100% basis of design report
TRANSCRIPT
July 2021
Parcel 86 Bank Stabilization Project
100% Basis of Design Report
Prepared for Port of Tacoma
Project Number: 200092-01.05
July 2021
Parcel 86 Bank Stabilization Project
100% Basis of Design Report
Prepared for
Port of Tacoma
One Sitcum Plaza
Tacoma, Washington 98421
Prepared by
Anchor QEA, LLC
1119 Pacific Avenue, Suite 1600
Tacoma, Washington 98402
100% Basis of Design Report i July 2021
TABLE OF CONTENTS
1 Introduction ................................................................................................................................ 1
1.1 Basis of Design Report Purposes and Objectives ................................................................................... 1
1.2 Document Organization ................................................................................................................................... 1
2 Project Area Background and Conditions ........................................................................... 2
2.1 Project Area Description ................................................................................................................................... 2
2.2 Land Ownership ................................................................................................................................................... 3
2.3 Site Conditions ..................................................................................................................................................... 3
2.3.1 Survey ....................................................................................................................................................... 3
2.3.2 Subsurface Conditions ....................................................................................................................... 3
2.3.3 Hydrogeology ....................................................................................................................................... 3
2.3.4 Creek Bank Conditions ...................................................................................................................... 4
2.3.5 Tides ......................................................................................................................................................... 5
2.3.6 Extreme Water Levels ......................................................................................................................... 6
2.3.7 Sea Level Rise ........................................................................................................................................ 6
2.4 Existing Site Structures ...................................................................................................................................... 7
2.4.1 Railway ..................................................................................................................................................... 7
2.4.2 Stormwater Infrastructure ................................................................................................................ 7
3 Bulkhead Design ........................................................................................................................ 9
3.1 Design Objectives ............................................................................................................................................... 9
3.2 Design Constraints .............................................................................................................................................. 9
3.3 Design Assumptions and Criteria .................................................................................................................. 9
3.3.1 Geotechnical ....................................................................................................................................... 11
3.3.2 Structural ............................................................................................................................................. 11
3.4 Installation ........................................................................................................................................................... 12
4 Schedule ..................................................................................................................................... 13
5 References ................................................................................................................................. 14
100% Basis of Design Report ii July 2021
TABLES
Table 1 Tidal Datums at Tacoma, Washington (NOAA Tidal Station #9446484) ............................ 6
Table 2 Summary of Sheet Pile Lengths along the Bulkhead Alignment ........................................ 10
Table 3 Subsurface Soil Profile and Preliminary Soil Engineering Properties ................................ 11
Table 4 Preliminary Construction Schedule .................................................................................................. 13
FIGURES
Figure 1 Overview of Parcel 86 ................................................................................................................................ 2
Figure 2 Bank Erosion at Parcel 86 at Low Tide ............................................................................................... 5
Figure 3 Stormwater Infrastructure Elevations ................................................................................................. 8
APPENDICES
Appendix A SupportIT Model Documentation
100% Basis of Design Report iii July 2021
ABBREVIATIONS
bgs below ground surface
MHHW mean higher high water
MLLW mean lower low water
NOAA National Oceanic and Atmospheric Administration
pcf pound per cubic foot
Port Port of Tacoma
psf pound per square foot
RCP Representative Concentration Pathway
100% Basis of Design Report 1 July 2021
1 Introduction
1.1 Basis of Design Report Purposes and Objectives
This Basis of Design Report has been prepared for the Port of Tacoma (Port). This report documents
the basis of design criteria for the construction of a bulkhead composed of sheet pile wall to prevent
erosion along the bank of the Hylebos Creek at the Port of Tacoma Parcel 86. This Basis of Design
Report includes a summary of investigations, which serve as the basis for characterizing site
conditions and establishing design criteria.
1.2 Document Organization
The remainder of this document is organized into the following sections:
• Section 2: Project Area Background and Conditions
• Section 3: Bulkhead Design
• Section 4: Schedule
The following appendices are attached to this Report:
• Appendix A: SupportIT Model Documentation
100% Basis of Design Report 2 July 2021
2 Project Area Background and Conditions
2.1 Project Area Description
Parcel 86, located within the Port at 3701 Taylor Way, is a former cleanup site, regulated by the
Washington State Department of Ecology. The property runs adjacent to the south bank of the
Hylebos Creek. The former owner and operator, Louisiana Pacific, placed Asarco slag and road ballast
across the site to stabilize the ground for operation of heavy log-yard machinery. The remedy was
implemented in 1993 and consists of a low-permeability asphalt cap and stormwater drainage
system. The Enforcement Order (DE92TC-S312) and Restrictive Covenant prohibits disturbance of the
cap and exposure to contaminated soil and slag under the cap. Erosion of the shoreline bank in the
southeast corner has progressed landward having exposed a manhole that is part of the Parcel 86
stormwater management system. The area of erosion is within clean backfill surrounding the
exposed manhole.
Figure 1
Overview of Parcel 86
Hylebos
Waterway
Bank Erosion
Area
SR 509
Tacoma Rail
Upland Swale
100% Basis of Design Report 3 July 2021
2.2 Land Ownership
The property is currently owned by the Port and is leased to Wallenius Wilhelmsen Logistics Services
who uses the site for post assembly of construction equipment and staging of equipment before
delivery to clients.
2.3 Site Conditions
Anchor QEA and Port staff previously conducted a site visit in June 2019 to observe the conditions of
the shoreline. The site visit was part of the scope of work for a Bank Erosion Assessment Report
(Anchor QEA 2019). Based on the analyses performed under that scope, it was determined that there
were three potential causes of bank erosion:
• Leakage from the stormwater conveyance system
• Inundation and drainage of the stormwater system conveyance piping gravel bedding layer
during tidal cycles
• Upland runoff
Further information about the erosion assessment can be found in the Bank Erosion Assessment
Report (Anchor QEA 2019).
2.3.1 Survey
A topographical survey of the project area, including the bank of the Hylebos Waterway down to the
creek centerline, was performed by Sitts & Hill Engineers, Inc., on June 23, 2020. The survey also
included the four on-site groundwater monitoring wells and documentation of the stormwater
conveyance system adjacent to the bank erosion area. Further information regarding the survey can
be found in the Conceptual Design Options Evaluation Report (Anchor QEA 2020).
2.3.2 Subsurface Conditions
A geotechnical subsurface field investigation including the advancement of one soil boring was
performed to collect necessary data for the design of a bulkhead and remediation measures. The
general lithology of the subsurface beneath the asphalt cap includes a layer of soft silt to a depth of
25 feet followed by a layer of poorly graded sand with silt to a depth of 35.3 feet. The subsurface
information obtained during the subsurface geotechnical investigation was used for design analysis
of a sheet pile bulkhead wall. Further information about the subsurface conditions can be found in
the Conceptual Options Evaluation Report (Anchor QEA 2020).
2.3.3 Hydrogeology
The estimated zone of groundwater fluctuation between elevation +10 and +12 feet mean lower low
water (MLLW) is based on seasonal water level observations made during the long-term monitoring
100% Basis of Design Report 4 July 2021
events required by the Washington State Department of Ecology cleanup (under Enforcement Order
No. DE 92TC-S312) for the Former Louisiana Pacific/Pony Lumber Facility. This monitoring occurred
periodically between 2007 and 2019. After review of these data, the following was concluded about
groundwater at the site: 1) the horizontal gradient towards the creek is relatively flat, and 2) there is a
slight downward gradient from the upper silt into the underlying sand layer.
The survey also documented the stormwater manholes and confirmed that the gravel bedding below
the manholes sits within the zone of groundwater fluctuation at approximately +10.3 feet MLLW.
This elevation is consistent with observations of groundwater seeps that emanate from the bank
adjacent to MH7.
2.3.4 Creek Bank Conditions
The creek bank erosion is occurring just downstream of the SR 509 and rail bridges that cross over
the Hylebos Creek. Figure 2 shows a photograph of bank erosion at the project site; the vault for
manhole MH7 is visible in the photograph. On-site observations suggested that the erosion had
been caused by a flow originating at the top of the tank, from within the bedding layer for the
manhole vault, or both. The flow was large enough to move the gravel bedding layer away from the
vault and down the bank as well as cutting an approximate 1-foot-deep incised channel down the
mud bank.
100% Basis of Design Report 5 July 2021
Figure 2
Bank Erosion at Parcel 86 at Low Tide
Note: Photograph looking southwest from rail bridge. Photograph taken April 2019.
2.3.5 Tides
Tidal heights in the adjacent Hylebos Waterway were taken from National Oceanic and Atmospheric
Administration (NOAA) tidal station #9446484 located on the Sitcum Waterway, in Tacoma,
Washington. Table 1 summarizes tidal datums relative to NAVD88 and MLLW based on NOAA tidal
station #9446484.
100% Basis of Design Report 6 July 2021
Table 1
Tidal Datums at Tacoma, Washington (NOAA Tidal Station #9446484)
Tidal Datum
Elevation
(feet relative to MLLW)
Elevation
(feet relative to NAVD88)
Mean Higher High Water (MHHW) +11.8 +9.4
Mean High Water (MHW) +10.9 +8.5
Mean Sea Level (MSL) +6.8 +4.4
Mean Low Water (MLW) +2.8 +0.4
North American Vertical Datum (NAVD88) +2.4 0
Mean Lower Low Water (MLLW) 0 -2.4
2.3.6 Extreme Water Levels
The Federal Emergency Management Agency 100-year flood elevation for the Hylebos Waterway
adjacent to the site location is 12 feet NAVD88 (+14.6 feet MLLW). This elevation is derived from
coastal processes (based on the Federal Emergency Management Agency flood map number
52053C0788E from March 7, 2017) and is approximately equal to the highest observed water level at
the NOAA tidal station #9446484 (+14.8 feet MLLW). Based on the elevations of the site topography,
the 100-year floodplain elevation is only expected to interface with a small portion of the bulkhead
local to the critical area of scour and is not expected to interface with any other exposed portions of
the bulkhead.
2.3.7 Sea Level Rise
A report prepared for the Washington Coastal Resiliency Project in 2018 provided an updated
assessment of projected sea level rise and the associated hazards for Washington state. The updated
projections for sea level rise are more comprehensive than past estimates, taking into consideration
recent research, land movement, and greenhouse gas emissions. Greenhouse gas emission
projections depend on a variety of factors related to human behavior. Therefore, probabilistic
projections for sea level rise have been made based on both low and high greenhouse gas scenarios.
Climate projections are made for two greenhouse gas emissions scenarios in this report:
Representative Concentration Pathway (RCP) 4.5 and RCP 8.5. RCP 4.5 is a low scenario in which
greenhouse gas estimates stabilize by mid-century and decrease thereafter. RCP 8.5 is a high
scenario in which there is continued increase in greenhouse gasses until the end of the 21st century
(Mauger et al. 2015).
The Washington Coastal Network used the information presented in this report to develop a
visualization tool (SLR Visualization Tools1) to assess projected sea level rise over the next century.
1 https://wacoastalnetwork.com/chrn/research/slr-visualization/
100% Basis of Design Report 7 July 2021
The site-specific sea level rise estimates for the Port under the RCP 4.5 low scenario for a 50%
probability is 2.1 feet by the year 2100, which would result in a new MHHW level of approximately
+13.9 feet MLLW. The minimum final elevation of the bulkhead will be established at +18 feet MLLW;
therefore, it is not expected that the wall would be overtopped within its design life.
2.4 Existing Site Structures
2.4.1 Railway
A rail line runs adjacent to SR 509 approximately 15 feet southeast from the boundary of Parcel 86.
The rail line is owned and operated by Tacoma Rail as part of the Tidelands Division.
2.4.2 Stormwater Infrastructure
Adjacent to the creek bank exist numerous manhole vaults. Figure 3 shows the elevations in feet
MLLW (Table 1) of the stormwater system just upland of the observed bank erosion; the locations of
MH7, MH8, and MH9; and the MHHW elevation. The erosion along the bank is adjacent to existing
stormwater infrastructure for Parcel 86, especially MH7. There exists an underground stormwater
vault that extends to the northwest of MH7 and MH8. A supplemental survey was completed by Sitts
& Hill Engineers, Inc., on April 14, 2021, to verify the location and position of MH7. The location of
this structure is shown on the engineering drawings.
100% Basis of Design Report 8 July 2021
Figure 3
Stormwater Infrastructure Elevations
Source: Port of Tacoma 2008; Elevations in MLLW.
N
Bank Erosion Area
100% Basis of Design Report 9 July 2021
3 Bulkhead Design
This section describes the preliminary design for the sheet pile bulkhead, including design criteria
and limitations.
3.1 Design Objectives
The objective of the bulkhead design is to stabilize the upper bank of the Hylebos Creek above the
MHHW mark to prevent damage to the environmental cap and stormwater system.
3.2 Design Constraints
There are several design constraints within the project area that were addressed during preliminary
design. First, the project area is bounded by the railroad to the southeast. Because the project is
located within the rail right-of-way, discussions with the owner were held to verify that the alignment
of the bulkhead would not impede rail operations. In general, the rail operates overnight and
construction should not coincide with operations.
Second, the location of stormwater infrastructure, primarily MH7 and the adjacent stormwater vault
in the upland portion of the creek bank provided a constraint to design. The stormwater vault proved
to be an added constraint as it cannot support excessive loading, requiring the need for a crane with
sufficient reach to perform the work from behind the vault.
Finally, the project area is constrained by the Hylebos Creek to the north, where the creek bank
begins immediately north of the property. Based on the topographical survey and due to the
locations of stormwater structures that exist at the site, the alignment of the bulkhead was modified
from the preliminary alignment as shown in A-01.
3.3 Design Assumptions and Criteria
As detailed in the Conceptual Options Evaluation (Anchor QEA 2020), the geotechnical investigation
that was completed in Fall 2020 indicated soft conditions in the upper 25 feet of the subsurface. The
sheet pile wall sections were modeled using SupportIT, a design software package used to model
earth pressures acting on cantilevered sheet pile walls (GTSoft 2007). The model utilizes subsurface
soil properties combined with sheet pile wall structural strength data to determine design criteria
such as minimum embedment depth requirements and anticipated bending moments. Computer
runs for various sheet pile sections and embedments were performed to establish the relationship
between wall embedment and deflection. Anchor QEA consulted a steel supplier, NucorSkyline, to
determine available and appropriate steel sheet pile sections for use at the site based on existing site
conditions and long-term maintenance expectations. Embedment depths for each section of the
bulkhead were determined by modeling each section using NZ19 ASTM A690 Grade 50 Hot Rolled
Sheet Pile. The NZ19 sheet pile section was selected due to its availability and ability to be rolled
100% Basis of Design Report 10 July 2021
using ASTM A690 steel. Data for the NZ19 panels as well as the subsurface soil profile determined by
the geotechnical investigation and lab results we input to this model. Note that ASTM A690 steel was
selected for this preliminary design due in part to its maintenance-free use in the marine
environment while not requiring protective coatings or a cathodic protection system.
For each section, reasonable assumptions were made for exposed sheet pile to conservatively
account for any future erosion that may occur seaward of the bulkhead due to fluid flow and tidal
cycles. The maximum deflection2 and embedment depths along each cross section were estimated
using the SupportIt model. Six total cross sections were developed to characterize changes in the
bank topography, as shown in Figure A-01. A critical cross section was determined at the area of
scour adjacent to MH7. During this interim design phase, it was determined that the NZ19 bulkhead
was sufficient to meet acceptable deflection tolerances at the critical cross section. The maximum
deflection for sections A-A’, B-B’, C-C’, D-D’, F-F’, and G-G’ was less than 1 inch. The maximum
deflection for the critical cross section E-E’ was less than 2 inches. The predicted deflections along
the length of the bulkhead are within the tolerance of the sheet pile interlocks. Table 2 summarizes
the alignment lengths and depths for each section of bulkhead.
Table 2
Summary of Sheet Pile Lengths along the Bulkhead Alignment
Evaluated
Section1
Approximate
Length of
Segment along
Alignment
Sheet
Depth
(bgs) Notes about Slope Condition at Cross-Section
Sections A-A’,
B-B’, and C-C’ 3 pair (~14 feet) 10 feet
West of observed bank erosion. Shoreline is stable and
vegetated.
Sections D-D’,
and F-F’ 3 pair (~14 feet)
Varies, 15 to
20 feet
Adjacent to main bank erosion area. Shoreline appears
relatively stable and is vegetated on the upper slope, but
potential future erosion may be expected as the adjacent
erosion area expands.
Section E-E’ 2 pair (~9 feet) 30 feet
Shoreline is not stable and significant erosion has occurred.
Multiple groundwater seeps are observed and gravel base
layer around and below the stormwater system provides
continuous flow path. Erosion will continue until bulkhead
is constructed.
Section G-G’ 2 pair (~9 feet) 10 feet Wall segment is perpendicular to the slope and is stable.
Note:
1. Section references are based on Figure A-01 in Appendix A and do not correspond to the sections shown on
the Plans.
Engineering drawings C3.0 and C4.0 show the plan view of the bulkhead alignment and the sectional
views. The bulkhead alignment will run parallel to the Hylebos creek north to south utilize a delta 3
2 Deflection is generally defined as the horizontal displacement of the top of a cantilever bulkhead that will occur over time.
100% Basis of Design Report 11 July 2021
connected to create a 110-degree elbow angling the bulkhead south as it approaches the rail line to
the south east. The 110-degree elbow was selected to route the perpendicular segment of the
bulkhead around existing natural features and to maintain function of the stormwater swale that runs
along the railroad. Further information regarding the details of the bulkhead design can be found in
the engineering drawings.
3.3.1 Geotechnical
Table 3 summarizes the subsurface geologic profile observed in the boring and associated modeling
parameters used to develop a conceptual bulkhead configuration. Modeling parameters were
established using geotechnical laboratory test results, as well as standard empirical correlations of
measured SPT-N values to soil engineering design properties. Selection of the design properties was
based on experience with similar materials on other projects and consistent with geotechnical
engineering design guidance.
Table 3
Subsurface Soil Profile and Preliminary Soil Engineering Properties
Subsurface Layer
Depth below Ground
Surface (feet)
Total Unit
Weight (ɣ) (pcf)
Effective Cohesion
(c’) (psf)
Friction Angle
(φ’) (degrees)
Asphalt 0–0.8 135 4,175.7 0
Gravel Base 0.8–2 110 0 40
Layer 1: Silt (ML) 2–25 100 500 18
Layer 2: Poorly Graded
Sand with Silt (SP-SM) 25–35.3 115 0 32
Layer 3: Silt (MH) 35.3–41.8 95 500 16
Layer 4: Poorly Graded
Sand with Silt (SP-SM) 41.8–45.6 110 0 30
Layer 5: Silty Sand (SM) 45.6–55.3 110 0 28
Layer 6: Poorly Graded
Sand with Silt (SP-SM) 55.3–80.1 125 0 32
3.3.2 Structural
There were a few structural considerations addressed during the preliminary design phase. Because
several segments of the bulkhead may be exposed to saline water, the evaluations focused on
available sections composed of ASTM A690 steel, which is a weathering steel alloy that develops an
oxidizing layer to protects against erosion without supplemental coating or active corrosion
protection anode systems. This steel is slightly more expensive than more common grades of steel
used for sheet pile, but will not require any near- or long-term maintenance. Sheet piles composed
100% Basis of Design Report 12 July 2021
of A690 steel may become a long-lead item since it is generally not carried in-stock and requires
special runs of fabrication.
The top surface of steel sheet piles can be a bit jagged based on installation procedures and should
be capped to create a finished appearance. We suggest a carbon steel inverted channel to be bolted
to the top of the steel bulkhead. Since this channel is accessible for maintenance, unlike portions of
the steel sheet piles, we have chosen a channel section of common A36 steel, blasted, primed, and
painted with a quality epoxy marine-grade coating. Obviously, this channel could be fabricated from
A690 material, or even obtained in stainless steel, although at much higher cost.
3.4 Installation
Sheet piles are typically installed using vibratory and impact hammer. The use of a diesel vibratory
hammer may potentially cause a liquefaction effect immediately adjacent to the piling, which
temporarily reduces localized soil strength. The Washington Department of Natural Resources
geologic portal3 categorizes the area in and around the Port as highly susceptible to liquefaction. It
is likely that very little driving force will be required to install the sheet piles into this layer, and so a
silent pile driver will be used to install the bulkhead, thus significantly reducing the potential for
installation to cause bank failure. For the approximately 10-foot (two pairs of sheet pile) segment of
bulkhead with embedment depths of 30 feet below ground surface (bgs), the deeper soils consist of
medium dense sand and soft silt. Increased hammer energy may be required to drive the piles into
the layer of medium dense sand; however, this could be accomplished using an impact hammer
which have a lower potential to cause a strength reduction in adjacent soils. Given the potential for
surficial bank soils to fail, we plan to specify the use of a silent pile driver and an impact hammer,
only if required, for this project.
We have assumed that the bulkhead will be installed from a landside position. Landside access to the
location of the proposed bulkhead is limited by the railroad and the infrastructure associated with
the stormwater management system. Based on our preliminary outreach to local pile installation
contractors, we believe that American Crane models 9299 or 9310 will be suitable to support pile
installation for this project. These cranes have the reach and load capacity to facilitate pile installation
while the crane is positioned landward of the stormwater treatment vault.
3 https://geologyportal.dnr.wa.gov/
100% Basis of Design Report 13 July 2021
4 Schedule
Based on the elements of the design, Table 4 presents the preliminary schedule for construction.
Working days are considered Monday to Friday. Please note that this schedule is preliminary and
may be altered based on feedback from contractors.
Table 4
Preliminary Construction Schedule
Task Expected Time to Complete
Mobilization and Site Preparation 10 Working Days
Sheet Pile Installation 6 Working Days
Backfill and Grading 2 Working Days
Steel Cap Installation 6 Working Days
Site Cleanup and Restoration 5 Working Days
100% Basis of Design Report 14 July 2021
5 References
Anchor QEA, 2019. Parcel 86 Bank Erosion Assessment. Prepared for Port of Tacoma. December 2019.
Anchor QEA, 2020. Conceptual Design Options Evaluation. Prepared for Port of Tacoma. October
2020.
GTSoft, 2007. SupportIT Sheet Pile Design Software, User Guide, v 2.38. GTSoft, LTD, Prestwick,
United Kingdom.
Mauger, G.S., J.H. Casola, H.A. Morgan, R.L. Strauch, B. Jones, B. Curry, T.M. Busch Isaksen, L. Whitely
Binder, M.B. Krosby, and A.K. Snover, 2015. State of Knowledge: Climate Change in Puget
Sound. Report prepared for the Puget Sound Partnership and the National Oceanic and
Atmospheric Administration. Climate Impacts Group, University of Washington, Seattle.
Port of Tacoma, 2008. EV001-V27, Sheet 3 of 5.
Appendix A
SupportIT Model Documentation
© 2020 Microsoft Corporation © 2020 Maxar ©CNES (2020) Distribution Airbus DS
Center of Existing Manhole #8Center of Existing Manhole #7
HYLEBO
S CREEK
MARINE VIEW DRIVE
EXISTING FENCELINE
EXISTING MANHOLE #6
BNSF RAILROAD
PORT OF TACOMA03213640243701 TAYLOR WY
CALBAG METALS CO/HERBERT CONSTRUCTION50003504701602 MARINE VIEW DR
P86-B-01
DA-01E
A-01
BA-01
EXISTING MANOLE #8
EXISTING MANHOLE #9
EXISTING MANHOLE #7
14'
9'
9'
41'
9'
9'
0
5
10
15
AA-01
CA-01
FA-01
GA-01
A-01
SH #
PIER
CE C
OUNT
Y, W
ASHI
NGTO
NCO
NCEP
TUAL
LAY
OUT
OF P
ROPO
SED
SHEE
T PI
LE W
ALL
CONC
EPTU
AL D
ESIG
N AL
TERN
ATIV
ES
BIND
ING
EDG
E
THIS
DRA
WIN
G IS
THE
PRO
PERT
Y O
F TH
E PO
RT O
F TA
COM
A AN
D SH
ALL
NOT
BE U
SED
ON
OTH
ER W
ORK
, DIS
CLO
SED,
CO
PIED
, IN
WHO
LE O
R IN
PAR
T, W
ITHO
UT W
RITT
EN P
ERM
ISSI
ON
P.O
. BO
X 18
37 T
ACO
MA,
WA
9840
1 (2
53)3
83-5
841
BIND
ING
EDG
E
THIS
DRA
WIN
G IS
THE
PRO
PERT
Y O
F TH
E PO
RT O
F TA
COM
A AN
D SH
ALL
NOT
BE U
SED
ON
OTH
ER W
ORK
, DIS
CLO
SED,
CO
PIED
, IN
WHO
LE O
R IN
PAR
T, W
ITHO
UT W
RITT
EN P
ERM
ISSI
ON
PORT
OF
TACO
MA
FILE
: K:\P
roje
cts\
0092
-Por
t of T
acom
a\Pa
rcel
86
Shor
elin
e Re
pair
Proj
ect\_
Conc
eptu
al D
esig
n Al
tern
ative
s\00
92-W
K-00
1 (P
lan_
Sect
ion)
OF #
PARC
EL 8
6 SH
OREL
INE
REPA
IR P
ROJE
CT
LEGEND:
CROSS SECTION LOCATION AND DESIGNATION
EXISTING GEOTECHNICAL BORING LOCATION
PROPOSED STEEL WALL LOCATION (40' DEEP SHEETSECTION)
PROPOSED STEEL WALL LOCATION (25' DEEP SHEETSECTION)
PROPOSED STEEL WALL LOCATION (15' DEEP SHEETSECTION)
EXISTING CONTOURS (1' & 5' INTERVALS)
ORDINARY HIGH WATER (OHW, SEE NOTE 1)
MEAN HIGHER-HIGH WATER (MHHW), +11.78'
MEAN LOW WATER (MLW), +2.84'
PARCEL BOUNDARY AND IDENTIFICATION
PARCEL 86 PROPERTY BOUNDARY
EXISTING RIGHT-OF-WAY
50-FOOT FWHCA MARINE BUFFER
P86-B-01
SOURCE: AERIAL ©2020 MICROSOFT CORPORATION ©2020 DIGITALGLOBE©CNES (2020) DISTRIBUTION AIRBUS DS. SURVEY BY SITTS & HILL, DATEDJUNE 2020.HORIZONTAL DATUM: WASHINGTON STATE PLANE SOUTH ZONE, NORTHAMERICAN DATUM OF 1983/2011 (NAD83/2011), U.S. SURVEY FEETVERTICAL DATUM: MEAN LOWER LOW WATER (MLLW)
NOTES:1. LOCATION OF OHW MARK SHOWN ALONG SECTION E-E' WAS
APPROXIMATED BASED ON OBSERVATIONS ALONG ADJACENTNON-ERODED SHORELINE AREAS.
2. 40' DEEP SHEET PILE SECTION MAY CONSIST OF A BOX PILECONFIGURATION (I.E., TWO ROWS OF SHEET PILES WELDED TOGETHERTO INCREASE STRUCTURAL STIFFNESS). OTHER SECTIONS WILLCONSIST OF A SINGLE SHEET.
5
0321364024
NORTH
0
SCALE IN FEET
8 16
2.0° 0.00 ftConcrete
0.80 ftDense Gravel
2.00 ftML
10.05 ft
WL 4.00 ft20.0°4.00 ftML
150.0 psf
Toe = 6.05 ft
0
2
4
6
8
10
(ft)
Page: 1 Section A-A', B-B', C-C'Date: 4.13.21
Sheet: NZ19 Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.52 Toe: Cantilever
Maximum d (ft)3.00psf373.35.25ftlb/ft2770.40.00in0.0
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
Input DataDepth Of Excavation =
Surcharge = Slope (active) =
4.00150.0
2.0
ftpsfdegrees
Soil ProfileDepth (ft) Soil Name (pcf) ' (pcf) C (psf) Ca (psf) (°) (°) Ka Kac Kp Kpc
0.00 Concrete 135.00 71.00 4175.7 0.0 0.0 0.0 1.00 2.00 1.00 2.000.80 Dense Gravel 110.00 46.00 0.0 0.0 40.0 0.0 0.22 0.00 4.60 0.002.00 ML 100.00 36.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.00
25.00 SP-SM 115.00 51.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.0035.30 ML 95.00 31.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.0041.80 SP-SM 110.00 46.00 0.0 0.0 30.0 0.0 0.33 0.00 3.00 0.0045.60 SM 110.00 46.00 0.0 0.0 28.0 0.0 0.36 0.00 2.77 0.0055.30 SP-SM 130.00 61.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.00
Active Side
Soil ProfileDepth (ft) Soil Name (pcf) ' (pcf) C (psf) Ca (psf) (°) (°) Ka Kac Kp Kpc
0.00 ML 100.00 36.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.0025.00 SP-SM 115.00 51.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.0035.30 ML 95.00 31.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.0041.80 SP-SM 110.00 46.00 0.0 0.0 30.0 0.0 0.33 0.00 3.00 0.0045.60 SM 110.00 46.00 0.0 0.0 28.0 0.0 0.36 0.00 2.77 0.0055.30 SP-SM 130.00 61.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.00
Passive Side
Depth Of Active Water = Depth Of Passive Water =
Slope (passive) =
4.0017.0020.0
ftftdegrees
Water Density = Minimum Fluid Density =
64.0031.82
pcfpcf
SolutionSheetSheet Name E
(psi)I
(in4/ft)f
(psi)Z
(in³/ft) (ftlb/ft) Allowed Mmax b
(in)A
(in²/ft)W
(lb/ft)Upstand
(ft)Toe(ft)
Length(ft)
Arbed AZ18 3.04E+07 283.10 24966.8 41.33 85989.8 27.56 7.07 35.0 0.00 6.05 10.05Pressure Model: Terzaghi (m = 1.0; a = 0.4); Apply hydrostatic pressure in cohesive soils
Maximum Depth (ft)Maxima
Pressure 373.3psf 3.00Bending Moment 2770.4ftlb/ft 5.25Deflection 0.0in 0.00Shear Force 1096.0lb/ft 4.01
Page: 2 Section A-A', B-B', C-C'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.52 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
0 2 40-2-4-6-8-10Pressure (psf) x102
2
4
6
8
10
12d(ft)
0 4 8 12 16 20 24 280-4Bending Moment (ftlb/ft) x102
2
4
6
8
10
12d(ft)
0 2 4 6 8 10 120-2Shear Force (lb/ft) x102
2
4
6
8
10
12d(ft)
0 1 2Deflection (in) x10-2
2
4
6
8
10
12d(ft)
Page: 3 Section A-A', B-B', C-C'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.52 Toe: Cantilever
Maximum d (ft)3.00psf373.35.25ftlb/ft2770.44.01lb/ft1096.00.00in0.0
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
depth(ft)
P(psf)
M(ftlb/ft)
D(in)
F(lb/ft)
depth(ft)
P(psf)
M(ftlb/ft)
D(in)
F(lb/ft)
depth(ft)
P(psf)
M(ftlb/ft)
D(in)
F(lb/ft)
0.00 153.00.07 160.60.14 167.40.22 175.00.29 181.80.36 189.40.43 196.20.50 203.80.57 211.40.65 218.10.72 225.80.79 232.50.86 240.10.93 246.91.01 254.31.08 258.81.15 262.81.22 267.31.29 271.31.36 275.81.44 279.81.51 284.31.58 288.81.65 292.81.72 297.31.80 301.31.87 305.81.94 309.82.01 314.32.08 318.82.15 322.82.23 327.32.30 331.32.37 335.82.44 339.82.51 344.32.59 348.82.66 352.82.73 357.32.80 361.32.87 365.82.94 369.83.02 369.73.09 353.13.16 338.33.23 321.73.30 306.9
3.38 290.33.45 275.63.52 259.03.59 242.33.66 227.63.73 211.03.81 196.23.88 179.63.95 164.84.02 -848.34.09 -851.84.17 -855.04.24 -858.54.31 -861.74.38 -865.24.45 -868.34.52 -871.94.60 -875.44.67 -878.64.74 -882.14.81 -885.34.88 -888.84.96 -891.95.03 -895.55.10 -899.05.17 -902.25.24 -905.75.31 -908.85.39 -912.45.46 -915.55.53 -919.15.60 -922.65.67 -925.75.75 -929.35.82 -932.45.89 -936.05.96 -939.16.03 -942.76.10 -946.26.18 -949.36.25 -952.96.32 -956.06.39 -959.36.46 -958.16.54 -956.86.61 -955.66.68 -954.4
6.75 -953.16.82 -952.06.89 -950.76.97 -949.67.04 -948.37.11 -947.07.18 -945.97.25 -944.67.33 -943.47.40 -942.17.47 -941.07.54 -939.77.61 -938.47.68 -937.37.76 -936.07.83 -934.97.90 -933.67.97 -932.48.04 -931.18.12 -929.98.19 -928.78.26 -927.48.33 -926.38.40 -925.08.47 -923.98.55 -922.68.62 -921.38.69 -920.18.76 -918.98.83 -917.78.91 -916.48.98 -915.39.05 -914.09.12 -912.79.19 -911.69.26 -910.39.34 -909.29.41 -907.99.48 -906.79.55 -905.49.62 -904.29.70 -903.09.77 -901.79.84 -900.69.91 -899.39.98 -898.2
10.05 -897.0
-0.9-0.50.62.75.59.6
14.120.227.535.044.754.366.478.393.0
109.1124.7143.7161.8183.6204.4229.2255.7280.6310.1337.8370.6401.3437.4475.3510.5551.8590.2635.0676.6725.1775.6822.1876.4926.3984.4
1037.81099.91164.11222.81290.71352.6
1423.81488.61562.91638.71707.21785.51856.11936.62009.12091.32170.82237.32307.62366.02427.02477.12528.82575.62613.02650.42679.42707.22727.82746.12759.32766.82770.32769.92765.02754.82740.12720.52696.52668.12635.72599.12558.62514.62454.42415.92348.02305.12230.02182.92101.52033.81964.0
1892.41819.11744.31668.01590.61512.11432.81352.81272.31191.41110.41029.4948.6868.1788.2709.0630.6553.3477.2402.5329.3257.8188.4120.955.70.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
0.011.922.935.947.961.974.990.0
105.7120.1136.9152.3170.2186.6205.5224.9242.4262.5280.6301.2319.9341.2362.9382.4404.7424.8447.7468.4492.0515.9537.4562.0584.1609.3632.0657.9684.0707.6734.4758.5786.0810.7838.8866.0889.1914.0935.0
957.5976.4996.5
1015.41031.11047.51061.11075.31086.81081.81017.7960.5895.9838.3773.2715.1649.5583.6524.9458.5399.3332.4272.7205.4137.777.49.2-1.4-3.0-4.5-5.9-7.3-8.4-9.4
-10.2-11.1-11.6-12.2-12.6-12.8-13.0-13.0-12.8-12.6-12.2-11.6-11.0
-10.3-9.4-8.5-7.7-6.8-6.0-5.3-4.6-4.0-3.3-2.8-2.3-1.8-1.4-1.0-0.7-0.4-0.20.00.10.20.20.30.20.10.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
0.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
0.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
0.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
Page: 4 Section A-A', B-B', C-C'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.52 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
0 40Pressure (psf)Active Soil
x10
2
4
6
8
10
12d(ft)
00-14Pressure (psf)Passive Soil
x102
2
4
6
8
10
12d(ft)
0 40Pressure (psf)Active Water
x10
2
4
6
8
10
12d(ft)
0 10Pressure (psf)Passive Water
2
4
6
8
10
12d(ft)
0 7Pressure (psf)Min. Fluid
x102
2
4
6
8
10
12d(ft)
0 40-10Pressure (psf)Net
x102
2
4
6
8
10
12d(ft)
Page: 5 Section A-A', B-B', C-C'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.52 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
Design Report1.The standard surcharge is 150.0psf. The Piling Handbook recommends a minimum surcharge of 200.0psf.
2.Are water depths correct? Passive water depth is not normally below the active water depth AND excavation depth.
3.Terzaghi was used for the active pressure. Rankine was used for the passive pressure.
4.Total stress values are being used (i.e. C > 0). Note that the Piling Handbook and CIRIA SP95 recommend that effective stress values be used in 'long term' excavations.
5.BSPH approximation used for slope calculation. i.e. Pressure modified by 5% for each 5° of slope.
6.Maximum bending moment = 2770.4ftlb/ft and f = 24966.8psi. MINIMUM required sheet section modulus is: Z = 1.33in³/ft (= M/f). Sheet section modulus in this design is Z = 41.33in³/ft, and is satisfactory.
7.FOS = 1.52 (Net Pressure)This is the factor of safety against rotation about the toe.The FOS can be changed using 'Defined FOS' or 'Manual' in the 'Wall' page.
Page: 6 Section A-A', B-B', C-C'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.52 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
2.0° 0.00 ftConcrete
0.80 ftDense Gravel
2.00 ftML
13.77 ft
WL 4.00 ft
20.0°5.00 ftML
150.0 psf
Toe = 8.77 ft
0
2
4
6
8
10
12
(ft)
Page: 1 Section D-D'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.53 Toe: Cantilever
Maximum d (ft)3.28psf428.46.83ftlb/ft5349.90.00in0.0
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
Input DataDepth Of Excavation =
Surcharge = Slope (active) =
5.00150.0
2.0
ftpsfdegrees
Soil ProfileDepth (ft) Soil Name (pcf) ' (pcf) C (psf) Ca (psf) (°) (°) Ka Kac Kp Kpc
0.00 Concrete 135.00 71.00 4175.7 0.0 0.0 0.0 1.00 2.00 1.00 2.000.80 Dense Gravel 110.00 46.00 0.0 0.0 40.0 0.0 0.22 0.00 4.60 0.002.00 ML 100.00 36.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.00
25.00 SP-SM 115.00 51.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.0035.30 ML 95.00 31.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.0041.80 SP-SM 110.00 46.00 0.0 0.0 30.0 0.0 0.33 0.00 3.00 0.0045.60 SM 110.00 46.00 0.0 0.0 28.0 0.0 0.36 0.00 2.77 0.0055.30 SP-SM 125.00 61.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.00
Active Side
Soil ProfileDepth (ft) Soil Name (pcf) ' (pcf) C (psf) Ca (psf) (°) (°) Ka Kac Kp Kpc
0.00 ML 100.00 36.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.0025.00 SP-SM 115.00 51.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.0035.30 ML 95.00 31.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.0041.80 SP-SM 110.00 46.00 0.0 0.0 30.0 0.0 0.33 0.00 3.00 0.0045.60 SM 110.00 46.00 0.0 0.0 28.0 0.0 0.36 0.00 2.77 0.0055.30 SP-SM 130.00 61.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.00
Passive Side
Depth Of Active Water = Depth Of Passive Water =
Slope (passive) =
4.0017.0020.0
ftftdegrees
Water Density = Minimum Fluid Density =
64.0031.82
pcfpcf
SolutionSheetSheet Name E
(psi)I
(in4/ft)f
(psi)Z
(in³/ft) (ftlb/ft) Allowed Mmax b
(in)A
(in²/ft)W
(lb/ft)Upstand
(ft)Toe(ft)
Length(ft)
Arbed AZ18 3.04E+07 283.10 24966.8 33.50 69698.9 24.80 7.09 24.1 0.00 8.77 13.77Pressure Model: Terzaghi (m = 1.0; a = 0.4); Apply hydrostatic pressure in cohesive soils
Maximum Depth (ft)Maxima
Pressure 428.4psf 3.28Bending Moment 5349.9ftlb/ft 6.83Deflection 0.0in 0.00Shear Force 1636.3lb/ft 5.00
Page: 2 Section D-D'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.53 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
0 2 4 60-2-4-6-8-10Pressure (psf) x102
2
4
6
8
10
12
14d(ft)
0 1 2 3 4 5 6Bending Moment (ftlb/ft) x103
2
4
6
8
10
12
14d(ft)
0 2 4 6 8 10 12 14 16 180-2Shear Force (lb/ft) x102
2
4
6
8
10
12
14d(ft)
0 1 2 3 4Deflection (in) x10-2
2
4
6
8
10
12
14d(ft)
Page: 3 Section D-D'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.53 Toe: Cantilever
Maximum d (ft)3.28psf428.46.83ftlb/ft5349.95.00lb/ft1636.30.00in0.0
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
depth(ft)
P(psf)
M(ftlb/ft)
D(in)
F(lb/ft)
depth(ft)
P(psf)
M(ftlb/ft)
D(in)
F(lb/ft)
depth(ft)
P(psf)
M(ftlb/ft)
D(in)
F(lb/ft)
0.00 153.00.10 165.90.20 177.30.30 190.20.39 201.70.49 214.60.59 226.00.69 238.90.79 251.80.89 263.30.98 276.21.08 287.61.18 300.51.28 310.41.38 316.51.48 322.61.57 328.01.67 334.01.77 339.41.87 345.51.97 350.92.07 357.02.16 363.02.26 368.42.36 374.52.46 379.92.56 385.92.66 391.32.75 397.42.85 403.52.95 408.93.05 414.93.15 420.33.25 426.43.34 428.43.44 428.43.54 428.43.64 428.43.74 428.43.84 410.43.93 387.64.03 368.94.13 352.74.23 336.64.33 322.34.43 306.14.52 291.8
4.62 275.64.72 261.34.82 245.24.92 229.05.02 -848.35.11 -854.25.21 -859.55.31 -865.45.41 -870.65.51 -876.55.61 -882.45.70 -887.75.80 -893.65.90 -898.86.00 -904.76.10 -909.96.20 -915.86.29 -921.76.39 -927.06.49 -926.56.59 -925.96.69 -925.16.79 -924.56.88 -923.86.98 -923.17.08 -922.57.18 -921.77.28 -921.17.38 -920.47.47 -919.87.57 -919.07.67 -918.37.77 -917.77.87 -917.07.97 -916.48.06 -915.68.16 -915.08.26 -914.38.36 -913.68.46 -912.98.56 -912.28.65 -911.68.75 -910.98.85 -910.38.95 -909.59.05 -908.89.15 -908.2
9.24 -907.59.34 -906.89.44 -906.19.54 -905.59.64 -904.89.74 -904.19.83 -903.49.93 -902.7
10.03 -902.110.13 -901.410.23 -900.710.33 -900.010.42 -899.310.52 -898.710.62 -898.010.72 -897.310.82 -896.610.92 -896.011.01 -895.311.11 -894.611.21 -893.911.31 -893.211.41 -892.611.51 -891.911.60 -891.211.70 -890.511.80 -889.811.90 -889.212.00 -888.512.10 -887.812.19 -887.112.29 -886.512.39 -885.812.49 -885.112.59 -884.412.69 -883.712.78 -883.112.88 -882.412.98 -881.713.08 -881.013.18 -880.313.28 -879.713.37 -879.013.47 -878.313.57 -877.613.67 -877.013.77 -876.4
0.00.72.97.1
12.520.729.942.557.673.393.6
114.2140.2166.0198.2233.7268.2310.3350.7399.6446.1502.0561.7618.0685.1748.1822.8892.6975.1
1061.81142.51237.51325.61428.91524.61636.51753.11860.51985.62100.72234.32356.52497.72642.72774.52926.13063.6
3221.33363.93526.93692.63841.94005.74143.74290.34412.94542.14661.94760.54862.64945.35029.35095.85161.65217.65259.15296.55321.55340.25348.65348.05332.55306.35263.55214.15146.45076.14986.14885.34787.24667.94554.54419.34292.84144.13989.33847.13682.73533.13361.63206.83030.72853.22694.8
2516.52358.62182.12026.91854.71685.81539.01378.21239.81089.6961.8824.8695.8588.4476.5385.3292.9220.2149.892.051.920.14.10.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
0.016.632.451.569.591.1
111.4135.5161.0184.7212.7238.6269.1297.3329.7362.8392.7426.9457.9493.3525.4562.0599.2632.9671.3706.0745.6781.3822.1863.5900.9943.5981.9
1025.71065.01109.31153.61193.01237.21275.81316.91351.51388.71424.21454.41486.81514.2
1543.41568.01594.11618.51626.61538.71460.11371.11291.51201.31110.51029.3937.4855.2762.1678.9584.6489.8405.0309.3224.3128.743.8-0.9-2.5-3.8-5.3-6.5-7.8-8.9
-10.0-11.1-12.0-13.0-13.8-14.6-15.2-15.9-16.5-17.0-17.4-17.8-18.1-18.3-18.5-18.6-18.6
-18.6-18.5-18.3-18.1-17.8-17.4-17.0-16.5-16.0-15.3-14.7-13.9-13.0-12.1-11.1-10.2-9.0-7.9-6.6-5.3-4.0-2.5-1.10.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
0.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
0.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
0.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
Page: 4 Section D-D'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.53 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
0 45Pressure (psf)Active Soil
x10
2
4
6
8
10
12
14d(ft)
00-16Pressure (psf)Passive Soil
x102
2
4
6
8
10
12
14d(ft)
0 7Pressure (psf)Active Water
x102
2
4
6
8
10
12
14d(ft)
0 10Pressure (psf)Passive Water
2
4
6
8
10
12
14d(ft)
0 9Pressure (psf)Min. Fluid
x102
2
4
6
8
10
12
14d(ft)
0 60-10Pressure (psf)Net
x102
2
4
6
8
10
12
14d(ft)
Page: 5 Section D-D'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.53 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
Design Report1.The standard surcharge is 150.0psf. The Piling Handbook recommends a minimum surcharge of 200.0psf.
2.Are water depths correct? Passive water depth is not normally below the active water depth AND excavation depth.
3.Terzaghi was used for the active pressure. Rankine was used for the passive pressure.
4.Total stress values are being used (i.e. C > 0). Note that the Piling Handbook and CIRIA SP95 recommend that effective stress values be used in 'long term' excavations.
5.BSPH approximation used for slope calculation. i.e. Pressure modified by 5% for each 5° of slope.
6.Maximum bending moment = 5349.9ftlb/ft and f = 24966.8psi. MINIMUM required sheet section modulus is: Z = 2.57in³/ft (= M/f). Sheet section modulus in this design is Z = 33.50in³/ft, and is satisfactory.
7.FOS = 1.53 (Net Pressure)This is the factor of safety against rotation about the toe.The FOS can be changed using 'Defined FOS' or 'Manual' in the 'Wall' page.
Page: 6 Section D-D'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.53 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
2.0° 0.00 ftConcrete 0.80 ftDense Gravel
2.00 ftML
25.00 ftSP-SM
31.55 ft
WL 4.00 ft
20.0°8.00 ftML
SP-SM25.00 ft
WL17.00 ft
150.0 psf
Toe = 23.55 ft
0
4
8
12
16
20
24
28
(ft)
Page: 1 Section E-E'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.49 Toe: Cantilever
Maximum d (ft)6.00psf721.5
13.80ftlb/ft27083.50.00in1.1
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
Input DataDepth Of Excavation =
Surcharge = Slope (active) =
8.00150.0
2.0
ftpsfdegrees
Soil ProfileDepth (ft) Soil Name (pcf) ' (pcf) C (psf) Ca (psf) (°) (°) Ka Kac Kp Kpc
0.00 Concrete 135.00 71.00 4175.7 0.0 0.0 0.0 1.00 2.00 1.00 2.000.80 Dense Gravel 110.00 46.00 0.0 0.0 40.0 0.0 0.22 0.00 4.60 0.002.00 ML 100.00 36.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.00
25.00 SP-SM 115.00 51.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.0035.30 ML 95.00 31.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.0041.80 SP-SM 110.00 46.00 0.0 0.0 30.0 0.0 0.33 0.00 3.00 0.0045.60 SM 110.00 46.00 0.0 0.0 28.0 0.0 0.36 0.00 2.77 0.0055.30 SP-SM 125.00 61.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.00
Active Side
Soil ProfileDepth (ft) Soil Name (pcf) ' (pcf) C (psf) Ca (psf) (°) (°) Ka Kac Kp Kpc
0.00 ML 100.00 36.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.0025.00 SP-SM 115.00 51.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.0035.30 ML 95.00 31.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.0041.80 SP-SM 110.00 46.00 0.0 0.0 30.0 0.0 0.33 0.00 3.00 0.0045.60 SM 110.00 46.00 0.0 0.0 28.0 0.0 0.36 0.00 2.77 0.0055.30 SP-SM 130.00 61.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.00
Passive Side
Depth Of Active Water = Depth Of Passive Water =
Slope (passive) =
4.0017.0020.0
ftftdegrees
Water Density = Minimum Fluid Density =
64.0031.82
pcfpcf
SolutionSheetSheet Name E
(psi)I
(in4/ft)f
(psi)Z
(in³/ft) (ftlb/ft) Allowed Mmax b
(in)A
(in²/ft)W
(lb/ft)Upstand
(ft)Toe(ft)
Length(ft)
Arbed AZ18 3.04E+07 283.10 24966.8 35.10 73027.9 24.80 7.07 24.0 0.00 23.55 31.55Pressure Model: Terzaghi (m = 1.0; a = 0.4); Apply hydrostatic pressure in cohesive soils
Maximum Depth (ft)Maxima
Pressure 721.5psf 6.00Bending Moment 27083.5ftlb/ft 13.80Deflection 1.1in 0.00Shear Force 4196.3lb/ft 8.02
Page: 2 Section E-E'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.49 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
0 4 80-4-8-12-16-20-24-28-32Pressure (psf) x102
4
8
12
16
20
24
28
32d(ft)
0 4 8 12 16 20 24 28Bending Moment (ftlb/ft) x103
4
8
12
16
20
24
28
32d(ft)
0 5 10 15 20 25 30 35 40 450-5-10Shear Force (lb/ft) x102
4
8
12
16
20
24
28
32d(ft)
0 1 2Deflection (in)
4
8
12
16
20
24
28
32d(ft)
Page: 3 Section E-E'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.49 Toe: Cantilever
Maximum d (ft)6.00psf721.5
13.80ftlb/ft27083.58.02lb/ft4196.30.00in1.1
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
depth(ft)
P(psf)
M(ftlb/ft)
D(in)
F(lb/ft)
depth(ft)
P(psf)
M(ftlb/ft)
D(in)
F(lb/ft)
depth(ft)
P(psf)
M(ftlb/ft)
D(in)
F(lb/ft)
0.00 153.00.23 191.00.45 224.80.68 262.80.90 296.61.13 334.61.35 368.41.58 406.51.80 444.52.03 476.62.25 498.72.48 518.32.70 540.32.93 559.93.16 582.03.38 593.63.61 593.63.83 593.64.06 597.04.28 612.14.51 625.64.73 640.84.96 655.95.18 669.45.41 684.55.63 698.05.86 713.16.09 710.26.31 673.36.54 636.36.76 603.46.99 566.47.21 533.57.44 496.57.66 463.67.89 426.68.11 -743.98.34 -742.68.56 -741.18.79 -739.79.02 -738.29.24 -736.99.47 -735.49.69 -733.99.92 -732.6
10.14 -731.110.37 -729.8
10.59 -728.310.82 -727.011.04 -725.511.27 -724.011.49 -722.611.72 -721.211.95 -719.812.17 -718.312.40 -717.012.62 -715.512.85 -714.013.07 -712.713.30 -711.213.52 -709.913.75 -708.413.97 -707.114.20 -705.614.42 -704.114.65 -702.714.88 -701.215.10 -699.915.33 -698.415.55 -697.115.78 -695.616.00 -694.116.23 -692.816.45 -691.316.68 -690.016.90 -688.517.13 -689.817.35 -693.617.58 -697.417.81 -700.718.03 -704.518.26 -707.918.48 -711.718.71 -715.018.93 -718.819.16 -722.619.38 -726.019.61 -729.819.83 -733.120.06 -736.920.28 -740.320.51 -744.120.74 -747.920.96 -751.2
21.19 -755.021.41 -758.421.64 -762.221.86 -765.522.09 -769.322.31 -773.122.54 -776.522.76 -780.322.99 -783.623.21 -787.423.44 -790.823.67 -794.623.89 -798.424.12 -801.724.34 -805.524.57 -808.924.79 -812.725.02 -815.625.24 -2245.225.47 -2276.525.69 -2304.225.92 -2335.526.14 -2363.226.37 -2394.526.60 -2422.326.82 -2453.527.05 -2484.827.27 -2512.527.50 -2543.827.72 -2571.527.95 -2602.828.17 -2630.628.40 -2661.828.62 -2693.128.85 -2720.829.07 -2752.129.30 -2779.829.53 -2811.129.75 -2838.929.98 -2870.130.20 -2901.430.43 -2929.130.65 -2960.430.88 -2988.131.10 -3019.431.33 -3047.231.55 -3074.9
0.04.2
16.843.078.5
134.3199.6292.6408.3532.1696.5866.1
1084.31303.71580.21889.22191.92563.82922.33357.23772.74273.14809.55317.25923.76495.17174.87812.58567.39359.9
10094.410952.611742.112658.513496.514463.815449.716301.417220.218002.218842.719555.120317.621038.921645.622289.322827.2
23393.723863.024352.524801.425166.325538.725835.826132.026361.526581.726761.926888.426993.227052.827082.327078.827050.626996.626926.626822.826707.926553.026392.026184.525948.525714.725424.025141.024794.324460.824057.323625.023217.222733.022280.621747.921254.120676.520076.619525.418886.018301.217625.817010.616302.815579.114923.5
14172.813494.612720.412022.911228.610425.19704.08885.98153.37324.16583.25746.34906.94159.33317.72569.71729.3984.1311.514.30.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
0.041.285.5
143.7203.1278.3352.8445.1546.4643.9759.7867.0992.7
1108.81244.31384.31509.31650.01775.11918.52049.02199.22353.02492.72653.22798.92966.33117.23280.63435.23565.23703.33818.73940.24040.84145.84118.13961.83786.23630.43455.53300.43126.12952.22798.02624.82471.1
2298.52145.51973.61802.11649.91479.01327.51157.31006.3836.8667.6517.5349.0199.531.7-15.3-38.6-62.2-83.5
-107.8-129.7-154.7-177.1-202.8-228.8-252.1-278.8-302.8-330.1-354.5-381.1-406.9-429.1-453.1-473.8-496.2-515.3-536.0-555.8-572.7-590.8-606.1-622.5-636.3-651.0-664.9-676.4
-688.5-698.5-709.0-717.5-726.2-734.1-740.3-746.4-751.1-755.6-758.8-761.6-763.4-764.3-764.5-763.9-762.4-760.3-422.7-77.7
0.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
1.11.01.01.01.01.01.00.90.90.90.90.90.90.80.80.80.80.80.80.70.70.70.70.70.70.60.60.60.60.60.60.50.50.50.50.50.50.50.40.40.40.40.40.40.40.30.3
0.30.30.30.30.30.30.20.20.20.20.20.20.20.20.20.20.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
0.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
Page: 4 Section E-E'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.49 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
0 6Pressure (psf)Active Soil
x102
4
8
12
16
20
24
28
32d(ft)
00-40Pressure (psf)Passive Soil
x102
4
8
12
16
20
24
28
32d(ft)
0 18Pressure (psf)Active Water
x102
4
8
12
16
20
24
28
32d(ft)
00-10Pressure (psf)Passive Water
x102
4
8
12
16
20
24
28
32d(ft)
0 24Pressure (psf)Min. Fluid
x102
4
8
12
16
20
24
28
32d(ft)
0 80-32Pressure (psf)Net
x102
4
8
12
16
20
24
28
32d(ft)
Page: 5 Section E-E'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.49 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
Design Report1.The standard surcharge is 150.0psf. The Piling Handbook recommends a minimum surcharge of 200.0psf.
2.Are water depths correct? Passive water depth is not normally below the active water depth AND excavation depth.
3.Terzaghi was used for the active pressure. Rankine was used for the passive pressure.
4.Total stress values are being used (i.e. C > 0). Note that the Piling Handbook and CIRIA SP95 recommend that effective stress values be used in 'long term' excavations.
5.BSPH approximation used for slope calculation. i.e. Pressure modified by 5% for each 5° of slope.
6.Maximum bending moment = 27083.5ftlb/ft and f = 24966.8psi. MINIMUM required sheet section modulus is: Z = 13.02in³/ft (= M/f). Sheet section modulus in this design is Z = 35.10in³/ft, and is satisfactory.
7.FOS = 1.49 (Net Pressure)This is the factor of safety against rotation about the toe.The FOS can be changed using 'Defined FOS' or 'Manual' in the 'Wall' page.
Page: 6 Section E-E'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.49 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
2.0° 0.00 ftConcrete
0.80 ftDense Gravel
2.00 ftML
18.47 ft
WL 4.00 ft
20.0°6.00 ftML
WL17.00 ft
150.0 psf
Toe = 12.47 ft
0
2
4
6
8
10
12
14
16
18
(ft)
Page: 1 Section F-F'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.52 Toe: Cantilever
Maximum d (ft)4.49psf515.08.70ftlb/ft9618.00.00in0.1
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
Input DataDepth Of Excavation =
Surcharge = Slope (active) =
6.00150.0
2.0
ftpsfdegrees
Soil ProfileDepth (ft) Soil Name (pcf) ' (pcf) C (psf) Ca (psf) (°) (°) Ka Kac Kp Kpc
0.00 Concrete 135.00 71.00 4175.7 0.0 0.0 0.0 1.00 2.00 1.00 2.000.80 Dense Gravel 110.00 46.00 0.0 0.0 40.0 0.0 0.22 0.00 4.60 0.002.00 ML 100.00 36.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.00
25.00 SP-SM 115.00 51.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.0035.30 ML 95.00 31.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.0041.80 SP-SM 110.00 46.00 0.0 0.0 30.0 0.0 0.33 0.00 3.00 0.0045.60 SM 110.00 46.00 0.0 0.0 28.0 0.0 0.36 0.00 2.77 0.0055.30 SP-SM 125.00 61.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.00
Active Side
Soil ProfileDepth (ft) Soil Name (pcf) ' (pcf) C (psf) Ca (psf) (°) (°) Ka Kac Kp Kpc
0.00 ML 100.00 36.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.0025.00 SP-SM 115.00 51.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.0035.30 ML 95.00 31.00 500.0 0.0 0.0 0.0 1.00 2.00 1.00 2.0041.80 SP-SM 110.00 46.00 0.0 0.0 30.0 0.0 0.33 0.00 3.00 0.0045.60 SM 110.00 46.00 0.0 0.0 28.0 0.0 0.36 0.00 2.77 0.0055.30 SP-SM 130.00 61.00 0.0 0.0 32.0 0.0 0.31 0.00 3.25 0.00
Passive Side
Depth Of Active Water = Depth Of Passive Water =
Slope (passive) =
4.0017.0020.0
ftftdegrees
Water Density = Minimum Fluid Density =
64.0031.82
pcfpcf
SolutionSheetSheet Name E
(psi)I
(in4/ft)f
(psi)Z
(in³/ft) (ftlb/ft) Allowed Mmax b
(in)A
(in²/ft)W
(lb/ft)Upstand
(ft)Toe(ft)
Length(ft)
Arbed AZ18 3.04E+07 283.10 24966.8 35.08 72986.3 27.56 7.07 24.0 0.00 12.47 18.47Pressure Model: Terzaghi (m = 1.0; a = 0.4); Apply hydrostatic pressure in cohesive soils
Maximum Depth (ft)Maxima
Pressure 515.0psf 4.49Bending Moment 9618.0ftlb/ft 8.70Deflection 0.1in 0.00Shear Force 2341.2lb/ft 6.00
Page: 2 Section F-F'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.52 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
0 2 4 60-2-4-6-8-10Pressure (psf) x102
2
4
6
8
10
12
14
16
18
20d(ft)
0 1 2 3 4 5 6 7 8 9 100-1Bending Moment (ftlb/ft) x103
2
4
6
8
10
12
14
16
18
20d(ft)
0 4 8 12 16 20 240-4Shear Force (lb/ft) x102
2
4
6
8
10
12
14
16
18
20d(ft)
0 1 2Deflection (in) x10-1
2
4
6
8
10
12
14
16
18
20d(ft)
Page: 3 Section F-F'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.52 Toe: Cantilever
Maximum d (ft)4.49psf515.08.70ftlb/ft9618.06.00lb/ft2341.20.00in0.1
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
depth(ft)
P(psf)
M(ftlb/ft)
D(in)
F(lb/ft)
depth(ft)
P(psf)
M(ftlb/ft)
D(in)
F(lb/ft)
depth(ft)
P(psf)
M(ftlb/ft)
D(in)
F(lb/ft)
0.00 153.00.13 172.50.26 189.80.40 209.30.53 226.70.66 246.20.79 263.50.92 283.01.06 302.51.19 319.81.32 339.31.45 356.61.58 369.91.71 378.11.85 387.41.98 396.72.11 404.92.24 414.22.37 422.52.51 431.72.64 440.02.77 449.32.90 458.63.03 466.83.17 476.13.30 483.53.43 483.53.56 483.53.69 483.53.83 483.53.96 483.54.09 489.44.22 497.34.35 506.14.49 514.04.62 497.14.75 475.44.88 456.25.01 434.55.14 415.35.28 393.65.41 374.45.54 352.75.67 331.15.80 311.85.94 290.26.07 -851.6
6.20 -860.26.33 -867.86.46 -871.76.60 -871.46.73 -871.16.86 -870.86.99 -870.57.12 -870.27.26 -870.07.39 -869.67.52 -869.37.65 -869.17.78 -868.77.92 -868.58.05 -868.28.18 -867.98.31 -867.68.44 -867.38.57 -867.08.71 -866.78.84 -866.48.97 -866.19.10 -865.89.23 -865.59.37 -865.29.50 -864.99.63 -864.69.76 -864.39.89 -864.0
10.03 -863.710.16 -863.410.29 -863.110.42 -862.810.55 -862.510.69 -862.210.82 -861.910.95 -861.611.08 -861.311.21 -861.011.35 -860.711.48 -860.411.61 -860.211.74 -859.811.87 -859.612.00 -859.312.14 -858.912.27 -858.7
12.40 -858.412.53 -858.112.66 -857.812.80 -857.512.93 -857.213.06 -856.913.19 -856.613.32 -856.313.46 -856.013.59 -855.713.72 -855.413.85 -855.113.98 -854.814.12 -854.514.25 -854.214.38 -853.914.51 -853.614.64 -853.314.78 -853.014.91 -852.715.04 -852.415.17 -852.115.30 -851.815.43 -851.515.57 -851.315.70 -850.915.83 -850.615.96 -850.416.09 -850.016.23 -849.816.36 -849.516.49 -849.216.62 -848.916.75 -848.616.89 -848.317.02 -848.417.15 -850.317.28 -852.617.41 -854.517.55 -856.717.68 -859.017.81 -860.917.94 -863.118.07 -865.118.21 -867.318.34 -869.318.47 -871.3
0.01.45.4
13.323.739.557.682.7
113.2145.2187.0229.6284.0338.3406.3481.7555.1645.1731.7836.8937.2
1058.11187.71310.21456.61594.31758.01911.32092.62283.12460.22668.32861.13087.13296.13540.53794.44027.84298.74546.44832.75093.55393.65700.65978.76297.36583.6
6893.37154.77433.17694.87913.48143.58334.08532.68695.18862.29012.59132.29251.19342.79430.29493.99549.89589.29610.19618.09606.19568.29513.79429.89323.49210.69064.68918.68737.38561.88349.38122.17908.67656.67423.17150.66900.76611.96316.16048.45742.85468.15156.84879.04566.24254.33978.8
3671.83402.63104.82845.52561.12285.42048.61792.71575.31343.41149.2945.4758.2606.7454.1335.2221.4138.968.121.72.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
0.022.745.273.0
100.0132.9164.5202.5243.2281.7327.6370.6421.2467.4520.5575.0624.4681.3732.9792.2846.0907.7970.7
1027.81093.21152.51219.51279.11346.11413.21472.81540.11601.01670.61733.51803.81871.01928.31989.92042.12098.02145.22195.42242.72282.12323.72288.9
2170.42064.11943.51822.81715.51594.91487.71367.11260.01139.51019.0912.0791.7684.7564.4457.5337.4217.2110.4
-0.1-1.0-1.9-2.7-3.5-4.3-5.0-5.8-6.4-7.0-7.5-8.1-8.6-9.0-9.5-9.8
-10.2-10.5-10.7-11.0-11.1-11.3-11.4-11.4-11.5-11.5-11.4-11.3
-11.2-11.0-10.8-10.6-10.3-9.9-9.6-9.1-8.7-8.2-7.7-7.1-6.5-5.9-5.2-4.5-3.7-3.0-2.1-1.2-0.30.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
0.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.10.00.00.00.00.00.00.00.00.00.00.0
0.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
0.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0
Page: 4 Section F-F'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.52 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
0 50Pressure (psf)Active Soil
x10
2
4
6
8
10
12
14
16
18
20d(ft)
00-18Pressure (psf)Passive Soil
x102
2
4
6
8
10
12
14
16
18
20d(ft)
0 10Pressure (psf)Active Water
x102
2
4
6
8
10
12
14
16
18
20d(ft)
0 10Pressure (psf)Passive Water
2
4
6
8
10
12
14
16
18
20d(ft)
0 12Pressure (psf)Min. Fluid
x102
2
4
6
8
10
12
14
16
18
20d(ft)
0 60-10Pressure (psf)Net
x102
2
4
6
8
10
12
14
16
18
20d(ft)
Page: 5 Section F-F'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.52 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org
Design Report1.The standard surcharge is 150.0psf. The Piling Handbook recommends a minimum surcharge of 200.0psf.
2.Are water depths correct? Passive water depth is not normally below the active water depth AND excavation depth.
3.Terzaghi was used for the active pressure. Rankine was used for the passive pressure.
4.Total stress values are being used (i.e. C > 0). Note that the Piling Handbook and CIRIA SP95 recommend that effective stress values be used in 'long term' excavations.
5.BSPH approximation used for slope calculation. i.e. Pressure modified by 5% for each 5° of slope.
6.Maximum bending moment = 9618.0ftlb/ft and f = 24966.8psi. MINIMUM required sheet section modulus is: Z = 4.62in³/ft (= M/f). Sheet section modulus in this design is Z = 35.08in³/ft, and is satisfactory.
7.FOS = 1.52 (Net Pressure)This is the factor of safety against rotation about the toe.The FOS can be changed using 'Defined FOS' or 'Manual' in the 'Wall' page.
Page: 6 Section F-F'Date: 4.13.21
Sheet: NZ19Works: PermanentPressure: Terzaghi (m = 1.0; a = 0.4)Analysis: Net Pressure
FOS: 1.52 Toe: Cantilever
Anchor QEA, LLC 1201 3rd Avenue Suite 2600Seattle, WA 98101Tel: 206-287-9130Fax: 206-287-9131
SupportIT, v2.38© 1997 - 2020, GTSoft Ltd.Tel/Fax: +44 (0)1292 477754
Email: [email protected]: www.GTSoft.org