Ease of Doing Business- Uttarakhand DIPP Point 254 254 Area 9c: Inspection by Building Proposal Office / relevant agency as part of obtaining construction permit Design and implement a system for identifying establishments that need to be inspected based on computerized risk assessment Sr. No Description Notification URL 1 Notification of the Comprehensive Formal Building Bye Laws namely Uttarakhand Building Bye Laws, 2016 applicable to the entire State 837/V-2-2016- 127/Aa/15-TC http://www.uhuda.org.in/by e_laws/ http://www.uhuda.org.in/wp - content/uploads/2016/06/b bl_2016.pdf 2 Circular Resolution passed by SIDA Board for Adoption of Uttarakhand Building Bye Laws 2016 453/CEO/SIDA/20 16 dated 06.06.2016 http://www.sidaonline.in/ 3 Government Order of Urban Development Directorate for all the ULBs across the State of Uttarakhand for the adoption of Uttarakhand Building Bye Laws, 2016 1093/IV(2)-Sha. Vi. – 2016 – 19 (Sa) / 16 dated 29.06.2016 Attached 4 Provision in the Uttarakhand Building Bye Laws 2016 for Inspections done on the basis of Risk Assessment into Low, Medium and High Categories - http://www.uhuda.org.in/wp - content/uploads/2016/06/b bl_2016.pdf (Page 194- 195) 5 System for identifying establishments that need to be inspected based on computerized risk assessment and implemented in the BPAMS Software at the time of obtaining Construction Permit / Building plan approval certificate - Attached

Upload: vutu

Post on 15-Mar-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business- Uttarakhand

DIPP Point 254

254

Area 9c: Inspection by

Building Proposal Office /

relevant agency as part of

obtaining construction permit

Design and implement a system for identifying

establishments that need to be inspected based on

computerized risk assessment

Sr.

No Description Notification URL

1

Notification of the Comprehensive

Formal Building Bye Laws namely

Uttarakhand Building Bye Laws, 2016

applicable to the entire State

837/V-2-2016-

127/Aa/15-TC

http://www.uhuda.org.in/by

e_laws/

http://www.uhuda.org.in/wp

-

content/uploads/2016/06/b

bl_2016.pdf

2

Circular Resolution passed by SIDA

Board for Adoption of Uttarakhand

Building Bye Laws 2016

453/CEO/SIDA/20

16 dated

06.06.2016

http://www.sidaonline.in/

3

Government Order of Urban

Development Directorate for all the

ULBs across the State of Uttarakhand

for the adoption of Uttarakhand

Building Bye Laws, 2016

1093/IV(2)-Sha.

Vi. – 2016 – 19

(Sa) / 16 dated

29.06.2016

Attached

4

Provision in the Uttarakhand Building

Bye Laws 2016 for Inspections done on

the basis of Risk Assessment into Low,

Medium and High Categories

-

http://www.uhuda.org.in/wp

-

content/uploads/2016/06/b

bl_2016.pdf (Page 194-

195)

5

System for identifying establishments

that need to be inspected based on

computerized risk assessment and

implemented in the BPAMS Software at

the time of obtaining Construction

Permit / Building plan approval

certificate

- Attached

Page 2: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business- Uttarakhand

Notification of the Comprehensive Formal Building Bye Laws namely Uttarakhand Building Bye Laws,

2016 (http://www.uhuda.org.in/wp-content/uploads/2016/06/bbl_2016.pdf)

Page 3: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business- Uttarakhand

Notification of the Comprehensive Formal Building Bye Laws namely Uttarakhand Building Bye Laws, 2016 (http://www.uhuda.org.in/wp-content/uploads/2016/06/bbl_2016.pdf)

Page 4: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business- Uttarakhand

Circular Resolution passed by SIDA Board for Adoption of Uttarakhand Building Bye Laws 2016

Page 5: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business- Uttarakhand

Circular Resolution passed by SIDA Board for Adoption of Uttarakhand Building Bye Laws 2016

Page 6: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business- Uttarakhand

Circular Resolution passed by SIDA Board for Adoption of Uttarakhand Building Bye Laws 2016

Page 7: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business- Uttarakhand

Circular Resolution passed by SIDA Board for Adoption of Uttarakhand Building Bye Laws 2016

Page 8: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business- Uttarakhand

Government Order of Urban Development Directorate for all the ULBs across the State of Uttarakhand for the adoption of Uttarakhand Building Bye Laws, 2016 (page 1)

Page 9: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business- Uttarakhand

Government Order of Urban Development Directorate for all the ULBs across the State of Uttarakhand for the adoption of Uttarakhand Building Bye Laws, 2016 (page 2)

Page 10: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business- Uttarakhand

Provision in the Uttarakhand Builidng Bye Laws 2016 for Inspections done on the basis of Risk

Assesment into Low, Medium and High Categories http://www.uhuda.org.in/wp-

content/uploads/2016/06/bbl_2016.pdf (Page 194-195)

Page 11: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business- Uttarakhand

SIDA

System for identifying establishments that need to be inspected based on computerized risk

assessment and implemented in the BPAMS Software at the time of obtaining Construction Permit /

Building plan approval certificate

Risk Based Classification Implementation at the time of Submitting the Application for CTE

Login: http://www.sidaonline.in/

Dashboard of the applicant where he submits a new proposal:

http://www.sidaonline.in/SWC.Admin/Home.aspx

Page 12: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business- Uttarakhand

Proposal Form For CTE: http://www.sidaonline.in/SWC.Admin/Home.aspx

Risk based classification: http://www.sidaonline.in/SWC.Admin/Home.aspx

Proposal risk will be calculated on the basis of following Parameters:

1. Building Classification

2. Plot Type

3. Industrial Area

4. Assembly Type

5. Slope

6. Floor area

7. Experience of the Design and Building

Team

8. Height of the Building

Page 13: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business - Uttarakhand Construction Permit Enablers

1

Page 14: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business - Uttarakhand Construction Permit Enablers

2

After Filling form Click on save - http://www.sidaonline.in/SWC.Admin/Home.aspx

On the basis of Risk Based Classification Parameters, Proposal Risk is calculated as either High

Risk, Low Risk or Medium Risk & on the right side of it (marked with an arrow below), the Risk

Matrix is also shown http://www.sidaonline.in/SWC.Admin/Home.aspx

Page 15: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business - Uttarakhand Construction Permit Enablers

3

The Risk Matrix shows that for each individual item, what Risk Level has been calculated and the overall

Risk Category of the Building is decided based on the highest risk parameter breached.

http://www.sidaonline.in/SWC.Admin/Home.aspx

In the following case since the Slope & Height of the Building are both in high risk category, hence

the overall risk of the building has been calculated as High Risk.

Inspections are then controlled basis the Risk Category of the Building – Preliminary inspection for

Low and Medium risk building is not required and only Self – certification is required.

Page 16: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business - Uttarakhand Construction Permit Enablers

4

Housing Department

System for identifying establishments that need to be inspected based on computerized risk

assessment and implemented in the BPAMS Software at the time of obtaining Construction Permit /

Building plan approval certificate

Risk Based Classification Implementation at the time of Submitting the Application for CTE

Website of Housing Department http://mddaonline.in/index.php & click on Building Plan Approval

Login with Applicant

Page 17: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business - Uttarakhand Construction Permit Enablers

5

Dashboard of the applicant where he submits a new proposal:

New Application Submission Form

Page 18: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business - Uttarakhand Construction Permit Enablers

6

Risk based classification: Proposal risk will be calculated on the basis of following Parameters:

1. Building Classification

2. Plot Type

3. Industrial Area

4. Assembly Type

5. Slope

6. Floor area

7. Experience of the Design and Building Team

8. Height of the Building

Proposal Use

Page 19: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business - Uttarakhand Construction Permit Enablers

7

Proposal Type

Building classification

Page 20: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business - Uttarakhand Construction Permit Enablers

8

Select District

Select Sector

Page 21: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business - Uttarakhand Construction Permit Enablers

9

Assembly Type

Floor area

Page 22: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business - Uttarakhand Construction Permit Enablers

10

Experience of the design team

Slope

Page 23: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business - Uttarakhand Construction Permit Enablers

11

UPCB Consent

Other Information

Page 24: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business - Uttarakhand Construction Permit Enablers

12

Save and Continue

Confirmation

Page 25: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business - Uttarakhand Construction Permit Enablers

13

Temporary file number is generated.

On the basis of Risk Based Classification Parameters, Proposal Risk is calculated as either High Risk, Low Risk or

Medium Risk & on the right side of it (marked with an arrow below), the Risk Matrix is also shown. Here it is shown

as High Risk. There is a Mesh Button which activates after the Risk Calculation.

Page 26: Ease of Doing Business- Uttarakhandsidaonline.in/UserManual/DIPP Point 254.pdf · Proposal Form For CTE: ... The Risk Matrix shows that for each individual item, ... Ease of Doing

Ease of Doing Business - Uttarakhand Construction Permit Enablers

14

After clicking on the Mesh Button, Risk Calculated on the basis of parameters. The Risk Matrix shows that for

each individual item, what Risk Level has been calculated and the overall Risk Category of the Building is decided

based on the highest risk parameter breached.

In the Following Case – Since Assembly Type and Height of the Building is under High Risk the overall Risk

Category of the Building has been calculated as High Risk

In the following case since the Slope & Height of the Building are both in high risk category, hence the overall risk of the building has been calculated as High Risk. Inspections are then controlled basis the Risk Category of the Building – Preliminary inspection for Low and Medium risk building is not required and only Self – certification is required.