BLOCK ‘A’ 9th floor roof slab shuttering in progress
DATE-30/04/2012
BLOCK ‘B’ Terrace slab shuttering IN PROGRESS .DATE-30/04/2012
BLOCK ‘C’14th floor column in progress.date-30/04/2012
BLOCK ‘D’11th floor roof slab 50% casted.date-30/04/2012
BLOCK ‘E’12th floor roof slab casted.date-30/04/2012
BLOCK ‘F’12th floor roof slab 50%ready to pour & 50%casted.date-30/04/2012
BLOCK ‘G’Terrace slab casted.date-30/04/2012
BLOCK ‘H’14th floor column in progress.date-30/04/2012
BLOCK ‘I’9th floor roof slab shuttering in progress.date-30/04/2012
BLOCK ‘J’8th floor roof slab casted.date-30/04/2012
BLOCK ‘M’10th floor roof slab shuttering in progress.date-30/04/2012
BLOCK ‘N’9th floor roof slab casted.date-30/04/2012
BLOCK ‘O’Raft completed.date-30/04/2012
BLOCK ‘D’ NON TOWERback side casted. Date-30/04/2012
BLOCK ‘C’ NON TOWERback side slab in progress.date-30/04/2012