diagnostic analysis of distressed hydraulic structures: case studies of gujarat, india

25
DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA VIVEK P. KAPADIA GOVERNMENT OF GUJARAT

Upload: iei-gsc

Post on 21-Jan-2018

71 views

Category:

Engineering


0 download

TRANSCRIPT

Page 1: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

VIVEK P. KAPADIA

GOVERNMENT OF GUJARAT

Page 2: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

2Backtracking from Symptoms to Causation

Forensic Analysis

Cause

Page 3: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

CASE STUDY – 1 NARMADA MAIN CANAL

Page 4: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

DESIGN FEATURES OF MAIN CANAL

• LARGEST IN THE WORLD HAVING CARRYING CAPACITY OF 1133 CUBIC METER PER SECOND AT THE OFF-TAKE POINT.

• AT CH. 195 KM BANK HEIGHT ABOVE THE GROUND LEVEL IS 12.5 M

• CANAL BED IS 70 M WIDE AND THE FULL SUPPLY DEPTH (FSD) IS 7.0 M

• DESIGNED DISCHARGE IS 825 M3/S

• CANAL SIDE SLOPES ARE 2 (H) : 1 (V)

4

Page 5: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

DIAGNOSIS OF THE PROBLEM

BOILING

Page 6: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

DIAGNOSIS OF THE PROBLEM

• BOILING AT SOME DISTANCE FROM THE TOE OF THE CANAL EMBANKMENT

• SUBSURFACE FLOW DUE TO FAVORABLE HYDRAULIC GRADIENT - COULD NOT BE ATTRIBUTED TO THE CANAL FLOW AS THE CANAL WAS LINED AND THE BED BANKING WAS MORE THAN 3.5 METER

• SHALLOW LIVE AQUIFER - CUT DUE TO CONSTRUCTION OF THE CANAL SIPHON IN THE DOWNSTREAM

Page 7: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

DIAGNOSIS OF THE PROBLEM

BOILING

SHALLOW AQUIFER

Page 8: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

DIAGNOSIS OF THE PROBLEM

• SEEPAGE ABOVE TOE - EITHER PHREATIC LINE DEVELOPED WITHIN THE CANAL EMBANKMENT OR CAPILLARY ACTION DEVELOPED NEAR THE TOE FROM WITHIN THE GROUND ITSELF OR BOTH TOGETHER

• LOAM TYPE OF SOIL - GENERALLY ERODIBLE AND PHREATIC LINE OR CAPILLARY ACTION COULD BE EASILY DEVELOPED DUE TO HIGH PERMEABILITY WHEN THE COMPACTION IS NOT SUFFICIENT

• DEEP RAIN-CUTS ON THE OUTER SIDE OF THE CANAL EMBANKMENTS WERE ALSO OBSERVED WHICH ALSO SUGGESTED ERODIBLE SOIL

Page 9: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

UNFOLDMENT OF SOLUTION OF THE PROBLEM• EXIT TO THE SUBSURFACE FLOW BY PROVIDING A LATERAL DRAIN -

ESTABLISH A STEADY STATE OF THE SOIL BENEATH THE CANAL EMBANKMENT SO THAT CRUMBLING OF THE FOUNDATION RESULTING IN TO FAILURE OF THE EMBANKMENT COULD BE AVOIDED

• ALSO TO STOP THE CAPILLARY ACTION OF WATER IN TO THE CANAL EMBANKMENT NEAR THE TOE IF ANY

• LATERAL DRAIN - A COLLECTING DRAIN WAS EXTENDED TO A FAR SITUATED POND FOR THE DISPOSAL

• AIMED AT RELEASING THE WATER ACCUMULATED IN LARGE QUANTITY WITHIN THE SOIL BENEATH THE CANAL EMBANKMENT

Page 10: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

UNFOLDMENT OF SOLUTION OF THE PROBLEM

BOILING

SHALLOW AQUIFER

Page 11: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

UNFOLDMENT OF SOLUTION OF THE PROBLEM• OBSERVATION FOR SOME DAYS - BOILING PHENOMENON ALMOST DISAPPEARED -

SEEPAGE REDUCED BUT NOT COMPLETELY STOPPED WHICH SUGGESTED THAT THE PHREATIC LINE HAD ESTABLISHED WITHIN THE EMBANKMENT

• ADDITIONAL BERM OF 5 METER WIDTH AND 5 METER HEIGHT

• JUTE TEXTILE BAGS WERE SPECIALLY DESIGNED IN THE FORM OF LONG ROLLS - FILLED UP WITH CEMENT SOIL IN 1:9 RATIO AND NAILED ON THE OUTER SLOPE OF THE CANAL EMBANKMENT

• AVOIDING ROLLING DOWN OF THE JUTE ROLLS, AN ANTI-EROSION SURFACE ON THE OUTER SLOPE OF THE EMBANKMENT AND TO ADD EXTRA BURDEN TO PROVIDE MORE STABILITY

Page 12: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

UNFOLDMENT OF SOLUTION OF THE PROBLEM

Page 13: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

CASE STUDY – 2 GORATHIYA DAM

Page 14: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

INTRODUCTION

• SABARKANTHA DISTRICT I.E. IN NORTH GUJARAT IN INDIA - COMPLETED BEFORE 10 YEARS - RIVER MESHWO

• GROSS STORAGE CAPACITY - 146 MILLION CUBIC FEET

• CATCHMENT AREA IS 371 SQUARE KILOMETERS - DESIGNED FLOOD WITH 1 IN 50 YEAR FREQUENCY IS 3774 CUBIC METER PER SECOND

• LENGTH OF THE SPILLWAY SECTION IS 101.80 METER - CONCRETE GRAVITY DAM WITH PROVIDED 9 VERTICAL GATES - HYDRAULIC JUMP TYPE STILLING BASIN - UPSTREAM AND DOWNSTREAM KEYS WERE 3.5 METER DEEP

Page 15: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

INTRODUCTION

• SIGNS OF DISTRESS IN ONLY 2 YEARS

• DOWNSTREAM GLACIS SLOPE 1:3 - TOE GOT DISINTEGRATED AND THE REINFORCEMENTS WERE PULLED OUT

• DOWNSTREAM APRON GOT DAMAGED BUT NOT IN THE ENTIRE LENGTH OF THE DAM, ONLY IN THE RIGHT HALF OF THE LENGTH I.E. RIVER’S HALF WIDTH

Page 16: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

INTRODUCTION

PULLED OUT REINFORCEMENT

Page 17: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

INTRODUCTION

PULLED OUT REINFORCEMENT AT TOE AND DAMAGED APRON

Page 18: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

DIAGNOSTIC ANALYSIS

• GLACIS WITH 1:3 SLOPE WAS INSUFFICIENT TO AVOID CAVITY FORMATION - THERE SHOULD HAVE BEEN A MUCH FLATTER SLOPE OR AN OGEE

• SOME RECORD - ORIGINALLY A BASALT MINE AS THE RIVER WAS HAVING GOOD QUALITY BASALT IN ITS BED - FOR PREPARATION OF THE SITE, THE DESIGN INCLUDED LEAN CONCRETE FILLING WITH LARGE COARSE AGGREGATE I.E. PLUM CONCRETE IN THE PIT

• SOME OTHER RECORDS WITH GEOLOGICAL MAPPING SUGGESTED THAT THE MINE WAS ONLY IN THE RIGHT HALF WIDTH OF THE RIVER AND THE DEPTH WAS ABOUT 9 METER

Page 19: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

DIAGNOSTIC ANALYSIS• LARGE COARSE AGGREGATES WERE IN PLACE - CEMENT AND SAND WERE IN LOOSE

FORM - WATER BENEATH THE APRON IN THE VOIDS - DAM WAS FULL UP TO CREST LEVEL - IT WAS THE WATER FROM THE RESERVOIR

• CONDITION WAS EXTREMELY DANGEROUS - SUBSURFACE FLOW COULD RESULT IN TO UNDERMINING THE FOUNDATION AND COLLAPSE OF THE CONCRETE DAM ITSELF.

• WHEN WATER WAS RELEASED, IMPACT OF THE WATER FALL WAS TAKEN UP BY THE APRON WHICH REQUIRED A SOLID FOUNDATION WHICH ACTUALLY WAS NOT THERE - CONCRETE APRON USED TO SETTLE - SAGGING RESULTING IN TO DAMAGE AT THE BOTTOM AND TOP – BOTTOM DAMAGE WAS NOT VISIBLE BUT THE TOP WAS

Page 20: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

RESTORATION• PLUM CONCRETE REMOVED UP TO 1.5 METER DEPTH – RICH CEMENT SAND MIX 1:4

WITH POLYMER POURED TO PLUG VOIDS IN PLUM CONCRETE

• LAYER OF 1.5 METETR THICKNESS OF RICH CONCRETE

• ADDITIONAL PERIPHERAL KEY OF 5 METER – FOUNDATION OF ABUTMENT STRENGTHENED

• CASTING OF APRON – REINFORCEMENT MESH AT TOP WELDED WITH TOE REINFORCEMENT – SURFACE HARDENER TO PROVIDE IMPACT RESISTANT SURFACE – FILLET AT TOE

• DOWNSTREAM RIVER CHANNEL REGRADED

Page 21: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

RESTORATION

Page 22: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

RESTORATION

Page 23: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

CONCLUSION

• PROBLEMS IN CIVIL ENGINEERING ARE VERY COMPLEX AND UNDERSTANDING THE REAL CAUSE OF THE PROBLEM IS THE MOST IMPORTANT ASPECT

• A SMALL ASPECT IGNORED AT THE CONSTRUCTION STAGE MAY LEAD TO DIFFICULT PROBLEMS

• EXPERIENCE AND INSIGHT NEEDED AS MOSTLY THE FINDINGS CAN BE REACHED BY WAY OF USING JUDGMENTAL AND INTUITIVE DECISIONS

Page 24: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

CONCLUSION

• SOMETIME THE DIAGNOSIS IS REQUIRED TO BE DONE STAGE-WISE ALONG WITH STEP BY STEP IMPLEMENTATION OF SOLUTION

• SEVERAL ACTIVITIES TO BE EXECUTED WITH PROPER SEQUENCE AND PROPER MATERIALS

Page 25: DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA

THANKS