Department of Port Control
Center for Regional Economic Initiatives
February 20051
Doan Brook Stream Restoration ProjectDoan Brook Stream Restoration Project
Center for Regional Economic Initiatives
February 2005
Department of Port Control
Center for Regional Economic Initiatives
February 20052
Doan Brook Restoration Doan Brook Restoration Project AreaProject Area
Rockefeller Park Subwatershed
Department of Port Control
Center for Regional Economic Initiatives
February 20053
Environmental Restoration Goals Environmental Restoration Goals
Reduction of high flow velocity during rainstorms
Reduction of flooding in Rockefeller Park
Development of stable stream-side vegetation
Maintain stable stream channel features
Improve fish population in Doan Brook
Improve recreational and educational uses
Department of Port Control
Center for Regional Economic Initiatives
February 20054
Doan Brook Watershed IssuesDoan Brook Watershed IssuesFlooding
Department of Port Control
Center for Regional Economic Initiatives
February 20055
Doan Brook Watershed IssuesDoan Brook Watershed IssuesDeteriorating walls
Department of Port Control
Center for Regional Economic Initiatives
February 20056
Doan Brook Watershed IssuesDoan Brook Watershed IssuesTrash and Debris
Department of Port Control
Center for Regional Economic Initiatives
February 20057
Doan Brook Watershed Issues Narrow stream channel
Department of Port Control
Center for Regional Economic Initiatives
February 20058
Improving Existing Conditions Improving Existing Conditions Replacement of check dams
Department of Port Control
Center for Regional Economic Initiatives
February 20059
Improving Existing ConditionsFlood plain creation
Department of Port Control
Center for Regional Economic Initiatives
February 200510
1800 Gal. Per ft. 1800 Gal.
Per ft.
Proposed Doan BrookChannel
Improving Existing Conditions
2400 Gal. Per ft.(Additional flood capacity)
Flood hydraulics
Existing Grade Level
Existing Doan BrookChannel
Department of Port Control
Center for Regional Economic Initiatives
February 200511
Project HistoryProject History
Project required by Ohio EPA Section 401 Permit Waiver Findings & Orders April 2001Project required by the Army Corps of Engineers Section 404 Permit May 2001Doan Brook restoration design commence Sept 2001Doan Brook 60% design completed April 2002Section 106 process commence (required under the National Historic Preservation Act) May 2002Section 106 completed December 2004Doan Brook 95% design completed December 2004
Department of Port Control
Center for Regional Economic Initiatives
February 200512
Section 106 ProcessSection 106 Process
Required by Army Corps of Engineers Section 404 Permit for airport expansion
Required under the National Historic Preservation Act to minimize the impacts of the restoration design on the historic resource of Rockefeller Park
Department of Port Control
Center for Regional Economic Initiatives
February 200513
Department of Port Control
Center for Regional Economic Initiatives
February 200514
Project Design Project Design at Rockefeller Lagoon Areaat Rockefeller Lagoon Area
Department of Port Control
Center for Regional Economic Initiatives
February 200515
Project Design at Sowinski Park Project Design at Sowinski Park
Department of Port Control
Center for Regional Economic Initiatives
February 200516
MOA RequirementsMOA Requirements
Nominate Rockefeller Park to the National Registry of Historic Places
Develop Rockefeller Park master plan
Submit final construction plans to Consulting Parties for review
Allow Consulting Parties opportunity to salvage stone wall material slated for removal
Develop construction project signage program
Establish an adaptive management fund
Monitor stream restoration for five years
Department of Port Control
Center for Regional Economic Initiatives
February 200517
MOA StatusMOA Status
Rockefeller Park nomination to the National Registry of Historic Places complete
100% design plans submitted to Consulting Parties complete
Internal coordination on Rockefeller Park Master Plan commenced
Restoration monitoring plan under development
Signage program under development
$250,000 post construction adaptive management fund established
Department of Port Control
Center for Regional Economic Initiatives
February 200518
MOA RequirementsMOA Requirements
Protect contributing trees during construction
Remove dead trees and some invasive trees within project limits
Eliminate invasive trees that threaten stone walls within the project limits
Provide replacement trees for those that expire after planting
Protect stone walls during construction
Construct new walls using form lined concrete and closely match existing stone pattern/color
Department of Port Control
Center for Regional Economic Initiatives
February 200519
Key Stakeholders in the Doan Brook Restoration Project
Regulatory:
Ohio Environmental Protection AgencyArmy Corps of EngineersAdvisory Council for Historic PreservationOhio Historic Preservation Office
Elected Officials:
Mayor Jane L. CampbellCleveland City CouncilCongressman Dennis KucinichCongresswoman Stephanie Tubbs JonesCouncilwoman Sabra Pierce ScottCouncilman Kevin Conwell
City of Cleveland:
Department of Port ControlDepartment of Water Pollution ControlDepartment of Parks, Recreation and MaintenanceCleveland Planning CommissionCleveland Landmarks Commission
Community:
City of Shaker HeightsCity of Cleveland HeightsNEORSDUniversity Circle IncorporatedShaker Lakes Nature CenterDoan Brook Watershed PartnershipEast Boulevard/Herrick Road Street ClubSt. Clair Superior CoalitionGlenville Development CorporationHolden Parks TrustCleveland Cultural Gardens Federation