damage assessment & remediation plan for

16
DAMAGE ASSESSMENT & REMEDIATION PLAN FOR “COMMERCIAL COMPLEX “SPAZE BOULEVARD-1”” at Village-Tikri, Sector-47, Gurgaon, Haryana Developed by M/s Spaze Towers Pvt. Ltd. PREPARED BY: M/s Perfact Researchers Pvt. Ltd. (NABL Accredited Testing Laboratory as per ISO/IEC 17025:2005, OSHAS 18001:2007 Certified Laboratory) 5 th Floor, NN Mall, Sector 3, Rohini, New Delhi-110085 & M/s Perfact Envirosolutions Pvt. Ltd. (NABET Registered Vide List of accredited Consultants organization / Rev 70/11th Oct. 2018 at S.No.-116) 5th Floor, NN Mall, Mangalam Palace, Sector 3, Rohini, New Delhi-110085 Email: [email protected]; Phone: 011- 49281360

Upload: others

Post on 23-Nov-2021

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

DAMAGE ASSESSMENT & REMEDIATION PLAN

FOR

“COMMERCIAL COMPLEX “SPAZE BOULEVARD-1””

at

Village-Tikri, Sector-47, Gurgaon, Haryana

Developed by

M/s Spaze Towers Pvt. Ltd.

PREPARED BY:

M/s Perfact Researchers Pvt. Ltd. (NABL Accredited Testing Laboratory as per ISO/IEC 17025:2005, OSHAS 18001:2007 Certified Laboratory)

5th Floor, NN Mall, Sector 3, Rohini, New Delhi-110085

&

M/s Perfact Envirosolutions Pvt. Ltd. (NABET Registered Vide List of accredited Consultants organization / Rev 70/11th Oct. 2018 at S.No.-116)

5th Floor, NN Mall, Mangalam Palace,

Sector 3, Rohini, New Delhi-110085

Email: [email protected]; Phone: 011- 49281360

Page 2: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

Contents

CHAPTER 1: INTRODUCTION ................................................................................................................................................. 3

CHAPTER 2: METHODOLOGY OF ASSESSMENT ..................................................................................................................... 4

2.1 CRITERIA OF ASSESSMENT....................................................................................................................................... 5

2.2 Objectives of Remediation Plan ............................................................................................................................... 5

2.3 Natural and Community Resource Augmentation Plan: ......................................................................................... 6

CHAPTER 3: DAMAGE ASSESSMENT AND REMEDIATION MEASURES ................................................................................... 7

3.1 Environmental Damage Assessed and its Remediation .......................................................................................... 7

3.2 Damage Matrix .....................................................................................................................................................12

3.3 Impact summary ...................................................................................................................................................14

CHAPTER 4: COST SUMMARY..............................................................................................................................................15

4.1 Remediation Plan ..................................................................................................................................................15

4.2 Augmentation Plan ...............................................................................................................................................16

List of Tables

Table 1: Project Details ........................................................................................................................... 3

Table 2: Criteria to assess the impact due to construction .................................................................... 5

Table 3: Matrix for Assessment of Damage Scale ................................................................................... 5

Table 4: Damage assessment and Remediation of Environmental components ................................... 8

Table 5: Impact Summary as per construction status .......................................................................... 14

Table 6: Cost summary.......................................................................................................................... 15

Page 3: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

Chapter 1: INTRODUCTION

The project Commercial Complex “Spaze Boulevard I” is situated at Village Tikri, Sector 47, Gurgaon,

Haryana is being developed by M/s Spaze Towers Pvt. Ltd. The total plot area and built-up area of

the project site is 11,537.50 sqm (2.85 acres) and 29,523.05 sqm respectively and the net plot area of

the project is 8653.43 sqm. This commercial project has provided retail spaces, luxury stores, BANKS,

restaurants, cafe and Office spaces

The total built-up area of the project will be 29523.05 sqm. Hence, the project falls under Category

“B” Schedule 8 (a) of EIA notification, 2006. However, as per the notification vide S.O. 804(E) dated

14.03.2017 the project was submitted to MoEF&CC under violation category. Subsequently, it was

considered in EAC meeting dated 19.02.2018 and thereafter, TOR was granted by MoEF&CC vide its

letter no. F.No. 23-39/2018-IA-III dated 7th June, 2018.

Now as per amendment in notification vide S.O. 1030(E) dated 8th March,2018 & OM no.

Z-11013/22/2017-IA. II (M) dated 15.03.2018 & 16.03.2018, the project falls under category ‘B’, of

Schedule 8(a) & is exempted from Public Hearing and will be appraised by SEAC/SEIAA, Haryana and

the same was submitted in Haryana SEAC on 11.07.2018 but was not appraised and now the tenure

of the committee has been completed.

Hence, in view of the aforesaid notification, a Damage Assessment and Remediation plan is required

to explain the extent of damage done due to construction.

Assessment of ecological damage with respect to air, water, land and other environmental attributes

has been done and EMP has been prepared comprising remediation plan and natural and community

resource augmentation plan corresponding to the ecological damage assessed and economic benefits

derived due to violation.

Table 1: Project Details

S. No Particulars Unit Total

1. Cost of project Rs. Crore 69.11

2. Total Plot Area sqm 11537.50

3. Area under deduction sqm 2884.07

4. Net Plot Area sqm 8653.43

5. Ground Coverage (Permissible) sqm 3461.37

6. Ground Coverage (Proposed) sqm 3461.26

7. F.A.R (Permissible) sqm 15143.50

Page 4: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

8. F.A.R (Proposed) sqm 15141.25

9. Total Basement area sqm 11770.58

10. Non-FAR Area sqm 2611.22

11. Total Built up Area (FAR+ Non-FAR+ Basement Area)

sqm 29523.05

12. Green Area (20 %) sqm 1730.68

13. Road Area & open area including surface parking

sqm 3461.49

14. No. of Floors - G+8

15. Levels of Basement - 3

16. Height of Building m 42

17. Parking required ECS 202

18. Parking proposed ECS 268

19. Total Power Load KW 1800

20. Power Backup KVA 2x1010 kVA and 1x500 kVA

Chapter 2: METHODOLOGY OF ASSESSMENT

As per notification vide S.O. 804(E) dated 14.03.2017 it has been notified that the violation cases/non-

Compliance will involve the assessment of ecological damage, remediation plan and natural and

community resource augmentation plan.

We have collected and analysed the data, for assessment of ecological damage, preparation of

remediation plan and natural and community resource augmentation plan and following

methodology will be adopted.

The overall impact on air, water, noise, soil and land environment will be assessed. In addition, it will

be weighed against the positive impact created on the socioeconomic scenario. To estimate the

impact produced, a framework has been designed as given ahead:

• The place of activity is permissible for the purpose (like it should not fall in eco-sensitive

zones etc.)

• Environmental Sensitivity to be clearly defined

• Status of work done till date

• Status of activities (in quantitative terms) undertaken during violation period and extent of

damage

Page 5: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

2.1 CRITERIA OF ASSESSMENT

• Negative impact indicates increase pollution load, vibration and public inconveniences

• Positive impact in terms of increased income due to employment, or other ancillary

activities. Also benefits generated due to activities undertaken under corporate social

responsibility

• Criteria to be used to assess the impact due to the construction (as per the table below):

Table 2: Criteria to assess the impact due to construction

Score Rating

4 Major

3 Moderate

2 Minor

1 Negligible

0 None

-1 Negligible

-2 Minor

-3 Moderate

-4 Major

Table 3: Matrix for Assessment of Damage Scale

Particulars Score Range

Extremely Damaging -61 to-80

Damaging -41 to-60

Minutely damaging -21 to-40

Not damaging significantly <-20

2.2 Objectives of Remediation Plan

• To suggest control measures for preventing deterioration of air quality along with

approximate cost

• To suggest control measures for preventing deterioration of noise quality along

with approximate cost

• To suggest control measures for preventing deterioration of water quality along

with approximate cost

• Remediation plan of loss of top soil, loss of vegetation including trees and their

approximate cost

Page 6: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

• To suggest control measures for keeping community safe from adverse effects of

activity approximate cost

• Plan and suggest Development of shelter of green belt to improve environment

2.3 Natural and Community Resource Augmentation Plan:

Augmentation plan will include various activities to be taken for augmentation of Natural

Resources like water, land vegetative cover in a time bound manner and estimation of

financial implication.

• Activities to be taken for augmentation of community resources. The key

community resources include —

• It can be a physical structure or place -- a school, hospital, library, recreation

center. It might also be an unused building that could house a community center,

a community owned forest, a park, a pond, or other pasture and open space

belonging to community.

• It can be a community service that makes life better for majority of community

members - public transportation, early childhood education center, community

recycling facilities, cultural organization.

• It can be an activity that provides jobs and supports the local economy.

The score calculated based on the above criteria along with the conditions given in TOR will be used

for damage assessment for estimation of the penal amount to be provided against creating impact

under violation.

Page 7: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

Chapter 3: DAMAGE ASSESSMENT AND REMEDIATION MEASURES

For assessment of damage to environment following Environmental aspects has been identified: -

1. Air Environment

2. Water Environment

3. Soil Environment

4. Waste management

5. Noise Environment

6. Ecological Environment

7. Community welfare

8. Use of Natural resources

9. Topography and Natural drainage

10. Local Issues

11. Environmental accidents

12. Geological changes

13. Hydrological changes

14. Traffic planning

To assess these environmental parameters team has been deputed to assess preliminary

assessment of damage to environment. Based on site inspection and the documentary evidences

the environmental aspects vs activity has been filled.

3.1 Environmental Damage Assessed and its Remediation

The Construction has been done by the contractor Surya Heiighcon Pvt. Ltd. The Damage Assessment

and Remediation of environmental parameters along with Cost basis is explained in the table No. 5:

Page 8: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

Table 4: Damage assessment and Remediation of Environmental components

Environmental component

Activities Damage Remediation

Air Environment

Transportation of construction material. The transportation of material was done using 4- 5 trucks & tractor daily (average), approx. 3608 RMC trucks 1JCB,1 crane, 1 loader and 2 excavator (long body).

Air emission from vehicular exhausts and handling of construction material

Plantation of trees around the project periphery including green crippers will help in neutralizing vehicular emissions.

Construction activity Gases emissions Proper Maintenance of construction equipment/ machineries, etc

Operation of construction machineries and DG sets

Air pollution due to particulates and gases

DG Sets of 1 x 125 KVA was used for construction

of project.

In operational phase, Total 2x 1250 KVA & 1x 500 will be the main source of Air pollution.

Dust suppression and water sprinkling system will be installed for suppression.

Water Environment

Stay of construction workers (Domestic consumption)

For 120 labours, 5 KLD of Water for domestic purpose was sourced through the canal water/ river water tankers

Low water consumption fixtures to be installed and STP treated water shall be reused for flushing, Gardening & DG cooling. The total water requirement will be 164 KLD out of which fresh water requirement will be 21 KLD, which will be met by HUDA/municipal supply

The rainwater will be channelized and collected in the 3 no which will recharge the ground water.

Page 9: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

Channelization of Rainwater Harvesting structures for water requirements.

Construction activity

4 KLD of waste water generated from the construction site was disposed off to septic tanks followed by soak pits

Wastewater generation shall be 66 KLD which shall be treated in 90 KLD Sewage Treatment Plant. 63 KLD of treated water shall be reused for flushing, gardening, cooling & Misc. purposes. For Cooling purposes, 80 KLD of water will be sourced through nearby STP water.

Average 15 KLD of water was required during construction work which was met through STP Tanker supply

Soil Quality Soil Excavation

The project was conceptualized with 3 level basement & foundation hence 35311.74 m3 of soil was excavated for 3 level of basements & foundation as per Mining permission granted by Department of Mines & Geology, Gurgaon, Haryana.

Land reclamation of nearby area- The

excavated soil was re-used for

backfilling, levelling & other purposes to

the extent possible and rest unused soil

was handed over to contractor as per

the agreement for final disposal. The

Contractor had sold the soil for ongoing

construction of roads & highways in the

nearby area. Top soil has already been

used in green area development.

Waste Management

Generation of Solid waste during construction activities

Contamination/degradation of soil/water quality

Approx. 200 kg/ day of organic waste

will be treated in an inhouse Organic

Waste Convertor.

Non- biodegradable waste (71 kg/day) &

plastic waste (14 kg/ day) will be given

to the recycler for recycling

Generation of Hazardous wastes Used DG oil was generated as Hazardous waste

Used oil generated from the DG sets of 2 x 1010 KVA & 1 X 500 KVA will be given to DG set service provider for disposal of used oil

Page 10: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

Noise Environment

Operation of construction machineries and DG sets

Health issue to the construction workers due to increase in noise levels from construction activities, operation of equipment and machineries and operation of DG sets

Plantation of trees around the project periphery including green crippers will act as Barricades around the project

Noise barrier around the project

Ecological Environment

Site clearance

No significant flora and fauna at project site

Total plantation area after complete development of the project, will be 1730.68 m2 (20 % of plot area). Total 108 no of trees shall be planted, out of which 100 trees have already been planted at the site.

Community welfare

Secure facilities to the construction workers

Structure of road

Infrastructure at village area.

Use of natural resources

Energy use was through diesel and petrol

Rain water Harvesting for Ground water

recharge

Sprinkling and watering of plantation on

nearby roads

Topography and Natural drainage

Excavation During construction period the natural contour is

disturbed which may affects the natural flow of

water

Natural drains near the project to be

maintained in order to maintain the

natural flow of water, which was

disturbed during excavation work.

Local Issues

The nearest habitat is Tikri village which is 0.42 Km

in W direction.

There were other projects in the vicinity and no

local issues. There was noise during construction

activities. Dust was generated during excavation &

transportation.

Page 11: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

The land was vacant land and converted into

commercial complex.

Environmental

Accident

The project work was done by experienced and

qualified contractor hence no environmental

accident like land subsidence or land slide

happened.

Geological changes

There was no mineral at project site and there was

only ordinary soil. The soil excavation and

construction of basement has changed the

geological profile

Hydrological

changes

There was no use of ground water in the area. The

water level in the Gurgaon region ranges between

20 and 30 m in major parts which is due to

Urbanization and industrialization in this area

parts which is due to Urbanization and

industrialization in this area.

Page 12: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

3.2 Damage Matrix

BUILDING CONSTRUCTION PROCESS

STEPS WORK

ENVIRONMENTAL ASPECTS

EMISSIONS TO

AIR RELEASES TO WATER

WASTE GENERATIO

N LAND Degradation

USE OF NATURAL

RESOURCES AND RAW

MATERIALS LOCAL ISSUES

TR

AN

SP

OR

T IS

SU

ES

EN

VIR

ON

ME

NT

AL

AC

CID

EN

TS

EF

FE

CT

S O

N B

IOD

IVE

RS

ITY

No

ise P

ollu

tio

n

So

il Q

uality

an

d M

an

ag

em

en

t

Geo

log

y

Hyd

rolo

gy

TO

TA

L

Current Status

PM

Gase

ou

s E

mis

sio

ns

Exec

uti

on

of

fou

nd

ati

on

s a

nd

reta

inin

g w

alls

Cle

an

ing

pro

ce

ss o

f m

ac

hin

ery

&

too

ls

San

itary

wate

r

C&

D w

aste

No

n-H

azard

ou

s w

aste

Hazard

ou

s &

E-W

aste

, B

att

ery

Waste

Du

mp

ing

du

e t

o u

se o

f co

nstr

ucti

on

mach

inery

Use o

f co

ncre

te r

ele

ase a

nd

su

rface

cle

an

ing

ag

en

ts

Du

mp

ing

of

oth

er

liq

uid

wa

ste

Ch

an

ge in

natu

ral d

rain

ag

e &

top

og

rap

hy

Wate

r

En

erg

y

Raw

Ma

teri

als

No

ise a

nd

vib

rati

on

s

Od

ou

r

Du

st

Lan

dscap

e A

lte

rati

on

STEP 1 Land occupation 100 10

0

STEP 2

Removal of vegetation or old

buildings 100 -4 -2 -2 -3 -3 -3 -2 -1 -20

STEP 3 Excavation work 100 -3 -1 -1 - -3 -3 -2 -3 -2 -3 -3 -4 -2 -4 -34

STEP 4 Foundation 100 -2 -1 -3 -1 -3 0 -3 -2 -3 -3 -3 -24

STEP 5 Piling 100 0 0

STEP 6 RCC Work 100 -2 -1 -4 -1 -3 -2 -3 0 -2 -2 -4 -4 -2 -30

STEP 7 Masonary Work 100 -2 -1 -3 -4 -3 0 -2 -2 -4 -2 -23

STEP 8 Roofs 100 -2 -1 -3 -3 -2 0 -2 -3 -2 -18

STEP 9

Timber work (Door and windows) 100 -4 -3 -2 0 -3 -3 -4 -4 -3 -26

Page 13: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

STEP 10

Piping of water & sewage 100 -1 -1 -3 -2 0 -2 -2 -2 -13

STEP 11 Drainge system 100 -1 -2 -2 -2 0 -3 -2 -2 -3 -1 -3 -21

STEP 12

Sewage Treatment Plant 100 -2 -1 -3 3 -2 -4 -1 -3 3 4 -4 -3 -2 -2 -3 4 4 -2 4 3 -7

STEP 13

Rainwater Harvesting 100 -2 -2 -2 -4 -3 -3 -3 -3 -2 -2 -1 -1 -2 3 -27

STEP 14 Plantation 85 3 3 2 2 1 1 2 2 2 4 3 3 -2 2 2 3 3 4 4 3 3 4 3 3 -2 3 61

STEP 15 Roads 100 -3 -1 -3 -3 -3 -2 -2 -3 -3 -3 -2 -3 -4 -4 -4 -43

STEP 16

Installation of Electrical,

mechanical items and fire 100 -1 -2 -3 -3 -4 0 -3 -2 -2 -20

STEP 17 Plastering 100 -1 -3 -3 0 -3 -2 -3 -1 -16

STEP 18

Bathroom fitting & Plumbing work 100 -2 -1 -2 -2 -2 -2 0 -4 -2 -3 -1 -3 -24

STEP 19 Flooring 100 -3 -1 -1 -2 -2 -3 0 -3 -2 -3 -1 -3 -24

STEP 20

Painting and exteriors 100 -4 -3 -3 0 -4 -2 -3 -3 -3 -2 -4 -1 -32

TOTAL -35 -

10 -18 0 4 -

26 -

19 -

14 -38 7 -7 -15 -

35 -

32 -

33 -

14 -7 -8 4 -9 7 8 -

31 -5 -12 -3 -341

Page 14: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

3.3 Impact summary

Table 5: Impact Summary as per construction status

ENVIRONMENTAL BASELINE MATRIX

S. No.

Identification Damage Evaluation

Environmental Element/ Units

Base Scale

Impact Scoring

1 Emissions to Air (-)20.0 Not damaging Significantly

2 Releases to Water (-)14.0 Not damaging Significantly

3 Waste Generation (-)19.66 Not damaging Significantly

4 Land Contamination (-)13.25 Not damaging Significantly

5 Use of natural resources and raw materials

(-)33.33 Minutely Damaging

6 Local Issues (-)6.25 Not damaging Significantly

7 Transport Issues (-)9 Not damaging Significantly

8 Environmental Accidents (+)7 Positive

9 Effects on Biodiversity (+)8 Positive

10 Noise Pollution (-)31 Minutely Damaging

110 Soil Quality and Management (-)5 Not damaging Significantly

12 Geology (-)12 Not damaging Significantly

13 Hydrology (-)3.0 Not damaging Significantly

Page 15: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

Chapter 4: COST SUMMARY

4.1 Remediation Plan

Table 6: Cost summary

S.NO ITEM ACTION PLAN (PROPOSED/ UNDERTAKEN) BUDGET IN RS. (Lakhs)

1. Air Environment

Plantation of trees around the project periphery 3.63

Installation of Dust suppression and water sprinkling system 0.78

Maintenance of construction equipment/ machineries 0.6

2. Water Environment Low water consumption fixtures 6

Channelization of Rainwater harvesting structure 9

3. Soil Quality Land reclamation of nearby area 12.95

4. Waste management Segregation and provision of Organic waste convertor 12

5. Noise Environment Plantation of trees around the project periphery 7.2

Noise barrier 3

6. Ecological Environment Landscaping and plantation around project 3.63

7. Topography and Natural Drainage

Natural drains near the project to be maintained 6.98

TOTAL 65.77

Page 16: DAMAGE ASSESSMENT & REMEDIATION PLAN FOR

4.2 Augmentation Plan

S.NO ITEM ACTION PLAN (PROPOSED/ UNDERTAKEN) BUDGET IN RS. (Lakhs)

1. Community welfare Proper transport planning by providing roads 9.0

Infrastructure at village area 6.0

2. Use of Natural resources Rain water Harvesting for ground water 5.0

Sprinkling and watering of plantation on nearby road. 5.0

TOTAL 25.0