design basis report 3

140
610-T17, Task No. 24 May-22 Contract 611-C26 Design Basis Report Part B: Building Works Revision: B Part B: Building Work Progress Stage : 30% Kingdom of Saudi Arabia ROYAL COMMISSION FOR JUBAIL & YANBU ROYAL COMMISSION IN JUBAIL Jubail Industrial City JOB NO. 610–T17 DESIGN AND ENGINEERING SERVICES FOR PUBLIC FACILITIES TASK NO. 24 CONTRACT NO. 611-C26 Government Buildings Phase II Document type: Design Basis Report Part B: Building Works Design stage: 30% B Dec. 2012 30% DESIGN STAGE A. Rances J. Holland J. Mangarin A. Hamed Rev. No. Date Revision(s) Prepared by QA/QC Submitted by Approved by Page 1 of 140

Upload: mohdalal86

Post on 16-Apr-2015

372 views

Category:

Documents


3 download

DESCRIPTION

Edited 3

TRANSCRIPT

Page 1: Design Basis Report 3

610-T17, Task No. 24 Apr-23 Contract 611-C26 Design Basis Report Part B: Building Works Revision: BPart B: Building Work Progress Stage : 30%

Kingdom of Saudi ArabiaROYAL COMMISSION FOR JUBAIL & YANBU

ROYAL COMMISSION IN JUBAILJubail Industrial City

JOB NO. 610–T17DESIGN AND ENGINEERING SERVICES FOR PUBLIC FACILITIES

TASK NO. 24CONTRACT NO. 611-C26

Government Buildings Phase II

Document type: Design Basis ReportPart B: Building Works

Design stage: 30%

B Dec. 2012 30% DESIGN STAGE A. Rances J. Holland J. Mangarin A. Hamed

Rev. No.

Date Revision(s) Prepared by QA/QC Submitted by Approved by

Job No. 610-17 Contract Nos. 611-C26

Doc. No. 611-C26-G00-20UA-GA-000REV

B

Page 1 of 96

Page 1 of 98

Page 2: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Design Basis Report Part B: Building Works Revision: APart B: Building Works Progress Stage: 10%

DOCUMENT ISSUANCE LOG

RevisionProgress

StageIssued for Date

Arch. Lead

Stru. Lead

Mech. Lead

Elec. Lead

Telecom. Lead

A 10% Client Review Dec 12 AHA T.A.J SK.W A.G MH

B 30% Client Review

C 90% Client Review

D 100% Client Review

0 FinalBldg.

Commissioning Turnover Documents

Page 2 of 98

Page 3: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Design Basis Report Part B: Building Works Revision: APart B: Building Works Progress Stage: 10%

DBR TABLE OF CONTENTS

DOCUMENT ISSUANCE LOG..........................................................................................................2

DBR TABLE OF CONTENTS............................................................................................................3

1. INTRODUCTION....................................................................................................................51.1 BACKGROUND AND BRIEF DESCRIPTION OF THE PROJECT..............................51.2 SCOPE OF WORK............................................................................................................61.3 DESIGN REQUIREMENTS................................................................................................6

2. WORK BREAKDOWN PLAN................................................................................................62.1 DATA GATHERING AND COORDINATION.....................................................................62.2 IDENTIFICATION OF CRITICAL ACTIVITIES..................................................................72.3 CONCEPT AND DETAILED DESIGN AND PREPARATION OF BID PACKAGE / RFP AND IFC PACKAGES...............................................................................................................72.4 VALUE ENGINEERING.....................................................................................................72.5 TECHNICAL REVIEWS.....................................................................................................7

3. DESIGN CRITERIA................................................................................................................73.1 PUBLIC SAFETY AND PROTECTION OF PROPERTY...................................................73.2 WATER CONSERVATION................................................................................................83.3 ENERGY CONSERVATION..............................................................................................83.4 MAINTAINABILITY............................................................................................................83.5 ACOUSTICS CONTROL...................................................................................................83.6 STANDARDIZED EQUIPMENT.........................................................................................83.7 CORROSION PROTECTION & CONTROL......................................................................83.8 INTERIOR DESIGN...........................................................................................................93.9 CODES AND STANDARD.................................................................................................93.10 CULTURE AND TRADITION.........................................................................................9

4. SCOPE OF FACILITIES........................................................................................................94.1 ARCHITECTURAL SYSTEMS..........................................................................................94.2 STRUCTURAL SYSTEMS...............................................................................................234.3 CONVEYING SYSTEMS..................................................................................................384.4 FIRE SUPPRESSION SYSTEM......................................................................................424.5 PLUMBING SYSTEM......................................................................................................474.6 HVAC SYSTEM...............................................................................................................554.7 ELECTRICAL SYSTEM...................................................................................................604.8 TELECOMMUNICATION SYSTEM.................................................................................68

5. APPLICABLE CODES AND STANDARDS........................................................................745.1 ARCHITECTURAL...........................................................................................................745.2 STRUCTURAL.................................................................................................................745.3 MECHANICAL.................................................................................................................775.4 ELECTRICAL CODES.....................................................................................................795.5 TELECOMMUNICATION.................................................................................................81

6. FIRE SAFETY AND LIFE PROTECTION MEASURES......................................................836.1 OCCUPANCY CLASSIFICATION...................................................................................83

Page 3 of 98

Page 4: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Design Basis Report Part B: Building Works Revision: APart B: Building Works Progress Stage: 10%

6.2 CONSTRUCTION CLASSIFICATION.............................................................................846.3 FIRE AND SMOKE PROTECTION REQUIREMENTS AND MEASURES.....................856.4 EXITS AND EGRESSES REQUIREMENTS...................................................................886.5 LIFE SAFETY PLANS.....................................................................................................92

7. DESIGN ANALYSIS............................................................................................................937.1 SITE INVESTIGATION....................................................................................................937.2 ENERGY CONSERVATION............................................................................................937.3 WATER CONSERVATION..............................................................................................947.4 NOISE REDUCTION........................................................................................................947.5 ENVIRONMENTAL PARAMETERS................................................................................947.6 LIGHTING REQUIREMENTS..........................................................................................957.7 POWER SYSTEM ANALYSIS.........................................................................................957.8 ACCESSIBILITY PROVISIONS.......................................................................................957.9 SECURITY PROVISIONS................................................................................................96

8. APPENDICES......................................................................................................................96

Page 4 of 98

Page 5: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

1. INTRODUCTIONThis Design Basis Report is to be read in conjunction with the cross discipline drawings, and forms a statement for all design intent, codes and standards, references and functional requirements for the project.

The primary objective of this Design Basis Report (DBR) is to illustrate and explain to its reviewing audience (primarily End-Users and the Royal Commission) the primary factors, elements, conditions, and/or assumptions considered in developing the facility systems and components, and to provide a fundamental foundation for the detailed multi-engineering design in “Government Building Phase II” that will serve as a guideline for the Development of Design and Engineering work in achieving the utmost, optimum and excellent architectural and engineering design solution.

Background and Brief Description of the ProjectThis engineering design work is being carried out as part of a consulting Framework Agreement (“T-Contract”) entitled:

Contract No. 610-T17: Design and Engineering Services for Public Facilities.

Concluded between the Royal Commission for Jubail and Yanbu, and the ACE Jubail Association (comprising the partners AbdulRahman Al-Naim Consultant Engineers with Bernard Ingenieure ZT GmbH and Obermeyer Planen und Beraten GmbH). The Agreement was signed on 18th January 2008, covering an application of the services to an open-ended number of Tasks. The agreement is of the framework type, and is complemented by a Task Release for each specific Task to be undertaken.

Components of Contract N o. 610-T17:

The Royal Commission is proposing to provide three additional service facilitiesin Jubail Industrial City, following are the description of each facility to be developed:

A. Jubail Governor’s Office Building :This is a Two Storey Building, approximately 5,500 sq.m. total floor area, which will be located adjacent to Tareeg Ts1, Tareeg Ts2 and Tareeg Abu Ali.

B. Dawa Office Building :This is a Two Storey Building, approximately 2,600 sq.m. total floor area to be located in Al Kuds.

C. Patrol Police Office Building :This is a Single Storey Building with approximately 1,000sq.m. total floor area. This building will be situated in a vacant lot adjacent to Al- Sinnah’ Avenue.

Page 5 of 98

Page 6: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Scope of WorkThe Scope of Work for this Task is to complete a Detailed Engineering Design and Prepare an RFP Package for “Government Building Phase II“ as per the Contract 610-T17 requirements, including site facilities, infrastructure, landscaping, hardscaping, fit for purpose building design site canopies, both fixed and portable building, furniture layout and supply and all items and elements incidental or otherwise to such a development.

Design RequirementsThe AE shall give due consideration to good Engineering Design practice in accordance with RC Engineering Manual, RC Guideline Specifications, Jubail Management Procedures, Marafiq and SEC standards and the Saudi Telecom Company Standards and Requirements.The building shall be designed with robust roofs, walls, framing and finishes which shall maximize form, function, economy, constructability, ease and speed, availability of materials and labor, thermal insulation, sound attenuation, fire resistance and energy efficiency. The floor plans and site layout shall maximize area utilization, material and building elements are to be selected such that they enable and facilitate rapid construction (e.g. use of precast concrete and other prefabricated systems and components for structural applications) but must also be readily available in Eastern Province or be easily sourced from other regions in the Kingdom of Saudi Arabia. Windows shall be selected to be of low emission, tinted or dark double –glass, and air tight construction with weather strips and gasket to conserve energy.The buildings and the site where applicable shall be provided with Power, Lighting, Telecommunication, LAN, HVAC, Plumbing, Fire Detection, Fire Suppression, Building Management System, Handicapped Accessibility and Special Architectural features, all as required for development of this Use, Occupancy, Form and function.

2. WORK BREAKDOWN PLANDelivering Quality Engineering Detailed Design and an RFP package in a timely manner as per the Royal Commission Standard, is one of the challenges to the AE Consultant. Below are the design process and milestones that will help to enable in achieving these goals:

Data Gathering and CoordinationUpon release of the task, AE will commence in conducting interface and data gathering activities, research, investigate, compile, review and validate data, as built drawings for buildings and existing site utilities, site topographic survey information, design guidelines, specifications, related studies, reports, contract packages and liaise and coordinate with all RC departments and end users who have concern with the project.

Page 6 of 98

Page 7: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Identification of Critical ActivitiesAE will prepare a schedule for the performance of this work and update the schedule on a regular basis as agreed with RC. The schedule will convey task progress, plan and actual, and identity the status of activities critical for successful and timely completion of the task deliverables.

Concept and Detailed Design and Preparation of Bid Package / RFP and IFC Packages

AE will provide conceptual designs according to their study from data gathered, site visits inputs from RC departments, end user and as per the conceptual design work shops. Upon approval, AE will proceed with the detailed engineering design based on sound and established engineering principles in accordance with RC specifications, guidelines, requirements, parameters, design criteria and all national and international standards. Also, AE will prepare construction schedule for site and building stages, bid package / RFP and IFC packages.

Value EngineeringAE will participate in the RC value engineering workshop at 10% design completion stage, to consider potential “ brainstorming” alternative ideas. Considerations will include, but not limited to, constructability and construction technology, suitability, functionality, impact on system design and specifications, manpower requirements, material availability, safety and reliability, operation & maintenance requirements, and initial and life cycle cost.

Technical ReviewsIn determining compliance of AE to RC standards, requirements, parameter, guidelines, design criteria and all national and international standards, there is a need for technical reviews at pre determined intervals. These reviews shall be held at the 10% conceptual and preliminary design phase, 30% develop design phase, 90% detail design phase and 100% finalized detail design phase before submittal of IFC package.

3. DESIGN CRITERIARoyal commission is seeking Economically Prudent, but high quality design and development throughout the project. The AE contractor shall perform all necessary analysis and selection of construction requirements & methods, fixtures, equipment and materials to meet this primary design objective. The AE consultant shall establish performance, function, quality and aesthetic appearance measures acceptable to the owner throughout the design development. In order to achieve an ‘’excellent design” the Royal Commission provides the following Design Parameters:

Public Safety and Protection of PropertyThe facilities design shall include provisions for public safety and property protection with all means and measure for fire protection and emergency evacuation in accordance with the requirements of the SBC 2006, IBC 2009, International Fire Code (IFC 2009) and applicable requirements of National Fire Protection Code (NFPA).

Page 7 of 98

Page 8: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Water ConservationThe facilities design shall include measures to conserve the potable and irrigation water consumption as per the applicable Royal Commission guidelines. All proposed water conservation systems must be justified with a life cycle cost analysis to demonstrate the water cost savings offset the additional cost for the system. The life cycle cost shall be based on a 20 year life and should include all operating and maintenance cost and any replacement cost. No annual escalation should be included water in the operating and maintenance costs.

Energy ConservationThe facilities design all include energy conservation measures such as shading, insulation minimizing air conditioning loads, energy recovery, lightning control, utilization of natural lighting and solar energy. All proposed energy conservation systems must be justified with life cycle cost analysis to demonstrate the energy cost saving offset of the additional cost for the system. The life cycle cost shall be based on a 20 year life and should include all operating and maintenance cost and any replacement cost. No annual escalation should be included in the energy operating and maintenance cost.

MaintainabilityThe overall design and the selection of fixtures, equipment, and materials shall provide for easy and low maintenance requirements, easy access, standardization of fixtures, equipment, and materials to achieve minimum spare parts and maximum flexibility to replace. Design shall ensure that all equipment is accessible for operation and maintenance and that those considerations for maintenance, repair and replacement have been addressed.

Acoustics ControlIncorporate into the design of the structural, mechanical, electrical and architectural systems measures to control and reduce noise and vibration levels in accordance with the applicable and pertinent codes, standards and recommendation from the owner. The facilities design shall include provision for sound and vibration isolation, as required between adjacent areas, including the selection of sound attenuation and absorption materials and components, where required.

Standardized EquipmentIncluded in the contract is a provision for incorporation of certain equipment which is standard throughout Jubail Industrial City. Standard specification for these items will be provided by the owner. Also included is the requirement to follow the precedence of certain established methods, schemes, practices and philosophies as called for in the specifications or shown on the task order drawings.

Corrosion Protection & ControlThe facilities, services and utilities design shall incorporate into its civil, architectural structural, electrical and mechanical components and systems measures necessary for corrosion protection and control. This may include the use of non-metallic components, ground water drainage, impressed current and sacrificial anodes, cathode protection and corrosion-resistant materials and alloys.

Page 8 of 98

Page 9: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Interior Design The AE shall provide interior design of the facilities as appropriate for RC approval.

Codes and StandardThe facilities shall comply with applicable RC codes and standards, other third parties related agencies standards, national and international codes and standards.

Culture and TraditionThe Architectural character and floor layout of the facility shall be based on the Islamic culture and tradition.

4. SCOPE OF FACILITIES

4.1 Architectural Systems4.1.1 Building Description

A. Jubail Governor’s Office Building This project is proposed as a Two Storey Building, approximately 5,500 sq.m. total floor area. This building will house the Governor of Jubail Industrial City to fulfil his functions designated to him including an administrative office and different offices for his staff that supports him in performing his duties and responsibilities.

B. Dawa Office Building This project consists of a Two Storey Building, approximately 2,600 sq.m. total floor area. This office building will have an administrative function, recreational and educational centre in order to provide spiritual education and rehabilitation of muslims and will call non-muslim to embrace Islam through worship and behaviour.

C. Patrol Police Office Building The project a Single Storey Building with approximately 1,000sq.m. total floor area. This office building is intended for the use of the Patrol Police officer.

4.1.1.1 Space Program RequirementsA. Jubail Governor’s Office Building

(See Attachment A) 8.0 Appendices

B. Dawa Office Building (See Attachment B) 8.0 Appendices

C. Patrol Police Office Building The Design is approved and this building is proposed to be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C.

Page 9 of 98

Page 10: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.1.1.2 Site InvestigationIn this section the site data gathering and identifying the site constraints and potential aspect of the site. (See the Site Condition Report).

4.1.1.3 Codes and Standards Review

A. Jubail Governor’s Office Building (See Attachment C) 8.0 Appendices

B. Dawa Office Building(See Attachment D) 8.0 Appendices

C. Patrol Police Office Building The Design is approved and building is proposed to be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C.

4.1.2 Building Design Approach

4.1.2.1 Space Interrelationship Matrix

A. Jubail Governor’s Office Building (See Attachment E) 8.0 Appendices

B. Dawa Office Building (See Attachment F) 8.0 Appendices

C. Patrol Police Office Building The Design is approved and building is proposed to be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C.

4.1.2.2 Bubble DiagramA. Jubail Governor’s Office Building

(See Attachment G) 8.0 Appendices(See Attachment H) 8.0 Appendices

B. Dawa Office Building (See Attachment I) 8.0 Appendices(See Attachment J) 8.0 Appendices

C. Patrol Police Office Building The Design is approved and building is proposed to be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C.

Page 10 of 98

Page 11: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.1.2.3 Architectural Design ConceptA. Jubail Governor’s Office Building

“Living now in the present is because of the past” the architect is inspired of the Post Modern Architecture blending of modern and a touch of Islamic architectural style of the gulf, in order for the people to appreciate and will not forget the history and significant of the past, even they are now living in the present. The Facility is intended for the Governor which is one of the respected and powerful men in the country. It is composed of a massive structure with a huge dome and column that signify power to carry the responsibility and protect the welfare of the community, and an element of groove straight lines denotes the character of the true leader leading towards the straight path of good governance. The building is not specifically same character with the building around it but it blends with the environment and nature.

Proposed Design

Governor’s Entrance Perspective

Page 11 of 98

Page 12: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Main Entrance Perspective

B. Dawa Office Building“Dawa” an Arabic term for calling, the facility is intended to rehabilitate, educate and call muslim and non muslim to embrace Islam. The architect is inspired to apply the Contemporary Modern Architecture which is suitable to convey the message to the people what is the building intend for, the architectural characteristic of the building is simple and plain (denotes that one should come and be humble to embrace Islam), recessed and projected elements in elevation with a variation of hue, black and white (to leave the dark past and start to live a new life); mirrored floor plans, with a centred courtyard (reflect and put Islam in the centre of one’s new life).

Proposed Design

Page 12 of 98

Page 13: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Main Facade

Bird’s Eye View

C. Patrol Police Office Building The Design is approved and this building is proposed to be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C.

4.1.3 Building Components

4.1.3.1 Flooring SystemA. Jubail Governor’s Office Building

Ground Bearing Floor Slabs

The proposed floor is made of 100 mm thk. reinforced concrete slab with 50mm cement screed rest on well compacted sub grade with structural fill. A provision of polyethylene sheet vapor barrier (200 micron) with joining tape shall be provided for moisture protection and water proofing membrane (2mm thk. UPVC) in wet areas for protection against water condensation and moisture from underneath.

Upper Floor Slabs

The upper floor are made of 150mm thk. reinforced concrete slab with 50 mm thk. cement screed provision for water proving membrane (2 mm thk. UPVC) in wet areas for protection against water condensation.

Page 13 of 98

Page 14: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

B. Dawa Office Building

Ground Bearing Floor Slabs

The floor is proposed to be made of 100 mm thk. reinforced concrete slab with 50mm cement screed rest on well compacted sub grade with structural fill. A provision of polyethylene sheet vapor barrier (200 micron) with joining tape shall be provided for moisture protection and water proofing membrane (2 mm thk. UPVC) in wet areas for protection against water condensation and moisture from underneath.

C. Patrol Police Office Building The Design is approved and this building is proposed to be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C.

4.1.3.2 Wall System

A. Jubail Governor’s Office Building Exterior Wall

This perimeter wall is 350 mm thk. composed of the following: 25 mm thk. internal cement plaster. 200 x 400 x 150 mm thk. concrete masonry unit. 50 mm thk. Polystyrene XPS insulation R value=13h.ft.². ºF /Btu (2.288

m².K/W). Polyethylene sheet vapor barriers (200 micron) with joining tape. 200 x 400 x 100 mm thk. concrete masonry unit. 25 mm thk. external cement plaster.

Interior Wall Generally partition wall is to be 200x400x150/100 mm thk. concrete

masonry unit with 25 mm thk. cement plaster on both sides.

Demountable Partitions 48 mm (width) x 29 mm (depth) galvanized steel floor runner. 92 mm (width) x 32 mm (depth) anodized aluminum ceiling track. Extruded aluminum H or T studs or support frames fit b/w floor and ceiling

tracks at (610 mm) o.c. 19 mm thk.x 610 mm width gypsum board panel attached to studs

w/alignment galvanized steel clips. Anodized aluminum base and ceiling trim.

Toilet Partition 13 mm thk. solid phenolic panel with 19mm thk. door panels. Class B fire rating.

Page 14 of 98

Page 15: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

B. Dawa Office Building Exterior Wall

This perimeter wall is 350 mm thk. composed of the following: 30 mm thk. internal cement plaster. 200 x 400 x 150 mm thk. concrete masonry unit. 50 mm thk. Polystyrene XPS insulation R value=13h.ft.². ºF /Btu (2.288

m².K/W). Polyethylene sheet vapor barriers (200 micron) with joining tape. 200 x 400 x 150 mm thk. concrete masonry unit. 20 mm thk. external cement plaster.

Interior Wall Generally partition wall is 200x400x150/100 mm thk. concrete masonry unit with 25 mm thk. cement plaster in both sides.

Demountable Partitions 48 mm (width) x 29 mm (depth) galvanized steel floor runner. 92mm (width) x 32 mm (depth) anodized aluminum ceiling track. Extruded aluminum H or T studs or support frames fit b/w floor and ceiling

tracks at (610 mm) o.c. 19mm thk.x 610 mm width gypsum board panel attached to studs

w/alignment galvanized steel clips. Anodized aluminum base and ceiling trim.

Toilet Partition 13mm thk. solid phenolic panel with 19 mm thk. door panels. Class B fire rating.

C. Patrol Police Office Building The Design is approved and this building is proposed to be the site adaptation of the Ministry of Interior Building Under Contract 611- C27, As specified in Form C.

4.1.3.3 Roofing SystemA. General

Roofing membranes shall be designed to with stand intense sunlight, strong wind, sand abrasion, sweating and rapid temperature change, following are the roofing type to be used for all buildings:

The inverted roofing system layers are composed of the following: Loose laid stones/loose laid tiles (300 x 300 x 20 mm thk.) for pathway. Filter cloth (separation layer). Polyethylene XPS thermal insulation 150 mm thk.

(R value=30h.ft² ºF/Btu (5.28m² K/W). Polyethylene sheet (200 micron) vapor barrier. Water proofing membrane (2 mm thick upvc). 50 mm-30 mm (varies) cement foam concrete sloped to drain.

Page 15 of 98

Page 16: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Particular attention shall be given to the design of flashing caulking and expansion joint cover so that they are continuous and remain weather tight under all conditions.

4.1.3.4 Doors All doors must comply with the following as required:

All swing doors should be located to clear passing pedestrian traffic without interference and arc of the door swing should exceed 90 degrees to allow the full width of the door opening to be unobstructed.

All glass doors and sidelights should be clearly identified to prevent the possibility of people walking directly into them accidentally and a provision of safety glazing to reduce accident due to broken glass.

All doors hinge jambs should be at least 6 inches (150 mm) from a wall perpendicular to a building face.

All frames shall be fixed into prepared openings within the external walls and shall ensure void free, solid, water proof joints caulked with approved paintable mastic sealant.

All fire rated door assemblies shall comply with (UL) requirements and shall be tested, listed and labeled in accordance with ASTM. Requirement by a supplier/ agency recognized by and acceptable to the Saudi Arabian authorities.

All fire rated doors shall be provided with door closers with the smoke in tumescent seals to head and both sides. Closer shall be specified to operate for individual door size/weight and for the particular internal and external air pressure. Fire rated doors with one hour fire resistant walls shall be provided with minimum 45 min. fire resistant rating.

Generally all doors sets shall be:Personnel access: 900 mm/850 mm wide x 2100 mm high (door leaf size). Equipment access: 180 0mm/2000 mm wide x 2100 mm/3000 mm high (door leaf size) subject to equipment size. Warehouse doors: 2500 mm /3000 mm wide x 3000/3000 mm high.

Each type of hardware set shall be provided with color, finish, texture and material as required by the Royal Commission and shall be obtained from a standard range of a single manufacturer. Hardware for fire rated doors sets shall comply with all IBC and RC requirements. Only hardware which has been tested for the types and sizes of doors which complies with requirement for the labeling /testing shall be provided. Hardware for exit door operation shall comply with swing and opening force requirement of the relevant RC codes and standards.

A two levels grand master key system shall be utilized. All locks shall be separated by change key and master keys. Finalization and confirmation of keying and lock arrangements shall be approved by the Royal Commission.

A. GeneralFollowing are the types of doors to be used for the three (3) buildings:

Exterior Doors a) Hollow Metal Doors

45 mm thk. Insulated hollow metal (U-value=0.75Btu/h.ft². ºF)

Page 16 of 98

Page 17: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

16 gauge galvanized steel sheet. Double –glaze low-e (medium solar gain) with argon gas filled light

openings coated (if required). U-VALUE= 0.33 Btu/h. ft². ºF SHGC = 0.55 VT = 0.52

b) Aluminum Glazed Door 45 mm thk. aluminum frame. Double –glaze low-e (medium solar gain) argon gas filled on powder

coated aluminum frame (if required).U-VALUE=0.33 Btu/h. ft². ºFSHGC = 0.55 VT = 0.52

Interior Doors a) Wood Doors

45 mm thk. natural hardwood veneer. If required, single glazed clear glass light openings.

b) Aluminum glazed door 45 mm aluminum frame. Fully tempered safety glass.

4.1.3.5 WindowsFollowing are the types of windows to be used for three (3) buildings:

A. General External Window Double –glaze low-e (medium solar gain) argon gas filled on powder

coated aluminum frame.U-VALUE=0.33 Btu/h. ft². ºFSHGC = 0.55 VT = 0.52

Internal Window Single-glazed clear glass on powder coated aluminum frame

U-VALUE =1.30 Btu/h. ft². ºFSHGC = 0.79VT = 0.69

4.1.3.6 FinishesGenerally, all finish materials shall be selected for their ability to withstand the harsh environmental condition prevalent at the site. All fitting materials shall be approved and recommended propriety products. Installation shall comply with the manufacturer’s recommendation. Each product shall be provided from the single manufacturer as approved by the Royal Commission. All finish materials shall comply with relevant ANSI, ASTM standards and IBC requirements chapter 8 Section 804.

Page 17 of 98

Page 18: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Floor FinishA. Jubail Governor’s Office Building

600 x 600 x 12 mm thk. polished granite tiles (for lobby). 200 x 200 x 6 mm thk. unglazed industrial granite tiles. 600 x 600 x 6 mm thk. glazed ceramic tiles (for offices).

B. Dawa Office Building 600 x 600 x 12 mm thk. polished granite tiles (for lobby). 200 x 200 x 6 mm thk. unglazed industrial granite tiles. 600 x 600 x 6 mm thk. glazed ceramic tiles (for offices).

C. Patrol Police Office BuildingThe Design is approved and this building is proposed to be the site adaptation of the Ministry of Interior Building Under Contract 611- C27, as specified in Form C.

Wall FinishesA. Jubail Governor’s Office Building

External Wall Finish Latex paint on fair faced concrete plaster.

Internal Wall Finish Latex paint on fair faced concrete plaster. Fabric wall covering (for demountable partitions). 200 x 200 x 6 mm thk. industrial granite tiles (for toilet).

B.Dawa Office BuildingExternal Wall Finish

Latex paint on fair faced concrete plaster.

Internal Wall Finish Latex paint on fair faced concrete plaster. Fabric wall covering (for demountable partitions). 200 x 200 x 6 mm thk. industrial granite tiles (for toilet).

C.Patrol Police Office BuildingThe Design is approved and this building is proposed to be the site adaptation of the Ministry of Interior Building Under Contract 611- C27, as specified in Form C.

Page 18 of 98

Page 19: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Ceiling Finishes

A. Jubail Governor’s Buildinga) Acoustic Ceiling Panel (Offices)

610 mm x 610 mm/1220 mm x 19 mm thk. rectangular edge fiber glass acoustic panel on suspended T-bar system.

b) PVC Ceiling Panel (Toilets & Wet Areas) 600 mmx600 mmx 0.6 mm thk. pvc ceiling panel Suspended ceiling is composed of:

Cold formed metal piece carriers installed on 1,220 mm o.c. support wires (38 mmx19 mm) 20 gauge cross channels unit struts.

c) Gypsum Ceiling Panel (Lobby) 19 mm thk. gypsum ceiling panel installed in suspend furring

channel system.

B. Dawa Office Building

a) Acoustic Ceiling Panel (Offices) 610mm x 610 mm/1220 mm x 19 mm thk. rectangular edge

fiber glass acoustic panel on suspended T-bar system.

b) PVC Ceiling Panel (Toilets & Wet Areas) 600 mm x 600 mm x 0.6 mm thk. pvc ceiling panel Suspended ceiling is composed of:

Cold formed metal piece carriers installed on 1,220 mm o.c. support wires (38 mm x 19 mm) 20 gauge cross channels unit struts.

c) Gypsum Ceiling Panel (Lobby) 19 mm thk. gypsum ceiling panel installed in suspend furring

C. Patrol Police Office Building

The Design is approved and this building is proposed to be the site adaptation of the Ministry of Interior Building Under Contract 611- C27, as specified in Form C.

4.1.3.7 FixturesGenerally, all sanitary fixtures and accessories shall be one uniform type, supplied by the same manufacturer, comply with relevant ANSI and ASTM standards and approved by Royal Commission.

A. GeneralFollowing are the types and kinds of fixtures and accessories to be used for all buildings:

a) Water Closet

Page 19 of 98

Page 20: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Wall mounted western water closet with flush valve. Eastern type water closet with washdown rim type, integral foot treads

and high level cistern. White glazed vitreous ceramic. Flushometer value: 1.6 gal. (6L) per flushing cycle. Flushometer tank type: 1.6 gal. (6L) per flushing cycle. Complete with manufacturers fittings and accessories.

b) Lavatory White glazed vitreous ceramic. Wall hung type lavatory with central mixing taps. Under counter mounted lavatory on acrylic vanity counter top with

back splash and central mixing taps. 2.5 gpm. (0.16 l/s) faucet. Complete with manufacturer’s fittings and accessories

c) Urinals White glazed vitreous ceramic. Wall hung type with visible water trap seal without strainer and with 13

mm thk. phenolic partition on both sides. 1 gal (3.8l) per flushing cycling. Complete with manufacturer’s fittings and accessories.

d) Kitchen Sink Double stainless steel sink. Under counter mounted sink on acrylic counter top with backsplash. 2.5 gpm (0.16 l/s) sink faucet. Complete with manufacturers fittings and accessories.

e) Service Sink White glazed vitreous ceramic. Floor mounted with hose connection and vacuum breakers. 2.5 gpm (0.16 l/s) sink faucet. Complete with manufacturers fittings and accessories.

f) Water Cooler And Drinking Fountains Stainless steel drinking fountain with drain below. 50 liters tank size/capacity per hour. Drinking bubbler of dial type fountain discharge profile. Gooseneck bubbler of push button type for glass filling. Complete with manufacturers fittings and accessories.

.g) Toilet Accessories

Stainless steel paper towel dispenser and receptacle. Stainless steel toilet tissue dispenser. Stainless steel framed 6 mm thk. float glass vanity mirrors. Stainless steel liquid soap dispenser. Stainless steel robe hook. 200x200 mm stainless steel floor drain. Flexible stainless steel hose perennial spray. 38 mm Ø stainless steel grab bar.

Page 20 of 98

Page 21: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Complete with manufacturers fittings and accessories.

h) Cabinet 19 mm thk. wood laminate. Overhead wall mounted cabinet. Floor mounted under counter cabinet. Complete with doors, retractable shelves and complete manufacturers

with fittings and accessories.

4.1.3.8 FurnitureA. General

Following are the type and kinds of furniture to be used for all buildings:

DESK Executive Desk

-Size of L2600 x W700 x H760-65 mm Table top thickness-Wire management both on desk and pedestal top-Attached size return L2230 x W750 x H540 mm-Finish: paper and color: dark brown

Managers Desk-L-SHAPE desk with leather insert on top-Size: Paper-Color : Dark Brown

Supervisor desk-L-shape desk-Size of L1800 x W900 x H760 mm-Mobile extension-Mobile pedestal with three (3) drawers and a keyboard drawer-Finish with paper-Color in Dark Brown

Staff Desk-L-Shape desk with vinyl in lay on top and with three(3) drawer Pedestal &keyboard drawer-Size : L1800 x W900 x H760 mm-Finish with paper and color with dark brown

CABINETS Side Cabinet

-Consist of two (2) doors on side & drawers units in the center-Size : L1200 x W400 x H800 mm-Finish wood venere-Color Dark Brown

Steel File Cabinet

Page 21 of 98

Page 22: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

-Consist of three (3) drawers cabinet-Size :D620 x W450 x H1320 mm-color in grays.

4.1.3.9 EquipmentsA. General

All equipment shall meet the manufacturers’ quality standard and approved by the Royal Commission, following is the equipment to be used for all three (3) buildings.

a) Computer Intel® Core™2 Quad Processor Q 9550s(12m Cache 2.83Ghz,1333

MHz FSR 512 MB NVIDIA NVS 420 Quad Monitor Display Port/Dvi Video Card 4GB and Four DMM Slots; Non-ECC dual-Channel 800mhs DDRZ

SDRAM Supporting To 8GB Memory Card. 320 GB 7200 RPM SATA II Hardrives. NVDIA Qaudro ® FX 580 graphic card. USB Quiet Key Board English /Arabic. Optical USB Mouse with scroll. 19’’ LCD Monitor TFT high Resolution 1908FP flat panel.

b) Workstation Intel Xeon Processor E5630 (12 Cache 2.53 GHz 5.86gt/S Intel ® Qpi). Intel Q45 Express Chipset w/ I Ch 10 Do. Windows 7 Enterprise 64 Bit Operating System. Bios & MB Flash Drive for system Bios SMIBIOS 2.5 Support. 8GB and can accept up to 72 GB with dual processor installed. Three

channel memory architecture per processor with 1333 MHz and 1066MHz DDR3 ECC Registered DIMM memory.

9 DMM slots; 6 slots (2 per channel) on motherboard and additional 3 slots on optional 2nd processor riser card .

Two Internal 9cm (3.5˝) HDD bays, two internal 13 cm (5.25’’) optical bays.

500 SATA 3.0 GB/s host controller (part of the Intel chipset) and the optional PCI-e SAS g/ir controller supports SAS drives with host based raid.

SATA 16x DVD+/- RW super multi light Scribe optical drives. NVDIA Qaudro® FX580. Integrated dual Broadcom 5764 TPM 1.2 controller optional Broadcom

NIC, Intel NIC.

c) Photo Copier Machines Cannon Image Runner Type: Black And White Digital MFP Mono copy speed : 30 pages per minute A4 capacity: 4,950 sheets(max) Size: free standing Additional: Full Color Network Scanning.

Page 22 of 98

Page 23: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

d) Printer????

e) Projector WXGA (1280X800) – PRM -25 (DLP) native resolutions. 1600 ANSI (normal), 2000 ANSI (high) Brightness (ANSI lumens). 2000:1 contrast ratio. Dimension: 335 mm x 102 mm x 256 mm. Manual focus and digital zoom. 0.54 m-1.22 m projection distance.

f) Active Board Size.87 in active board + 2 fixed 387 pro 14,600 x 9200 resolution. Overall dimension: 2105 mm x 1329 mm. 1865 mm x 1175 mm active area dimension.

g) RefrigeratorColor white double door refrigerator has capacity of 180L energy class A: 220-240/50hz: with a dimension of 524 mm (width) x 544 mm (depth) x 1,306 mm (height)

h) Microwave Oven

i) Coffee Maker

4.2 STRUCTURAL SYSTEMS

4.2.1 INTRODUCTION

This design basis report lists the general design criteria that will be used in the calculations for the design of structural items involved in this task. This design criterion complies with all relevant Royal Commission codes and standards, latest editions of engineering and industry codes and Saudi Arabian government codes.

The function and occupancy of the different buildings is divided into three major categories,

(A) Jubail Governor’s Office. (B) Dawa office. (C) Patrol Police Office.

Each of the buildings is well described in the Architectural section of this DBR.

4.2.2 STRUCTURAL SYSTEM

4.2.2.1 Sub-Structure

For all of buildings mentioned above; Soil bearing pressure and other subsurface information for use in foundation design shall be in accordance with the recommendations of the geotechnical investigation report. However due to unavailability of the geotechnical report at this current design stage, the

Page 23 of 98

Page 24: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

foundation is designed for assumed bearing capacity of 100 KN/m2. The proposed foundation system is as follows:

For most of the building area the foundation system is spread footings, but at some locations combined footings are proposed to avoid overlapping OR any closely spaced isolated footings. For more details refer to the structural drawings.

The assumed minimum foundation embedment depth is 1.375 m below the bottom of slab on grade.

Reinforced concrete grade beams are applied at the building perimeter in order to carry the exterior composite CMU walls. Interior grade beams will only be provided where it is deemed necessary to increase the strength of the structure. Interior CMU walls shall be supported by the thickened slab on grade.

Reinforced concrete slabs-on-grade is applied. The slabs-on-grade are non-structural and mildly reinforced with welded wire fabric.

The atmosphere, soil, and water conditions in Jubail Town are severely corrosive. The construction of foundations and superstructures include competent corrosion mitigation measures to achieve long-term durability. At this design stage, Coal tar epoxy coating will be applied to all the structural concrete elements below finished grade.

For more details of the proposed sub-structure system, refer to the attached SE drawings with this design stage package.

4.2.2.2 Civil-Structural works

For any of the Structural works outside the main building (likewise manholes, foundation of the electrical poles, retaining walls, etc), concept is presented in our civil drawings.

4.2.2.3 Super-Structure

At this current design stage various framing systems of the buildings are proposed and recommended for the review and approval. The proposals are intended to finalize the best possible framing system.

A. Jubail Governor’s Office : The following two options are presented for the structural system of the ground + one storey building.

Option 1: Hollow Core Slabs having a thickness in the range of 150 mm to 250 mm are proposed to be supported by reinforced concrete beam-column frames having span bays at intervals in the range of 6.0 m to 12.0 m; however a long span reinforced concrete dome is proposed above roof level.

Option 2: Reinforced concrete solid beam-slab frame supported on columns is proposed in this option, the building floor forms simple two way and one way panels. One way solid joist frame is proposed to achieve longer spans of 12.0 m length, in the areas such as the meeting room.

Page 24 of 98

Page 25: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Option 3: Considering the occupancy and architectural features of the building a Steel framing system is not feasible for this type of building.

Recommendation: Hollow core slab system (Option1) is recommended here, considering the large slab spans with lesser dead weight and time saving in construction.

B. Dawa Office : Following two options are presented for the structural system of this ground + one storey building.

Option 1: Hollow core slabs having a thickness in the range of 150 mm to 250 mm are proposed to be supported by reinforced concrete beam-column frames having span bays at intervals in the range of 6.0 m to 12.0 m, However a long span reinforced concrete dome is proposed above roof level.

Option 2: Reinforced concrete solid beam-slab frame supported on columns is proposed in this option, the building floor forms simple two way and one way panels. One way solid joist frame is proposed to achieve longer spans of 12.0 m length, in the areas like meeting rooms.

Option3: Considering the occupancy and architectural features of the building steel framing system is not feasible for this type of building.

Recommendation: Hollow core slab system (Option1) is recommended here, considering the large slab spans with lesser dead weight and time saving in construction.

C. Patrol Police Station: As the building is a site adaptation from (027-T20, Task No. 1, Contract 611-C27), therefore a similar framing system of reinforced concrete flat plat is being adapted in this task.

Page 25 of 98

Page 26: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.2.4 SPECIFICATIONS

4.2.4.1 Concrete

f’c = 35 MPa (5.08 ksi)

Design concrete cylinder compressive strength at 28 days for all cast-in-situ reinforced structural concrete elements in contact with soil, or exposed to weather, salt, salt water, brackish water, seawater or spray from these sources.

Royal Commission Engineering Manual, Design Criteria, Structural, Chapter 9, Section 9.08 B.2.b

f’c = 30 MPa (4.35 ksi)

Design concrete cylinder compressive strength at 28 days for all cast-in-situ reinforced structural concrete elements and pre-cast walls not in contact with soil, or exposed to weather, salt, salt water, brackish water, seawater or spray from these sources.

Royal Commission Engineering Manual, Design Criteria, Structural, Chapter 9,

f’c = 35 MPa (5.08 ksi)

Design concrete cylinder compressive strength at 28 days for all pre-stressed reinforced structural concrete elements.

Section 9.08 B.2.b

4.2.4.2 Reinforcing Steel

fy = 420 MPa (60 ksi)

Minimum yield strength of all reinforcing steel. Epoxy coated reinforcement shall be used for below grade structure and up to 1 m above grade.

Royal Commission Engineering Manual,Design Criteria, Structural, Chapter 9, Sections 9.08 B.3.b.1 & B.3.c.1

4.2.4.3 Pre-stressing Strand

fy = 1860 MPa (270 Ksi)

Minimum yield strength of pre-stressing strand. Uncoated seven (7) wire low relaxation strand conforming to ASTM A416

4.2.4.4 Cement

a) For reinforced concrete structures, Portland-pozzolana cement concrete (Type I cement) shall be used in accordance with Royal Commission Guideline Specification for Structural Concrete, Section 03310, for the following types of concrete structures:1) All concrete structures in contact with ground or the ground water.2) All waterfront structures in contact with seawater or in locations subject to seawater spray.3) All mass concrete construction; for this purpose, the mass concrete is defined as monolithically poured slabs and wall over 1 m in thickness.

Royal Commission Engineering Manual, Design Criteria, Structural, Chapter 9, Section 9.08 B.1.

Page 26 of 98

Page 27: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

b) For reinforced concrete not in contact with the ground, Type I cement shall be used in accordance with Royal Commission Guideline Specification for Structural Concrete, Section 03310.

c) For plain concrete blinding, Type V cement shall be used in accordance with Royal Commission Guideline Specification for Structural Concrete, Section 03310.4.2.4.5 Welded Wire Fabric (WWF)

Fy = 240 MPa (34.8 ksi)Where: Fy = yield strength of WWF

Royal Commission Engineering Manual, Design Criteria, Structural, Chapter 9, Section 9.08 B.3.b

4.2.4.6 Anchor Bolts

Fy = 240 MPa (34.8 ksi) ASTM A36 M

Royal Commission Engineering Manual, Design Criteria, Structural, Chapter 9, Section 9.09 C.2.a

4.2.4.7 Concrete Masonry Units

Concrete masonry units will be Type 1, Grade N with minimum assembly strength at 28 days (f’m = 13.8 MPa). Mortar shall be Type N for interior walls or Type S for exterior walls. Grout shall have a minimum compressive strength at 28 days f’g= 13.8 Mpa.

Royal Commission Engineering Manual,

Concrete masonry units, grout and mortar shall be according to the ASTM standards.

Design Criteria, Structural, Chapter 9,

4.2.5 DESIGN CALCULATIONS

4.2.5.1 Dead Loads:

1. Unit Weights of different building materialsa. Reinforced concrete = 24 kN/m3

b. Steel = 77.32 kN/m3

c. Mortar, cement = 20.43 kN/m3

d. Pre-cast panels = 24 kN/m3

e. Plain concrete (perlite) = 7.86 kN/m3

Royal Commission Engineering Manual, Design Criteria, Structural, Chapter 9, Table 9B

2. CMU Walls (normal weight)a. 150 mm thk. CMU wall grouted @ 1200 mm c/c & 15 mm thk. plaster on both sides = 1.70 + (2 x 0.24) = 2.18 kN/m2

b. 200 mm thk. CMU wall grouted @ 1200 mm c/c & 15 mm thk. plaster

Royal Commission Engineering Manual, Design Criteria, Structural, Chapter 9, Table 9A

Page 27 of 98

Page 28: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

both sides = 2.39 + (2 x 0.24) = 2.87 kN/m2

3. Roofinga. 50 mm thick gravel @ 0.26 KN/m² (per 25mm thickness) = 0.52KN/m²b. 150 mm thick polystyrene foam @ 0.01 KN/m² (per 25 mm thickness) = 0.06 kN/m2

c. Water proofing membrane = 0.03 kN/m2

d. 120 mm thick lightweight concrete screed =1.82 kN/m2

Royal Commission Engineering Manual, Design Criteria, Structural, Chapter 9, Table 9A.

4. Ceiling (Suspended Ceiling)a. Acoustical fiber board = 0.05 kN/m2

b. Suspended steel channel sys. = 0.10 kN/m2

c. Provision for mechanical duct = 0.19 kN/m2

d. Provision for elec. lighting = 0.05 kN/m2

Royal Commission Engineering Manual,Design Criteria, Structural, Chapter 9, Table 9A.

4.2.5.2 Live Loads:

1. Roof Deck (Flat) = 1.0 kN/m2 or Rain Load ASCE 7-10, Table 4-1

2. AHU Units = As per the selection of the equipment by the mechanical discipline and the Manufacturer’s recommendation.

4.2.5.3 Rain Loads:

The Rain Water Load (where applicable) shall estimated as per ACSE 7-10, chapter-8, as follows:

R = 5.2(ds + dh) , equation (8.3-1)

In SI metric units : R = 0.0098(ds + dh)

Where symbols are:R = rain load on the un-deflected roof, in lb/ft2 (kNlm2). When the phrase "un-deflected roof' is used, deflections from loads (including dead loads) shall not be considered when determining the amount of rain on the roof.ds = depth of water on the un-deflected roof up to the inlet of the secondary drainage system when the primary drainage system is blocked (i.e., the static head), in inches. (mm).dh = additional depth of water on the un-deflected roof above the inlet of the secondary drainage system at its design flow (i.e., the hydraulic head), in inches. (mm).

The Rain Water Load for this building is NOT applicable because SCUPPERS as a Secondary / Emergency Rain drainage system had already been Provided at the Roof to reduce the magnitude of the Rain Load (in case of the Primary / Main drainage system Blocked). This is a structural design requirement for slab safety. The water discharge level of the Scuppers shall not exceed 150 mm from the higher of the roof finish level.

ASCE 7-10, Chapter 8

Page 28 of 98

Page 29: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.2.5.4 Wind Loads:

(Method 2) SEI/ASCE 7-10, Chapter 26 & 27

1. Risk Category = III ASCE 7-10, Table 1.5-1

2. Exposure Category = DASCE 7-10, Section 26.7.3

3. Structure Type = Rigid BuildingASCE 7-10, Section 27.4.1

4. Basic Wind Speed, V = 155 kph (43.06 m/s)

Royal Commission Engineering Manual,Design Criteria: Structural, Chapter 9, Section 9.07D.2.a.1

5. Velocity Pressure

qz = 0.613 (Kz) (Kzt) (Kd) (V2) (N/m2) ASCE 7-10, Section 27.3.2

Kz = 1.12 ASCE 7-10, Table 27.3-1

Kzt = 1.0ASCE 7-10, Section 26.8.2

Kd = 0.85 ASCE 7-10, Table 26.6.1 V = m/s ASCE 7-10, Sect. 26.5.16. Building Design Wind Pressure

P = q G Cp – qi ( G Cpi )ASCE 7-10, Section 27.4.1

Where: G = gust effect factor = 0.85ASCE 7-10, Section 26.9

Cp = external pressure coefficientASCE 7-10, Figures 27.4-1, 27.4-2 and 27.4-3

(GCpi) = internal pressure coefficient ASCE 7-10, Table 26.11-1

Pmin = 0.77 kN/m2 ASCE 7-10, Section 27.4.7

4.2.5.6 Seismic Loads

SEI/ASCE 7-10 Chapters 11 & 12 is adopted as basis for Seismic Load Calculation for the proposed Buildings.

1. Site Class = DASCE7-10, Chapter 20,

Table 20.3-12. Risk Category = III ASCE7-10, Table 1.5-13. Importance Factor, Ie = 1.25 ASCE7-10, Table 1.5-2

4. (MCE) Spectral Response Acceleration for Short PeriodsASCE7-10, Section

11.4.4SMS = Fa SS ASCE7-10, Eq. 11.4-1SM1 = Fv S1 ASCE7-10, Eq. 11.4-2

Where: SS = 0.15gRoyal Commission

Requirement for Jubail

S1 = 0.04gRoyal Commission

Requirement for JubailFa = 1.6 ASCE7-10, Table 11.4-1Fv = 2.4 ASCE7-10, Table 11.4-2

5. Design Spectral Acceleration Parameters ASCE7-10, Eq. 11.4-3

Page 29 of 98

Page 30: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

SDS = 2/3 * SMS

= 2/3 x (1.6 x 0.15) = 0.16ASCE7-10, Eq. 11.4-4

SD1 = 2/3 * SM1

= 2/3 x (2.4 x 0.04) = 0.0646. Seismic Design Category (SDC)As per Royal Commission Requirement for Jubail, S1= 0.04 and Ss = 0.15, the Building structure fall under Seismic Design Category A.

ASCE7-10,Section 11.4.1

As per ASCE 7-10, “ Where S1, is less than or equal to 0.04 and Ss is less than on equal to 0.15, the structure is permitted to be designed to Seismic Design Category A and is only required to comply with Section 11.7

For the Building: SDC = AASCE7-10, Section 11.7.1

7. Design Requirements for Seismic Design Category A.Each structure shall be analyzed for effects of static lateral forces applied independently in each of two orthogonal directions. In each direction the static lateral forces shall be applied simultaneously.

Fx = 0.01 wx

where:Fx = design lateral force applied at story xwx = portion of the total dead load of thestructure located or assigned to level x

ASCE7-10, Section 1.4

ASCE7-10, Eq. 1.4.1

8. Horizontal Distributed of ForcesThe seismic design story shear in any story shall be determined from

V x=∑i=1

n

Fi

ASCE7-10,Section 12.8.4

ASCE7-10, Section 12.8.13

9. Inherent and Accidental TorsionInherent and accidental torsion are not covered under SEI/ASCE7-10, Section 12.3 when SDC = A

ASCE7-10,Sections 12.8.4.1 &

12.8.4.2

ASCE7-10, Section 12.3

Horizontal diaphragms are considered rigid while the vertical diaphragms are considered flexible, hence the seismic lateral force at level x is assumed to be carried and distributed equally among the vertical resisting elements (columns) at that story.

Assumed

4.2.5.7 Load Combinations

A. Service Loads (Allowable Stress Design): SEI/ASCE7-10, Chapter 2 Combinations of Loads

a. D

b. D + L

Page 30 of 98

Page 31: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

c. D + (Lr or R or S)

d. D + 0.75L + 0.75(Lr or R or S)

e. D + (0.6 W or 0.7E)

f. D + 0.75L + 0.75(0.6W) + 0.75(Lr or R or S)

g. 1.0 D + 0.75(0.70E) + 0.75S

h. 0.60D + 0.6W

i. 0.60D + 0.70E

B. Factored Loads (Strength Design): SEI/ASCE7-10, Chapter 2, Combinations of Loads

a. 1.40 D

b. 1.20 D + 1.60 L + 0.5 (Lr or R or S)

c. 1.20 D + 1.60 (Lr or S or R) + (L or 0.5W)

d. 1.2 D + 1.0W + L + 0.5(Lr or S or R)

e. 1.2 D + 1.0E + L + 0.2S

f. 0.90 D + 1.0 W

g. 0.90D + 1.0 E

Where: D – Dead Load

L – Live Load

W – Wind Load

E – Earthquake Load

Lr – Roof Live Load

R – Rain Load

S – Snow load

Exceptions to Factored Load Combinations

1. Where lateral earth pressure provides resistance to structural actions from other forces, it shall not be included in H but shall be included in the design resistance.

2. H shall be set to zero if the structural action due to H counteracts that due to the other load cases.

3. Effects on one or more loads not acting in whole or in part shall be investigated. This includes patterning transient loads in continuous and cantilever framing.

4. E and W are permitted to be applied independently in each of two orthogonal directions and orthogonal interaction effects are permitted to be neglected.

5. Minus E and minus W directions shall be investigated.

4.2.6 Drift and Displacement

A. Maximum Allowable Drift:

1. Wind Loads

The design story drift (Δi) shall be computed as the difference of the displacements at the center of mass at

ASCE7-10, Chapter 26,27ASCE7-10, Appendix C.

Page 31 of 98

Page 32: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

the top and bottom of the story under consideration.

Δ i/Li < 0.0025

where: Li = story height under consideration

C.C.1.2.

2. Earthquake Loads

Displacements of the structure shall be considered using the amplified displacement obtained from the following formula:

Δx = Cd xe/Iewhere: Δx = Amplified deflection Cd = Deflection amplification factor xe = Deflections determined in elastic analysis

using the strength level seismic forces (i.e., 1.0 E, not 0.70 E) of ASCE 7

Ie = Importance Factor

The design story drift (Δi) shall be computed as the difference of the amplified displacements at the center of mass at the top and bottom of the story under consideration.

Δ i/Li < 0.020

where: Li = story height under consideration

ASCE7-10, Chapter 12

ASCE7-10, Eq. 12.8-15

ASCE7-10, Table 12.2-1

ASCE7-10, Sect. 11.5.1

ASCE7-10, Table 12.12-1

4.2.7 Concrete Cover

A. The table below defines the minimum concrete cover measured from outermost rebar (tie-bar) that shall be provided for reinforcement of cast-in-place concrete structures.

Concrete ExposureMinimum

Cover (mm)

Royal Commission Guideline Specification, Section 03205, Table 3A

Concrete in contact with soil; exposed to sea water; potable or treated water

75

Page 32 of 98

Page 33: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Concrete exposed to weather :Columns, Walls and Beams

All sizes of bars Slab & Joists

All sizes of bars Shells & Folded Plates

All sizes of bars All welded Wire Fabric (WWF)

50

40

30

Concrete exposed to interior, non-air-conditioned environments below grade (e.g. interior of underground manhole)All sizes of bars

75

Concrete not exposed or not in contact with soil or water:Columns and Beams

All sizes of bars Slab, Walls & Joists

All sizes of bars Shells & Folded Plates

16 mm and larger bars

All Welded Wire Fabric (WWF) and bars smaller than 16 mm dia.

40

25

25

20

B. The Table below defines minimum concrete cover measured from outermost rebar (tie-bar) that shall be provided for reinforcement of pre-cast concrete structures.

Royal Commission Guideline Specification, Section 03205, Table 3B

Concrete Exposure Minimum

Cover (mm)

Concrete in contact with soil; exposed to sea water; potable or treated water All sizes of bars 75Concrete exposed to weather:Walls and Slab Panels; All sizes of bars All other members All sizes of bars

30

50

Concrete exposed to interior, non-air conditioned environments below grade

All sizes of bars 50Concrete exposed to whether and

Page 33 of 98

Page 34: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

concrete not in contact with soil or water of any type:Slabs ,Walls and Joist; All sizes of bars

Beams and Columns; All sizes of bars

Shells and Folded Plates; 16 mm and larger smaller than 16 mm and all WMM

High Strength Polymer Grid All exposure conditions

25

30

2020

20

4.2.8 Stability

Overturning/Sliding:

RM/OM > Factor of SafetyRM – Resisting MomentOM – Overturning Moment

* The minimum safety factor against overturning and sliding shall be 1.50; The coefficient of friction shall be 0.40, unless specified otherwise in the Geotechnical Investigation Report.

* The minimum safety factor against Buoyancy shall be 1.20

Royal Commission Engineering Manual,Design Criteria, Structural, Chapter 9,Section 9.08 F.5

4.2.9 Slab on Grade

Slab on grade shall be designed in accordance with ACI 360R.

Royal Commission Engineering Manual,Design Criteria, Chapter 9, Section 9.08 G.1.a

4.2.10 Soil Bearing

Net allowable soil bearing capacity (NABC) for foundation design shall be as recommended by the geotechnical reports prepared by Independent Soil Testing Agency (geotechnical consultant). Those geotechnical reports are provided by Royal Commission.

Royal Commission Engineering Manual, Design Criteria, Structural, Chapter 9, Section 9.06

Royal Commission Guideline Specification, Section 02315

Page 34 of 98

Page 35: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.2.11 Corrosion Control

A. The atmosphere, soil, and water conditions in Jubail Industrial City are severely corroded. The design and construction of foundations, structures, piping, and equipment shall include competent corrosion mitigation measures to achieve long-term durability. Contractors are obligated to adopt all Royal Commission-issued corrosion related documents.

Royal Commission Engineering Manual,Design Criteria, Corrosion Control, Chapter 12

B. Steel at interior, dry environments where the steel is not embedded in or connected to concrete:1. Steel shall be cleaned in accordance with SSPC-

SP6 “Commercial Blast Cleaning” to produce a sharp angular surface profile as recommended by the paint manufacturer.

2. Steel shall receive one (1) shop coat of a two-component polyamide cured epoxy primer containing zinc phosphate corrosion-inhibiting pigment applied as per the manufacturer’s instruction to produce a dry film thickness of 75 microns (3 mils).

Royal Commission for Jubail and Yanbu,Corrosion Engineering Manual

C. Exterior steel, interior steel in wet environments, high-strength bolts and nuts, and washers for joints, anchor rods, nuts, and plate washers, and steel parts and accessories attached to or embedded in concrete:1. Steel shall be cleaned in accordance with SSPC-

SP8, “Pickling.”D. Field touch-up: Primer and galvanize coating at all field

weld areas and abraded areas and all interior and exterior high-strength bolts, nuts, and washers shall be cleaned and coated as follows:1. Steel cleaned as per SSPC-SP3 – Power tool

cleaning or as recommended by paint manufacturer.2. Steel shall receive one shop coat of a two-

component polyamide cured epoxy primer containing zinc phosphate corrosion-inhibiting pigment applied as per the manufacturer's instruction to produce a dry film thickness of 50 microns (2 mils).

E. Structural concrete in contact with soil, within 1 m of finished grade, or exposed to weather:1. Comply with Royal Commission Guideline

Specification Section 03310, Table 1C, and Type C35 as a minimum.

2. Reinforcing steel shall comply with Royal Commission Guideline Specification Section 03205, Fusion-bonded Epoxy-coated Reinforcing (FBECR).

F. Structural concrete formed against soil, including, but not limited to, slabs, footings, walls, and grade beams, shall be cast on a 50 mm minimum thick blinding slab

Page 35 of 98

Page 36: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

complying with Royal Commission Guideline Specification Section 03310, Table 1C, Type C20. The top surface of the blinding slab shall be waterproofed and the waterproofing protected prior to commencing any work on the structural concrete.1. Blinding slabs under slabs-on-grade shall be cast

on a 200 micron minimum thick polyethylene vapor retarder with overlapped and waterproofed-taped joints.

G. Structural concrete in contact with soil and located more than 1 m above the highest groundwater table shall be protected by coating with coal tar epoxy for all concrete surfaces to comply with RC Guideline Specification Sections 07100 and 07110.

H. Exterior, above-grade structural concrete surfaces shall be coated to comply with Royal Commission Guideline Specification Section 09660 and as follows:1. Primer (two-component, solvent-free, amine-cured

epoxy sealing primer, which shall be thinned on-site as per the manufacturer’s recommendation and requirements); and

2. Intermediate and top coats (two-component, solvent-free, amine-cured coal tar epoxy, each coat 200 microns minimum thick with the total coating to result in a dry-film thickness (DFT) of 400 microns minimum.

4.2.12 ENVIRONMENTAL IMPACTS

4.2.12.1 Energy EfficiencyBuildings shall be designed and constructed in accordance with the International Energy Conservation Code 2009. For more details refer to the mechanical and architectural clauses in part "A" of this design basis report (DBR).

4.2.12.2 Building thermal envelope insulationThe insulation shall be installed with applicable thickness for the areas covered and shall be of R-value in accordance with the code. For more details refer to the mechanical and architectural clauses in part "A" of this design basis report (DBR).

4.2.12.3 Moisture ControlThe mandatory requirement for moisture control in the buildings shall be in accordance with IECC 2009. Vapor retarder along with the insulation shall be installed wherever applicable.Joints and seams shall be sealed with caulking materials or closed with gasketing systems.

4.2.13 SAFETY

4.2.13.1 Existing Safety IssuesAll designs and project execution activities shall comply with the local safety standards applicable to this project.

Page 36 of 98

Page 37: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.2.13.2 Safety Improvement SolutionsOrientation seminars for all workers and equipment screening (of the Contractor) shall be initiated prior to commencement of work.  Daily ‘Tool Box’ meetings regarding work safety shall be held to update the personnel on the importance of safety issues.

4.2.14 DESIGN DEVELOPMENT APPROACH & STAGES

4.2.14.1 10% Design Conceptual StageThis Design Basis Report consist of concepts and philosophy of designs for structural discipline review, conceptual architectural plans and elevations for RC review and approval prior to development of 30% design stage.

4.2.14.2 30% Design Development StageSufficient information with drawings and preliminary calculations shall be submitted to demonstrate the adequacy of an integrated foundation and superstructure (walls, floor slabs, beams, columns, as appropriate) system. The submittal shall consist of:

Information on subsurface soils conditions, as established in the soil investigation report (refer to RC issued Geotechnical Investigation Report).

Preliminary design criteria indicating preliminary structural scope, applicable codes & standards, material specifications, loadings, load combinations, and other parameters to be used in the design calculations for the building (see Structural Design Criteria).

Preliminary calculations for the basic structural framing system, with representative calculations for foundation design (see Structural Design Calculation).

Drawings showing the framing system to be used, the foundation system proposed and alternatives considered, and the selected construction materials. These shall be sufficiently complete to define major structural dimension, spacing of columns, direction of spans, and configuration of foundation.

Typical structural details for foundations and major structural components (walls, floor slabs, columns, beams, as appropriate).

Typical structural details of selected important connections (wall-to-wall, wall-to-floor, beam-to-wall, beam-to-floor, beam-to-column, as appropriate).

Typical details of other features. Drawings and descriptions shall be completed with sufficient detail to illustrate the A/E’s concept relative to the availability of manufacturing capability and construction practices.

List of all the RC Guideline Specifications which will be used without any changes. Complete text of any proposed revision for a RC Guideline Specification. Approval

for such revision shall have been obtained based on explanation submitted with the 30% Design Development Documents.

Complete texts of other Sections of Specifications written by A/E not covered by the above (if there are any).

Index of structural drawings showing complete list of drawings including those anticipated for Final Submittal.

4.2.14.3 90% Design Development Stage Incorporation of all comments made at 30% Design Development Documents

submittal and will proceed with the Detailed Engineering and Design work to progress the Design to a 90%.

List of all the RC Guideline Specifications which will be used without any changes.

Page 37 of 98

Page 38: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Complete text of any proposed revision for a RC Guideline Specification. Approval for such revision shall have been obtained based on explanation submitted with the 90% Design Development Documents.

Complete texts of other Sections of Specifications written by A/E not covered by the above (if there is any).

Index of structural drawings showing complete list of drawings including those anticipated for Final Submittal.

This DBR document shall be finalized and brought to conclusion when all its 90% level outlines and preliminary information have been finalized and completed.

All the DBR attachments and Indices with all types of Engineering Calculations, Analysis and Sizing shall be completed and brought to conclusion.

The Structural Discipline shall incorporate all Review Comments of the RC for all documents submitted and resubmit to obtain Final Acceptance.

The 90% design stage submittal shall be an essentially completed set of Contract Documents.

4.2.14.4 100% Design Development Stage A/E shall incorporate or resolve all comments made by the RC at 90% design stage

in order for Contract Documents to qualify as 100% design stage completed package and submit such package as required by the Contract.

Page 38 of 98

Page 39: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.3 Conveying Systems

4.3.1 APPLICABLE CODES: ANSI A117.1 –2007 - Specification for making Building and Facilities

Accessible to and Usable to physically Handicapped People.

EN81-1:1998/SASO or ASME/ANSI A17.1 - Safety Code for Elevators and Escalator.

EN81/SASO or ASME/ANSI A17.20 - Inspector’s Manual for Elevators and Escalators and Moving Walks.

AISE - Specification for the Design, Fabrication and Erection of Structural Steel for Buildings.

APA American Plywood Association. AWS D1.1 Structural Welding Code. NEMA LD-3 High Pressure Laminates. NEMA MG1 Motors and Generators. NEC National Electrical Code. NFPA Fire Doors and Windows. SSPC (Steel Structures Painting Council) – Steel Structures Painting

Manual. UL 10B Fire Tests of Door Assemblies. EN81-70 Safety Rules for the Construction and Installations of Lifts - Part 70:

Accessibility to Lifts for Persons including Persons with Disability

4.3.2 APPLICABLE STANDARD: ASTM A36/A36M - Structural Steel. ASTM A139 - Electric – Fusion (ARC)-Welded Steel Pipe (Size 4 in. and

Over). ASTM A167 - Stainless and Heat-Resisting Chromium-Nickel Steel Plate,

Sheet and Strip. ASTM A336/A366M - Steel, Carbon Cold-Rolled Sheet, Commercial Quality. ASTM A446/A446M - Sheet, Zinc Coated (Galvanized by the Hot-Dip

Process, Structural (Physical Quality). ASTM B221 Aluminum - Alloy Extruded Bars, Rods, Wire, shapes and

Tubes. ASTM B221M Aluminum - Alloy Extruded Bars, Rods, Wire, Shapes, and

Tubes (Metric).

4.3.1 Guidelines and Standard Requirements Capacity and Loading:

GOVERNOR HOUSE ELEVATORS:ASME A17.1 Section 2.16.1.1 Minimum Load Permitted states that the rated load in kg (lb) for passenger elevators shall be based on the inside net platform area, and shall not be less than shown by Table 2.16.1.1. (See

Page 39 of 98

Page 40: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

attached sheet, page 1). Therefore as per table Table 2.16.1.1, the rated load of a net area of 2.05m² (from the standard) is 800 kg for elevator type Athe rated load of a net area of 1.76m² (from the standard) is 700 kg. for elevator type B

DAWA OFFICE:ASME A17.1 Section 2.16.1.1 Minimum Load Permitted states that the rated load in kg (lb) for passenger elevators shall be based on the inside net platform area, and shall not be less than shown by Table 2.16.1.1. (See attached sheet, page 1). Therefore as per table Table 2.16.1.1, the rated load of a net area of 1.76m² (from the standard) is 700 kg for elevator type B.

General: All elevators shall comply with Section 407 of ANSI A117.1 known as Accessible and Usable Buildings and Facilities.

Section 407.4.1 Car Dimensions states that inside dimensions of elevator cars shall comply with Table 407.4.1 which is further explained graphically by Figure 407.4.1 (see attached files, pages 2-3). The figure presents five (5) drawings of different inside dimensions and configurations of the elevator for more flexibility of the users. Drawing “D” or the third drawing is the most suitable for the project. It has a net inside area of 2.32 m².

General note:

To allow for variations in cab designs, an increase in the maximum inside net platform area not exceeding 5% shall be permitted for the various loads. Therefore a 5% addition to 2.32 m² will result in a 2.43 m² total area.

4.3.2 END-USER REQUIREMENT:

Building name

Number of

elevatorsLoad capacity

No. of

stops

Clear cab size

( mm)

Door size

( mm)Type

Governor’s House

2 For 8 – 10 Persons

2 1525 X 1525 915 A

2 For 6 – 8 Persons

2 1525 X 1525 915 B

Dawa Office

2 For 6 – 8 Persons

2 1525 X 1525 915 B

4.3.3 PROVISIONAL:The code and standards require that the elevator that suits the project requirement has to have a rated load of 800 kg., The 800 kg rated load therefore is enough to serve the needs of the end-user

Page 40 of 98

Page 41: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.3.4 SYSTEM DESCRIPTION

PASSENGER ELEVATORS MACHINE ROOM LESS TYPE

The selected type of elevator is a revolutionary system and based on the first major breakthrough in lifting technology .This system employs a smaller sheave than conventional geared and gearless elevators. The reduced sheave size together with a redesigned modern motor, allows the machine to be mounted within the hoist way itself -eliminating the need for a bulky machine room on the roof.

1. Rated Net Capacity: (800 KG)2. Rated Speed: 1.00 mps

3. Cab Internal Dimension 1.525 m X1.525 m 4 Door Type: Automatic Sliding Central Door Opening 915mm 5 Door Operation: Centre Opening 6. Number of Stops: 2 stops: Ground to first Floor7. Pit Depth: 1.40 meters (4.5 feet)8. Power Supply:

Phase- 380 Volts – 60 Hz (±5%)9. Lighting:

1Phase-220 volts – 60 Hz10. Machine Room Location Above Inside Lift Shaft Enclosures:

Round Handrail on Rear Wall Stainless Steel Clear Mirror On Full Width Half Height At Rear Wall Electric Fan (automatic on/off) Emergency Exit On Top Of Car

11. Structure wall Dimension (Width x Depth) (2.3 m x 3.2 m)12. Door control features:

Program door control to open doors automatically when car arrives at floor and with photo cell.

Provide QCC feature to close doors on car call. Nudging feature: If doors are prevented from closing for approximately ten

seconds because of obstruction, automatically disconnect door re-opening devices, close doors slowly sounding a buzzer until obstruction is cleared.

Provide group control for the passenger elevators.

Interconnect elevator control system with building fire alarm system. Elevator to return to main floor without stopping.

Provide emergency alarm bell to sound in case of activating alarm button on car control station.

Provide intercom telephone and dial phone connected to PABX inside elevator car.

Provide manufacturer standard serial transmission selective collective automatic operation as defined in EN81/SASO or ASME/ANSI A171.1

Set system operation so that momentary pressure of hall button at other landing dispatches car to that landing in correct sequence. Allow call registered by momentary pressure of hall button at any time and to remain

Page 41 of 98

Page 42: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

registered until car stops in response to that call at that landing

4.3.5 ELEVATOR SYSTEM LIST OF P & C SPECIFICATIONS: Section 01320 Construction Progress Documentation

Section01330 Submittal Procedures

Section 01410 Regulatory Requirements

Section01450 Quality Control

Section 01650 Product Delivery Requirements

Section01660 Product Storage and Handling Requirements

Section 03310 Structural Concrete

Section 03430 Pre-cast Structural Concrete

Section 04220 Concrete Masonry Units

Section 05520 Handrails and Railing

Section 07130 Sheet Waterproofing

Section 16140 Wiring Devices

Section 16150 Wiring Connections

4.3.6 SEE 8.0 APPENDICES (ATTACHMENT K):

Page 42 of 98

Page 43: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.4 Fire Suppression System

4.4.1 FIRE SUPPRESSION SYSTEMS REQUIREMENTS

Governor’s Office Building The building is mixed use group (A2),(B),(R) . See (IBC 303.1,304.1,310.1).

Dawah Office Building The building is group (A3),(B). See (IBC 303.1,304.1).

Patrol Police Office Building The building is group (B). See (IBC 304.1).

4.4.1.1 Codes Requirements:

A. Governor’s Office Building

Sprinkler system is required, see IBC 903.2.1, 903.2.1.2, 903.2.8. Sprinkler system shall be in accordance to NFPA13, 13R ,see IBC 903.3.1.1

IBC 903.3.1.2 Quick response or residential sprinkler to be provided in group (R) occupancy

see IBC 903.3.2 Stand pipe is not required where the floor level of the highest story above the

lowest level of fire department access is less than 9.144 m, see IBC 905.3.1 Portable fire extinguishers are required in the building, Refer IBC 906.1.

B. Dawah Center Office Sprinkler system is not required, see IBC 903.2.1,903.2.1.3. Stand pipe is not required where the floor level of the highest story above the

lowest level of fire department access is less than 9.144 m, see IBC 905.3.1 Portable fire extinguishers are required in the building, refer IBC 906.1.

C. Patrol Police Office Building Sprinkler system is not required as the building comes under Group B occupancy

classification Sprinkler system is not required in electrical and telecom rooms, refer IBC 903.2-

exception. Automatic Clean Agent Fire Suppression system is required in server room, refer

IBC904.10. Stand Pipe is not required as the building has only ground floor with building

height less than 9.144 m, Refer IBC 905.3.1. Portable fire extinguishers are required in the building, refer IBC 906.1.

Page 43 of 98

Page 44: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.4.1.2 Standards Requirements:

A. Governor’s Office Building Light hazard is existing in the building. See (NFPA13, A.5.2). Sprinkler design area = 1500 ft2 , Design density = 0.1 gpm/ft2, Spray sprinkler

(k factor = 5.65); See (NFPA 13, 11.2.3.1.1). Fire extinguishers shall be in accordance to NFPA 10. Water demand for sprinkler system shall be in accordance to (NFPA 13, 11.2.3).

B. Dawah Center Office Light hazard is existing in the building. See (NFPA13, A.5.2).

Fire extinguishers shall be in accordance to NFPA 10.

C. Patrol Police Office Building Fire extinguishers shall be in accordance to NFPA10. Automatic Clean Agent Fire Suppression system is required in Server room in

accordance with NFPA 2001.

4.4.1.3 Guidelines Requirements: Adhere to NFPA standards. (See RC Engineering Manual 6.07.D.1). Provisions for life safety shall be arranged in accordance with NFPA 101

(See RC engineering manual 6.07. B. 3. A).

4.4.1.4 End User Requirements:

Not applicable.

4.4.1.5 Other Systems Requirements Recommended by the AE:

Not applicable.

4.4.2 FIRE SUPPRESSION SYSTEMS DESCRIPTION

A. Governor’s Office Building Building area = 4785.5 m2 The fire suppression system shall include Automatic wet sprinkles system, spray

pendent sprinklers in all the building except residential portion, residential or quick response sprinkler shall be used.

Black galvanized, seamless steel pipes according to ASTM795 shall be used.4.5 kg portable dry chemical type (ABC) fire extinguishers shall be provided to cover the area.

Electrical room and Telecom room shall be provided with a carbon dioxide type UL rated (5B: C) portable fire extinguisher.

One riser shall be provided for sprinkler system where floor area is less than 4831 m2.

Fire water pump may not be required where the available pressureIs around 2.2 bar until conformation come from Marafiq .

The required fire water demand is Q =255.7 gpm, P = 29.5 psi ( for Governor’s Office Building)

Page 44 of 98

Page 45: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

B. Dawah Center Office Building area = 3008 m. 24.5 kg portable dry chemical type (ABC) fire extinguishers shall be provided to

cover the area. Electrical room and Telecom room shall be provided with a carbon dioxide type

UL rated (5B: C) portable fire extinguisher.

C. Patrol Police Office Building The fire suppression system shall include:

A 4.5 kg portable dry chemical type (ABC) fire extinguisher shall be provided to cover the areas as required.

Electrical room and Telecom room shall be provided with a carbon dioxide type UL rated (5B: C) portable fire extinguisher.

A Clean Agent Fire Suppression System will be provided in server room. The capacity of the cylinders shall be based on the calculations and recommendations of manufacturer.

CLASSIFICATION OF FIRE PROTECTION SYSTEM IN ALL FACILITIES

A. Governor’s Office Building

AREA NAMEFIRE PROTECTION SYSTEM

TYPE

STAND PIPE

CLASS

K-FACTOR

BUILDING GROUP

(IBC 2009)

OfficesAutomatic wet sprinkler

system - 5.6 BMeeting Rooms

Automatic wet sprinkler system

- 5.6 A2

Food Hall Guest hall

Automatic wet sprinkler system

- 5.6 A2

Bed Rooms, Living rooms

Automatic wet sprinkler system

- 8 R

Electrical Room,

Telecom Room

Carbon Dioxide Type Portable Fire Extinguisher

- - -

Page 45 of 98

Page 46: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

B. Dawah Center Office

AREA NAME

FIRE PROTECTION SYSTEM TYPE

STAND PIPE CLASS

K-FACTO

R

BUILDING GROUP

(IBC 2009)

OfficesDry chemical fire extinguisher

(ABC) - - BExhibition

hall, recreation center, library ,prayer hall

Dry chemical fire extinguisher (ABC)

- - A3

Electrical Room,

Telecom Room

Carbon Dioxide Type Portable Fire Extinguisher

- - -

C. Patrol Police Office Building

AREA NAMEFIRE PROTECTION

SYSTEM TYPE

STAND PIPE CLASS

K-FACTO

R

BUILDING GROUP

(IBC 2009)Prayer Hall, Work Hall, Meeting

Room, All General Offices, Kitchen,

Workshop, Archives

Dry chemical fire extinguisher (ABC)

- - B

Server RoomAutomatic Clean Agent

Fire Suppression System- - B

Electrical Room,

Telecom Room

Carbon Dioxide Type Portable Fire Extinguisher

- - -

Systems Components Description:

Water Supply: Fire Water System is to be tied-in to the Potable/Fire water loop around the building. Refer to civil site plans for fire and potable water drawings.

Page 46 of 98

Page 47: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Systems Operational Philosophy & Controls Description:

A- General.

A typical fire suppression water sprinkler system as installed in many buildings includes an array of individual fire sprinklers which are supplied with water through a main conduit and various branch conduits.

B- Operation.

The individual fire sprinklers are generally provided with a fusable link that melts when the ambient temperature reaches a predetermined level indicative of a fire.The melting of the member opens the fire sprinkler to spray water in order tosuppress the fire. Water damage is minimized: The individual fire sprinklers are provided with afusable link to be melt so that the spray of water will hopefully be limited to theregion of the building where the fire is present. In this way, the extent of waterdamage may be minimized.

B-1 alarm.

Such fire suppression systems also oftentimes have one or more alarms thatdetects the flow of water through the main conduit and to indicate that a fire has started. The alarm typically triggers an audible signal to warn occupants of the building that a fire has started and may also send an appropriate signal directly to fire department.

B-1-1 minimum water flow required to trigger alarm.

A flow of water, even from a single sprinkler is sufficient to move the member and trigger the alarm. Oftentimes, such water flow indicator alarms are electrically connected to an audible alarm single generator as well as to light panels to indicate the area in which the fire has occurred.

B-2 The community water supply system.

Fire suppression systems which include water sprinklers are oftentimes in fluid communication with the community water supply system or with whatever source of potable water is available in the vicinity. The water within the fire suppression system itself, however, can remain within the piping for a considerable period of time and is considered to be stagnant water.Note that water supply line to the building is provided by back flow preventer, Refer to civil site drawings for fire and potable water drawing.

B-3 The fire department.

In addition, a pump provided by the fire department will be connected to an inlet in communication with the fire suppression system in order to provide additional water and/or pressure in the event of a fire.

Page 47 of 98

Page 48: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.4.3 FIRE SUPPRESSION SYSTEMS DESIGN CALCULATION METHODS & TOOLS

Fire Water Building Total Demand:

Calculation: Demand (Pressure, flow) is required.Demand for sprinkler system requirement where k- factor for sprinkler head is 5.6: Q = 255.7 gpm, P = 29.5 psi (for governor’s offices)Note: the existing potable water network can deliver 255.7 gpm and therefore fire pump may not be Needed, where the available pressure is around (2.2 bar) and waiting conformation come from Marafiq.

Other Suppression Systems Total Demand:

Not applicable

Calculations to be prepared:

Min water flow rate.Min residual static pressure.

Methods & Tools to be used for all Calculations:

Hydraulic calculation methods see (NFPA 13, 11.2.3).Elite program as (tool).

4.4.4 FIRE SUPPRESSION SYSTEMS LIST OF P&C DRAWINGS TO BE IFC

Building drawings: General fire suppression system legend, symbols abbreviation and general notes. Standard details for fire protection system. Fire protection floor plans. Drawings to be prepared for Systems Coordination: Refer to site civil Plans for potable and fire water drawings.

4.4.5 FIRE SUPPRESSION SYSTEMS LIST OF P&C SPECIFICATIONS TO BE IFC

P&C Specifications by the AE and Issued for Construction: Not applicable

RC Specifications to be Amended by the AE and Issued for Construction: Not applicable, RC Specifications to be issued as-is by the AE for Construction.

RC Master Guidelines Specification:

Section 15375 Standpipe and hose system Section 15055 General requirements for piping systems. Section 15060 Hangers and supports. Section 15105 Pipes and tubes. Section 15110 Valves Section 15130 Pumps Section 15195 Testing of piping

4.4.6 FIRE SUPPRESSION SYSTEMS APPENDIXCode, Standards & Design Guidelines

See appendix L: Codes & standards.

Page 48 of 98

Page 49: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.5 Plumbing System

4.5.1 PLUMBING SYSTEMS REQUIREMENTS

4.5.1.1 Codes Requirements

Buildings are designed to the following code requirements. Saudi Building Code Requirements (SBC 701 version 2007) IPC International Plumbing Code -2009 Standards Requirements

Buildings are designed to the following standard requirements. ASSE American Society of Sanitary Engineering ASPE American Society of Plumbing Engineering AWWA American Water Works Association ADA American Disabled Association For Handicapped

4.5.1.2 Guidelines Requirements

The buildings have been designed as per Royal Commission Engineering Manual guideline requirements.

4.5.1.3 Building Functions Requirements

The buildings will be provided with adequate plumbing systems in accordance with the requirements of the latest editions of the International Building, Mechanical, Energy Conservation, Codes (IBC, IPC, & IMC) and ASSE, ASPE, AWWA standards to suit the building usage requirements, consisting of a potable cold and hot water system, sanitary drainage and vents system, condensate and storm drainage system, plumbing fixtures, specialties and equipments.

4.5.1.4 End Users Requirements

Should conform as per end user's requirements

4.5.1.5 LEED energy conservation measures

Requirements and measures for sanitation and hygiene are as follows: Low water consumption system will be used for flush valves and domestic water

faucets. Electric Water Heater using minimum KW rating. Centralized Solar Water Heater system

4.5.2 BUILDINGS ARCHITECTURAL DESIGN AND DATA

The Government Buildings Phase II project consists of the following buildings.

A. Jubail Governor Office BuildingThis is a two storey building, approximately 5,500 sq.m. ground & first floor located at Jubail Industrial City near Abu Ali road.

D. Dawa Office BuildingThis is a two storey building, approximately 2600 sq.m. ground & first floor located at Jubail Industrial City in Al-Kuds.

Page 49 of 98

Page 50: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

E. Patrol Police Office BuildingThis is a single storey building, approximately 1000 sq.m. ground floor located at Jubail Industrial City near the “Anas Bin Malik Jam’a Masjid at Al-Huwaylat”.

The “General Office Building for the Patrol Police Offices” shall be a site adaptation of the “Ministry of Interior Building under Contract 611-C27

4.5.3 BUILDINGS SYSTEMS REQUIREMENTS

The design of both drainage and water supply system will be in accordance with 2009 Edition International Plumbing Code (IPC), 2007 Edition ASHRAE Application Handbook for hot water demand and Royal Commission Plumbing Design Criteria.

4.5.4 OTHER SYSTEMS REQUIREMENTSThe building will be provided with adequate drainage and vent system for sanitary waste as well as storm water from the roof and adequate cold and hot water supply. Drainage and water supply system will be connected at the available site drainage and water supply system networks. A Water storage tank with booster a pumps system will be provided if in the event the discharge pressure of the available potable water supply line network at site not enough to satisfy system demand are. Otherwise direct connection could be done if flow and pressure are adequate enough to satisfy the system requirements. P.R.V will be provided if pressure at connection point with the available potable water supply line network at site exceeds 500 kpa.

Potable water line service connections to each building, which is connected to the available potable water supply line network at site, will be provided with a water meter in which the location is shown on civil water supply system network drawing.

The Plumbing System will be designed to provide the desired water supply system demand requirements and adequate sanitary drainage and vent system in all toilets, pantries, water supply and drainage in mechanical areas and in buildings with ablution areas as well as adequate drainage of storm water from the roof of the buildings.

4.5.5 DESIGN DEVELOPMENT APPROACH & STEPSThe following conceptual plumbing system configurations and descriptions are developed and submitted as part of the 10% design development documents and for this purpose the Architectural Option-1 for the Government Building, Phase ll has been used.

A. Jubail Governor Office Building: The building will be provided with sanitary drainage and vent system, water supply system in all public and private toilets, pantry and janitor’s rooms at ground and first floor of the building. Centralized Solar Water Heating system with Electric Water heater storage back-up with heating elements will be provided as a means of supplying hot water demand of the building. Water hammer arrestors will be provided at desired locations on both cold and hot water supply lines. Drains will be provided at roof of the building to collect storm water via horizontal drains connected to vertical leaders with splash blocks and discharged to walkways or in open areas.

Drainage lines will be provided with indirect waste line to collect condensate drains from the mechanical air conditioning units.

Page 50 of 98

Page 51: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Piping material will be in uPVC, Sched. 40 for the sanitary drainage vent and storm drainage system.

Piping material will be in uPVC, Schedule 80, cPVC, Schedule 80 for cold & hot water supply systems respectively.

B. Dawa Office Building : The building office area will be provided with sanitary drainage and vent system, water supply system in all toilets, pantry and janitor’s rooms at ground and first floor of the building. A Centralized Solar Water Heating system with Electric Water heater storage back-up with heating elements will be provided as a means of supplying the hot water demand of the building. Water hammer arrestors will be provided at desired locations on both cold and hot water supply lines. Drains will be provided at the roof of the building to collect storm water via horizontal drains connected to vertical leaders with splash blocks and discharged to walkways or in open areas.

Drainage lines will be provided with indirect waste line to collect condensate drains from the mechanical air conditioning units.

Piping material will be in uPVC, Sched. 40 for sanitary drainage / vent and storm drainage system.

Piping material will be in uPVC, Schedule 80, cPVC, Schedule 80 for cold & hot water supply systems respectively.

C. Patrol Police Office Building: This building is IFC and a site adaption from Contract no 611-C27 Ministry of Interior Office Building

4.5.6 PLUMBING SYSTEMS DESCRIPTION

4.5.6.1 Systems Overall Description;

The work to be performed under this task is to complete a detailed engineering design and prepare a full RFP package for Contract 611-C26 of Government Building, Phase ll in Jubail Industrial City as per Contract 610-T17 requirements.

In compliance with LEED Conservation measures the following Plumbing Equipments will be used:

Use low water consumption flush systems (flush valve for w.w.c, ). Use low flow wash lavatories faucets and shower heads . Use of Electric Water Heater of standard KW rating Use of Solar Water Heating System with Hot Water Storage and Electric Heating

element.

Page 51 of 98

Page 52: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Cold water system Cold water supply pipe service connection will be directly connected to the

nearest available potable water supply line network at site. Cold water supply will be provided for all the fixtures in public toilets, private

toilets, ablution areas, mechanical areas and in pantry rooms. A potable water line service connection connected to the available potable water

supply line network at site will be provided with water meter in which the location is shown on the Civil drawings.

A Water storage tank with booster pumps system will be provided if in the event the discharge and pressure of the available potable water supply line network at site is not enough to satisfy system demand. Otherwise direct connection will be done if flow and pressure are adequate to satisfy the system requirements.

Cold water supply pipes will be in uPVC Schedule 80 and hot water supply will be in cPVC, Schedule 80, according to SASO 14 and 15 or other approved. Water supply lines running in space used as return air plenums will be in copper pipe, type K.

The system incorporates water hammer arrestors. Water hammer arrestors will be provided at desired location on both cold & hot

water lines to absorb eventual shock, preventing damage to pipe, especially on pipe joints.

P.R.V will be provided if pressure at connection point with the available potable water supply line network exceeds 500 kpa.

Design of potable water system will be in accordance with 2009 IPC, Chapter 13 Appendix E, Table E103.3 (2) & 103.3(3) pages 130-131.

Hot water system Hot water will be provided for lavatories, pantry sink ablution faucets and service

sinks using individual electric water heaters for the Patrol Police Office Building. A Centralized Solar Water Heating System with Hot Water storage back-up with electric heating element will be provided for both Jubail Governors Office and Dawa Office Building.

Hot water supply will be in cPVC, Schedule 80, according to SASO 14 and 15 or other approved. Hot water supply lines running in space used as return air plenums will be in copper pipe, type K.

Insulations will be provide for both cold and hot water supply lines running above ceilings, shafts and exposed areas. Insulations on pipes embedded in concrete or in masonry is not required.

Hot water demand and heater design will be in accordance with 2007 ASHRAE Application Handbook , Table 10, Page 49.19

Sanitary Drainage and Vent System The sanitary drainage is designed as a one pipe system, where waste and soil

drainage are discharged in a common pipe. Vents will be an individual venting system connected to fixtures with P-traps. All secondary vents will be terminated through the roof.

Soil, waste and vent pipes including all fittings will be in uPVC, Schedule 40. All pipes penetrations in wall and slabs will be provided with pipe sleeves filled

with sealant. Where wall cleanouts are necessary, they will be in a stainless steel body

adaptable to the pipe with stainless steel cover plates and a vandal-proof centre screw secured to the cleanout plug.

Page 52 of 98

Page 53: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Floor cleanouts will be in a stainless steel body and frame with a round adjustable scripted secured stainless steel top, closure plug, and spigot outlet.

Drains will be adjustable, with a cast iron body and flashing collar, with protector top and with a polished bronze strainer head secured with a vandal-proof square hold grate.

Design of sanitary drainage system will be in accordance with 2009 IPC Chapter 7, Table 709.1 & 710.1(2), Pages 63-64,

Design of vent system will be in accordance with 2009 IPC, Chapter 9, Table 916.1, Page 75.

AHU, PACU and FCU will be provided with condensate drain and draining will be with indirect waste funnel connected to a pipe routed to nearest toilet .

Storm Drainage System The Building roof will be provided with roof drains including overflow drains to

collect storm water via horizontal pipes connected to vertical leaders. A splash block will be provided in all discharge points of vertical leaders. Storm drains will have free discharge to open areas or walkways.

Roof drains will be in cast iron body, combined flashing collar and cast iron dome, with a deep sump body.

Design of the storm drainage system will be in accordance with 2009 IPC, Chapter 11, Table 1106.2, Page 90.

The roof shall be designed for the maximum possible depth of water that will pond thereon as determined by the relative levels of the roof deck and overflow weirs, scuppers, edges or serviceable drains in combination with the deflected structural elements.

Scuppers shall be provided where the roof perimeter construction extends above the roof in such a manner that water will be entrapped if the primary drains allow build-up for any reason.

4.5.7 DESIGN CRITERIA The following are the Design Criteria for Plumbing system:

Sanitary Drainage system in accordance with RC Design Criteria:Diameter 100 mm and above (slope) = 1 %Diameter 100 mm and below (slope) = 2 %Vent pipe minimum diameter = 50 mmMinimum diameter of soil pipe = 100 mm

Water Supply system in accordance with RC Design Criteria:Maximum flow velocity in pipe = 1.5 m/sec.

Storm Drainage system in accordance with RC Design Criteria:Jubail rainfall intensity (10 minutes duration) = 127 mm

Page 53 of 98

Page 54: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.5.8 LISTS OF ALL CALCULATIONS TO BE PREPARED BY THE AE AND ISSUED

4.5.8.1 Potable Water Flow Load Calculations

See P-SC, Chapter-1 for Potable Water Loads Calculations Document

4.5.8.2 Plumbing Equipment Sizing Calculations

See P-SC, Chapter-2 for Solar Water Heater / Circulation Pump Capacities and Ratings Calculation Document

4.5.8.3 Sanitary Waste Discharge Load Calculations

See P-SC, Chapter-3 for Sanitary Waste Discharge Loads calculations Document

4.5.8.4 Storm Drainage Systems Calculations

See P-SC, Chapter-4 for Storm Drainage Pipes Sizing Calculation Document

4.5.8.5 List of Methods & Tools to be used for all Calculations

Fixture units (value) method will be used in design calculations on both potable water supply and sanitary drainage systems.

Hot water demand load calculations will be in accordance with ASHRAE Application handbook.

All water closets either with flush valve or flush tank will be provided with perennial hose spray.

4.5.9 PLUMBING SYSTEMS LIST OF P&C SPECIFICATIONS TO BE IN IFC STAGE

List all Applicable Plumbing P&C Specifications needed to be used as a part of the IFC Documents. This shall be selected from the RC P&C guideline specification after being revised, as necessary, to suit the project specification.

1. JUBAIL GOVERNOR’s OFFICE BUILDING

Ground floor plumbing potable water supply plan. First floor plumbing potable water supply plan. Plumbing potable water supply enlarged plan & isometric (sheet 1 of 2). Plumbing potable water supply enlarged plan & isometric (sheet 2 of 2). Ground floor plumbing sanitary drainage plan. First floor plumbing sanitary drainage plan. Plumbing sanitary drain enlarged plan & isometric (Sheet 1 of 2). Plumbing sanitary drain enlarged plan & isometric (Sheet 2 of 2). Roof floor plumbing potable water supply plan Roof floor plumbing sanitary drainage plan Solar System riser diagram. Pre-installation of utilities and foundation.

Page 54 of 98

Page 55: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

General schedule of plumbing fixtures & equipments.

2. DAWA OFFICE BUILDING

Ground floor plumbing potable water supply plan. First floor plumbing potable water supply plan. Plumbing potable water supply enlarged plan & isometric (sheet 1 of 2). Plumbing potable water supply enlarged plan & isometric (sheet 2 of 2). Ground floor plumbing sanitary drainage plan. First floor plumbing sanitary drainage plan. Plumbing sanitary drain enlarged plan & isometric (Sheet 1 of 2). Plumbing sanitary drain enlarged plan & Isometric (Sheet 2 of 2). Roof floor plumbing potable water supply plan Roof floor plumbing sanitary drainage plan Solar System riser diagram. Pre-installation of utilities and foundation. General schedule of plumbing fixtures & equipments.

3. PATROL POLICE OFFICE BUILDING

Ground floor plumbing potable water supply plan. Plumbing potable water supply enlarged plan & isometric(sheet 1 of 2). Ground floor plumbing sanitary drainage plan. Plumbing Sanitary Drain Enlarged Plan & Isometric (Sheet 1 of 2). Roof floor plumbing Sanitary Drainage Plan Pre-installation of utilities and foundation. General schedule of plumbing fixtures & equipments.

A. Common drawing General,symbol,legend & Abbr. General plumbing installation details.

The A&E will provide and issue for construction, as necessary, any additional P&C specification, in the same format as those of the Royal Commission, to support any systems, products, and/or components included in the design.

Chapter 1 General Design Requirements Chapter 2 Environmental Chapter 5 Water and Wastewater Chapter 6 Mechanical Chapter 12 Corrosion Control

B. New RC Standard Specifications SECTION 01450 Guideline Specification for Quality Control SECTION 10810 Guideline Specification for Toilet Accessories SECTION 15051 Guideline Specification for Materials and Methods SECTION 15055 Guideline Specification for General Requirements for

Piping Systems SECTION 15060 Guideline Specification for Hangers and Supports SECTION 15105 Guideline Specification for Pipes and Tubes

SECTION 15110 Guideline Specification for Valves SECTION 15140 Guideline Specification for Domestic Water Piping

Page 55 of 98

Page 56: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

SECTION 15145 Guideline Specification for Flushing, Cleaning and Treatment of Water Piping

SECTION 15150 Guideline Specification for Sanitary Waste and Vent Piping

SECTION 15160 Guideline Specifications for Storm Drainage Piping SECTION 15480 Guideline Specifications for Domestic Water Heaters SECTION 15410 Guideline Specifications for Plumbing Fixtures

C. A/E Prepared Specifications SECTION 15430 Guideline Specifications for Electric Drinking Fountain

4.5.10 PLUMBING SYSTEMS APPENDIX

To be included at 30% design stage.

4.6 HVAC System4.6.1 Buildings Functions Requirements:

The building shall be provided with Heating, Ventilation and Air conditioning system in accordance with the ASHRAE Standards, ASHRAE Handbook and Royal Commission HVAC Design Criteria.

HVAC System shall be designed to provide the desired indoor and environmental condition for efficient operation of building facilities. Each space shall be provided with heating and cooling facility with temperature control. Where required, rooms shall be provided with supply air with around 5% positive pressurization to eliminate the effect of infiltration into the building.

The toilets and pantries shall be provided with heating and cooling system. The toilets and pantries shall be provided with 100% exhaust with negative pressurization in order to avoid ex-filtration and odor spreading to other rooms.

4.6.2 Other Systems Requirements: Use of energy efficient air conditioning units with high EER not less than 10.5. Use of high efficiency electric motors in all motorized HVAC equipment. Use of comprehensive PLC/DDC energy management system for the control

of all HVAC systems. Use of variable frequency drives (VFD) to allow fans to operate at reduced

speed depending on a load. The air distribution system shall be a galvanized, metal ductwork system. The

system shall be sized using equal friction method and in accordance with Royal Commission guide lines. To minimize pressure drop, long radius elbows shall be used.

Page 56 of 98

Page 57: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.6.3 Design Development Approach & Steps

For Construction and Expansion of Service Facilities Buildings the following conceptual HVAC system configurations and descriptions are developed and submitted as part of the 10% design development documents and for this purpose Architectural Option-1 for Construction and Expansion of Service Facilities Buildings has been used.

A. Jubail Governor Office Building The following two (2) options are proposed for the HVAC system for Jubail Governor Office Building.

Option-1: Roof Top Packaged Units

The building shall be provided with (3) roof top packaged air conditioning units located on the roof. The HVAC system is to provide conditioned air to satisfy the return air temperature set point all year round on each zone. Heating will be activated to satisfy zone set points during winter. In all cases the outdoor air entering the building shall be controlled based on the design outdoor air flow. The exhaust system serving these zones shall be roof mounted up-blast exhaust fans.

Option-2: DX Central Ducted Split Units

The building shall be provided with (3) Central ducted split units. The building zones shall be served with VAV (variable air volume) system. The HVAC system is to provide conditioned air to satisfy the return air temperature set point all year round on each zone. Heating will be activated to satisfy zone set points during winter. In all cases the outdoor air entering the building shall be controlled based on the design outdoor air flow. The exhaust system serving these zones shall be roof mounted up-blast exhaust fans.

B. Dawa Office Building The following two (2) options are proposed for the HVAC system for the Dawa Office Building.

Option-1: Roof Top Packaged Units

The building shall be provided with (4) roof top packaged air conditioning units located on roof. The HVAC system is to provide conditioned air to satisfy the return air temperature set point all year round on each zone. Heating will be activated to satisfy zone set points during winter. In all cases the outdoor air entering the building shall be controlled based on the design outdoor air flow. The exhaust system serving these zones shall be roof mounted up-blast exhaust fans.

Option-2: DX Central Ducted Split Units

The building shall be provided with (4) Central ducted split units. The building zones shall be served with VAV (variable air volume) system. The HVAC system is to provide conditioned air to satisfy the return air temperature set point all year round on each zone. Heating will be activated to satisfy zone set points during winter. In all cases the outdoor air entering the building shall be controlled

Page 57 of 98

Page 58: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

based on the design outdoor air flow. The exhaust system serving these zones shall be roof mounted up-blast exhaust fans.

C. Patrol Police Office Building: A single option is proposed for the HVAC system for Patrol Police Office Building as it is a site adaptation of the “Ministry of Interior Building under Contract 611-C27

Option-1: Roof Top Packaged Units

The building shall be provided with (2) roof top packaged air conditioning units

located on roof. The HVAC system is to provide conditioned air to satisfy the return air temperature set point all year round on each zone. Heating will be activated to satisfy zone set points during winter. In all cases the outdoor air entering the building shall be controlled based on the design outdoor air flow. The exhaust system serving these zones shall be roof mounted up-blast exhaust fans.

HVAC System Load Description (SLD):

4.6.4 DESIGN CRITERIA

The following is the Design Criteria for the HVAC system:

Outdoor design conditions as per Royal Commission Mechanical Design Criteria, Chapter 6, and Section 6.17.B.2

Summer

Dry bulb = 460C

Wet bulb = 30oC

Daily Range = 13oC

Building No. Building/Facilities Area(M2) HVAC System Approximate Capacity(TR)

1 Jubail Governor Office Building

5600 Package or DX Central ducted Split unit

300

2 Dawa Office Building 2600 Package or DX Central ducted Split Unit

200

3 Patrol Police Office Building

1000 Package or DX Central ducted Split Unit

50

Page 58 of 98

Page 59: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

WinterDry bulb = 5oC

Indoor design conditions as per Royal Commission Mechanical Design Criteria, Chapter 6, and Section 6.17.B.3

Summer

Dry Bulb = 24oC +1

Relative Humidity = 45%

Winter

Dry Bulb = 2oC

4.6.5 LIST OF HVAC ENGINEERING CALCULATIONS

Methods and tools to be used in performing the Engineering Calculations and sizing are:

Cooling, humidifying, dehumidifying, and heating load calculations:

Elite Software Program (CHVAC Version 7.01.108)

Design tools Duct Sizer Version 6.4

4.6.6 List of all Methods & Tools to be used for all Calculations

Elite software program (CHVAC7.01.108) Commercial HVAC load calculation program shall be used for the heating and cooling load calculations. The outputs from Elite Software shall be utilized for the following:

Air quantities to spaces with psychometrics.

Packaged Unit sizing and coil selections.

Electric heater sizing using the winter heat loss.

The following data shall be required to begin with HVAC calculations:

Information about each building, it’s environment and suitable type of HVAC equipment shall be gathered. This step involves extracting data from building plans, evaluating building usage and studying HVAC system needs.

Construction material data for walls, roof, windows, doors, exterior shading devices, floors and interior partitions between conditioned and non-conditioned spaces.

Building size and layout data including wall, roof, window, door and floor areas, exposure orientations and external shading features.

Internal load characteristics determined by levels and schedules for occupancy, lighting systems, office equipment, appliances and machinery within the building.

Page 59 of 98

Page 60: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.6.7 HVAC System List of P&C Guideline Specifications

The A/E will list all HVAC P&C Specifications to be used as a part of the IFC Documents. This list shall be selected from the RC P&C guideline specifications after being revised, as necessary, to suit the project specifics.

The A&E shall provide, as necessary, any additional P&C specification, in the same format as those of the Royal Commission, to support any systems, products, and/or components included in the design.

Page 60 of 98

Page 61: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Section No. Guideline Specification Title

15051 Materials and Methods

15055 General Requirements for Piping Systems

15060 Hangers and Supports

15065 Equipment Installation

15070 Mechanical, Sound, Vibration and Seismic Control

15075 Mechanical Identification

15080 Mechanical Insulation

15085 Welding, Brazing and Soldering of Piping

15105 Pipes and Tubes

15110 Valves

15120 Piping Specialties

15145 Flushing, Cleaning and Treatment of Water Piping

15180 Heating and Cooling Piping

15195 Testing of Piping

15720 Air Handling Units

15730 Unitary Air conditioning Equipment

15810 Ducts

15820 Duct Accessories

15830 Fans

15840 Air Terminal Units

15850 Air Outlets and Inlets

15860 Air Cleaning Devices

15910 Direct Digital Controls

15915 Electric and Electronic Controls

15935 Building Systems Controls

15955 Testing, Adjusting and Balancing

Page 61 of 98

Page 62: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.6.8 HVAC systems appendix

To be attached at 30% design stage.

4.6.9 Systems Conceptual Single Diagram

To be attached at 30% design stage.

4.6.10 Typical Systems Operational Philosophy

See submitted control diagram drawings which include system operational philosophy and control sequences in 30%.

4.6.11 Sample Systems Catalog Cut-sheets

Not Applicable

4.7 Electrical System

4.7.1 Scope of Work

The scope of work shall include a complete detailed engineering design and prepare action of a full RFP package for site utilities infrastructure.

Detailed engineering design shall include medium voltage (MV) power distribution system network interface, new substations consisting of pad distribution transformer, RMU, interface low voltage (LV) distribution panel and metering system, exterior lighting system and all other necessary requirements to provide power supply for the proposed Operation and Maintenance Department Building as complete functioning facilities.

The drawing numbering system shall be in accordance with RC procedure JMP-0120202 and G/L-G 1004 Revision F and Engineer manual.

The drawings and documents mentioned below shall be supplied for each subsystem, package unit, for detailed system parts and for equipment, where applicable:

Specifications

General layout

Building layout

Dimension outline and electrical drawings

Equipment layout and arrangement drawings

Single line diagrams (power and fire alarm system)

Wiring and terminal connection drawings

Material and equipment lists and schedules

Short circuit and voltage drop calculations and calculation sheets,

Equipment and instruments characteristics, data sheets and diagrams,

Cable list, cable tray layout and cable route.

Page 62 of 98

Page 63: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Grounding plot plan grounding and lightning protection layout.

Electrical installation drawings within buildings.

Other drawings and documents as needed.

4.7.2 DESIGN CRITERIA

4.7.2.1 LV Power Distribution System

Nominal voltage system to the facility shall be 400/230V, 3Ph, 4W, 60Hz, with provision to accommodate special requirements, as necessary.

Electrical load estimation shall be carried out as per SEC standards criteria for demand factor requirements to estimate circuit breaker ratings and unit substation capacity.

4.7.2.2 Wires and Cables

For all internal wiring circuits controlled from panel boards, generally XLPE insulated or THHN single core copper conductor, 90°C maximum operating temperature, heat moisture, flame and oil resistant, rated 600/1000 Volt shall be used. The wires shall be laid in EMT or PVC conduit. Sizing of cable shall include 20% spare capacity. Cable ampacity, electrical characteristics, and insulating thickness shall conform to the National Electric Code (NEC).

Minimum required cross section:

Power circuits 4 mm²

Lighting, control and measuring circuits 4 mm²

Auxiliary power circuits 4 mm²

The control, signal and alarm circuits must be wired separately and protected by individual MCB’s within the various cabinets.

All wires and cables shall have copper conductors. Cable shall be manufactured in accordance with IPCEA standards.

Ground cables shall be soft drawn, tinned bare copper for direct buried and PVC insulated where installed exposed or in conduit/raceways. Minimum size shall be 4mm².

Cable color coding shall be used consistently throughout the electrical system installation.

4.7.2.3 Conduit

Conduit shall be run concealed, unless in mechanical rooms or in remodeling projects involving existing wall construction that does not allow for recessed conduit and boxes

Conduits shall be independently supported; conduits shall not be supported from ductwork. Vertical feeder conduits and bus duct shall be independently supported at each floor level

Electrical metallic tubing (EMT) shall be installed in ceiling plenums or built –up walls, minimum size shall be 20mm diameter. EMT shall comply with the NEC requirements.

Page 63 of 98

Page 64: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Rigid steel galvanized conduits shall be used in exposed locations and where embedded in concrete, minimum size shall be 20 mm diameter. Where in contact with soil, it shall be PVC coated and minimum size shall be 20 mm.

Conduits used for underground main cable runs shall be PVC, extra strength, type “DB” when direct buried and type “EB” when concrete encased. These shall be 160 mm or 110 mm diameter as required.

Flexible, metal oil-tight conduits shall be used for connection of necessary lighting fixtures, motors and equipment subject to vibration. Minimum conduit size shall be 12 mm diameter.

Floor outlets cable/wiring, where required, shall be run in cable duct.

Outlet junction boxes and other conduit fittings shall be in accordance with NEC, UL and other applicable codes and standards.

4.7.2.4 Cable Trays

Cables and cable trays are part of the cable management system. Cable tray cables are quality products and have withstood the rigors of severe environments. They are protected by either a metal or plastic armour jacket over individual conductor insulations. They can be rated for outdoors, indoors, corrosive areas, hazardous locations, high electrical noise and vibration areas. They should be U.L. listed and generally marked as cable tray rated. They are tested for flammability and other mechanical and temperature tests that allow them to be U.L. listed.

All cable trays shall be selected as per NEMA VE-1 standard requirement. They shall be provided in accessible area and maintainable locations such as under acoustic tile suspended ceilings, as required by the design. Cable trays will not be provided in plenum areas. They will be sized in accordance with NEC Article 392 (Cable Trays) and shall consider the required bending radius of the largest cable on the cable tray.

The types of wiring methods permitted in cable trays are listed in NEC Section 318-3 along with the corresponding NEC article that describes the conductions of use for that particular type of cable. Cables should be applied according to the environment they are located, for instance, hazardous areas, plenums, outdoor (sunlight rated), indoor, corrosive areas, etc.

4.7.2.5 Panelboards

For all panel boards, all pertinent information including the voltage, amperage, and minimum system (i.e. individual component) short circuit rating shall be specified.

Interrupting capacity of circuit breakers in switchgear or panel boards shall be suitable for the power system feeding them.

Describe selection, sizing and installation criteria as per National and All panel/switch boards shall be factory assembled. “Dead front” type compatible with the available fault level.

Main distribution panel/switch boards (MDP) shall be rated at 400/230 Volts, 3-Phase, 4 wire and shall have ground bus and plug in type thermal magnetic trip

Page 64 of 98

Page 65: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

circuit breakers. Circuit breaker installed outdoor shall be ambient compensated to 50°C.

Surface mounted Panel/Switch boards shall be used in industrial zones.

Enclosures for Panel/Switch boards installed indoor shall be general-purpose type equivalent to NEMA 1, and those installed outdoor shall be dust-tight and water tight equivalent to NEMA 4X.

Panel/switchboard shall have at least 20% of their circuit breakers spare for future use.

Circuit breakers rated 100 ampere and above shall be adjustable trip with built-in ground fault protection.

Panel/switch boards shall be effectively grounded and labeled with designated identification name and number with circuit directory indicating circuit numbers and connected loads.

The cubicles and panel/switchboards for the power supply system shall be installed in the rooms with sufficient space for cable connection, operation and maintenance.

All cubicles and panel/ switchboards shall be erected on base frames which are either embedded in the concrete floor/screed or incorporated in the double floor construction. If not specified otherwise the horizontal tolerance of the frames shall not exceed +/-1.5 mm over a length of 5 m.

4.7.2.6 General Purpose Receptacle

General-purpose Receptacle outlets will be provided as required and shall be limited to eight per branch circuit. The general purpose receptacle shall be 13 Amp 250 volts flat pins as per SASO standard. The general-purpose receptacles are in addition to the dedicated outlets for specific equipment such as computers, office equipment and others.

Circuit loading shall be estimated on the basis of 180 VA for each outlet, unless specific conditions necessitate other loading.

All socket outlets in wet areas, outside areas and kitchen shall be protected with earth leakage circuit breakers ELCB or RCD. The sockets in the outside shall also be weather-proof.

Location of receptacles shall be coordinated with the equipment and furniture arrangements.

Special power receptacles for three phase 400 Volts or single phase 230 Volts shall be provided wherever required.

4.7.2.7 Power supply to HVAC Equipment

The electrical services design shall include the electrical requirements for all HVAC equipment and controls. Protective devices and cable sizes for HVAC equipment shall be sized in accordance with NEC, Article 440.

HVAC sub-circuit and control wiring shall be in accordance and coordination with Mechanical Discipline. The whole of the electrical services for HVAC

Page 65 of 98

Page 66: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

equipment shall be in accordance with NFPA 70 (NEC Code) and other relevant NFPA Codes.

4.7.3 LIGHTING

4.7.3.1 Interior Lighting System

Complete interior lighting systems consisting of conduit installation, wiring, selection of lighting fixtures and switches will be provided. Illumination levels for interior lighting shall be in accordance with the IES handbook recommendation.

Lighting fixtures shall consist of fluorescent lamp, metal discharge lamps and compact fluorescent lamps are to be used.

Lighting fixtures will generally be distributed on the ceilings in a regularly repeated separated arrangement. Lighting fixtures with high intensity discharge lamps shall be used in high ceiling areas.

All lighting fixtures provided for T5 (14 Watts and 28 Watts) shall operate at 230 volts. High power factor ballasts and electronic ballasts shall be used to correct power factor to minimum 0.95. All lighting fixtures shall be a standard product from an established manufacturer. Lighting fixture types and lamps shall be selected according to the RC guideline.

The illumination levels will comply with illuminating engineering society handbook (IES) as well as RC Engineering Manual recommended average values.

4.7.3.2 Emergency and Exit Lighting

Emergency lighting shall be in accordance with NFPA 101 and NFPA 70 specifications to light primary escape routes during lighting failure.

Emergency lighting with built-in solid state charger and battery pack capable of 90 minutes of operation shall be provided in each building and inside the mechanical and electrical rooms maintaining minimum illumination level.

Exit doors shall be provided with exit lights. Hallways, corridors, and egress shall be provided with exit lights with the word “EXIT” and its Arabic equivalent clearly visible.

Emergency and exit lighting fixtures with battery packs units shall be provided at selected locations as per RC guideline requirements. The number and locations of emergency and exit lighting fixtures shall be based on calculations in accordance with the Illuminating Engineering Society of North America handbook (IESNA) recommendations and the functional requirement. These lights shall be ceiling or wall-mounted. Exit lights shall be provided with or without directional arrows as required.

Page 66 of 98

Page 67: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.7.4 GROUNDING

System Grounding

The grounding shall be designed based on RC Design Criteria and Guideline Specifications and as per the latest edition of the National Electrical Code. A separate grounding conductor shall be provided in all lighting, power circuits, cable tray, and telecommunication equipment.

A grounding system shall be provided for all buildings. The entire facility shall be securely connected with minimum practicable resistance to the common ground grid.

The maximum resistance to ground from connection point to any facility will not exceed 5 ohms.

Equipment grounding conductor shall run in raceways. The equipment grounding conductors shall have green or green with yellow stripes color insulation.

4.7.5 FIRE ALARM AND DETECTION SYSTEM

The building will be provided with a fire alarm system in accordance with NFPA 70, NFPA 72, NFPA 101, BS 5839, IBC and SBC.

Fire detectors should be selected based on the burning characteristics of the materials present and the nature of location they will be used to protect.

Some detection systems may be provided in excess of code to protect special hazards or critical equipment. In these cases, the typical operating characteristics of each detector must be compared to the proposed application. The quantity of fuel, ignition sources, size of the room, value of the contents, costs of the detectors and ambient conditions (temperature, humidity, corrosion, HVAC, etc.) must all be considered. Automatic detection systems will be designed and installed as required by codes, after establishing the building and occupancy type in accordance with NFPA 101.

After the detector type has been selected, the detectors can be located within the space. The manufacturer’s data and Underwriters Laboratories listed spacing can be used as a starting point. The nominal rated spacing was developed using a smooth ceiling 5 m high and should be adjusted for other conditions. NFPA 72E specifies requirements for locating detectors on ceilings with joists beams and other obstructions.

Each building for which a fire alarm system is to be provided shall have an independent system. Fire alarm system shall be comprised of the following:

An addressable microprocessor-based fire alarm control panel.

A microprocessor-based repeater fire alarm panel. A custom-made graphic annunciator panel for the building (since it has

more than 3 zones). Conventional or intelligent and addressable detectors, manual stations,

bells, horns and strobes.

Page 67 of 98

Page 68: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

The system shall be electrically supervised against short, ground and open wiring faults in the detection circuit, alarm circuit, alarm and trouble relay coils, and extinguishing system release circuit (if any).

The system shall be capable of being expanded at any time and shall have no limitations as to the number of heat detectors or manual stations per zone. The system shall be capable of having ionization, thermal, photo-electric and flame detecting devices connected across the same set of wires. Also the system shall contain duct smoke detectors, flow switches, and tamper switches. The system will be interfaced with the HVAC system and fire-fighting system.

The alarm and trouble condition for each building shall also be relayed, through a set of controls to the main fire alarm annunciator panel where provided, and to the central fire station.

The system design shall ensure that an alarm signal from any manual station (fire condition) overrides a trouble signal (fault condition).

The system shall be interfaced thru modem communication between each monitored building and the remote fire station department via LAN / WAN network system.

4.7.6 LIGHTNING PROTECTION SYSTEM

The completed lightning protection system shall comply with the latest issue of the following standards and form a part of this specification.

CODE DESCRIPTIONNFPA 780 Standard for the Installation of Lightning Protection

SystemUL 96A Installation Requirements for Lightning Protection

SystemSBC 401 Saudi Building Code for Electrical Requirements

Design criteria for buildings lightning protection systems shall to conform to the Rolling Sphere and Design Basic Methods of NFPA 780 code.

Air terminal shall be located within 600 mm of roof edges and outside corners of protected areas. Air terminal bases shall be securely fastened to the structure in accordance with the specified standard including the use of an adhesive that is compatible with the surface which it is to be used on or stainless steel fasteners.

Each down conductor shall be terminated at a grounding electrode dedicated to the lightning protection system. The down conductors shall be attached permanently to the grounding electrode system by bolting, brazing, welding or high-compression connector listed for the purpose, and clamps suitable for direct burial. Bonding of the direct buried ground cable to ground counterpoise shall be accomplished by exothermic welding system.

4.7.7 DESIGN CALCULATIONS

All the design calculations and parameters for sizing and capacity of selected electrical equipment/materials have been taken into consideration, the design calculations generated are based on the given below computer based software programs.

Page 68 of 98

Page 69: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Ecodial 3.4L: Software for short circuit and voltage drop calculationsDialux evo 1: Software for lighting illumination calculation

Manual method for the design calculations shall also be done based on the SEC, NFPA-72 and RC requirements.

4.7.8 ENVIRONMENT AND SAFETY

Unless otherwise specified, the equipment/material for the electrical power supply system shall be designed and constructed for operating at their standard ratings for continuous operation against a salt laden climate, sand and sand storms and a severely corrosive environmental coastal area.

4.7.8.1 Indoor conditions

For indoor rooms, general air conditioning or ventilation will be provided. The temperatures in the various rooms depend on the room classification for air conditioning and ventilation. In case of failure in the air conditioning or ventilation system, the power supply equipment shall be suitable for continuous full load operation.

Air conditioned buildings 25 °C Buildings where no air-conditioning is provided 40 °C Areas with possible water sprays Pump house Valve shafts Flow control shafts Equipment and instrument shafts Areas with aggressive atmosphere

4.7.9 SEC-EOA COORDINATION AND APPROVAL

The design will be based on the latest RC specification, RC Engineering Manual requirements, RC Standard Drawings, latest National Electrical Code, Contract specifications, and Saudi Electricity Company (SEC) standards.

Electrical design development work for the power interface is being carried out with the necessary consultations with SEC. After incorporating all SEC comments based on 30%, 90% and 100% submittals, final IFC drawings shall be submitted to SEC for stamping and these shall be submitted to RC along with IFC submission.

Page 69 of 98

Page 70: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

4.8 Telecommunication System4.8.1 Introduction

The design criteria for telecommunication systems for the proposed buildings under this contract (as listed below), is based on latest RC specification, RC Engineering Manual requirements, latest National Electrical Code (NEC), contract specifications and Saudi Telecommunication Company (STC) standards.

4.8.2 Scope of telecom work

The telecom work shall include the following systems:

Telephone SystemData systemNetwork based video surveillance CCTV SystemIP-clock systemCommunity Antenna Television (CATV) SystemPublic Address (PA) SystemAudio/Visual systemIP-Based Door Access Control System Codes and standards

4.8.3 Telephone System

For all buildings under this contract:

New proposed outdoor telephone cable 0.63 mm² conductors, non-armoured polyethylene jelly filled cable, shall be installed inside proposed PEC duct of 110 mm outside diameter to connect proposed MDF at main telecom room of each building. The indoor telephone cable for standard telephone sets shall be a 3 pair CAT 3 UTP cables.

An intermediate distribution frame (IDF) with terminal bock will be provided in the telecom room of each building for distribution purposes. Telephone outlets shall be provided in general offices, work stations, and any other areas requiring telephone service.

The telephone system cabling will be adjoined in the cable tray through PVC conduits on embedded installations and EMT conduits on concealed installations up to the MDF or IDF. Cable trays will be provided for all the horizontal CAT 3 UTP cabling. Plenum-rated cables are to be used when installed in cable trays.

A complete telephone network and wiring layouts (including all accessories) are required to have a complete working system that will be ready to provide telephone service in the premises.

4.8.4 Data System

For all buildings under this contract:

A new data system will be provided for all proposed buildings under this contract by adding new data terminal cabinets, Ethernet (Edge) switches, WLAN Access Point to covering all proposed buildings as per their plan to provide a complete data system solution as per the end user requirements.

The proposed buildings under this contract shall be connected to the RC MAN-PHASE II data network through outdoor fiber optic cable single mode and shall be terminated at the proposed fiber patch panels at the building telecom room.

Page 70 of 98

Page 71: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

The proposed data network shall provide a complete functional LAN and WLAN system including but not limited to Data cabinets, Ethernet switches, Fiber/UTP patch panels and all other data equipments.

The data network system shall consist of data outlets with RJ-45 modular jacks and face plates. These outlets shall be connected to UTP patch panels through CAT 6, 4-pair UTP cables, and with a maximum horizontal run of 90 meters. LAN cabling shall be adjoined with the cable tray through PVC conduits on embedded installations or EMT conduits on concealed installations up to the UTP patch panels.

Cable trays shall be provided for all the horizontal CAT6 UTP cabling and also for the fiber optic cables inside each building.

4.8.5 Wireless local area network (WLAN)

For all buildings under this contract:

Wireless LAN communications are based on the use of radio signals to exchange information through an association between a wireless LAN card and a nearby access point.

The buildings under this project will have wireless access network connectivity by proposing many wireless access points to be distributed strategically inside the proposed building to cover all areas and halls as shown in the design drawing.

Wireless LAN design will fulfil the following main criteria:

Minimal interference

Maximum security for data transfer

Provision of wireless access points inside the building

Support of the IEEE 802.11n and IEEE 802.11g wireless standard as a minimum for all WLAN hardware including access points.

Support of the 128-bit Wired Equivalency Protocol (WEP) by the wireless access points.

Restricting access to the network must be available so that only authorized people can use it; unauthorized users will be prevented from reading confidential data appearing on the network.

4.8.6 Network-based video surveillance CCTV System

For buildings under this contract:

The design covered under this section will include a complete IP-based video surveillance system using IP-cameras, data switch with Power over Ethernet (PoE) capability, computer workstation with video management software and enough storage and screens for monitoring.

For outdoor applications, fixed dome IP-cameras shall be located in appropriate places to give the field of view covering the required sector. The IP-camera shall be capable of network video function. The camera's movement is easily controlled via a computer connected to the network. The system shall use Motion JPEG or MPEG-4 type of compression for the digital video.

Page 71 of 98

Page 72: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Fixed dome IP-cameras can be fixed to only look at one specific view or it can be movable using panning, tilting and zooming (i.e., moving left and right, up and down, zoom-in/zoom-out). Its location will be in corridors in one direction with its specific coverage area according to its specifications. The cameras coverage is between 10 meters to 20 meters.

IP-cameras are distributed in proper locations inside and outside the building to cover all entrances and exits of the proposed building as shown in the design drawings.

A network video recorder shall be installed inside the main data cabinet in the telecom room at the proposed RC Administration Building.

CCTV workstations with monitoring screens and CCTV management software shall be installed at proper locations inside each building or any other proper location as per end user requirements.

4.8.7 IP clock System

For all buildings under this contract:A wired centralized IP-master clock system will be provided for all proposed buildings. The clocks will be distributed strategically at several locations within the building. The clock will be IP (12” POE analogue clock) and all IP-clocks will be selected according to functional requirements.

Once clock is connected to the network and power is applied, an assented IP address assigned to it, each clock will search the local area network for time servers. The correct time will display within a few minutes of obtaining a time server clock.

An RJ-45 Ethernet jack will be available at the back of each clock for connecting to the Ethernet network cable. CAT-6 cabling shall provide power and data to each IP-clock based on the Power over Ethernet (PoE) feature in the Ethernet switch.

4.8.8 CATV / Satellite System:

For Jubail Governor’s Office building only

The area location of the proposed Jubail Governor’s Office building is approximately 7 KM from the RC CATV head-end, and there is no existing CATV network to serve the proposed building. “NO CATV system is provided”

This contract shall provide Satellite TV network for this building only by providing dishes, LNB, multi-switch, coaxial cables, etc. Also SAT TV outlets shall be provided for the selected rooms only, such as waiting area, offices, or wherever TV outlet is necessary based upon end user recommendations.

For Patrol Police Office & AL-DAWA Office Building only:

Television box (TVB) will be installed at proposed buildings inside the telecom room with amplifier and required equipment and accessories. TV outlets will be provided in selected rooms only, such as waiting area, or wherever TV outlet is necessary. RG-6 coaxial cable will be installed from TV outlets to the TVB inside electrical metallic tubing (EMT).

Page 72 of 98

Page 73: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

The CATV will be designed to achieve the following performance characteristics:

Minimum signal level at each outlet: -3 dBmV

Maximum signal level at each outlet: +14 dBmV

The TV outlets shall be flush mounted jacks with covers that automatically provide a 75 ohm termination on the cable when a plug is not inserted into the jack. Splitters or tap-off shall be used at each branching point in the cable. Any output of a splitter not used at a branch point shall be terminated in a 75 ohm resistor.

4.8.9 Public Address System

For all buildings under this contract:

A complete public address system shall be provided in common areas for clear announcements during public addressing, paging, prayer calls and one way communication during emergency, background music where required, the system will be manual and automatic public broadcast, the public address system will have different types of inputs with different type of priority. The public address rack contains power amplifiers, mixer/pre amplifier, zone selector and the power control unit. The public address rack shall be located in the admin building inside main telecom room. The system shall contain following components:

Ceiling mounted speakers

Low power speaker will be used to provide uniform sound distribution at low volume levels.

For maximum coverage corridor speakers will be spaced at a maximum of twice the ceiling height apart.

Speakers located in individual rooms will be provided with separate volume controls.

The ceiling speakers shall be with a built-in matching transformer with taps of (1w,2w,4w,6w) watt.

The body of speaker construction must be suitable for the environmental and site applications.

Mounting locations of the loudspeakers shall be chosen to attain the most uniform sound pressure level (SPL) distribution to any given listening position as possible, with minimum variations caused by some unavoidable factors, such as conflict with the arrangement of lighting fixtures, ceiling tiles, or irregular shape of the area.

All ceiling speakers shall have a 6 watts maximum power rating. Speakers shall have a built-in matching transformer. Matching transformers for ceiling speakers must have taps of 1W, 2W, 4W and 6W.

A Dynamic microphone desk stands with led indicator and control base at control room will be included.

Power amplifier for power amplification shall be solid state.

A Digital audio source will be provided.

Auxiliary inputs, monitor panel and selector switch, voice inputs.

It is recommended that public address system rack to be interfaced with fire alarm system to play pre-recorded fire alarm emergency message in case of fire.

Page 73 of 98

Page 74: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Cabling for the public address system will be 2x2.5 mm2 shielded cables routed from the PA rack to the speakers in EMT conduits running above a false ceiling.

The PA system shall use 70 volts distribution system.

4.8.10 Audio/Visual system

For all buildings under this contract:

The proposed Audio-Visual System shall be installed in the buildings which have a meeting rooms only (and shall consist of ceiling mounted network multimedia projector, motorized projection screen with 200” diagonal length, computer workstation and audio-video matrix switch with amplifiers and mixers. All of this equipment shall be installed in the meeting room to provide a good quality service. Outlets for the MIC, AV, VGA/HDMI and RJ-45 shall be provided as shown in the contract drawings. As stated in BICSI Standard, for appropriate sound coverage, 60watt wall-mounted speakers (column speakers) should be mounted 2.4 to 3.7 meters above the floor. As a general rule, one speaker is required for every 56 m² of floor space.

4.8.11 IP-Based Door Access Control System

For all buildings under this contract:

An IP-Based Door access control system shall be provided in this contract as part of the telecommunication system and it shall consist of:

Card reader with embedded door controller: The card reader has the ability to make the decision to grant or deny access based on the users rights. The answer is immediate with no communication needed with the server or controllers, avoiding possible network problems or need to form an emergency master key. In case of network failure, access is granted through Virtual Network technology without compromising security or the user’s access rights. There is a dedicated CAT-6 data cable connecting the door controller to the LAN network to be interfaced with the door access control management software as shown in the design drawings.

1) The network door controller shall provide access control processing, host functionality and power for a single door, including reader, lock, door status, request-to-exit device, and auxiliary sounder.

2) The network door controller shall accept Wiegand output card readers and card formats up to 128 bits in length.

3) The network door controller shall provide a complete, fully featured access control hardware and firmware infrastructure for host-based access control software application.

4) The network door controller shall communicate with hosted access control software using TCP/IP protocol over Ethernet or Internet and shall have an RS-232 port for Modem or connectivity to other systems.

Page 74 of 98

Page 75: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

5) The network door controller shall be capable of employing AES 256 with symmetrical key encryption for all communications between the controller and host(s) system(s).

6) The network door controller shall provide full distributed processing of all access control functions. The unit shall provide fully functional off line operation when not actively communicating with the host access control software application; performing all access decisions and event logging. Upon connection with the host access control software application, the network door controller or network controller/reader shall upload all buffered off-line transactions (minimum of 5,000) to the host software.

7) The network door controller shall incorporate a 32-bit 100 MHz RISC processor running the Linux operating system. The unit shall include a Windows® DLL, and the direct-communication OPIN® API for integration to host-based access control applications.

8) The network door controller shall not be a proprietary product of the manufacturer of the host access control software application, and must have the ability to migrate to an alternative manufacturer’s host access control software application by remote reconfiguration or firmware upgrade and without intervention from the original controller manufacturer.

9) The network door controller shall provide diagnostics and configuration operations through connection to a local laptop computer.

10) The network door controller shall provide on-board Flash memory to allow program updates to be downloaded directly via the network. The network door controller or network controller/reader shall provide the following minimum memory:

8 MB on-board Flash memory

32 MB SDRAM

256k SRAM

Page 75 of 98

Page 76: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

5. APPLICABLE CODES AND STANDARDS

5.1 Architectural The building is designed and shall be constructed in accordance with the following:

Building Codes:

Saudi Building Code (SBC) 2007, Edition

International Building Code (IBC 2009 &2012)

International Fire Code (IFC) 2009 Edition

International Energy Conservation Code IECC-09

American National Standards (ANSI A117.1-2003)

American with Disabilities Act Accessibility Guidelines (ADAAG)

Building Standards:

Saudi Arabian Standards Organization Documents (SASO)

National Fire Protection Association (NFPA 13r)

National Fire Protection Association (NFPA 101-2009) Life Safety Code

American Society for Testing Materials (ASTM)

Underwriters Laboratories (UL)

National Fire Protection (NFPA 80) Standard for fire doors and windows

5.2 Structural

5.2.1 APPLICABLE DESIGN CODES

5.2.1.1 Loading1. Royal Commission Engineering Manual Structural, Chapter 9

General Design Requirement, Latest Revision

2. SEI/ASCE 7-10

Structural Engineering Institute/ American Society of Civil Engineers: Minimum design loads for buildings and other structures

3. IBC-12International Building Code, 2012

4. SBC-2007 Saudi Building Code

5.2.1.2 Concrete1. Royal Commission Guideline Specifications

Division 3, Concrete

Page 76 of 98

Page 77: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

a) Structural Concrete Section 03310

b) Portland Cement Section 03310-1

c) Reinforcement for Concrete Section 03205

d) Cast-in-Place Concrete Forms & Accessories

Section 03105

e) Pre-cast Structural Concrete Section 03430

f) Pre-cast Architectural Concrete Section 03450

g) RC GS 03310-3.07-C

An amendment will be prepared for the RFP to RC GS 03310 to preclude anything but wet-curing of precast concrete. The amendment should read:

Amend Royal Commission Guideline Specification SECTION 03310-3.07-C by adding: "6. Precast concrete (pre-stressed and non-pre-stressed; structural and architectural)."

2. ACI 318-11American Concrete Institute: Building Code, Requirements for Structural Concrete

3. ACI 315-99American Concrete Institute: Details and Detailing of Concrete Reinforcement

4. PCI Design HandbookPre-cast/Pre-stressed Concrete Institute.

5.2.1.3 Masonry

1. Royal Commission Guideline Specifications

Division 4, Masonry

a) Masonry Mortar

b) Masonry Grout

Section 04060

Section 04070

c) Masonry Anchorage & Reinforcement

Section 04080

d) Masonry Accessories Section 04090

e) Clay Masonry Units Section 04210

f) Unit Masonry Assemblies Section 04810

2. ACI 530-05 Section 04810

3. ACI 530.1-05 American Concrete Institute: Building Code Requirements for Masonry Structures and Commentary

Page 77 of 98

Page 78: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

5.2.1.4 Structural Steel

Royal Commission Guideline Specifications

Division 5, Section 05120

5.2.1.5 Corrosion Control

1. Royal Commission Corrosion Engineering Manual

Design Criteria: Corrosion Control

Chapter 12

2. Royal Commission Guideline Specifications

Division 7, Thermal & Moisture Protection

a) Damp proofing & Waterproofing

Section 07100

b) Damp proofing Section 07110

c) Preformed Joint Seal Section 07190

d) Joint Seals Section 07920

5.2.1.6Thermal and Moisture ProtectionRoyal Commission Guideline Specifications

Division 7, Thermal & Moisture Protection

5.2.1.7 Calculations

1. Royal Commission Engineering Manual

Design Criteria, Structural, Preparation & Checking of Structural Calculations

Chapter 9, Sections 9.12 & 9.13

2. JMP 10202 Jubail Management Procedure

5.2.1.8 Foundation & Geotechnical Investigations1. Royal Commission Engineering Manual

Design Criteria, Structural, Geotechnical Investigations

Chapter 9, Section 9.06

2. Royal Commission Guideline Specifications

Division 2, Site Construction

a) Excavation and Fill Section 02315

b) Soil Densification Section 02340-3

3. Project Geotechnical investigation reports

By Royal Commission

The foundation design shall comply with requirements of Final Geotechnical Report.

Page 78 of 98

Page 79: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

5.2.1.9 Safety

1. OSHAOccupational Safety & Health Administration, Latest Editions

Mechanical 5.3.1 FIRE SUPPRESSION SYSTEMS DESIGN REFERENCES

Applicable Codes

IBC International Building Code 2009 Edition IFC International Fire Code 2009 Edition

Applicable Standards

NFPA 10 Standard for Portable Fire Extinguishers 2006 Edition NFPA 13 Standard for the Installation of Sprinkler Systems 2010 Edition. NFPA13 R Standard for the Installation of Sprinkler Systems in Residential

Occupancies up to and Including Four Stories in Height 2006 Edition

NFPA 72 National Fire Alarm Code® 2006 Edition. NFPA 2001 Standard on Clean Agent Fire Extinguishing System ASTM American Society for Testing of Materials. UL Underwriters Laboratories Inc. FM Factory Mutual, Inc. NFPA 101 Life Safety Code® 2009 Edition.

5.3.2 PLUMBING SYSTEMS DESIGN REFERENCES

5.3.2.1 Applicable Codes

The following Codes were referred to while designing the Mechanical systems for the building. Saudi Building Code Requirements (SBC 701 version 2007) IPC International Plumbing Code -2009

5.3.2.2 Applicable Standards

The following standards were followed for the plumbing system design and engineering calculation requirements.

Page 79 of 98

Page 80: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

AWWA-110 American Water Work Association ASSE-102 American Society of Sanitary Engineer PDI WH201 Water Hammer Arrestors 2007 ASHRAE American Society of Heating Refrigeretion & Airconditioning Engineers Application Handbook

5.3.2.3 Applicable Design Guidelines

RC Engineering Manual

5.3.3 HVAC System Design References

5.3.3.1 Applicable Codes

IBC International Building Code (Edition 2009) IMC International Mechanical Code (Edition 2006) SBC Saudi Building code (Edition 2007)

5.3.3.2 Applicable Standards

Following Standards shall be followed for HVAC System design and Engineering Calculations.

ASHRAE 62.1-2007 Indoor Air Quality ASHRAE 90.1-2004 Energy Standard For Buildings ASHRAE 15 Safety of Mechanical Refrigeration

5.3.3.3 Applicable Standards

Following Standards shall be followed for HVAC System design and Engineering Calculations.

ASHRAE 62.1-2007 Indoor Air Quality ASHRAE 90.1-2004 Energy Standard For Buildings ASHRAE 15 Safety of Mechanical Refrigeration

The following Standards shall be followed for products (Equipment & Materials) Fabrication Materials & Methods, Safety, Quality, Performance Ratings, Environmental Compliance, and Testing Requirements.

ARI-340 Air Coils AMCA-4 Fan Construction SMACNA-1 Construction of Low Pressure HVAC Ductwork

5.3.3.4 Applicable Design Guidelines

Royal Commission Mechanical Design Criteria (Chapter 6).

5.3.3.5 Guidelines Requirements

Following Guideline requirements shall be:

ASHRAE Handbook - Applications ASHRAE Handbook – Fundamentals

Page 80 of 98

Page 81: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Electrical Codes CODES AND STANDARDS

The design of the building, procurement of equipment, materials, Construction / installation, inspection, testing and commissioning shall be done in accordance with the latest revision of RC Guideline Specifications, Engineering Manual Chapter-7, and Standard Drawings or other approved equal national or international Codes and Standards, but not limited to the following:

CODES

CODES DESCRIPTIONSBC Saudi Building CodeRC Royal Commission StandardsSASO Saudi Arabian Standard OrganizationSEC Saudi Electricity CompanyNEC National Electrical Code (Latest Edition)IEEE Institute of Electrical & Electronic EngineersIEC International Electro-technical CommissionIESNA Illuminating Engineering Society of North AmericaANSI American National Standard InstituteNFPA National Fire Protection AssociationASTM American Society for Testing & MaterialsUL Underwriters Laboratory Inc.NIH National Institute of Health

STANDARDS

STANDARDS DESCRIPTIONASTM B-3 Soft or Annealed Copper WireASTM B-4 Concentric Lay-Stranded Copper Conductor, Hard, Medium-

Hard, or SoftASTM B-33 Tinned Soft or Annealed Copper Wire for Electrical PurposesANSI C2 National Electrical Safety CodeANSI C80.1 Rigid Steel Conduit – Zinc CoatedANSI C80.3 Electrical Metallic Tubing – Zinc CoatedNFPA 70 National Electrical Code (NEC)NFPA 72 National Fire Alarm CodeNFPA 101 Life Safety CodeUL 3 Flexible Non Metallic Tubing for Electric WiringUL 6 Electrical Rigid Metal Conduit – SteelUL 20 General Use Snap SwitchesUL 67 Panel boardsUL 98 Enclosed and Dead Front SwitchesUL-486A Wire Connectors and Soldering Lugs for Use with Copper

ConductorsUL 489 Molded-Case Circuit Breakers, Molded-Case Switches, and

Circuit Breaker Enclosures.UL 651 Rigid Non-Metallic ConduitNEMA AB1 Molded Case Circuit Breakers and Molded Case switches.NEMA PB1 Panel boards

Page 81 of 98

Page 82: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

NEMA 250 Enclosure for Electrical EquipmentNEMA WD-1 General Color Requirements for Wiring DevicesNEMA WD-6 Wiring Device – Dimensional RequirementsIESNA Illuminating Engineering Society of North America–Lighting

HandbookIEC 60227– 1 Polyvinyl Chloride Insulated Cables of Rated Voltages up to and

including 450/750V, Part – 1: General RequirementsIEC 60529 Degrees of Protection Provided by EnclosuresSASO 2203 Plug & Sockets outlets- General use 220V

SPECIFICATION

Following are the latest RC Guideline Specifications:

DOCUMENT NUMBER

DOCUMENT TITLE

Section 16055 General Provision of Low Voltage Electrical WorksSection 16060 Grounding and BondingSection 16075 Electrical IdentificationSection 16120 Conductors and CablesSection 16130 Raceway and BoxesSection 16140 Wiring DevicesSection 16150 Wiring ConnectionsSection 16410 Enclosed Switches and Circuit BreakersSection 16440 Switchboards, Panel boards and Control CenterSection 16510 Interior LuminairesSection 13100 Lightning Protection Section 13850 Detection and Alarm

Following are SEC-EOA Engineering Standards and Materials Specifications:

DOCUMENT NUMBER

DOCUMENT TITLE

01-SDMS-01Specifications for General Requirements for All Equipment/Material

23-SMSS-1Specifications for PVC Conduits & Fittings for U/G Ducts

37-SDMS-01Specifications for LV Molded Case Circuit Breakers for Service Connections

Page 82 of 98

Page 83: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Telecommunication

5.5.1 Codes and standards

All works covered by this scope shall be performed in accordance with, but not be limited to, the applicable portions of the Industry Codes and Standards, and RC Specifications listed in Section 5.2. Specific reference may be made in the following sections of this scope of work to sections of these Codes, Standards, and Specifications.

This does not relieve the Contractor of his obligation to comply with requirements of all applicable sections of Codes, Standards, and Specifications. Portions of other RC, Industry and International Codes shall also apply as appropriate.

The work shall conform to the latest edition of the following Industry Codes and Standards and RC / STC Specifications and other applicable standards.

Design Standards, Manuals, Guide Specifications and Guide Details

The following summarizes available design standards, manuals, guide specifications and guide details which shall be used.

Saudi Arabian Standards:

Saudi Arabian standards which shall be use are listed below.

SSD Saudi Security Directives SSD/9 Minimum Standards for Building Housing Sensitive SSD/10 Protection of Vital Equipment SSD/11 Power Supplies SSD/12 Communications SSD/16 Automatic Control of Entry (ACE) SSD/19 Work Permit Procedures STC Saudi Telecom Company

RC Standards: RC design codes which shall be used are listed below.

RCBCA Royal Commission Building Code Administration RCEM Royal Commission Engineering Manual JMP Jubail Management Procedure

RC Manuals:

RC design manuals which shall be used are listed below.

Engineering Manual Environmental Regulations Drafting Guidelines

Page 83 of 98

Page 84: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

RC Guide Specifications (RCGS) and Guide Details:

RCGS and guide details which shall be used are listed below.

G/L No. DESCRIPTIONREVISIONS

NO DATE

DIVISION 1 – GENERAL REQUIREMENTS

01430 Construction Quality Control 3 02-10-8401533 Construction Barriers 0 08-04-8101725 As-Built Documents 0 14-11-83

DIVISION 2 – SITE WORK

02220 Structure Excavating and Backfill 0 13-04-81

02221Trenching, Bedding, Backfilling and Compacting

3 22-08-82

02447 Security Fence and Gates 2 27-04-8202452 Roadway Signs 2 04-02-8602555 Asphalt Concrete Pavement Construction 2 14-10-0102578 Pavement Marking 3 01-05-8502604 Manhole Covers and Frames 1 19-01-83

DIVISION 11 – EQUIPMENT

11801 Telecommunications Jointing Chambers 3 10-03-8411802 Telecommunications Duct Banks 4 10-03-8411803 Telecommunication External Cable 5 10-03-8411804 Telecommunication Internal Cable 1 18-10-8111806 Telecommunications External Cable Jointing 1 19-01-83

11808Protection and Marketing of Telecom Underground Plant

0 13-03-89

DIVISION 16

16740 Subscriber Telephone Instruments 1 05-01-8116745 Installation of Telecommunication Facilities 0 10-06-8016746 Pay Stations Telephones 2 17-05-8216755 Public Address and Paging System 0 26-11-8816775 Music Address and Paging System 1 05-01-8116780 Television Distribution System 1 05-01-81

Page 84 of 98

Page 85: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Industry Codes and Standards BICSI-TDMM Building Industry Consulting Services, International

Telecommunications Distribution Methods Manual EIA/TIA-568-A Commercial Building Telecommunications Wiring Standard EIA/TIA-569 Commercial Building Standard for Telecommunications Pathway

and Spaces EIA/TIA-606 Administrative Standard for the Telecommunications

Infrastructure of Commercial Buildings EIA/TIA-607 Commercial Building Grounding and Bonding Requirements for

Telecommunications IEEE 802.3 Carriers Sensing Multiple Access/Collision Detection (CSMA/CD)

Access Method

Abbreviations

The following abbreviations are used throughout the document:

EMT Electrical Metallic Tubing IDF Intermediate Distribution Frame PVC Polyvinyl Chloride RSC Rigid Steel Conduit TMGB Telecommunications Master Ground Bus bar UTP Unshielded Twisted Pair SASO Saudi Arabian Standards Organization BICSI Building Industries Consulting Services International

6. FIRE SAFETY AND LIFE PROTECTION MEASURES

Occupancy ClassificationA. Jubail Governor’s Office Building

Primary Occupancy:

Business Group B Occupancy includes, among others the use of a building or structure, or portion thereof, for office, professional or service-type transaction, including storage of records and accounts. As per IBC Section 304.

Secondary Occupancies:

Residential Group R-1 Occupancy, intended as sleeping units where the occupants are primarily transient in nature, as per IBC Section 310.

Assembly Group A-2 Occupancy Assembly intended for food and/or drink consumption, as per IBC Section 302.

Assembly Group A-3 Occupancy Assembly intended for worship, as per IBC Section 302.

Page 85 of 98

Page 86: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

B. Dawa Office Building

Primary Occupancy:Business Group B Occupancy includes, among others the use of a building or structure, or portion thereof, for office, professional or service-type transaction, including storage of records and accounts, as per IBC Section 304.

C. Patrol Police Office BuildingThe Design is approved and this will be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C.

Construction ClassificationA. Jubail Governor’s Office Building

Construction Classification: Type II B, The building elements, primary structural frame, wall (exterior and interior), floor construction and roof construction are of non-combustible materials. Source: IBC 2009 Section 602.

The following table identifies fire-resistive ratings associated with the type of construction addressed above.

Fire-Resistance Rating Requirements for Building Elements (IBC Section, 601,420.2, 709,712.3 Exceptions)

Building ElementType II (B)

Fire Rating (hours)

Structural frame 0

Bearing walls – Exterior 0

Interior 0

And partitions exterior 0

Floor Construction 0

Roof Construction 0

Walls separating Occupancies

1

Page 86 of 98

Page 87: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

Required Separation of Occupancies

(IBC Section 508 Table 508.4)

OccupancyBusiness Group B

ResidentialGroup R-1

AssemblyGroup A-2

Business Group B

No Separation

1 hour 1 hour

ResidentialGroup R-1

1 hourNo

Separation1 hour

AssemblyGroup A-2

1 hour 1 hourNo

Separation

B. Dawa Office Building

Construction Classification: Type II B, The building elements, primary structural frame, wall (exterior and interior), floor construction and roof construction are of non-combustible materials. Source: IBC 2009 Section 602.

The following table identifies fire-resistive ratings associated with the type of construction addressed above.

Fire-Resistance Rating Requirements for Building Elements (IBC Section, 601,420.2, 709,712.3 Exceptions)

Building ElementType II (B)

Fire Rating (hours)

Structural frame 0

Bearing walls – Exterior 0

Interior 0

And partitions exterior 0

Floor Construction 0

Roof Construction 0

C. Patrol Police Office BuildingThe Design is approved and this will be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C.

Fire and Smoke Protection Requirements and Measures

6.3.1 Fire Suppression System

Page 87 of 98

Page 88: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

A. Jubail Governor’s Office Building

B.

Dawa Office Building

C. Patrol Police Office Building

The Design is approved and this will be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C

Page 88 of 98

OCCUPANCY FIRE AREAFIRE SUPPRESSION

SYSTEM(S)IBC REFER.

BusinessGroup B 3707.36 m²

Automatic Fire Sprinkler System with Portable Fire Extinguisher

Section 903

Residential Group R-1

506.87 m²Automatic Fire Sprinkler System with Portable Fire Extinguisher

Section 903

Assembly Group A-2

457.87 m²Automatic Fire Sprinkler System with Portable Fire Extinguisher

Section 903

Assembly Group A-3

157.84 m²Automatic Fire Sprinkler System with Portable Fire Extinguisher

Section 903

OCCUPANCY FIRE AREAFIRE SUPPRESSION

SYSTEM(S)IBC REFER.

BusinessGroup B

2935.41 m²Automatic Fire Sprinkler System is not required, building is equipped with Portable Fire Extinguisher only

Section 903

Page 89: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

6.3.2 Fire Separation

A. Jubail Governor’s Office Building

EXTER. WALL DISTANCEDEGREE OF

OPENING PROTECTION

AREA OF OPENINGS (% OF

WALLS)

NORTH 10- 14 feetUnprotected Sprinklered

45 %

EAST 10- 14 feetUnprotected Sprinklered

45 %

SOUTH 10- 14 feetUnprotected Sprinklered

45 %

WEST 10- 14 feetUnprotected Sprinklered

45 %

B. Dawa Office Building

EXTER. WALL DISTANCEDEGREE OF

OPENING PROTECTION

AREA OF OPENINGS (% OF

WALLS)

NORTH 20- 24 feetUnprotected

Non Sprinklered45 %

EAST 20- 24 feetUnprotected

Non Sprinklered45 %

SOUTH 20- 24 feetUnprotected

Non Sprinklered45 %

WEST 20- 24 feetUnprotected

Non Sprinklered45 %

C. Patrol Police Office BuildingThe Design is approved and this will be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C

6.3.3 Service Penetration

A. General (applicable for all buildings)

Page 89 of 98

Page 90: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

All openings in fire resistance walls, due to pipe crossing and conduits, shall be sealed with intumescent fire stopping material rated at the same fire barrier in accordance with ASTM E814 or UL 1479. Fire stop material types shall be in accordance with the UL system No. as follows:

PENETRATION ITEM

FIRE STOP MATERIAL TYPE UL SYSTEM NO.

Pipe Conduits UL 263

Ducts25mm thk. Filled with Fiber Glass

Board Insulation UL 1479

Steel Electrical Box

UL 1479

NOTE: Ductwork and other large service penetrations which penetrate fire barriers shall be provided with fire dampers rated at the same fire rating as the fire barrier.

Exits and Egresses Requirements6.4.1 Egress Width Calculation

A. Jubail Governor’s Office Building

EGRESS WIDTH CALCULATION

FLOOR AREA/SPACENO. OF OCCUP.

EXIT DOORS EGRESS WIDTH

NO. REQ’D.

ACTWIDTH

PER OCCUP.

TOTAL WIDTH REQ’D

ACT

GroundFloor

Offices 209.6 2 6 5.08 mm 1062 mm 1945mm

Guest House 6.41 1 1 5.08 mm 32.56mm 2568mm

Guest/Food Hall

328.57 2 3 5.08 mm 1669.1mm 2950mm

Prayer Hall 343.13 2 2 5.08 mm 1743.1mm 2425mm

FirstFloor

Offices 190 2 5 5.08 mm 965.2mm 1945mm

Guest Suite 20.86 3 3 5.08 mm 105.96mm 2568mm

B. Dawa Office Building

EGRESS WIDTH CALCULATION

Page 90 of 98

Page 91: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

FLOOR AREA/SPACENO. OF OCCUP.

EXIT DOORS EGRESS WIDTH

NO. REQ’D.

ACTWIDTH

PER OCCUP.

TOTAL WIDTH REQ’D

ACT

GroundFloor

Offices 153.17 2 8 5.08 mm 778.1 mm 1945mm

FirstFloor

Offices 163.77 2 8 5.08 mm 831.95mm 1945mm

C. Patrol Police Office Building

The Design is approved and this will be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C

6.4.2 Stair Number and Width Calculation

A. Jubail Governor’s Office Building

STAIR NUMBER AND WIDTH CALCULATIONS

FLOORAREA / SPACE

NO. OFOCC.

STAIRWAYS STAIR WIDTH

MIN. REQ’D.

ACTUALWIDTH

per OCCUP.

TOTAL WIDTH REQ’D

ACT.

First Floor

Offices 190 4 4 7.62mm 1447mm 1500mm

Guest Suite 20.86 2 2 7.62mm 152.4mm 1500mm

FLOOR STAIRWAY SUMMARY 6 6

NOTE:Number of stairs and stairway width per provisions in Chap. 10, IBC 2009.

Page 91 of 98

Page 92: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

B. Dawa Office Building

STAIR NUMBER AND WIDTH CALCULATIONS

FLOORAREA / SPACE

NO. OFOCC.

STAIRWAYS STAIR WIDTH

MIN. REQ’D.

ACTUALWIDTH

per OCCUP.

TOTAL WIDTH REQ’D

ACT.

First Floor

Offices 163.77 4 4 7.62mm 1447mm 1500mm

FLOOR STAIRWAY SUMMARY 4 4

C. Patrol Police Office Building

The Design is approved and this will be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C

6.4.3 Exit Access Design

A. Jubail Governor’s Office Building

TRAVEL DISTANCE, DEAD END & COMMON PATH OF EGRESS REQUIREMENTS

OCCUP. CLASS.FIRE SPRLR.

(Yes / No)TRAVEL

DISTANCEDEAD END DISTANCE

COMMON PATH OF TRAVEL

DISTANCE

BusinessGroup B

Yes 91440mm 15240mm 30480mm

Residential Group R-1

Yes 76200mm 15240mm 22860mm

AssemblyGroup A-2&3

Yes 76200mm 6096mm 22860mm

NOTE:Maximum allowable distances are identified in Tables in Chapter 10 of the IBC 2009. Automatic sprinkler systems increase the allowable distance to exits.

Page 92 of 98

Page 93: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

B. Dawa Office Building

TRAVEL DISTANCE, DEAD END & COMMON PATH OF EGRESS REQUIREMENTS

OCCUP. CLASS.FIRE SPRLR.

(Yes / No)TRAVEL

DISTANCEDEAD END DISTANCE

COMMON PATH OF TRAVEL

DISTANCEBusinessGroup B

No 60960mm 6096mm 22860mm

NOTE:Maximum allowable distances are identified in Tables in Chapter 10 of the IBC 2009. Automatic sprinkler systems increase the allowable distance to exits.

C. Patrol Police Office Building

The Design is approved and this will be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C

6.4.4 Area of Refuge Calculation

A. Jubail Governor’s Office Building

The building is equipped with an automatic sprinkler system and as per IBC Section 1007.3, Buildings or levels provided with automatic sprinkler systems is exempt from providing areas of refuge.

B. Dawa Office Building

AREA OF REFUGE CALCULATIONS

FLOOR LEVELOCCUPANT

LOADREQ’D AREA OF REFUGE

PROVIDED AREA OF REFUGE*

Ground Floor 153.17 0.92m² 2.25m²

First Floor 163.77 0.92m² 2.25m²

Section 1007, IBC 2009

C. Patrol Police Office Building

The Design is approved and this will be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C

Page 93 of 98

Page 94: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

6.4.5 Assembly Occupancy Egress Requirements

A. Jubail Governor’s Office Building

ROOM / AREA

OCCUP. CLASS.

LIFE SAFETY / EGRESS REQUIREMENTS

IBC REFERENCE

Guest hallAssembly Group A-2

Travel distance shall not be greater than 76 200mm.

Sec. 1028.7

Common path of egress travel shall not exceed 9144mm from any seat to a point where an occupant has a choice of egress travel to two exits.

Sec. 1028.8

Minimum aisle width is 1067mm for level aisles having seating on both side and 914mm for level aisles having seating on only one side.

Sec. 1028.8

Food hallAssemblyGroup A-2

Travel distance shall not be greater than 76 200mm.

Sec. 1028.7

Common path of egress travel shall not exceed 9144mm from any seat to a point where an occupant has a choice of egress travel to two exits.

Sec. 1028.8

Minimum aisle width is 1067mm for level aisles having seating on both side and 914mm for level aisles having seating on only one side.

Sec. 1028.8

B. Dawa Office Building

The building has no Assembly Occupancy.

C. Patrol Police Station Building

The Design is approved and this will be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C.

Life Safety Plans

A. Jubail Governor’s Office Building

It is not required in the 10% Submittal, Life Safety Plans will be submitted in the 30 % design stage submittal.

Page 94 of 98

Page 95: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

B. Dawa Office BuildingIt is not required in the 10% Submittal, Life Safety Plans will be submitted in the 30 % design stage submittal.

C. Patrol Police Office BuildingThe Design is approved and this will be the site adaptation of the Ministry of Interior Building Under contract 611- C27, as specified in Form C

7. DESIGN ANALYSIS

Site InvestigationA. Jubail Governor’s Office Building Site

It is a vacant lot and there is no existing facility to be demolished, the lot is uneven there is existing trees and bushes that is favourable to be a landscaping aspect of the site and there is an existing access road and easement road with parking that is potentially the access to entrance the building. The site has existing utilities like transformer, high voltage electrical manhole, telecom manhole that can be a tie in point of access to the building. Generally, the whole site is surrounded by a fence that serves as a protective measure for all buildings situated in the site.

B. Dawa Office Building SiteThere is an existing “STC Telecom Tower” on the site whose lease has been expired. This is an issue between the R.C and Saudi Telecom (STC). AE recommends that this must be subjected for relocation for this is a hindrance for the design and construction of the Facility. There is an existing access road that will serve as an entry point to the site. The site has existing utilities like transformer and high voltage electrical manhole that can be a tie in point of access to the building.

C. Patrol Police Office Building SiteIt is a vacant lot and there is no existing facility to be demolished, the lot is uneven there is existing trees and bushes and there is an existing access road that is subjected for expansion and it is potentially the access to entrance the building. The site has existing electrical utilities (medium voltage) that can be a tie in point of access to the building. Generally, the whole site is not surrounded by a fence.

Energy ConservationA. General (Applicable for all buildings)

The Proposed Building is potentially oriented to minimize the afternoon heat of the sun and acquire the natural wind flow, the building is designed with shades and louvers; and for the building envelope; Double –glazed low-e (medium solar gain) argon gas fill on powder coated aluminum frame (U-VALUE=0.33 Btu/h. ft². ºF) for the windows, 350mm thick wall with R value of 13h.ft.². ºF /Btu (2.288 m².K/W); and Inverted Roofing system with R value of 30h.ft.². ºF /Btu (5.28 m².K/W); that serves as a protection and heat penetration in order to prevent the potential heat gain of the building from the harsh environment outside that lessen the requirements for Air

Page 95 of 98

Page 96: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

conditioning system. The building is also design with enough window opening, and skylight to provide penetration of natural light to help reduce the consumption of electricity in terms of lighting.

Water ConservationA. General (Applicable to all buildings)

The Jubail Governor’s Office consisting of ground and first floor are provided with several toilets. Cold and hot water supply system will be provided in each toilet to supply water demand for all fixtures. In compliance with Water Conservation measures, low flow water consumption flush valve will be used in all water closets, low flow faucets for lavatories, low flow faucet for pantry sink and low flow shower heads for showers. For other building except Police Patrol Office building, Instead of using individual electric water heater as a source of hot water and due to several number of fixtures that will require hot water, application of Centralized Solar water heating system with electric water heater storage back-up with heating elements will be suited as a measure of conserving energy to supply the hot water demand of the building. In Police Patrol Office building due to a few numbers of fixtures that will require hot water application of individual water heater system is suited to provide the hot water demand of the building. Standard electric water heater with the minimum KW rating will be used as a measure of energy conservation.

Noise ReductionA. General ( Applicable to all buildings)The layout of the proposed building is designed as per segregation of different areas according to its function to minimize the disturbance of the noisy areas from the offices, in the noisy areas the wall is designed as per the Royal Commission sound isolation criteria for the separation of each space. With the help of landscaping designed trees that serves as the buffer Zone we are enabled to minimize the noise coming from the vehicles in the adjacent road near the site.

Environmental ParametersA. Jubail Governor’s Office Building Site

There is an existing main road at the east part of the site, and it might cause some air and noise pollution to the facility. AE recommends putting more trees that will serves as a noise barrier and air filter to lessen the air and noise pollution.

B. Dawa Office Building SiteThere is an existing access road at the southern part of the site and will serve as the main entry, and main road on its north part and it might cause some air and noise pollution to the facility. AE recommends that the building will be located in the center of the site and putting more trees that will serves as a noise barrier and air filter to lessen the air and noise pollution. AE recommends providing a fence around the site for protective measures

Page 96 of 98

Page 97: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

C. Patrol Police Office Building SiteThere is an existing access road at the west part of the site, and it might cause some air and noise pollution to the facility. AE recommends that the building will be located in the east part away from the main road and putting more trees that will serves as a noise barrier and air filter to lessen the air and noise pollution. AE recommends providing a fence around the site for protective measures.

Lighting RequirementsAll lighting fixtures shall consist of t5 (14 watts and 28 watts) fluorescent lamps with high power factor electronic ballasts and with compact fluorescent lamps. Lighting fixture types and lamps shall be selected according to the rc guideline.The illumination levels will comply with illuminating engineering society handbook (ies) as well as rc engineering manual recommended average values.

Area Illumination level Main Entrance Lobbies 200 luxCorridors 220 luxOffices 770 luxToilets 330 luxPantry 300 luxStaircases 330 luxReception 300 luxKitchen 500 luxElectrical room 220 luxStores 200 lux

Power System AnalysisThe incoming electrical power supply shall be supplied from the sec electrical network at 13.8KV, 3-phase, 60hz. Sec shall approve the exact location of the proposed substations or existing substations. All 13.8KV and low voltage electrical equipment, transformer, main switchboard, panel boards, interface and connections, metering including connection fees shall be in accordance with the sec requirements and procedures.This contract consist of following buildings, which shall be fed from different transformers. 300-KVA transformer shall supply to Petrol Police Building.1000-KVA transformer shall supply to Dawa Office Building. 1500-KVA transformer shall supply to Jubail’s Govern Office Building.

Accessibility ProvisionsA. General ( Applicable to all buildings)

The Proposed Site and Building is a handicapped friendly environment, it provides accessibility from the parking with a curb ramp and a stair ramp into a building. The Corridor width is way enough to provide a circulation space for a wheelchair. In terms of change of floor levels, the building is equipped with elevator with enough area to provide space for wheelchair for the persons with disability and stretcher in case of

Page 97 of 98

Page 98: Design Basis Report 3

610-T17, Task No. 24 Apr-23Contracts 611-C26 Building Systems Design Basis Report Revision: BBuildings Progress Stage: 30%

emergency; and an area of refuge is provided in case of fire. The building is designed also to provide enough number of toilets for disabled as per the International Building Code Requirement.

Security ProvisionsA. General (Applicable to all Buildings)

Typically the Facility is designed to secure and protect the end user; it is a requirement to provide a boundary fence and a security guard house or security room that will serves as the facility for the security personels. The building is also equipped of CCTV Camera that monitors the activities in the facility. The building keying system is as per the Royal Commission and Standard.

8. APPENDICES

Page 98 of 98