Road Projects
About DMIA
Dhaya Maju Infrastructure (Asia) Sdn Berhad is one of the Leading
Infrastructure Company in Malaysia since 1996.
Dhaya Maju has successfully completed many Railway, Road &
Building projects in Malaysia.
Dhaya Maju also executing many road projects in India since
2002- 2010 through its Indian Subsidiaries i.e.,
• TDM Infrastructure Private Limited
• Jabalpur Corridor (India) Private Limited
Dhaya Maju has undertaken prestigious project like;
• 4 Laning Sira – Chitradurga
• 6 Laning of Chennai IT Corridor
• 4 Laning of Jaipur Mahua
• 6 Laning of Chilakaluripet – Vijayawada
• 2 Laning of Sagar Damoh - Jabalpur
SIRA - CHITRADURGA
CHENNAI IT CORRIDOR
VIJAYAWADA- CHILAKALURIPET
SAGAR DAMOH – JABALPUR
JAIPUR - MAHUA
DMIA in India
Sira Chitradurga – Project Particulars
Project Name Western Transport Corridor - Tumkur Haveri NH4 Package 2,
Length 67.00 Km
Authority National Highway Authority of India
Main
Contractor UEM – ESSAR Joint Venture
Contractor TDM Infrastructure Private Limited
Location Tumkur, Karanataka State, India.
Project Cost Rs. 143.78 Crore
Date of
commencement 24.05.2002
Date of
Completion 01.05.2006
Sira Chitradurga– Scope of Works
4 Laning of Sira to Chitradurga Section of 67.00 Km along with Service Road
including Construction of Culverts , Bridges and Protection works ;
• Earth Filling of 7,68,900 Cum.
• Granular Sub- Base Works of 4,35,933 Cum
• Wet Mix Macadam of 3,70,466 Cum
• Dense Graded Bituminous Macadam of 1,76,483 Cum
• Bituminous Macadam of 15,379 Cum
• Bituminous Concrete of 20,034 Cum
• Structural Concrete of 53,821 Cum
• Major Bridge having Span Length of 26.50 Km
Sira Chitradurga – During execution
Sira Chitradurga – After completion
Chennai IT Corridor – Project Particulars
Project Name Improvement and Maintenance of IT Corridor in Chennai
Length 20.00 Km
Authority
IT Expressway Limited,
(A Special Purpose Vehicle of Tamil Nadu Road Development
of Corporation)
Location Chennai, Tamil Nadu State, India.
Main Contractor Ahmad Zaki Resources Berhad, Malaysia
Contractor TDM Infrastructure Private Limited
Project Cost Rs. 117.53 Crore
Date of
commencement 14.04.2005
Date of
Completion 04.10.2008
Chennai IT Corridor- Scope of Works
Construction of 6- Lane Expressway of 20.00 Km in the heart of the City with
high traffic environment including the following;
• Construction of Main Carriageway with a center median width of 3.00 Mtr.
• Construction of Services Road
• Construction of Culverts & Minor Bridges
• Construction of Foot Path
• Construction of Service Trenches for Water Lines & Power Lines
• Construction of 12 Lane Toll Plaza
• Providing Street Lights in the Median
Chennai IT Corridor- During execution
Chennai IT Corridor – After completion
Chennai IT Corridor- Toll Plaza
Jaipur – Mahua - Project Particulars
Name of the Project Four laning of Mahua – Jaipur Section (KM 202+000 –
KM 229+000) of NH 11 in the state of Rajasthan
Length 22.00 Km
Authority National Highway Authority of India.
Concessionaire Jaipur Mahua Tollway Private Limited
(A Sabsidiary of IJM Group)
Main Contractor IJM (India) Infrastructure Limited
Contractor TDM Infrastructure Private Limited
Location Jaipur, Rajasthan, India.
Project Cost Rs. 59.37 Crore
Date of commencement 01.09.2005
Date of Completion 31.10.2009
Jaipur Mahua - Scope of Works
4 Laning of Jaipur Mahua road section from Km 202+000 to Km 229+000 of
NH-11 having length of 22 Km including following works ;
• Earth works & Sub base works
• Granular Sub- Base Works
• Wet Mix Macadam works
• Dense Graded Bituminous Macadam works
• Bituminous Concrete of works
Jaipur Mahua - After Completion
Vijayawada Chilakaluripet - Particulars
Project Name
Six laning Vijayawada Chilakaluripet Road Section of NH-
5 from Km 355.00 to Km 434.15 in the state of Andhra
Pradesh, India
Length 82.50 Km
Authority National Highway Authority of India.
Concessionaire Vijayawada Tollway Private Limited
Main Contractor IJM (India) Infrastructure Limited
Contractor TDM Infrastructure Private Limited
Location Andhra Pradesh, India.
Project Cost Rs. 129.12 Crore
Date of
commencement 26.05.2009
Date of Completion 01.06.2010
Vijayawada Chilakaluripet - Scope of Works
Construction of 6 Lane Road Section of Vijayawada Chilakaluripet NH-5 from Km
355+000 to Km 434+150 including the following;
• Construction of 6-Lane Main Carriageway.
• Construction of Services Road
• Construction of Structure like Culverts, Bridges, Underpasses & Flyover etc.,
• Providing and Fixing of Sign Boards
• Road Marking works
• Construction of Toll Plaza.
• Improvement of Junctions
• Construction of Truck Laybys
• Construction of Bus bays
• Providing Street Lights in the Median
Vijayawada Chilakaluripet
Sagar Damoh Jabalpur – Project Particulars
Project Name Designing, Strengthening, widening & up-gradation of Sagar
Damoh Jabalpur Road on BOT basis
Length 176 Km
Authority Madhya Pradesh Road Development Corporation Limited
Concessionaire Jabalpur Corridor (India) Private Limited
Location Jabalpur, Madhya Pradesh State, India.
Project Cost Rs. 89.78 Crore
Concession Period 15 Years
Date of
commencement 11.04.2003
Date of
Completion 12.07.2007
Construction of 2 Lane Road Section of Sagar Damoh to Jabalpur of 176.00 Km
length including the following;
• Construction of 2 lane Carriageway.
• Construction of Structure like Culverts, Bridges
• Providing and Fixing of Sign Boards
• Road Marking works
• Construction of Toll Plaza.
• Improvement of Junctions
Sagar Damoh Jabalpur – Scope of Works
Sagar Damoh Jabalpur – Scope of Works
Assets
Assets
THANK YOU