damage assessment & remediation plan for
TRANSCRIPT
DAMAGE ASSESSMENT & REMEDIATION PLAN
FOR
“COMMERCIAL COMPLEX “SPAZE BOULEVARD-1””
at
Village-Tikri, Sector-47, Gurgaon, Haryana
Developed by
M/s Spaze Towers Pvt. Ltd.
PREPARED BY:
M/s Perfact Researchers Pvt. Ltd. (NABL Accredited Testing Laboratory as per ISO/IEC 17025:2005, OSHAS 18001:2007 Certified Laboratory)
5th Floor, NN Mall, Sector 3, Rohini, New Delhi-110085
&
M/s Perfact Envirosolutions Pvt. Ltd. (NABET Registered Vide List of accredited Consultants organization / Rev 70/11th Oct. 2018 at S.No.-116)
5th Floor, NN Mall, Mangalam Palace,
Sector 3, Rohini, New Delhi-110085
Email: [email protected]; Phone: 011- 49281360
Contents
CHAPTER 1: INTRODUCTION ................................................................................................................................................. 3
CHAPTER 2: METHODOLOGY OF ASSESSMENT ..................................................................................................................... 4
2.1 CRITERIA OF ASSESSMENT....................................................................................................................................... 5
2.2 Objectives of Remediation Plan ............................................................................................................................... 5
2.3 Natural and Community Resource Augmentation Plan: ......................................................................................... 6
CHAPTER 3: DAMAGE ASSESSMENT AND REMEDIATION MEASURES ................................................................................... 7
3.1 Environmental Damage Assessed and its Remediation .......................................................................................... 7
3.2 Damage Matrix .....................................................................................................................................................12
3.3 Impact summary ...................................................................................................................................................14
CHAPTER 4: COST SUMMARY..............................................................................................................................................15
4.1 Remediation Plan ..................................................................................................................................................15
4.2 Augmentation Plan ...............................................................................................................................................16
List of Tables
Table 1: Project Details ........................................................................................................................... 3
Table 2: Criteria to assess the impact due to construction .................................................................... 5
Table 3: Matrix for Assessment of Damage Scale ................................................................................... 5
Table 4: Damage assessment and Remediation of Environmental components ................................... 8
Table 5: Impact Summary as per construction status .......................................................................... 14
Table 6: Cost summary.......................................................................................................................... 15
Chapter 1: INTRODUCTION
The project Commercial Complex “Spaze Boulevard I” is situated at Village Tikri, Sector 47, Gurgaon,
Haryana is being developed by M/s Spaze Towers Pvt. Ltd. The total plot area and built-up area of
the project site is 11,537.50 sqm (2.85 acres) and 29,523.05 sqm respectively and the net plot area of
the project is 8653.43 sqm. This commercial project has provided retail spaces, luxury stores, BANKS,
restaurants, cafe and Office spaces
The total built-up area of the project will be 29523.05 sqm. Hence, the project falls under Category
“B” Schedule 8 (a) of EIA notification, 2006. However, as per the notification vide S.O. 804(E) dated
14.03.2017 the project was submitted to MoEF&CC under violation category. Subsequently, it was
considered in EAC meeting dated 19.02.2018 and thereafter, TOR was granted by MoEF&CC vide its
letter no. F.No. 23-39/2018-IA-III dated 7th June, 2018.
Now as per amendment in notification vide S.O. 1030(E) dated 8th March,2018 & OM no.
Z-11013/22/2017-IA. II (M) dated 15.03.2018 & 16.03.2018, the project falls under category ‘B’, of
Schedule 8(a) & is exempted from Public Hearing and will be appraised by SEAC/SEIAA, Haryana and
the same was submitted in Haryana SEAC on 11.07.2018 but was not appraised and now the tenure
of the committee has been completed.
Hence, in view of the aforesaid notification, a Damage Assessment and Remediation plan is required
to explain the extent of damage done due to construction.
Assessment of ecological damage with respect to air, water, land and other environmental attributes
has been done and EMP has been prepared comprising remediation plan and natural and community
resource augmentation plan corresponding to the ecological damage assessed and economic benefits
derived due to violation.
Table 1: Project Details
S. No Particulars Unit Total
1. Cost of project Rs. Crore 69.11
2. Total Plot Area sqm 11537.50
3. Area under deduction sqm 2884.07
4. Net Plot Area sqm 8653.43
5. Ground Coverage (Permissible) sqm 3461.37
6. Ground Coverage (Proposed) sqm 3461.26
7. F.A.R (Permissible) sqm 15143.50
8. F.A.R (Proposed) sqm 15141.25
9. Total Basement area sqm 11770.58
10. Non-FAR Area sqm 2611.22
11. Total Built up Area (FAR+ Non-FAR+ Basement Area)
sqm 29523.05
12. Green Area (20 %) sqm 1730.68
13. Road Area & open area including surface parking
sqm 3461.49
14. No. of Floors - G+8
15. Levels of Basement - 3
16. Height of Building m 42
17. Parking required ECS 202
18. Parking proposed ECS 268
19. Total Power Load KW 1800
20. Power Backup KVA 2x1010 kVA and 1x500 kVA
Chapter 2: METHODOLOGY OF ASSESSMENT
As per notification vide S.O. 804(E) dated 14.03.2017 it has been notified that the violation cases/non-
Compliance will involve the assessment of ecological damage, remediation plan and natural and
community resource augmentation plan.
We have collected and analysed the data, for assessment of ecological damage, preparation of
remediation plan and natural and community resource augmentation plan and following
methodology will be adopted.
The overall impact on air, water, noise, soil and land environment will be assessed. In addition, it will
be weighed against the positive impact created on the socioeconomic scenario. To estimate the
impact produced, a framework has been designed as given ahead:
• The place of activity is permissible for the purpose (like it should not fall in eco-sensitive
zones etc.)
• Environmental Sensitivity to be clearly defined
• Status of work done till date
• Status of activities (in quantitative terms) undertaken during violation period and extent of
damage
2.1 CRITERIA OF ASSESSMENT
• Negative impact indicates increase pollution load, vibration and public inconveniences
• Positive impact in terms of increased income due to employment, or other ancillary
activities. Also benefits generated due to activities undertaken under corporate social
responsibility
• Criteria to be used to assess the impact due to the construction (as per the table below):
Table 2: Criteria to assess the impact due to construction
Score Rating
4 Major
3 Moderate
2 Minor
1 Negligible
0 None
-1 Negligible
-2 Minor
-3 Moderate
-4 Major
Table 3: Matrix for Assessment of Damage Scale
Particulars Score Range
Extremely Damaging -61 to-80
Damaging -41 to-60
Minutely damaging -21 to-40
Not damaging significantly <-20
2.2 Objectives of Remediation Plan
• To suggest control measures for preventing deterioration of air quality along with
approximate cost
• To suggest control measures for preventing deterioration of noise quality along
with approximate cost
• To suggest control measures for preventing deterioration of water quality along
with approximate cost
• Remediation plan of loss of top soil, loss of vegetation including trees and their
approximate cost
• To suggest control measures for keeping community safe from adverse effects of
activity approximate cost
• Plan and suggest Development of shelter of green belt to improve environment
2.3 Natural and Community Resource Augmentation Plan:
Augmentation plan will include various activities to be taken for augmentation of Natural
Resources like water, land vegetative cover in a time bound manner and estimation of
financial implication.
• Activities to be taken for augmentation of community resources. The key
community resources include —
• It can be a physical structure or place -- a school, hospital, library, recreation
center. It might also be an unused building that could house a community center,
a community owned forest, a park, a pond, or other pasture and open space
belonging to community.
• It can be a community service that makes life better for majority of community
members - public transportation, early childhood education center, community
recycling facilities, cultural organization.
• It can be an activity that provides jobs and supports the local economy.
The score calculated based on the above criteria along with the conditions given in TOR will be used
for damage assessment for estimation of the penal amount to be provided against creating impact
under violation.
Chapter 3: DAMAGE ASSESSMENT AND REMEDIATION MEASURES
For assessment of damage to environment following Environmental aspects has been identified: -
1. Air Environment
2. Water Environment
3. Soil Environment
4. Waste management
5. Noise Environment
6. Ecological Environment
7. Community welfare
8. Use of Natural resources
9. Topography and Natural drainage
10. Local Issues
11. Environmental accidents
12. Geological changes
13. Hydrological changes
14. Traffic planning
To assess these environmental parameters team has been deputed to assess preliminary
assessment of damage to environment. Based on site inspection and the documentary evidences
the environmental aspects vs activity has been filled.
3.1 Environmental Damage Assessed and its Remediation
The Construction has been done by the contractor Surya Heiighcon Pvt. Ltd. The Damage Assessment
and Remediation of environmental parameters along with Cost basis is explained in the table No. 5:
Table 4: Damage assessment and Remediation of Environmental components
Environmental component
Activities Damage Remediation
Air Environment
Transportation of construction material. The transportation of material was done using 4- 5 trucks & tractor daily (average), approx. 3608 RMC trucks 1JCB,1 crane, 1 loader and 2 excavator (long body).
Air emission from vehicular exhausts and handling of construction material
Plantation of trees around the project periphery including green crippers will help in neutralizing vehicular emissions.
Construction activity Gases emissions Proper Maintenance of construction equipment/ machineries, etc
Operation of construction machineries and DG sets
Air pollution due to particulates and gases
DG Sets of 1 x 125 KVA was used for construction
of project.
In operational phase, Total 2x 1250 KVA & 1x 500 will be the main source of Air pollution.
Dust suppression and water sprinkling system will be installed for suppression.
Water Environment
Stay of construction workers (Domestic consumption)
For 120 labours, 5 KLD of Water for domestic purpose was sourced through the canal water/ river water tankers
Low water consumption fixtures to be installed and STP treated water shall be reused for flushing, Gardening & DG cooling. The total water requirement will be 164 KLD out of which fresh water requirement will be 21 KLD, which will be met by HUDA/municipal supply
The rainwater will be channelized and collected in the 3 no which will recharge the ground water.
Channelization of Rainwater Harvesting structures for water requirements.
Construction activity
4 KLD of waste water generated from the construction site was disposed off to septic tanks followed by soak pits
Wastewater generation shall be 66 KLD which shall be treated in 90 KLD Sewage Treatment Plant. 63 KLD of treated water shall be reused for flushing, gardening, cooling & Misc. purposes. For Cooling purposes, 80 KLD of water will be sourced through nearby STP water.
Average 15 KLD of water was required during construction work which was met through STP Tanker supply
Soil Quality Soil Excavation
The project was conceptualized with 3 level basement & foundation hence 35311.74 m3 of soil was excavated for 3 level of basements & foundation as per Mining permission granted by Department of Mines & Geology, Gurgaon, Haryana.
Land reclamation of nearby area- The
excavated soil was re-used for
backfilling, levelling & other purposes to
the extent possible and rest unused soil
was handed over to contractor as per
the agreement for final disposal. The
Contractor had sold the soil for ongoing
construction of roads & highways in the
nearby area. Top soil has already been
used in green area development.
Waste Management
Generation of Solid waste during construction activities
Contamination/degradation of soil/water quality
Approx. 200 kg/ day of organic waste
will be treated in an inhouse Organic
Waste Convertor.
Non- biodegradable waste (71 kg/day) &
plastic waste (14 kg/ day) will be given
to the recycler for recycling
Generation of Hazardous wastes Used DG oil was generated as Hazardous waste
Used oil generated from the DG sets of 2 x 1010 KVA & 1 X 500 KVA will be given to DG set service provider for disposal of used oil
Noise Environment
Operation of construction machineries and DG sets
Health issue to the construction workers due to increase in noise levels from construction activities, operation of equipment and machineries and operation of DG sets
Plantation of trees around the project periphery including green crippers will act as Barricades around the project
Noise barrier around the project
Ecological Environment
Site clearance
No significant flora and fauna at project site
Total plantation area after complete development of the project, will be 1730.68 m2 (20 % of plot area). Total 108 no of trees shall be planted, out of which 100 trees have already been planted at the site.
Community welfare
Secure facilities to the construction workers
Structure of road
Infrastructure at village area.
Use of natural resources
Energy use was through diesel and petrol
Rain water Harvesting for Ground water
recharge
Sprinkling and watering of plantation on
nearby roads
Topography and Natural drainage
Excavation During construction period the natural contour is
disturbed which may affects the natural flow of
water
Natural drains near the project to be
maintained in order to maintain the
natural flow of water, which was
disturbed during excavation work.
Local Issues
The nearest habitat is Tikri village which is 0.42 Km
in W direction.
There were other projects in the vicinity and no
local issues. There was noise during construction
activities. Dust was generated during excavation &
transportation.
The land was vacant land and converted into
commercial complex.
Environmental
Accident
The project work was done by experienced and
qualified contractor hence no environmental
accident like land subsidence or land slide
happened.
Geological changes
There was no mineral at project site and there was
only ordinary soil. The soil excavation and
construction of basement has changed the
geological profile
Hydrological
changes
There was no use of ground water in the area. The
water level in the Gurgaon region ranges between
20 and 30 m in major parts which is due to
Urbanization and industrialization in this area
parts which is due to Urbanization and
industrialization in this area.
3.2 Damage Matrix
BUILDING CONSTRUCTION PROCESS
STEPS WORK
ENVIRONMENTAL ASPECTS
EMISSIONS TO
AIR RELEASES TO WATER
WASTE GENERATIO
N LAND Degradation
USE OF NATURAL
RESOURCES AND RAW
MATERIALS LOCAL ISSUES
TR
AN
SP
OR
T IS
SU
ES
EN
VIR
ON
ME
NT
AL
AC
CID
EN
TS
EF
FE
CT
S O
N B
IOD
IVE
RS
ITY
No
ise P
ollu
tio
n
So
il Q
uality
an
d M
an
ag
em
en
t
Geo
log
y
Hyd
rolo
gy
TO
TA
L
Current Status
PM
Gase
ou
s E
mis
sio
ns
Exec
uti
on
of
fou
nd
ati
on
s a
nd
reta
inin
g w
alls
Cle
an
ing
pro
ce
ss o
f m
ac
hin
ery
&
too
ls
San
itary
wate
r
C&
D w
aste
No
n-H
azard
ou
s w
aste
Hazard
ou
s &
E-W
aste
, B
att
ery
Waste
Du
mp
ing
du
e t
o u
se o
f co
nstr
ucti
on
mach
inery
Use o
f co
ncre
te r
ele
ase a
nd
su
rface
cle
an
ing
ag
en
ts
Du
mp
ing
of
oth
er
liq
uid
wa
ste
Ch
an
ge in
natu
ral d
rain
ag
e &
top
og
rap
hy
Wate
r
En
erg
y
Raw
Ma
teri
als
No
ise a
nd
vib
rati
on
s
Od
ou
r
Du
st
Lan
dscap
e A
lte
rati
on
STEP 1 Land occupation 100 10
0
STEP 2
Removal of vegetation or old
buildings 100 -4 -2 -2 -3 -3 -3 -2 -1 -20
STEP 3 Excavation work 100 -3 -1 -1 - -3 -3 -2 -3 -2 -3 -3 -4 -2 -4 -34
STEP 4 Foundation 100 -2 -1 -3 -1 -3 0 -3 -2 -3 -3 -3 -24
STEP 5 Piling 100 0 0
STEP 6 RCC Work 100 -2 -1 -4 -1 -3 -2 -3 0 -2 -2 -4 -4 -2 -30
STEP 7 Masonary Work 100 -2 -1 -3 -4 -3 0 -2 -2 -4 -2 -23
STEP 8 Roofs 100 -2 -1 -3 -3 -2 0 -2 -3 -2 -18
STEP 9
Timber work (Door and windows) 100 -4 -3 -2 0 -3 -3 -4 -4 -3 -26
STEP 10
Piping of water & sewage 100 -1 -1 -3 -2 0 -2 -2 -2 -13
STEP 11 Drainge system 100 -1 -2 -2 -2 0 -3 -2 -2 -3 -1 -3 -21
STEP 12
Sewage Treatment Plant 100 -2 -1 -3 3 -2 -4 -1 -3 3 4 -4 -3 -2 -2 -3 4 4 -2 4 3 -7
STEP 13
Rainwater Harvesting 100 -2 -2 -2 -4 -3 -3 -3 -3 -2 -2 -1 -1 -2 3 -27
STEP 14 Plantation 85 3 3 2 2 1 1 2 2 2 4 3 3 -2 2 2 3 3 4 4 3 3 4 3 3 -2 3 61
STEP 15 Roads 100 -3 -1 -3 -3 -3 -2 -2 -3 -3 -3 -2 -3 -4 -4 -4 -43
STEP 16
Installation of Electrical,
mechanical items and fire 100 -1 -2 -3 -3 -4 0 -3 -2 -2 -20
STEP 17 Plastering 100 -1 -3 -3 0 -3 -2 -3 -1 -16
STEP 18
Bathroom fitting & Plumbing work 100 -2 -1 -2 -2 -2 -2 0 -4 -2 -3 -1 -3 -24
STEP 19 Flooring 100 -3 -1 -1 -2 -2 -3 0 -3 -2 -3 -1 -3 -24
STEP 20
Painting and exteriors 100 -4 -3 -3 0 -4 -2 -3 -3 -3 -2 -4 -1 -32
TOTAL -35 -
10 -18 0 4 -
26 -
19 -
14 -38 7 -7 -15 -
35 -
32 -
33 -
14 -7 -8 4 -9 7 8 -
31 -5 -12 -3 -341
3.3 Impact summary
Table 5: Impact Summary as per construction status
ENVIRONMENTAL BASELINE MATRIX
S. No.
Identification Damage Evaluation
Environmental Element/ Units
Base Scale
Impact Scoring
1 Emissions to Air (-)20.0 Not damaging Significantly
2 Releases to Water (-)14.0 Not damaging Significantly
3 Waste Generation (-)19.66 Not damaging Significantly
4 Land Contamination (-)13.25 Not damaging Significantly
5 Use of natural resources and raw materials
(-)33.33 Minutely Damaging
6 Local Issues (-)6.25 Not damaging Significantly
7 Transport Issues (-)9 Not damaging Significantly
8 Environmental Accidents (+)7 Positive
9 Effects on Biodiversity (+)8 Positive
10 Noise Pollution (-)31 Minutely Damaging
110 Soil Quality and Management (-)5 Not damaging Significantly
12 Geology (-)12 Not damaging Significantly
13 Hydrology (-)3.0 Not damaging Significantly
Chapter 4: COST SUMMARY
4.1 Remediation Plan
Table 6: Cost summary
S.NO ITEM ACTION PLAN (PROPOSED/ UNDERTAKEN) BUDGET IN RS. (Lakhs)
1. Air Environment
Plantation of trees around the project periphery 3.63
Installation of Dust suppression and water sprinkling system 0.78
Maintenance of construction equipment/ machineries 0.6
2. Water Environment Low water consumption fixtures 6
Channelization of Rainwater harvesting structure 9
3. Soil Quality Land reclamation of nearby area 12.95
4. Waste management Segregation and provision of Organic waste convertor 12
5. Noise Environment Plantation of trees around the project periphery 7.2
Noise barrier 3
6. Ecological Environment Landscaping and plantation around project 3.63
7. Topography and Natural Drainage
Natural drains near the project to be maintained 6.98
TOTAL 65.77
4.2 Augmentation Plan
S.NO ITEM ACTION PLAN (PROPOSED/ UNDERTAKEN) BUDGET IN RS. (Lakhs)
1. Community welfare Proper transport planning by providing roads 9.0
Infrastructure at village area 6.0
2. Use of Natural resources Rain water Harvesting for ground water 5.0
Sprinkling and watering of plantation on nearby road. 5.0
TOTAL 25.0