{
Project Management
Joe DiFalcoPMP, PMI-ACP, CSPO, Systems Engineer
Owner CVShout™
Profile: CVShout.com/joedifalcoContact: [email protected]
Review of the Project Management Body of Knowledge (PMBOK) 5th edition
Day 5 review Ethics Earned value management
Knowledge Areas Procurement Management
Risk topics Cost topics Scope topics Time topics Tips and tricks for PMP test
Day 6 Agenda
Ethics ReviewYou are a project manager of a company and your project is currently in execution phase. The customer has requested you for additional work. This work will affect the budget, but not the schedule of the project. What should you do next?A. Add the additional requirements to the project plan.B. Ignore the request.C. Explain the change procedure and ask to submit a request
for change.D. Discuss with the project team about the change.
C is the correct answer.Explain the change procedure and ask to submit a request for change is the best choice.
Project Budget ComponentsKnown un-Knowns
un-Known un-Knowns
This is the level of granularity to track measurement
Project Budget Components
Reserves
Contingency vs Management reserves
Planned Value (PV)
From PMBOK 5th Edition
The approved budget for the work scheduled to be completed by a specified date.
• Scheduled work• Work for an activity (work breakdown component)• Defines the physical work that SHOULD have been
accomplished• Total of all PV can be referred to as:
• Total PV is also: budget at completion (BAC)
Earned Value (EV)
From PMBOK 5th Edition
The approved budget for the work actually completed by the specified date
• Measure of work performed• Based on PV (authorized budget)• Percent complete of a project• EV cannot be greater than PV• Monitored:
• Incrementally – for current status• Cumulatively – performance trends
Actual Cost (AC)
From PMBOK 5th Edition
• Realized cost incurred• Cost of work performed during a time period• Specific to the work that the EV measured• Corresponds to what was planned – PV• Has no upper limit – it is what it is
Earned Value
From PMBOK 5th Edition
Formulas to memorizeSchedule Variance (SV)
From PMBOK 5th Edition
Formulas to memorizeCost Variance (CV)
From PMBOK 5th Edition
Earned Value Measurement
From PMBOK 5th Edition
Exercise
Earned Value Measurement
From PMBOK 5th Edition
Status after 1 hour
Earned Value Measurement
From PMBOK 5th Edition
Use EVM to forecast
Earned Value MeasurementAccountant’s Pal Online
Budget ad Completion BAC 1200
Planned Value PV 240
Earned Value EV 230
Actual Cost AC 250
Schedule Variance(EV – PV)
SV 230 – 240 = -10
Cost Variance(EV – AC)
CV 230 – 250 = -20
Schedule Performance Index (EV/PV)
SPI 230/240 = .95
Cost Performance Index(EV/AC)
CPI 230/250 = .92
Estimate at CompletionBAC/CPIAC + BAC – EVAC + [(BAC-EV)/(CPI*SPI]
EAC 1200/.92 = 1304250 + 1200 – 230 = 1220250+[(1200-230)/(.92*.95) = 1360
Estimate to Complete(EAC – AC) or re-Estimate
ETC 1304 – 250 = 1054
To Complete Performance Index(BAC – EV) / (BAC – AC)
TCPI (1200-230)/(1200-250) = 1.02
Variance at Completion(BAC – EAC)
VAC 1200 – 1304 = -104
From PMBOK 5th Edition
Note: the numbers in the chart refer to the chapter in the PMBOK
Procurement Management
From PMBOK 5th Edition
Procurement Management
From PMBOK 5th Edition
Procurement Management
From PMBOK 5th Edition
• Agreements• Binding contracts• Terms and conditions• Purchase order• Understanding• Usually subjected to extensive review/approval• Many times involves Legal department
Plan Procurement Management
From PMBOK 5th Edition
Inputs
Fixed-price contracts• Firm Fixed Price (FFP)
• Most common• Variance – seller
• Fixed Price Incentive Fee (FPIF)• Price ceiling – incentives• Variance – seller• Incentive – seller
• Fixed Price with Economic Price Adjustment (FP-EPA)• Fixed price• Provision for change• Variance – seller and buyer
Cost reimbursable contracts• Cost Plus Fixed Fee (CPFF)
• Seller reimbursed for costs• Fee is fixed except for scope changes
• Cost Plus Incentive Fee (CPIF)• Seller reimbursed for costs• Buyer and seller share cost risk (+ /
-)• Cost Plus Award Fee (CPAF)
• Seller reimbursed for costs• Fee is subject to buyer’s evaluation
Time and Material (T&M)
Plan Procurement Management
From PMBOK 5th Edition
Tools & Techniques
Plan Procurement Management
From PMBOK 5th Edition
Outputs
Conduct Procurements
From PMBOK 5th Edition
Inputs
Conduct Procurements
From PMBOK 5th Edition
Tools & Techniques
Conduct Procurements
From PMBOK 5th Edition
Outputs
Control Procurements
From PMBOK 5th Edition
InputsTools & Techniques
Outputs
Risk
From PMBOK 5th Edition
How an organization views risk
Risk
From PMBOK 5th Edition
Risk Breakdown Structure (RBS)
Risk
From PMBOK 5th Edition
Risk Impact Scales
RiskProbability Impact Matrix
Risk
From PMBOK 5th Edition
Techniques
Risk
From PMBOK 5th Edition
Techniques
Risk SWOT Analysis
Risk
Risk Register
Risk
From PMBOK 5th Edition
Risk
From PMBOK 5th Edition
Qualitative Risk Analysis
Risk
From PMBOK 5th Edition*Sometimes data is not available
Risk
From PMBOK 5th Edition
Risk
From PMBOK 5th Edition
Strategies for Negative Risks
Risk
From PMBOK 5th Edition
Strategies for Negative Risks
Risk
From PMBOK 5th Edition
Strategies for Positive Risks
Tips and Tricks
From PMBOK 5th Edition
• PMP exam is NOT a test of PMBOK – you cannot rely on real world experience – rely on training aligned with PMBOK
• Make up of exam (probably changed for 5th Edition)• Initiating 11%• Planning 23%• Executing 27%• Monitoring/control 21%• Closing 9%• Ethics 9%
• 200 multiple choice – 175 count (need 106 to pass or 61%)• Know how to apply the information• About 150 “what would you do?” questions• 8-10 formula related questions• 10-12 earned value questions• Questions with 2 or more right answers – which is most
right• Questions with extraneous information• Questions with made up terms• Questions with more than one item in each answer - secret
Tips and Tricks
From PMBOK 5th Edition
Study tips• Don’t
• Read every book you can find• Study too long• Not listen to advice from those who have passed
• The Magic Three – visit a topic 3 times to learn it• Take practice exams (take at lease 1 full, 4 hour test)• Plan your study program
• Test yourself with 20 questions in each group• Read one of the exam prep books• Use flash cards or other tools• Form a study group• Take a review course• Take practice exams until you can get 85%
Tips and Tricks
From PMBOK 5th Edition
Recurring themes• Project managers can save the universe• The PM puts the best interests of the project first• Perspective of a large project (200 people from many
countries, takes at least a year, never been done before in the organization with a budget of $100M)
• PM has the power and perform all PMBOK activities• The PM is assigned during initiation• The PM understands the process of project
management• The PM always knows why their project was selected • The PM spends time planning, managing, assessing
and controlling scope, time, cost, quality, risk, resources and customer satisfaction
• Your organization has a PMO• Your organizations has OPA and EPA• A Work Breakdown Structure (WBS) is used on every
project)
Tips and Tricks
From PMBOK 5th Edition
Invest:• Prep class• Prep book• Join PMI
Thank You
From PMBOK 5th Edition
Any Questions?