26.5%

Canada Revenue Agency

ATMARR 3% Based on MARR

Planning Horizon 30 years -

Bank Loan Interest

Rate

6% Highway 407 Ontario

Page 11: Economic Feasibility Study for Highway 640

Methods of Evaluation

The 8 Steps of a Systematic Economic Analysis

Technique:

1. Identify the alternatives

2. Define the planning horizon

3. Specify the discount rate

4. Estimate the cash flows (BTCF)

5. Determine the After Tax Cash Flow (ATCF)

6. Compare the alternatives

7. Perform supplementary analyses

8. Select the preferred investment

Page 12: Economic Feasibility Study for Highway 640

2. Defining The Planning Horizon

The planning horizon is the amount of time an organization will look into the future

when preparing a strategic plan.

Four methods:

1. LCM

2. Longest Life

3. Shortest Life

4. Organizational needs

The planning horizon is estimated according to our “Firm’s need” decision based on

our contract duration period of 30 years, rather than the “Longest Life” planning

horizon which equals to 60 years.

Page 13: Economic Feasibility Study for Highway 640

3. Specify the discount rate

The minimum attractive rate of return (MARR) is the interest rate that a firm

wished to earn on its investment

In order to calculate the value of MARR, the following equation is used:

(1 + MARR) = (1 + r) * (1+ f) where,

r = Real Interest rate

f = Inflation Rate

Real Interest Rate = 2.85% Annual Inflation Rate = 1.07% (Inflation Canada 2015(CPI))

From the equation, MARR = 3.95%

Page 14: Economic Feasibility Study for Highway 640

4. Estimate The Before Tax Cash Flow (BTCF)

Bank Loan Cash Flow Project Cash Flow

Page 15: Economic Feasibility Study for Highway 640

Bank Loan Cash Flow

Financing Plan A Financing Plan B

Page 16: Economic Feasibility Study for Highway 640

BANK Loan Repayment Plans

Four loan repayment plans are evaluated:

1. Pay interest due at end of each year, and principal at end of year 30.

2. Make equal end-of-period principal payments of $10,179,409.21 and pay

interest each period on the unpaid balance at the beginning of the period.

3. Make 30 equal end-of-period payments over the loan period.

4. Make no payment until the end of the loan period.

Corporate interest rate of 6% compounded annually.

Method #2 has been chosen: Make equal end-of-period principal payments of

$10,179,409.21 and pay interest due at the end of each period. The interest

of each period is the interest on the unpaid balance at the beginning of the

year.

Page 17: Economic Feasibility Study for Highway 640

Tabular Method- Alternative 1

Using the Tabular Method,

the annual payment

(includes the principal &

interest) is calculated

using the annual worth

equation

Using The Tabular method,

the loan payment schedule

is constructed showing the

remaining balance at the

end of each year, Interest

payment and Principal

payment.

The payment will start

after the first year when

the construction phase is

over.

Page 18: Economic Feasibility Study for Highway 640

Loan Repayment Cash Flow- Alternative 1

(50,000,000.00)

-

50,000,000.00

100,000,000.00

150,000,000.00

200,000,000.00

250,000,000.00

300,000,000.00

350,000,000.00

Bank L

oan C

ash

Flo

w (

$)

Year

Page 19: Economic Feasibility Study for Highway 640

Tabular Method- Alternative 2

Using the Tabular Method,

the annual payment

(includes the principal &

interest) is calculated

using the annual worth

equation

Using The Tabular method,

the loan payment schedule

is constructed showing the

remaining balance at the

end of each year, Interest

payment and Principal

payment.

The payment will start

after the first year when

the construction phase is

over.

Page 20: Economic Feasibility Study for Highway 640

Loan Repayment Cash Flow- Alternative 2

(100,000,000.00)

(50,000,000.00)

-

50,000,000.00

100,000,000.00

150,000,000.00

200,000,000.00

250,000,000.00

300,000,000.00

350,000,000.00

400,000,000.00

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

2027

2028

2029

2030

2031

2032

2033

2034

2035

2036

2037

2038

2039

2040

2041

2042

2043

2044

2045

Bank L

oan C

ash

Flo

w (

$)

Year

Page 21: Economic Feasibility Study for Highway 640

Project Cash Flow

Cash flows are key to discounted cash flow valuations. To measure cash flows,

the following parameters have to be taken into consideration:

1. Specify the initial investment.

2. Specify the discount rate

3. Determine the salvage value

4. Determine the annual operating & maintenance expenses.

5. Determine the annual net income.

6. Determine the net cash flow in each year.

Page 22: Economic Feasibility Study for Highway 640

Project Cash Flow

Alternative 1 Alternative 2

(500,000,000.00)

(400,000,000.00)

(300,000,000.00)

(200,000,000.00)

(100,000,000.00)

-

100,000,000.00

200,000,000.00

300,000,000.00

400,000,000.00

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30

Net

Befo

re T

ax C

ash

Flo

w($

)

End Of Year (EOY)

BTCF Traditional Highway-Alternative 1

(600,000,000.00)

(400,000,000.00)

(200,000,000.00)

-

200,000,000.00

400,000,000.00

600,000,000.00

800,000,000.00

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30

Net

Befo

re T

ax C

ash

Flo

w($

)

End Of Year (EOY)

BTCF Sustainable Highway

Page 23: Economic Feasibility Study for Highway 640

5. After Tax Cash Flow Analysis (ATCF)

INCOME TAX =Taxable income * Tax Rate

ATCF = Before Tax CF – income tax

MARR = ATMARR/ (1 – tax rate)

4% = ATMARR/ (1-26.5%)

ATMARR= 3%

CAA Depreciation Method

Page 24: Economic Feasibility Study for Highway 640

CAA Depreciation

The CCA rate for

highways is 8% in

class 17

Planning horizon =

30 years

Page 25: Economic Feasibility Study for Highway 640

ATCF

Salvage Value/Market

Value > Book value @ year

30

Page 26: Economic Feasibility Study for Highway 640

6. Compare Between Alternatives

Single project- Investment Worth Measurement:

1. Payback Period (PBP)

2. Present Worth (PW)

3. Annual Worth (AW)

4. Future Worth (FW)

5. Internal Rate of Return (IRR)

6. External Rate of Return (ERR)

7. Capitalized worth method (CW)

Accept the investment if:

PW >= 0$

FW >= 0$

AW >= 0$

IRR >= ATMARR

ERR >= ATMARR

Page 27: Economic Feasibility Study for Highway 640

6. Compare Between Alternatives

PW analysis results:

The Present Worth (PW) of alternative 2 is $1,954,306,928 CAD and bigger than 0. The PW for Alternative 1 is $544,853,106 CAD and bigger than 0. The two investments are accepted.

AW analysis results:

Based on the Annual Worth analysis (AW) for each alternative, alternatives 1&2 are accepted.

FW analysis results:

Based on the Future Worth analysis (FW), FW1= $ 1 284 519 418,31 > 0, and FW2 =4,607,379,805 > 0, both alternatives are accepted.

IRR analysis:

IRR for Alternative 1- Simple investment (one sign change) is 10.92%

IRR for Alternative 2- Simple investment (one sign change) is 35%

Both alternative IRR’s value are bigger than that of the ATMARR, but IRR Alternative B is higher and so the Sustainable Highway investment is more attractive, since the higher the IRR on a project and the greater the amount by which it exceeds the cost of capital.

Page 28: Economic Feasibility Study for Highway 640

Ranking Approach

In order to compare

between

alternatives using

the ranking

approach:

Find PW, of

Alternatives 1&2

Select the one with

the highest positive

PW value. Where;

Present worth (PW)

= F*(1+i) n

Consider the option

of “Doing Nothing”

= not to invest in

either alternatives.

Alternative B - Sustainable highway

is selected; PW(B) is the highest.

Page 29: Economic Feasibility Study for Highway 640

Incremental Approach PW (B-A) > 0 select alternative B If IRR (B-A) > ATMARR

PW (B-A) = 0 select either one If IRR (B-A) = ATMARR

PW (B-A) < 0 select alternative A If IRR (B-A) < ATMARRT

PW (A-0) = $497,746,362.54 > 0

Alternative A is better than “do nothing”

PW (B- A) = $1,509,677,166.62 > 0

Alternative (B) is better than Alternative (A)

Alternative B is the best.

Page 30: Economic Feasibility Study for Highway 640

Supplementary Analysis 1. Sensitivity Analysis

Case 1

All parameters are fixed except for “ATMARR”.

Shows how change in ATMARR affect PW, AW, FW, and IRR.

$-

$200,000,000.00

$400,000,000.00

$600,000,000.00

$800,000,000.00

$1,000,000,000.00

$1,200,000,000.00

$1,400,000,000.00

Valu

e i

n $

% Error ATMARR

Sensitivity - % Error ATMARR -Alternative 1

PW Traditional

FW Traditional

AW Traditional

IRR Traditional

Page 31: Economic Feasibility Study for Highway 640

Supplementary Analysis 1. Sensitivity Analysis

Case 2

All parameters are fixed except for “The total number of highway user”, which

directly affect the revenues.

Shows how change in the Revenue affect on “PW”, “AW”, “FW”, and “IRR”.

$(2,000,000,000.00)

$-

$2,000,000,000.00

$4,000,000,000.00

$6,000,000,000.00

$8,000,000,000.00

$10,000,000,000.00

$12,000,000,000.00

Valu

e in $

% Error No. of Users

Sensitivity - % Error No. of Users -Sustainable

PW Sustainable

FW Sustainable

AW Sustainable

IRR Sustainable

Page 32: Economic Feasibility Study for Highway 640

Supplementary Analysis Depreciation Methods Comparison-Alternative 1

0

50000000

100000000

150000000

200000000

250000000

300000000

350000000

400000000

450000000

1 2 3 4 5 6 7 8 9 10111213141516171819202122232425262728293031

AN

NU

AL B

OO

K V

ALU

E (

$)

YEAR

Comparision between Depreciation Methods

streight line

SOYD

CCA

Page 33: Economic Feasibility Study for Highway 640

Methods of Loan Repayment Comparison for

Alternative 1

Page 34: Economic Feasibility Study for Highway 640

8.Select Preferred Investment

The two alternatives have been evaluated using the 8 Economic Methods of

Evaluation, Alternative 2, the Sustainable Highway design for Highway 640 is

selected, since it best meets the objectives of the study.