does better scheduling drive execution success?

22
// Does Better Scheduling Drive Execution Success? Dr. Dan Patterson PMP// CEO Acumen May 9 2012

Upload: acumen

Post on 14-Jun-2015

740 views

Category:

Technology


2 download

DESCRIPTION

Delivered at PMI SCoP's 9th Annual Scheduling Conference, this presentation discusses the results from a recently conducted research project showing the correlation between the quality of a plan and overall project success, as well as a means of assessing schedule quality and forecasting accuracy using metric analysis.

TRANSCRIPT

Page 1: Does Better Scheduling Drive Execution Success?

//

// Does Better Scheduling Drive Execution Success? Dr. Dan Patterson PMP// CEO Acumen

May 9 2012

Page 2: Does Better Scheduling Drive Execution Success?

//

// Acumen

◦  Project Management Software

◦  Oracle Primavera partner

◦  Insight into challenges & use of analytics to overcome them

◦  Core Concepts: 1.  Project success requires a sound plan

2.  Forecast accuracy requires risk consideration

Proven Project Analytics

Product Offerings

Risk Workshops

Acumen Fuse®

Software Training

Realistic Scheduling

Critiqued

The Base

Risk-Adjusted

Optimized

Team-Aligned // S5

// S4

// S3

// S2

// S1

May 10, 2012 2

Page 3: Does Better Scheduling Drive Execution Success?

//

// Presentation Overview A Case Study

S1//S5 Schedule Maturity Model

Developing sound schedules

Case Study/software demo

Questions & Answers

Schedule Index™

Baseline Compliance™

Acumen Fuse analysis

May 10, 2012 3

Page 4: Does Better Scheduling Drive Execution Success?

//

// Schedule Maturity Framework Acumen S1//S5

 S1  •  Schedule  Basis  • Owner/contractor  schedule  

S2  • Cri/qued  Schedule  •  Ensure  structural  integrity  

S3  • Risk-­‐Adjusted  Schedule  • Account  for  risk/uncertainty  

S4  • Op/mized  Target  Scenarios  •  Schedule  accelera>on  

S5  •  Team  Validated  Scenario  • Buy-­‐in  on  op>miza>on  0  

1  

2  

3  

4  

5  

6  

0   1   2   3   4   5   6  

Chan

ce  of  S

ucess  

Maturity  Level  

Measure quality through the Fuse Schedule Index™

May 10, 2012 4

Page 5: Does Better Scheduling Drive Execution Success?

//

// Schedule Quality Measurement

◦  Legacy ◦  duration, constraints, excessive lags,

negative float ◦  Industry Standards

◦  DCMA 14 Point Assessment ◦  NDIA GASP/ GAO

◦  Acumen Metrics ◦  Logic Density™ ◦  Insufficient Detail™

May 10, 2012 5

Metric Analysis

Page 6: Does Better Scheduling Drive Execution Success?

//

// Acumen Schedule Metrics

Logic  Density™  • Measure  of  complexity/completeness  

Logic  Hotspot™  • Timely  start?  

Float  Ra>o™  • Degree  of  flexibility  per  day  of  work  

Redundancy  Index™  • Non-­‐needed  logic  

Advanced Project Insight

Finish  Compliance™  • Accurate  measure  of  performance  

Insufficient  Detail™  • Ac>vity  V  project  dura>on  

Milestone  Ra>o™  • Detail  V  repor>ng  

Broad  Risk  Range  • Check  for  erroneous  risk  input  

Page 7: Does Better Scheduling Drive Execution Success?

//

// Logic Density™

◦  Determine Logic Hotspots™ in schedule

◦  Indication of sufficient logic

◦  Excellent means of trending detail level

Planning Consistency

May 10, 2012

More  defini>on  needed  

7

Page 8: Does Better Scheduling Drive Execution Success?

//

// Advanced Logic Analysis

◦  Use of FS, FF, SS, FS links

◦  Lags & Leads

◦  Lags hide schedule detail

◦  Leads cause reverse dates

◦  Circular logic between projects

◦  Out-of-Sequence updates

◦  Open ends/missing logic

◦  Open start/finish (hidden open ends)

◦  Logic Density

◦  Logic Hotspot

◦  Redundancy Index

Sound Basis of Schedule

A

B

C

redundant

Page 9: Does Better Scheduling Drive Execution Success?

//

// Measuring Schedule Quality Fuse Schedule Index™

May 10, 2012 9

Page 10: Does Better Scheduling Drive Execution Success?

//

// Baseline Compliance Index™

Examines  how  many  ac>vi>es  fell  within  the  expected  

repor>ng  period  

Page 11: Does Better Scheduling Drive Execution Success?

//

// Baseline Compliance™

◦  More than date comparison ◦  Measures period-compliance ◦  Included in Fuse® library

Performance Analysis

May 10, 2012 11

0%  

50%  

100%  

Page 12: Does Better Scheduling Drive Execution Success?

//

// Acumen Fuse Platform

◦  Fuse: analytics platform

◦  Improves schedule quality

◦  Insight into performance

◦  Fuse 360: goal-based acceleration

◦  Schedule Acceleration

◦  Decision-support

Enterprise Project Analysis

May 10, 2012

Metric  Analyzer  

Logic  Analyzer  

Forensic  Analyzer  

Schedule  Cleanser  

Schedule  Accelerator  

Page 13: Does Better Scheduling Drive Execution Success?

//

// Metric Analysis Slice & Dice

May 10, 2012

Benefit:

" Pinpoint shortcomings

" Project characteristics

" Slice and dice

Schedule  

• Logic  • Float  • Dura>on  

Cost  

• Overrun  • Capacity  • Burn  rates  

Performance  

• Status  • Completed  • Delayed  

Characteris>cs  

• Level  of  detail  • Constrained  • Riding  Data  Date  

Earned  Value  

• CPI/SPI  • Trending  • Earned  schedule  

Risk  

• Exposure  • Hot  spots  • Hidden  paths  

Page 14: Does Better Scheduling Drive Execution Success?

//

// Metrics to fit: Criteria, Thresholds Fuse Metric Editor

Page 15: Does Better Scheduling Drive Execution Success?

//

// Fuse Schedule Cleanser™ Actionable Insight

Page 16: Does Better Scheduling Drive Execution Success?

//

// Project Forensics Insight into Schedule Cleanse

May 10, 2012

Page 17: Does Better Scheduling Drive Execution Success?

//

// Claims Analysis

◦  Advanced forensics

◦  Fuse gives meaning to the

impact of changes

◦  Pinpoints changes to critical/

driving path

◦  Every single project attribute

can be checked

◦  Calendar definition changes

Insight into project variances

May 10, 2012

Page 18: Does Better Scheduling Drive Execution Success?

//

// Acumen Fuse® Software Demonstration Case Study

Page 19: Does Better Scheduling Drive Execution Success?

//

// Case Study

•  Houston-based oil/gas owner

•  Objective:

•  More on-time completion for projects over $250MM

•  Encourage more mature contractor schedules

•  Overcome “brain drain” in scheduling

•  How achieved:

•  Mandated contractor Fuse Schedule Index of 75+

•  Gave contractor opportunity to self-assess

Owner/contractor Alignment

Page 20: Does Better Scheduling Drive Execution Success?

//

// Quality Planning Truly Drives Success

0%  

10%  

20%  

30%  

40%  

50%  

60%  

70%  

80%  

90%  

100%  

0%   10%   20%   30%   40%   50%   60%   70%   80%   90%   100%  

Pro

babilit

y of

On-T

ime C

om

ple

tion

Fuse Schedule Index™

May 10, 2012 20

Page 21: Does Better Scheduling Drive Execution Success?

//

// Q&A

Page 22: Does Better Scheduling Drive Execution Success?

//

//

More information: White papers: www.projectacumen.com Software Trial: www.projectacumen.com/trial Twitter: @projectacumen Email: [email protected]