development and verification of an internal equalization ...697884/fulltext01.pdf · development...

76
Development and verification of an internal equalization charge system for lead-acid batteries in hybrid power systems JOHN LJUNGBERG ANDREAS WESTERGREN Master of Science Thesis Stockholm, Sweden 2013

Upload: others

Post on 18-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

Development and verification of an internal

equalization charge system for lead-acid batteries in hybrid power systems

JOHN LJUNGBERG ANDREAS WESTERGREN

Master of Science Thesis

Stockholm, Sweden 2013

Page 2: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries
Page 3: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

Development and verification of an internal equalization charge system for lead-acid

batteries in hybrid power systems

John Ljungberg Andreas Westergren

Master of Science Thesis MMK 2013:35 MDA 457

KTH Industrial Engineering and Management

Machine Design

SE-100 44 STOCKHOLM

Page 4: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries
Page 5: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

Examensarbete MMK 2013:35 MDA 457

Utveckling och verifiering av ett internt utjämningsladdningssystem för blybatterier i

hybrida kraftsystem

John Ljungberg

Andreas Westergren

Godkänt

2013-Juni-11

Examinator

Mats Hanson

Handledare

Mikael Hellgren

Uppdragsgivare

Northstar Sitetel Sweden AB

Kontaktperson

Ulf Krohn

Sammanfattning

Detta examensarbete är utfört hos Northstar Sitetel Sweden AB. Examensarbetet innehåller en produktutveckling av ny teknologi med intern utjämningsladdning för batterier i hybrida kraftsystem till radiobasstationer. De befintliga system som används idag, använder en dieselgenerator för att ladda batterier som sedan förser radiobasstationen med kraft. Dessa system har ofta dålig bränsleeffektivitet på grund av långa utjämningsladdningar med låg last till dieselgeneratorn. Ibland har de även dålig mätnoggrannhet vilket gör att batteri kapacitet och dieselgeneratorer ofta överdimensioneras.

Studier har gjorts av olika typer av hybridsystem och även batterier, fokus har varit på en djup analys av bly batterier och hur dessa ska laddas optimalt med speciella typer av utjämningsladdningar.

En simulering av tänkt system har gjorts baserat på studierna och ett verkligt system har designats och tillverkats bestående av hårdvara med mikrokontroller, elektronik samt mjukvara med laddnings- och kontrollalgoritmer. Testning med utjämningsladdning av parallellkopplade batterier har utförts. Analys av data från tester har gjorts och jämförts med de system som finns på marknaden, speciellt med hänsyn till ekonomi och driftsfall inom speciella laddningsgrader av batterierna.

Resultaten visar att denna nya typ av intern utjämningsladdning fungerar väl och kan spara upp till 13,5 % i diesel förbrukning samt 260 timmars körningstid av dieselgeneratorn per år. Även mätnoggrannheten har förbättrats markant vilket gör att batteriernas kapacitet och dieselgeneratorns storlek kan minskas utan försämrad tillförlitlighet.

Page 6: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries
Page 7: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

Master of Science Thesis MMK 2013:35 MDA 457

Development and verification of an internal equalization charge system for lead-acid

batteries in hybrid power systems

John Ljungberg

Andreas Westergren

Approved

2013-June-11

Examiner

Mats Hanson

Supervisor

Mikael Hellgren

Commissioner

Northstar Sitetel Sweden AB

Contact person

Ulf Krohn

Abstract

This thesis is conducted together with Northstar Sitetel Sweden AB. The thesis contains a product of new technology with internal equalization charge for batteries in hybrid power systems for radio base stations. The existing systems in use today, uses a diesel generator to charge the batteries which then supplies the radio base station with power. These systems often have poor fuel efficiency due to long equalization charges with low load to the diesel generator. They sometimes have poor accuracy, which means that battery capacity and diesel generators are often oversized.

Studies have been made in different types of hybrid systems and also batteries. A deeper analysis of lead batteries and how these should be optimized with specific types of equalization charges have been made.

A simulation of the system based on studies on a real system is designed and manufactured consisting of hardware with microcontroller, electronics and software with charging and control algorithms. Tests of equalization charge of batteries connected in parallel have been performed. Analysis of data from the tests have been done and compared with the systems available on the market, especially with regard to economy and operating conditions in specific charge levels of the batteries.

The results show that the new type of internal equalization charging works well and can save up to 13.5 % in fuel consumption as well as 260 h less runtime of the diesel generator per year. The measurement accuracy has been significantly improved, which means that the capacity of batteries and diesel generator size can be reduced without loss in reliability.

Page 8: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries
Page 9: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

Table of contents

1 INTRODUCTION ............................................................................................................................................ 1

1.1 BACKGROUND ..................................................................................................................................................... 1 1.2 PURPOSE............................................................................................................................................................ 1 1.3 SCOPE AND OBJECTIVES ........................................................................................................................................ 2 1.4 METHOD ............................................................................................................................................................ 2 1.5 CHAPTER STRUCTURE ............................................................................................................................................ 2

2 LIST OF ABBREVIATIONS USED IN THIS THESIS ............................................................................................. 5 3 FRAME OF REFERENCE ................................................................................................................................. 7

3.1 HYBRID POWER SYSTEMS ....................................................................................................................................... 7

3.1.1 Energy sources that provide power to the load and the batteries ........................................................ 7 3.1.2 Different combinations of hybrid power systems ................................................................................ 10 3.1.3 Most common batteries types for hybrid power system ..................................................................... 12 3.1.4 Battery charge controllers ................................................................................................................... 16

3.2 VALVE REGULATED LEAD-ACID BATTERY MODEL ...................................................................................................... 18

3.2.1 Charge and discharge reactions .......................................................................................................... 18 3.2.2 Overcharging process .......................................................................................................................... 21 3.2.3 Aging factors ....................................................................................................................................... 22 3.2.4 Different methods for equalization charge ......................................................................................... 23

4 DESCRIPTION OF THE TASK ......................................................................................................................... 26

4.1 INTERNAL EQUALIZATION CHARGE SYSTEM FOR THE PROTOTYPE .................................................................................. 26

5 MODELING AND SIMULATION OF THE SYSTEM WITH INTERNAL EQUALIZATION CHARGE .......................... 27

5.1 CYCLING AT PARTIAL-STATE-OF-CHARGE ................................................................................................................. 27 5.2 EVALUATING POWER REQUIREMENTS FOR A REMOTE AREA POWER SUPPLY .................................................................. 28 5.3 MODELING AND SIMULATION OF THE SYSTEM IN SIMULINK ........................................................................................ 28

6 DEVELOPMENT OF A PROTOTYPE FOR THE CHARGE CONTROLLER .............................................................. 29

6.1 HARDWARE ...................................................................................................................................................... 30

6.1.1 Charging equipment for the system .................................................................................................... 32 6.1.2 The microcontroller used for the charge controller ............................................................................. 33 6.1.3 Simulation of the hardware in MultiSim ............................................................................................. 34 6.1.4 Design and development of the Printed Circuit Board ........................................................................ 35

6.2 BUDGET AND COST FOR THE COMPONENTS USED FOR THE PROTOTYPE .......................................................................... 36 6.3 SOFTWARE ....................................................................................................................................................... 37

6.3.1 Handling of the communication with external sources ....................................................................... 37 6.3.2 Logging of the important data ............................................................................................................ 39 6.3.3 Handling of sensing data and control of the system ........................................................................... 40

7 IMPLEMENTATION OF THE CHARGE CONTROLLER IN A REAL SYSTEM ......................................................... 42 8 TEST AND VERIFICATION ............................................................................................................................. 44

8.1 PREVIOUS WORK DONE BY SITETEL ........................................................................................................................ 44 8.2 TEST AND VERIFICATION OF THE PROTOTYPE ............................................................................................................ 45

9 RESULT ........................................................................................................................................................ 46

9.1 ANALYSIS ......................................................................................................................................................... 50

10 CONCLUSION ............................................................................................................................................... 54 11 DISCUSSION AND FUTURE DEVELOPMENT .................................................................................................. 55 12 REFERENCE .................................................................................................................................................. 57 13 APPENDIX ................................................................................................................................................... 59

Page 10: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries
Page 11: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

1

1 Introduction

1.1 Background

In non-electrified parts of the world with increasing telecommunication demand, electricity is generated

with diesel generators and/or solar cells. A common way is the use of diesel generators along with

battery storage, so-called hybrid systems. Diesel generators produce power that is many times larger

than what telecom station (usually a radio base station) needs. A diesel generator runs intermittent

charging batteries and supplies the radio base station. When turned off, the station is operating on

battery until it is appropriate to charge the batteries again. This is repeated cyclically. The advantages

are that diesel has a higher efficiency at high power, and that the operating time is sharply reduced,

thereby extending the intervals between refueling and servicing of diesel generator. A further plus is

that the time when the diesel emits noise is reduced and also more environmentally friendly due to less

exhausts.

To optimize the hybrid operation, battery charging time should be as low as possible. This is done most

efficiently by limiting the charge state to not fully charge. During charge the charging current is

substantially proportional to the uncharged ampere-hours, which mean that you can charge at a higher

current through the entire charge if you settle for a not fully charged state. This type of operation is

called partial state of charge (PSoC). A disadvantage of PSoC operation is that the batteries available

energy content is reduced, leading to the need to use a larger battery, another disadvantage is that the

batteries have to be subjected to a more thorough charging with low current for a long time at certain

intervals a so called equalization charge. It may require 12-24 hours of charge and diesel generator

operation in these cases.

Northstar SiteTel is a global company producing batteries and site solutions for radio base stations.

Apart from Northstar SiteTel there are other companies in the business e.g. Eltek, Emersys, PowerOne,

Huawei and Emerson competing for market shares. This thesis work is done together with Northstar

SiteTel to evaluate a new solution to save diesel generator runtime.

1.2 Purpose

With a tough telecom market, everyone wants to sell their system. This work was done together with

SiteTel to build a new hybrid system, which should be a leader on the market with the best fuel saving

technology, cheap and environmentally friendly. Main aspects are listed in the following.

Long equalization charges do not use the diesel full power, which decreases the efficiency

drastically.

Hybrid systems at remote areas require regularly refilling of diesel, which is expensive.

Existing hybrid system lack measurement accuracy, as an effect of this the batteries used are

sometimes over dimensioned.

In order for this to work, a new technology for equalizing batteries needs to be evaluated. A Hybrid

system with internal equalization charge for batteries connected in parallel is built, tested and

compared to other already known hybrid systems, mainly in terms of cost, fuel consumption and

climate. By moving already existing energy in the batteries to another by using a boost converter, the

system can now equalize each battery at a time with low losses and almost no extra uptime for the

diesel generator.

Page 12: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

2

The system is built upon an already existing cooling cabinet, which are used when charging batteries, a

commercial charger with rectifiers are used and controlled to cycle the batteries.

This thesis will present different hybrid solutions and charge control strategies, which are used for cyclic

operation. It presents comparisons between different types of batteries including design, operational

performance and maintenance.

Details are provided for Valve Regulated Lead Acid (VRLA) batteries, which are used in this thesis, and a

deeper section about different kinds of equalization charges, especially this new technology with

internal equalization charge.

1.3 Scope and Objectives

The important questions which are addressed in this thesis.

Which are the basic types of batteries used in a hybrid system?

What are the different types of hybrid solutions already on the market?

What is an equalization charge and what happens?

What are the different kinds of equalization systems available on the market?

How can you measure health of VRLA batteries?

How much savings can you expect from this new technology?

1.4 Method

To be able to understand how to build the system and when to charge etc. a pre study was made prior

to the prototype implementation. The frame of reference work was divided between the authors. The

first part about hybrid power systems, different batteries and charge controllers was made by John

Ljungberg. Next part about lead acid batteries and equalization charge was made by Andreas

Westergren.

A simulation was made in parallel with the pre study which continued until the prototype phase. The

work continued using the development process V-model, this process was well suited for this thesis

work. The prototype was designed according to requirements of the system, and the software design

was built upon this system. Changes in requirements, system design and software design were made

after verification. The prototype was tested and the results were compared to earlier data.

1.5 Chapter structure

The frame of reference will go deeper in describing some of the theory, which is needed to understand

how hybrid systems are built up. The section hybrid power system will describe some different

combinations in energy sources used in hybrid applications; different batteries and charge controllers

for these are also mentioned. Next section about battery model will give a deeper understanding in

Valve Regulated Lead-Acid (VRLA) batteries used in this thesis. It will also show different ways of

equalizing batteries, especially this new internal equalization method, and why you should equalize.

Task description describes the task deeper, why this thesis was made, and also some more information

about the internal equalization charge. The project started with a simulation, this section will describe

the whole simulation phase with different data and assumptions.

As the project prolonged, a prototype was built consisting of both hardware and software. The

prototype was tested and verified which is shown in section Verification. All necessary data and analysis

can be seen in the Result section.

Page 13: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

3

In the end a conclusion will summarize the work done, and the discussion/Future recommendations

finalizes this thesis with some thoughts about future development. Where references have been

considered necessary they are marked with [ref], where ref is the number referring to correct reference.

Page 14: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

4

Page 15: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

5

2 List of abbreviations used in this thesis

Table 1, List of abbreviations used in this report

Abbreviation Description

A Ampere

AC Alternating Current

ADC Analog to Digital Converter

AGM Absorbed Glass Mat

Ah Ampere Hours

ARV Array Reconnect Voltage

BMS Battery Management System

CAN Controller Area Network

CAPEX Capital Expenditures

DC Direct Current

DOD Depth of Discharge

EMC Electromagnetic Compability

EMI Electromagnetic Interference

EOD End of Discharge

GPIO General Purpose Input Output

Hz Hertz

LP Low Pass

LRV Load Reconnect Voltage

LVD Low Voltage Load Disconnect

LVDH Low Voltage Load Disconnect Hysteresis

OpAmp Operational Amplifier

OPEX Operating Expenditures

PSoC Partial State of Charge

PV Photovoltaic

RAPS Remote Area Power Supply

RBS Radio Base Station

RTOS Real Time Operating System

SD Secure Digital

SLI Start Light Ignition

SOC State of Charge

SPI Serial Parallel Interface

USART Universal Asynchronous Receiver/Transmitter

V Voltage

VDC Volts of Direct Current

VR Voltage Regulation

VRH Voltage Regulation Hysteresis

VRLA Valve Regulated Lead Acid

W Watt

Page 16: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

6

Page 17: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

7

3 Frame of reference

3.1 Hybrid power systems

A system consisting of batteries where the batteries are recharged, by for instance a diesel generator, is

called Hybrid Power System, but these systems can be designed in many different ways.

Hybrid power systems can consist of various combinations of solar panels, wind turbines, generators

powered by different fossil fuels and batteries. [19]

The most common combinations are:

Diesel generator with batteries

Wind turbine or solar panels with diesel generator and batteries

A combination consisting of all sources

These types of hybrid power systems are used as remote area power supply (RAPS) systems, which is an

electricity system for locations where electricity distribution systems are unavailable. Typical RAPS

systems are used in telecom for their off grid radio base stations (RBS). With the increased use and

dependence of cell phones and wireless communication, these systems have become much more

important.

Figure 1, Hybrid power system design [1]

3.1.1 Energy sources that provide power to the load and the batteries

Wind turbine

In a hybrid power system with wind turbines, small wind turbines are more common. The wind turbine

generates electric energy from low wind speed to a specified maximum speed. For small wind turbines

the current is often direct current (DC) and larger turbines have alternating current (AC). [1][16]

Generation source

- Solar panel

- Wind turbine

- Diesel generator

Power conversion and control

- Rectifiers

- Inverters

- Battery charger

- Control system

Energy-storage facility

- Deep-cycle batteries

Load

Page 18: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

8

Figure 2, Power output at different wind speeds [15]

As seen in Figure 2 the wind turbine has a cut-in speed where the turbine starts to generate electric

energy. When the wind speed increases the output power raises rapidly to the rated output speed

where the electrical generator reaches the limit to generate more power, also called rated output

power. Too high wind speed can damage the turbine structure and therefore it has a cut-out speed

where a braking system locks the wind turbine and power generation stops. [15]

Solar panel

According to Jacobi’s Law the "Maximum power is transferred when the internal resistance of the

source equals the resistance of the load, when the external resistance can be varied, and the internal

resistance is constant." [21]

Figure 3, I-V curve of a typical PV array [17]

This requires an ideal load, but the batteries in a hybrid system are far from ideal. In general the

operating voltage for a photovoltaic (PV) array that will charge a 12 V battery is 17 V. Usually lead acid

batteries are charged up to 14 V and when the discharging starts the voltage will drop to 12 V [17].

Because the battery also is a power source, the operating voltage for the PV array will be pulled down to

12 V because the opposing voltage from the battery due to the difference in resistance [20] (see Figure

4).

Page 19: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

9

Figure 4, I-V curve for a typical PV array while charging a 12 V battery without an ideal load [17]

As seen in Figure 4 the delivered power from the array will only be 50 W instead of the specified 75 W,

because the un-optimized power output is 50 W at 12 V. To prevent this problem a voltage regulator

that act as an ideal load is placed between the PV array and the battery to get the specified 75 W and a

DC/DC converter adjust the output from the PV array to the battery voltage. [1][4][17]

Other factors that affect the output power from the array are the solar irradiation and the ambient

temperature.

Figure 5, power change with a decrease in solar irradiation on a typical PV array [17]

Figure 6, power change with an increase in ambient temperature around a typical PV array [17]

If the solar irradiation is decreasing, so will the short circuit current, but the open circuit voltage will only

decrease slightly (see Figure 5). When the ambient temperature is rising there will only be a small

increase of the short circuit voltage, but a relatively larger decrease of the open circuit voltage will occur

(see Figure 6), compared to the decrease in solar irradiance. [17]

Diesel generator

A diesel generator is an internal combustion engine with an electrical generator for electrical energy

generation. A hybrid power system usually has a small diesel generator because it only charges the

batteries or is used for backup.

For small diesel generators it is necessary to run the load no less than 60-70 % of the maximum load to

obtain best possible fuel efficiency. [1]

Page 20: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

10

3.1.2 Different combinations of hybrid power systems

A hybrid power system that only consists of renewable energy sources is desirable but not practically

possible for many applications. That is because it is not possible to know the energy generation from the

sources. The reliability decreases significantly and the capital expenditures (CAPEX) cost increases due to

the maintenance and required space. [3]

The simplest hybrid system is a diesel generator with batteries. In this type of system the diesel

generator is charging the batteries with a rectifier or a battery charger in between to convert AC from

the converter to DC. The load is driven by the batteries and when the battery capacity becomes too low

the generator starts to charge the batteries. When the capacity comes to the defined max level the

generator stops.

To get this to work autonomously the system needs to be controlled with a control system. Usually this

control system consists of a microcontroller with some sensor and contactors/relays attached to it. The

important sensing data for this system is voltage and current. With this data the microcontroller can

calculate the capacity of the batteries and control the generator to power on and off.

Most hybrid power system has a backup generator to improve the reliability of the system, which is

important to ensure a solid access to energy.

Figure 7, renewable hybrid power system with a backup generator [18]

These systems can be run optimal with different configurations for the renewable energy source and

generator.

One configuration is to produce 80 % of the energy required for the batteries using a diesel generator to

allow the generator to run at optimal efficiency during the entire charging phase. The remaining 20 %

Page 21: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

11

takes time to charge because it requires low power. This part is an ideal application for the renewable

source. [3]

Figure 8, 80/20 fuel to solar configuration [3]

In Figure 8 the power for the load is negative, but to be able to easily compare both load and sources,

the power for all of them are positive.

If the area for installation of the system is sufficient the renewable energy sources can provide 80 % of

the required energy and the diesel generator acts as backup at unfavorable weather. [3]

To determine how the system should look like, the conditions for the location where the system will be

placed must be investigated. The components of the system can be selected after all the data for the

location has been collected. The manufactures for the PV-arrays and the wind turbines have

characteristic curves for their products and with the collected data the choice of right sources can easily

be done, to get the most cost effective and reliable system possible. [4]

An important fact is the relationship between CAPEX and operating expenditures (OPEX) for the system,

where a system is relatively cheap to install the OPEX will be high and vice versa.

Figure 9, illustrative graph showing the relationship between OPEX and CAPEX for different hybrid system combinations

Page 22: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

12

Figure 9 above illustrates how the relationship between OPEX and CAPEX change for different

combinations of a hybrid system. A system that is not dependent on renewable energy is costly to run

and maintain while a system only consisting renewable energy sources is instead costly to build, but less

expensive to run and maintain. [3]

Conclusion

When designing a hybrid power system the developer must consider different solutions depending of

the location of the system, economy, natural resources, availability etc. If it is difficult to get access to

the site, there will be hard to run and maintain a system containing e.g. a diesel generator and in some

cases batteries. In these cases the CAPEX cost will increase, due to the dependence of renewable energy

sources, but on the other hand a decrease in OPEX cost will occur. The natural resources like sun and

wind are highly dependent of the location and these resources have to be carefully investigated for each

site. Both sun and temperature are important for PV arrays in order to utilize full power, so there are

many challenges to take into account.

3.1.3 Most common batteries types for hybrid power system

Rechargeable batteries that are used in hybrid power systems are called secondary batteries. Common

secondary batteries for these systems and their characteristics are listed in Table 2 below.

Table 2, Characteristics of secondary battery types [2]

Battery Type

Cost

Deep Cycle Performance

Maintenance

Flooded Lead-Acid

Lead-Antimony low good high

Lead-Calcium Open Vent low poor medium

Lead-Calcium Sealed Vent low poor low

Lead Antimony/Calcium Hybrid medium good medium

Captive Electrolyte Lead-Acid (VRLA)

Gelled medium fair low

Absorbed Glass Mat medium fair low

Nickel-Cadmium

Sintered-Plate high good none

Pocket-Plate high good medium

As seen in Table 2 many types of lead acid batteries are used in hybrid power systems. Because of

differences in performance and design they are often classified in one of the following three categories

[2]:

SLI Batteries Lead-acid batteries that are designed for shallow cycle service, belongs to the category of

starting, lighting and ignition (SLI) batteries. These batteries are not designed for long life under

deep cycle service, but because they are the only manufactured batteries in some developing

countries, hybrid power systems sometimes contains SLI batteries. If the daily depth of discharge

is limited to 10-20 % and the maximum discharge is limited to 40-60 % the batteries can provide

service up to two years in small systems.

Page 23: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

13

Motive Power or Traction Batteries Batteries that are designed for deep discharge cycle service belongs to the category called

motive power or traction batteries. The normal use of these batteries is in electrically operated

vehicles. Because of their deep cycle capability they are very popular in hybrid power systems.

Stationary Batteries For un-interruptible power supplies (UPS), stationary batteries are most common. These

batteries are designed for occasional deep discharge and limited cycle service but they have

characteristics similar to the two previously categories. Due to the continuous float charging that

is common for stationary battery applications, battery designs with low water loss lead-calcium

are generally used.

Lead-Antimony Batteries

Lead acid batteries with antimony as alloying element in the plate grid, which is the electrodes in the

battery with a specific pattern, are called Lead-Antimony Batteries. The advantages of using lead-

antimony alloys are high discharge rate performance, excellent deep discharge, better mechanical

strength than pure lead grids, better lifetime at higher temperatures than lead-calcium batteries and the

shedding of active material is limited. The disadvantages are high self-discharge rate and, depend on the

amount of overcharge and temperature, frequent water additions is required. Generally Lead-antimony

batteries are classified as motive power or traction batteries. [2]

Lead-Calcium Batteries

Lead-calcium batteries has calcium as alloying element and in addition to the same advantages as Lead-

antimony batteries, lead-calcium batteries has less loss off water and lower maintenance requirements

due to reduced gassing of the batteries. The disadvantages are reduced battery life at higher operating

temperatures and repeated deep discharges, which also leads to poor charge acceptance. [2]

There are two types of flooded lead-calcium batteries:

Flooded Lead-Calcium, Open Vent

Usually classified as stationary batteries and have a capacity range up to 1000 Ah. Low water loss, low self-discharge and a lifetime of up to 20 years in standby or float service are some advantages.

Flooded Lead-Calcium, Sealed Vent

Have a capacity range between 50 and 120 Ah. Apart from the advantage from other lead-calcium designs these batteries are “maintenance free” which means that water does not need to be added. The disadvantage is limited lifetime.

Lead-Antimony/Lead-Calcium Hybrid

These batteries have lead-calcium at the positive electrodes and lead-antimony at the negative plates

and are typically flooded batteries. This combination has the advantages from both lead-antimony and

lead-calcium batteries. [2]

Captive Electrolyte Lead-Acid Batteries

Very common types of lead-acid batteries for hybrid power systems are captive electrolyte lead-acid

batteries. In this type of batteries the electrolyte is immobilized and under normal conditions the

battery is sealed. The batteries start to gas at excessive overcharging and at that time the valves open

Page 24: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

14

under gas pressure. Captive electrolyte lead-acid batteries are often referred to as valve regulated lead

acid (VRLA) batteries.

This battery design is intolerant of excessive overcharge because the electrolyte cannot be replenished

which also is accelerated in higher temperatures. The charge regulation voltage, charging methods and

temperature regulation are very important for this type of batteries. To prevent excessive overcharge,

constant-voltage with compensation of the temperature is a recommended charging algorithm. [2]

Gelled batteries and Absorbed Glass Mat (AGM) batteries are the most common type of captive

electrolyte batteries:

Gelled Batteries

Water loss is reduced by limiting the escape of gas. Improvements of deep discharge cycle performance in some batteries by an addition of phosphoric acid.

Absorbed Glass Mat (AGM) Batteries

Near full state of charge are gasses containing a composition of hydrogen and oxygen produced and an internal gas recombination prevent water loss.

Nickel-Cadmium Batteries

Different kinds of secondary batteries are Nickel-cadmium (Ni-Cad) batteries. Compared to lead-acid

batteries they have several advantages. The advantages are long life, low maintenance, handle excessive

discharges and exhaustive overcharge. Ni-Cad batteries are costly and compared to lead-acid the

availability is limited. [1][2]

Sintered Plate Ni-Cads and Pocket Plate Ni-Cads are the most common primary types of Nickel-Cadmium

batteries:

Sintered Plate Ni-Cads

Immobilized batteries that prevent leakage and are easy to transport and handle. The battery type has so called “memory effect”, which means that the batteries will reduce its capacity due to incomplete discharge cycles. This can partly be reversed by conducting a calibration charge cycle

Pocket Plate Ni-Cads

Much better than lead-acid batteries to manage deep discharges and temperature extremes and do not have the “memory effect”. The high initial cost is a disadvantage.

Lithium-ion Battery

Compared to the standard Ni-Cad the lithium-ion battery has twice the energy density, self-discharge is

less than half and similar behavior in terms of discharge. They don’t have a “memory effect” and don’t

require scheduled cycling, which means it, is a low maintenance battery. The maximum current flow

under cycling is between 1 C and 2 C. A rate of 1 C represents a charge current equal to the rated

capacity.

The disadvantages are the need of a protection circuit, or battery management system (BMS), to

maintain safe operation, which limits the peak voltage while charging and, under discharge, preventing

the voltage to drop too low. To prevent temperature extremes, the cell temperature is also monitored.

Page 25: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

15

Another problem is aging of the batteries and because of this, after two or three years [22], the

batteries frequently fail.

Table 3 below is a summarized list of the advantages and disadvantages between the different batteries

from this chapter, which provides a clear overview of them all.

Table 3, Advantages and disadvantages with different battery types [2]

Battery Type Advantages Disadvantages

Flooded Lead-Acid

Lead-Antimony low cost, wide availability, good deep cycle and high temperature performance, can replenish electrolyte

high water loss and maintenance

Lead-Calcium Open Vent low cost, wide availability, low water loss, can replenish electrolyte

poor deep cycle performance, intolerant to high temperatures and overcharge

Lead-Calcium Sealed Vent low cost, wide availability, low water loss

poor deep cycle performance, intolerant to high temperatures and overcharge, cannot replenish electrolyte

Lead-Antimony/Calcium Hybrid

medium cost, low water loss limited availability, potential for stratification

Captive Electrolyte Lead-Acid (VRLA)

Gelled medium cost, little or no maintenance, less susceptible to freezing, install in any orientation

fair deep cycle performance, intolerant to overcharge and high temperatures, limited availability

Absorbed Glass Mat medium cost, little or no maintenance, less susceptible to freezing, install in any orientation

fair deep cycle performance, intolerant to overcharge and high temperatures, limited availability

Nickel-Cadmium

Sealed Sintered-Plate wide availability, excellent low and high temperature performance, maintenance free

only available in low capacities, high cost, suffer from “memory effect”

Flooded Pocket-Plate excellent deep cycle, low and high temperature performance, tolerance to overcharge

limited availability, high cost, water additions required

Lithium-Ion

high energy density, low self-discharge, no memory effect, don’t require scheduled cycling, low maintenance

the need of a protection circuit, problem with aging

Conclusion

When choosing batteries for a hybrid power system it is important to know how the system should

work, what source it will contains and how the load will behave. There are lots of differences between

batteries e.g. cost, charging behavior, temperature dependence, maintenance etc. The most efficient

battery for one solution might not be suited for another operation.

NorthStar SiteTel has since the beginning of year 2000 been developing lead-acid VRLA batteries and

site solutions. They just recently started to develop lithium-ion batteries, but BMS are hard to develop.

For this purpose VRLA batteries are used for this thesis work.

Page 26: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

16

3.1.4 Battery charge controllers

Battery charge controllers are important to:

Prevent battery from overcharging

By limiting the energy supplied by the source when the battery reaches a fully charged state.

Prevent battery from discharging to a low state of charge

By disconnecting the battery from the load or start charging when too low state of charge is

reached.

A battery charge controller regulates the charge of the battery and related to the performance and life

for the battery, it is the most important function. The main purpose is to, without overcharging, fully

recharge the battery. If the battery charge is not regulated, the voltage will reach to high levels and

cause major gassing, electrolyte loss and heating which will damage the battery.

By limiting or interrupting the current flow from the source the charge controller prevents excessive

overcharge of the battery when it becomes fully charged. This is often achieved by limiting the

maximum value of the voltage and this is called the voltage regulation (VR) set point. If for example a PV

array is used to charge the batteries while it is sunny, the array will be disconnected until the voltage

drops to the array reconnect voltage (ARV) set point. Another method that is used is to calculate the

ampere-hour (Ah) into and out of the battery to determine when to charge or discharge.

Excessive discharging of the battery repeatedly will result in loss off capacity and life. Most charge

controllers include a feature that disconnects the load or force charges the battery when the battery

reaches a too low voltage to protect from this. The low voltage state is a pre-set or adjustable state

called low voltage load disconnect (LVD) set point. If the load is disconnected, it reconnects again once

the battery is recharge to the load reconnect voltage (LRV) Set Point. [1][2][4]

Figure 10, set points for a charge controller [2]

Voltage Regulation (VR) Set Point

VR set point is defined as “the maximum voltage that the charge controller allows the battery to reach,

limiting the overcharge of the battery “[2]. The controller will interrupt the charging or limit the current

Page 27: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

17

flow once the VR set point is reached. Dual VR set points are sometime used with for example higher

voltage for the first charge of the day and a lower voltage for the rest of the cycles. This will provide a

more effective float charge of the battery due to the gassing and equalization from the first charge. For

flooded batteries, the voltage selection should be at a point to minimize gassing, but for VRLA batteries

the gassing should be avoided.

If the system is a stand-alone PV system, the VR set point should be higher than the recommendation by

the battery manufactures, this because the need of shorter charging time due to the limited period of

useful time of the arrays. [2]

If the difference between VR and ARV is too large the current flow to the battery will be disconnected

for long period of time. This will make it difficult to fully recharge the batteries again. If the difference is

too small it can damage electro-mechanical switching elements due to the rapid on-off cycling. This

difference is called voltage regulation hysteresis (VRH).

A hysteresis between 0.4 V and 1.4 V is most common in on-off type controllers for nominal 12 V

systems. If a PV system does not have a daytime load the VRH should be smaller and vice versa. [2]

Load Reconnect Voltage (LRV) Set Point

The LRV set point is the voltage, which the controller reconnects the load or stops charging the batteries

after that LVD have occurred. If the load was disconnected, the voltage rises to its open-circuit voltage

(OCV) after reconnection and even more if additional charge is provided. The LVD set point occurs when

the voltage and the state of charge (SoC) is high enough.

The batteries lifetime will be shortened if LRV set point is selected too low so, just like with the LVD set

point, the developer have to consider the charge rates for the loads and sources. [2]

If the difference between LVD and LRV is too small the load or controller can be damaged due to the

rapid on-off cycling, and extending the charging time, if the difference is too large the charging time will

be extended. This difference is called low voltage load disconnect hysteresis (LVDH). [2]

Array Reconnect Voltage (ARV) Set Point

When the current flow from the array is disconnected from the batteries the voltage begins to fall. After

a while the voltage will drop to the ARV set point and the array starts to charge the batteries again. With

this method the array will cycle current to the batteries in an on-off manner and let the batteries be

fully charged repeatedly under the day. Otherwise the batteries would not be fully charged. [2]

In some controller designs of pulse width modulation (PWM) types the current flow is limited by

constant voltage and is not regulated in an on-off manner. [1][2]

Low Voltage Load Disconnect (LVD) Set Point

If the voltage goes to low at discharge the batteries could be damaged. The minimum safe voltage value

before this can occur is LVD set point. Sometimes a unit with LVD functionality is separated from the

main charge controller, especially when the load should be disconnected from the batteries instead of

charging them to a safe voltage. The definition of the LVD set point is “the actual allowable maximum

depth-of-discharge and available capacity of the battery” [2]. In a hybrid power system design the

available capacity must, under the development process, be carefully estimated to get the actual depth

of discharge.

The developer has to consider the rate of discharge to determine a proper LVD set point. For high

discharge rates lower LVD set points is needed but for example small stand-alone PV systems the

battery voltage is not significantly affected by the low discharge rate that is used. When selecting the

Page 28: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

18

LVD set point battery manufactures have a specified cut-out voltage that corresponds to 100 % depth of

discharge (DoD) and is typically 10.5 V for a 12 V battery. In order not to shorten the battery service life,

the batteries should never discharge completely, in general the LVD set point should be selected no

greater than 75-80 % DoD. [2]

3.2 Valve Regulated Lead-Acid Battery model

All lead acid batteries consist of lead plates that are covered in electrolyte, each cell produces

approximately 2.1 V. This means that 6 cells are series produces when charged, 12.6 V, this is a typical

12 V-battery.[23]

Figure 11, components of a VRLA battery

The electrolyte that the lead plates are submerged into is a mixture of positive charged hydrogen ions

and negatively charged sulfate.[23][26]

3.2.1 Charge and discharge reactions

Electricity from the charger produces chemical energy, to be able to charge, the charger has to provide

higher voltage than the cell voltage but not too high, that can damage the battery. The current flow

produces electrons to the negative plate, which attracts positive hydrogen ions. Now hydrogen reacts

with the lead sulfate bonded to the plate and forms sulfuric acid and lead, this process goes on until

most of the sulfates have reacted and hydrogen starts to rise from the negative plate.

Water contained in the electrolyte reacts with lead sulfate bonded on the positive plate and forms back

into lead dioxide, when the process is nearly complete remaining oxygen is formed as bubbles which rise

from the positive plates.

Page 29: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

19

Figure 12, charging process with gassing and the plates are covered in lead sulfate

During discharge sulfate ions are moved to the negative plate, here the ion loses its negative charge and

combines with the active material to form lead sulfate. Excess electrons now flow through the negative

pole to the applied load and back to the positive pole where they are attracted by the positive plate.

The active material on the positive plate, lead dioxide, contains oxygen that reacts with hydrogen and

produces water. Remaining lead forms lead sulfate that sticks on both the positive and negative plate.

Figure 13, discharging the battery, lead sulfate is formed on the plates

During discharge of the cell the number of ions contained in the electrolyte decreases and more lead

sulfate covers the active material.

The electrolyte that contains sulfuric acid gets depleted until almost only water remains. Sulfate coats

the plates, thus reducing active material surface, which means that the chemical reaction will eventually

stop, and the voltage will decrease until the plates are fully covered. [26]

Charging lead batteries

A normal charging process for VRLA batteries consists of different charging modes, bulk, float and boost

which all have different voltage settings. [5]

Page 30: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

20

Bulk mode is the first phase, which provides high constant current. Next phase is float charge, which has

a constant voltage, normally just below the gassing voltage seen at V1 in Figure 14.

Last is the boost, or equalization, the battery is overcharged with high voltage for a short period.

Equalization charge is above the gassing voltage, V2, which will produce essential gassing to remove lead

sulfate. Figure 14 below shows the typical charge curve.

Figure 14, a typical recharge curve. Bulk mode can be seen during charge when current is constant which turns into float and equalization charge

Grid reactions

The chemical process in a VRLA battery that produces the storage is achieved by conversion of lead

sulfate to lead dioxide which occurs on the positive electrode, and on the negative electrode lead

sulfate is converted into sponge lead. This reversible process is shown in equations (1)-(2), (5)-(6), and

net reactions equation (9)-(10). [14]

Positive electrode

(1)

(2)

(3) (4)

Negative electrode

(5)

Page 31: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

21

(6)

(7) (8)

Net reactions

(9) (10)

The reversible reactions mean that the battery cell is either discharged or charged depending on the

direction of the current. During a discharge the sponge lead and lead oxide are converted to lead

sulfate. As seen in equation (9), water is produced during discharge; the concentration of acid

electrolyte is reduced when discharging the cell.

The charging process is the opposite; sulfate is converted back into sponge lead and lead dioxide. As

seen in equation (10), acid electrolyte concentration increases when the battery cell is charged.

The cell is fully charged when all lead sulfates have been converted back to sponge lead and lead

dioxide. When the chemical reaction no longer can absorb the applied charging current, the excess

current will be consumed by overcharging processes.

3.2.2 Overcharging process

As Previously described above are the regular charge chemical reactions, and when the reaction stops

the excess current goes to the overcharge process.

The VRLA battery has an internal design, which will prevent the gas from escaping; instead it will diffuse

back to the negative plate where it chemically reacts with the sponge lead to form lead oxide. The

electrolyte reacts with the formed lead oxide, which then forms lead sulfate and water. Lead sulfate will

continue with further chemical reductions to form lead and sulfuric acid. During the whole time the

battery is fully charged, and charging continues, this overcharge process will continue as shown in

equations (11)-(13): [14],[10],[11]

(11)

During the regeneration, water is reverted back from the positive plate and consumed at the negative

plate.

(12)

(13)

When the cell is nearly fully charged, the overcharge process will start which will release oxygen from

the positive electrode:

(14)

Page 32: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

22

The oxygen will diffuse through the separator to the negative plate. At the negative plate oxygen reacts

chemically with sponge lead to form lead oxide, equation (11).

Gassing

As mentioned, when the battery is nearly fully charged the oxygen starts to form bubbles. This is called

gassing the battery. During charge until gassing, is called the natural absorption rate, which means the

amount of current that can be applied without the electrolyte is formed to hydrogen and oxygen. After

this level overcharging starts, that means that some of the current is wasted to heat and electrolyte

starts to evaporate. In VRLA batteries, this gas is re circulated back into the electrolyte so it does not

escape, thus VRLA batteries does not need to be refilled with distilled water as flooded lead batteries.

Gassing also occurs at normal charge, but at a much lower rate, this means that more Ah needs to be

charged into the battery than were taken out. [23][24][25][26]

3.2.3 Aging factors

Grid corrosion

When a battery is in a charged state the positive electrode is covered with active material, lead dioxide.

In addition to providing mechanical strength, it gives a low resistance path from the active material

through the plate to an access point. Any potential difference, which is common for the positive

electrode in a VRLA cell, will gradually corrode the grid. This can never be eliminated, but different alloys

can reduce the rate of corrosion. The Corrosion consumes the protecting lead dioxide layer. Equalization

charges are required periodically to rebuild this protecting layer. [26]

Stratification

“Battery Stratification is caused by the fact that the electrolyte in the battery is a mixture of water and

acid and, like all mixtures, one component, the acid, is heavier than water." [25]

Acid can start to settle at the bottom of the battery. Due to the high concentration of acid, more sulfate

will easier be stored on the plates. This reduces both capacity due to less active material, see Figure 15.

Figure 15, acid settles in the bottom of the battery

Page 33: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

23

Sulfation

When the battery is cycled with incomplete charging cycles, the lead sulfate crystals left will gradually

form bigger particles harder to dissolve during normal charge. They stick at the plates that will reduce

the capacity due to less active material. Repeatedly performed incomplete charging cycles will increase

the sulfate crystals, which eventually degrade the batteries capacity. [7]

Loss of electrolyte

This occurs due to gassing of flooded lead acid batteries, hydrogen disappears during charge/discharge

specially when performing a full charge with higher voltage. The cell will degrade its performance due to

less current flow. By adding water the cell can be rescued, adding electrolyte will distort the mass and

probably shorten the lifetime through higher corrosion. In VRLA permeation is also a problem, which

occurs during overcharge, these cannot be refilled as easily as flooded. This can be reduced by changing

the float voltage, keeping the right temperature and be careful when equalizing. [24]

3.2.4 Different methods for equalization charge

When cycling batteries at PSoC, as in hybrid systems, battery stratification occurs after some cycles, this

process can partly be reversed with an equalization charge. Gassing is used to recover the battery.

Basically lead crystals grow bigger each discharge cycle and normal charge cannot break these.

Equalization charge is an overcharge sometimes with higher voltage to force gassing resulting in

breaking the crystals. In a normal hybrid solution for RBS off grid, the equalization would typically occur

twice per month and would consist of a long charge. During this the diesel, or other charging

equipment, would charge for approximately 10-20 hours. [6][12]

What happens during overcharge is:

1. Charge of discharged material.

2. Oxygen Development, which recombine into the battery.

3. Hydrogen Development that leads out from the battery.

4. Corrosion of the positive grid.

In point 1, it may happen that one plate is more charged then the other, this is what happens in the

hybrid case with PSoC operation where there will be a severe fraction of the lead sulfate over time. This

is where the equalization is designed to charge and resolve these hard small grains.

Different methods

The normal way of equalizing lead acid battery is with a overcharge, where the voltage is usually higher

than float. The equalization will be complete when the charging current no longer increases. This is

called a passive equalization, which is not effective for batteries connected in parallel. Batteries behave

different and with the passive charge the battery with higher voltage will be more charged and perform

more gassing with higher temperature, which eventually harms the battery.

An active equalization is a special equalization where the charge only applies for each battery, or even

cell level. This method has several advantages for batteries connected in serial. The batteries do not

have to be charged with higher voltage, which will reduce amount of water loss. It will only charge each

Page 34: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

24

battery as much as necessary. There are mainly four different types of active equalization systems,

where all of them act as a BMS: [8]

1. Relay array:

Relays connects cells to the charger which can provide extra power if necessary, which will

remove the imbalance between cells. Main problem is that the relay array is very large and the

wiring is complex.

2. Switched capacitor system

Capacitors transfer energy when switched together, thus taking power from the higher voltage

cells to the lower. Mosfet switches in the range of hundreds kHz which reduce the sizing of

capacitors. The charging rate between cells is typically between C/500 to C/200.

3. Multi-output transformer

A multi output transformer transfer energy to the lowest voltage cell. Most of the energy is

transferred via diodes. A disadvantage is the power and duty cycle of the system is limited due to

not saturate the transformer.

4. Distributed structure on DC/DC converters

Both isolated and non-isolated DC/DC converters are used in this system. In the more charged

battery the energy is stored in the transformer when the particular transistor is switched on. A

disadvantage in this method is high cost and lots of components.

By combining the active and passive equalization charge you will get a cheap system which combines

the advantages from the active method but keeps the simplicity from the passive. The method is called

internal equalization charge, it can be seen as the series connected string is "one battery" and the

equalization charge will equalize one string when necessary.

Measure health of batteries

There are many different ways to measure SoC, they often require removing the battery and in some

cases letting it "rest" for at least one hour before measurements. The problem lies in how to measure

the stratification and to know when to equalize.[10]

Voltage

A normal way is to measure the voltage, this works well for lead acid batteries, but is quite inaccurate.

When measuring voltage to estimate SoC it is important to let the battery rest, as the acid diffuses

through the cells the voltage will drop. A problem with the voltage measurement is that it only

measures SoC, not state of health (SoH), which means a battery can seem to be fully charged but may

have less capacity because of battery stratification. Temperature also matters when measuring voltage,

higher temperature raises the open circuit voltage and lower lowers it.

Internal resistance

A way is to measure the internal resistance, the more sulfate left on the plates, the higher internal

resistance due to the lead sulfate acts as an insulator. High resistance of a battery allows it to accept a

higher current charge than when fully charged. This method requires the battery terminals to be

disconnected and a special instrument to be used.

Page 35: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

25

Coulomb counting

In hybrid systems to be able to cycle batteries in particular PSoC window are of great importance. The

normal way is to use coulomb counting, that means "counting" Ah. Measuring current during

charge/discharge multiplying with time gives the Ah produces some problems:

A problem is measurement accuracy with high current.

Batteries have internal losses, which need to be taken into account, and these vary during the

battery lifetime.

The batteries have a lower efficiency during equalization charge, which is hard to define.

Basically some of the energy is lost due to internal resistance and gassing. This efficiency is typically in

the range of >95 % during PSoC. For the batteries used in this thesis the efficiency goes up as high as

99%.

During overcharge, the voltage is above the gassing range, which means the efficiency is lower. This

efficiency is hard to measure. Theoretically, an accurate measurement of the emitted composition and

the amount of gases can help to determine the efficiency at the charging. However, one should have a

measure of the change in the battery before and after equalizing charge by conducting an accurate

capacity measurement.

Energy counting

Counting energy in and out from batteries is also common amongst hybrid systems; losses in form of

heat generated from the battery meaning temperature must also be taken into account. The difference

in voltage when charging and discharging gives is a significantly higher amount of energy put into the

battery than taken out. This energy counting efficiency is typically around 80-90 %.

In general counting energy, both in terms of watt and Ah, in and out from the battery is the easiest way

of determining SoC of a lead battery during cycling. Although this requires knowing the initial SoC

otherwise it has to start with a full charge. Depending on how well the system is calibrated it might also

periodically calibration by discharge and fully charged. [9]

The ability to determine SoC / SoH can be done but to a cost, the system must be disconnected or an

external reading has to be done.

Designing algorithms for controlling SoH to know when to perform equalization charge, or replace the

battery, is done by lab tests. Batteries are cycled and measured, the data would show that at a certain

PSoC operation the battery will need equalization charge after XX cycles and after XX cycles it is time to

replace the battery.

Page 36: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

26

4 Description of the task

The existing systems from different manufacturers are not as energy efficient as they could be, the

measurement accuracy is sometimes poor and the long equalization charge increases diesel cost. This

thesis aims to continue the development and improve the efficiency both in measurement and diesel

cost. SiteTel does not sell or develop any hybrid controller, so the task is to build a charge controller to

cycle batteries in a particular PSoC window and the batteries should switch between equalization charge

and normal charge at specified time.

The system should include a climate solution consisting of SiteTels outdoor cabinet Site Star-Tall. This

system will include four battery strings delivered by SiteTel. Diesel generator should be simulated by a

power supply that turns on and off from the system. The electrical components required to implement

internal equalizing charge has to be produced and tested.

The system's use windows need to be examined, mainly in terms of average power output, and

temperature changes. The system's competitiveness against what is known technologies in hybrid

energy solutions should be analyzed.

4.1 Internal equalization charge system for the prototype

The complexity of the equalization on cell levels and higher cost lead to that it will not be used. Instead

the equalization will be performed within string level, which is four 12 V batteries connected in series to

provide a 48 V “string”. This method has been tested by SiteTel in laboratory environment. The basic

idea is very simple, disconnect one string and perform an equalization charge with higher voltage during

a certain specified time.

During tests performed at SiteTel, they came up with optimal time, voltage and current. That is to

charge the 48 V string with 64 V during three hours with around 7.5 A, which should apply each 28 cycle.

Just as the long 12 hour overcharge this new method with higher voltage will boost the batteries enough

to reduce the stratification and almost restore the original capacity. In laboratory with only one string

the charging process is easy, just connect a 64 V power source with current limiter and disconnect after

three hours.

Our solution is a real system with four parallel-connected strings with some requirements:

The output voltage must never be disconnected, i.e. the load must always be powered.

Output voltage should not be increased due to the maximum in a 48 V telecom equipment is

around 56 V. This means that the string to be equalized should be disconnected from the rest

during this charge.

When in PSoC cycling mode, all batteries are connected in parallel; the charger charges all batteries,

which are also connected to the load. After 28 cycles, one string is switched to boosting stage; the two

(depending on how many used, it can also be three) other strings are now connected to both the load

and boost converter, which will then equalize the string for three hours. The idea is that during this time

the diesel generator should not have to be switched on.

Page 37: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

27

Advantages when using internal equalization charge

Main advantage of using equalization charge is of course to improve battery lifetime. With this kind of

internal equalization charge, the diesel does not have to run as much as the normal systems where the

equalization would typically be with diesel running for 12 hours twice per month.

In these kinds of hybrid applications this is of great importance, the cabinet is often placed in remote

areas where roads might be rough etc. so improving lifetime of batteries and increasing time between

refueling is an advantage.

The other advantage is in the environmental question, these hybrid systems are supposed to be

environmentally friendly, so reducing the diesel running time is important.

5 Modeling and simulation of the system with internal equalization

charge

Radio base stations have variable load depending on the traffic load. One purpose of this system is of

course to reduce fuel cost in terms of less diesel run time. Another aspect could be to have "quiet

hours" during the night to reduce disturbing noise. In order to measure the battery behavior and

possible savings in diesel run time, i.e. fuel, a simulation was made using the computer program

Simulink. The block model can be seen in Appendix 1.

A battery model included in Simulink was modified with values from the batteries supposed to be used

in the real system. Just as the real system will look, four strings are used one string includes four

batteries connected in serial, to make the simulation as realistic as possible.

Batteries are dynamically changing, meaning they behave different depending on ambient temperature,

pressure, power outage etc. Each battery is also not the other alike as they might have slightly different

compound or different filled electrolyte. Therefore battery dynamic is hard to simulate and predict.

For this thesis, the model in Simulink is adequate; a simple battery model does the job, as the system

will be tested in real test conditions.

5.1 Cycling at partial-state-of-charge

SiteTel have performed several tests showing that ideal PSoC window is somewhere at 60-90 % SoC. This

is the basis of how the hybrid charge control should work for best performance.

Figure 16, PSoC window normally used in cyclic operations

Cycling at PSoC is graphically displayed in Figure 16 above; LVD set point is usually at 42 V for a 48 V

system and should never be reached during a normal cycle. To be able to maintain performance, the

PSoC window should not drift more than ± 5 % within these boundaries. In this range the charge

acceptance is high which will improve efficiency of the diesel generator. The DoD is fairly low which will

provide a longer lifetime of the battery.[7][13]

Page 38: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

28

5.2 Evaluating power requirements for a Remote Area Power Supply

To get as close to reality as possible, real data from a radio base station in India acquired during one

week worked to simulate the variable load. This data was provided by the telecom company Ericsson.

India is a typical RAPS area where this kind of system would possibly be installed. At some places the

service providers have lower fees during the night that of course gives different power load, but the

data used serves as a good mean value of RAPS areas. [13][31]

Figure 17, shows how power consumptions for a RBS varies over time

Maximum power requirement is around 1240 W and drops down to 1050 W during nights. These values

were put into a signal builder inside Simulink to provide the correct load.

5.3 Modeling and simulation of the system in Simulink

This simulation is not to compare to reality, assumptions have been made about the charge acceptance

during overcharge, the battery model is far too simple which makes it hard to predict the charge

acceptance etc. The DC/DC converter is not modeled from reality, so during equalization charge we have

little ideas of how much current will flow to the battery and the efficiency of the DC/DC converter.

By combining the RAPS operating schedule together with the PSoC operation and building the switching

system, i.e. contactors and relays, it was possible to make a simulation of the systems switching

between equalization and normal cycling.

Together with the simulated diesel generator the simulation gave some results, which makes it possible

to have this kind of equalization charge without too low SoC. This data provided us with ideas how to

build up the switching in the prototype. The best time would be during night when the traffic load is at

its lowest to not let SoC sink too low, this is something which will have to be implemented in a real

system. Simulation showed that the best time to switch to equalization charge should occur directly

after the charging cycle to not let the SoC decrease more than necessary. The simulation also provided

some good hints about the possible current and voltage spikes which will occur during each switch

between equalization charges.

Page 39: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

29

Figure 18, data from simulation showing voltage during cycling

In Figure 18 above, the graph from the simulation shows cycling during three days during which the equalization would occur. Cycles between equalization were in this simulation set to zero.

One battery string will equalize each cycle, so the whole process in this simulation takes around 1.5

days. In a real system considering the power requirement of the RBS and if set to only equalize during

nights this might take longer time. It can clearly be seen that the cycle time between charge and

discharge decreases during equalization charge, this was of course expected due to that one battery is

disconnected thus reducing the amount of available energy or Ah.

6 Development of a prototype for the charge controller

To be able to test the hypothesis, that this equalization charge will work, and compare how well it

follows the simulation, a first prototype was built.

The system includes a climate solution consisting of SiteTels outdoor cabinet SiteStar-Tall. This system

can include four battery strings delivered by SiteTel. Diesel generator will not be used but instead a

power supply that turns on and off from the system. This prototype will also serve as real hybrid test

equipment to be able to compare to the existing ones on already on the market, the system's

competitiveness against what is known technologies in hybrid energy solutions will be evaluated further

down in this report.

In order to expand the systems user-friendly, a number of additional features listed and ranked, and will

be implemented as time permits.

Page 40: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

30

Table 4, ranking of features

Extra features Rank

Log data 1

Extern reading of data 2

Quiet hours of diesel generator 3

Present data graphically 4

Touch display 5

Autonomous control from logged data 6

User customization of parameters 7

6.1 Hardware

Hardware is a critical part in the design of the system, there will be high current and voltages that needs

to me measured with high accuracy, and the switching to equalize charge needs to withstand high

switching capacities, i.e. current spikes. All this needs to be controlled via a microcontroller.

Battery cabinet as well as batteries are provided from SiteTel consisting of:

12 pcs of 12 V 170 Ah lead batteries, four batteries are connected in serial to form a 48 V "string"

which in turn is parallel connected to get higher capacity.

Battery cabinet SiteStar Tall including four battery shelves and cooling compressor.

To control the equalize charge, a contactor with high current rating is used which in term is activated

from a mosfet transistor controlled via microcontroller. The contactor has a two-way switch, which

allows current to flow through one way when closed, and once activated the current flows via the

DC/DC and back to the battery. This allows us to control which battery should be equalized and which

battery should provide extra power to the boost. With this setup the charging is modular and

expandable; the system is built for four strings, but in this application there will be three strings. When

three strings are used, two battery strings will equalize the third.

In the prototype the generator is replaced by rectifiers connected to three-phase wall outlet. The RBS is

replaced by a resistive load, which is controlled by a relay activated via a mosfet connected to the

microcontroller.

The load is fixed to a mean value of a RBS; this means that the load is constant during the whole day.

The simulation showed that the best time for equalization charge is during the night when the load is

lower; in this prototype the SoC might have to go deeper.

Page 41: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

31

Sensing part

The prototype has different sensors for:

Current measurement:

Current is measured all the time in and out from the batteries, the range is from -100 A to 100 A.

According to specialists at SiteTel, the current resolution needs to be accurate to approximately

±0.1 A. The total ampere-hours are calculated from this measurement so a bad accuracy will

dramatically change the accumulated ampere-hours after some time. The zero point needs to be

accurate and calibrated; otherwise the difference in ampere-hours during charge and discharge

will differ too much. This will make the whole cycle algorithm skew and drift either up or down

resulting in bad efficiency or reduced battery lifetime.

Voltage measurement:

Is measured all the time to be able to shut down if there are any anomalies, the main criteria

here are LVD which is set to save the batteries from totally draining. The system is a -48 V

system, but the measurement range will be 0 to 64 V.

Temperature measurement:

Is monitored inside the cabinet, in-between two batteries, to be able to shut down if

temperature climbs to high during charge or equalization charge. The temperature sensor is

sealed with built in analog to digital converter (ADC) just sending digital values, which we read in

the microcontroller. The working temperature for these systems can vary from between below

zero to 45 C, but since the cabinet cools the batteries the temperature inside should be around

30 C. The temperature sensor should sense when temperature inside cabinet climbs over 50 C

and should then shut down the system.

Figure 19, block diagram of how the system is built up, one battery string with current and voltage measurements. The contactor is also connected to visualize how the current should flow

Page 42: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

32

Current shunts used, one for each string, are rated 100 A 60 mV which in turn is connected to an

operational amplifier (OpAmp) to amplify the voltage from 60 mV to correct level in order for the ADC to

handle. Care had to be taken to be able to handle both positive and negative current during charge and

discharge. Voltage can go as high as 64 V during equalization charge and the ADC can handle maximum

5 V. To be able to get 5 V a voltage divider is used before the ADC.

6.1.1 Charging equipment for the system

The charger, or rectifier, is built for -48 V systems and have earth connected to -48 V which means that

everything which is not built for -48 V systems have to be potential free, otherwise that will short circuit.

Figure 20, DELTA charger with rectifiers

The charger has rectifiers that produce 2 kW, depending on the applications rectifiers can be added to

the right power requirements. This charger automatically switches between float and boost charge

depending on the settings. In this case with hybrid application and internal equalization charge, the

charger is set to float, i.e. 54 V all the time, this will reduce gassing of batteries. For this prototype three

rectifiers are used producing in total 6 kW.

Load

The load used is Lingo dry type load bank, 48V max 300A. This is used to simulate RBS.

Figure 21, resistive load used to simulate the RBS

Page 43: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

33

Charge controller

To activate the charging, a relay box consisting of a 24 VDC relay and a three-phase contactor is used.

The relay is activated via a mosfet through the microcontroller which activates the contactor for three-

phase and controls the charger and load.

Figure 22, relay box which controls the charging

64 V DC/DC converter

The equalization charge should be at a higher voltage than a regular float charge, in this case 64 V. Since

DC/DC converters are complex, the only alternative was a off the shelf solution.

Figure 23, DC/DC converter Eltek PSC305-LV/60-8

The telecom DC Power manufacturer ELTEK provided one with the right criterion; it should be powered

through the batteries inside the cabinet, i.e. somewhere between 40-56 V and an output of 64 V. This

model can provide an output in the range of 45.2 to 82.5 V with maximum 8 A. The DC/DC is mounted

inside a 19" rack and came with a CAN-dongle which allows different settings of both voltage and

current limits.

6.1.2 The microcontroller used for the charge controller

The evaluation kit EVK1101 is used to be able to receive sensing data, do calculations and control the

system. The kit contains an Atmel AVR UC3B, which is a low power 32-Bit microcontroller with a core

frequency up to 30 MHz and 256 KB internal memory. Other features that are used are an inbuilt SD-

card reader, several General Purpose Input/Output (GPIO) ports and Serial Peripheral Interface (SPI)

connection.

Page 44: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

34

6.1.3 Simulation of the hardware in MultiSim

Since the current measurement is most critical, this was simulated first in computer program called

MultiSim from the company National Instruments. The current shunt will give 60 mV at 100 A, and of

course -60 mV at -100 A. This is amplified so that 100 A, 60 mV, equals 5 V and -100 A equals 0 V. There

are four different current measurements, one for each string used, and this OpAmp has four individually

amplified channels. OpAmps have a common mode rejection ratio (CMRR), this can be good or bad

depending on both the printed circuit board (PCB) design and the OpAmp itself, and this is also

something to see during simulation.

Figure 24, connection diagram of one of the four channels connected to LM324

The resistors are chosen as high precision, 0.1 %, to have as high accuracy as possible. To get a reference

0 at 2.5 V a voltage reference is connected directly to the positive input of the operational amplifier that

feeds constantly 2.5 V, which is added to the measured value. If the current reaches outside of the

shunts range, the output value is nonlinear and will reach above 60 mV. This is something that might

occur during the switching from equalization charge. By adding a 5.6 V zener diode, the input voltage to

the ADC will never reach above the maximum input range and the ADC will not take any damage.

Table 5, values from simulated operational amplifier

Real [V] Simulated [V] Difference [V] Shunt [mV]

5 5.083 0.083 60

3.75 3.834 0.084 30

2.5 2.584 0.084 0

1.25 1.3356 0.086 -30

0 0.08613 0.086 -60

Page 45: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

35

The common mode fault for operational amplifier LM324 and the difference to the "real" values are

shown in the Table 5 above. The difference is almost constant and the simulated values are slightly

higher and without any correction this will give significantly higher current.

To cope with this problem the values were plotted and compared to the real values, a simplified linear

equation for calibration was made.

(15)

This calibration is easy to adapt into the microcontroller, but these are of course just simulated values

and are theoretical values, so a small calibration has to be made in the microcontroller when everything

is connected.

6.1.4 Design and development of the Printed Circuit Board

Prototype started with a breadboard, which then was transferred to a PCB using MultiSim/Ultiboard.

The PCB includes all Low Pass (LP) filters, mosfet, ADC, OpAmp, voltage regulators, and connectors for

analog channels. Communication to the EVK1101 is done via SPI and GPIO.

Figure 25, external PCB

Some thoughts were spent on how to make it less sensitive to disturbances etc. All low pass filters are

placed as close to the ADC as possible, decoupling capacitors are placed close to all integrated circuits

(IC) also keeping the ground plane on the bottom as intact as possible to reduce radiated emissions and

maintain the capacitance. The circuit drawing can be seen in Appendix 2.

Low Pass filter

To improve measurement accuracy a LP filter is used on each of the eight channels to the ADC. Current

is most critical, an oscilloscope helped identifying possible disturbances, and since the sampling rate is

high the filter is set to a cut of frequency at 200 Hz. The high cut of frequency can be doubtful because

the change in current is a slow process, but simulation showed that the switching back from

equalization charge gives a high current spike which we thought would be nice to be able to see,

anything left is then filtered in the software. Since this prototype is optimized for lab environment with

a particular load and charger, the filters have to be redone since we have no clue how and which kind of

disturbances a real RBS might have.

Measurement accuracy

As mentioned earlier, the current needs to be nearly precise in order for the SoC to stay within its

boundaries. Even a small fault in measurement will accumulate into a quite large over time. It might not

seem as a terrible thing, but since this system should be a fuel saver a small deviation each charge cycle

might end up with a lot of more diesel run hours.

Page 46: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

36

The bottleneck in this design is the current shunt, which has an accuracy of 0.5 %, all other parts are

chosen to be better or as good as possible. Resistors for the gain on the operational amplifier are high

precision 0.1 %, they are chosen so as the maximum voltage at 100 A will be 5 V.

The evaluation board EVK1101 has a built in 10 bit ADC, but this is not accurate enough. An extern ADC

12 bit communicating via SPI is used. The maximum nr. of bits in the voltage range of the ADC, 5 V, will

be:

(16)

Since we are measuring 100 A during both charge and discharge it will have a range of 200 A, which

gives:

(17)

The maximum resolution in the ADC is ±0,049 A.

Display

Values are needed to be displayed somehow, a simple pixel matrix LCD was implemented. This cheap

display communicates via SPI, which was good solution since there are spare ports on the EVK1101. It

has 48 rows, 84 column outputs that will be enough to show values of current, voltage etc.

The small size limits the view of lots of data; to enhance the user performance a simple menu system

was built, see software implementation. By using four buttons the user can navigate through the menu

to see different data and settings.

These extra features were added after the PCB was sent for manufacturing. The buttons used for

navigating through the menu had horrible bouncing effect; this meant adding external PCB with button

debounce. This can normally be handled by the software, but since we do not use real time operating

system (RTOS), this gave lots of problems with delays etc. so all debounce had to be fixed by hardware.

The solution was to add debounce circuit consisting of a resistor and capacitor LP filter.

6.2 Budget and cost for the components used for the prototype

The prototype is designed for use within telecom industry, they are reluctant to pay more for high tech

features, so a goal for this prototype was to make is as cheap as possible. This will also help to make it as

competitive as possible on the telecom market. The prototype should also prove that it is possible to

have high accuracy measurements and a switching part for the equalization with cheap components. All

this together with the internal equalization charge, the system does not need to be over dimensioned in

terms of both diesel and battery capacity.

The DC/DC converter is the most expensive part in this solution; this of course included a CAN dongle,

which is a onetime cost. If this will be productified a special DC/DC for this purpose needs to be ordered.

On the other hand, more parts, like four contactors and a PCB, is something that would have been used

in a normal hybrid application anyway.

Different solutions were discussed about this implementation with contactors, how many to use etc. if

the system would be used to only have switching between two strings, i.e. two strings equalizing the

remaining two. This solution would not be much cheaper; the only difference would be two contactors.

Page 47: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

37

That combined with the lack of functionality, it will only work with four strings in parallel, lead to the

solution with four independent switching contactors.

For this project / thesis there were no real budget, only that it should be as cheap as possible. The total

expenditure for this prototype reached 12200 SEK where the DC/DC converter was most expensive, this

also included the evaluation board EVK1101, LCD display etc. A bill of materials used for the PCB can be

found in Appendix 3.

6.3 Software

The software is divided in several parts with different functions for the prototype. Every important part

has its own C. and H. files to make it easy to find and make changes. This is also preferable in order to

save resources if that part does not have to be used at the moment in the program. To obtain an overall

view of how the software is working, it is divided into three categories or subsections. These subsections

are further subdivided in several parts. Under subsection 6.3.1 is where the parts about communication

with external sources are explained. The parts which is about logging of data are under subsection 6.3.2

and under the subsection 6.3.3, the most important parts that handle the sensing data, timing and

control of the main function of the system (charge controller), are placed.

6.3.1 Handling of the communication with external sources

Serial Peripheral Interface

The hardware has different interfaces to communicate with the microcontroller. The most central

communicating interface in this solution is SPI. The ADC, the SD-card reader and the display are all using

SPI to send and receive data. The ADC has a sampling rate at 100 kHz and the clock frequency for the

display should be no more than 4 MHz. Due to this the ADC and the display are using the same SPI clock

at 1 MHz, because it is 10 times the sampling rate for the ADC, while the SD-card reader is using a

separate SPI clock at 1.2 MHz. Two different SPI options are used, one for the ADC and the display, the

second for the SD-card reader.

SPI options for the ADC and the display

SPI options for the SD-card reader

spi_options_t spiOptions = .baudrate = 1000000, .bits = 8, .spck_delay = 0, .trans_delay = 0, .stay_act = 1, .spi_mode = 0, .modfdis = 1 ;

spi_options_t spiOptions = .reg = 0, .baudrate = 1200000, .bits = 8, .spck_delay = 0, .trans_delay = 0, .stay_act = 1, .spi_mode = 0, .modfdis = 1 ;

To be able to choose between the display and the ADC, spiOptions.reg is set to 2 for the ADC and 3 for

the display.

GPIO

GPIO pins are used to control parts of the hardware. Apart from the pins for the display, five GPIO pins

are used to control the five mosfets, which are used to throughput current to the contactors and the

Page 48: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

38

relay for the charging. One pin is also used to communicate with the temperature sensors ADC. Four

pins are connected to buttons, up/down and enter/return for the menu system.

Display

Apart from the SPI communication the display have a reset and a Data/Command pin that has to be on

separate GPIO pins. In the initialization the reset pin has to go high and low in a specific order to be able

to communicate with it. Before data can be printed out on the screen The Data/Command pin has to go

low to send important commands to the display. To send data this pin has to be high. On the display a

menu system has been implemented, to easily and independently of a computer, have the ability to see

how the system is working.

Figure 26, flowchart of the menu system

Important information like current, voltage and ampere-hour for each battery can be selected and are

then printed out on the screen. Status information like uptime and system temperature can also be

selected.

Figure 27, different display screens

Some variables might be important to change if something in the system has been changed or needs to

operate differently. This can be done by via the menu system, e.g. number of battery strings, high state

of charge, charge factor etc.

Page 49: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

39

6.3.2 Logging of the important data

Serial communication

To obtain an overall view of the system, data is transmitted using serial communication or USART. Same

information as for the display is printed out on the computer monitor.

Figure 28, data via USART

This is useful when all the data needs to be displayed at once in real time. The use of USART is also

preferred when you need to import data to computer programs like MatLab.

SD-Card

With a SD-card, logging of all the important data is done using the SD-card reader. This is necessary to

provide an overview of the system behavior over a long period of time. In addition to all the data that

are displayed in real-time like current, voltage and ampere-hour for all the battery stings as well as the

system temperature, it also logs the runtime of the system to provide a timescale.

Figure 29, data in the logging file on the SD-card

With the use of the timescale, custom made graphs can easily be plotted with different selection of

data.

All the data is logged in a .csv file on the SD-card to easily put the different battery strings and type of

data in separate columns. The advantage of a .csv file is the simplicity of column separating, just by

adding a semicolon after each value. This type is perfectly suited for computer programs such as

Microsoft Excel. In order not to fill storage with data too quickly the logging is done only every 30

seconds.

Page 50: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

40

6.3.3 Handling of sensing data and control of the system

Analog to digital converter

To get some values from the ADC, bytes of eight bits have to be sent and received in a specific order.

Before receiving data, two bytes containing information about which channel it is, must be send to get a

“data_high” byte. This data_high byte has to be bitmasked into four bits. A dummy byte has to be sent

to get a “data_low” byte. These two bytes are then merged to get a full 12 bit ADC value.

Bytes send and receive for the ADC

byte=0b00000110; if(ch>3) byte|=0b00000001; spi_selectChip(&AVR32_SPI, 2); spi_write(&AVR32_SPI, byte); byte=ch<<6; spi_write(&AVR32_SPI, byte); spi_read (&AVR32_SPI, &data_high); data_high&=0b00001111; spi_write(&AVR32_SPI, DUMMY_BYTE); spi_read (&AVR32_SPI, &data_low); spi_unselectChip(&AVR32_SPI,0);

result = ((data_high<<8)|data_low);

In the C. file for the external ADC a software LP needed to be implemented due to some high frequency disturbances were detected. This filter has a cutoff frequency of 500 Hz. To further improve the measurements, mean value calculations of all samples from the ADC have been implemented.

Interrupts

Several types of interrupts are used for different kinds of functions. The GPIO pins for the buttons

triggers an interrupt to set various variables to be able to maneuver in the menu system. A real time

counter interrupt is used to get an accurate clock for the system and a timer/counter interrupt is used to

get an accurate timing. The real time counter that uses the external oscillator on the EVK1101 triggers

its interrupt every second to make it simple to generate a real clock.

Temperature sensor

To keep track of the temperature of the system and the batteries a temperature sensor is important. To

communicate with the ADC built into the temperature sensor, data has to be sent in a specific order

with predefined delays in between. The temperature value is divided in two parts, one digit part and

one decimal part. These two are put together to get the full temperature value.

Main program

The software’s core is the main program where the actual control of the system is done. The main

purpose of the system is to control the charging, discharging and equalization charge of the batteries. To

have the ability to do this, information about the batteries current, voltage and Ah are received or

calculated. The status of the voltage and current are received from the ADC that is running constantly

but timed by the timer/counter interrupt. The Ah of the batteries are then calculated using the real time

counter clock and current for each battery string. In order for the program to know when to charge, stop

to charge or perform equalization charge, they are divided in different states. In addition to Ah, some

other variables are in use with information about high and low state of charge and what state it is. The

state information is used to know what to do next and to prevent conflicts. The logging and USART

printing is done in the main program after all the calculations and control.

Page 51: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

41

Figure 30, flowchart of the main loop

Page 52: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

42

7 Implementation of the charge controller in a real system

The prototype is implemented in the cabinet provided by SiteTel and three battery strings, with the

possibility to add a fourth. The diesel generator is still not used and the RBS is replaced by a resistive

load.

Figure 31, block diagram showing the connection and setup of hardware, as it is supposed to look like when implemented in a real system

The cabinet has one cooling compressor with a cooling capacity of approximately 150 W at 25 °C

ambient. To be able to have lots of data and measurements we want to decrease the time between

cycles, but the cooling capacity of the cabinet limits both external load and charging current, otherwise

the batteries produce too much heat. The batteries have an energy efficiency of 85 % which means 15 %

of the total energy is reverted into heat. During the equalization charge, the energy efficiency is lower,

which means the temperature rises in a faster rate. In a real system, the cycling will be slower resulting

in less heat from batteries; a different cabinet with higher cooling capacity can be used.

Since the batteries are placed inside a closed unventilated container, venting tubes are drawn from each

battery and outside of the cabinet (see Figure 32), this is critical since the batteries produce high

amount of gas during equalization charge which otherwise could be ignited by one of the contactors.

Page 53: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

43

Figure 32, gas ventilations are set up on batteries [29]

The cabinet have place for four battery strings as seen in Figure 33 below, we are only connecting three for this test purpose, due to the amount of accessibility of batteries.

Figure 33, showing SiteStar Tall cabinet equipped with four battery strings [29]

The switching part is mounted in the bottom shelf of the cabinet, this allows all contactors to fit and

provides easy access. Voltage measurements (wires), and cables going to the boost DC/DC converter are

also placed at the bottom shelf. This solution is a good way of proving that the system easily can be

implemented on a real system.

Figure 34, bottom shelf inside cabinet and modified bottom shelf with three contactors mounted and measurement wires for voltage

Page 54: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

44

8 Test and verification

8.1 Previous work done by SiteTel

Various long time tests were conducted previously in lab environment verifying that the equalization

charge works as proposed. [28]

Those tests were only cycling the batteries, and after certain cycles increasing the voltage to 64 V. No

tests have been performed previously with this internal equalization, taking energy from batteries

equalizing others.

The test case looks as follows:

Discharge 5hours 11.4 A

Charge one hour 100 A

Each 28th cycle perform equalization charge at 3hours 7.5 A

The test measured end of discharge (EoD), which are plotted to see how the battery degrades, and how

much it gains from the equalization charge. Figure 55 shows the EoD vs. cycles plotted. The test case

was changed as the test prolonged, so the graph only shows the last 700 cycles, which have the same

cycling periods.

Figure 35, showing EOD of the batteries during cycling with equalization charge

Figure 35 above shows around 700 cycles with measured EoD, each equalization charge clearly raises

the EoD back to a higher level. The negative trend that can be seen is normal; the batteries are

decreasing in performance. The spike seen at 480 cycles is a capacity measurement, which is a full

discharge, followed by a full charge. As seen this raises the EoD even higher than the normal

Page 55: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

45

equalization charge, this is due to the long charge removing some large particles and increasing the

active material.

The test will continue until approximately 2000 cycles, then the weight will be measured and conclusions can be made on the battery SoH. These batteries are allowed a weight loss of 500 g of electrolyte until they are rated as bad. Any real conclusions and comparisons are hard to make, as the batteries are not the same as the one used in this thesis, but similar 150 Ah instead of 170 Ah. [28]

8.2 Test and verification of the prototype

The prototype was turned on and left for cycling to see that everything works as expected. Via the menu

system the equalization cycles were set to three to be able for a more rapid test, the initial test were

mainly to see if the switching part i.e. contactors worked as they should.

This test case looks as following:

1. One time charge until all strings have a charge current < 1.0 A

2. Discharge with 25 A until SoC reaches 50 % (load is always on)

3. Charge with 111 A until SoC reaches 90 % (minus the 25 A supplied to the load)

4. Continue cycling at PSoC for two more cycles

5. Perform first equalization charge (battery string 1)

6. Charge until 90 % SoC

7. Next equalization charge

8. Charge until 90 % SoC

9. Last equalization charge

10. Start from point 5.

After five days the system was shut down and SD card removed to analyze the collected data.

Page 56: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

46

9 Result

The key point of this prototype was to evaluate if it is possible to build this kind of internal equalization

device, it should work properly and not be too expensive. We proved this is possible to build and it

works as it is supposed to.

As the system turned on, a calibration charge was made as seen in the beginning of Figure 36 which

charged until the current to all strings were below 1 A. After calibration charge, the accumulated Ah

were reset to number of strings (three) multiplied by maximum Ah per string (170), which gave 510 Ah,

also seen in Figure 36 below.

Figure 36, accumulated capacity, Ah, for all strings and total capacity for whole system during five cycles, where the last three are equalization cycles

As seen in Figure 36 above the Ah counting works as it is supposed to, even with the initial calibration

charge. A small jag can be seen at the second cycle, this is nothing more than a power failure and our

safety system shut down the charger and load.

After three cycles, the first string is performing equalizing charge (Battery string 1 shown in blue), the Ah

increases up to more than fully charged (170 Ah is maximum) while the other two decreases in a faster

rate. The same goes for next two strings; one equalizes each cycle and the other two decreases faster.

The total Ah is still the same, energy has not been lost, just transferred energy from two batteries to

another. In the Figure 36 the equalizing battery reaches above maximum, which should be impossible.

This might be due to the columbic efficiency during overcharge; this is something we expected. During

normal charge efficiency is around 99 % and this is something we are taking into account when

calculating Ah. During overcharge there are very few, if any, measurements of the efficiency so we are

using the same 99 %, which obviously is wrong.

Page 57: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

47

Something that we thought of already at the start of the project was the systems high current during

charge and we expected high current spikes during the switch back from equalization charge. The

equalized battery is now fully charged whilst the other are discharged to about 60 % SoC.

Figure 37, current plot looking at one battery during cycling, one equalization charge and two cycles where next battery is equalizing

In Figure 37 current is shown from battery string 1 during four cycles, after the first equalization cycle

there is a current spike when battery string 1 is discharged rapidly to charge the other batteries. In

Figure 38 this spike can be seen even more clearly, since logging on the SD-card only occurs each 30

second. Current reaches (down to) approximately -205 A during the first couple of seconds. The current

shunt is a 100 A 60 mV and is calibrated to show maximum 100 A, this is why the measurements looks

distorted, but battery string two and three accepts around 90 A each while the load is set for 25 A.

Page 58: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

48

Figure 38, screen dump from Realterm, new value each second, showing more accurate current since the logging only occurs every 30 s

To be able to see if we are cycling correctly, i.e. counting Ah correctly, looking at the EoD voltage gives a

good indication. Figure 39 below shows the voltage from battery string 1 during cycling and equalization

charge.

Figure 39, voltage change during equalization charge for one battery

As seen in Figure 39 above the EoD voltage is stable, this means that we are taking out approximately

the same amount of energy each time, which is a good indication that everything works as it is supposed

to. Compared to the simulation, the voltage does not increase as much and fast. This is due to the

Page 59: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

49

simplified battery model used. But the simulation gave an idea of how it would look which at least looks

like reality.

Figure 40, zoomed view of equalization with included temperature

Temperature is logged during the whole time to be able to analyze how much more heat is generated

during the equalization charge cycle. Figure 40 above shows one equalization charge, the test was

performed in room temperature and with an open cabinet. As seen the temperature increases during

the whole charging, the temperature sensor was located in between the batteries.

By analyzing data from the previous cycling, the energy efficiency during equalization charge can be

calculated. This is done by dividing the power outtake in watts by the amount of watts charged. Doing

this in two cycles, one regular cycle and, one equalization cycle will give some difference in energy

efficiency.

The first cycle gave approximately 90 % efficiency and during equalization it decreased to 83 %. This

means that more energy is reverted into heat during overcharge.

Page 60: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

50

Figure 41, voltage and current for battery string 1 compared during an equalization charge

As seen in graph above current is limited during the first two hours equalizing, this is due to the DC/DC

converter and should be limited to approximately 7.5A. When the voltage increases up to 64 V the

current starts to drop, this has to do with the overcharge of the battery.

During the test we measured gassing at the same time as equalizing the battery. This was done with

specially made bags, which were connected to the gas ventilation tubes. Each bag could be filled with 5

liters of gas; so two bags were connected in "parallel".

The stoichiometry for full overcharge i.e. pure water electrolysis is 1 A, and a cell produces 0.630 L gas

during one hour. With 24 cells (48 V string) and 5 A, we get up to 75 L per hour. [28]

The first two and a half hours, when the voltage still increased, filled the two bags i.e. 10 l. Bags were

emptied and one was connected again, this was filled during the last half hour. In total 15 l was

produced, but it was only when the voltage reached 64 V as the amount of gassing increased up to 10 l /

h. This means that out of 75 L, 65 L are recombined back into the battery.

9.1 Analysis

By comparing both the simulation and data from our tests to existing hybrid system results show how much this new system with internal equalization charge will save.

If we compare to other hybrid systems already on the market, why is this better or how much will you

save?

To start with fuel savings, the existing hybrid systems have a kind of boost/topping charge as lead

batteries need to work properly during cycling. That system will at a preset time charge the batteries for

maybe 12 hours, diesel generator running constantly, at boost voltage, thus equalizing the internal

Page 61: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

51

differences between the cells. Without this topping charge, the EoD will slowly sink to a critical level

where the batteries have to little active material left.

The idea with this new internal equalization charge is to reduce the equalization time by increasing the

charge voltage above the gassing voltage, this way the time can rapidly be reduced. The batteries are set

for more gassing and resolving the crystals increasing the active material.

In a real system the charging time will not be limited by the ampere available from the wall outlet fuse.

According to SiteTel the charging time is expected to be approximately one hour and with a discharge

rate at 11 hours the diesel will run for two hours per day. By looking at the graph in Figure 39 and

comparing the time between a recharge one can see that during equalization the time is shorter. During

this (one equalization cycle per string) the diesel runtime will increase to about 2.5 hours per day. With

a setup of four battery strings, charging time will be up to 60 hours of charge each month (30 days).

The regular system with a 12 hour charge two times per month gives (during the 12 hour charge one

charge cycle is reduced) 58 hours of charge and two times 12 hour boost charge:

(18)

With expected life of 3 years, or 36 months, this equals

(19)

By comparing this with the new expected diesel runtime

( ) (20)

This new system will reduce the diesel runtime for almost 800 hours during 3 years. This can be

compared to the old system and can reduce the diesel runtime with up to 27 %. Diesel generators

require maintenance regularly, and with 800 hours decreased runtime, many service intervals are saved.

Looking at fuel consumption, for these calculations a 20 kW generator is concerned with expected fuel

consumption of 4.9 l / hour at high load and 2.3 l / hour during low load (low load is during the 12 hour

long charge when the current drops). [27]

60 hours with high load, i.e. 4.9 l / hour:

(21)

Considering the old system, 58 hours high capacity charge and 24 hours of slow charge:

( ) (22)

(23)

The total savings will then be:

(24)

This represents a yearly saving of:

(25)

The total fuel savings can reach 550 liters/year which equals 13.5 % less per year.

Page 62: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

52

Why not just set the diesel/charger for high volt charge at 3 hours?

Both ways are making the same effect on the batteries, but the new internal takes energy from the

other batteries already charged which reduces the runtime of diesel generator at low efficiency. During

the equalization cycle, the charge time increases to approximately 1.25 hours / day, by just changing to

the three hours boost charge, this new internal system will save:

(26)

up to 60 % time per cycle.

With 2000 cycles, nr of equalization cycles will reach 72. With 4 cycles / equalization times 1.25 hours,

this gives:

(27)

Compared to:

(28)

The difference by using internal equalization charge compared to using diesel to charge for three hours

will be 500 hours during the expected lifetime of the batteries i.e. three years. Compared to the old

system, three hour equalization with diesel running can save 10 % in diesel runtime which is not as good

as the internal equalization system.

How is battery lifetime improved?

As stated previously the expected lifetime when cycling batteries and conducting equalization charges

with 64 V would be at least 2000 cycles. Comparing this with data from RBS (in RAPS areas), average 2

cycles per day, will give a lifetime expectancy of closer to 3 years. According to previous replacement

intervals of hybrid batteries, this is somewhere between 2-3 years meaning battery lifetime might be

increased slightly.[29]

Another factor is how much gas the batteries produces, by comparing the amount of gas in a 12 hour

charge with boost voltage (56 V) to an equalization charge of three hours at 64 V can give an indication

on if this new equalization charge will improve the battery lifetime. The batteries is said to have reached

end of life when lost 500 g of electrolyte.

Presume that a valve-regulated battery is operating at float voltage and current,

(29)

where 20 % of the current generates gas. H2 per hour is 0.461 l / Ah and a 12 V battery has 6 cells, 48 V

string has 24 cells:

(30)

Page 63: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

53

For a 48 V string with 170 Ah, this is equal to:

(31)

As the voltage increases, so does the amount of gas. The International Electrotechnical Commission IEC

has guidelines for batteries and gassing levels. Amount of gas during boost will reach to about 1.8 l /

hour.

Figure 42, normal conditions gassing levels assumed 170 Ah/48V [28]

Batteries used for this thesis are new but they have been stored for almost a year at room temperature

above average, without any float charge. This makes it hard to draw any real conclusions, but we have

seen in the data analyzed that the batteries are regaining some of the original capacity, the equalization

charges clearly has a positive effect.

Due to this the recombination phase might not be 100 % correct. But comparing the results we got gave

some results about how much gas can be expected. During a normal equalization charge at boost

voltage the batteries will produce 1.7 L / hour:

(32)

Compared to the internal equalization charge where we got 15 L. With these calculations and

assumptions we can expect a decrease in gas emission, which might imply a slight improvement in

battery lifetime.

Page 64: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

54

10 Conclusion

The prototype built is working as it is supposed to, which means that it is possible to productify in the

future. Main purpose of this product is to have as low fuel consumption as possible and to be as

competitive as possible on the market. This is also an advantage in both environmental aspects as well

as disturbing noise from the diesel generator will be reduced. Savings in terms of fuel can, according to

simulations and calculations, be up to 550 l and 264 hours of less runtime per year, which equals a

saving of 13.5 % in fuel consumption compared to the old system.

The battery lifetime is also an important aspect with this internal equalization charge. According to tests

conducted to similar batteries, the batteries will last for at least 2000 cycles with 40 % DoD. [29]

We have also proved that this system is possible and easy to build with cheap components. In a mass

production, special order a DC/DC converter will reduce the price. All the switching is made by four

contactors, which can be mounted on the already existing bottom shelf. Everything can be controlled

through the AVR microcontroller, which also is cheap.

Some of the important questions which are addressed in this thesis are summarized below:

Which are the basic types of batteries used in a hybrid system?

- Flooded Lead-Acid

- Captive Electrolyte Lead-Acid, VRLA

- Nickel-Cadmium

- Lithium Ion

What are the different types of hybrid solutions already on the market?

The most common combinations are:

- Diesel generator with batteries

- Wind turbine or solar panels with diesel generator and batteries

- A combination consisting of batteries, wind, solar and diesel generator

What is an equalization charge and what happens?

An equalization charge is a forced overcharge that aims to reduce the stratification and remove

sulfate from the plates to recover the capacity in the battery.

What are the different kinds of equalization systems available on the market?

There are active and passive methods. The passive method is a forced overcharge with no

sensing mechanism. The active methods can consist of different sensing mechanisms and charge

each cell or battery which needs to be recovered. The active equalization charge system is not

available on the market but it is developed for each specific purpose. The system developed in

this thesis is an active equalization charge system.

How can you measure health of VRLA batteries?

The most common ways are:

- Voltage measurement

- Internal resistance

How much savings can you expect from this new technology?

This active internal equalization charge system can save, compared to old systems, 27 % in

diesel runtime and up to 13.5 % in diesel consumption which would be 550 l / year.

Page 65: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

55

11 Discussion and future development

To find a correct DC/DC converter was a struggle in the beginning of the project, since this is supposed

to run on voltages that aren’t standard. The solution was found from ELTEK, but was more expensive

than anything that can be used in the real system, but for this prototype it worked fine. A problem was

also that the voltage settings had to be manually configured via a CAN dongle, sold separately, which

increased the price even more, of course just a onetime cost. During the search to find the right DC/DC

converter, a lot of companies were found who could build these especially for the purpose. This was not

an option at this time due to time and cost, ordering just one is always much more expensive.

A robust temperature sensor should monitor the temperature inside the cabinet in between batteries.

Our solution was a sealed sensor with built in ADC just sending digital values, but due to not using RTOS

or something likewise, the delays needed for the send and receive functions disturbed other non-

critical, like the display of values, functions in our program. A quick fix for this at the time was to not

enter temperature function when using the display.

As this prototype contains many batteries, lot of power, it needed some kind of safety system. If the

system reaches a thermal runway or something in our software locks or voltage reaches LVD the load

and charging should turn off. Problem is that our system is powered via batteries, so if all batteries are

disconnected via the contactors the system will stop. A solution to this would be to have a small backup

battery to power the system.

As for now, an external safety system is used; this measures both temperature and voltage and

disconnects both load and charging if high temp or LVD occurs.

When designing the PCB, thoughts were spent on how to have high EMC and small EMI, something went

wrong during the auto routing and the card was sent for manufacturing, a lot of wires were not

connected directly to the power plane but instead routed like normal wires. The bottom copper power

plane was cut up quite much that may give some disturbances. This is something we encountered when

testing the system; we found some high noises, which were transferred into the ADC resulting in

oscillating values. There was no time to make another PCB so this had to be filtered out with a digital LP

filter.

During the design of LP filter we only measured disturbances we could encounter in lab environment,

only in hindsight we thought about how a real radio base station will send out strange signals. This does

not make any effect on this prototype, but something to think about in future development.

This system relies on having accurate measurements, thus time must also be correct. On the EVK1101

evaluation board there is an external crystal which we use to form an interrupt each second. Something

in the software is disturbing this that changes the time drastically. The crystal should have 30ppm

accuracy, but our time differed up to 5 s / min. For now the fix was in the software manually calibrating

the prescaler for the interrupt so that it matches real time as close as possible. In a future development

an external clock would be recommended, or if RTOS is used better scheduling routines could be applied

for the different functions.

This prototype should run over a long time, so data has to be reached somehow, the SD card logging

works as expected but leaves usability. The card needs to be removed when you want to see data,

during this time the system cannot continue logging. Real time data can of course be read through the

serial terminal, but since we have not implemented anything that is just for monitoring real time. The

Page 66: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

56

good thing is that it logs to a .csv file which can directly be opened in excel. One can easily build a macro

that reads the data and presents a graph of the interesting data. A better solution to this would be to

have a web server or similar which you can access via computer to read values.

Some thoughts have been spent on how to know when to equalize the batteries etc. this is hard to

predict, therefore this system will equalize on specified cycle nr. An adaptive algorithm could measure

the power to the RBS and then calculate when, time of day, the system would perform its equalization

cycle. This could then be configured to have “quiet hours”. This will increase the performance because it

will perform the equalization when the power requirements are at its lowest. This algorithm could be

even smarter by measuring power output to the RBS. So with a RBS having low power requirements the

equalization can be set different cycles which also will increase performance and reduce fuel

consumption.

We have also noticed that a so called capacity measurement will increase the capacity because of the

long slow charge. This is something that could be implemented, that after “half time” of the battery

lifetime, perform a capacity measurement. A capacity measurement is a full discharge followed by a full

charge. This will of course require the diesel to run for a long time, but if the batteries can last longer it

might be worth it. This can also give some interesting data, you can compare to the original Ah, which

would give an idea of how many percent of the battery lifetime is left. Another idea could be to have a

setting in the menu where the user can set a capacity measurement whenever he wants to.

Depending on how long the batteries have been stored, a capacity measurement can have a rewarding

effect on the batteries. Long time storage will reduce the capacity due to buildup of large crystals that

are hard to break during normal charging. A capacity measurement with higher boost voltage would

reduce these crystals and improve charge acceptance.

During the equalization charge, the current increased more than we expected. The current shunts used

are rated 100 A 60 mV, this does not mean they cannot handle more, when reaching above 100 A the

scale is nonlinear. We also designed the amplification so that at 100 A the output to the ADC would be

the maximum 5 V, meaning going above 100 A will not make any effect. This is something seen in

chapter 9, Result, where the current during equalization charge is described more. In a future

application the current shunts should be considered changed.

Page 67: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

57

12 Reference

[1] R.H. Newnham, W.G.A. Baldsing, ”Benefits of partial-state-of-charge operation in remote-area

power-supply systems”, Journal of Power Sources, 2002, Vol.107(2), pp.273-279

[2] James P. Dunlop, P.E., “Batteries and Charge Control in Stand-Alone Photovoltaic Systems

Fundamentals and Application”, Florida Solar Energy Center, 1997

[3] Arthur D. Sams, “Various Approaches to Powering Telecom Sites”, 2011 IEEE 33rd International

Telecommunications Energy Conference, Oct. 2011, pp.1-8

[4] Gebriele Seeling-Hochmuth, “Optimisation of hybrid energy systems sizing and operation

control”, Kassel University Press GmbH, 1999, ISBN 3-933146-19-4

[5] Y.S.Wong, W.G. Hurley, W.H. Wölfle, "Charge regimes for valve-regulated lead-acid batteries:

Performance overview inclusive of temperature compensation", Journal of Power Sources, 2008,

Vol.183(2), pp.783-791

[6] K. Mamadoua,c, T.M.P. Nguyenb, E. Lemaire-Potteauc, C. Glaizea, J. Alzieub, "New accelerated

charge methods using early destratification applied on flooded lead acid batteries", Journal of

Power Sources, 2010, Vol.196(8), pp.3981-3987

[7] Patrick T. Moseley, "High rate partial-state-of-charge operation of VRLA batteries", Journal of

Power Sources, 2004, Vol.127(1), pp.27-32

[8] Kong Zhi-Guo, Zhu Chun-Bo, Lu Ren-Gui, Cheng Shu-Kang, "Comparison and Evaluation of

Charge Equalization Technique for Series Connected Batteries", 2006 37th IEEE Power

Electronics Specialists Conference, June 2006, pp.1-6

[9] Kong-Soon Ng, Yao-Feng Huang, Chin-Sien Moo, and Yao-Ching Hsieh, "An Enhanced Coulomb

Counting Method for Estimating State-of-Charge and State-of-Health of Lead-Acid Batteries",

INTELEC 2009 - 31st International Telecommunications Energy Conference, Oct. 2009, pp.1-5

[10] M. Thele a, J. Schiffer a, E. Karden b, E. Surewaard b, D.U. Sauer a, "Modeling of the charge

acceptance of lead–acid batteries", Journal of Power Sources 2007, Vol.168(1), pp.31-39

[11] Gu W.B, Wang G.Q, Wang C.Y, "Modeling the overcharge process of VRLA batteries", Journal of

Power Sources 2002, Vol.108(1), pp.174-184

[12] Yutian Pan, Yanqiang Ma, Qingzhang Qin, Peiying Li, "Study on an Active Voltage Equalization

Charge System of a Series Battery Pack", Proceedings of 2011 International Conference on

Electronic & Mechanical Engineering and Information Technology, Aug. 2011, Vol.1, pp.141-144

[13] R.H. Newnham, W.G.A. Baldsing, "Advanced management strategies for remote-area power-

supply systems", Journal of Power Sources 2004, Vol.133(1), pp.141-146

Page 68: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

58

[14] Hunter, Phillip M., " VRLA battery float charge : analysis and optimisation", University of

Canterbury. Electrical and Electronic Engineering, 2003

[15] Wind turbine power output variation with steady wind speed, Retrieved 2013-02-25, from:

http://www.wind-power-program.com/turbine_characteristics.htm

[16] Wind turbine, Retrieved 2013-02-25, from: http://en.wikipedia.org/wiki/Wind_turbine

[17] Solar Power (Technology and Economics), Retrieved 2013-02-27, from:

http://www.mpoweruk.com/solar_power.htm

[18] Can I Go “Off-Grid”?, Retrieved 2013-03-01, from: http://windpower.facts-and-review.com/can-

i-go-off-grid

[19] Hybrid Energy Systems, Retrieved 2013-03-01, from:

http://exploringgreentechnology.com/solar-energy/hybrid-energy-systems/

[20] Series resistance, Retrieved 2013-06-02, from: http://pveducation.org/pvcdrom/solar-cell-

operation/series-resistance

[21] Jacobi’s Law, Retrieved 2013-02-27, from:

http://en.wikipedia.org/wiki/Moritz_von_Jacobi#Jacobi.27s_Law

[22] The lithium ion battery, Retrieved 2013-05-28, from:

http://batteryuniversity.com/learn/article/is_lithium_ion_the_ideal_battery

[23] Learn about batteries, Retrieved 2013-02-18, from: http://batteryuniversity.com/learn/

[24] The Basic Chemistry of Gas Recombination in Lead-Acid Batteries, Retrieved 2013-02-25, from:

http://www.tms.org/pubs/journals/jom/0101/nelson-0101.html

[25] SULFATERADE BATTERIER, Retrieved 2013-03-04, from:

http://www.micropower.se/CM.php?PageID=191196

[26] Battery Basics, Retrieved 2013-03-04, from: http://www.progressivedyn.com/battery_basics.html

[27] Diesel fuel consumption chart, Retrieved 2013-05-14, from: http://www.perfectfuel.ca/pdf/Diesel%20Consumption%20Litres%2012092009.pdf

[28] Gunder Karlsson, NorthStar SiteTel Sweden AB

[29] NorthStar SiteTel Sweden AB

[30] About Northstar SiteTel, Retrieved 2013-06-19:

http://www.northstarsitetel.com/northstar/about/index.php

[31] Kent Westergren, Ericsson AB

Page 69: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

Bat

tery

Mod

el

pow

ergu

i

Con

tinuo

us

Sco

pe4

Sco

pe3

Sco

pe2

Sco

pe1

Sco

pe

Rel

ay s

yste

m3In

Out

Con

n1

Con

n3C

onn2

Rel

ay s

yste

m2In

Out

Con

n1

Con

n3C

onn2

Rel

ay s

yste

m1In

Out

Con

n1

Con

n3C

onn2

Rel

ay s

yste

mInO

ut

Con

n1

Con

n3C

onn2

Mor

e In

fo

?

Load

In1

Out

1V

+

V-

Gai

n3

1/10

0

Gai

n2

1/10

0

Gai

n1

1/10

0Gai

n

1/10

0

Dio

de

DC

/DC

In1

Out

2

Con

n1C

onn2

Cha

rgin

g

In1

In2

In3

Out

2

Con

n1

Con

n2

Add

Bat

tery

3

+ _

m

Bat

tery

2

+ _

m

Bat

tery

1

+ _

m

Bat

tery

+ _

m

SO

C

SO

C

<Vol

tage

(V)>

<SO

C (%

)>

SO

CS

OC

SO

C<Vol

tage

(V)>

<SO

C (%

)>S

OC

SO

C

<Vol

tage

(V)>

<SO

C (%

)>S

OC

SO

C

<Vol

tage

(V)>

<SO

C (%

)>

Andreas
Typewritten Text
Andreas
Typewritten Text
Andreas
Typewritten Text
Appendix 1 - Simulink Model
Andreas
Typewritten Text
Andreas
Typewritten Text
Andreas
Typewritten Text
Andreas
Typewritten Text
Andreas
Typewritten Text
Andreas
Typewritten Text
Andreas
Typewritten Text
Andreas
Typewritten Text
Andreas
Typewritten Text
Page 70: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

0 0

1 1

2 2

3 3

4 4

5 5

6 6

7 7

8 8

AA

BB

CC

DD

EE

FF

GG

Q1

IRF520N

ADC

MCP3208

CH

0C

H1

CH

2C

H3

CH

4C

H5

CH

6C

H7

DG

ND

CS

Di

nD

ou

tC

LK

AG

ND

Vr

ef

Vd

d

Q2

IRF520N

Q3

IRF520N

Q4

IRF520N

GATE_GPIO

HDR1X5

DRAIN

HDR1X5

ADC_EVK

HDR1X5

Q5

IRF520N

SupplyVoltage

HDR1X3

LM

32

4O

PA

MP

OP

AM

P

V+

V-

OU

T1

OU

T4

OU

T2

OU

T3

IN

1-

IN

1+

VCC2.5

IN

2-

IN

2+

IN

3-

IN

3+

IN

4-

IN

4+

5V24V

5V

Tempsens

HDR1X3

5V

R184.7kΩ

Vo

lt

ag

ed

iv

id

er

DC

me

as

ur

e

CH

1C

H2

CH

3C

H4

IN

1I

N2

IN

3I

N4 V

+V

-

VoltageIN

DSUB9F

J2

DSUB9F

+12

-12

24V

+12

-12

DC

DC

TR

A1

-2

42

2

+V

in

GN

D-

Vo

ut

Co

mm

on

+V

ou

t

U2

MAX6225ACPA

I.

C1

IN

NR

GN

DTR

IM

OU

TI

.C

2I

.C

3

24V

C131.0µF

C14

2.2µF

C17

2.2µF

Vref2.5

Vref2.5

Cu

rr

en

t_

LP

_F

il

te

r

LP

FI

LT

ER

CH

1C

H2

CH

3C

H4

CH

1o

ut

CH

2o

ut

CH

3o

ut

CH

4o

ut

+12

-12

R46

1.0kΩ

R47

1.0kΩ

R48

10kΩ

R49

10kΩR50

10kΩR51

10kΩ

R52

10kΩ

C15

0.1µF

C16

0.1µF

Andreas
Typewritten Text
Appendix 2 - Multisim PCB Design
Andreas
Typewritten Text
Andreas
Typewritten Text
Andreas
Typewritten Text
Page 71: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

0 0

1 1

2 2

3 3

4 4

5 5

6 6

7 7

8 8

AA

BB

CC

DD

EE

FF

GG

lm

32

4_

op

am

p

LM

32

4

IN

1-

IN

2+

IN

2-

IN

3+

IN

3-

IN

4+

IN

4-

OU

T4

OU

T3

OU

T2

OU

T1

IN

1+

V-

V+

V+

V-

OUT1

OUT4

OUT2

OUT3

R1

1.2kΩ

0.1%

C1 6.8nF

C2 6.8nF

IN1-

R4

3.3kΩ

0.1%

C3 6.8nF

R3

100kΩ

0.1%

IN1+

VCC2.5

VCC2.5

R17100kΩ

0.1%

R2

1.2kΩ

0.1%

VCC2.5 R6

1.2kΩ

0.1%

C4 6.8nF

C5 6.8nF

IN2-

R8

3.3kΩ

0.1%

C6 6.8nF

R7

100kΩ

0.1%

IN2+

R5

1.2kΩ

0.1%

VCC2.5.1

R14

1.2kΩ

0.1%

C10 6.8nF

C11 6.8nF

IN3-

R16

3.3kΩ

0.1%

C12 6.8nF

R15

100kΩ

0.1%

IN3+

R13

1.2kΩ

0.1%

VCC2.5.3

R10

1.2kΩ

0.1%

C7 6.8nF

C86.8nF IN

4-

R12

3.3kΩ

0.1%

C9 6.8nF

R11

100kΩ

0.1%

IN4+

R9

1.2kΩ

0.1%

VCC2.5.2

VCC2.5.1

VCC2.5.2

VCC2.5.3

R29100kΩ

0.1%

R30100kΩ

0.1%

R31100kΩ

0.1%

D2BZX85-C5V6

D1 BZX85-C5V6

D3BZX85-C5V6

D4 BZX85-C5V6

R27

100kΩ

0.1%

R28

100kΩ

0.1%

R32

100kΩ

0.1%

R33

100kΩ

0.1%

R34100kΩ

0.1%

R35100kΩ

0.1%

R36100kΩ

0.1%

R37100kΩ

0.1%

Andreas
Typewritten Text
Andreas
Typewritten Text
Page 72: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

0 0

1 1

2 2

3 3

4 4

5 5

6 6

7 7

8 8

AA

BB

CC

DD

EE

FF

GG

CH1

CH2

CH3

CH4

R19

1kΩ

R20

12kΩ

R21

1kΩ

R22

12kΩ

R23

1kΩ

R24

12kΩ

R25

1kΩ

R26

12kΩ

IN1

IN2

IN3

IN4

D5 BZX85-C5V6

D6 BZX85-C5V6

D7 BZX85-C5V6

D8 BZX85-C5V6

U3A

LM324AN

U3B

LM324AN

U3C

LM324AN

U3D

LM324AN

V+ V-

C22

0.1µF

C23

0.1µF

C24

0.1µF

C25

0.1µF

R42

8kΩ R43

8kΩ R44

8kΩ R45

8kΩ

C26 0.1µF

C27 0.1µF

C28 0.1µF

C29 0.1µF

Page 73: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

0 0

1 1

2 2

3 3

4 4

5 5

6 6

7 7

8 8

AA

BB

CC

DD

EE

FF

GG

R38

8.0kΩ

CH1

CH2

CH3

CH4

CH1out

CH2out

CH3out

CH4out

C180.1µF

R39

8.0kΩ

R40

8.0kΩ

R41

8.0kΩ

C190.1µF

C200.1µF

C210.1µF

Page 74: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

Ulti

boar

d In

form

atio

n Ex

port

File

Repo

rt D

ate

: 23

Apr

il 20

13CO

MPO

NEN

TVA

LUE

NO

.PO

SITI

ON

CAP

0.1u

F14

C15,

C16,

C18,

C19,

C20,

C21,

C22,

C23,

C24,

C25,

C26,

C27,

C28,

C29

RES

1.0k

Ohm

2R4

6,R4

7CA

P1.

0uF

1C1

3RE

S1.

2kO

hm 0

.1%

8R1

,R2,

R5,R

6,R9

,R10

,R13

,R14

RES

1kO

hm4

R19,

R21,

R23,

R25

CAP

2.2u

F2

C14,

C17

RES

3.3k

Ohm

0.1

%4

R4,R

8,R1

2,R1

6RE

S4.

7kO

hm1

R18

CAP

6.8n

F12

C1,C

2,C3

,C4,

C5,C

6,C7

,C8,

C9,C

10,C

11,C

12RE

S8.

0kO

hm4

R38,

R39,

R40,

R41

RES

8kO

hm4

R42,

R43,

R44,

R45

RES

10kO

hm5

R48,

R49,

R50,

R51,

R52

RES

12kO

hm4

R20,

R22,

R24,

R26

RES

100k

Ohm

0.1

%16

R3,R

7,R1

1,R1

5,R1

7,R2

7,R2

8,R2

9,R3

0,R3

1,R3

2,R3

3,R3

4,R3

5,R3

6,R3

7ZE

NER

DIO

DEBZ

X85-

C5V6

8D1

,D2,

D3,D

4,D5

,D6,

D7,D

8CO

NN

ECTO

RDS

UB9

F2

J2,V

OLT

AGEI

NCO

NN

ECTO

RHD

R1X3

2SU

PPLY

VOLT

AGE,

TEM

PSEN

SCO

NN

ECTO

RHD

R1X5

3AD

C_EV

K,DR

AIN

,GAT

E_GP

IOVO

LTAG

E RE

FTR

A 1-

242

21

J1M

OSF

ETIR

F520

N5

Q1,

Q2,

Q3,

Q4,

Q5

OpA

MP

LM32

4AN

2U

1,U

3DC

DCM

AX62

25AC

PA1

U2

ADC

MCP

3208

1AD

C

Andreas
Typewritten Text
Andreas
Typewritten Text
Appendix 3 - PCB Components
Andreas
Typewritten Text
Andreas
Typewritten Text
Andreas
Typewritten Text
Andreas
Typewritten Text
Andreas
Typewritten Text
Andreas
Typewritten Text
Page 75: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries

Veck

a:23

Plan

erin

g%

slu

tför

t%

slu

tför

t (ef

ter p

lane

ring)

Fakt

iskFa

ktisk

(eft

er p

lane

ring)

PLAN

ERIN

GPL

ANER

ING

FAKT

ISK

FAKT

ISK

PRO

CEN

T

AKTI

VITE

TST

ART

VARA

KTIG

HET

STAR

TVA

RAKT

IGH

ETSL

UTF

ÖRT

VECK

AM

1M

2M

3M

4M

5

56

78

910

1112

1314

1516

1718

1920

2122

2324

2526

2728

29

Plan

erin

g5

45

410

0%Fö

rstu

die

56

510

100%

Sim

uler

ing

73

73

100%

Hård

vara

97

910

100%

Mju

kvar

a10

89

1210

0%Im

plem

enta

tion

155

155

100%

Verif

ierin

g/te

st18

416

710

0%Ra

ppor

t9

158

1610

0%

Pro

jekt

plan

erin

g

Andreas
Typewritten Text
Appendix 4 - Gantt Planning
Andreas
Typewritten Text
Andreas
Typewritten Text
Andreas
Typewritten Text
Page 76: Development and verification of an internal equalization ...697884/FULLTEXT01.pdf · Development and verification of an internal equalization charge system for lead-acid batteries