Transcript
Page 1: Project Management Class ( based on PMBOK) - Day 6

{

Project Management

Joe DiFalcoPMP, PMI-ACP, CSPO, Systems Engineer

Owner CVShout™

Profile: CVShout.com/joedifalcoContact: [email protected]

Review of the Project Management Body of Knowledge (PMBOK) 5th edition

Page 2: Project Management Class ( based on PMBOK) - Day 6

Day 5 review Ethics Earned value management

Knowledge Areas Procurement Management

Risk topics Cost topics Scope topics Time topics Tips and tricks for PMP test

Day 6 Agenda

Page 3: Project Management Class ( based on PMBOK) - Day 6

Ethics ReviewYou are a project manager of a company and your project is currently in execution phase. The customer has requested you for additional work. This work will affect the budget, but not the schedule of the project. What should you do next?A. Add the additional requirements to the project plan.B. Ignore the request.C. Explain the change procedure and ask to submit a request

for change.D. Discuss with the project team about the change.

C is the correct answer.Explain the change procedure and ask to submit a request for change is the best choice.

Page 4: Project Management Class ( based on PMBOK) - Day 6

Project Budget ComponentsKnown un-Knowns

un-Known un-Knowns

This is the level of granularity to track measurement

Page 5: Project Management Class ( based on PMBOK) - Day 6

Project Budget Components

Reserves

Contingency vs Management reserves

Page 6: Project Management Class ( based on PMBOK) - Day 6

Planned Value (PV)

From PMBOK 5th Edition

The approved budget for the work scheduled to be completed by a specified date.

• Scheduled work• Work for an activity (work breakdown component)• Defines the physical work that SHOULD have been

accomplished• Total of all PV can be referred to as:

• Total PV is also: budget at completion (BAC)

Page 7: Project Management Class ( based on PMBOK) - Day 6

Earned Value (EV)

From PMBOK 5th Edition

The approved budget for the work actually completed by the specified date

• Measure of work performed• Based on PV (authorized budget)• Percent complete of a project• EV cannot be greater than PV• Monitored:

• Incrementally – for current status• Cumulatively – performance trends

Page 8: Project Management Class ( based on PMBOK) - Day 6

Actual Cost (AC)

From PMBOK 5th Edition

• Realized cost incurred• Cost of work performed during a time period• Specific to the work that the EV measured• Corresponds to what was planned – PV• Has no upper limit – it is what it is

Page 9: Project Management Class ( based on PMBOK) - Day 6

Earned Value

From PMBOK 5th Edition

Page 10: Project Management Class ( based on PMBOK) - Day 6

Formulas to memorizeSchedule Variance (SV)

From PMBOK 5th Edition

Page 11: Project Management Class ( based on PMBOK) - Day 6

Formulas to memorizeCost Variance (CV)

From PMBOK 5th Edition

Page 12: Project Management Class ( based on PMBOK) - Day 6

Earned Value Measurement

From PMBOK 5th Edition

Exercise

Page 13: Project Management Class ( based on PMBOK) - Day 6

Earned Value Measurement

From PMBOK 5th Edition

Status after 1 hour

Page 14: Project Management Class ( based on PMBOK) - Day 6

Earned Value Measurement

From PMBOK 5th Edition

Use EVM to forecast

Page 15: Project Management Class ( based on PMBOK) - Day 6

Earned Value MeasurementAccountant’s Pal Online

Budget ad Completion BAC 1200

Planned Value PV 240

Earned Value EV 230

Actual Cost AC 250

Schedule Variance(EV – PV)

SV 230 – 240 = -10

Cost Variance(EV – AC)

CV 230 – 250 = -20

Schedule Performance Index (EV/PV)

SPI 230/240 = .95

Cost Performance Index(EV/AC)

CPI 230/250 = .92

Estimate at CompletionBAC/CPIAC + BAC – EVAC + [(BAC-EV)/(CPI*SPI]

EAC  1200/.92 = 1304250 + 1200 – 230 = 1220250+[(1200-230)/(.92*.95) = 1360

Estimate to Complete(EAC – AC) or re-Estimate

ETC 1304 – 250 = 1054

To Complete Performance Index(BAC – EV) / (BAC – AC)

TCPI (1200-230)/(1200-250) = 1.02

Variance at Completion(BAC – EAC)

VAC 1200 – 1304 = -104

Page 16: Project Management Class ( based on PMBOK) - Day 6

From PMBOK 5th Edition

Note: the numbers in the chart refer to the chapter in the PMBOK

Page 17: Project Management Class ( based on PMBOK) - Day 6

Procurement Management

From PMBOK 5th Edition

Page 18: Project Management Class ( based on PMBOK) - Day 6

Procurement Management

From PMBOK 5th Edition

Page 19: Project Management Class ( based on PMBOK) - Day 6

Procurement Management

From PMBOK 5th Edition

• Agreements• Binding contracts• Terms and conditions• Purchase order• Understanding• Usually subjected to extensive review/approval• Many times involves Legal department

Page 20: Project Management Class ( based on PMBOK) - Day 6

Plan Procurement Management

From PMBOK 5th Edition

Inputs

Fixed-price contracts• Firm Fixed Price (FFP)

• Most common• Variance – seller

• Fixed Price Incentive Fee (FPIF)• Price ceiling – incentives• Variance – seller• Incentive – seller

• Fixed Price with Economic Price Adjustment (FP-EPA)• Fixed price• Provision for change• Variance – seller and buyer

Cost reimbursable contracts• Cost Plus Fixed Fee (CPFF)

• Seller reimbursed for costs• Fee is fixed except for scope changes

• Cost Plus Incentive Fee (CPIF)• Seller reimbursed for costs• Buyer and seller share cost risk (+ /

-)• Cost Plus Award Fee (CPAF)

• Seller reimbursed for costs• Fee is subject to buyer’s evaluation

Time and Material (T&M)

Page 21: Project Management Class ( based on PMBOK) - Day 6

Plan Procurement Management

From PMBOK 5th Edition

Tools & Techniques

Page 22: Project Management Class ( based on PMBOK) - Day 6

Plan Procurement Management

From PMBOK 5th Edition

Outputs

Page 23: Project Management Class ( based on PMBOK) - Day 6

Conduct Procurements

From PMBOK 5th Edition

Inputs

Page 24: Project Management Class ( based on PMBOK) - Day 6

Conduct Procurements

From PMBOK 5th Edition

Tools & Techniques

Page 25: Project Management Class ( based on PMBOK) - Day 6

Conduct Procurements

From PMBOK 5th Edition

Outputs

Page 26: Project Management Class ( based on PMBOK) - Day 6

Control Procurements

From PMBOK 5th Edition

InputsTools & Techniques

Outputs

Page 27: Project Management Class ( based on PMBOK) - Day 6

Risk

From PMBOK 5th Edition

How an organization views risk

Page 28: Project Management Class ( based on PMBOK) - Day 6

Risk

From PMBOK 5th Edition

Risk Breakdown Structure (RBS)

Page 29: Project Management Class ( based on PMBOK) - Day 6

Risk

From PMBOK 5th Edition

Risk Impact Scales

Page 30: Project Management Class ( based on PMBOK) - Day 6

RiskProbability Impact Matrix

Page 31: Project Management Class ( based on PMBOK) - Day 6

Risk

From PMBOK 5th Edition

Techniques

Page 32: Project Management Class ( based on PMBOK) - Day 6

Risk

From PMBOK 5th Edition

Techniques

Page 33: Project Management Class ( based on PMBOK) - Day 6

Risk SWOT Analysis

Page 34: Project Management Class ( based on PMBOK) - Day 6

Risk

Risk Register

Page 35: Project Management Class ( based on PMBOK) - Day 6

Risk

From PMBOK 5th Edition

Page 36: Project Management Class ( based on PMBOK) - Day 6

Risk

From PMBOK 5th Edition

Qualitative Risk Analysis

Page 37: Project Management Class ( based on PMBOK) - Day 6

Risk

From PMBOK 5th Edition*Sometimes data is not available

Page 38: Project Management Class ( based on PMBOK) - Day 6

Risk

From PMBOK 5th Edition

Page 39: Project Management Class ( based on PMBOK) - Day 6

Risk

From PMBOK 5th Edition

Strategies for Negative Risks

Page 40: Project Management Class ( based on PMBOK) - Day 6

Risk

From PMBOK 5th Edition

Strategies for Negative Risks

Page 41: Project Management Class ( based on PMBOK) - Day 6

Risk

From PMBOK 5th Edition

Strategies for Positive Risks

Page 42: Project Management Class ( based on PMBOK) - Day 6

Tips and Tricks

From PMBOK 5th Edition

• PMP exam is NOT a test of PMBOK – you cannot rely on real world experience – rely on training aligned with PMBOK

• Make up of exam (probably changed for 5th Edition)• Initiating 11%• Planning 23%• Executing 27%• Monitoring/control 21%• Closing 9%• Ethics 9%

• 200 multiple choice – 175 count (need 106 to pass or 61%)• Know how to apply the information• About 150 “what would you do?” questions• 8-10 formula related questions• 10-12 earned value questions• Questions with 2 or more right answers – which is most

right• Questions with extraneous information• Questions with made up terms• Questions with more than one item in each answer - secret

Page 43: Project Management Class ( based on PMBOK) - Day 6

Tips and Tricks

From PMBOK 5th Edition

Study tips• Don’t

• Read every book you can find• Study too long• Not listen to advice from those who have passed

• The Magic Three – visit a topic 3 times to learn it• Take practice exams (take at lease 1 full, 4 hour test)• Plan your study program

• Test yourself with 20 questions in each group• Read one of the exam prep books• Use flash cards or other tools• Form a study group• Take a review course• Take practice exams until you can get 85%

Page 44: Project Management Class ( based on PMBOK) - Day 6

Tips and Tricks

From PMBOK 5th Edition

Recurring themes• Project managers can save the universe• The PM puts the best interests of the project first• Perspective of a large project (200 people from many

countries, takes at least a year, never been done before in the organization with a budget of $100M)

• PM has the power and perform all PMBOK activities• The PM is assigned during initiation• The PM understands the process of project

management• The PM always knows why their project was selected • The PM spends time planning, managing, assessing

and controlling scope, time, cost, quality, risk, resources and customer satisfaction

• Your organization has a PMO• Your organizations has OPA and EPA• A Work Breakdown Structure (WBS) is used on every

project)

Page 45: Project Management Class ( based on PMBOK) - Day 6

Tips and Tricks

From PMBOK 5th Edition

Invest:• Prep class• Prep book• Join PMI

Page 46: Project Management Class ( based on PMBOK) - Day 6

Thank You

From PMBOK 5th Edition

Any Questions?


Top Related