Motivation• Memory built-in self-test (MBIST)
– Essential DFT technique in modern SOCs– MBIST design impacts chip resources and quality of test solution– Physical optimizations of MBIST logic: not well-studied
MEM MEM
MEM MEM
MEM
MEM
MEM
MEMMEM
MEM
MEM
MEM
MEM
MEM
MEM
MEM
MEM
MEM
BISTBIST
BISTBIST
BIST
TAP
Memory BIST Architecture
-4-
Challenges and Contributions• Challenge: Multiple optimization criteria
– Minimize test time– Minimize number of BIST controllers– Minimize wirelength between BIST logic and memories
• Our work: Three-stage heuristic– Memory partitioning : FM in a weighted hypergraph model– Test scheduling : Integer Linear Program (ILP) formulation– MBIST logic placement : min-weight maximum matching
-5-
Outline
• Motivation and Contributions• Related Works• ILP Formulation• Heuristic Flow• Experimental Results• Conclusions and Future Work
-6-
Related Works• Test scheduling
– Reduction of test time is a fundamental goal in DFT– Typical: scheduling as rectangle packing– Also typical: scheduling as ILP
• Design optimizations for memory BIST controllers– Most works focus on architectural and testing aspects– Chien et al. [2009] propose a memory BIST design optimization
• ILP for clustering of memories to controllers• Studies physical design aspects • Various simplifications: all of a cluster is tested in parallel, no
two clusters tested simultaneously, …
-7-
Outline
• Motivation and Contributions• Related Works• ILP Formulation• Heuristic Flow• Experimental Results• Conclusions and Future Work
-8-
ILP Formulation
• Objective: Minimize test end time• Subject to: Upper bound on test power
• Logical constraints capture parallel and serial testing scenarios
MEM3
pow
er
MEM8
MEM6
MEM5
MEM9
MEM7
MEM1MEM2 MEM4
time
Test power limit
Improved test time is possible
Red
uce
d t
est
tim
e
MBI
ST1
MBI
ST2
pow
er
time
MEM4
MEM2
MEM1
MEM3
MEM8
MEM6MEM5
MEM9MEM7
Test power limit
Test time with one solution
MBIST1
MBIST2
-9-
Outline
• Motivation and Contributions• Related Works• ILP Formulation• Heuristic Flow• Experimental Results• Conclusions and Future Work
-10-
Overall Flow
Input: Memories, Constraints
(1) Memory Partitioning with Hypergraph (MLPart [1], FM-style)
(2) Test Scheduling with ILP formulation(CPLEX [2], logical constraints)
(3) Placement of BIST Logic for each Partition ([3], Min-Weight Max-Cardinality Matching)
Output: Memory BIST Groups, Test Schedules, BIST Logic Placements
[1] MLPart. http://vlsicad.ucsd.edu/GSRC/bookshelf/Slots/Partitioning/MLPart[2] IBM ILOG CPLEX Optimizer. http://www.ilog.com/products/cplex[3] Hungarian algorithm source code. http://www.informatik.uni-freiburg.de/~stachnis/index.html
-11-
Memory Partitioning• Divide memories into k partitions using MLPart
– MLPart: Min-cut hypergraph partitioner based on multilevel FM – k = number of BIST controllers
• Hypergraph: vertices = memories; hyperedge weights reflect test time implications of grouping– Reduced test time if memories with same shape and depth in same group
Example Hypergraph
MEM MEM MEM
MEM
MEM MEM MEM
MEM
Hyperedges: The same shape, depth and test power, respectivelyEdges: Distances < D1, < avg(D1, D2) and < D2, respectively (where D1 < D2)
-12-
Test Scheduling• Solve ILP formulation
– Minimize test time, subject to power constraint– ILP solver: CPLEX Optimizer 12.5.1
• Additional partition (BIST controller) for better test time– Obtain alternative test scheduling solution with extra BIST controller
• {1 BIST controller, 2 BIST controllers} per each partition
Solution with one BIST controller Solution with two BIST controllers
MEMMEM
MEMMEM
MEM
MEM
MEM
MEM
MEM MEM
BIST1
MEM
Est. Test Time 1000
MEMMEM
MEMMEM
MEM
MEM
MEM
MEM
MEM MEM
BIST1
MEMBIST2
Est. Test Time 900
-13-
Memory BIST Logic Placement• To minimize wirelength between
each BIST and memories• Min-weight maximum-cardinality
matching in a bipartite graph– Apply Hungarian algorithm – Cost: Diameter from a grid to
all memories in a group
MEM
MEMMEM
MEMMEM
MEM
MEMMEM
MEM
Memories in the same BIST group
Possible grids for BIST logic placement
Forbidden grids (intersection with memories)
BIST placement solution
-14-
Outline
• Motivation and Contributions• Related Works• ILP Formulation• Heuristic Flow• Experimental Results• Conclusions and Future Work
-15-
Experimental Setup• Develop MBIST-solver to implement our heuristics
– C++ / g++ 4.8.0– User options include min/max # partitions, min/max # memories in a
partition, max diameter, power constraint, weight parameters, …– MLPart: Memory partitioner– CPLEX 12.5.1: ILP solver
• Testcases: six industrial testcases (from industry partners)
TC #M #P DMAX
TC1 143 13 3900
TC2 150 11 4500
TC3 124 8 2200
TC4 160 13 3400
TC5 137 7 3200
TC6 148 12 4100
TC = testcaseM = #memoriesP = #partitionsDMAX = maximum diameter w/o BIST [μm]
-16-
Our solutions1. Reduce test time by up to 11.57% (Testcase 3)2. Reduce number of BIST controllers by up to 41.6% (Testcase 6)3. Reduce maximum diameter by up to 31.7% (Testcase 6)
Experimental Results
Industrial solution (TC1)• Test time = 1067• # BISTs = 13• Maximum Diameter = 3900μm
Our solution (TC1)• Test time = 969• # BISTs = 12• Maximum Diameter = 2100μm
memories
BIST controller
Large Maximum Diameter Smaller Maximum Diameter
-17-
Outline
• Motivation and Contributions• Related Works• ILP Formulation• Heuristic Flow• Experimental Results• Conclusions and Future Work
-18-
Conclusions and Future Work• Three-step heuristic methodology
– Co-optimization of (1) Memory BIST grouping, (2) test scheduling, and (3) memory BIST logic placement
– Objective: minimize test time for a given #BIST controllers• Handle various serial / parallel testing options in ILP• Minimize diameter of BIST groups less-critical timing, less
need for LVT instances in BIST implementation, etc.
• Future work– Integrate these optimizations into ‘production’ PD flow– Improve hypergraph weighting, scalability of ILP– Improve congestion- and timing-awareness of BIST placement